As corporations consistently seek to maximize customer loyalty, secure predictable revenue, gain a competitive advantage and ensure customer satisfaction, more than often the words ‘Contact Center’ are never spoken. Much of the budget is allocated to the corporate marketing groups as they unveil flashy new websites, packaging and literature targeted for new and existing customers. More often than not, the Contact Center which is a critical portal to these customers is neglected with respect to revenue generation and customer loyalty.
3. Agenda
The Case Study – Business Processes
The Implementation - Finesse
The Implementation - IVR
The Implementation - Video
Q & A
4. Business Process
Transformation:
Contact Center
Challenges
• Understanding the requirements from 8 different
business units
• Producing a business plan showing a significant
NPV that will enable funding for the project
• Converting a Cost Center to a revenue contributor
Solution
• Map out a functional roadmap as a starting point
• Utilize Six Sigma to align the business units with the
end customer and produce reliable and repeatable
processes
Results
• Solid business plan that held up under financial
leadership scrutiny
• Confidence and buy-in from all business units
• Transform business processes to utilize the latest
technologies to produce higher customer satisfaction
Case Study
5. Contact Center Case Study
London
Canadian (2)
Benefits
Scotland
Manila
India
Dominican
Republic
Mauritius
Payroll
Lifeworks
• 8 Business Units
• 6000 Agents
• 7 countries
6. Consider the Business Issues, challenges and requirements “hand in hand”
with technical strategies and capabilities aligned with the overriding
IT Strategy and produce a roadmap
7. Roadmap Methodology
• Six High Level Phases
Define
Projects
and
Programs
Roadmap
Dev.
Prioritize
Definition
Of
Initiatives
End State
Definition
& Goals
Current
State
Discovery
In other words,
1. What do I have today, and what projects are running?
2. Where do I want to be, by when?
3. What is going on that will affect/influence my path?
4. What is most important and what will deliver the greatest benefit?
5. How do I turn this input into a roadmap?
6. What Programs and/or Projects will implement the steps in my roadmap?
8. Roadmap Methodology – Detail Steps 1-3
Definition
Of
Initiatives
End State
Definition
& Goals
Current
State
Discovery
Installed base of Contact Centers
Current and planned
CC Projects
Current Changes,
Incidents and
Problems
9. Roadmap Methodology – Detail Steps 1-3
Definition
Of
Initiatives
End State
Definition
& Goals
Current
State
Discovery
Installed base of Contact Centers
Current and planned
CC Projects
Current Changes,
Incidents and
Problems
Business Requirements
Key Infrastructure Projects
IT Strategy
Technical Options
Industry & Market
Trends
10. Roadmap Methodology – Detail Steps 1-3
Definition
Of
Initiatives
End State
Definition
& Goals
Current
State
Discovery
Installed base of Contact Centers
Current and planned
CC Projects
Current Changes,
Incidents and
Problems
Business Requirements
Key Infrastructure Projects
IT Strategy
Technical Options
Industry & Market
Trends
Key Infrastructure
Project Detail
Related Project
Portfolio
Key Business
Drivers
& Objectives
11. Roadmap Methodology – Deliverables
Definition
Of
Initiatives
End State
Definition
& Goals
Current
State
Discovery
1. Contact Center Inventory
3. CC Project Portfolio
2. Summary of
current issues,
changes and
problems
4. Current Cost Overview
Business Requirements
Key Infrastructure Projects
IT Strategy
Technical Options
Industry & Market
Trends
Key Infrastructure
Project Detail
Related Project
Portfolio
Key Business
Drivers
& Objectives
12. Roadmap Methodology – Deliverables
Definition
Of
Initiatives
End State
Definition
& Goals
Current
State
Discovery
Business Requirement
Definition
List of Key Infrastructure Projects
that are related to Contact Centers/Telephony
Assessment of related sections of
The IT Strategy
Description/Scope of Tech
Capabilities
Description and Impact
of Industry & Market
Trends
Key Infrastructure
Project Detail
Related Project
Portfolio
Key Business
Drivers
& Objectives
1. Contact Center Inventory
2. Summary of current issues, changes and problems
3. CC Project Portfolio
4. Current Cost Overview
Stage 1 : Current State Description
14. What Are We doing…
General background statement to define the nature of the work:
Current telephony systems are based on a legacy Time Division
Multiplexing (TDM) technology that requires its own infrastructure
and support mechanisms. Extensive electronic components are
required to facilitate this infrastructure and is not conducive to
Moves , adds and changes. These systems also require separate
FTE's to maintain. The legacy systems are aging and their
availabilities are directly impacting our internal and external SLA
to a point where are external customers are at risk. The inherent
infrastructure is costly and doesn't allow us to take advantage of
great cost savings due to consolidation and centralization. Yearly
maintenance costs are exceeding $1.2M and rising due to the
age of the systems.
Define
1. Identify the major source problem areas that are impacting customer SLA's. Identify major
cost savings by replacing the aging systems. Map each of these areas out.
2. Survey individual Business Units and map out impacting areas of concern.
Measure
3. Map out the Critical to Quality (CTQ) Characteristics behind these problems.
4. Establish performance standards for each CTQ.
5. Conduct Measurement System Analysis.
6. Define baseline performance levels.
7. Define process capabilities.
Analyze
8. Identify the causes behind errors and defects through testing.
9. Apply specific techniques such as FMEA
Improve
10. Develop and evaluate solutions.
11. Design a To Be Process and Test Pilot.
12. Submit Full Scale Improvement Plan.
Control
13. Design a Control Plan
14. Summarize and Communicate Best Practices.
15. Develop Operating Procedures and Training Modules.
16. Create a Project Summary Document
15. What's Wrong?…
Pareto Chart Impact of Telephony Systems Failures on Internal / External Customers (JAN /09 - JUNE /09)
Contributor % Impact Notes
I3 PBX Software
Failures
49%
Telecom Human Error 25%
I3 PBX Hardware
Failure
18%
Telecom Circuits 8%
Total 100%
49%
25%
18%
8%
0% 0% 0% 0% 0% 0%
0%
10%
20%
30%
40%
50%
60%
I3 PBX Software
Failures
Telecom Human
Error
I3 PBX Hardware
Failure
Telecom Circuits
Basic Steps for Pareto Chart:
1. Quantify the Impact of Each Defect
2. Rank in Descending Order
NOTE: You should have at least three types of defects. If you have too many, then you may w ant to group them together.
This Pareto Chart simply looked at different types of Telephony Faulures and how do these relate to Customer Satisfaction.
** These stats w ere derivedfromthe 2009 HS UPTIME MONTHLY MASTER REPORT and their associated RCA's.
16. Measure the Customer Experience…
Critical to Quality Characteristics (CTQC)
Call Center Telephony Project
< - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - Operational Definition - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - > Continuous
No CTQ per Diagram Performance Standard Measurement Test Measurement Results or Discrete
1 Redundant / Reliable Telephony Systems - Internal
Customer / Internal SLA's are measured daily
and weekly and are within acceptable levels
Telephony system avalability is measured as
uptime for a customers service within a BU Service Desk Outage Reporting Discrete Broken
2 Diverse / Redundant Telecom PSTN - External
Customer / Internal SLA's are measured daily
and weekly and are within acceptable levels
Telephony system avalability is measured as
uptime for a customers service within a BU Service Desk Outage Reporting Discrete Broken
3 CTI / Web Self-Service Integration
Higher customer satisfaction levels and
reduced Call Center costs.
Project cost comparisons. Call Center Cost
reductions and improved customer service levels.
Key KPI measurements
Business Unit measurement of monthly KPI's
and SLA's Discrete Broken
4 IVR Quality Programming
High deflection rate (calls satisfied within the
IVR) Customer SLA and KPI Measurements
Business Unit measurement of monthly KPI's
and SLA's Discrete Broken
5 Telecom System Administration
Quicker time to market for projects resulting
in lower project costs and higher customer
satisfaction. Telecom FTE Cost analysis GNS Monthly Run Rate Analysis Continuous Broken
6 Automated Processes
Lower telephony operating costs and Call
Center administration Call Center Cost analysis
Business Unit measurement of monthly KPI's
and SLA's Continuous Broken
Preliminary Testing and Reviews for each CTQ listed above:
1. Compare the current availabilities of our telephony system and its direct affect on the end customer's SLA.
2. Compare the current Telecom Circuit availabilities and its direct affect on the end customers SLA
3. Compare the active Telecom group personnel and Professional Service outsourcing to support the telephony systems and the BU
3. Contact the BU to analyze current % of customers utilizing these features and their availabilities
4. Contact the BU to determine current deflection rates and % of calls completing within the IVR
Based on the four tests above, one of three grades was assigned to the CTQ:
Working - The process related to CTQ appears to meet the performance standard defined.
Broken - The process related to the CTQ appears to be broken and needs improvement.
U T D - Unable to Determine; need to sample and test the population data.
This preliminary review should assist to determine the scope and downstream work required for this project.
