2. Which of the following statements is true about the requirements traceability matrix?
A. The requirements traceability matrix links product requirements to the assigned
resource.
B. The requirements traceability matrix shows the relationship between the product
requirements with the assigned cost to complete the requirements.
C. The requirements traceability matrix is created through the Define Scope process.
D. The requirements traceability matrix helps to track requirements throughout the
project lifecycle.
HINT: Remember the concept of the requirements traceability matrix.
QUESTION:
3. The correct answer is D.
The requirements traceability matrix links the requirements with work products and
deliverables throughout the project lifecycle to ensure each requirement is tracked for its
completeness and changes.
The requirements traceability matrix is a part of the requirements documentation, which is
created during the Collect Requirements process and is used in the Validate Scope
process.
ANSWER: