This project aimed to develop a system to monitor and correct alternating current power factor by switching capacitor banks. The system used a Hampden motor to create an inductive load. A SATEC programmable logic controller measured the power factor and was programmed to energize relays to switch capacitor banks in or out when the power factor dropped below a set point. The goal was to maintain the power factor high enough to avoid utility company charges. Testing showed the motor's power factor could be varied from 0.3 to 0.8 lagging by adjusting its load. The controller and software allowed programming actions to switch capacitors and correct the power factor.
Automatic power factor_improvement_and_monitoring_by_using_plc[1]ferozpatowary
Power factor correction (PFC) is a process of negotiating the unwanted effects of electric loads that create a power factor less than one. Power factor correction may be applied either by an electrical power transmission utility to enhance the efficiency of transmission network. In this paper three transformers of different ratings have been used which acts as inductive load each of which produce different power factor variation. The power factor of the supply line is directly monitored by the Power Meter which is connected in parallel to the supply line. The value of the capacitance (capacitor bank) required for correcting the power factor variation due to each transformer and their combination is found out separately. Capacitor bank for the respective load is triggered by using PLC.
Power factor improvement is the essence of any power sector for realible operations. This report provides literature study of a fixed capacitor thyristor controlled reactor type of power factor compensator by matlab simulation and implementation in programmed microcontroller. To retaining power factor closed to unity under various load condition the arduino ATmega8 microcontroller is used which is programmed by keil software. The simulation is done using proteus software which display power factor according to the variation in load whenever a capacitive load is connected to the transmission line, a shunt reactor is connected which injects lagging reactive VARs to the power system. This report also includes the matlab simulation for three phase power factor improvement by using fixed capacitor thyristor controlled reactor. As a
result the power factor is improved. The results given in this report provides
suitable matlab simulation and proteus simulation based reactor power compensation and power factor improvement and techniques using a FCTCR.
Automatic power factor_improvement_and_monitoring_by_using_plc[1]ferozpatowary
Power factor correction (PFC) is a process of negotiating the unwanted effects of electric loads that create a power factor less than one. Power factor correction may be applied either by an electrical power transmission utility to enhance the efficiency of transmission network. In this paper three transformers of different ratings have been used which acts as inductive load each of which produce different power factor variation. The power factor of the supply line is directly monitored by the Power Meter which is connected in parallel to the supply line. The value of the capacitance (capacitor bank) required for correcting the power factor variation due to each transformer and their combination is found out separately. Capacitor bank for the respective load is triggered by using PLC.
Power factor improvement is the essence of any power sector for realible operations. This report provides literature study of a fixed capacitor thyristor controlled reactor type of power factor compensator by matlab simulation and implementation in programmed microcontroller. To retaining power factor closed to unity under various load condition the arduino ATmega8 microcontroller is used which is programmed by keil software. The simulation is done using proteus software which display power factor according to the variation in load whenever a capacitive load is connected to the transmission line, a shunt reactor is connected which injects lagging reactive VARs to the power system. This report also includes the matlab simulation for three phase power factor improvement by using fixed capacitor thyristor controlled reactor. As a
result the power factor is improved. The results given in this report provides
suitable matlab simulation and proteus simulation based reactor power compensation and power factor improvement and techniques using a FCTCR.
The proposed model automatically corrects the power factor without any human presence. It consist of a micro controller which detects the power factor value,if the power factor goes low during peak hours it automatically connects capacitor banks to improve it. The main aim of the model is to maintain the power factor as high as possible which helps to increase the efficiency of the system.
Automatic Power Factor Improvement by Using PLC & SCADAferozpatowary
Power factor correction (PFC) is a process of negotiating the unwanted effects of electric loads that
create a power factor less than one. Power factor correction may be applied either by an electrical power transmission utility to enhance the efficiency of transmission network. In this paper three transformers of different ratings have been used which acts as inductive load each of which produce different power factor variation. The power factor of the supply line is directly monitored by the Power Meter which is connected in parallel to the supply line. The value of the capacitance (capacitor bank) required for correcting the power factor variation due to each transformer and their
combination is found out separately. Capacitor bank for the respective load is triggered by using PLC, which connects the capacitor bank parallel to the load and thereby bringing the power factor near to unity. This paper represents the most effective automatic power factor improvement and monitoring by using static capacitors which will be controlled by a PLC with very low cost although many existing systems are present which are expensive and difficult to manufacture. In this study, many small rating capacitors are connected in parallel and a reference power factor is set as standard value into the PLC. Suitable number of static capacitors is automatically connected according to the instruction of the PLC to improve the power factor close to unity. Some tricks such as using resistors instead of potential transformer and using one of the most low cost PLC SIEMENS S7-200 CPU215 DC/DC/DC which also reduce programming complexity that make it most economical system than any other controlling system.