Preliminary
Testing Results
17. Process Mapped to A Customer (Internal/External)
AT & T / Sprint 1-800-# Automatic Number Identifier (ANI) Inbound Call Detail Records Call Center Operations Team
Dialed Number Identification Service (DNIS)
Ceridian's Customer Social Security Number (SSN) Call Processing Record Call Center Operations Team
Account Number Call Deflection Record
Menu Selection Average Speed of Answer (ASA)
Web Self Services Records BU Managers, GIS Teams
Ceridian CRM Customer Account Information
Callers Call History
Customers Priority
Call Center Supervisors Call Handling Information Monthly Performance Reports COO, BU Managers
First Call Resolution (FCR) GIS Teams
Average Handle Time (AHT) Quality Team
Customer Survey After Call Work (ACW) COO, BU Managers
Customer Satisfaction Record Quality Team
SIPOC DIAGRAM - High Level
► ►
Call Center and Telephony Project
► ►Supplier Input Process
Inbound Call
IVR Processing
CTI Integration
w/CRM
Queueing
Routing
Output Customer
CSR
After Call Work
18. The Voice of the Customer
Customer Benefits Requirements Rank Measure
Direct internal
Service / Call Center Operations
Phone Agents
Agents are aware of the current
call flows and the KPI metrics at
all times
Dashboard Statistics 6
Supervisors
Streamlined Call Centers with
predicabilities. Ability to control
agent counts. Dashboard
reporting and tight WFM QA
allows better selection of agents
and training.
Quality systems with high
availability. Call Center
Dashboards. First Call
Resolution
9
Management
Cost controls. Superior SLA's
and customer retention.
Processing more contacts with
less and a higher percentage of
FCR. Virtualization.
CTI integration as well as
Multi-channel (inbound email
and chat). Complete
IVR/ACD and Web self
service is essential
6
Call Center Service Delivery
Workforce Mgmt
Higher levels of training. Better
control of agent scheduling and
suggestive training processes to
achieve better customer
satisfaction. Better reporting and
QA. Higher rate of FCR.
Complete integration with
Verint Blue Pumpkin with
Scheduling. Incorporation of
Speech Analytics to aid in
FCR
9
Quality Team
Better understanding of
customer calls. Higher training
quality. Results are higher
customer satisfaction and
retention
Implementation in a global
Quality Management
features including Score
carding, Audio Capturing and
Screen Capture
6
Reporting Analyst
Reduction in time spent in
formulating reports. Reports are
more accurate and concise.
Automated dashboards from
agent level to executive level
provide "finger on the pulse"
monitoring
Full Suite of Reporting with
integrated links to the QM
modules for Quality scoring
and historical reporting.
6
Voice of the Customer Grid
21. Justifying the Investment
At Start Year 1 Year 2 Year 3 Year 4 Year 5 Cumulative
Of Project 2008 Forecast Jan-12 Jan-13 Jan-14 Jan-15
Revenue Inflows $0 $0 $0 $0 $0 $0 $0
Adj Revenue to CF from Accounting basis 0 0 0 0 0 0 0
Total Inflows $0 $0 $0 $0 $0 $0 $0
Outflows
Total Expenses P&L Above (525,000) 306,177 2,630,324 2,630,324 4,550,324 4,550,324 14,142,472
Add: Depreciation 0 1,920,000 1,920,000 1,920,000 0 0 5,760,000
Adj OT deferred cost to CF from Accounting basis 0 0 0 0 0 0 0
Deduct: Capital purchases (4,000,000) (1,760,000) 0 0 0 0 (5,760,000)
Cashflow before Tax (4,525,000) 466,177 4,550,324 4,550,324 4,550,324 4,550,324 14,142,472
Tax payments (301,384) (1,109,349) (1,267,979) (1,379,020) (1,456,749) (5,514,481)
Total Outflows ($4,525,000) $164,793 $3,440,975 $3,282,345 $3,171,304 $3,093,575 $8,627,991
Net Operating Cash Flow ($4,525,000) $164,793 $3,440,975 $3,282,345 $3,171,304 $3,093,575 $8,627,991
Is this an acquisition where a terminal value will apply?
If YES, enter revenue multiple factor for estimating terminal value: 1.20
Estimated Minimum Terminal Value:
n/a
n/a
Minim um Term inal Value A or B above n/a
Intangible Capital Residual Value based on NBV at end of year 5 $0
Tangible Capital Residual Value based on NBV at end of year 5 $0
39%
4,879,998$
n/a
-$
4,879,998$
NPV of Capital at end of project:
Total Net Present Value (NPV)
NPV of Terminal Value at end of project:
Internal Rate of Return (IRR)
Operating Cash Flow Statement For Project
A) Residual Value Based on Free Cash Flow at end of year
B) Residual Value Based on Revenue Multiple at end of year
NPV of Operating Cash Flows from project:
32. Complete Your Paper
“Session Evaluation”
Give us your feedback and you could win
1 of 2 fabulous prizes in a random draw.
Complete and return your paper
evaluation form to the room attendant
as you leave this session.
Winners will be announced today.
You must be present to win!
..visit them at BOOTH# 100