installation CHECKLISTS
The Checklists on the following pages are to help remind you of proper sequencing
as well as highlight items that could be missed.
The lists will help crews continue to build efficiently at times when the lead hand
is unavailable.
PHASE	 JOB STatus	workbook page
1 Prior to Job Page 3
2 Product Delivery Page 3
3 Start of Job Check List Page 4
4 Row 1 Page 4
5 Reinforcement Page 5
6 Row 2 Page 5
7 Row 3 Page 6
8 Row 4 Page 6
9 Bracing Page 7
10 Openings Page 8
11 Top Row Page 8
12 Prior to Concrete Page 9
13 Multiple Levels Page 9
14 Concrete Page 10
15 Post Concrete Page 11
16 Extreme Weather Concreting Page 11
6110 Abbott Drive | Omaha, NE 68110 | 877-369-2562 | WWW.FOXBLOCKS.COMFox Blocks Installation Checklist: 1ST Edition 3
Phase 1: Prior to Job
1 Blueprint shows rebar schedule or proper rebar design has been established.
2 Rough opening sizes are available for all window and door openings.
3 Wall heights have been pre-planned to determine the number of courses needed.
4 Height of top and/or bottom of openings are clear.
5 Depth of backfill is clear if needed.
6 Thickness of concrete is established.
_________________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
Phase 2: product delivery
1 There is clear access for delivery truck
2 Staging area is established for block.
3 Bracing and rebar will be arriving at or close to the same time as ICF block.
4 Job is squared prior to material being moved in. (Hard to do after)
_________________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
____________
877-369-2562 | WWW.FOXBLOCKS.COM | 6110 Abbott Drive | Omaha, NE 68110 Fox Blocks Installation Checklist: 1ST Edition4
Phase 3: start of Job	
items needed to build job:	 tools including:
1 Rebar and design.
2 Blueprint.
3 Buck material and opening sizes.
4 ICF blocks.
5 Alignment/scaffold system
including screws.
6 2 x 10 planks.
7 Anchor bolts or Simpson Hangers
8 Strapping
9 Fox Block HV Clips
________________________________________________________________________________
________________________________________________________________________________
Phase 4: row 1
1 Footing / Slab is clean level & squared.
2 Chalk lines are complete. (Outside of form is outside of
building dimension)
3 Mark out all window and door openings on working surface. Have someone
start to build bucks.
4 Place the ICF corner block - line up to chalk line. Can go either way with long
leg of corner.
5 Starting at corner block, place straight ICF blocks and attach tightly together
end to end with Fox Block HV Clips.
6 Work from each corner block toward the center of the wall. Creating a joint at
an opening works well.
7 Decide if you are going to use a butt or lapped joint. (Butt joints do not need to
be cut on a line, lapped joints must be cut straight and on a line.)
8 Once 1st row is complete, install rebar as per plans, code or engineering.
(See sheet 2 on reinforcement)
________________________________________________________________________________
________________________________________________________________________________
1 Saws (pruning and handsaw)
2 Tie wire & Pliers
3 Spray foam adhesive
4 Rebar bender / cutter
5 Chalk and string lines
6 Proper signage
7 Table saw to rip cut block
6110 Abbott Drive | Omaha, NE 68110 | 877-369-2562 | WWW.FOXBLOCKS.COMFox Blocks Installation Checklist: 1ST Edition 5
Phase 5: reinforcement	
1 As rebar is placed, remember that concrete needs access to fill wall.
2 Horizontal rebar should alternate to allow vertical rebar to be held
in place.
3 All lap splices should overlap 40 bar diameters.
(Unless Engineering shows different.)
4 Contact lap splices must be tied. Non contact lap splices do not
need to be tied.
5 Lintel rebar should have 2” concrete cover at bottom.
C - Stirrups as per reinforcing charts or Engineering.
Clever Tip: Reinforcing Steel
Below Grade Walls = Usually Tension Side.
Above Grade Walls = Usually Center of Wall
________________________________________________________________________________
________________________________________________________________________________
Phase 6: row 2
1 Start row 2 at same corner you started row 1 and using the opposite corner
you started with on row 1.
2 Place straight forms from the corner form. Webs should line up automatically.
3 Use Fox Block HV Clips to connect rows 1 and 2 together at 24” o/c and 1st
and 3rd tie from every corner.
4 Once 2nd row is complete, install rebar as per plan, code or engineering.
5 Check top of 2nd course to confirm level footings. Shim and/or trim as needed
to be +/- 1/4”
6
If satisfied, kick wall to the chalk lines and spray foam to footings at 16” o/c
and both sides of wall. (Insert tip of spray foam under form so spray foam fills about
2” of space.)
7
Remember that courses 1,3,5,7 and courses 2,4,6,8
are all the same pattern for stacking. Once you have
the first 2 courses stacked this is your blueprint for
all other courses.
________________________________________________________________________________
________________________________________________________________________________
877-369-2562 | WWW.FOXBLOCKS.COM | 6110 Abbott Drive | Omaha, NE 68110 Fox Blocks Installation Checklist: 1ST Edition6
Phase 7: row 3	
1 Start at same corner as row one and lay forms out along wall.
2 All joints should line up with joints on row one.
3 Use Fox Block HV Clips on 1st and 3rd tie from each corner and in both
directions from corner.
4 If a block is to be cut, it’s size should be the same as row one.
5 Install rebar as per plan, code or engineering.
________________________________________________________________________________
________________________________________________________________________________
Phase 8: row 4
1 Start at same corner as row one and lay forms out along wall.
2 All joints should line up with joints on row two.
3 Use Fox Block HV Clips on 1st and 3rd tie from each corner and in both
directions from corner.
4 If a block is to be cut, it’s size should be the same as row two.
5 Install rebar as per plan, code or engineering.
________________________________________________________________________________
________________________________________________________________________________
________________________________________________________________________________
________________________________________________________________________________
A
A
A
A B
A)	Vertical Fox Block HV Clips to
	 course below
B)	Horizontal Fox Block HV Clips
	 holding corner block to
	 straight block
FOX BLOCK HV CLIP
6110 Abbott Drive | Omaha, NE 68110 | 877-369-2562 | WWW.FOXBLOCKS.COMFox Blocks Installation Checklist: 1ST Edition 7
Phase 9: bracing	
1 When laying out bracing keep in mind how it will safely support scaffold planks.
2 At each corner you should have at least one scaffold, place it on the 4th tie
from the corner. (24”)
3 Space bracing so planks will fit. (9 or 10 webs apart work good for 14’ planks)
4
Attach strong backs using one #10 sheet metal screw, at the top of the
slots, into the tie of each ICF form. Keep screws loose enough to slide in the
slot. Do not use tapping screws. Strong back should line up with cut lines on
form units to ensure they will line up with top row ties.
5
Attach one turnbuckle and scaffold bracket to one strong back and measure
to make sure height will be good for concrete placement. If not, try another
set of holes in the strong back.
6 Install all turnbuckles at same height.
7 Attach turnbuckles to ground slab or floor. (Not less than 45 degrees. Extend
if needed)
8 Install all scaffold brackets at same height to allow planks to line up.
9 Place planking and secure in place.
10 Install guard rails if needed.
11
Plumb all corners and install a string line at top of wall along the out side edge.
Slide a 3/4” spacer block between the string and the form at each corner, and
slide a 3/4” spacer block along wall and adjust the plumb of the wall with the
alignment turnbuckles as you move along the wall from corner to corner.
12 Just before concrete placement it is a good practice to adjust the top of the
wall IN about a 1/4”. Leave the corners plumb.
13 During the concrete placement monitor the string line and if the wall moves
toward the string have someone adjust it back.
14 After the concrete placement, realign the walls using the string, blocks and
turnbuckles.