Abstract This paper presents different kind of SEPIC converter Topologies. Those are conventional SEPIC converter, multi resonant SEPIC converter and new resonant SEPIC converter. It is a type of dc-dc converters. It can deliver the output voltage that is less than or larger than the input voltage. It is a fourth order dc-dc converter. Basic operating principle of SEPIC converter is ZVS. MOSFET is used as the switch because of low voltage drop. Conventional SEPIC has two bulk inductors. Multi resonant SEPIC converter needs a resonant capacitor and resonant inductor. The bulk inductor reduces the response speed. The new resonant SEPIC converter has small size, excellent transient performance and higher efficiency. Efficient power conversion can be achieved by switched mode RF inverters like class E inverter. The new resonant SEPIC converter is a dc-dc converter with high frequency and efficiency. New resonant SEPIC converter operating at fixed frequency and duty ratio. It reduces the component count and eliminates the need of bulk inductor. The new resonant SEPIC converter is operating at switching frequency of 20 KHz and converter is simulated by using MAT LAB/SIMULINK for 3.6V input supply. Keywords: conventional SEPIC Converter, Multi resonant SEPIC converter, New resonant SEPIC converter, soft switching
Voltage Sag Mitigation in Utility Connected System Using Current Source Conve...IDES Editor
This paper discusses the implementation of current
source converter based distribution type static synchronous
compensator. For eliminating the lower order harmonics, the
power semiconductors are switched by pulse width modulation
technique. Current source converter, input filter, dc link
reactor are combined to design the proposed CSC based
STATCOM. Since the STATCOM is a current injection
device, the performance of the device is improved by a currentsource
converter (CSC) combination. So a controllable current
is generated at the output terminals of the device. Filter circuit
at the input terminal is designed to eliminate the higher order
harmonics. The proposed D- STATCOM is simulated and the
results are validated using MATLAB.
Simulation Analysis of Ac/Dc Adapter Under Zero No-Load Power Consumption usi...IJPEDS-IAES
The burst-mode control is generally used to regulate the output voltage of the ac/dc adapter under light or no-load condition. Although the burst-mode control reduces the switching loss, the control-IC and the feedback circuit at the output side still consume a large amount of power. In order to further reduce the power consumption at no-load condition, a zero no-load power (ZNP) ac/dc adapter for electronic equipment with an embedded battery is proposed in this paper. When the proposed adapter is load connected, the operation is same as that of the conventional adapter. At no-load condition, the adapter is totally turned off. As a result the adapter can reduce the no- load power consumption to less than 1mW. Simulation of a 65 W adapter is presented in order to verify its validity
Abstract This paper deals with the operation of the separately excited dc-drive in each of the four quadrants which is fed by symmetrical multi pulse modulated signal, leads to improved power quality by using single-phase, dual AC-DC buck converter. Here the armature control of the dc drive with constant load torque is considered in both forward and reverse directions in the motoring and generating actions. When a variable load condition occur the load voltage get changed, simultaneously other parameters such as torque, speed at load side and voltage, current profiles at source side get affected. Due to which there is lot of distortion in the sending end parameters. To overcome these drawbacks the essential variables are analyzed by feeding these variables back to the converter switches, which regulates the output voltage, fed to separately excited DC-Drive, which indicates that, at the ac interface the harmonic profile of the separately excited dc drive fed by the improved power quality dual converter is achieved using closed loop system. Keywords: AC-DC Buck Converter, Power Quality, Closed Loop, PI Controller, Symmetrical Multipulse Modulation (SMM) etc.
Highly efficient Active Front End enables trouble free operation of low harmo...Schneider Electric
NEW 3 level Active Front End (AFE) technology from Schneider Electric allows trouble free operation, both for mains supply side and motor side.
This technology allows exceptional low harmonics impact on the main side, which helps to protect other assets while saving energy. It also solves the major issue existing with 2 level AFE which can create premature wear on motors' bearings. By suppressing the common mode voltage, the 3 level AFE technology ensures the motor is running without potential issue, extending the motor’s lifetime and saving maintenance costs.
Micro-controller based Automatic Power Factor Correction System ReportTheory to Practical
This project report represents one of the most effective automatic power factor improvements by using static capacitors which will be controlled by a Microcontroller with very low cost although many existing systems are present which are expensive and difficult to manufacture. In this study, many small rating capacitors are connected in parallel and a reference power factor is set as standard value into the microcontroller IC. Suitable number of static capacitors is automatically connected according to the instruction of the microcontroller to improve the power factor close to unity. Some tricks such as using resistors instead of potential transformer and using one of the most low cost microcontroller IC (ATmega8) which also reduce programming complexity that make it one of the most economical system than any other controlling system.
Jinpat Precise Sip Ring , Fiber Optical Rotary Joint Sarah Wu
keeping improving and innovating, precision slip rings produced by Jinpat have been applied in engineering machinery, security, radar antenna, automation equipment , robot, instrument, medical, aviation, marine equipment, ship and other vessel and military fields.
The proposed model automatically corrects the power factor without any human presence. It consist of a micro controller which detects the power factor value,if the power factor goes low during peak hours it automatically connects capacitor banks to improve it. The main aim of the model is to maintain the power factor as high as possible which helps to increase the efficiency of the system.
