GUNJAN KUMAR
Mobile: +91 9992447449/ +91 9352126441
E-Mail: gunjan.dubey327@gmail.com
Aspires to pursue challenging assignments in Production Operations/Sheet Metal Cutting/ Paint Shop
(Automobile & Geyser)/ Enamel Coating(Geyser)/Semi Automatic Weld Shop/Erection/Civil Work
(Structure work, RCC Road, Plaster, Plinth &Room) Site Management with an organization of high repute and
willing to work any where in India.
Profile Summary
Dynamic Professional with over 6 years of rich experience in
~ Erection ~ Fabrication ~ Commissioning
~ Project Planning & Execution ~ Plant Operations ~ Material Management
~ Operations & Maintenance ~ Resource Optimization ~ Quality Assurance & Control
~ Auto cad ~ Geyser Production (10L,15L&25L) ~ Weld Shop
~ Conveyor Installation for Refrigeration line , Washing machine line and Geyser line
• Knowledge in Geyser production and process for square & vertical model tank
• Knowledge in weld shop, paint shop & enamel coating line
• Excellent knowledge of all welding codes like ASME.
• Adept at carrying out tests / inspection for various processes and checking quality standards of final goods
• Proficient in handling fabrication operations for manufacturing and accountable for quality service & timely
completion of the projects
• Well versed with the concepts of handling material indent according to requirement during operations &
maintaining consumption record of stores and spares
• An effective communicator with excellent relationship management skills and strong analytical, leadership,
decision making, problem solving & organizational abilities
Key Skills
Project Management
• Coordinating and Interacting with team members to ensure smooth progress of project work by ensuring
adherence to quality norms throughout the project
• Monitoring the activity at sites and review of project schedule, estimating & costing within budget, planning for
cash flow requirements, etc.
• Taking stringent quality measures including preparation / maintenance of necessary documents to ensure better quality
Operations & Maintenance
• Planning & implementing preventive & breakdown maintenance schedules of utilities for improving overall
reliability and safety of equipments & machinery
Fabrication Operations
• Studying drawings, plans or patterns of structures to be made or repaired as per requirements
• Eliminating redundant / obsolete processes involved in the design, development processes and working towards
value-addition
Erection & Commissioning
• Anchoring erection & commissioning of machines & equipment and ensuring completion of project in minimum
turnaround time effective resource utilisation to maximise the output
• Overseeing installation & commissioning as well as conducting tests & inspections to ensure operational
effectiveness of utilities; planning & effectuating maintenance plans for machines and equipment
Purchase Management
• Planning and monitoring inventory management, raw materials, etc. and monitoring inbound logistics
Organizational Experience
Since Apr’ 15 Empire Home Appliances Ltd. , Baddi , Himanchal Pradesh as Project Manager
Key Result Areas:
• 5+ years of experience in Manufacturing /Automobile Industrial & Civil Constructions work
• Micro planning of daily construction activity
• Preparing bids
• All type of fabrication, installation, Distribution Transformer installation, prefabricated Buildings& Civil work(Road
, Plinth & Drainage System)
• Communicating with vendor & customer
• Report to GM on daily issues
• Estimating
• Paint shop work(Automobile) and Enamel Coating line(Geyser)
• Semi Automatic Weld Shop
• Conveyor Installation Work
Oct’12 to Mar’15: Advancetech Engineering Pvt. Ltd., Bilaspur, Gurgaon as Site Engineer
Key Result Areas:
• Overseeing construction related activities like fabrication, all type of tanks, panels, external ducts, ovens, conveyor
support, process drain pan, deck & fence, mezzanine (layout, support, hand rail), spray booth and post deck
• Carrying out installation of different tanks in Pre Treatment Area, Electro Deposition tank, Air supply unit, Flash Off
zone, Clear booth, Base booth, Primer booth, Ducting and Piping related activities etc.
May’10 to Sep’12: Sidharth Automat India Pvt. Ltd., Shahjahanpur, Alwar as Production Engineer
Key Result Areas:
• Handled of project under Project Head (Fabrication & Assembly) and reporting to Plant Head
• Managed the overall project activities and complete operation function like productivity improvement & product
development, manufacturing and production
• Looked after maintaining and updating project related documents, visual management, supervision of daily work
management, identification, elimination of non-value addition activities, build effective systems & processes and
providing timely training to workers
• Ensured Management Information System (MIS) to Head Office, schedule adherence, progress reports, capacity
utilization, consumable cost, etc.