________________________________________________________________________________
________________________________________________________________________________
________________________________________________________________________________
________________________________________________________________________________
877-369-2562 | WWW.FOXBLOCKS.COM | 6110 Abbott Drive | Omaha, NE 68110 Fox Blocks Installation Checklist: 1ST Edition8
Phase 10: openings	
1 Establish the bottom of buck and mark on forms.
2
If the outside edge of buck lines up on a tie you
should alter web pattern or simply slide the buck
over.
3 Cut the forms to accept the bucks.
4 If needed install vertical rebar into spaces under
the buck locations.
5 Bucks should be built with access points in
bottom to allow for concrete placement.
6 Place the bucks onto position on wall. Buck does
not need to line up with cut lines on forms.
7 Build ICF forms around buck.
________________________________________________________________________________
________________________________________________________________________________
Phase 11: top row
1 Establish where lintel rebar will need to be prior to laying forms in place.
2
If needed place lintel rebar on top of window and door bucks. Remember to
keep the rebar up off the buck to allow the proper amount of concrete to flow
around rebar as required by code.
3 Start at same corner as row one and lay forms out along wall.
4 Use Fox Block HV Clips to hold the forms together horizontally.
5 Use Fox Block HV Clips at 1st and 3rd tie from each corner and in both
directions from corner.
6 Use Fox Block HV Clips on entire row at 2’ o/c. (Second tie back from all joint
lines)
7 Install service penetrations if needed.
8 Insert beam pockets if needed. Hint: 2 layers of ICF foam cut from scrap on site will
give you a 5 1/4” pocket. Then just cut it out after the concrete cures.
9 Install vertical rebar as per plan, code or Engineering.
________________________________________________________________________________
________________________________________________________________________________
6110 Abbott Drive | Omaha, NE 68110 | 877-369-2562 | WWW.FOXBLOCKS.COMFox Blocks Installation Checklist: 1ST Edition 9
Phase 12: Prior to concrete
1
Attach a string line to monitor wall during concrete placement. (A good spot for
the string line is opposite the bracing about 2” down from the top of the wall. See
notes in bracing section)
2 Rebar and lintel steel is complete as per plan.
3 Openings have been braced and framed.
4 Stacked joints (any joints 8” or less apart) have been strapped.
5 Short wall sections (4’ or less) have been strapped.
6 Beam pockets are in place.
7 Sill plate attachment is ready for installation after concrete placement.
8 Space is ready for concrete pump to set up.
________________________________________________________________________________
________________________________________________________________________________
________________________________________________________________________________
________________________________________________________________________________
Phase 13: multiple levels
1 Top of foam has been covered to protect from concrete.
2 Service penetrations have been installed. (Vents, central vac exhaust etc.)
3 Rebar dowels are ready to be installed.
4 When placing concrete remember to leave a portion of the tie exposed. This
will allow you to tie the next row down when you continue building.
5 Embeds Installed and secured
________________________________________________________________________________
________________________________________________________________________________
________________________________________________________________________________
________________________________________________________________________________
877-369-2562 | WWW.FOXBLOCKS.COM | 6110 Abbott Drive | Omaha, NE 68110 Fox Blocks Installation Checklist: 1ST Edition10
Phase 14: concrete	
1
Establish concrete crew and who will be responsible for what.
a. One person to place concrete
b. Two people to consolidate concrete
c. One or two people leveling walls
d. Extra manpower on pour day is not a bad thing!
2 You have to tell the pump operator how many lifts you will be doing and what
slump concrete you want. 2’ to 4’ lifts with a 5” to 6” slump is normal.
3 Start placing concrete at least 2’ from a corner. (Never into a corner as it
could move the wall). Always flow the concrete through the corner.
4
If the concrete gets through the top rebar with just a bit of restriction the
slump is good. If the concrete flows freely past the top rebar the slump could
be to high.
5 Create a lift of concrete on either side of corner before actually filling the cor-
ner. These lifts on either side act as an anchor holding the corner in place.
6
At a window fill from one side and let the concrete flow under the window
buck, then stop the pump, move to the opposite side of the buck, and
continue. Some windows will require extra concrete to be placed into the
opening at bottom of buck.
7 Consolidate concrete during each lift following the person who is
placing concrete.
8 Leave at least 18” to 24” at top of wall for final lift. This will allow concrete
pump to keep up.
9 Monitor walls during and after concrete placement and then adjust
turnbuckles to level walls.
10 If required, install anchor bolts.
11 Ensure all window and door bucks have been consolidated properly by hitting
their face all around with a hammer.
12 Clean concrete off footings, slabs, scaffold, walls, tools etc.
13 Before you leave take one last look to ensure your walls are straight and
plumb.
________________________________________________________________________________
________________________________________________________________________________
________________________________________________________________________________
________________________________________________________________________________
6110 Abbott Drive | Omaha, NE 68110 | 877-369-2562 | WWW.FOXBLOCKS.COMFox Blocks Installation Checklist: 1ST Edition 11
Phase 15: post concrete
1
Bracing should be left in place for 72 hours after concrete placement. If you
must remove bracing, from 24 to 72 hours after concrete placement, it is
recommended that you place temporary bracing against walls prior to
removing ICF bracing.
2 Damp proofing may be required according to building code. (Peel & Stick and/or
dimple membranes have been the most common damp proofing methods for ICF’s.)
3 Prior to backfill you may need to have floor diaphragm in place according to
building code.
________________________________________________________________________________
________________________________________________________________________________
Phase 16: Extreme weather concreting
When building with ICF’s in extreme weather, there are just a few additional precautions that
need to be taken.
1 Keep walls covered to keep snow out of wall cavity. Concrete does not melt
snow.
2
If you get snow into the wall cavity you must remove it prior to concrete
placement. This can be done by cutting temporary holes into the bottom of
forms or drizzling hot water into the forms. Hot water comes on the mixer
trucks in winter.
3 Use 18” wide insulated tarps or equivalent along top of wall.
4
In very cold weather (-0˚ F / -20˚ C) only lift off 8’ of insulation at a time while
placing concrete. This will allow the warmth of the concrete to preheat the wall
and rebar during the pour.
5
When complete cover the wall to protect concrete from cooling. The hydration
process will keep the wall at a good temperature without the need for any extra
hoarding or heating.
6 Remember to cover exposed concrete at bucks.
7 In very hot weather keep exposed concrete covered and apply moisture applied.
________________________________________________________________________________
________________________________________________________________________________
________________________________________________________________________________
6110 Abbott Drive | Omaha, NE 68110 | 877-369-2562 | WWW.FOXBLOCKS.COMFox Blocks Installation Checklist: 1ST Edition
A PRODUCT OF:
Please go to:
www.foxblocks.com
Where you will find:
Regional Manager Contact Information
Local Dealer Contact Information
Downloadable Technical Files
Estimating Software
On-Site Movies
Photos & More
Head Office:
6110 Abbott Drive | Omaha, NE 68110 | 1-877-369-2562
Manufacturing Locations in Alberta, Manitoba, Quebec, Idaho (2), California,
Arizona, Colorado, Nebraska, Massachusetts, North Carolina, Florida

More Related Content

What's hot

Aci reinf details aci 315-99
Aci reinf details aci 315-99Aci reinf details aci 315-99
Aci reinf details aci 315-99
Laquiao Ganagan
 
Rereindetailing
RereindetailingRereindetailing
Rereindetailing
archi2012
 
Durabilty of concrete
Durabilty of concreteDurabilty of concrete
Durabilty of concrete
vairamuni3
 
Design of Steel Frames
Design of Steel FramesDesign of Steel Frames
Design of Steel Frames
Maria João Espada
 
Process of Semiconductor Manufacturing
Process of Semiconductor ManufacturingProcess of Semiconductor Manufacturing
Process of Semiconductor Manufacturing
WAFER WORLD, INC
 
Corrosion control of underwater piles
Corrosion control of underwater pilesCorrosion control of underwater piles
Corrosion control of underwater piles
Aglaia Connect
 
Corrosion of Steel in Concrete
Corrosion of Steel in ConcreteCorrosion of Steel in Concrete
Corrosion of Steel in Concrete
Piyush Verma
 
Civil technical quiz
Civil technical quizCivil technical quiz
Civil technical quiz
premsai05
 
solution for 2D truss1
solution for 2D truss1solution for 2D truss1
solution for 2D truss1
Mohammaderfan Zandieh
 
Hybrid bonding methods for lower temperature 3 d integration 1
Hybrid bonding methods for lower temperature 3 d integration 1Hybrid bonding methods for lower temperature 3 d integration 1
Hybrid bonding methods for lower temperature 3 d integration 1
SUSS MicroTec
 
Repair and rehabilitation of structures
Repair and rehabilitation of structuresRepair and rehabilitation of structures
Repair and rehabilitation of structures
Korrapati Pratyusha
 
control of corrosion of under water piles
control of corrosion of under water pilescontrol of corrosion of under water piles
control of corrosion of under water piles
Aglaia Connect
 
Solidworks engineering design with solid works
Solidworks engineering design with solid worksSolidworks engineering design with solid works
Solidworks engineering design with solid works
محمد ماجيك
 
ALD/CVD applications, equipment and precursors in high volume manufacturing
ALD/CVD applications, equipment and precursors in high volume manufacturingALD/CVD applications, equipment and precursors in high volume manufacturing
ALD/CVD applications, equipment and precursors in high volume manufacturing
Jonas Sundqvist
 
Bearing handbook for electric motor skf
Bearing handbook for electric motor skfBearing handbook for electric motor skf
Bearing handbook for electric motor skf
ducnamtrinh
 
Bs 4483 1985
Bs 4483 1985Bs 4483 1985
Strengthening Of Beams for flexure Using FRP
Strengthening Of Beams  for flexure Using FRPStrengthening Of Beams  for flexure Using FRP
Strengthening Of Beams for flexure Using FRP
Reham fawzy
 
MMUP exam quastions (provided by people who took the exam)
MMUP exam quastions (provided by people who took the exam)MMUP exam quastions (provided by people who took the exam)
MMUP exam quastions (provided by people who took the exam)
Waseem Ahmad
 
Bridge-Plate & Multi-Plate Applications and Case Studies (Randy McDonald, P.E...
Bridge-Plate & Multi-Plate Applications and Case Studies (Randy McDonald, P.E...Bridge-Plate & Multi-Plate Applications and Case Studies (Randy McDonald, P.E...
Bridge-Plate & Multi-Plate Applications and Case Studies (Randy McDonald, P.E...
Communications Branding
 
finfet & dg-fet technology
finfet & dg-fet technologyfinfet & dg-fet technology
finfet & dg-fet technology
Kritika Ramesh
 

What's hot (20)

Aci reinf details aci 315-99
Aci reinf details aci 315-99Aci reinf details aci 315-99
Aci reinf details aci 315-99
 
Rereindetailing
RereindetailingRereindetailing
Rereindetailing
 
Durabilty of concrete
Durabilty of concreteDurabilty of concrete
Durabilty of concrete
 
Design of Steel Frames
Design of Steel FramesDesign of Steel Frames
Design of Steel Frames
 
Process of Semiconductor Manufacturing
Process of Semiconductor ManufacturingProcess of Semiconductor Manufacturing
Process of Semiconductor Manufacturing
 
Corrosion control of underwater piles
Corrosion control of underwater pilesCorrosion control of underwater piles
Corrosion control of underwater piles
 
Corrosion of Steel in Concrete
Corrosion of Steel in ConcreteCorrosion of Steel in Concrete
Corrosion of Steel in Concrete
 
Civil technical quiz
Civil technical quizCivil technical quiz
Civil technical quiz
 
solution for 2D truss1
solution for 2D truss1solution for 2D truss1
solution for 2D truss1
 
Hybrid bonding methods for lower temperature 3 d integration 1
Hybrid bonding methods for lower temperature 3 d integration 1Hybrid bonding methods for lower temperature 3 d integration 1
Hybrid bonding methods for lower temperature 3 d integration 1
 
Repair and rehabilitation of structures
Repair and rehabilitation of structuresRepair and rehabilitation of structures
Repair and rehabilitation of structures
 
control of corrosion of under water piles
control of corrosion of under water pilescontrol of corrosion of under water piles
control of corrosion of under water piles
 
Solidworks engineering design with solid works
Solidworks engineering design with solid worksSolidworks engineering design with solid works
Solidworks engineering design with solid works
 
ALD/CVD applications, equipment and precursors in high volume manufacturing
ALD/CVD applications, equipment and precursors in high volume manufacturingALD/CVD applications, equipment and precursors in high volume manufacturing
ALD/CVD applications, equipment and precursors in high volume manufacturing
 
Bearing handbook for electric motor skf
Bearing handbook for electric motor skfBearing handbook for electric motor skf
Bearing handbook for electric motor skf
 