Automatic Power Factor Improvement by Using PLC & SCADAferozpatowary
Power factor correction (PFC) is a process of negotiating the unwanted effects of electric loads that
create a power factor less than one. Power factor correction may be applied either by an electrical power transmission utility to enhance the efficiency of transmission network. In this paper three transformers of different ratings have been used which acts as inductive load each of which produce different power factor variation. The power factor of the supply line is directly monitored by the Power Meter which is connected in parallel to the supply line. The value of the capacitance (capacitor bank) required for correcting the power factor variation due to each transformer and their
combination is found out separately. Capacitor bank for the respective load is triggered by using PLC, which connects the capacitor bank parallel to the load and thereby bringing the power factor near to unity. This paper represents the most effective automatic power factor improvement and monitoring by using static capacitors which will be controlled by a PLC with very low cost although many existing systems are present which are expensive and difficult to manufacture. In this study, many small rating capacitors are connected in parallel and a reference power factor is set as standard value into the PLC. Suitable number of static capacitors is automatically connected according to the instruction of the PLC to improve the power factor close to unity. Some tricks such as using resistors instead of potential transformer and using one of the most low cost PLC SIEMENS S7-200 CPU215 DC/DC/DC which also reduce programming complexity that make it most economical system than any other controlling system.
Abstract This paper presents different kind of SEPIC converter Topologies. Those are conventional SEPIC converter, multi resonant SEPIC converter and new resonant SEPIC converter. It is a type of dc-dc converters. It can deliver the output voltage that is less than or larger than the input voltage. It is a fourth order dc-dc converter. Basic operating principle of SEPIC converter is ZVS. MOSFET is used as the switch because of low voltage drop. Conventional SEPIC has two bulk inductors. Multi resonant SEPIC converter needs a resonant capacitor and resonant inductor. The bulk inductor reduces the response speed. The new resonant SEPIC converter has small size, excellent transient performance and higher efficiency. Efficient power conversion can be achieved by switched mode RF inverters like class E inverter. The new resonant SEPIC converter is a dc-dc converter with high frequency and efficiency. New resonant SEPIC converter operating at fixed frequency and duty ratio. It reduces the component count and eliminates the need of bulk inductor. The new resonant SEPIC converter is operating at switching frequency of 20 KHz and converter is simulated by using MAT LAB/SIMULINK for 3.6V input supply. Keywords: conventional SEPIC Converter, Multi resonant SEPIC converter, New resonant SEPIC converter, soft switching
Voltage Sag Mitigation in Utility Connected System Using Current Source Conve...IDES Editor
This paper discusses the implementation of current
source converter based distribution type static synchronous
compensator. For eliminating the lower order harmonics, the
power semiconductors are switched by pulse width modulation
technique. Current source converter, input filter, dc link
reactor are combined to design the proposed CSC based
STATCOM. Since the STATCOM is a current injection
device, the performance of the device is improved by a currentsource
converter (CSC) combination. So a controllable current
is generated at the output terminals of the device. Filter circuit
at the input terminal is designed to eliminate the higher order
harmonics. The proposed D- STATCOM is simulated and the
results are validated using MATLAB.
Simulation Analysis of Ac/Dc Adapter Under Zero No-Load Power Consumption usi...IJPEDS-IAES
The burst-mode control is generally used to regulate the output voltage of the ac/dc adapter under light or no-load condition. Although the burst-mode control reduces the switching loss, the control-IC and the feedback circuit at the output side still consume a large amount of power. In order to further reduce the power consumption at no-load condition, a zero no-load power (ZNP) ac/dc adapter for electronic equipment with an embedded battery is proposed in this paper. When the proposed adapter is load connected, the operation is same as that of the conventional adapter. At no-load condition, the adapter is totally turned off. As a result the adapter can reduce the no- load power consumption to less than 1mW. Simulation of a 65 W adapter is presented in order to verify its validity
Abstract This paper deals with the operation of the separately excited dc-drive in each of the four quadrants which is fed by symmetrical multi pulse modulated signal, leads to improved power quality by using single-phase, dual AC-DC buck converter. Here the armature control of the dc drive with constant load torque is considered in both forward and reverse directions in the motoring and generating actions. When a variable load condition occur the load voltage get changed, simultaneously other parameters such as torque, speed at load side and voltage, current profiles at source side get affected. Due to which there is lot of distortion in the sending end parameters. To overcome these drawbacks the essential variables are analyzed by feeding these variables back to the converter switches, which regulates the output voltage, fed to separately excited DC-Drive, which indicates that, at the ac interface the harmonic profile of the separately excited dc drive fed by the improved power quality dual converter is achieved using closed loop system. Keywords: AC-DC Buck Converter, Power Quality, Closed Loop, PI Controller, Symmetrical Multipulse Modulation (SMM) etc.
Highly efficient Active Front End enables trouble free operation of low harmo...Schneider Electric
NEW 3 level Active Front End (AFE) technology from Schneider Electric allows trouble free operation, both for mains supply side and motor side.
This technology allows exceptional low harmonics impact on the main side, which helps to protect other assets while saving energy. It also solves the major issue existing with 2 level AFE which can create premature wear on motors' bearings. By suppressing the common mode voltage, the 3 level AFE technology ensures the motor is running without potential issue, extending the motor’s lifetime and saving maintenance costs.
Micro-controller based Automatic Power Factor Correction System ReportTheory to Practical
This project report represents one of the most effective automatic power factor improvements by using static capacitors which will be controlled by a Microcontroller with very low cost although many existing systems are present which are expensive and difficult to manufacture. In this study, many small rating capacitors are connected in parallel and a reference power factor is set as standard value into the microcontroller IC. Suitable number of static capacitors is automatically connected according to the instruction of the microcontroller to improve the power factor close to unity. Some tricks such as using resistors instead of potential transformer and using one of the most low cost microcontroller IC (ATmega8) which also reduce programming complexity that make it one of the most economical system than any other controlling system.
Jinpat Precise Sip Ring , Fiber Optical Rotary Joint Sarah Wu
keeping improving and innovating, precision slip rings produced by Jinpat have been applied in engineering machinery, security, radar antenna, automation equipment , robot, instrument, medical, aviation, marine equipment, ship and other vessel and military fields.
Global Validation of the REST2 Solar Model From VaisalaGwendalyn Bender
Vaisala created a global validation of the REST2 clear sky model used for determining solar irradiance for use in solar PV development. This presentation details the process used and the results.
FMI Open Data Interface and Data ModelsRoope Tervo
Description of FMI Open Data Portal services and data models including some WFS basics. The presentation includes also a description of INSPIRE harmonised data models used in the portal.
Probing the atmosphere - new radar & lidar technologies for remote sensing of...CLIC Innovation Ltd
MMEA (The Measurement, Monitoring and Environmental Efficiency Assessment) research program final seminar presentation by Dr. Ari-Matti Harri, Finnish Meteorological Institute
This project is used to develop a fire fighting robot using Android remote. The robotic vehicle is filled with water in tank and pumped through wireless communication.
For more details: http://goo.gl/Nxtc5P
International Journal of Engineering Research and Applications (IJERA) is an open access online peer reviewed international journal that publishes research and review articles in the fields of Computer Science, Neural Networks, Electrical Engineering, Software Engineering, Information Technology, Mechanical Engineering, Chemical Engineering, Plastic Engineering, Food Technology, Textile Engineering, Nano Technology & science, Power Electronics, Electronics & Communication Engineering, Computational mathematics, Image processing, Civil Engineering, Structural Engineering, Environmental Engineering, VLSI Testing & Low Power VLSI Design etc.
The purpose of this paper is to explain power factor and the methods that electric utilities use to impose a charge or “power factor penalty” on the bills of large industrial customers to compensate the utility for the incremental costs associated with providing the increased current, supplying the additional losses, and otherwise covering the costs associated with the effects of poor power factor on the electric system.
Notes of Load Shifting, Motor Drive, Lighting System, Selection of UPS.Amar Preet Singh
In this file, concept of load shifting, selection of motor dive for different types of application, lighting system, and selection of UPS are mentioned.
When discussing energy savings and variable frequency drives (VFD) the attention often focuses on a centrifugal fan or pump application. However, you should not overlook other applications which also have large potential energy savings and energy recovery. Applications involving regeneration, power factor correction, common bus applications or a combination of the three can also quickly achieve a signi cant reduction in energy use.
Arduino-based power factor correction (PFC) involves using an Arduino microcontroller to monitor and improve the power factor of an electrical system. The power factor is the ratio of real power (used to do work) to apparent power (total power within the system), and a lower power factor indicates inefficiencies due to reactive power (caused by inductive or capacitive loads). Improving the power factor can reduce energy costs and increase the efficiency of electrical systems.Setup Sensors: Connect the voltage and current sensors to the Arduino. Ensure that the sensors are correctly calibrated to provide accurate readings.
Zero-Crossing Detection: Write code to detect the zero-crossings of voltage and current signals. This can be done using interrupt service routines (ISRs) in the Arduino.
Calculate Power Factor: Use the time difference between zero-crossings to calculate the phase angle and, consequently, the power factor.
Automatic power factor correction by fine tuning of graded capacitorsIJARIIT
Today’s power system demands improved power factor in order to harness various advantages associated with improved
power factor. Till date, various methods have been deployed to improve the power factor of the power system. This paper mainly
focuses on a novel methodology for reactive power compensation and thereby power factor improvement at the load end. This
paper presents a novel approach of capacitance grading for achieving fine tuning of power factor. The concept for automatic
power factor correction by fine tuning of graded capacitors with the help of microcontroller and binary logic is proposed,
simulated, and implemented. The method presented is of iterative nature and is cost competitive over other deployed methods.
An algorithm is developed and a model is made to deploy the concept of iteration with binary logic. The same is tested on an
induction motor and results obtained are analyzed.
Development of a power factor model for power sysytem loadstheijes
The International Journal of Engineering & Science is aimed at providing a platform for researchers, engineers, scientists, or educators to publish their original research results, to exchange new ideas, to disseminate information in innovative designs, engineering experiences and technological skills. It is also the Journal's objective to promote engineering and technology education. All papers submitted to the Journal will be blind peer-reviewed. Only original articles will be published.
The papers for publication in The International Journal of Engineering& Science are selected through rigorous peer reviews to ensure originality, timeliness, relevance, and readability.
Simulation and Analysis of a D-STATCOM for Load Compensation and Power Facto...IJMER
Power Generation and Transmission is a complex process, requiring the working of many
components of the power system in tandem to maximize the output. One of the main components to form
a major part is the reactive power in the system. It is required to maintain the voltage to deliver the
active power through the lines. Loads like motor loads and other loads require reactive power for their
operation. To improve the performance of ac power systems, we need to manage this reactive power in
an efficient way and this is known as reactive power compensation. In developing countries like India,
where the variation of power frequency and many such other determinants of power quality are
themselves a serious question, it is very vital to take positive steps in this direction.
The work presented here illustrates a method to compensate for the load reactive power using a
DSTATCOM
A DSTATCOM injects a current into the system to provide for the reactive component of the load
current. The validity of proposed method and achievement of desired compensation are confirmed by
the results of the simulation in MATLAB/ Simulink.
IRJET - Power Quality Improvement in Distribution Power System using STATCOM
Final project report
1. Alternating Current Power Factor Monitoring and Correction:
Final Project Report
Bryan Underwood
Advisor: Prof. Gutschlag
May 9, 2012
2. Abstract:
Power factor is the value of a system that reflects how much power is being borrowed from the
power company for the system. Quantitatively, power factor ranges from zero to one and is the cosine
of the difference in the angle between the current and voltage. Many power companies regulate
residential and industrial power factors to make sure that they do not fall below a certain level and
charge the customer more on their utility bills if the power factor falls below a certain level.
Power factor correction serves to correct low power factors by reducing the phase difference between
the current and voltage at the distribution point for a company or residence. The most common way to
correct the power factor is to switch capacitor banks at the source to generate “negative” reactive
power. This project’s goal is to make a system that will switch capacitor banks in and out of the circuit
when the power factor drops below a certain point to avoid power company charges.
4. Introduction:
Power factor is the value of a system that reflects how much power is being borrowed from the power
company for the system. Quantitatively, power factor ranges from zero to one and is the cosine of the
difference in the angle between the current and voltage. Poor power factors are due to inductive loads
such as the induction motors found in air conditioners and refrigerators.
According to Pacific Gas & Electric Company, about 60% of all loads in the United States are electric
motors. This fact in combination with the United States Energy Information Administration (EIA)
statistic of only about 25,000 out of 200,000 manufacturing companies participating in power factor
correction, illustrates a need for companies to implement power factor correction devices to improve
efficiency and reduce energy waste.
One incentive for companies to install power factor correction devices is the charges that many utility
companies impose for falling below a certain power factor. For example, Ameren Illinois requires
customers to install power factor correction devices on their system if the power factor falls below
0.85. If the customer does not install any devices then Ameren can actually come out to the customer’s
property and install devices themselves and charge the customer a hefty rate for doing so.
Pacific Gas & Electric (PG&E) charges 0.6% for each percentage point of power factor below 0.85 on
a utility bill. So if a customer’s utility bill is $10,000 and has an average power factor of 0.83 for the
month, the customer would be charge 1.2% of the total bill more because of that low power factor.
PG&E also provides an incentive to maintain a power factor above 0.85 as well. If a customer has a
power factor above 0.85 the customer receives a credit equal to the process described above instead of
a charge.
There are also a couple of reasons for power companies to be concerned with low power factor. One of
the most important reasons they are concerned is the power losses that occur through their transmission
lines or the “I squared R losses.” This is power that the customer never uses and is not charged for.
This is a problem both for generating and distribution companies as a distribution company might be
charged for running at a low power factor in their system by a generating company. These charges
incurred are also important for keeping power companies’ rates low to remain competitive.
With several power companies offering incentives and most power companies charging some type of
fee for falling below their specified power factor, some may wonder why companies do not actively
pursue to improve their power factor. This can be due to several factors. One is that the companies’
administrators do not think the company will be able to recover costs from installing power factor
correction devices. Another is that some companies might not have enough inductive loads to be
concerned about power factor at all.
Power factor correction acts to improve poor power factors by keeping a customer’s power factor
above the level specified by the power company. The most common method of controlling power is by
the use of switching capacitor banks and was the method implemented in this project. Capacitor banks
generate “negative” reactive power or absorb the reactive power produced by inductive loads.
However, it is possible to add too much capacitance to the system and still incur power company
charges. This occurs when the amount of capacitance added is so much greater than the inductance of
the system that the power factor goes below 0.85 leading. The goal of this project was to obtain a
power factor as close to one as possible or to control the system power factor within a range that will
avoid any power company charges possible.
5. System Description:
Figure 4-1, System Diagram
A 120 [VAC] source was used to power an inductive load as seen in Figure 4-1 above, since the
load power factor can be easily changed by adjusting the inductance of the load. The load used in this
project was a three phase Hampden 1.4[A] 1/3 [HP] motor with attached pony brake to easily vary the
power factor of the motor. Capacitor banks were used in parallel with the motor to improve the power
factor due to the inductive load. The SATEC programmable power meter shown in Figure 2-1 was
used to measure the power factor, current, voltage, and the active, reactive, and apparent power. The
meter was also used to energize the relays that switched the capacitors in and out of the system. The
software program, Power Analysis Software, used with the power meter allowed to specify a set point
that when set to true, switched on a relay when the power factor dropped below a certain point.
6. Equipment List:
Hampden Type WRM-100 Three Phase Motor
Figure 6-1, Hampden Motor with Attached Load
Motor is rated at 1.4 [A] 220 [VAC] 1725 RPM 1/3 [HP]. Shown in Figure 6-1, attached is a pony
brake load that allows varying the power factor of the motor. The top of the pony brake is cut off, but
the load is varied by a knob that is twisted. A force meter is also attached so that efficiency can be
measured by calculating the torque of the motor at various loads. A tachometer was also used to
measure the RPM output of the motor. The torque was then multiplied by the output speed in radians
per second gave the output power of the motor. This output power was divided by input power, which
was obtained from meter readings, and multiplied by one hundred to obtain efficiency. A graph of
these results was prepared and compared against power factor and is shown on the next page.
7. Motor Power Factor and Efficiency:
Figure 7-1, Motor Power Factor vs Efficiency
As can be seen from Figure 7-1 the motor’s power factor is variable from about 0.3 to about 0.8
lagging. This provides a wide range in which to test different values of capacitance to switch in and
out of the system. The power factor also generally increases with motor efficiciency until an output
power of about 150 W. At this point the efficiency of the motor begins to level off at about fifty five
percent while the power factor continues to rise to its maximum value of about 0.8 lagging.
SATEC PM172E-N Three Phase Programmable Logic Controller
Figure 7-2, SATEC Programmable Logic Controller
8. The SATEC programmable logic controller was used as the meter for this project along with the energy
source used to energize the relays used for switching. The data values taken from the meter for this
project are the line to nuetral voltages, active power, power factor, apparent power, reactive power, line
currents, and the individual line powers and power factors. The controller is programmed either by the
buttons provided on the front of the meter or through SATEC’s free software program, Power Analysis
Software (PAS). This software allows the user to program set points that perform a certain action
when one or multiple conditions are set. One such action that can be taken is to energize or release
realys based on what the power factor of the system is. The software also provides several charts and
graphs that either stored data or real time data from the controller. A tutorial of the main functions of
the controller is provided at the end of this report.
Alternative Controllers:
It should be noted that there are other programmable logic controllers available and a lot of them have
more than two relay inputs and outputs. These alternative controllers also may have more
programming options, such as the ability to set an action when the power factor goes above a certain
point instead of only below as is the case for the controller used for this project. Two of the main
companies that make these other controllers are Schweitzer Engineering Laboratories and General
Electric Company. For this project, this controller was graciously loaned from Ameren Corporation so
it was the controller that was used.
The two controllers shown in Figure 8-1 and Figure 8-2 are two examples of alternative controllers that
can be used. The controller shown in Figure 8-1 is a Schweitzer Engineering Laboratory 734B Logic
Controller. The controller shown in Figure 8-2 is a General Electric PM35 Logic Controller.
Figure 8-1, SEL PLC Figure 8-2, GE PLC
9. Potter & Brumfield KRPA-11AG-120 Power Relays
Figure 9-1 shows the relays that were used to switch the capacitor banks in and out of the circuit.
These relays were controlled by the SATEC PLC and were also generously donated by Ameren
Corporation. Figure 9-2 is a side view of the relays.
Figure 9-1, Top View of Relay Figure 9-2, Side View of Relay
Capacitor Banks
These were the capacitor banks used in this project. There are two values of steps that could be used
with the range of capacitance per step that was able to be switched into the system was 1.6uF to 50uF.
Figure 9-3 shows a maximum value of 50uF capacitor bank with switches that enable different values
of capacitance to be configured. Figure 9-4 switches in the same way, but contains only a maximum
capacitance of 40uF.
Figure 9-3, 50uF Capacitor Bank Figure 9-4, 40uF Capacitor Bank
10. Damping Resistors:
Damping resistors are placed in series with the capacitors that are being switched into the system to
limit the inrush current that occurs. Figure 10-1 shows a resistor valued at 25 ohms. This inrush
current occurs because when a capacitor is switched on initially it looks like a short circuit and draws
very large currents for a short amount of time. Normally in a power factor correction system these
resistors are only placed in series with the capacitors for a very short amount of time to limit these
inrush currents and avoid excessive power losses due to the resistors. After this short amount of time,
the resistors are switched out of the circuit and the capacitors remain in parallel with the load. Due to
the limited about of relay outputs available on the controller used for this project, the damping resistors
were kept in series with the capacitors and losses were calculated.
Current through 10uF Capacitor
Power Losses
Current through 20uF Capacitor
Power Losses
Current through 30uF Capacitor
Power Losses
Figure 10-1, Damping Resistor 25 ohms
][6159.84450395.0
6159.84433.266
0120
AI °∠=
°−∠
°∠
=
][07139.525*)450395.0( 22
WRIP ===
][3252.79889119.0
3252.79965.134
0120
AI °∠=
°−∠
°∠
=
][7633.19 WP =
][2121.7430597.1
2121.748857.91
0120
AI °∠=
°−∠
°∠
=
][639.42 WP =
11. Software:
The software used in this project is the Power Analysis Software available directly from SATEC’s
website. There is no code involved with programming the meter so there is no specific programming
language. Rather, several graphical user interfaces (GUI) are provided to program the meter. One
example is shown in Figure 11-1 below.
Figure 7-1, Software Set Point
This is the menu provided to program set points to the meter. With set points, the user can specify
certain conditions that need to occur for one or several actions to occur. In the figure above, the set
point becomes true and relay one is operated when the current in line A is above 0.1 Amps and the
power factor of the system is below 0.85 lagging. In addition to the relay being operated, the controller
records this event in the event log contained within the controller that is viewable by the program. This
set point can be described by the flow chart in Figure 11-2 and also is the process at which the system
in this project operates.
Flow Chart:
Figure 7-2, Software Flow Chart
12. Beginning at the top of Figure 7-2 once the controller powers up, it checks to see whether a load is
present by checking whether there is any line current in the system and if no current is present, any
relays that are on are turned off and this check is repeated. If there is current then the meter checks to
see if the system is running at a power factor below 0.85 lagging and if it is the relays are energized and
the capacitor banks are switched into the system. The check for line current and a lagging power factor
continue until the meter is powered down.
Results:
To determine what value of capacitance needed to be switched into the system, a theoretical model of
the motor was made. The magnitude of impedance of the motor was found by dividing the voltage by
the current of a single line of the motor. The phase angle of the impedance was found by taking the
inverse cosign of the power factor of the motor. The impedance of the motor was recorded at four
different power factors, 0.3, 0.45, 0.6, and 0.78 lagging. Five different values of capacitances were
each added with each of the different power factors. Once the model of the motor was developed, the
damping resistor and capacitor bank were added in parallel and the equivalent impedance was found.
This allowed a calculation of the phase angle of the total impedance and the cosign of this angle was
taken to obtain a source power factor. A table, Figure 12-1, and a graph, Figure 12-2, are shown below.
Any value above one should be subtracted from two and taken as a leading power factor.
0.3 0.45 0.6 0.78
10uF 0.609445 0.74704 0.855108 0.933201
15uF 0.873233 0.928109 0.964573 0.983411
20uF 0.999937 0.999926 1.00002 0.999972
30uF 1.13754 1.09493 1.06663 1.03199
40uF 1.21777 1.17129 1.13211 1.07689
Figure 12-1, Theoretical Values
Figure 12-2, Theoretical Graph
13. As can be seen from Figure 12-2, it is desired to use 20uF of capacitance per phase to increase power
factor to near unity and avoid any power company charges. Data was taken at the different values of
capacitance from the controller to confirm that 20uF was the ideal capacitane for this project. A
comparison of experimental and theoretical results is shown below. Again, any value over one
represents a leading power factor and should be subtracted from two to find the value of that power
factor.
Figure 13-1, Theoretical and Experimental Values
Figure 13-2, Theoretical and Experimental Values
0.3 0.45 0.6 0.78
10uF Meter 0.5815 0.704 0.85 0.93
15uF Meter 0.845 0.906 0.944 0.972
20uF Meter 0.992 0.997 0.999 0.999
30uF Meter 1.097 1.076 1.049 1.02
40uF Meter 1.196 1.154 1.1 1.074
10uF 0.609445 0.74704 0.855108 0.933201
15uF 0.873233 0.928109 0.964573 0.983411
20uF 0.999937 0.999926 1.00002 0.999972
30uF 1.13754 1.09493 1.06663 1.03199
40uF 1.21777 1.17129 1.13211 1.07689
14. A final picture of the system is shown in Figure 14-1. The motor seen on the right has the attached
pony brake and is currently running. This is shown by the controller in between the two capacitor
banks. The controller is currently measuring the apparent power, power factor, and active power.
Behind the controller is the fused power source, with several neutral points being used and a ground.
The damping resistors are right in front of the capacitor banks, but connected in series with them.
Finally, Power Analysis Software can be seen on the computer displaying real time values of the
system including individual active powers, line voltages, and individual line power factors.
Figure 14-1, Picture of Current System
15. Satec PM172-N Programmable Logic Controller and Power Analysis Software Tutorial:
Powering Controller and Communicating with Computer:
To power up the meter, a 120 [VAC] source is needed along with a ground and neutral connection.
These are connected to ports 10, 12 and ground as demonstrated in Figure 9-1 below.
Figure 9-1, Terminal Connections
When connecting the controller to line voltage and current there are several different wiring modes
available and depending on which are available the controller will need to be told which ones to use.
16. These settings can be set in the meter or the software program. One such configuration and the one
used in this project can be seen in Figure 10-1.
Figure 10-1, 4LL3 or 4Ln3 Wiring Configuration
Note in the above diagram that current transformers are used. The controller can be told what ratio of
potential and current transformers are used if not directly connecting the controller to line power.
The controller is able to be programmed from the front to do and see anything that would be set or seen
in the software program. As there are easily over two hundred settings and measurements that can be
viewed, this tutorial will only cover the settings used in this project and will only cover which method
was used to configure these settings. The rest can be found in the manual downloaded from the
SATEC website.
The most common way to connect the controller to a computer to view data or configure settings is
through a serial port connection, although an adapter can be bought to communicate over ethernet or
dial up. This serial port connection also needs to use a null modem cord and not a straight modem
cord, otherwise the controller will not respond to computer commands.
When using the Power Analysis Software, the user can create multiple databases corresponding to each
controller connected. For this project since only one controller was used, there was no need to create
multiple databases and remained with the default database.
To set up communications with the controller press Configuration from the Tools menu at the top and
select the site database to be used along with the model number of the controller, which for this project
was PM172-N.
17. The Device Address, Device ID, and Sampling Rate settings in the software need to match the settings
contained in the controller. To check the settings in the controller, press select and three options should
appear as Sta, Ops, and Chg as seen in Figure 11-1.
To move through these menus on the controller use the select button, while
pressing enter will enter that menu. To check the status of a setting the Sta
menu will be used, while changing a setting will require the Chg menu. Now
scroll through the menu that should appear like Figure 11-2.
Figure 11-1, Select Menu
Press the UP or DOWN button to scroll through these options with the top menu
highlighted until Prt.1 is blinking and press enter. Then use the up and down arrows
to scroll the different settings available for communications and make sure these
correspond to the settings in the software. This process is shown in Figure 11-3.
Figure 11-2, Status Menus
Figure 11-3, Diagram Showing Route to Communication Settings
Once all of the communication settings for the controller have been set, communications can be tested
by powering up the controller and setting the software to go “on-line.” This is a state in which the
software can communicate with the controller to read or send settings and read data. The button that
takes the controller on-line is to the right of the drop down menu where the database being used in
located. When pressed, communications are tested by trying to communicate with the controller in
anyway. The most common method used is selected the plus sign next to the database name in the tree
located in the right panel of the program.
Configuring Basic Device Setup:
The basic device settings need to be setup for the controller in order for data to be correctly read.
These settings can be accessed in two ways; the first is to select General Setup under the MeterSetup
menu at the top next to the Logs menu. The other way is to select the plus sign next to your database
name in the right panel and then the plus sign next to General Setup and finally double click Basic
Setup. This will bring up a window that contains the basic configuration settings on the meter starting
with wiring mode. For this project, the only setting that needed to be confirmed was the wiring mode,
PT ratio and multiplier, and the nominal frequency. Notice, that all the tabs at the top of this window
correspond to the options under General Setup, therefore all options can be accessed by clicking the
tabs at the top of the window. In the panel at the right the Memory/Log, Energy/TOU Setup,
Communication Setup, and Protocol Setup were not used in this project.
18. Viewing Data:
When the controller is initially power on, the line to neutral voltages are displayed which is shown by
the L present in the bottom left corner. To scroll through the measurements, the up and downs arrows
are used and if the down arrow is pressed the line to line voltages are displayed which is shown by a P.
The next set of measurements will be the line currents and the next measurements are the apparent
power, power factor, and real power respectively. The last set of menus displays the neutral line
current, frequency, and the reactive power.
These values can also be viewed in the software along with many other data. To view real time values
in chart or graph form, go to the monitor menu at the top and scroll over RT data monitor. This will list
all the available chart or graph types that can be read. The ones used in the project are the Data Set 1
Real Time Measurements and Data Set 2 Average Measurements. Initially, the chart form of data is
shown, but graph form can be displayed by pressing the first top left button that is called data trend
when hovered over. When in chart form, the data displayed can be changed for any data set by
pressing the fifth button from the left that when hovered over is called data set. For changing data
values displayed in the graph, the fifth button from the left is pressed.
An event log that displays user defined events, when set points are set, and when the controller is
powered up or down. This event log can be found by selecting the event log under the logs menu at the
top. This event log is very useful for viewing when a set point has been activated or released and when
the set points were sent to the controller.
Programming Set Points:
The set point menus can be accessed from the same window that was used to access the Basic Setup
Menu. Click the Control/Alarm Setpoints tab and there should be a drop down menu where the set
point number is chosen, a triggers box where logic operators, trigger parameters, and operate and
release limits are set, an actions box where actions to take when the set point becomes true, and a box
for operate and release delays.
For this project the three important trigger parameters that were used are the LO PF LAG AVR, LO PF
LEAD AVR, and HI I1 AVR. The operate parameter for a lagging power factor was set at 0.85 while
the release limit was at 1.0. This was anded with the current parameter to ensure the relays only switch
when line current is present. The set point became true when the power factor at the source fell below
0.85 lagging and line current is present. The actions taken were OPERATE RELAY #1 and EVENT
LOG. The operate relay action sent a signal out of the relay output #1 from the controller and the event
log action logged that the set point was evaluated to be true.
To send the current configuration to the controller there is a send button in the bottom left of the
window. Configurations can be saved and loaded into the databases mention earlier by pressing the
save as button and selecting the database pertinent to the controller being programmed.