• Involved in process planning, raw material planning, inventory management, BOM preparation, dispatch
scheduling, etc.; conducting and taking care of Quality Review Meetings
• Carried out activities of implementation, maintenance and improvement of quality system & procedures
Highlights:
• Successfully initiated system based work culture related to operations by introducing monthly & weekly planning,
capacity planning, monthly production plan, daily M/C loading plan, production review meeting, quality review
meeting and in process check sheets
Major Projects
Installation Projects:
o Mar ’13 to May ’13: Tata Motor Ltd., Jamshedpur for TAL Manufacturing Solution
o Oct’12 to Feb’13: Toyota Kirlosker Motors (Bangalore) for Trinity Industrial Corp.
Fabrication:
o Jul’14 to Dec’14: International Tractors Ltd., Hoshiarpur for Taikisha Engineering India Ltd.
o Sep’11 to Dec’11: Wheels India, Rampur for Sidharth Automat India
o Dec’10 to Jan‘11: Volkswagen India, Pune for Sidharth Automat India
Education
• B.Tech. (Mechanical Engineering) from JNTU, Hyderabad in 2010 with 65%
• 12th
from B.I.E.C. Patna .
• 10th
from B.S.E.B. Patna .
Extramural Engagements & Other Accolades
• Involved and participated in various cultural activities at school as well as college level
Voluntary Assignments
• Participated in Pulse Polio Awareness Programme at Hyderabad in 2008
• Involved in AIDS Control Awareness Programme at Hyderabad in 2009
IT Skills
o Operating System: Windows 7, Windows XP Professional and 98/2000
o Package: MS-Office
o Tools: Auto CAD
Personal Details
Date of Birth: 2nd
Jan, 1984
Address: A-137, Ground Floor, Noida, Sector-20, G.B. Nagar-201301, Uttar Pradesh
Languages Known: English & Hindi
(please refer to the annexure for project details)
ANNEXURE
Organizational Projects
• Successfully completed the following projects:
Installation Projects:
o April 15 to Till now: Dynamic Appliances(Water heater line, Paint shop, Weld shop), Baddi , Himanchal
Pradesh
o Dec’ 15 to jan’16 Empire Home Appliances(Refrigeration line and Washing machine line) , Baddi ,
Himanchal Pradesh
o Jan’ 16 to till now Empire Home Appliances(Cyclo pentene civil & structure work), Baddi , Himanchal
Pradesh
o Oct’13 to Jun’14: Hero Motocorp Ltd., HMCL Neemrana for Wurster India
For Fabrication:
o May’13 to Sep’13: Hero Motocorp Ltd., HMCL Neemrana for Wurster India
o Jul’12 to Sep’12: Toyota Kirlosker Motors, Bangalore for Trinity Industrial Corp.
o Apr’ 13 to Jul’ 13: Class India, Morinda for Sidharth Automat India
o Dec’11 to Apr’12: Maruti Suzuki India, Gurgaon for Parker Engineering
o Apr’11 to Aug’11: Toyota Kirlosker Motors, Bangalore for Trinity Industrial Corp.
o Dec’10 to Mar’11: Metalman, Pantnagar for Parker Engineering
o Jun’10 to Nov’10: Maruti Suzuki India, Gurgaon for Parker Engineering
Key Result Areas:
• Communicate with Contractor and meet scheduling requirements and contribute to a continuous improvement
environment
• Responsible for in-coming, in-process & final quality of the parts manufactured
• Reviewing drawing to ensure that fabrication is made as per drawing
• Accountable for job procedures & specifications as per the drawing
• Maintaining and preparing QA Documents (Check Sheet and Control Plan)
• Analyzing customer complaints and take corrective measures to provide prompt resolution
• Overseeing entire activities in welding shop (MIG, TIG and Arc Welding)
• Carrying out activities of erection, production & maintain quality of the shop
• Assisting and monitoring the project activities in accordance with customer’s demand, company’s quality control
system requirements and also advise the project manager in case of any violation
• Performing, conducting and witnessing of DP test, air bubble test, radiography test & visual testing and reviewing of reports
• Implementing 5S activities and working for continuous improvement of projects
• Ensuring adherence to quality standards through timely product and process audit

Gunjan Resume

  • 1.
