This document provides a 16-phase checklist for installing Fox Block insulated concrete forms (ICFs). The checklist outlines procedures for tasks like laying out the first row of blocks, installing reinforcement, bracing walls, adding openings, and pouring concrete. Completing each phase in sequence helps ensure a proper ICF installation.
Esai ini membahas penggunaan material komposit untuk memperbaiki pipa baja yang rusak akibat korosi dengan metode composite wrap. Metode ini melibatkan pemberian lapisan komposit berupa serat karbon atau serat kaca yang dilapisi resin untuk memperkuat area yang rusak dan mengembalikan integritas struktural pipa. Esai ini juga membahas jenis material komposit yang digunakan, sistem perbaikan komposit, dan simulasi perbaikan pipa baja dengan
The document discusses corrosion of steel reinforcement in concrete and methods to minimize it. It describes how carbonation and chloride attacks can cause corrosion through electrochemical processes. Various techniques are presented to mitigate corrosion, including using epoxy coatings on rebar, adding fibers or memory alloys to concrete, using admixtures, hybrid fiber reinforced concrete, and fiber reinforced polymers applied after corrosion begins. Ongoing research gaps and a proposed future study are also mentioned.
Designing a Cold-Formed Steel Beam Using AS4600:2018 and 2005 - WebinarClearCalcs
Recording: https://vimeo.com/318370452
Cold-formed and light gauge steel are rapidly growing in use across residential and commercial projects thanks to their cost-effective and customisable nature.
In this presentation, ClearCalcs engineer Brooks Smith discusses what makes CFS unique, how to design a cold-formed beam to the newly released AS4600:2018, and key differences between the older 2005 version of the standard - most notably the new preference for the use of the Direct Strength Method over the Effective Width Method.
This document provides standards for the design and construction of concrete foundations at Saudi Aramco. It outlines requirements for soils analysis, foundation stability, concrete specifications, and the use of precast foundations. The standards are intended to ensure foundations are adequately designed for their intended use based on accepted engineering practices and industry codes. The document provides mandatory rules for soil bearing pressures, reinforcement, construction methods, and addressing potential underground interferences.
This document discusses the components and types of crash barriers. It describes that crash barriers have various components like W Beam Highway Crash Barrier to protect vehicles from accidents. The types include single sided, double beam, and Thrie beam barriers. Double beams provide strength and durability while Thrie beams offer high performance for large vehicles. Selection of crash barriers depends on the level of protection, installation criteria, flexibility, and conforming to industry standards.
Esai ini membahas penggunaan material komposit untuk memperbaiki pipa baja yang rusak akibat korosi dengan metode composite wrap. Metode ini melibatkan pemberian lapisan komposit berupa serat karbon atau serat kaca yang dilapisi resin untuk memperkuat area yang rusak dan mengembalikan integritas struktural pipa. Esai ini juga membahas jenis material komposit yang digunakan, sistem perbaikan komposit, dan simulasi perbaikan pipa baja dengan
The document discusses corrosion of steel reinforcement in concrete and methods to minimize it. It describes how carbonation and chloride attacks can cause corrosion through electrochemical processes. Various techniques are presented to mitigate corrosion, including using epoxy coatings on rebar, adding fibers or memory alloys to concrete, using admixtures, hybrid fiber reinforced concrete, and fiber reinforced polymers applied after corrosion begins. Ongoing research gaps and a proposed future study are also mentioned.
Designing a Cold-Formed Steel Beam Using AS4600:2018 and 2005 - WebinarClearCalcs
Recording: https://vimeo.com/318370452
Cold-formed and light gauge steel are rapidly growing in use across residential and commercial projects thanks to their cost-effective and customisable nature.
In this presentation, ClearCalcs engineer Brooks Smith discusses what makes CFS unique, how to design a cold-formed beam to the newly released AS4600:2018, and key differences between the older 2005 version of the standard - most notably the new preference for the use of the Direct Strength Method over the Effective Width Method.
This document provides standards for the design and construction of concrete foundations at Saudi Aramco. It outlines requirements for soils analysis, foundation stability, concrete specifications, and the use of precast foundations. The standards are intended to ensure foundations are adequately designed for their intended use based on accepted engineering practices and industry codes. The document provides mandatory rules for soil bearing pressures, reinforcement, construction methods, and addressing potential underground interferences.
This document discusses the components and types of crash barriers. It describes that crash barriers have various components like W Beam Highway Crash Barrier to protect vehicles from accidents. The types include single sided, double beam, and Thrie beam barriers. Double beams provide strength and durability while Thrie beams offer high performance for large vehicles. Selection of crash barriers depends on the level of protection, installation criteria, flexibility, and conforming to industry standards.
This document provides standards of practice for both architects/engineers and reinforcing steel detailers in detailing concrete reinforcement. It defines the responsibilities of both parties and establishes standards for structural drawings, placing drawings, fabrication practices, and computer-assisted detailing. The document is divided into three parts addressing the A/E responsibilities, detailer responsibilities, and reference tables and figures.
This document discusses guidelines and best practices for reinforcing concrete structural elements through proper detailing of rebar. It provides examples of correct and incorrect rebar detailing for slabs, beams, columns, foundations and other elements. The document emphasizes the importance of detailing to ensure structural safety and prevent failures. It outlines general rules for labeling, scheduling and placing rebar as well as specific requirements in codes like IS 456 and IS 13920.
Concrete durability is affected by many factors including the quality of materials used, water-cement ratio, compaction, and curing. Lack of durability can result in cracking, scaling, spalling, or disintegration of concrete. Environmental factors like abrasion, biological growth, freezing and thawing, or chemical attacks from carbonation, chlorides, acids, or sulfates can also damage concrete over time if not properly addressed. Proper concrete mix design, placement, and curing can improve durability.
The document describes 7 examples of designing steel frames using SAP2000. Example 1 analyzes a column using both frame and shell finite element models in SAP2000, finding the shell models more accurately consider shear flexibility. Example 2 analyzes a beam, with shell models again more accurate by including shear and local/distortional effects. Example 3 analyzes a beam-column, showing shell models provide more accurate buckling loads than formulas alone by including shear and joint geometry. Overall, the examples illustrate how SAP2000 tools can be used to both check and optimize steel frame designs according to Eurocode 3, and that shell models tend to provide more accurate analyses and results compared to frame models or formulas alone.
Are you looking to buy Si Wafer? We are a leading supplier of Silicon wafers across six continents in over 45 countries. Call (561) 842-4441 or Shop at our website.
The document summarizes corrosion of steel in concrete. It discusses the common corrosion processes like pitting and crevice corrosion. The main causes of corrosion are chloride ions and carbonation, which can lower the alkalinity of the concrete and expose the steel. It also outlines prevention methods like using epoxy coatings, fly ash, and cathodic protection to protect the steel reinforcement and prevent corrosion.
This document describes using the finite element method to analyze stresses in a truss structure. It defines the truss geometry, elements, and nodes. Stiffness matrices are developed for each element and combined into a global stiffness matrix. Boundary conditions are applied and the system of equations is solved to determine displacements. Stresses are then calculated for each element using the displacements. Finally, reactions are computed at fixed supports.
Hybrid bonding methods for lower temperature 3 d integration 1SUSS MicroTec
* Overview of primary 3D bonding processes
* Mechanics of metal bonding options
* Mechanics for hybrid bond materials
* Process requirement comparisons
* Equipment requirements for hybrid bond processes
The repair and rehabilitation of concrete structures is necessary to extend their lifespan and ensure durability by restoring structural systems to their original positions. Deterioration can be caused by various factors and have effects that endanger safety and utility, requiring distressed structures to be brought back to line, level, and required strength through rehabilitation methods and materials. Tests are available to determine deterioration in structures in need of rehabilitation through case studies of damaged buildings.
When the subsurface stratum is water based or if we deal with a hydraulic structure, the piles are to be driven into water and under water strata. Piles used in underwater structures are often subjected to corrosion. There is no absolute way to eliminate all corrosion; but corrosion protection measures are employed to control the effect of corrosion.
interesting civil engineering topics
civil engineering topics for presentation
civil seminar topics ppt
civil engineering seminar topics 2018
best seminar topics for civil engineering
seminar topics pdf
seminar topics for mechanical engineers
seminar topic for civil engineering pdf
Solidworks engineering design with solid worksمحمد ماجيك
This document provides instructions for a project to design components of a flashlight using SolidWorks software. The four components to be designed are:
1) BATTERY - Created using an extruded base and cuts, with fillets and extruded bosses added for the battery terminals. Dimensions are based on ANSI standards.
2) BATTERY PLATE - Created using an extruded base to hold the battery in place.
3) LENS - Created using the revolve feature to form the lens shape.
4) BULB - Also created using the revolve feature.
The document provides guidance on selecting features and dimensions to complete each component design within SolidWorks.
ALD/CVD applications, equipment and precursors in high volume manufacturingJonas Sundqvist
This document discusses trends in atomic layer deposition (ALD) and chemical vapor deposition (CVD) applications, equipment, and precursors for high-volume manufacturing. It notes that ALD equipment sales have grown to $1.8-1.9 billion annually, with 300mm spatial ALD and multi-wafer tools gaining market share. Advanced logic and memory nodes like 10nm and 7nm are driving increased use of ALD for applications like high-k dielectrics. Key precursor suppliers are also discussed.
Bearing handbook for electric motor skfducnamtrinh
The document is a handbook for electric motor bearings from SKF that provides specifications and information about various bearing types. It includes speed ratings, dimensions, installation tips, lubrication recommendations, and other technical details for SKF deep groove ball bearings in their 6200 and 6300 series. The handbook aims to help users select, install, and maintain SKF bearings for optimal electric motor performance.
This document summarizes British Standard BS 4483:1985 which specifies requirements for factory made welded steel fabric for reinforcing concrete. It outlines information to be provided by purchasers, permissible dimensions and tolerances, classification and testing requirements. Fabric must be manufactured from plain or deformed wire complying with other British Standards, with shear-resistant welded intersections tested to specified loads. The standard provides examples of common designated fabric types and their properties.
Strengthening Of Beams for flexure Using FRPReham fawzy
This document discusses fiber reinforced polymer (FRP) composites used for strengthening concrete structures. It covers various topics such as FRP materials and systems, causes of structural defects, strengthening techniques, and design considerations. Specifically, it describes the different types of fibers and matrices used in FRP, advantages of FRP over traditional materials, and applications of FRP like flexural, shear, and axial strengthening of beams, columns, slabs and walls. It also identifies potential structural defects in design, construction or over the service life of a structure that could require strengthening.
MMUP exam quastions (provided by people who took the exam)Waseem Ahmad
The document contains multiple choice questions about engineering concepts. It covers topics like materials strength, stresses, concrete properties, structural analysis, transportation engineering, project management, and geotechnical engineering. The questions test understanding of key terms, formulas, and applications across various domains of civil engineering.
Bridge-Plate & Multi-Plate Applications and Case Studies (Randy McDonald, P.E...Communications Branding
Ron Prychitko, P.Eng. & Randy McDonald, P.Eng. will provide a complete overview of Bridge-Plate and Multi-Plate applications in Canada. Please join them for a review of engineering, construction, and performance considerations in various applications. This webinar includes case examples for bridges, culverts, stream enclosures, mine portals, road and rail grade separations, pedestrian tunnels and more.
FINFETs were developed to address issues with traditional MOSFETs as components continue to shrink, including short channel effects and higher leakage currents. FINFETs utilize a fin-like structure with a gate on three sides to improve control over the channel and suppress short channel effects. This allows for better scaling to smaller sizes while maintaining performance and lowering power consumption compared to planar MOSFETs and dual-gate devices.
newtableconcept is a slim but solid table that you can mount on your wall like a paint.
The foldable table is an innovative piece of contemporary forniture of italian design.
The user manual describes the space saving features of the collapsible table and giudes you in assembling it.It\'s created from the same designer of the table.
This document provides standards of practice for both architects/engineers and reinforcing steel detailers in detailing concrete reinforcement. It defines the responsibilities of both parties and establishes standards for structural drawings, placing drawings, fabrication practices, and computer-assisted detailing. The document is divided into three parts addressing the A/E responsibilities, detailer responsibilities, and reference tables and figures.