Bs 4483 1985
Bs 4483 1985Bs 4483 1985
Bs 4483 1985
 
Strengthening Of Beams for flexure Using FRP
Strengthening Of Beams  for flexure Using FRPStrengthening Of Beams  for flexure Using FRP
Strengthening Of Beams for flexure Using FRP
 
MMUP exam quastions (provided by people who took the exam)
MMUP exam quastions (provided by people who took the exam)MMUP exam quastions (provided by people who took the exam)
MMUP exam quastions (provided by people who took the exam)
 
Bridge-Plate & Multi-Plate Applications and Case Studies (Randy McDonald, P.E...
Bridge-Plate & Multi-Plate Applications and Case Studies (Randy McDonald, P.E...Bridge-Plate & Multi-Plate Applications and Case Studies (Randy McDonald, P.E...
Bridge-Plate & Multi-Plate Applications and Case Studies (Randy McDonald, P.E...
 
finfet & dg-fet technology
finfet & dg-fet technologyfinfet & dg-fet technology
finfet & dg-fet technology
 

Similar to Fox Blocks Installation Checklist

newtableconcept user manual
newtableconcept user manualnewtableconcept user manual
newtableconcept user manual
Renzo Lisei
 
Geomembrane Welding Machine
Geomembrane Welding MachineGeomembrane Welding Machine
Geomembrane Welding Machine
JC tool
 
Basic ShoreMaster Kit Dock Instruction
Basic ShoreMaster Kit Dock InstructionBasic ShoreMaster Kit Dock Instruction
Basic ShoreMaster Kit Dock Instruction
Kurt Welch
 
Fabral SSR Metal Roofing Installation Manual
Fabral SSR Metal Roofing Installation ManualFabral SSR Metal Roofing Installation Manual
Fabral SSR Metal Roofing Installation Manual
Western-Building-Center
 
Folding Table - User Manual Rev. 03
Folding Table - User Manual Rev. 03Folding Table - User Manual Rev. 03
Folding Table - User Manual Rev. 03
Renzo Lisei
 
Sluice Gate Installation Guide - Watch Technologies
Sluice Gate Installation Guide - Watch TechnologiesSluice Gate Installation Guide - Watch Technologies
Sluice Gate Installation Guide - Watch Technologies
Watch Technologies
 
Bright_Covers_Installation_Manual
Bright_Covers_Installation_ManualBright_Covers_Installation_Manual
Bright_Covers_Installation_Manual
Nestor J. Molina-Rosado
 
Summer training report
Summer training reportSummer training report
Summer training report
aki8872233
 
Engineering quality version 2014 for construction projects
Engineering quality version 2014 for construction projectsEngineering quality version 2014 for construction projects
Engineering quality version 2014 for construction projects
meetgiannis
 
Deck marking
Deck markingDeck marking
Deck marking
Zulaiha Amaria
 
2058 1
2058 12058 1
2058 1
joaoseravat
 
THE EFFECT OF OPENINGS IN THE SLAB STIFFENED WITH SHALLOW BEAMS
THE EFFECT OF OPENINGS IN THE SLAB STIFFENED WITH SHALLOW BEAMSTHE EFFECT OF OPENINGS IN THE SLAB STIFFENED WITH SHALLOW BEAMS
THE EFFECT OF OPENINGS IN THE SLAB STIFFENED WITH SHALLOW BEAMS
IRJET Journal
 
Dowels
DowelsDowels
FrameWRX Installation Instructions
FrameWRX Installation InstructionsFrameWRX Installation Instructions
FrameWRX Installation Instructions
Installation Manuals - Southwest Solutions Group
 
IRJET- Design and Development of Fixture for Skid Sole of Rotavator
IRJET- Design and Development of Fixture for Skid Sole of RotavatorIRJET- Design and Development of Fixture for Skid Sole of Rotavator
IRJET- Design and Development of Fixture for Skid Sole of Rotavator
IRJET Journal
 
FIT-Slab-EN.pdf
FIT-Slab-EN.pdfFIT-Slab-EN.pdf
FIT-Slab-EN.pdf
mypham_kxd
 
Folding Table Compact - User Manual Rev. 04
Folding Table Compact - User Manual Rev. 04Folding Table Compact - User Manual Rev. 04
Folding Table Compact - User Manual Rev. 04
Renzo Lisei
 
Quad-Lock Insulated Concrete Forms Installation Guide
Quad-Lock Insulated Concrete Forms Installation GuideQuad-Lock Insulated Concrete Forms Installation Guide
Quad-Lock Insulated Concrete Forms Installation Guide
Western-Building-Center
 
Fox Blocks ICF Guidebook
Fox Blocks ICF GuidebookFox Blocks ICF Guidebook
Fox Blocks ICF Guidebook
Western-Building-Center
 
Design and analysis of punching die
Design and analysis of punching dieDesign and analysis of punching die
Design and analysis of punching die
eSAT Journals
 

Similar to Fox Blocks Installation Checklist (20)

newtableconcept user manual
newtableconcept user manualnewtableconcept user manual
newtableconcept user manual
 
Geomembrane Welding Machine
Geomembrane Welding MachineGeomembrane Welding Machine
Geomembrane Welding Machine
 
Basic ShoreMaster Kit Dock Instruction
Basic ShoreMaster Kit Dock InstructionBasic ShoreMaster Kit Dock Instruction
Basic ShoreMaster Kit Dock Instruction
 
Fabral SSR Metal Roofing Installation Manual
Fabral SSR Metal Roofing Installation ManualFabral SSR Metal Roofing Installation Manual
Fabral SSR Metal Roofing Installation Manual
 
Folding Table - User Manual Rev. 03
Folding Table - User Manual Rev. 03Folding Table - User Manual Rev. 03
Folding Table - User Manual Rev. 03
 
Sluice Gate Installation Guide - Watch Technologies
Sluice Gate Installation Guide - Watch TechnologiesSluice Gate Installation Guide - Watch Technologies
Sluice Gate Installation Guide - Watch Technologies
 
Bright_Covers_Installation_Manual
Bright_Covers_Installation_ManualBright_Covers_Installation_Manual
Bright_Covers_Installation_Manual
 
Summer training report
Summer training reportSummer training report
Summer training report
 
Engineering quality version 2014 for construction projects
Engineering quality version 2014 for construction projectsEngineering quality version 2014 for construction projects
Engineering quality version 2014 for construction projects
 
Deck marking
Deck markingDeck marking
Deck marking
 
2058 1
2058 12058 1
2058 1
 
THE EFFECT OF OPENINGS IN THE SLAB STIFFENED WITH SHALLOW BEAMS
THE EFFECT OF OPENINGS IN THE SLAB STIFFENED WITH SHALLOW BEAMSTHE EFFECT OF OPENINGS IN THE SLAB STIFFENED WITH SHALLOW BEAMS
THE EFFECT OF OPENINGS IN THE SLAB STIFFENED WITH SHALLOW BEAMS
 
Dowels
DowelsDowels
Dowels
 
FrameWRX Installation Instructions
FrameWRX Installation InstructionsFrameWRX Installation Instructions
FrameWRX Installation Instructions
 
IRJET- Design and Development of Fixture for Skid Sole of Rotavator
IRJET- Design and Development of Fixture for Skid Sole of RotavatorIRJET- Design and Development of Fixture for Skid Sole of Rotavator
IRJET- Design and Development of Fixture for Skid Sole of Rotavator
 
FIT-Slab-EN.pdf
FIT-Slab-EN.pdfFIT-Slab-EN.pdf
FIT-Slab-EN.pdf
 
Folding Table Compact - User Manual Rev. 04
Folding Table Compact - User Manual Rev. 04Folding Table Compact - User Manual Rev. 04
Folding Table Compact - User Manual Rev. 04
 
Quad-Lock Insulated Concrete Forms Installation Guide
Quad-Lock Insulated Concrete Forms Installation GuideQuad-Lock Insulated Concrete Forms Installation Guide
Quad-Lock Insulated Concrete Forms Installation Guide
 
Fox Blocks ICF Guidebook
Fox Blocks ICF GuidebookFox Blocks ICF Guidebook
Fox Blocks ICF Guidebook
 
Design and analysis of punching die
Design and analysis of punching dieDesign and analysis of punching die
Design and analysis of punching die
 

More from Western-Building-Center

Channellock Ratchet Flyer
Channellock Ratchet FlyerChannellock Ratchet Flyer
Channellock Ratchet Flyer
Western-Building-Center
 
Channellock Tool Book
Channellock Tool BookChannellock Tool Book
Channellock Tool Book
Western-Building-Center
 
Tool Book March - June 2016
Tool Book March - June 2016Tool Book March - June 2016
Tool Book March - June 2016
Western-Building-Center
 
Delta Catalog 2015
Delta Catalog 2015Delta Catalog 2015
Delta Catalog 2015
Western-Building-Center
 
2015 Lighting Catalog
2015 Lighting Catalog2015 Lighting Catalog
2015 Lighting Catalog
Western-Building-Center
 
Home Impressions Catalog 2015
Home Impressions Catalog 2015Home Impressions Catalog 2015
Home Impressions Catalog 2015
Western-Building-Center
 
2015 Ceiling Fan Catalog
2015 Ceiling Fan Catalog2015 Ceiling Fan Catalog
2015 Ceiling Fan Catalog
Western-Building-Center
 
SawStop Job Site Saw Pricelist
SawStop Job Site Saw PricelistSawStop Job Site Saw Pricelist
SawStop Job Site Saw Pricelist
Western-Building-Center
 
SawStop Job Site Saw Flyer
SawStop Job Site Saw FlyerSawStop Job Site Saw Flyer
SawStop Job Site Saw Flyer
Western-Building-Center
 
WBC Barn Special
WBC Barn SpecialWBC Barn Special
WBC Barn Special
Western-Building-Center
 
Medallion Specials 2016
Medallion Specials 2016Medallion Specials 2016
Medallion Specials 2016
Western-Building-Center
 
WBC Monthly Specials February 2016
WBC Monthly Specials February 2016WBC Monthly Specials February 2016
WBC Monthly Specials February 2016
Western-Building-Center
 
40' x 60' x 16' Pole Barn
40' x 60' x 16' Pole Barn40' x 60' x 16' Pole Barn
40' x 60' x 16' Pole Barn
Western-Building-Center
 
30' x 40' x 12' Pole Barn
30' x 40' x 12' Pole Barn30' x 40' x 12' Pole Barn
30' x 40' x 12' Pole Barn
Western-Building-Center
 
24' x 24' x 10' Pole Barn
24' x 24' x 10' Pole Barn24' x 24' x 10' Pole Barn
24' x 24' x 10' Pole Barn
Western-Building-Center
 
Keeping the Dream Alive
Keeping the Dream AliveKeeping the Dream Alive
Keeping the Dream Alive
Western-Building-Center
 
WBC Makita Sale Catalog
WBC Makita Sale CatalogWBC Makita Sale Catalog
WBC Makita Sale Catalog
Western-Building-Center
 
Do it Best Outdoor Living Catalog
Do it Best Outdoor Living CatalogDo it Best Outdoor Living Catalog
Do it Best Outdoor Living Catalog
Western-Building-Center
 
Do it Best Home Decor Catalog
Do it Best Home Decor CatalogDo it Best Home Decor Catalog
Do it Best Home Decor Catalog
Western-Building-Center
 
Fence Brochure
Fence BrochureFence Brochure
Fence Brochure
Western-Building-Center
 

More from Western-Building-Center (20)

Channellock Ratchet Flyer
Channellock Ratchet FlyerChannellock Ratchet Flyer
Channellock Ratchet Flyer
 
Channellock Tool Book
Channellock Tool BookChannellock Tool Book
Channellock Tool Book
 
Tool Book March - June 2016
Tool Book March - June 2016Tool Book March - June 2016
Tool Book March - June 2016
 
Delta Catalog 2015
Delta Catalog 2015Delta Catalog 2015
Delta Catalog 2015
 
2015 Lighting Catalog
2015 Lighting Catalog2015 Lighting Catalog
2015 Lighting Catalog
 
Home Impressions Catalog 2015
Home Impressions Catalog 2015Home Impressions Catalog 2015
Home Impressions Catalog 2015
 
2015 Ceiling Fan Catalog
2015 Ceiling Fan Catalog2015 Ceiling Fan Catalog
2015 Ceiling Fan Catalog
 
SawStop Job Site Saw Pricelist
SawStop Job Site Saw PricelistSawStop Job Site Saw Pricelist
SawStop Job Site Saw Pricelist
 
SawStop Job Site Saw Flyer
SawStop Job Site Saw FlyerSawStop Job Site Saw Flyer
SawStop Job Site Saw Flyer
 
WBC Barn Special
WBC Barn SpecialWBC Barn Special
WBC Barn Special
 
Medallion Specials 2016
Medallion Specials 2016Medallion Specials 2016
Medallion Specials 2016
 
WBC Monthly Specials February 2016
WBC Monthly Specials February 2016WBC Monthly Specials February 2016
WBC Monthly Specials February 2016
 
40' x 60' x 16' Pole Barn
40' x 60' x 16' Pole Barn40' x 60' x 16' Pole Barn
40' x 60' x 16' Pole Barn
 
30' x 40' x 12' Pole Barn
30' x 40' x 12' Pole Barn30' x 40' x 12' Pole Barn
30' x 40' x 12' Pole Barn
 
24' x 24' x 10' Pole Barn
24' x 24' x 10' Pole Barn24' x 24' x 10' Pole Barn
24' x 24' x 10' Pole Barn
 
Keeping the Dream Alive
Keeping the Dream AliveKeeping the Dream Alive
Keeping the Dream Alive
 
WBC Makita Sale Catalog
WBC Makita Sale CatalogWBC Makita Sale Catalog
WBC Makita Sale Catalog
 
Do it Best Outdoor Living Catalog
Do it Best Outdoor Living CatalogDo it Best Outdoor Living Catalog
Do it Best Outdoor Living Catalog
 
Do it Best Home Decor Catalog
Do it Best Home Decor CatalogDo it Best Home Decor Catalog
Do it Best Home Decor Catalog
 
Fence Brochure
Fence BrochureFence Brochure
Fence Brochure
 

Recently uploaded

Supermarket Floral Ad Roundup- Week 22 2024.pdf
Supermarket Floral Ad Roundup- Week 22 2024.pdfSupermarket Floral Ad Roundup- Week 22 2024.pdf
Supermarket Floral Ad Roundup- Week 22 2024.pdf
KarliNelson4
 
Social Media is Eating Retail- The $Trillion Trend You Can't Ignore.pdf
Social Media is Eating Retail- The $Trillion Trend You Can't Ignore.pdfSocial Media is Eating Retail- The $Trillion Trend You Can't Ignore.pdf
Social Media is Eating Retail- The $Trillion Trend You Can't Ignore.pdf
Jasper Colin
 
快速办理(BC毕业证书)波士顿学院毕业证PDF成绩单一模一样
快速办理(BC毕业证书)波士顿学院毕业证PDF成绩单一模一样快速办理(BC毕业证书)波士顿学院毕业证PDF成绩单一模一样
快速办理(BC毕业证书)波士顿学院毕业证PDF成绩单一模一样
aezncfe
 
A Guide to Planting and Caring for Your Land
A Guide to Planting and Caring for Your LandA Guide to Planting and Caring for Your Land
A Guide to Planting and Caring for Your Land
The Green Corner
 
Introducing Bliss Point by Tinuiti Webinar
Introducing Bliss Point by Tinuiti WebinarIntroducing Bliss Point by Tinuiti Webinar
Introducing Bliss Point by Tinuiti Webinar
Tinuiti
 
Supermarket Floral Ad Roundup- Week 23 2024.pdf
Supermarket Floral Ad Roundup- Week 23  2024.pdfSupermarket Floral Ad Roundup- Week 23  2024.pdf
Supermarket Floral Ad Roundup- Week 23 2024.pdf
KarliNelson4
 
The Future of E-commerce: first-hands insights.
The Future of E-commerce: first-hands insights.The Future of E-commerce: first-hands insights.
The Future of E-commerce: first-hands insights.
Solvd, Inc.
 
怎么购买澳洲南十字星大学毕业证文凭毕业证原版一模一样
怎么购买澳洲南十字星大学毕业证文凭毕业证原版一模一样怎么购买澳洲南十字星大学毕业证文凭毕业证原版一模一样
怎么购买澳洲南十字星大学毕业证文凭毕业证原版一模一样
w6zyq7uj
 
原版复制澳洲莫纳什大学毕业证硕士学历原版一模一样
原版复制澳洲莫纳什大学毕业证硕士学历原版一模一样原版复制澳洲莫纳什大学毕业证硕士学历原版一模一样
原版复制澳洲莫纳什大学毕业证硕士学历原版一模一样
w6zyq7uj
 

Recently uploaded (9)

Supermarket Floral Ad Roundup- Week 22 2024.pdf
Supermarket Floral Ad Roundup- Week 22 2024.pdfSupermarket Floral Ad Roundup- Week 22 2024.pdf
Supermarket Floral Ad Roundup- Week 22 2024.pdf
 
Social Media is Eating Retail- The $Trillion Trend You Can't Ignore.pdf
Social Media is Eating Retail- The $Trillion Trend You Can't Ignore.pdfSocial Media is Eating Retail- The $Trillion Trend You Can't Ignore.pdf
Social Media is Eating Retail- The $Trillion Trend You Can't Ignore.pdf
 
快速办理(BC毕业证书)波士顿学院毕业证PDF成绩单一模一样
快速办理(BC毕业证书)波士顿学院毕业证PDF成绩单一模一样快速办理(BC毕业证书)波士顿学院毕业证PDF成绩单一模一样
快速办理(BC毕业证书)波士顿学院毕业证PDF成绩单一模一样
 
A Guide to Planting and Caring for Your Land
A Guide to Planting and Caring for Your LandA Guide to Planting and Caring for Your Land
A Guide to Planting and Caring for Your Land
 
Introducing Bliss Point by Tinuiti Webinar
Introducing Bliss Point by Tinuiti WebinarIntroducing Bliss Point by Tinuiti Webinar
Introducing Bliss Point by Tinuiti Webinar
 
Supermarket Floral Ad Roundup- Week 23 2024.pdf
Supermarket Floral Ad Roundup- Week 23  2024.pdfSupermarket Floral Ad Roundup- Week 23  2024.pdf
Supermarket Floral Ad Roundup- Week 23 2024.pdf
 
The Future of E-commerce: first-hands insights.
The Future of E-commerce: first-hands insights.The Future of E-commerce: first-hands insights.
The Future of E-commerce: first-hands insights.
 
怎么购买澳洲南十字星大学毕业证文凭毕业证原版一模一样
怎么购买澳洲南十字星大学毕业证文凭毕业证原版一模一样怎么购买澳洲南十字星大学毕业证文凭毕业证原版一模一样
怎么购买澳洲南十字星大学毕业证文凭毕业证原版一模一样
 
原版复制澳洲莫纳什大学毕业证硕士学历原版一模一样
原版复制澳洲莫纳什大学毕业证硕士学历原版一模一样原版复制澳洲莫纳什大学毕业证硕士学历原版一模一样
原版复制澳洲莫纳什大学毕业证硕士学历原版一模一样
 

Fox Blocks Installation Checklist

  • 1. 6110 Abbott Drive | Omaha, NE 68110 | 877-369-2562 | WWW.FOXBLOCKS.COMFox Blocks Installation Checklist: 1ST Edition Fox Block installation checklist 1ST Edition
  • 2. 877-369-2562 | WWW.FOXBLOCKS.COM | 6110 Abbott Drive | Omaha, NE 68110 Fox Blocks Installation Checklist: 1ST Edition2 installation CHECKLISTS The Checklists on the following pages are to help remind you of proper sequencing as well as highlight items that could be missed. The lists will help crews continue to build efficiently at times when the lead hand is unavailable. PHASE JOB STatus workbook page 1 Prior to Job Page 3 2 Product Delivery Page 3 3 Start of Job Check List Page 4 4 Row 1 Page 4 5 Reinforcement Page 5 6 Row 2 Page 5 7 Row 3 Page 6 8 Row 4 Page 6 9 Bracing Page 7 10 Openings Page 8 11 Top Row Page 8 12 Prior to Concrete Page 9 13 Multiple Levels Page 9 14 Concrete Page 10 15 Post Concrete Page 11 16 Extreme Weather Concreting Page 11
  • 3. 6110 Abbott Drive | Omaha, NE 68110 | 877-369-2562 | WWW.FOXBLOCKS.COMFox Blocks Installation Checklist: 1ST Edition 3 Phase 1: Prior to Job 1 Blueprint shows rebar schedule or proper rebar design has been established. 2 Rough opening sizes are available for all window and door openings. 3 Wall heights have been pre-planned to determine the number of courses needed. 4 Height of top and/or bottom of openings are clear. 5 Depth of backfill is clear if needed. 6 Thickness of concrete is established. _________________________________________________________________________________ _________________________________________________________________________________ _________________________________________________________________________________ _________________________________________________________________________________ Phase 2: product delivery 1 There is clear access for delivery truck 2 Staging area is established for block. 3 Bracing and rebar will be arriving at or close to the same time as ICF block. 4 Job is squared prior to material being moved in. (Hard to do after) _________________________________________________________________________________ _________________________________________________________________________________ _________________________________________________________________________________ _________________________________________________________________________________ ____________
  • 4. 877-369-2562 | WWW.FOXBLOCKS.COM | 6110 Abbott Drive | Omaha, NE 68110 Fox Blocks Installation Checklist: 1ST Edition4 Phase 3: start of Job items needed to build job: tools including: 1 Rebar and design. 2 Blueprint. 3 Buck material and opening sizes. 4 ICF blocks. 5 Alignment/scaffold system including screws. 6 2 x 10 planks. 7 Anchor bolts or Simpson Hangers 8 Strapping 9 Fox Block HV Clips ________________________________________________________________________________ ________________________________________________________________________________ Phase 4: row 1 1 Footing / Slab is clean level & squared. 2 Chalk lines are complete. (Outside of form is outside of building dimension) 3 Mark out all window and door openings on working surface. Have someone start to build bucks. 4 Place the ICF corner block - line up to chalk line. Can go either way with long leg of corner. 5 Starting at corner block, place straight ICF blocks and attach tightly together end to end with Fox Block HV Clips. 6 Work from each corner block toward the center of the wall. Creating a joint at an opening works well. 7 Decide if you are going to use a butt or lapped joint. (Butt joints do not need to be cut on a line, lapped joints must be cut straight and on a line.) 8 Once 1st row is complete, install rebar as per plans, code or engineering. (See sheet 2 on reinforcement) ________________________________________________________________________________ ________________________________________________________________________________ 1 Saws (pruning and handsaw) 2 Tie wire & Pliers 3 Spray foam adhesive 4 Rebar bender / cutter 5 Chalk and string lines 6 Proper signage 7 Table saw to rip cut block
  • 5. 6110 Abbott Drive | Omaha, NE 68110 | 877-369-2562 | WWW.FOXBLOCKS.COMFox Blocks Installation Checklist: 1ST Edition 5 Phase 5: reinforcement 1 As rebar is placed, remember that concrete needs access to fill wall. 2 Horizontal rebar should alternate to allow vertical rebar to be held in place. 3 All lap splices should overlap 40 bar diameters. (Unless Engineering shows different.) 4 Contact lap splices must be tied. Non contact lap splices do not need to be tied. 5 Lintel rebar should have 2” concrete cover at bottom. C - Stirrups as per reinforcing charts or Engineering. Clever Tip: Reinforcing Steel Below Grade Walls = Usually Tension Side. Above Grade Walls = Usually Center of Wall ________________________________________________________________________________ ________________________________________________________________________________ Phase 6: row 2 1 Start row 2 at same corner you started row 1 and using the opposite corner you started with on row 1. 2 Place straight forms from the corner form. Webs should line up automatically. 3 Use Fox Block HV Clips to connect rows 1 and 2 together at 24” o/c and 1st and 3rd tie from every corner. 4 Once 2nd row is complete, install rebar as per plan, code or engineering. 5 Check top of 2nd course to confirm level footings. Shim and/or trim as needed to be +/- 1/4” 6 If satisfied, kick wall to the chalk lines and spray foam to footings at 16” o/c and both sides of wall. (Insert tip of spray foam under form so spray foam fills about 2” of space.) 7 Remember that courses 1,3,5,7 and courses 2,4,6,8 are all the same pattern for stacking. Once you have the first 2 courses stacked this is your blueprint for all other courses. ________________________________________________________________________________ ________________________________________________________________________________
  • 6. 877-369-2562 | WWW.FOXBLOCKS.COM | 6110 Abbott Drive | Omaha, NE 68110 Fox Blocks Installation Checklist: 1ST Edition6 Phase 7: row 3 1 Start at same corner as row one and lay forms out along wall. 2 All joints should line up with joints on row one. 3 Use Fox Block HV Clips on 1st and 3rd tie from each corner and in both directions from corner. 4 If a block is to be cut, it’s size should be the same as row one. 5 Install rebar as per plan, code or engineering. ________________________________________________________________________________ ________________________________________________________________________________ Phase 8: row 4 1 Start at same corner as row one and lay forms out along wall. 2 All joints should line up with joints on row two. 3 Use Fox Block HV Clips on 1st and 3rd tie from each corner and in both directions from corner. 4 If a block is to be cut, it’s size should be the same as row two. 5 Install rebar as per plan, code or engineering. ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ A A A A B A) Vertical Fox Block HV Clips to course below B) Horizontal Fox Block HV Clips holding corner block to straight block FOX BLOCK HV CLIP
  • 7. 6110 Abbott Drive | Omaha, NE 68110 | 877-369-2562 | WWW.FOXBLOCKS.COMFox Blocks Installation Checklist: 1ST Edition 7 Phase 9: bracing 1 When laying out bracing keep in mind how it will safely support scaffold planks. 2 At each corner you should have at least one scaffold, place it on the 4th tie from the corner. (24”) 3 Space bracing so planks will fit. (9 or 10 webs apart work good for 14’ planks) 4 Attach strong backs using one #10 sheet metal screw, at the top of the slots, into the tie of each ICF form. Keep screws loose enough to slide in the slot. Do not use tapping screws. Strong back should line up with cut lines on form units to ensure they will line up with top row ties. 5 Attach one turnbuckle and scaffold bracket to one strong back and measure to make sure height will be good for concrete placement. If not, try another set of holes in the strong back. 6 Install all turnbuckles at same height. 7 Attach turnbuckles to ground slab or floor. (Not less than 45 degrees. Extend if needed) 8 Install all scaffold brackets at same height to allow planks to line up. 9 Place planking and secure in place. 10 Install guard rails if needed. 11 Plumb all corners and install a string line at top of wall along the out side edge. Slide a 3/4” spacer block between the string and the form at each corner, and slide a 3/4” spacer block along wall and adjust the plumb of the wall with the alignment turnbuckles as you move along the wall from corner to corner. 12 Just before concrete placement it is a good practice to adjust the top of the wall IN about a 1/4”. Leave the corners plumb. 13 During the concrete placement monitor the string line and if the wall moves toward the string have someone adjust it back. 14 After the concrete placement, realign the walls using the string, blocks and turnbuckles. ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________
  • 8. 877-369-2562 | WWW.FOXBLOCKS.COM | 6110 Abbott Drive | Omaha, NE 68110 Fox Blocks Installation Checklist: 1ST Edition8 Phase 10: openings 1 Establish the bottom of buck and mark on forms. 2 If the outside edge of buck lines up on a tie you should alter web pattern or simply slide the buck over. 3 Cut the forms to accept the bucks. 4 If needed install vertical rebar into spaces under the buck locations. 5 Bucks should be built with access points in bottom to allow for concrete placement. 6 Place the bucks onto position on wall. Buck does not need to line up with cut lines on forms. 7 Build ICF forms around buck. ________________________________________________________________________________ ________________________________________________________________________________ Phase 11: top row 1 Establish where lintel rebar will need to be prior to laying forms in place. 2 If needed place lintel rebar on top of window and door bucks. Remember to keep the rebar up off the buck to allow the proper amount of concrete to flow around rebar as required by code. 3 Start at same corner as row one and lay forms out along wall. 4 Use Fox Block HV Clips to hold the forms together horizontally. 5 Use Fox Block HV Clips at 1st and 3rd tie from each corner and in both directions from corner. 6 Use Fox Block HV Clips on entire row at 2’ o/c. (Second tie back from all joint lines) 7 Install service penetrations if needed. 8 Insert beam pockets if needed. Hint: 2 layers of ICF foam cut from scrap on site will give you a 5 1/4” pocket. Then just cut it out after the concrete cures. 9 Install vertical rebar as per plan, code or Engineering. ________________________________________________________________________________ ________________________________________________________________________________
  • 9. 6110 Abbott Drive | Omaha, NE 68110 | 877-369-2562 | WWW.FOXBLOCKS.COMFox Blocks Installation Checklist: 1ST Edition 9 Phase 12: Prior to concrete 1 Attach a string line to monitor wall during concrete placement. (A good spot for the string line is opposite the bracing about 2” down from the top of the wall. See notes in bracing section) 2 Rebar and lintel steel is complete as per plan. 3 Openings have been braced and framed. 4 Stacked joints (any joints 8” or less apart) have been strapped. 5 Short wall sections (4’ or less) have been strapped. 6 Beam pockets are in place. 7 Sill plate attachment is ready for installation after concrete placement. 8 Space is ready for concrete pump to set up. ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ Phase 13: multiple levels 1 Top of foam has been covered to protect from concrete. 2 Service penetrations have been installed. (Vents, central vac exhaust etc.) 3 Rebar dowels are ready to be installed. 4 When placing concrete remember to leave a portion of the tie exposed. This will allow you to tie the next row down when you continue building. 5 Embeds Installed and secured ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________
  • 10. 877-369-2562 | WWW.FOXBLOCKS.COM | 6110 Abbott Drive | Omaha, NE 68110 Fox Blocks Installation Checklist: 1ST Edition10 Phase 14: concrete 1 Establish concrete crew and who will be responsible for what. a. One person to place concrete b. Two people to consolidate concrete c. One or two people leveling walls d. Extra manpower on pour day is not a bad thing! 2 You have to tell the pump operator how many lifts you will be doing and what slump concrete you want. 2’ to 4’ lifts with a 5” to 6” slump is normal. 3 Start placing concrete at least 2’ from a corner. (Never into a corner as it could move the wall). Always flow the concrete through the corner. 4 If the concrete gets through the top rebar with just a bit of restriction the slump is good. If the concrete flows freely past the top rebar the slump could be to high. 5 Create a lift of concrete on either side of corner before actually filling the cor- ner. These lifts on either side act as an anchor holding the corner in place. 6 At a window fill from one side and let the concrete flow under the window buck, then stop the pump, move to the opposite side of the buck, and continue. Some windows will require extra concrete to be placed into the opening at bottom of buck. 7 Consolidate concrete during each lift following the person who is placing concrete. 8 Leave at least 18” to 24” at top of wall for final lift. This will allow concrete pump to keep up. 9 Monitor walls during and after concrete placement and then adjust turnbuckles to level walls. 10 If required, install anchor bolts. 11 Ensure all window and door bucks have been consolidated properly by hitting their face all around with a hammer. 12 Clean concrete off footings, slabs, scaffold, walls, tools etc. 13 Before you leave take one last look to ensure your walls are straight and plumb. ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________
  • 11. 6110 Abbott Drive | Omaha, NE 68110 | 877-369-2562 | WWW.FOXBLOCKS.COMFox Blocks Installation Checklist: 1ST Edition 11 Phase 15: post concrete 1 Bracing should be left in place for 72 hours after concrete placement. If you must remove bracing, from 24 to 72 hours after concrete placement, it is recommended that you place temporary bracing against walls prior to removing ICF bracing. 2 Damp proofing may be required according to building code. (Peel & Stick and/or dimple membranes have been the most common damp proofing methods for ICF’s.) 3 Prior to backfill you may need to have floor diaphragm in place according to building code. ________________________________________________________________________________ ________________________________________________________________________________ Phase 16: Extreme weather concreting When building with ICF’s in extreme weather, there are just a few additional precautions that need to be taken. 1 Keep walls covered to keep snow out of wall cavity. Concrete does not melt snow. 2 If you get snow into the wall cavity you must remove it prior to concrete placement. This can be done by cutting temporary holes into the bottom of forms or drizzling hot water into the forms. Hot water comes on the mixer trucks in winter. 3 Use 18” wide insulated tarps or equivalent along top of wall. 4 In very cold weather (-0˚ F / -20˚ C) only lift off 8’ of insulation at a time while placing concrete. This will allow the warmth of the concrete to preheat the wall and rebar during the pour. 5 When complete cover the wall to protect concrete from cooling. The hydration process will keep the wall at a good temperature without the need for any extra hoarding or heating. 6 Remember to cover exposed concrete at bucks. 7 In very hot weather keep exposed concrete covered and apply moisture applied. ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________
  • 12. 6110 Abbott Drive | Omaha, NE 68110 | 877-369-2562 | WWW.FOXBLOCKS.COMFox Blocks Installation Checklist: 1ST Edition A PRODUCT OF: Please go to: www.foxblocks.com Where you will find: Regional Manager Contact Information Local Dealer Contact Information Downloadable Technical Files Estimating Software On-Site Movies Photos & More Head Office: 6110 Abbott Drive | Omaha, NE 68110 | 1-877-369-2562 Manufacturing Locations in Alberta, Manitoba, Quebec, Idaho (2), California, Arizona, Colorado, Nebraska, Massachusetts, North Carolina, Florida