Adam Goodin
Fossil Hydro Operations
Co-op Development Program
August 13, 2015
About Me
■ University of Kentucky
– Senior
– Civil Engineering
– Graduation: 8/16
■ 3rd Rotation with Duke
– Woodsdale (Spring 14)
– Plainfield (Fall 14)
– Gibson Station (Current)
■ Gibson Station, Capital Group
– Mentor: Mick Harpenau
My Safety Moment
■ Participated in Sitewide Safety Stand-down
– Walkdown with experienced Duke and Contractor
Management with the sole purpose of eliminating
hazards in the workplace
■ Looked for technical malfunctions
– Deteriorating grounding equipment
– Broken/corroded conduit
■ Housekeeping
– Ladders in isleway
– Stray pieces of wood and metal could become falling
object
Responsibilities this Rotation
■ Document Control on Unit 5 FGD Structural Refurbishment
– Maintained IFC Drawings and updated for revisions
– Provided Field Support
■ U5 Mercury Re-emission project
– Developed P&IDs
– Created Valve Lists and Valve Numbers
■ Involved in fall outage coordination meetings
– Logistics of large scale project
– Schedule formed, laydown areas designated, scope of work
Dry Bottom Ash Conversion
■ Support Engineering Efforts on the recently
initiated Dry Bottom Ash Conversion Project
– April 2015 EPA Ruling
– Gibson to adopt a Continuous Dewatering and
Recirculation (CDR) System
– Locate Existing Underground Drawings
– Obtain Existing Area General Arrangement (GA’s)
Drawings
– Layout Route for new Sanitation System piping
Dry Bottom Ash Conversion (Cont.)
– Locate Existing Sanitation System Drawings for
locating tie points
– Layout new Sanitation System GA’s,
■ Effluent Guidelines
– Review EPA’s proposed rules
– Gained Consensus on liner requirements as they
pertain to the DBA design
■ Researched and scoped out equipment for installation of a Water
Table Monitoring System
ELG & CCR Ruling
Typical Wet-to-Dry Ash Conversion Project Durations
Task
January
February
March
April
May
June
July
AugustSeptemberOctoberNovemberDecemberJanuary
February
March
April
May
June
July
AugustSeptemberOctoberNovemberDecemberJanuary
February
March
April
May
June
July
AugustSeptemberOctoberNovemberDecemberJanuary
February
March
April
May
June
2015 2016 2017 2018
Planning Study/
Spec. Development/
Permitting
Request for Proposal/
Procurement
Engineering
Procurement/
Fabrication
Construction/
Commissioning
TOTAL PROJECT DURATION 36-42 months
2015 2016 2017
6-12 months
3-6 months
9-12 months
12 months
12-18 months
2018
Water Table Testing
■ CCR Impoundments must be constructed with a
base/liner located 5 feet above the water table
■ Researched EPA regulations “uppermost aquifer”
■ Developed a Request for and obtained Proposal
for a groundwater measuring system (Solonist)
■ Project Manager currently working with Site
Environmental Representative to obtain approval
for installation.
■ Some of this slide will be moved to slide #
Bottom Ash WTD Conversion Alternatives
Continuous Dewatering & Recirculation System (CDR) with Remote Submerged
Flight Conveyor (RSFC)
Bottom Ash WTD Conversion Alternatives
Continuous Dewatering & Recirculation System (CDR) with Remote SFC’s
Benefits
■ Allow Gibson Station To Stay in Operation
■ Learned basics about the business aspect of power generation
– How EPA rules impact Utilities and ultimately the Ratepayer
– Investing in Capital
■ Doubled the workforce on this project
■ Saved the team time
Conclusion/Summary
■ Going forward, the project team will continue juggling the outage
projects and work towards meeting the deadline on the WTD Ash
project
■ The drawings I have accumulated will be used along with the 3Ds
from UCC to place the high pressure pipes in the plant
■ We will hopefully begin the construction process on the
piezometer soon, then we will be able to determine if the base of
the Continuous Dewatering System will need to be built on
ground level or not
This Rotation
■ More opportunity to get involved
■ More responsibility
■ Transitioning from a corporate setting
■ Work alongside other engineering disciplines
■ The potential benefit of 2 consecutive terms
Looking Ahead
■ After graduation, I would like to build upon my knowledge in the
power industry
■ Potential project management/ structural focus
Questions?

gibson

  • 1.
    Adam Goodin Fossil HydroOperations Co-op Development Program August 13, 2015
  • 2.
    About Me ■ Universityof Kentucky – Senior – Civil Engineering – Graduation: 8/16 ■ 3rd Rotation with Duke – Woodsdale (Spring 14) – Plainfield (Fall 14) – Gibson Station (Current) ■ Gibson Station, Capital Group – Mentor: Mick Harpenau
  • 3.
    My Safety Moment ■Participated in Sitewide Safety Stand-down – Walkdown with experienced Duke and Contractor Management with the sole purpose of eliminating hazards in the workplace ■ Looked for technical malfunctions – Deteriorating grounding equipment – Broken/corroded conduit ■ Housekeeping – Ladders in isleway – Stray pieces of wood and metal could become falling object
  • 4.
    Responsibilities this Rotation ■Document Control on Unit 5 FGD Structural Refurbishment – Maintained IFC Drawings and updated for revisions – Provided Field Support ■ U5 Mercury Re-emission project – Developed P&IDs – Created Valve Lists and Valve Numbers ■ Involved in fall outage coordination meetings – Logistics of large scale project – Schedule formed, laydown areas designated, scope of work
  • 5.
    Dry Bottom AshConversion ■ Support Engineering Efforts on the recently initiated Dry Bottom Ash Conversion Project – April 2015 EPA Ruling – Gibson to adopt a Continuous Dewatering and Recirculation (CDR) System – Locate Existing Underground Drawings – Obtain Existing Area General Arrangement (GA’s) Drawings – Layout Route for new Sanitation System piping
  • 6.
    Dry Bottom AshConversion (Cont.) – Locate Existing Sanitation System Drawings for locating tie points – Layout new Sanitation System GA’s, ■ Effluent Guidelines – Review EPA’s proposed rules – Gained Consensus on liner requirements as they pertain to the DBA design ■ Researched and scoped out equipment for installation of a Water Table Monitoring System
  • 7.
    ELG & CCRRuling Typical Wet-to-Dry Ash Conversion Project Durations Task January February March April May June July AugustSeptemberOctoberNovemberDecemberJanuary February March April May June July AugustSeptemberOctoberNovemberDecemberJanuary February March April May June July AugustSeptemberOctoberNovemberDecemberJanuary February March April May June 2015 2016 2017 2018 Planning Study/ Spec. Development/ Permitting Request for Proposal/ Procurement Engineering Procurement/ Fabrication Construction/ Commissioning TOTAL PROJECT DURATION 36-42 months 2015 2016 2017 6-12 months 3-6 months 9-12 months 12 months 12-18 months 2018
  • 8.
    Water Table Testing ■CCR Impoundments must be constructed with a base/liner located 5 feet above the water table ■ Researched EPA regulations “uppermost aquifer” ■ Developed a Request for and obtained Proposal for a groundwater measuring system (Solonist) ■ Project Manager currently working with Site Environmental Representative to obtain approval for installation. ■ Some of this slide will be moved to slide #
  • 9.
    Bottom Ash WTDConversion Alternatives Continuous Dewatering & Recirculation System (CDR) with Remote Submerged Flight Conveyor (RSFC)
  • 10.
    Bottom Ash WTDConversion Alternatives Continuous Dewatering & Recirculation System (CDR) with Remote SFC’s
  • 11.
    Benefits ■ Allow GibsonStation To Stay in Operation ■ Learned basics about the business aspect of power generation – How EPA rules impact Utilities and ultimately the Ratepayer – Investing in Capital ■ Doubled the workforce on this project ■ Saved the team time
  • 12.
    Conclusion/Summary ■ Going forward,the project team will continue juggling the outage projects and work towards meeting the deadline on the WTD Ash project ■ The drawings I have accumulated will be used along with the 3Ds from UCC to place the high pressure pipes in the plant ■ We will hopefully begin the construction process on the piezometer soon, then we will be able to determine if the base of the Continuous Dewatering System will need to be built on ground level or not
  • 13.
    This Rotation ■ Moreopportunity to get involved ■ More responsibility ■ Transitioning from a corporate setting ■ Work alongside other engineering disciplines ■ The potential benefit of 2 consecutive terms
  • 14.
    Looking Ahead ■ Aftergraduation, I would like to build upon my knowledge in the power industry ■ Potential project management/ structural focus
  • 15.