This document discusses guidelines and best practices for reinforcing concrete structural elements through proper detailing of rebar. It provides examples of correct and incorrect rebar detailing for slabs, beams, columns, foundations and other elements. The document emphasizes the importance of detailing to ensure structural safety and prevent failures. It outlines general rules for labeling, scheduling and placing rebar as well as specific requirements in codes like IS 456 and IS 13920.
Concrete durability is affected by many factors including the quality of materials used, water-cement ratio, compaction, and curing. Lack of durability can result in cracking, scaling, spalling, or disintegration of concrete. Environmental factors like abrasion, biological growth, freezing and thawing, or chemical attacks from carbonation, chlorides, acids, or sulfates can also damage concrete over time if not properly addressed. Proper concrete mix design, placement, and curing can improve durability.
The document describes 7 examples of designing steel frames using SAP2000. Example 1 analyzes a column using both frame and shell finite element models in SAP2000, finding the shell models more accurately consider shear flexibility. Example 2 analyzes a beam, with shell models again more accurate by including shear and local/distortional effects. Example 3 analyzes a beam-column, showing shell models provide more accurate buckling loads than formulas alone by including shear and joint geometry. Overall, the examples illustrate how SAP2000 tools can be used to both check and optimize steel frame designs according to Eurocode 3, and that shell models tend to provide more accurate analyses and results compared to frame models or formulas alone.
Are you looking to buy Si Wafer? We are a leading supplier of Silicon wafers across six continents in over 45 countries. Call (561) 842-4441 or Shop at our website.
The document summarizes corrosion of steel in concrete. It discusses the common corrosion processes like pitting and crevice corrosion. The main causes of corrosion are chloride ions and carbonation, which can lower the alkalinity of the concrete and expose the steel. It also outlines prevention methods like using epoxy coatings, fly ash, and cathodic protection to protect the steel reinforcement and prevent corrosion.
This document describes using the finite element method to analyze stresses in a truss structure. It defines the truss geometry, elements, and nodes. Stiffness matrices are developed for each element and combined into a global stiffness matrix. Boundary conditions are applied and the system of equations is solved to determine displacements. Stresses are then calculated for each element using the displacements. Finally, reactions are computed at fixed supports.
Hybrid bonding methods for lower temperature 3 d integration 1SUSS MicroTec
* Overview of primary 3D bonding processes
* Mechanics of metal bonding options
* Mechanics for hybrid bond materials
* Process requirement comparisons
* Equipment requirements for hybrid bond processes
The repair and rehabilitation of concrete structures is necessary to extend their lifespan and ensure durability by restoring structural systems to their original positions. Deterioration can be caused by various factors and have effects that endanger safety and utility, requiring distressed structures to be brought back to line, level, and required strength through rehabilitation methods and materials. Tests are available to determine deterioration in structures in need of rehabilitation through case studies of damaged buildings.
When the subsurface stratum is water based or if we deal with a hydraulic structure, the piles are to be driven into water and under water strata. Piles used in underwater structures are often subjected to corrosion. There is no absolute way to eliminate all corrosion; but corrosion protection measures are employed to control the effect of corrosion.
interesting civil engineering topics
civil engineering topics for presentation
civil seminar topics ppt
civil engineering seminar topics 2018
best seminar topics for civil engineering
seminar topics pdf
seminar topics for mechanical engineers
seminar topic for civil engineering pdf
Solidworks engineering design with solid worksمحمد ماجيك
This document provides instructions for a project to design components of a flashlight using SolidWorks software. The four components to be designed are:
1) BATTERY - Created using an extruded base and cuts, with fillets and extruded bosses added for the battery terminals. Dimensions are based on ANSI standards.
2) BATTERY PLATE - Created using an extruded base to hold the battery in place.
3) LENS - Created using the revolve feature to form the lens shape.
4) BULB - Also created using the revolve feature.
The document provides guidance on selecting features and dimensions to complete each component design within SolidWorks.
ALD/CVD applications, equipment and precursors in high volume manufacturingJonas Sundqvist
This document discusses trends in atomic layer deposition (ALD) and chemical vapor deposition (CVD) applications, equipment, and precursors for high-volume manufacturing. It notes that ALD equipment sales have grown to $1.8-1.9 billion annually, with 300mm spatial ALD and multi-wafer tools gaining market share. Advanced logic and memory nodes like 10nm and 7nm are driving increased use of ALD for applications like high-k dielectrics. Key precursor suppliers are also discussed.
Bearing handbook for electric motor skfducnamtrinh
The document is a handbook for electric motor bearings from SKF that provides specifications and information about various bearing types. It includes speed ratings, dimensions, installation tips, lubrication recommendations, and other technical details for SKF deep groove ball bearings in their 6200 and 6300 series. The handbook aims to help users select, install, and maintain SKF bearings for optimal electric motor performance.
This document summarizes British Standard BS 4483:1985 which specifies requirements for factory made welded steel fabric for reinforcing concrete. It outlines information to be provided by purchasers, permissible dimensions and tolerances, classification and testing requirements. Fabric must be manufactured from plain or deformed wire complying with other British Standards, with shear-resistant welded intersections tested to specified loads. The standard provides examples of common designated fabric types and their properties.
Strengthening Of Beams for flexure Using FRPReham fawzy
This document discusses fiber reinforced polymer (FRP) composites used for strengthening concrete structures. It covers various topics such as FRP materials and systems, causes of structural defects, strengthening techniques, and design considerations. Specifically, it describes the different types of fibers and matrices used in FRP, advantages of FRP over traditional materials, and applications of FRP like flexural, shear, and axial strengthening of beams, columns, slabs and walls. It also identifies potential structural defects in design, construction or over the service life of a structure that could require strengthening.
MMUP exam quastions (provided by people who took the exam)Waseem Ahmad
The document contains multiple choice questions about engineering concepts. It covers topics like materials strength, stresses, concrete properties, structural analysis, transportation engineering, project management, and geotechnical engineering. The questions test understanding of key terms, formulas, and applications across various domains of civil engineering.
