Hello everyone! Test your PMP exam preparation and answer this Free PMP® Exam Sample Question of the week. For more of this free PMP exam sample question visit: https://free.pm-exam-simulator.com/free-pmp-exam-simulator
2. The project sponsor asks for a copy of the document that contains the description, owner, source,
priority, and status of product requirements.
Which project document is the project sponsor requesting?
A. The requirements management plan
B. The requirements traceability matrix
C. The scope management plan
D. The work breakdown structure (WBS)
HINT: The document described by the sponsor in the scenario links product requirements from
their origin to the deliverables that satisfy them.
Question
3. The correct answer is B
In this scenario, the project sponsor requested a document that provides specific information
about the product requirements of your current project. The requirements traceability matrix is a
grid that links product requirements from their origin to the deliverables that satisfy them.
Typical attributes used in the requirements traceability matrix may include a unique identifier, a
textual description of the requirement, the rationale for inclusion, owner, source, priority, version,
current status, and status date. Additional attributes to ensure that the requirement has met
stakeholders' satisfaction may include stability, complexity, and acceptance criteria.
Answer
4. All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge
(PMBOK® Guide) standard.
Stop by at free.pm-exam-simulator.com/ and try the
PM Exam Simulator free for 7 days.
We are a trusted and experienced education provider.