    GUNJAN KUMAR Mobile: +919992447449/ +91 9352126441 E-Mail: gunjan.dubey327@gmail.com Aspires to pursue challenging assignments in Production Operations/Sheet Metal Cutting/ Paint Shop (Automobile & Geyser)/ Enamel Coating(Geyser)/Semi Automatic Weld Shop/Erection/Civil Work (Structure work, RCC Road, Plaster, Plinth &Room) Site Management with an organization of high repute and willing to work any where in India. Profile Summary Dynamic Professional with over 6 years of rich experience in ~ Erection ~ Fabrication ~ Commissioning ~ Project Planning & Execution ~ Plant Operations ~ Material Management ~ Operations & Maintenance ~ Resource Optimization ~ Quality Assurance & Control ~ Auto cad ~ Geyser Production (10L,15L&25L) ~ Weld Shop ~ Conveyor Installation for Refrigeration line , Washing machine line and Geyser line • Knowledge in Geyser production and process for square & vertical model tank • Knowledge in weld shop, paint shop & enamel coating line • Excellent knowledge of all welding codes like ASME. • Adept at carrying out tests / inspection for various processes and checking quality standards of final goods • Proficient in handling fabrication operations for manufacturing and accountable for quality service & timely completion of the projects • Well versed with the concepts of handling material indent according to requirement during operations & maintaining consumption record of stores and spares • An effective communicator with excellent relationship management skills and strong analytical, leadership, decision making, problem solving & organizational abilities Key Skills Project Management • Coordinating and Interacting with team members to ensure smooth progress of project work by ensuring adherence to quality norms throughout the project • Monitoring the activity at sites and review of project schedule, estimating & costing within budget, planning for cash flow requirements, etc. • Taking stringent quality measures including preparation / maintenance of necessary documents to ensure better quality Operations & Maintenance • Planning & implementing preventive & breakdown maintenance schedules of utilities for improving overall reliability and safety of equipments & machinery Fabrication Operations • Studying drawings, plans or patterns of structures to be made or repaired as per requirements • Eliminating redundant / obsolete processes involved in the design, development processes and working towards value-addition Erection & Commissioning • Anchoring erection & commissioning of machines & equipment and ensuring completion of project in minimum turnaround time effective resource utilisation to maximise the output • Overseeing installation & commissioning as well as conducting tests & inspections to ensure operational effectiveness of utilities; planning & effectuating maintenance plans for machines and equipment
  • 2.
    Purchase Management • Planningand monitoring inventory management, raw materials, etc. and monitoring inbound logistics Organizational Experience Since Apr’ 15 Empire Home Appliances Ltd. , Baddi , Himanchal Pradesh as Project Manager Key Result Areas: • 5+ years of experience in Manufacturing /Automobile Industrial & Civil Constructions work • Micro planning of daily construction activity • Preparing bids • All type of fabrication, installation, Distribution Transformer installation, prefabricated Buildings& Civil work(Road , Plinth & Drainage System) • Communicating with vendor & customer • Report to GM on daily issues • Estimating • Paint shop work(Automobile) and Enamel Coating line(Geyser) • Semi Automatic Weld Shop • Conveyor Installation Work Oct’12 to Mar’15: Advancetech Engineering Pvt. Ltd., Bilaspur, Gurgaon as Site Engineer Key Result Areas: • Overseeing construction related activities like fabrication, all type of tanks, panels, external ducts, ovens, conveyor support, process drain pan, deck & fence, mezzanine (layout, support, hand rail), spray booth and post deck • Carrying out installation of different tanks in Pre Treatment Area, Electro Deposition tank, Air supply unit, Flash Off zone, Clear booth, Base booth, Primer booth, Ducting and Piping related activities etc. May’10 to Sep’12: Sidharth Automat India Pvt. Ltd., Shahjahanpur, Alwar as Production Engineer Key Result Areas: • Handled of project under Project Head (Fabrication & Assembly) and reporting to Plant Head • Managed the overall project activities and complete operation function like productivity improvement & product development, manufacturing and production • Looked after maintaining and updating project related documents, visual management, supervision of daily work management, identification, elimination of non-value addition activities, build effective systems & processes and providing timely training to workers • Ensured Management Information System (MIS) to Head Office, schedule adherence, progress reports, capacity utilization, consumable cost, etc. • Involved in process planning, raw material planning, inventory management, BOM preparation, dispatch scheduling, etc.; conducting and taking care of Quality Review Meetings • Carried out activities of implementation, maintenance and improvement of quality system & procedures Highlights: • Successfully initiated system based work culture related to operations by introducing monthly & weekly planning, capacity planning, monthly production plan, daily M/C loading plan, production review meeting, quality review meeting and in process check sheets Major Projects Installation Projects: o Mar ’13 to May ’13: Tata Motor Ltd., Jamshedpur for TAL Manufacturing Solution o Oct’12 to Feb’13: Toyota Kirlosker Motors (Bangalore) for Trinity Industrial Corp. Fabrication: o Jul’14 to Dec’14: International Tractors Ltd., Hoshiarpur for Taikisha Engineering India Ltd. o Sep’11 to Dec’11: Wheels India, Rampur for Sidharth Automat India o Dec’10 to Jan‘11: Volkswagen India, Pune for Sidharth Automat India Education
  • 3.
    • B.Tech. (MechanicalEngineering) from JNTU, Hyderabad in 2010 with 65% • 12th from B.I.E.C. Patna . • 10th from B.S.E.B. Patna . Extramural Engagements & Other Accolades • Involved and participated in various cultural activities at school as well as college level Voluntary Assignments • Participated in Pulse Polio Awareness Programme at Hyderabad in 2008 • Involved in AIDS Control Awareness Programme at Hyderabad in 2009 IT Skills o Operating System: Windows 7, Windows XP Professional and 98/2000 o Package: MS-Office o Tools: Auto CAD Personal Details Date of Birth: 2nd Jan, 1984 Address: A-137, Ground Floor, Noida, Sector-20, G.B. Nagar-201301, Uttar Pradesh Languages Known: English & Hindi (please refer to the annexure for project details)
  • 4.
    ANNEXURE Organizational Projects • Successfullycompleted the following projects: Installation Projects: o April 15 to Till now: Dynamic Appliances(Water heater line, Paint shop, Weld shop), Baddi , Himanchal Pradesh o Dec’ 15 to jan’16 Empire Home Appliances(Refrigeration line and Washing machine line) , Baddi , Himanchal Pradesh o Jan’ 16 to till now Empire Home Appliances(Cyclo pentene civil & structure work), Baddi , Himanchal Pradesh o Oct’13 to Jun’14: Hero Motocorp Ltd., HMCL Neemrana for Wurster India For Fabrication: o May’13 to Sep’13: Hero Motocorp Ltd., HMCL Neemrana for Wurster India o Jul’12 to Sep’12: Toyota Kirlosker Motors, Bangalore for Trinity Industrial Corp. o Apr’ 13 to Jul’ 13: Class India, Morinda for Sidharth Automat India o Dec’11 to Apr’12: Maruti Suzuki India, Gurgaon for Parker Engineering o Apr’11 to Aug’11: Toyota Kirlosker Motors, Bangalore for Trinity Industrial Corp. o Dec’10 to Mar’11: Metalman, Pantnagar for Parker Engineering o Jun’10 to Nov’10: Maruti Suzuki India, Gurgaon for Parker Engineering Key Result Areas: • Communicate with Contractor and meet scheduling requirements and contribute to a continuous improvement environment • Responsible for in-coming, in-process & final quality of the parts manufactured • Reviewing drawing to ensure that fabrication is made as per drawing • Accountable for job procedures & specifications as per the drawing • Maintaining and preparing QA Documents (Check Sheet and Control Plan) • Analyzing customer complaints and take corrective measures to provide prompt resolution • Overseeing entire activities in welding shop (MIG, TIG and Arc Welding) • Carrying out activities of erection, production & maintain quality of the shop • Assisting and monitoring the project activities in accordance with customer’s demand, company’s quality control system requirements and also advise the project manager in case of any violation • Performing, conducting and witnessing of DP test, air bubble test, radiography test & visual testing and reviewing of reports • Implementing 5S activities and working for continuous improvement of projects • Ensuring adherence to quality standards through timely product and process audit