Bridge-Plate & Multi-Plate Applications and Case Studies (Randy McDonald, P.E...Communications Branding
Ron Prychitko, P.Eng. & Randy McDonald, P.Eng. will provide a complete overview of Bridge-Plate and Multi-Plate applications in Canada. Please join them for a review of engineering, construction, and performance considerations in various applications. This webinar includes case examples for bridges, culverts, stream enclosures, mine portals, road and rail grade separations, pedestrian tunnels and more.
FINFETs were developed to address issues with traditional MOSFETs as components continue to shrink, including short channel effects and higher leakage currents. FINFETs utilize a fin-like structure with a gate on three sides to improve control over the channel and suppress short channel effects. This allows for better scaling to smaller sizes while maintaining performance and lowering power consumption compared to planar MOSFETs and dual-gate devices.
newtableconcept is a slim but solid table that you can mount on your wall like a paint.
The foldable table is an innovative piece of contemporary forniture of italian design.
The user manual describes the space saving features of the collapsible table and giudes you in assembling it.It\'s created from the same designer of the table.
Fabral provides installation guidelines for their 1-1/2" SSR metal roofing system. Key details include:
- Panels are factory caulked and have a minimum slope of 1:12.
- Proper substrate preparation and underlayment are required before installing panels.
- Panels are installed starting at the gable end and locked together along the length using overlapping ribs.
- Accessories like closures, flashings and trims are installed using sealants and fasteners to provide a weather tight seal.
- Proper storage, handling and installation techniques are outlined to ensure quality installation and performance of the system.
The user manual describes how to install and use the foldable table. The collapsible table is very compact, yet is very easy end fast to open and close.
The folding table is wall mounted, it is only a little bit more than one inch, an innovativate space-saving feature.
The table is a piece of contemporary design furniture made in Italy with lacquered or laminated board and stainless steel structures.
The following Installation Guide is designed to provide Watch Technologies’
customers with sufficient information to successfully install our gates as designed.
Typically, our customers were provided both Shop Drawings and a 3-D CAD model
of their gates prior to manufacture for both review and authorization to
manufacture. If that was not the case please contact our office and secure these
documents. These documents alone, however, may not provide the all the
guidance everyone may require to place their gates into position and secure them
for the long-term. This Guide will clearly define how Watch Technologies’ staff
would install our gates.
This document provides installation instructions for a Bright Covers patio cover system. It begins with general recommendations to fully read and understand the instructions before installation. The document then lists required tools and system components. It provides details on laying out the system, including minimum pitch requirements and height measurements. Instructions are given for installing the hanging rail to the house or roof, as well as for installing the posts and I-beam. Diagrams illustrate hanging rail connection details. The document aims to ensure a successful standard installation of the Bright Covers system.
This document provides details about the summer training project undertaken by the author at a construction site of GEE INTERNATIONALS. It summarizes the key aspects of the project which involved construction of government senior secondary school. The project details shared include the EHS safety protocols followed, quality management processes, site planning through drawings and bar charts, and sequencing of construction activities from site clearance to project completion. The summary focuses on the high-level overview and essential details provided in the document.
The document provides instructions for laying out the deck by marking the location of footings and support posts using string lines and measurements to ensure the deck is level, square, and positioned correctly based on the design plans. Key steps include marking the ledger board height and drainage slope, establishing the perimeter outline and interior post locations with string lines, and checking for square. Accuracy in measurements and layout is emphasized to avoid problems during construction.
The document describes Spectral's CATENA modular furniture system. CATENA allows for endless design combinations by mixing and matching cabinets of varying widths, heights, and depths that can be assembled in different configurations. Cabinets can be placed on bases, mounted on walls, or used freestanding in the center of a room. The system includes options for doors, drawers, shelves, and integrated sound systems to create beautiful, functional living spaces.
THE EFFECT OF OPENINGS IN THE SLAB STIFFENED WITH SHALLOW BEAMSIRJET Journal
This document summarizes a study that analyzed the effect of openings in reinforced concrete slabs stiffened with shallow beams. 24 slab models with different beam depths and opening locations/sizes were analyzed using finite element modeling. The modeling found that as beam depth decreased, deflection increased but still met serviceability standards. Ultimate load capacity generally increased as beam depth decreased, with the center opening slab having the highest capacity. The study concluded that designing based on orthotropy values that account for openings ensures ultimate capacity exceeds design loads, and trends in capacity can be explained by reinforcement quantity and stress.
Dowels are used to obtain precise positioning between mating parts. Dowels provide a press fit in one component and a tight push fit in the mating component. When assembling parts with blind dowel holes, a slight flat is provided along the dowel's length to prevent air locks. For ease of assembly, one dowel is typically made longer than the other by about one diameter. To ensure precise alignment of dowel holes, the holes are drilled and reamed with the components screwed together.
IRJET- Design and Development of Fixture for Skid Sole of RotavatorIRJET Journal
The document discusses the design and development of a fixture for the skid sole of a rotavator. It begins with an abstract and introduction on the importance of fixtures in manufacturing. It then provides details on the existing problem at Jadhao Layland company, where the long setup time for their rotavator product was an issue. The document then covers fixture design procedures and considerations, such as locating surfaces, clamping positions, and ensuring stability and accuracy. It describes the development process for a new fixture for the skid sole of the rotavator, to address the long setup times with the existing fixture. The new fixture aims to improve productivity through time savings.
This document provides information about Fit Slab formworks for constructing voided slabs made of reinforced concrete. Fit Slab is a lightweight polypropylene formwork that is used in conjunction with prefabricated concrete beams or lattice slabs to form voided slabs. Using Fit Slab allows for quicker installation and yields slabs that are lighter in weight compared to traditional construction methods. The document includes contact information, technical specifications of Fit Slab modules, applications, advantages, and installation instructions.
Folding Table Compact - User Manual Rev. 04Renzo Lisei
1. This document provides instructions for assembling and using a compact folding table.
2. The table folds for storage and features a patented "FastLeg" locking mechanism for easy opening and closing.
3. Assembly requires attaching the tabletop and legs to the wall using supplied screws and dowels, with options for adding a shock absorber.
This document provides installation instructions for the Quad-Lock Building System. It begins with safety checks and reviewing other documentation. It then provides step-by-step instructions for installing panels, ties, and brackets to form walls. Details are given for corners, angles, joints and adding accessories. Pre-pour checks are listed and concrete placement instructions emphasize proper consolidation and lifting. Bracing, forming and curing are also outlined.
This document provides information about Fox Blocks insulated concrete forms (ICFs), including their training programs, product lineup, installation benefits, and estimating process. The training programs provide different certification levels as contractors gain experience. The product lineup includes straight blocks, corners, specialty pieces, and accessories. Key benefits are that the large interlocking system and extended corners eliminate the need for extra materials like truss wire or strapping. Contractors can save time and money on installations using Fox Blocks.
1. The document describes the design and analysis of a punching die. It aims to design an interchangeable die and punches to reduce weight by changing materials.
2. The die set is designed to perform individual operations at each station with a single press stroke, unlike a progressive die. The parts are designed in SolidWorks and analyzed using SimulationXpress.
3. The die, punches, and guide pins are made of LM6 alloy for its light weight and hardness. The bottom plate is designed to provide space for die operations while withstanding bending stresses well below its limits.
Channellock is launching a new line of high-performance ratchets, sockets, and wrenches exclusively at the store. The new tools offer improved grip with textured bands, easy identification of metric and SAE sockets with color bands, and better performance with the 72-tooth ratchet's 5 degree swing compared to the standard 10 degree. The store is also providing a free copy of the new Channellock catalog and features a lifetime warranty on all tools.
This document provides a table of contents and product listings for tools and tool accessories. It includes summaries of socket sets, wrenches, pliers, screwdrivers, and other items. Channellock brand tools are highlighted in blue text and are available exclusively at the store or online. The summary encourages customers to shop the store for their tool and workshop needs.
The document provides information about tools available for purchase from a hardware store or warehouse. It lists over 67,000 items under categories such as routers, sanders, grinders, planers, drills, saws, and more. It describes the features of sample tools in each category and provides the stock keeping unit number and price for each. The document encourages customers to shop in-store, online, or call to order if an item is needed but not in stock in the store.
This document is a 2015 product catalog for Delta and Peerless kitchen, bath and plumbing products. It includes kitchen faucets with pull-down, pull-out and single handle designs. It also includes bath faucets, shower systems, toilets and accessories. The catalog provides product images, descriptions and part numbers to help customers identify the appropriate products for their projects.
This document describes several lighting collections from Canarm Ltd., including:
1) The Warren Collection, an upper mid-level price point option with traditionally inspired designs in rubbed antique bronze finish and tea stained glass.
2) The Flamenco Collection, also an upper mid-level price point featuring classical curved lines with opal glass in brushed nickel.
3) Collections of vanity lights and interior lighting in various price points and styles to suit different room needs and budgets.
This document provides an overview and product listings for Home Impressions brand bathroom fixtures and accessories. It includes:
- An introduction to the Home Impressions line and benefits of the brand for retailers.
- Tables of contents and product listings for various categories including faucets, showerheads, bath accessories and more.
- Specifications and features for each product line.
The document aims to showcase the variety of styles and finishes available within the Home Impressions collection for retailers to offer customers comprehensive bathroom solutions. It highlights over 400 stock keeping units across 11 categories of fixtures.
This document provides information on ceiling fan assortments for different ceiling heights. The 12' ceiling fan assortment offers a variety of styles, sizes, finishes, and price points to appeal to different customers. The 8' assortment also varies in popular features while reducing sku count. The 4' assortment focuses on lower prices, sizes, and mounts to attract new customers. Each assortment aims to provide ceiling fans to suit different customer needs and budgets.
This document provides the pricing and order form for a SawStop jobsite saw and accessories. It lists the price for shipping a saw directly from SawStop to a customer as $100. It also provides the item descriptions, part numbers, prices and quantities for the 1.5HP jobsite saw and various blade cartridges, guards, inserts and blades that can be ordered. Shipping rates and notices that prices are subject to change without notice are also included.
The SawStop Jobsite Saw provides SawStop safety technology in a compact, portable design. It features an innovative one-turn blade elevation system, easy blade tilting, advanced dust collection, and a smooth-sliding fence for accuracy. The low-profile blade guard and quick-change riving knife increase safety while minimizing interference. Large wheels and a collapsible cart make it easy to transport the saw between job sites.
Western Building Center is having a pole barn special where 6x6 treated wood posts ranging from 8 to 20 feet long are $333 per linear foot and 36-inch metal roofing and siding is $180 per linear foot, with the sale ending on April 30, 2016.
Elkay is running a promotion from February 2nd to March 14th, 2016 in Region 2 that offers percentage discounts on cabinets based on price groups when a minimum of 10 cabinets are purchased. The discounts are 10% for price groups 7-12, 7% for price groups 1-6, and 5% for Silverline cabinets. To qualify for the discounts, orders must meet the 10 cabinet minimum, not be a special project, and be released and scheduled within 5 days of the promotion end date. Elkay reserves the right to amend or terminate the promotion.
Western Building Centers is having a sale from January 27th through February 26th with discounted prices on various tools, supplies, and hardware items. The document lists 25 different products on sale including windshield washer fluid for $1.59, DucTape for $2.19, a 14.5" magnetic floor sweeper for $16.47, a rubbermaid 32 gallon trash can for $22.97, and an 18 gauge Hitachi 2" brad nailer for $67.97. Most items are priced significantly lower than the suggested retail price. The sale is for stock on hand only and does not apply to dealer or big box store sales.
The document is a quote from Western Building Center for building materials for a 40x60 pole barn. It includes a list of materials such as treated lumber posts and beams, sheathing, roofing materials, and other items. The total cost of the quote is $23,000 including taxes. It provides the contractor with a complete list of all materials needed to build the pole barn.
The document is a quote from Western Building Center for materials for a 30x40 pole barn with two 10x10 overhead doors and one man door. It includes a list of building materials such as lumber, fasteners, roofing materials, and pre-engineered trusses. The total quote amount is not stated. The quote is addressed to Cash Account 0101 and expires on December 12, 2015.
This document is a quote from Western Building Center for materials to build a 24x24 pole barn with a 16x8 overhead door and one man door. It lists the various lumber, hardware, and metal roofing materials needed along with quantities, descriptions, and pricing. The total quote amount is not stated but includes items like 6x6 treated timbers, 2x6 and 2x8 boards, roofing screws, hanger straps, a door unit, and prefabricated metal roof pieces.
This document provides guidance on maintaining and finishing a log or wood home exterior. It discusses the importance of regular maintenance to preserve the home's appearance and protect the wood. Some key points covered include preparing the wood surface by cleaning and sanding, choosing an appropriate stain based on compatibility and performance, and applying a top coat. Regular inspections are recommended along with reapplying stain as needed, especially to sun-exposed sides of the home. Proper construction techniques like adequate eaves and drainage are also discussed to minimize wood exposure to elements.
The document describes Makita power tools that are on sale during the summer of 2015. It provides details on several Makita 18V lithium-ion cordless tool combo kits, individual tools, and accessories. These include hammer drills, impact drivers, circular saws, jigsaws, reciprocating saws, and more. Specifications such as voltage, battery type, torque output, weight, and included accessories are provided for each item.
This document provides information about various outdoor furniture sets for patio and backyard use, including chat sets, dining sets, and individual pieces. It describes the materials, features, and prices of multiple product lines. Some highlights include the Glenwood chat set made of durable PVC wicker, the Monaco curved sectional featuring all-weather resin wicker, and the Champlain chat set with a center fire table. Accessories like umbrellas, speakers, and beverage tables are also mentioned.
The document is a catalog for home décor and hardware products. It includes sections for cabinet and door hardware, lighting and fans, flooring, bath décor, kitchen accessories, and home enhancements. It encourages browsing the store or website for over 67,000 product options. The cover image shows mini pennant lights.
This document lists fencing materials for sale including 3” x 6'6” and 5” x 6'6” treated fence posts, 4” x 16'6” half round and treated rails, and 1”x6” x 6' cedar fencing. The items are available at Western Building Center located at 1019 East Idaho in Kalispell, Montana and can be purchased for the prices provided.
It’s no secret that the marketing landscape is growing increasingly complex, with numerous channels, privacy regulations, signal loss, and more. One of the biggest problems facing marketers today is that they’re experiencing data deluge and data drought simultaneously.
Bliss Point by Tinuti addresses these challenges by providing a single, user-friendly platform for measuring what marketers previously struggled to measure. With Bliss Point, you can move beyond simply validating past actions and instead use measurement to guide real-time decision-making on what should happen next.
Join our product experts for a live demonstration of Bliss Point. Discover how it can empower your brand with the tools and insights needed to optimize each channel, across your entire media mix, and your overall brand performance.
The Future of E-commerce: first-hands insights.Solvd, Inc.
According to Statista, revenue in the e-commerce market is projected to reach US$4,117.00bn in 2024. New technologies and methodologies constantly influence how the e-commerce market develops and shapes itsthe future of e-commerce. The main questions are in the air: How can we stay aligned with e-commerce business owners and ensure our engineering services meet their evolving needs?
At Solvd, this question prompted a deep dive into the current e-commerce landscape. Our goal was to get information about the future of e-commerce directly from first-hand sources. In the course of our research, we explored:
- Portrait of respondents.
- Current challenges and pain points of the e-commerce industry.
- Emerging trends and upcoming opportunities.
- Human resource allocation for e-commerce projects.
- Solutions and actionable advice for business owners.
- The role of a reliable partner in problem-solving.
Explore, download, and share invaluable insights made by Solvd!
2. 877-369-2562 | WWW.FOXBLOCKS.COM | 6110 Abbott Drive | Omaha, NE 68110 Fox Blocks Installation Checklist: 1ST Edition2
installation CHECKLISTS
The Checklists on the following pages are to help remind you of proper sequencing
as well as highlight items that could be missed.
The lists will help crews continue to build efficiently at times when the lead hand
is unavailable.
PHASE JOB STatus workbook page
1 Prior to Job Page 3
2 Product Delivery Page 3
3 Start of Job Check List Page 4
4 Row 1 Page 4
5 Reinforcement Page 5
6 Row 2 Page 5
7 Row 3 Page 6
8 Row 4 Page 6
9 Bracing Page 7
10 Openings Page 8
11 Top Row Page 8
12 Prior to Concrete Page 9
13 Multiple Levels Page 9
14 Concrete Page 10
15 Post Concrete Page 11
16 Extreme Weather Concreting Page 11
3. 6110 Abbott Drive | Omaha, NE 68110 | 877-369-2562 | WWW.FOXBLOCKS.COMFox Blocks Installation Checklist: 1ST Edition 3
Phase 1: Prior to Job
1 Blueprint shows rebar schedule or proper rebar design has been established.
2 Rough opening sizes are available for all window and door openings.
3 Wall heights have been pre-planned to determine the number of courses needed.
4 Height of top and/or bottom of openings are clear.
5 Depth of backfill is clear if needed.
6 Thickness of concrete is established.
_________________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
Phase 2: product delivery
1 There is clear access for delivery truck
2 Staging area is established for block.
3 Bracing and rebar will be arriving at or close to the same time as ICF block.
4 Job is squared prior to material being moved in. (Hard to do after)
_________________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
____________
4. 877-369-2562 | WWW.FOXBLOCKS.COM | 6110 Abbott Drive | Omaha, NE 68110 Fox Blocks Installation Checklist: 1ST Edition4
Phase 3: start of Job
items needed to build job: tools including:
1 Rebar and design.
2 Blueprint.
3 Buck material and opening sizes.
4 ICF blocks.
5 Alignment/scaffold system
including screws.
6 2 x 10 planks.
7 Anchor bolts or Simpson Hangers
8 Strapping
9 Fox Block HV Clips
________________________________________________________________________________
________________________________________________________________________________
Phase 4: row 1
1 Footing / Slab is clean level & squared.
2 Chalk lines are complete. (Outside of form is outside of
building dimension)
3 Mark out all window and door openings on working surface. Have someone
start to build bucks.
4 Place the ICF corner block - line up to chalk line. Can go either way with long
leg of corner.
5 Starting at corner block, place straight ICF blocks and attach tightly together
end to end with Fox Block HV Clips.
6 Work from each corner block toward the center of the wall. Creating a joint at
an opening works well.
7 Decide if you are going to use a butt or lapped joint. (Butt joints do not need to
be cut on a line, lapped joints must be cut straight and on a line.)
8 Once 1st row is complete, install rebar as per plans, code or engineering.
(See sheet 2 on reinforcement)
________________________________________________________________________________
________________________________________________________________________________
1 Saws (pruning and handsaw)
2 Tie wire & Pliers
3 Spray foam adhesive
4 Rebar bender / cutter
5 Chalk and string lines
6 Proper signage
7 Table saw to rip cut block
5. 6110 Abbott Drive | Omaha, NE 68110 | 877-369-2562 | WWW.FOXBLOCKS.COMFox Blocks Installation Checklist: 1ST Edition 5
Phase 5: reinforcement
1 As rebar is placed, remember that concrete needs access to fill wall.
2 Horizontal rebar should alternate to allow vertical rebar to be held
in place.
3 All lap splices should overlap 40 bar diameters.
(Unless Engineering shows different.)
4 Contact lap splices must be tied. Non contact lap splices do not
need to be tied.
5 Lintel rebar should have 2” concrete cover at bottom.
C - Stirrups as per reinforcing charts or Engineering.
Clever Tip: Reinforcing Steel
Below Grade Walls = Usually Tension Side.
Above Grade Walls = Usually Center of Wall
________________________________________________________________________________
________________________________________________________________________________
Phase 6: row 2
1 Start row 2 at same corner you started row 1 and using the opposite corner
you started with on row 1.
2 Place straight forms from the corner form. Webs should line up automatically.
3 Use Fox Block HV Clips to connect rows 1 and 2 together at 24” o/c and 1st
and 3rd tie from every corner.
4 Once 2nd row is complete, install rebar as per plan, code or engineering.
5 Check top of 2nd course to confirm level footings. Shim and/or trim as needed
to be +/- 1/4”
6
If satisfied, kick wall to the chalk lines and spray foam to footings at 16” o/c
and both sides of wall. (Insert tip of spray foam under form so spray foam fills about
2” of space.)
7
Remember that courses 1,3,5,7 and courses 2,4,6,8
are all the same pattern for stacking. Once you have
the first 2 courses stacked this is your blueprint for
all other courses.
________________________________________________________________________________
________________________________________________________________________________
6. 877-369-2562 | WWW.FOXBLOCKS.COM | 6110 Abbott Drive | Omaha, NE 68110 Fox Blocks Installation Checklist: 1ST Edition6
Phase 7: row 3
1 Start at same corner as row one and lay forms out along wall.
2 All joints should line up with joints on row one.
3 Use Fox Block HV Clips on 1st and 3rd tie from each corner and in both
directions from corner.
4 If a block is to be cut, it’s size should be the same as row one.
5 Install rebar as per plan, code or engineering.
________________________________________________________________________________
________________________________________________________________________________
Phase 8: row 4
1 Start at same corner as row one and lay forms out along wall.
2 All joints should line up with joints on row two.
3 Use Fox Block HV Clips on 1st and 3rd tie from each corner and in both
directions from corner.
4 If a block is to be cut, it’s size should be the same as row two.
5 Install rebar as per plan, code or engineering.
________________________________________________________________________________
________________________________________________________________________________
________________________________________________________________________________
________________________________________________________________________________
A
A
A
A B
A) Vertical Fox Block HV Clips to
course below
B) Horizontal Fox Block HV Clips
holding corner block to
straight block
FOX BLOCK HV CLIP
7. 6110 Abbott Drive | Omaha, NE 68110 | 877-369-2562 | WWW.FOXBLOCKS.COMFox Blocks Installation Checklist: 1ST Edition 7
Phase 9: bracing
1 When laying out bracing keep in mind how it will safely support scaffold planks.
2 At each corner you should have at least one scaffold, place it on the 4th tie
from the corner. (24”)
3 Space bracing so planks will fit. (9 or 10 webs apart work good for 14’ planks)
4
Attach strong backs using one #10 sheet metal screw, at the top of the
slots, into the tie of each ICF form. Keep screws loose enough to slide in the
slot. Do not use tapping screws. Strong back should line up with cut lines on
form units to ensure they will line up with top row ties.
5
Attach one turnbuckle and scaffold bracket to one strong back and measure
to make sure height will be good for concrete placement. If not, try another
set of holes in the strong back.
6 Install all turnbuckles at same height.
7 Attach turnbuckles to ground slab or floor. (Not less than 45 degrees. Extend
if needed)
8 Install all scaffold brackets at same height to allow planks to line up.
9 Place planking and secure in place.
10 Install guard rails if needed.
11
Plumb all corners and install a string line at top of wall along the out side edge.
Slide a 3/4” spacer block between the string and the form at each corner, and
slide a 3/4” spacer block along wall and adjust the plumb of the wall with the
alignment turnbuckles as you move along the wall from corner to corner.
12 Just before concrete placement it is a good practice to adjust the top of the
wall IN about a 1/4”. Leave the corners plumb.
13 During the concrete placement monitor the string line and if the wall moves
toward the string have someone adjust it back.
14 After the concrete placement, realign the walls using the string, blocks and
turnbuckles.
________________________________________________________________________________
________________________________________________________________________________
________________________________________________________________________________
________________________________________________________________________________
8. 877-369-2562 | WWW.FOXBLOCKS.COM | 6110 Abbott Drive | Omaha, NE 68110 Fox Blocks Installation Checklist: 1ST Edition8
Phase 10: openings
1 Establish the bottom of buck and mark on forms.
2
If the outside edge of buck lines up on a tie you
should alter web pattern or simply slide the buck
over.
3 Cut the forms to accept the bucks.
4 If needed install vertical rebar into spaces under
the buck locations.
5 Bucks should be built with access points in
bottom to allow for concrete placement.
6 Place the bucks onto position on wall. Buck does
not need to line up with cut lines on forms.
7 Build ICF forms around buck.
________________________________________________________________________________
________________________________________________________________________________
Phase 11: top row
1 Establish where lintel rebar will need to be prior to laying forms in place.
2
If needed place lintel rebar on top of window and door bucks. Remember to
keep the rebar up off the buck to allow the proper amount of concrete to flow
around rebar as required by code.
3 Start at same corner as row one and lay forms out along wall.
4 Use Fox Block HV Clips to hold the forms together horizontally.
5 Use Fox Block HV Clips at 1st and 3rd tie from each corner and in both
directions from corner.
6 Use Fox Block HV Clips on entire row at 2’ o/c. (Second tie back from all joint
lines)
7 Install service penetrations if needed.
8 Insert beam pockets if needed. Hint: 2 layers of ICF foam cut from scrap on site will
give you a 5 1/4” pocket. Then just cut it out after the concrete cures.
9 Install vertical rebar as per plan, code or Engineering.
________________________________________________________________________________
________________________________________________________________________________
9. 6110 Abbott Drive | Omaha, NE 68110 | 877-369-2562 | WWW.FOXBLOCKS.COMFox Blocks Installation Checklist: 1ST Edition 9
Phase 12: Prior to concrete
1
Attach a string line to monitor wall during concrete placement. (A good spot for
the string line is opposite the bracing about 2” down from the top of the wall. See
notes in bracing section)
2 Rebar and lintel steel is complete as per plan.
3 Openings have been braced and framed.
4 Stacked joints (any joints 8” or less apart) have been strapped.
5 Short wall sections (4’ or less) have been strapped.
6 Beam pockets are in place.
7 Sill plate attachment is ready for installation after concrete placement.
8 Space is ready for concrete pump to set up.
________________________________________________________________________________
________________________________________________________________________________
________________________________________________________________________________
________________________________________________________________________________
Phase 13: multiple levels
1 Top of foam has been covered to protect from concrete.
2 Service penetrations have been installed. (Vents, central vac exhaust etc.)
3 Rebar dowels are ready to be installed.
4 When placing concrete remember to leave a portion of the tie exposed. This
will allow you to tie the next row down when you continue building.
5 Embeds Installed and secured
________________________________________________________________________________
________________________________________________________________________________
________________________________________________________________________________
________________________________________________________________________________
10. 877-369-2562 | WWW.FOXBLOCKS.COM | 6110 Abbott Drive | Omaha, NE 68110 Fox Blocks Installation Checklist: 1ST Edition10
Phase 14: concrete
1
Establish concrete crew and who will be responsible for what.
a. One person to place concrete
b. Two people to consolidate concrete
c. One or two people leveling walls
d. Extra manpower on pour day is not a bad thing!
2 You have to tell the pump operator how many lifts you will be doing and what
slump concrete you want. 2’ to 4’ lifts with a 5” to 6” slump is normal.
3 Start placing concrete at least 2’ from a corner. (Never into a corner as it
could move the wall). Always flow the concrete through the corner.
4
If the concrete gets through the top rebar with just a bit of restriction the
slump is good. If the concrete flows freely past the top rebar the slump could
be to high.
5 Create a lift of concrete on either side of corner before actually filling the cor-
ner. These lifts on either side act as an anchor holding the corner in place.
6
At a window fill from one side and let the concrete flow under the window
buck, then stop the pump, move to the opposite side of the buck, and
continue. Some windows will require extra concrete to be placed into the
opening at bottom of buck.
7 Consolidate concrete during each lift following the person who is
placing concrete.
8 Leave at least 18” to 24” at top of wall for final lift. This will allow concrete
pump to keep up.
9 Monitor walls during and after concrete placement and then adjust
turnbuckles to level walls.
10 If required, install anchor bolts.
11 Ensure all window and door bucks have been consolidated properly by hitting
their face all around with a hammer.
12 Clean concrete off footings, slabs, scaffold, walls, tools etc.
13 Before you leave take one last look to ensure your walls are straight and
plumb.
________________________________________________________________________________
________________________________________________________________________________
________________________________________________________________________________
________________________________________________________________________________
11. 6110 Abbott Drive | Omaha, NE 68110 | 877-369-2562 | WWW.FOXBLOCKS.COMFox Blocks Installation Checklist: 1ST Edition 11
Phase 15: post concrete
1
Bracing should be left in place for 72 hours after concrete placement. If you
must remove bracing, from 24 to 72 hours after concrete placement, it is
recommended that you place temporary bracing against walls prior to
removing ICF bracing.
2 Damp proofing may be required according to building code. (Peel & Stick and/or
dimple membranes have been the most common damp proofing methods for ICF’s.)
3 Prior to backfill you may need to have floor diaphragm in place according to
building code.
________________________________________________________________________________
________________________________________________________________________________
Phase 16: Extreme weather concreting
When building with ICF’s in extreme weather, there are just a few additional precautions that
need to be taken.
1 Keep walls covered to keep snow out of wall cavity. Concrete does not melt
snow.
2
If you get snow into the wall cavity you must remove it prior to concrete
placement. This can be done by cutting temporary holes into the bottom of
forms or drizzling hot water into the forms. Hot water comes on the mixer
trucks in winter.
3 Use 18” wide insulated tarps or equivalent along top of wall.
4
In very cold weather (-0˚ F / -20˚ C) only lift off 8’ of insulation at a time while
placing concrete. This will allow the warmth of the concrete to preheat the wall
and rebar during the pour.
5
When complete cover the wall to protect concrete from cooling. The hydration
process will keep the wall at a good temperature without the need for any extra
hoarding or heating.
6 Remember to cover exposed concrete at bucks.
7 In very hot weather keep exposed concrete covered and apply moisture applied.
________________________________________________________________________________
________________________________________________________________________________
________________________________________________________________________________
12. 6110 Abbott Drive | Omaha, NE 68110 | 877-369-2562 | WWW.FOXBLOCKS.COMFox Blocks Installation Checklist: 1ST Edition
A PRODUCT OF:
Please go to:
www.foxblocks.com
Where you will find:
Regional Manager Contact Information
Local Dealer Contact Information
Downloadable Technical Files
Estimating Software
On-Site Movies
Photos & More
Head Office: