SlideShare a Scribd company logo
A
Comprehensive Project Report
ON
“FEASIBILITY OF MAINTENANCE AGENCY IN
BARODA”
Submitted to
Anand Institute of Management, Anand
Under The Guidance Of
SNEHAL BHATT
Assistant Professor, AIM
In partial Fulfilment of the Requirement of the award of the degree of
Master of Business Administration
Offered by
Gujarat Technological University, Ahmadabad
Prepared By
UTKARSH AMARAVAT
(127020592003)
MBA SEMESTER IV
May, 2014
i
Declaration
I, UTKARSH AMARAVAT hereby declare that the report on entitled
“Feasibility of Maintenance Agency in Baroda” is a result of my own work and
my indebtedness to other work Publications, if any, have been duly
acknowledgment.
Place: - Anand, Gujarat, India
Date: - 6th
May, 2014
Utkarsh Amaravat
ii
Preface
As undergoing the course of Masters of Business Administration in Gujarat
Technological University, This comprehensive project report has been
prepared in partial fulfilment of the requirement of academic where one can
get opportunity to meet the real working people of different industries and to
learn practical aspect of management.
Before finishing MBA and going in practical world, it is necessary to learn how
actually Company do any feasibility study for new project. I take Marketing as
specialization in MBA and to do marketing it’s necessary to find product or
service feasibility in market. It was a complete learning and research process
throughout this project. I had a very memorable and worthy experience.
The rationale behind doing the project work is to study, analyze and find
feasibility of blue ocean maintenance agency idea in real world.
iii
Acknowledgement
It was indeed an opportunity for me to prepare a feasibility study project
report. during M.B.A. programme. My heartful thanks to Mr. Snehal Bhatt, my
project guide and Mr. Akash Shah and Miss. Suchi Patel who helped me to
bring out this project in good manner with them precise suggestion and rich
experience. I gratefully acknowledge my sincere thanks to my friends
Specifically Mr. Bharat Gohil who help me in this project when needed.
I am extremely thankful to all companies who participate as respondent in this
research; and Makarpura, Pore, Ranoli, Salvi, Nandesari and Vagodia GIDC
offices to provide helpful guidance and materials.
iv
LIST OF TABLES
Table No. Table Description Page No.
1.1 Maintenance Agency Fixed Cost or Initial Investment 13
1.2 Maintenance Agency Variable Cost per month 14
2.1 Content Analysis 23
5.1 Demographic Profile 39
5.2 Machinery basic Data 40
5.3 Type of Machinery 41
5.4 Operational Machinery Usage 42
5.5 No. of Operational Machinery 44
5.6 Average age of Operational Machinery 46
5.7 Conveying Machinery Usage 48
5.8 No. of Conveying Machinery 49
5.9 Average age of Conveying Machinery 50
5.10 Power supply Machinery Usage 51
5.11 No. of Power supply Machinery 52
5.12 Average age of Power supply Machinery 53
5.13 Different Manufacturer machinery usage 54
5.14 Maintenance Department Inquiry 55
5.15 Maintenance Department Ability 56
5.16 Maintenance Department Man power 57
5.17 Awareness of other Maintenance agency 58
5.18 Other Maintenance agency AMC 59
5.19 Machinery warranty period Inquiry 60
5.20 Likert Scale: Statement 1 61
5.21 Likert Scale: Statement 2 62
5.22 Likert Scale: Statement 3 63
5.23 Likert Scale: Statement 4 64
5.24 Likert Scale: Statement 5 65
5.25 Likert Scale: Statement 6 66
5.26 Likert Scale: Statement 7 67
v
5.27 Likert Scale: Statement 8 68
5.28 Likert Scale: Statement 9 69
5.29 Likert Scale: Statement 10 70
5.30 Likert Scale: Statement 11 71
5.31 Likert Scale: Statement 12 72
5.32 Likert Scale: Statement 13 73
5.33 Likert Scale: Statement 14 74
5.34 Likert Scale: Statement 15 75
5.35 Likert Scale: Statement 16 76
5.36 Likert Scale: Statement 17 77
5.37 Purchase Maintenance agency services in Future 78
6.1 Hypothesis 1 79
6.2 Hypothesis 2 80
6.3 Hypothesis 3 81
6.4 Hypothesis 4 82
6.5 Hypothesis 5 84
6.6 Hypothesis 6 85
6.7 Hypothesis 7 86
6.8 Hypothesis 8 87
7.1 Fixed Investment Cost requirement for next 3 Years 88
7.2 Variable Cost requirement for next 3 Years 89
7.3 Future customer analysis 91
7.4 Estimated Cash inflow 93
7.5 Estimated P/L Accounts 93
7.6 Payback Period 95
7.7 PV of Cash Inflow 95
7.8 PV of Cash Outflow 96
vi
LIST OF FIGURES
Figure No. Figure Description Page No.
1.1 Flow Diagram of Breakdown Maintenance 2
1.2 Preventive Maintenance Process Flow 3
1.3 Comparison of Breakdown, Predictive and Routine
Maintenance
4
5.1 Machinery basic Data 40
5.2 Type of Machinery 41
5.3 Operational Machinery Usage 43
5.4 No. of Operational Machinery 45
5.5 Average age of Operational Machinery 47
5.6 Conveying Machinery Usage 48
5.7 No. of Conveying Machinery 49
5.8 Average age of Conveying Machinery 50
5.9 Power supply Machinery Usage 51
5.10 No. of Power supply Machinery 52
5.11 Average age of Power supply Machinery 53
5.12 Different Manufacturer machinery usage 54
5.13 Maintenance Department Inquiry 55
5.14 Maintenance Department Ability 56
5.15 Maintenance Department Man power 57
5.16 Awareness of other Maintenance agency 58
5.17 Other Maintenance agency AMC 59
5.18 Machinery warranty period Inquiry 60
5.19 Likert Scale: Statement 1 61
5.20 Likert Scale: Statement 2 62
5.21 Likert Scale: Statement 3 63
5.22 Likert Scale: Statement 4 64
5.23 Likert Scale: Statement 5 65
5.24 Likert Scale: Statement 6 66
5.25 Likert Scale: Statement 7 67
vii
5.26 Likert Scale: Statement 8 68
5.27 Likert Scale: Statement 9 69
5.28 Likert Scale: Statement 10 70
5.29 Likert Scale: Statement 11 71
5.30 Likert Scale: Statement 12 72
5.31 Likert Scale: Statement 13 73
5.32 Likert Scale: Statement 14 74
5.33 Likert Scale: Statement 15 75
5.34 Likert Scale: Statement 16 76
5.35 Likert Scale: Statement 17 77
5.36 Purchase Maintenance agency services in Future 78
6.1 Hypothesis 1 79
6.2 Hypothesis 4 83
6.3 Hypothesis 5 83
6.4 Hypothesis 8 87
7.1 Estimated PAT 94
viii
TABLE OF CONTENTS
Page No.
Declaration i
Preface ii
Acknowledgement iii
List of Tables iv
List of Figures vi
Table of Contents viii
1 About Industry
1.1 Maintenance 1
1.2 Maintenance Agency 6
1.3 Maintenance Agency Service Mix 9
1.4 Maintenance Agency Cost 13
2 Secondary Data Analysis
2.1 Literature Review 15
2.2 Content Analysis 23
2.3 Research Gap 34
3 Signification of Study 35
4 Research Methodology
4.1 Research Statement 36
4.2 Objective of Study 36
4.3 Research Hypothesis 36
4.4 Research Design 38
4.5 Sampling Method 38
4.6 Data Collection Instruments 38
4.7 Sampling Unit 38
4.8 Sample Size 38
ix
5 Data Analysis
5.1 Demographic Profile 39
5.2 Response Rate 39
5.3 Questionnaire Analysis 40
6 Hypothesis Testing 79
7 Maintenance agency Profitability and Feasibility Analysis
7.1 Cost of Project 88
7.2 Means of Financing 90
7.3 Estimated Cash Flow for next 3 years 91
7.4 Estimated Profit and Loss Accounts 93
7.5 Feasibility Analysis 95
8 Finding 97
9 Conclusion 98
Annexure I x
Bibliography xiv
Chapter 1
About Industry
1
1.1. Maintenance
The old concept of Maintenance was “Maintenance is about preserving
physical asset”. However, the new concept is that “Maintenance is about
preserving the functions of assets”. Maintenance can be define as “It is a
routine or a recurring process of keeping a particular machine or asset in its
normal operating condition, so that it can deliver its expected performance or
service without causing any loss of time on account of accidental damage or
breakdown.”
Main function is to keep the equipment in working condition by replacing or
repairing some of the component of the machine and increased availability of
production system, with increased safety and optimized cost.
1.1.1. Maintenance Concepts
Actually, Maintenance is an age old function, which developed and
progressed, knowingly or unknowingly, along with the operation of the
equipment/ machines. In early ages, maintenance was not a separate identity
but the job of maintenance was considered as part and parcel of operator’s
job. This was possible because of simplicity and openness of the machines.
Here some concepts of Maintenance given as per there generation which are
followed by Industries:
1. Breakdown Maintenance Concept (Before 1950)
Breakdown Maintenance concept/system is oldest concept in Maintenance
management. In this not do anything as long as everything is going well and
maintenance repair is done after failure has already occurred. The equipment
allowed running undisturbed till it fails. This maintenance concept also called
as Reactive Maintenance Concept or Unplanned Maintenance or Operate to
failure concept.
Breakdown maintenance can only be suitable for small scale industries where
numbers of equipments are few and sudden failure of equipment will not
2
cause several financial losses in term of delivery commitment. This system
look to be simple and less expensive, but is not really so. It does not provide
any guarantee of reliability to the smooth production running. In breakdown
maintenance downtime of equipment is high after breakdown.
Fig. 1.1 Flow Diagram of Breakdown Maintenance
2. Preventive Maintenance Concept (Between 1950 to 1960)
Some group of Japanese engineers started a new concept/system in
maintenance that consisted on following the manufactures recommendation
about the care that should be taken in the operation and maintenance of
machine and devices. That new concept was called Preventive Maintenance
or Schedule Maintenance Concept. This Maintenance program is scheduled
in consultation with the production/operation department so that relevant
equipment is made available for maintenance work and utilizes idle time of
equipment. In this maintenance action such as inspection, lubrication,
cleaning, adjustment and replacement are undertaken at fixed interval of
number of hours or kilometres. Although it reduces downtime it was an
expensive alternative. The reason many parts were replaced on a time basis,
while they could have lasted longer. Also many unnecessary man-hours were
put into it and in not few cases excess lubrication caused more damage than
good.
3
Fig. 1.2 Preventive Maintenance Process Flow
3. Predictive Maintenance Concept (Between 1960 to 1970)
With time change new concept/system established which determined a more
professional approach. This assign of higher responsibility to all the people
related to maintenance consisted of series of considerations about the
reliability and design of equipment and plant itself. When equipment/system is
taken down for maintenance, changing one or few warn out component
opportunity can be utilized for maintenance, changing other wearing out
component even though they have not failed. This would probably be
economical in the long run. It is very beneficial for non-monitored component
which are inaccessible for inspection. This maintenance concept also called
as Productive Maintenance Concept or Opportunity Maintenance Concept or
Reliability Maintenance Management Concept.
4. Condition based Maintenance Concept (Between 1960 to 1970)
Condition monitoring detects and diagnoses faults and it helps in planned
maintenance based on equipment condition. This condition based on
maintenance strategy is preferred for critical system and for such system
breakdown maintenance is to be avoided. A number of condition based
maintenance techniques such as vibration, temperature, oil analysis, etc.
Have been developed, which guide the users in planned maintenance.
4
5. Total Productive Maintenance Concept (Between 1970 to 1985)
This concept is about the involvement and participation of each and every one
of the members in the organizations toward optimizing the outcome of each
piece of equipment. This is a completely new philosophy is different approach
that will keep updated by itself. It implies a continuous improvement in all
aspect and is also called Total Participation Maintenance.
The purpose is to transform the attitude of all the members of the industrial
community, all kinds and levels of workers, operators, supervisors, engineers,
administrators are included in this major responsibility. TPM implementation is
a goal that all company members share. It also generates benefits for all.
Through this effort, all are responsible for the up keeping of the equipment. It
becomes more productive, safer and easier to operate and even looks nicer.
The participation of people, who are not familiar with the equipment and its
operation, enriches the result because their observations are in many cases
more objective than those of the people who live with equipment in a daily
basis.
6. Routine Maintenance Concept (Between 1970 to 1985)
It is the Simplest form of part maintenance but very essential which Carrying
out minor maintenance job such as cleaning, lubrication, inspection, minor
adjustment of pressure, flow, tightness, etc. or inspection of bearing, belts,
coupling, joints, foundations, bolts, earthings, etc. at regular intervals.
Small/Critical effects using such inspection are rectified immediately. It is not
need base, all equipment are inspected. It may consider small portion of
preventive maintenance. It needs very little investment in terms of time and
money. The duration routine maintenance is generally so small that it does
not affect the output of machine appreciably. However, the cost of not doing
routine maintenance may be very high as a small develop in big and
catastrophic failure.
5
Fig. 1.3 Comparison of Breakdown, Predictive and Routine Maintenance
7. Computerized Maintenance Management System – CMMS (After 1985)
It is also known as Enterprise Asset Management and Computerized
Maintenance Management Information System (CMMIS). A CMMS software
package maintains a computer database of information about an
organization’s maintenance operations. This information is intended to help
maintenance worker do their jobs more effectively and to help management
make informed decisions. CMMS data may also be used to verify regulatory
compliance. CMMS package may be used by any organization that must
perform maintenance on equipment, assets and property. CMMS packages
can produce status reports and documents giving details or summaries of
maintenance activities. The more sophisticated the package, the more
analysis facilities are available. Many CMMS packages can be either web
based meaning they are hosted by the company selling the product on an
outside server or LAN based meaning that the company buying the software
hosts the product on their own server.
6
1.1.2. Selection criteria for selection of Maintenance Concept
in Industries
Presently many maintenance concepts are in use in industries and selection
has to be made depending the need, complexity and reliability needed and
also considering techno-economics. Criteria must consider are-
1) Work Procedures (Maintenance and Operation etc.)
2) Problems, Defect and Fault Reports
3) Work Schedules, Job Orders etc.
4) Work History
5) Assets
6) Inventory
7) Finance, etc.
1.2. Maintenance Agency
“Maintenance Agency is the Organization provides service to the Industries to
maintain their asset.” Asset involves infrastructure, machinery, equipment,
hardware, software, etc. Here consider maintenance agency which deals with
machinery and equipment means mechanical elements any industry.
Maintenance agency involves managing function of maintenance. Maintaining
equipment in the field has been a challenging task since the beginning of
industrial revolution. Since then, a significant of progress has been made to
maintain equipment effectively in the field. As the engineering equipment
becomes sophisticated and expensive to produce and maintain, maintenance
work has face even more challenging situations to maintain effectively such
equipments in industrial environment, And Maintenance agency are outside
agency doing this work for any industry.
1.2.1. Why Maintenance agency is needed?
In Industries now a day’s various companies such as Fanuc, Siemens,
Motorola, etc. machines are used such as lathe machine, milling machine,
7
shaper machine, drilling machine, etc. Now a day’s machine are two type
numerical and computer control CNCs machine which are more complicated
in nature. Today robot used also increased and that’s why in industry various
robotic machines or equipment are used such as welding robot, painting
robot, etc. All machineries run due to electricity that’s why maintaining of
generator and motor is also important aspect.
Other than these complex machineries on work station to transfer work in
progress material from one work station to another various different type of
material conveying system are used and sometime it is particularly made for
that industry only.
To deal with this type of modern machineries and equipments maintenance
experience maintenance department is needed by any industries which can
able to deal with any type of maintenance problem.
Small scale industries are purchased advance machinery such as CNCs,
robot, etc. to survive in market by increasing productivity with higher quality
but these industries don’t have separate maintenance department or expertise
worker who can deal with machine problems so these industries mostly deals
with breakdown maintenance concept which increase downtime of machine
and affect overall productivity of industries. Thus these industries always need
outside support for their machineries maintenance.
Medium scale industries have separate maintenance department or not but
these industry people are not that much expertise like particular maintenance
agency people who can able to solve any problem related to maintenance
because Industry maintenance department people deals with limited existing
machinery so don’t have more knowledge about new machinery and due to
less man power sometime these people deals with other function of Industry
also other than maintenance. Industry can give training to their maintenance
department people but if industry gives more focus on maintenance training
than its affect on industry productivity, thus these industries always need
outside support for their machineries maintenance.
8
Large scale industries mostly have well expertise separate maintenance
department but these industries always try to cut their cost, so if these
industries find better option in terms of maintenance agency for maintenance
so in place of go to the maintenance department where monthly salary and
training expenses are needed these industries like to go with expertise
maintenance agency out sourcing services so that these industries more
focus on effective production in place of machinery maintenance.
Maintenance agency is important aspect because,
1. It lowers down production unit cost for industries.
2. It minimizes downtime for industries.
3. It improves total availability of system in any industry.
4. It extended useful life of equipment which used in industries.
5. It increases safety of personals who work in industries.
6. It helps in reducing overtime in industries which reflect in terms of cost
saving.
7. It provides better process stability in any industry.
8. It reduce maintenance part inventory which stored in industry if that
industry have maintenance department.
Actually equipment or machinery manufacturer provides maintenance
services for their products during warranty period and after that through
contract, But now a day’s industries are having more than one company
machinery or equipment for example same industry having lathe machine of
two different company Fanuc and Siemens so after completing of warranty
period doing contract of maintenance with more than one company its quite
difficult where these manufacturer service station are not located at nearer
place (In Gujarat all machine manufacturer service station are located in
Ahmadabad so for industry which located in Ahmadabad its feasible to use
manufacturer maintenance services) and take almost two days to come after
complaining which affect production. Thus after completing warranty period all
industries are like to go with one maintenance agency who is expertise in
maintenance which provide them all type of machinery and equipment
maintenance service for any manufacturer machinery and equipment, But
9
these type of maintenance agency is not present in India actually in world for
machinery and equipment maintenance that’s why this business idea to start
maintenance agency is blue ocean business idea where maximum chances
for success.
1.3. Maintenance Agency Service Mix
1.3.1. Product
Maintenance agency should provide all machinery maintenance services
under one roof on 24X7 bases to industries for various maintenance problems
and also provide services in term of annual maintenance contract.
13.2. Place
This maintenance agency should start in Baroda city in initial basis and based
on success in future will try to increase service area from Baroda region to
Baroda District and then will try to capturing whole Gujarat then move towards
India.
Why Maintenance agency in Baroda?
Baroda is headquarters of Baroda District and after Ahmadabad and Surat
now main attraction for investor for further development. In Baroda District
total 15 Industrial area (GIDC) where total 5466 no. of units in production.
The industrial clusters include Chemicals & fertilizers, Pharmaceuticals,
Biotechnology, Cotton Textiles, Machine Tools, Glass, Engineering, Tobacco,
Fisheries and Dairy. There are over 18,000 small scale industrial units in
Baroda, in which repairs & services units are maximum in numbers
accounting nearly 5,713 units, 1,923 textiles, 1,615 metal works, 1,357
chemicals, 1,316 equipmentsmachinery, 1,145 rubber & its products, 1,047
food products and 3,840 are misc. units . Other key small scale industries
include textiles, metal works, chemicals, equipments, rubber products and
food products etc.885 glass, ceramics & cement, 829 equipments related to
10
electricity, 753 papers & its products, 601 non ferrous metals, 543 leathers,
173 tobacco and 56 are misc. units. In Baroda district 18067 units are
registered and total investment is of Rs. 223250.54 lakhs.
While in Baroda region 15534 units are registered and total investment is of
Rs. 99435.21 lakhs, which shows lots of business opportunity for
maintenance agency in Baroda region where small scale, medium scale and
large scale means all type of Industries having their present and more
investor are move towards Baroda region for investment and building strong
industrial culture.
For maintenance agency for machinery maintenance machine spare part are
required and machine spare part main market is located in Ahmadabad which
near to Baroda so to arrange required spare part in shorter period of time is
easy if maintenance agency is located in Baroda and in Gujarat all machine
manufacturer industries service station are located in Ahmadabad so for
industry machine which maintenance is quite difficult for maintenance agency
than if maintenance agency is in Baroda can used out source service of main
machine manufacturer easily.
1.3.3.Process
 Any Industry belong in Baroda region can contact this maintenance
agency for any type of maintenance problem in their machinery or
equipment.
 Any Industry can registered maintenance problem to maintenance
agency through mail, through website, through call or through
personnel contact for any type of problem.
 Maintenance problems registration should open for 24x7 and
maintenance agency should provide services 24x7.
 For any maintenance problem, that industry should get response in
terms of visit from maintenance agency within 24 hours after
registering their maintenance problem.
11
 During visit of particular industry maintenance agency experts should
try to solve problem at a time and if at that time it is not possible to
solve the problems at a time then always try to solve problem as early
as possible by giving correct estimated time.
 After repairing or solving any problem, Maintenance agency person
should verify it from that industry person, take that person signature on
document and collect those service charges.
 Maintenance agency should take annual contract for maintenance if
any industry wants, Annual contract on two ways-
- Half annual Contract where provide servicing facility to all
machinery but spare part or other replacement charges are
chargeable.
- Full annual contract where provide all type of services including
servicing of machinery to replacement in one predefined annual
amount only.
1.3.4.Price
To get success in Baroda region maintenance agency will take minimum
charges compare to other manufacturer charges and provide all machinery
maintenance services. Also maintenance agency should provide instalment
payment option.
Maintenance agency experts should visit particular industry after their problem
registration, and which charges will be Rs. 450/ machine and Rs. 800/ two
machines to that industry to check problem and correct problem if possible.
This rate should be changed based on market.
Other charges for maintenance like spare part and other out sourcing services
should be taken based on those market values.
To built long term relation maintenance agency should provide discount to
regular clients. If industry will increase service level then maintenance agency
12
should provide them more benefit in terms of additional discount in service
charges.
1.3.5. Promotion
To get success marketing is important aspect, and this maintenance agency
will used direct marketing approach and mailed relevant information and
website link with contact information to all industries mail id and also as
physical evidence send pamphlet to all industries in Baroda region.
1.3.6. People
In service Industry trust towards service provider is important aspect and
people who work as service provider can build trust towards company in the
mind of consumer.
Here in this maintenance agency people means employee of agency are
required to attain or register customer maintenance complains, visit customer
place and using expertise solve customer maintenance problem.
If Maintenance agency employee behaves in such way and creating
impression in the mind of customer in such way about maintenance agency
service then customer will buy again and again maintenance agency service
and convert it into annual contract in terms of long term professional
relationship.
1.3.7. Physical Evidence
In Maintenance agency services are provided at place of customer so
physical evidence are not matter more compare to other service industry, In
terms of physical evidence one shop is required at ground floor where storing
agency spare parts and tool; and where agency person sit and received order
in terms of maintenance problem through internet or telephone.
13
1.4. Maintenance Agency Cost
1.4.1. Fixed Cost/ Investment
To start any business initial amount is required for investment and to start
maintenance agency as shown in Table 1.1. Rs. 746500 is required as fixed
initial cost.
Table 1.1 Maintenance Agency Fixed Cost or Initial Investment
unit Rs.
Shop Deposit - 50000
Website charges - 15000
Toolbox 3 15000
Hand Drill 3 10000
Welding Machine 3 26500
Grinder/cutter 3 6000
Hacksaw 3 6000
Computer 1 22000
Printer 1 4500
Shop Furniture/ chairs - 30000
Vehicles
Tata Chhota Hathi 2 560000
Cycle 1 1500
Total 746500
1.4.2.. Variable Cost
To run any business and deal with it expanse certain amount is required on
monthly bases; and here as shown in Table 1.2. Rs. 123400 is required as
monthly working capital money to run maintenance agency.
14
Table 1.2 Maintenance Agency Variable Cost per month
Rs.
Shop Rent 5000
Petrol/ Diesel 8000
Electricity Bill 2500
Telephone Bill 3000
Stationary Cost 500
Employee Salary
Diploma Mechanical
>15 yr experience 38500
>1 yr experience 5000
Diploma electrical
>2 yr experience 6000
Computer operator 4500
Telephone operator 4500
Wages
ITI
>10 yr experience 320*2 Worker 19200
>5 yr experience 255*2 Worker 15300
Helper 190*2 Helper 11400
Total (Rs. Required per Month) 123400
Chapter 2
Secondary Data Analysis
15
2.1. Literature Review
1. The Economic Times (2013, November 25), “RIL shuts secondary unit at
its Jamnagar refinery for planned maintenance” which suggest
importance of maintenance for any industry as big industry like Reliance
close it one unit where diesel is produced and which affect Reliance
diesel stock.
2. Dilanthi M G S (2013) studied on improving productivity with maintenance
function in manufacturing industry of Sri Lanka: literature review.
The researcher reviewed literature and develop strategy to improve
productivity in manufacturing industry in country by improving
maintenance operation.
3. Department of Education and Early Childhood Development (2013)
measured feasibility of secondary education in to the broader
Sandringham area and concluded that high level of interest in discussion
about secondary education options in the Sandringham and Beaumaris
area.
4. Rexroad APG (2013) checked Colorado Springs public market feasibility
and find out that the members of the Colorado Springs Public Market
Project (CSPMP) founding organization, become increasingly exposed as
the effort becomes more and more real. Awareness and support are
important elements to making the Public Market a success. The
establishment of the market is a long and sometimes arduous process
that the public generally has little tolerance for. In order to sustain fickle
public attention without the burden of detail, communication of progress
and public involvement should be carefully managed. This is increasingly
difficult when factored to the demands of public financial support.
5. Ghaffari H et al (2012) studied on alax copper/gold feasibility projects in
Kamloops, British Columbia.
16
The researchers find out that documentation for the drilling campaigns
completed in the Ajax area before 1980 is limited or not available.
Because of the limited documentation, the pre-1980 drill campaigns were
not included in the 2011 resource model database. No factors were
identified with the data collection from the drill programs used that could
affect Mineral Resource or Mineral Reserve estimation. The Ajax deposits
have been sampled at drill-hole spacing appropriate for a property at this
level of development. Because of the irregular shape of the mineralized
body, the orientation of the mineralization with respect to drill intercepts is
unknown. The Ajax concentrator has been designed to produce a
saleable copper concentrate. The complete processing circuit has been
designed according to metallurgical test work conducted over the years
and proven equipment.
6. Tito D A et al (2012) studied on feasibility analysis for a manned mars
free return mission in 2018.
The researchers concluded that a manned Mars free-return mission is a
useful precursor mission to other planned Mars missions. It will develop
and demonstrate many critical technologies and capabilities needed for
manned Mars orbit and landing missions. The technology and other
capabilities needed for this mission are needed for any future manned
Mars missions. Investments in pursuing this development now would not
be wasted even if this mission were to miss its launch date.
7. Riccetti S (2011) studied on Product safety and equipment reliability in the
food industry through maintenance engineering.
The researcher reviewed that Failure mode and effect analysis is
important aspect for reducing maintenance problem.
8. Tahboub K K (2011) studied on an assessment of maintenance practice
and problem in Jordanian industries.
The researcher concluded that maintenance problem is mainly because
of unavailability of spare part and lack of specialities in maintenance field.
17
9. Pophaley M and Vyas R K (2010) studied on plant maintenance
management practices in automobile industries: A retrospective and
literature review.
The researchers concluded that the current work gives a broader view of
maintenance practices and research carried across the globe, but now
maintenance is the widely accepted philosophy for competitive
advantage.
10.Bliss G (2010) studied on feasibility study of services needed for aging in
place in steuben country.
The researcher find out that there is a general lack of
knowledge/understanding in people who might use the services and
about services currently being provided by the Office for the Aging and
other area service providers. There are further innovative in delivery
required for services.
11.Kalensky D and Johnson F (2010) studied on technical feasibility study
Carbon Monoxide sensing safety system foe appliances.
The researchers concluded that CO sensors would be able to operate in
the combustion chamber or the flue of a gas-fired appliance for a length of
time to be used for safety or combustion control. Smaller surfaces
improve heating and cooling times and reduce the power requirements.
12.AECOM Australia Pvt. Ltd. (2010) done pre feasibility study for a solar
power precinct and concluded that large scale solar projects are unlikely
to be financially viable for the next 10-20 years and it is hard to see a
developer making financial investments in large scale solar power plants
in the short term.
13.Transportation Economics and Management Systems, Inc. (2010)
Measured feasibility of High speed rail and concluded that The feasibility
of high-speed rail in Colorado represents a tremendous transportation
and development opportunity for the Colorado and the Rocky Mountain
west High-speed rail can provide a more efficient and cost-effective
18
means of connecting Colorado’s commercial centers with one another as
well as the national and international destinations served by the state’s
airports. High-speed rail also provides a more reliable, enjoyable and
convenient way for tourists from all over the globe to get to some of the
most important and popular recreational resort destinations in North
America and the world. The economic benefits of such an investment are
considerable. While the costs of implementing high-speed rail are large,
as would be expected given the mountainous conditions in the I-70
corridor ($16 billion to $21 billion for service in both corridors), analysis
indicates that investing in high-speed rail would generate an impressive
$33 billion of benefits to Colorado. These benefits are generated by the
rapid growth of the state and its need to accommodate a doubling of its
population over the next 30-40 years. High-speed rail is by no means the
silver bullet that solves all of Colorado’s transportation challenges. But, as
this study clearly shows, it is a critical part of that solution and will be
invaluable to the growth of the state’s economy.
14.Wilson R J (2010) studied on 2009‐2010 Feasibility and Market Research
Study for Commercial Hop Production in New England.
The researcher determined that is feasible to grow a commercial hop crop
in New England. There is sufficient demand, there is sufficient price
elasticity, and there is now the information, technology, supplies, and
equipment available to meet the needs of a 1‐10 acre commercial hop
yard.
15.Fonollera D L (2009) studied on feasibility study, project plan and
business plan.
The researcher concluded that feasibility study is used as a means of
exploring the viability of an idea. The viability of an idea, its accuracy and
its reliability depends on the information gathered through market
research and analysis which used mainly to support project feasibility.
16.Lepelle-Nkumpi Local Municipality (2009) studied goat meat production
feasibility study and find out that each co-operative member and/or
19
worker will be required to register for a goat management-training course
offered by the Agricultural Research Council of South Africa.
17.Sautter F C et al (2008) studied on an integrated Maintenance
management information system is the key to enabling condition based
maintenance.
The researchers find that the maintenance management information
systems are the foundation for the data that support effective
management decision.
18.Reis N, Sydness G S and Barton D N (2007) studied feasibility of
payment for water services.
The researchers concluded that In India, PWS programmes that increase
employment opportunities by stimulating the demand in agricultural labour
are likely to have the greatest benefits for the poor. If too many of the
constraints consider in this work are present in a watershed, market-like
arrangements will not be likely to offer the optimal way of achieving
environmental conservation and solving water-related conflicts.
19.Hopwood V et al (2007) studied feasibility of the prevalence of home
education in England.
The researchers find out that it is not feasible to reliably ascertain the
prevalence of home educated children through a national survey of LAs
and home education organizations (as a route through which to access
parents/careers). This is because despite improvements in LA records,
there could be significant numbers of home educated children who are
not known to an LA.
20.Pe’re’setal F and Noyes D (2006) studied on envisioning e-logistics
developments: Making spare parts in situ and on demand: State of art
and guideline for future developments.
The researchers expressed the problem of supplying the spare part by
automobile manufacturers. Thus effective maintenance system need is
further increases.
20
21.Firmansyah A, Veronika A and Trigunarsyah B (2006) studied on risk
analysis in feasibility study of building construction projects.
The researchers find out that Feasibility study analysis with calculating
risk factors cause a decrease in investment feasibility parameters and if
treatments are done against the risks, hence the parameters will
increase. Risk factors give a significant influence to the investment plan of
research object. Risk factors that have the highest influence to the
construction project are those that have relation with economical and
financial aspect. The economic factors that have high sensitivity of
investment feasibility are loan interest rate and increments of sales.
Meanwhile, the factors that have low sensitivity are inflation changes and
equity percentage.
22.Batson R G and Wan Q (2004) studied on quality of assembly assurance.
The researchers find out that Quality of assembly is complex issue and
four management systems are important namely production, quality,
maintenance and human resources.
23.Chelbi A and Aitkadi D (2004) studied on analysis of a
production/inventory system with randomly failing production unit
submitted to regular preventive maintenance
The researcher concluded that a repairable production unit subject to a
random failures, such as in automobile manufacturing, a mathematical
model has been developed to support maintenance strategy.
24.Batson R, Hall D and Hauer D (2001) studied on the role of equipment
maintenance in lean assembly system.
The researchers concluded that the excellence in equipment
maintenance is essential to lean assembly.
25.Hoagland W H and Williamson L (2000) overviewed feasibility studies.
21
The researcher concluded that a feasibility study is an important tool for
making the right decisions in starting of new business and a wrong
decision at this point often leads to business failure.
26.Wadswoeth B (1999) studied on factor affecting forestland conversion
and the feasibility of cooperative land management efforts at king
countries urban/rural interface.
The researcher concluded that King County's urban/rural interface
presents a complex problem for planners and natural resource managers.
The changing population and the associated fragmentation of large
ownerships into small residential home sites has resulted in an increasing
spectrum of landowner values and objectives that makes planning for the
interface a difficult and potentially frustrating task. If King County leaders
are committed to preserving the forest land base, they cannot ignore the
problem, and they must act to set policy with this commitment in mind.
Hopefully, this research can provide direction for King County’s planners
and elected officials as they strive to work with forest landowners at the
urban/rural interface to preserve forestland. The issue of forestland
conversion at the urban/rural interface is not unique to King County, and
many of the results from this study may well apply to other interface areas
throughout the country.
27.Novak L R (1996) studied on guiding way for market feasibility study.
The researcher concluded that Market and feasibility studies are quite
complex. The best way to learn about market and feasibility studies, like
most things, is by doing. If you don't have the opportunity to work on a
study acquire and review a couple. The importance of market studies is
not going to decrease. Capital is becoming more difficult to acquire and
regulatory considerations are becoming more complex. In the competitive
world of real estate development, the investor with the best information is
going to be the most successful.
28.Murry R J and Mitchell B F (1994) studied on cost saving from practical
preventive maintenance program.
22
The researchers showed the importance of predictive maintenance in
effective maintenance management.
29.Meade B W and Hunsucker D Q (1991) studied on Cost effective
maintenance Contracting – A literature review.
The researchers find out that routine maintenance approaches reduce
maintenance problem in highways which done on activity based.
30.Reichelderfer K (1984) studied on factor affecting the economic feasibility
of the biological control of the weeds.
The researcher the individual or group responsible for application and/or
maintenance of the potential bio control approach perceive the target
weed problem, the economic activity impacted by the weed has high
value, and the biological control agent’s effect on the weed is neither slow
nor highly variable, There either no current affective control available for
the target weed or current control is very costly and the net economic
returns to users of the bio control tactic are expected to equal or exceed
those for alternative control.
23
2.2.ContentAnalysis
Table2.1.ContentAnalysis
Remark
NA
NA
NA
Gap
Maintenanceisan
importantaspectfor
industriesbutno
machinemaintenance
agencypresentin
world.
Maintenanceisan
importantaspectfor
manufacturingindustry
butnomachine
maintenanceagency
presentinworld.
Researchisnotcarried
outformeasuring
maintenanceagency
feasibility.
Finding
RILshutssecondaryunitat
itsJamnagarrefineryfor
planedmaintenance.
Productivityofmanufacturing
industryisincreasedby
improvingmaintenance
operation.
Highlevelofinterestin
discussionaboutsecondary
educationoptionsinthe
SandringhamandBeaumaris
area.
Test
Appeared
NA
NA
NA
Sample
Size
NA
NA
2970
Country
India
Srilanka
UK
Year
2013
2013
2013
Author
TheEconomic
Times
DilanthiMGS
Departmentof
Educationand
EarlyChildhood
Development
Sr.
No.
1
2
3
24
Table2.1(Continue...)
Remark
NA
NA
Gap
Researchisnot
carriedoutfor
measuring
maintenanceagency
feasibility.
Researchisnot
carriedoutfor
measuring
maintenanceagency
feasibility.
Finding
Organizationbecomes
increasinglyexposedasthe
effortbecomesmoreand
morereal.Awarenessand
supportareimportant
elementstomakingthePublic
Marketasuccess.Thisis
increasinglydifficultwhen
factoredtothedemandsof
publicfinancialsupport.
Thepre-1980drillcampaigns
werenotincludedinthe2011
resourcemodeldatabase.
TheAjaxconcentratorhas
beendesignedtoproducea
saleablecopperconcentrate.
Thecompleteprocessing
circuithasbeendesigned
accordingtometallurgicaltest
work
Test
Appeared
NA
NA
Sample
Size
NA
NA
Country
USA
Kamloops
British
Columbia.
Year
2013
2012
Author
RexroadAPG
GhaffariHetal
Sr.
No.
4
5
25
Table2.1(Continue...)
Remark
NA
NA
NA
Gap
Researchisnot
carriedoutfor
measuring
maintenanceagency
feasibility.
Maintenanceisan
importantaspectfor
continuesgrowthbut
nomachine
maintenanceagency
presentinworld.
Scopefor
Maintenanceagency
whichhaveall
necessaryexpertise
andsparepartatthe
timeofmaintenance.
Finding
Itwilldevelopand
demonstratemanycritical
technologiesand
capabilitiesneededfor
mannedMarsorbitand
landingmissions.
Failuremodeandeffect
analysisisimportantaspectfor
reducingmaintenance
problem.
Maintenanceproblemis
mainlybecauseof
unavailabilityofsparepart
andlackofspecialitiesin
maintenancefield.
Test
Appeared
NA
NA
NA
Sample
Size
NA
NA
NA
Country
USA
USA
Jordan
Year
2012
2011
2011
Author
TitoDAetal
RiccettiS
TahboubKK
Sr.
No.
6
7
8
26
Table2.1(Continue...)
Remark
NA
NA
NA
Gap
Maintenanceis
necessarytoget
competitive
advantagebutno
machinemaintenance
agencypresentin
world.
Researchisnot
carriedoutfor
measuring
maintenanceagency
feasibility.
Researchisnot
carriedoutfor
measuring
maintenanceagency
feasibility.
Finding
Thecurrentworkgivesa
broaderviewofmaintenance
practicesandresearch
carriedacrosstheglobe,but
nowmaintenanceisthe
widelyacceptedphilosophy
forcompetitiveadvantage.
Lackofknowledgeinpeople
whomightusetheservices
andaboutservicescurrently
beingprovidedbytheOffice
fortheAgingandotherarea
serviceproviders.
COsensorswouldbeableto
operateinthecombustion
chamberortheflueofagas-
firedapplianceforalengthof
timetobeusedforsafetyor
combustioncontrol.Smaller
surfacesimproveheatingand
coolingtimesandreducethe
powerrequirements.
Test
Appeared
NA
NA
NA
Sample
Size
NA
3038
NA
Country
India
USA
USA
Year
2010
2010
2010
Author
PophaleyM
VyasRK
BliseG
KalenskyD
JohnsonF
Sr.
No.
9
10
11
27
Table2.1(Continue...)
Remark
NA
NA
NA
Gap
Researchisnot
carriedoutfor
measuring
maintenance
agencyfeasibility.
Researchisnot
carriedoutfor
measuring
maintenance
agencyfeasibility.
Researchisnot
carriedoutfor
measuring
maintenance
agencyfeasibility.
Finding
Largescalesolarprojectsare
unlikelytobefinanciallyviablefor
thenext10-20yearsanditis
hardtoseeadevelopermaking
financialinvestmentsinlarge
scalesolarpowerplantsinthe
shortterm.
Investinginhigh-speedrailwould
generateanimpressive$33billion
ofbenefitstoColorado.
Feasibletogrowacommercial
hopcropinNewEngland.There
issufficientdemand,thereis
sufficientpriceelasticity,and
thereisnowtheinformation,
technology,supplies,and
equipmentavailabletomeetthe
needsofa1‐10acrecommercial
hopyard.
Test
Appeared
NA
NA
NA
Sample
Size
NA
3038
NA
Country
Australia
USA
UK
Year
2010
2010
2010
Author
AECOM
AustraliaPvt.
Ltd.
Transportation
Economicsand
Management
Systems,Inc.
WilsonRJ
Sr.
No.
12
13
14
28
Table2.1(Continue...)
Remark
NA
NA
NA
Gap
Todayintheworld
nomachine
maintenance
agencyexistingso
tocheckviability
ofmaintenance
agency,its
feasibilitystudyis
necessary.
Researchisnot
carriedoutfor
measuring
maintenance
agencyfeasibility.
Maintenance
agencyisrequired
formanaging
maintenance
information.
Finding
Feasibilitystudyisusedasa
meansofexploringtheviability
ofanidea.Theviabilityofan
idea,itsaccuracyandits
reliabilitydependsonthe
informationgatheredthrough
marketresearchandanalysis
whichusedmainlytosupport
projectfeasibility.
Eachco-operativemember
and/orworkerwillberequired
toregisterforagoat
management-trainingcourse
offeredbytheAgricultural
ResearchCouncilofSouth
Africa.
Themaintenance
managementinformation
systemsarethefoundationfor
thedatathatsupporteffective
maintenancedecision.
Test
Appeared
NA
NA
NA
Sample
Size
NA
NA
NA
Country
Philippines
SouthAfrica
USA
Year
2009
2009
2008
Author
FonolleraDL
Lepelle-Nkumpi
Local
Municipality
SautterFCetal
Sr.
No.
15
16
17
29
Table2.1(Continue...)
Remark
NA
NA
NA
Gap
Researchisnot
carriedoutfor
measuring
maintenanceagency
feasibility.
Researchisnot
carriedoutfor
measuring
maintenanceagency
feasibility.
Scopefor
Maintenanceagency
whichhaveall
necessarysparepart
atthetimeof
maintenance.
Finding
PWSprogrammesthat
increaseemployment
opportunitiesbystimulating
thedemandinagricultural
labourarelikelytohavethe
greatestbenefitsforthepoor
people.
itisnotfeasibletoreliably
ascertaintheprevalenceof
homeeducatedchildren
throughanationalsurveyof
LAsandhomeeducation
organizations
Automobilemanufacturer
facingprobleminsupplying
sparepart.Thuseffective
maintenancesystemneedis
increases.
Test
Appeared
NA
NA
NA
Sample
Size
NA
NA
NA
Country
India
UK
NA
Year
2007
2007
2006
Author
ReisN
SydnessGS
BartonDN
HopwoodV
O’NeillL
CastroG
HodgsonB
Pe’re’setalF
NoyesD
Sr.
No.
18
19
20
30
Table2.1(Continue...)
Remark
NA
NA
NA
Gap
Maintenanceagency
feasibilitystudyis
necessarytominimize
itsrisk.
Maintenanceisan
importantaspectfor
managementbutno
machinemaintenance
agencypresentin
world.
Todevelopeffective
mathematicalmodel
formaintenance
machinemaintenance
agencyisrequired.
Finding
Riskfactorsgiveasignificant
influencetotheinvestment
planofresearchobject.Risk
factorsthathavethehighest
influencetotheconstruction
projectarethosethathave
relationwitheconomicaland
financialaspect.
Qualityofassemblyiscomplex
issueandfourmanagement
systemareimportantnamely
production,quality,
maintenanceandhuman
resources.
Arepairableproductionunit
subjecttoarandomfailures,
suchasinautomobile
manufacturing,amathematical
modelhasbeendevelopedto
supportmaintenancestrategy.
Test
Appeared
NA
NA
NA
Sample
Size
NA
NA
NA
Country
Thailand
USA
USA
Year
2006
2004
2004
Author
FirmansyahA
VeronikaA
TrigunarsyahB
BatsonRG
WanQ
ChelbiA
AitkadiD
Sr.
No.
21
22
23
31
Table2.1(Continue...)
Remark
NA
NA
Gap
Maintenanceisan
importantaspectbut
nomachine
maintenanceagency
presentinworld.
Researchisnot
carriedoutfor
measuring
maintenanceagency
feasibility.
Finding
Theexcellencein
equipmentmaintenanceis
essentialtoleanassembly..
Afeasibilitystudyisan
importanttoolformakingthe
rightdecisionsinstartingof
newbusinessandawrong
decisionatthispointoften
leadstobusinessfailure.
Test
Appeared
NA
NA
Sample
Size
NA
NA
Country
USA
UK
Year
2001
2000
Author
BastonR
HallD
HauerD
HoaglandWH
WilliamsonL
Sr.
No.
24
25
32
Table2.1(Continue...)
Remark
NA
NA
NA
Gap
Researchisnot
carriedoutfor
measuring
maintenanceagency
feasibility.
TolearnMaintenance
agencyfeasibilityits
necessarytomeasure
itbydoingmarket
research.
Maintenanceisan
importantaspectfor
managementbutno
machinemaintenance
agencypresentin
world.
Finding
Thechangingpopulationand
theassociatedfragmentationof
largeownershipsintosmall
residentialhomesiteshas
resultedinanincreasing
spectrumoflandownervalues
andobjectivesthatmakes
planningfortheinterfacea
difficultandpotentially
frustratingtask.
Thebestwaytolearnabout
marketandfeasibilitystudies,
likemostthings,isbydoing.
theimportanceofpredictive
maintenanceineffective
maintenancemanagement
Test
Appeared
NA
NA
NA
Sample
Size
1830
NA
NA
Country
NA
USA
USA
Year
1999
1996
1994
Author
WadswoethB
NovakLR
MurryRJ
MitchellBF
Sr.
No.
26
27
28
33
Table2.1(Continue...)
Remark
NA
NA
Gap
Routinemaintenance
leadsmaintenance
agencyrequirement
forcontinuous
maintenancework.
Researchisnot
carriedoutfor
measuring
maintenanceagency
feasibility.
Finding
Routinemaintenance
approachesreduce
maintenanceproblemin
highwayswhichdoneon
activitybased.
Individualorgroupresponsible
forapplicationand/or
maintenanceofthepotential
biocontrolapproachperceive
thetargetweedproblem,the
economicactivityimpactedby
theweedhashighvalue,and
thebiologicalcontrolagent’s
effectontheweedisneither
slownorhighlyvariable,and
theneteconomicreturnsto
usersofthebiocontroltactic
areexpectedtoequalor
exceedthoseforalternative
control.
Test
Appeared
NA
NA
Sample
Size
NA
NA
Country
USA
USA
Year
1991
1984
Author
MeedeBW
HunsuckerDQ
ReichelderferK
Sr.
No.
29
30
34
2.3. Research Gap
Literature Review Conclusion:
Scope of Maintenance is increasing to get competitive advantage.
Maintenance management support management to take effective
management decision and for effective maintenance management
computer based maintenance information system and mathematical
model is required now a days. In Maintenance machine spare part
availability and maintenance person expertise is major problem.
Maintenance is important for any industry as big industry like Reliance
close it one unit where diesel is produced and which affect Reliance diesel
stock.
Maintenance is important aspect for industries but today in world no
machinery maintenance agency presents which provides all type of
expertise, 24x7 availability for all type of machinery under one roof.
So here try to find out this type of maintenance agency is feasible in actual
industrial environment or not based on industries review.
Chapter 3
Signification of Study
35
1. This study is used to know which types of machinery are mostly used in
Baroda region.
2. This study is help to know the intention of the existing industries towards
services provide by maintenance agency.
3. This study is help to know the interest of the existing industries in services
provided by maintenance agency.
4. This study is help to know the perception of the existing industries towards
maintenance agency.
5. This study is help to know existing industries purchasing attitude towards
service provide by maintenance agency.
6. This study is help to measure profitability of maintenance agency based on
responses.
Chapter 4
Research Methodology
36
4.1. Problem Statement
“To study the feasibility of Maintenance agency in Baroda.”
4.2. Objective of the Study
1. To know the intention of the existing industries towards services
provide by maintenance agency.
2. To know the interest of the existing industries in services provided by
maintenance agency.
3. To know the perception of the existing industries towards maintenance
agency.
4. To know existing industries purchasing attitude towards service provide
by maintenance agency.
5. To measure profitability of maintenance agency based on responses.
4.3. Research Hypothesis
Intension
1 H0: Existing industries are not having positive intension towards
maintenance agency services.
H1: Existing industries are having positive intension towards
maintenance agency services.
2 H0: Company Intension towards Maintenance agency services is
not independent of the type of Industry and Company annual
maintenance budget.
H1: Company Intension towards Maintenance agency services is
independent of the type of Industry and Company annual
maintenance budget.
37
Interest
3 H0: Company interest level towards Maintenance agency
services is not independent of the type of Industry and
Company annual maintenance budget.
H1: Company interest level towards Maintenance agency
services is independent of the type of Industry and Company
annual maintenance budget.
4 H0: Existing industries are not interested in services provided by
maintenance agency.
H1: Existing industries are interested in services provided by
maintenance agency.
Perception
5 H0: Existing industries are not having good perception towards
maintenance agency.
H1: Existing industries are having good perception towards
maintenance agency.
6 H0: Company Perception towards Maintenance Agency is not
independent of the type of Industry and Company annual
maintenance budget.
H1: Company Perception towards Maintenance Agency is
independent of the type of Industry and Company annual
maintenance budget.
Attitude
7 H0: There is no significant difference among type of Industry or
company annual maintenance budget regarding decision of
purchasing maintenance agency services.
H1: There is significant difference among type of Industry or
company annual maintenance budget regarding decision of
purchasing maintenance agency services.
38
8 H0: Existing industries are not purchased services provided by
maintenance agency.
H1: Existing industries are purchased services provided by
maintenance agency.
4.4. Research Design
For this research we used Descriptive type research Design.
4.5. Sampling Method
We used simple random sampling method to select Company plot in GIDCs
but if in one plot more than one company used convenience sampling method
to select sample from that particular plot for completing quota for our
research.
4.6. Data collection Instrument
For this research we used questionnaire for collecting the information from the
respondents. (Refer Annexure I)
4.7. Sampling Unit
All 15534 industrial units which are registered in Baroda region are able to
became sample.
4.8. Sample Size
We are taken 400 industries as respondents for collecting the information for
the research.
Chapter 5
Data Analysis
39
5.1. Demographic Profile
Table 5.1 Demographic Profile
Frequency Percentage
Area
Makarpura GIDC 86 21.50
Pore GIDC 40 10.00
Nandesari GIDC 18 4.50
Ranoli GIDC 97 24.25
Salvi GIDC 63 15.75
Vagodia GIDC 96 24.00
Type of Industry
Machine work Industry 256 64.00
Fabrication Industry 48 12.00
Sheet Metal Work Industry 20 5.00
Foundry Industry 40 10.00
Service Industry 12 3.00
Others
24 6
Cement Industry
Chemical Industry
Paint Industry
Pharmaceutical Industry
Annual
Maintenance
Budget (Rs.)
Below 4999 55 13.75
5000 to 14999 192 48.00
15000 to 24999 82 20.50
25000 to 34999 20 5.00
35000 to 44999 27 6.75
Above 45000 24 6.00
5.2. Response Rate
=
400 ∗ 100
435
= 90.9 %
40
5.3. Questionnaire Analysis
Q-1: Do you have machinery in your company?
Table 5.2 Machinery basic Data
Particulars Frequency
Yes 400
No 0
Fig 5.1 Machinery basic Data
Interpretation:
This question is one of the basic filter question, If answer is Yes then one can
consider further response of that respondent otherwise rejected that
questionnaire. So 400 means 100 % respondent whose answer is Yes are
consider as respondent in this research.
100%
0%
0%
20%
40%
60%
80%
100%
120%
Yes No
41
Q-2: Rank following type of machinery based on number of
machine you have of that type.
Table 5.3 Type of Machinery
Particulars Rank Mean
Conventional 1 2.65
Semi Automatic 2 1.29
Automatic 3 0.25
Fig 5.2 Type of Machinery
Interpretation:
This question is used to generate interaest and to know which type of
machinery expertise required by maintenance agency to get success in future.
Based on responces companies have 63.19% conventional machinery, 30.85
% Semi Automatic machinery and 5.96 % Automatic machinery in Baroda.
63.19%
30.85%
5.96%
0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
70.00%
Conventional Semi Automatic Automatic
42
Q-3: For Operational Machinery,
Rank based on usage in operation.
Table 5.4 Operational Machinery Usage
Particulars Rank Mean Percentage
Lathe m/c 1 9.90 16.46
Milling m/c 4 5.88 9.77
Boring m/c 5 4.26 7.08
Shaper m/c 7 3.70 6.15
Drilling m/c 2 8.92 14.83
Hobbing m/c 13 1.07 1.78
Cutting m/c 3 8.09 13.45
Wire cut m/c 17 0.54 0.89
Heating Equipments 9 2.42 4.02
Polishing/Grinding m/c 8 2.89 4.80
Moulding m/c 12 1.14 1.89
Sand Mixer 14 1.00 1.66
Knockout m/c 18 0.43 0.71
Forging m/c 16 0.68 1.13
Rolling m/c 10 2.25 3.74
Welding Equipments 6 4.09 6.79
Sort blasting m/c 15 0.83 1.37
Bending/Punching m/c 11 2.06 3.42
Interpretation:
If machinery usage is incresed then its maintenance problem occuring rate
also increase. By knowing which Operational machinery used more here try to
find which machinery expertise will be required mainly by Maintenance
agency in future. Based on responces companies are maximum using
Operational machinery like Lathe m/c (16.46 %), Drilling m/c (14.83 %),
Cutting m/c (13.45 %), Milling m/c (9.77 %), Boring m/c (7.08 %), Welding
Equipments (6.79 %) and Shaper m/c (6.15 %) in Baroda; Companies are
43
Fig 5.3 Operational Machinery Usage
moderate way using Operational machinery like Polishing/Grinding m/c (4.80
%), Heating Equipments (4.02 %), Rolling m/c (3.74 %) and
Bending/Punching m/c (3.42 % ) in Baroda; While Companies are very less
using Operational machinery like Moulding m/c (1.89 % ), Hobbing m/c (1.78
% ), Sand Mixer (1.66 % ), Sort blasting m/c (1.37 % ), Forging m/c (1.13 % ),
Wire cut m/c (0.89 % ) and Knockout m/c (0.71 %) in Baroda. By using Table
5.4 it can be interpreted that to get success in Baroda initial stage
Maintenance agency should get expertise in Operational machinery like Lathe
m/c, Drilling m/c, Cutting m/c, Milling m/c, Boring m/c, Welding Equipments
and Shaper m/c maintenance works; then move towards other Operational
machinery expertise.
0.00%
2.00%
4.00%
6.00%
8.00%
10.00%
12.00%
14.00%
16.00%
18.00%
Lathem/c
Millingm/c
Boringm/c
Shaperm/c
Drillingm/c
Hobbingm/c
Cuttingm/c
Wirecutm/c
HeatingEquipments
Polishing/Grindingm/c
Mouldingm/c
SandMixer
Knockoutm/c
Forgingm/c
Rollingm/c
WeldingEquipments
Sortblastingm/c
Bending/Punchingm/c
44
No. of Operational machinery In Companies.
Table 5.5 No. of Operational Machinery
Particulars Mean (Units) Percentage
Lathe m/c 2.92 20.15
Milling m/c 1.50 10.37
Boring m/c 1.05 7.26
Shaper m/c 0.88 6.08
Drilling m/c 2.02 13.96
Hobbing m/c 0.38 2.63
Cutting m/c 1.14 7.88
Wire cut m/c 0.07 0.48
Heating Equipments 0.43 2.97
Polishing/Grinding m/c 0.70 4.84
Moulding m/c 0.24 1.66
Sand Mixer 0.18 1.24
Knockout m/c 0.09 0.63
Forging m/c 0.15 1.04
Rolling m/c 0.75 5.18
Welding Equipments 1.42 9.82
Sort blasting m/c 0.23 1.59
Bending/Punching m/c 0.32 2.22
Interpretation:
If no. of machinery is more then only generate expertise to solve it
maintenance problem become worthful. By knowing which Operational
machinery is more in number Maintenance agency should try to develop more
expertise for that type of machinery. Based on responces companies have
Operational machinery like Lathe m/c (20.15 %), Drilling m/c (13.96 %),
Milling m/c (10.37 %), Welding Equipments (9.82 %), Cutting m/c (7.88 %),
Boring m/c (7.26 %), Shaper m/c (7.08 %), Rolling m/c (5.18 %),
Polishing/Grinding m/c (4.84 %), Heating Equipments (2.97 %), Hobbing m/c
45
Fig 5.4 No. of Operational Machinery
(2.63 % ), Bending/Punching m/c (2.22 %), Moulding m/c (1.66 %), Sort
blasting m/c (1.59 %), Sand Mixer (1.24 %), Forging m/c (1.04 %), Knockout
m/c (0.63 %) and Wire cut m/c (0.48 %) in Baroda. By using Table 5.5 it can
be interpreted that to get success in Baroda initial stage Maintenance agency
should get expertise in Operational machinery like Lathe m/c, Drilling m/c,
Milling m/c, Welding Equipments, Cutting m/c, Boring m/c, Shaper m/c,
Rolling m/c and Polishing/Grinding m/c maintenance works; then move
towards other operational machinery expertise.
0.00%
5.00%
10.00%
15.00%
20.00%
25.00%
Lathem/c
Millingm/c
Boringm/c
Shaperm/c
Drillingm/c
Hobbingm/c
Cuttingm/c
Wirecutm/c
HeatingEquipments
Polishing/Grindingm/c
Mouldingm/c
SandMixer
Knockoutm/c
Forgingm/c
Rollingm/c
WeldingEquipments
Sortblastingm/c
Bending/Punchingm/c
46
Average age of Operational machinery in Companies.
Table 5.6 Average age of Operational Machinery
Particulars Mean (Years)
Lathe m/c 7.24
Milling m/c 6.83
Boring m/c 6.73
Shaper m/c 6.04
Drilling m/c 8.05
Hobbing m/c 7.00
Cutting m/c 7.37
Wire cut m/c 5.67
Heating Equipments 8.87
Polishing/Grinding m/c 8.95
Moulding m/c 9.14
Sand Mixer 9.67
Knockout m/c 7.33
Forging m/c 6.00
Rolling m/c 8.11
Welding Equipments 7.07
Sort blasting m/c 8.20
Bending/Punching m/c 9.46
Interpretation:
If machinery age is more then chances of its break down in high means more
scope for its maintenance problem. By knowing which Operational machinery
age is more, Maintenance agency should try to develop more expertise for
that type of machinery. Based on responces companies have Operational
machinery of with average age of 9.67 years old Sand Mixer, 9.46 years old
Bending/Punching m/c, 9.14 years old Moulding m/c, 8.95 years old
Polishing/Grinding m/c, 8.87 years old Heating Equipments, 8.20 years old
Sort blasting m/c, 8.11 years old Rolling m/c, 8.05 years old Drilling m/c, 7.37
years old Cutting m/c, 7.33 years old Knockout m/c, 7.24 years old Lathe m/c,
47
Fig 5.5 Average age of Operational Machinery
7.07 years old Welding Equipments, 7.00 years old Hobbing m/c, 6.83 years
old Milling m/c, 6.73 years old Boring m/c, 6.04 years old Shaper m/c, 6.00
years old Forging m/c, and 5.67 years old Wire cut m/c in Baroda. Based on
this data it interpreted that all Operational machinery have age is around more
than 6 years so warranty periods are over and good scope for maintenance
works so Maintenance agency will try to develop expertise for all Operational
machinery.
0
2
4
6
8
10
12
Lathem/c
Millingm/c
Boringm/c
Shaperm/c
Drillingm/c
Hobbingm/c
Cuttingm/c
Wirecutm/c
HeatingEquipments
Polishing/Grindingm/c
Mouldingm/c
SandMixer
Knockoutm/c
Forgingm/c
Rollingm/c
WeldingEquipments
Sortblastingm/c
Bending/Punchingm/c
Years
48
Q-4: For Conveying Machinery,
Rank based on usage in operation.
Table 5.7 Conveying Machinery Usage
Particulars Rank Mean Percentage
Crain 1 1.73 74.92
Bucket Elevator 2 0.27 11.62
Belt Conveyor 3 0.24 10.42
Pipe Line 4 0.07 3.04
Fig 5.6 Conveying Machinery Usage
Interpretation:
If machinery usage is incresed then its maintenance problem occuring rate
also increase. By knowing which Conveying machinery used more here try to
find which machinery expertise will be required mainly by Maintenance
agency in future. Based on responces companies are maximum using Crain
(74.92 %) for Conveying purpose in Baroda. Companies are also using
Buckete Elevator (11.62 %), Belt Conveyor (10.42 %) and Pipeline (3.04 %)
for Conveying purpose in Baroda. Thus to get success in Baroda Crain
maintenance work expertise is essential for Maintenance agency.
0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
70.00%
80.00%
Crain Bucket Elevator Belt Conveyor Pipe Line
49
No. of Conveying machinery In Companies.
Table 5.8 No. of Conveying Machinery
Particulars Mean (Unit) Percentage
Crain 1.28 42.51
Bucket Elevator 0.23 7.61
Belt Conveyor 0.42 13.73
Pipe Line 1.09 36.14
Fig 5.7 No. of Conveying Machinery
Interpretation:
If no. of machinery is more then only generate expertise to solve it
maintenance problem become worthful. By knowing which Conveying
machinery is more in number Maintenance agency should try to develop more
expertise for that type of machinery. Based on responces companies have
mainly Crain (42.51) % and Pipe line (36.14 % - used in Chemical industries
mainly but in large quantity) as Conveying machinery in Baroda; Companies
also have Belt conveyor (13.74 %) and Bucket Elevator (7.61 %) for
Conveying purpose in Baroda. Thus to get success in Baroda Crain
maintenance work expertise is essential for Maintenance agency at initial
stage and then move towards other Conveying machinery expertise.
0.00%
5.00%
10.00%
15.00%
20.00%
25.00%
30.00%
35.00%
40.00%
45.00%
Crain Bucket Elevator Belt Conveyor Pipe Line
50
Average age of Conveying machinery in Companies.
Table 5.9 Average age of Conveying Machinery
Particulars Mean (Years)
Crain 7.22
Bucket Elevator 8.48
Belt Conveyor 8.23
Pipe Line 6.85
Fig 5.8 Average age of Conveying Machinery
Interpretation:
If machinery age is more then chances of its break down in high means more
scope for its maintenance problem. By knowing which Conveying machinery
age is more, Maintenance agency should try to develop more expertise for
that type of machinery. Based on responces companies have 8.48 years old
Bucket Elevator, 8.23 years old Belt conveyor, 7.22 years old Crain and 6.85
years old pipelines as Conveying machinery in Baroda. All Conveying
machinery have age is around more than 7 years so warranty periods are
over and good scope for maintenance works so Maintenance agency will try
to develop expertise for all Conveying machinery.
0
1
2
3
4
5
6
7
8
9
Crain Bucket Elevator Belt Conveyor Pipe Line
Years
51
Q-5: For Power supply Machinery,
Rank based on usage in operation.
Table 5.10 Power supply Machinery Usage
Particulars Rank Mean Percentage
Motor 2 0.07 22.05
Generator 1 0.16 50.39
Transformer 3 0.05 14.96
Electric Panel 4 0.04 12.59
Fig 5.9 Power supply Machinery Usage
Interpretation:
If machinery usage is incresed then its maintenance problem occuring rate
also increase. By knowing which Power supply machinery used more here try
to find which machinery expertise will be required mainly by Maintenance
agency in future. Based on responces companies are maximum using
Generator (50.39 %) for Power supply purpose in Baroda. Companies are
also using Motor (22.05 %), Transformer (14.96 %) and Electric Panel (12.59
%) for Power supply purpose in Baroda. Thus to get success in Baroda
Generator maintenance work expertise is essential for Maintenance agency.
0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
Motor Generator Transformer ElectricPanel
52
No. of Power supply machinery In Companies.
Table 5.11 No. of Power supply Machinery
Particulars Mean (Unit) Percentage
Motor 0.35 81.28
Generator 0.06 14.04
Transformer 0.01 2.34
Electric Panel 0.01 2.34
Fig 5.10 No. of Power supply Machinery
Interpretation:
If no. of machinery is more then only generate expertise to solve it
maintenance problem become worthful. By knowing which Power supply
machinery is more in number Maintenance agency should try to develop more
expertise for that type of machinery. Based on responces companies have
mainly motor (81.28 %) as Power supply machinery in Baroda; Companies
also have Generator (14.04 %), Transformer (2.34 %) and Electric panel (2.34
%) for Power supply purpose in Baroda. Thus to get success in Baroda Motor
maintenance work expertise is essential for Maintenance agency at initial
stage and then move towards other Power supply machinery expertise.
0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
70.00%
80.00%
90.00%
Motor Generator Transformer ElectricPanel
53
Average age of Power supply machinery in Companies.
Table 5.12 Average age of Power supply Machinery
Particulars Mean (Years)
Motor 6.86
Generator 9.5
Transformer 5
Electric Panel 5
Fig 5.11 Average age of Power supply Machinery
Interpretation:
If machinery age is more then chances of its break down in high means more
scope for its maintenance problem. By knowing which Power supply
machinery age is more, Maintenance agency should try to develop more
expertise for that type of machinery. Based on responces companies have 9.5
years old Generator, 6.86 years old Motor, 5.00 years old Transformer and
Electric panel as Power supply machinery in Baroda. All Power supply
machinery have age is around more than 5 years so warranty periods are
over and good scope for maintenance works so Maintenance agency will try
to develop expertise for all Power supply machinery.
0
1
2
3
4
5
6
7
8
9
10
Motor Generator Transformer ElectricPanel
Years
54
Q-6: Do you use machinery of different manufacturer?
Table 5.13 Different Manufacturer machinery usage
Particulars Frequency
Yes 365
No 35
Fig 5.12 Different Manufacturer machinery usage
Interpretation:
This question is used to measure Intention, because if company have only
one manufacturer machinery then manufacturer maintenance services are
better option and do not easily purchase Maintenance agency services.
Based on responces around 91.25 % companies in Baroda are using
machinery of different manufacture and 8.75 % companies in Baroda are
using machinery of same different manufacture.
91.25%
8.75%
0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
70.00%
80.00%
90.00%
100.00%
Yes No
55
Q-7: Do you have maintenance department in your company?
Table 5.14 Maintenance Department Inquiry
Particulars Frequency
Yes 55
No 345
Fig 5.13 Maintenance Department Inquiry
Interpretation:
This question is used to measure Intention, because if company have own
maintenance department then company do not easily purchase Maintenance
agency services. Based on responces around 13.75 % companies in Baroda
have own maintenance department and 86.25 % companies in Baroda do not
have own maintenance department which are prospected target at initial
stage.
13.75%
86.25%
0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
70.00%
80.00%
90.00%
100.00%
Yes No
56
If Yes then your maintenance department,
Table 5.15 Maintenance Department Ability
Particulars Frequency
Within specific time solve all maintenance problems 36
Take more time to solve all maintenance problems 11
Don’t able to solve all maintenance problems 8
Fig 5.14 Maintenance Department Ability
Interpretation:
This question is used to measure Intention of company having maintenance
department, because if company having own maintenance department but do
not satisfied with their maintenance department then posibility they will
purchase Maintenance agency services. Out of 55 companies which having
maintenance department around 65.45 % maintenance department within
specific time solve all maintenance problems; 20 % maintenance department
take more time to solve all maintenance problems and 14.55 % maintenance
department don’t able to solve all maintenance problems. So all companies
which have maintenance deparetment which take more time to solve all
maintenance problems and don’t able to solve all maintenance problems are
also prospected target at initial stage.
65.45%
20%
14.55%
0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
70.00%
Within specific time solve all
maintenanceproblems
Take more time to solve all
maintenanceproblems
Don’t able to solve all
maintenanceproblems
57
How many man powers in your maintenance department?
Table 5.16 Maintenance Department Man power
Particulars Only
Permanent
Both Permanent
and Contract
Only
Contract
Less than 5 39 12 0
Between 5 to 10 0 0 4
Fig 5.15 Maintenance Department Man power
Interpretation:
This question is used to measure Intention of company having maintenance
department, because if company having own maintenance department but
required more man power and having more man power also dont able to
solve company maintenance problem effectivly then they they will purchase
Maintenance agency services. Out of 55 companies which having
maintenance department around 70.91 % maintenance department have only
parmenent maintenance employess in quantity of less than 5; 7.27 %
maintenance department have both parmenent and contract based
maintenance employess in quantity of less than 5 each and 81.82 %
maintenance department have only contract based maintenance employess
in quantity between 5 to 10.
70.91%
7.27%
00 0
81.82%
0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
70.00%
80.00%
90.00%
Only Permanent Both Permanent and
Contract
Only Contract
Less than 5 Between 5 to 10
58
Q-8: Are you aware about other maintenance agency?
Table 5.17 Awareness of other Maintenance agency
Particulars Frequency
Yes 400
No 0
Fig 5.16 Awareness of other Maintenance agency
Interpretation:
This question is used to measure Intention, because if company is aware
about other maintenance agency then might be company is using that other
maintenance agency services means manufacturer maintenance services
then company do not easily purchase Maintenance agency services unless
find more benefit in it. Based on responces of 400 companies all 100 %
companies in Baroda are aware about other maintenance agency, so they
can purchase Maintenance agency services if Maintenance agency is able to
provide extra benefit.
100%
0%
0%
20%
40%
60%
80%
100%
120%
Yes No
59
If Yes then are you having annual maintenance contract?
Table 5.18 Other Maintenance agency AMC
Particulars Frequency
Yes 64
No 336
Fig 5.17 Other Maintenance agency AMC
Interpretation:
This question is used to measure Intention, because if company have annual
maintenance contact of other maintenance agency means manufacturer
maintenance contract then company do not able to purchase Maintenance
agency services at initial basis and if company is satisfied with that contract
then company dont purchase Maintenance agency services in future also.
Based on responces around 16 % companies in Baroda have annual
maintenance contract of other maintenance agency and 84 % companies in
Baroda do not have annual maintenance contract of other maintenance
agency. So companies which do not have AMC are prospected target at initial
stage and companies which dissatisfied with current AMC are prospected
target for Maintenance Agency.
16%
84%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
Yes No
60
Q-9: Do your most of the machinery come under warranty
period?
Table 5.19 Machinery warranty period Inquiry
Particulars Frequency
Yes 64
No 336
Fig 5.18 Machinery warranty period Inquiry
Interpretation:
This question is used to measure Intention, because if company machinery
come under warrenty period then company use manufacturer maintenance
services and do not purchase Maintenance agency servies at initial stage.
Based on responces around 3 % companies in Baroda having machinery
which come under warrenty periods and 97 % companies in Baroda do not
having machinery which come under warrenty periods which are prospected
target for Maintenance Agency.
3%
97%
0%
20%
40%
60%
80%
100%
120%
Yes No
61
Q-10: Likert Scale Analysis,
Statement 1: Company is satisfied with current maintenance practice.
Table 5.20 Likert Scale: Statement 1
Particulars Frequency Mean
Strongly Disagree 0
3.03
Disagree 144
Neutral 104
Agree 148
Strongly Agree 4
Fig 5.19 Likert Scale: Statement 1
Interpretation:
This question is used to measure Intention, Based on responces, Companies
in Baroda are neutral with the statement ‘Company is satisfied with current
maintenance practice.’ because their response mean is 3.03; Where 37 %
Companies are agree with this statement and 36 % Companies are disagree
with this statement.
0%
36%
26%
37%
1%
0%
5%
10%
15%
20%
25%
30%
35%
40%
SD D N A SA
62
Statement 2: Company is planning to improve its maintenance practices.
Table 5.21 Likert Scale: Statement 2
Particulars Frequency Mean
Strongly Disagree 0
3.87
Disagree 4
Neutral 60
Agree 320
Strongly Agree 16
Table 5.20 Likert Scale: Statement 2
Interpretation:
This question is used to measure Intention, Based on responces, Companies
in Baroda are agree with the statement ‘Company is planning to improve its
maintenance practices.’ because their response mean is 3.87; Where 87 %
Companies are agree with this statement.
0% 1%
15%
80%
4%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
SD D N A SA
63
Statement 3: Company machine manufacturer provides excellent
maintenance services.
Table 5.22 Likert Scale: Statement 3
Particulars Frequency Mean
Strongly Disagree 0
3.14
Disagree 75
Neutral 197
Agree 124
Strongly Agree 4
Fig 5.21 Likert Scale: Statement 3
Interpretation:
This question is used to measure Interest, Based on responces, Companies
in Baroda are neutral with the statement ‘Company machine manufacturer
provides excellent maintenance services.’ because their response mean is
3.14; Where 31 % Companies are agree with this statement.
0%
19%
49%
31%
1%
0%
10%
20%
30%
40%
50%
60%
SD D N A SA
64
Statement 4: Company is paying reasonable price to current maintenance
agency for servicing machinery.
Table 5.23 Likert Scale: Statement 4
Particulars Frequency Mean
Strongly Disagree 0
3.46
Disagree 24
Neutral 168
Agree 198
Strongly Agree 8
Fig 5.22 Likert Scale: Statement 4
Interpretation:
This question is used to measure Interest, Based on responces, Companies
in Baroda are neutral with the statement ‘Company is paying reasonable price
to current maintenance agency for servicing machinery.’ because their
response mean is 3.46; Where 49 % Companies are agree with this
statement.
1%
6%
42%
49%
2%
0%
10%
20%
30%
40%
50%
60%
SD D N A SA
65
Statement 5: Breakdown leads to shutdown in your company.
Table 5.24 Likert Scale: Statement 5
Particulars Frequency Mean
Strongly Disagree 8
3.05
Disagree 151
Neutral 80
Agree 133
Strongly Agree 28
Fig 5.23 Likert Scale: Statement 5
Interpretation:
This question is used to measure Interest, Based on responces, Companies
in Baroda are neutral with the statement ‘Breakdown leads to shutdown in
your company.’ because their response mean is 3.05; Where 33 %
Companies are agree with this statement and 38 % Companies are disagree
with this statement.
2%
38%
20%
33%
7%
0%
5%
10%
15%
20%
25%
30%
35%
40%
SD D N A SA
66
Statement 6: For Company, prevention of breakdown is important aspect.
Table 5.25 Likert Scale: Statement 6
Particulars Frequency Mean
Strongly Disagree 0
4.12
Disagree 4
Neutral 24
Agree 292
Strongly Agree 80
Fig 5.24 Likert Scale: Statement 6
Interpretation:
This question is used to measure Interest, Based on responces, Companies
in Baroda are agree with the statement ‘For Company, prevention of
breakdown is important aspect.’ because their response mean is 4.12; Where
73 % Companies are agree with this statement and 20 % Companies are
strongly agree with this statement.
0% 1%
6%
73%
20%
0%
10%
20%
30%
40%
50%
60%
70%
80%
SD D N A SA
67
Statement 7: Maintenance agency should provide all maintenance services
under one roof.
Table 5.26 Likert Scale: Statement 7
Particulars Frequency Mean
Strongly Disagree 0
4.22
Disagree 4
Neutral 28
Agree 241
Strongly Agree 127
Table 5.25 Likert Scale: Statement 7
Interpretation:
This question is used to measure Interest, Based on responces, Companies
in Baroda are agree with the statement ‘Maintenance agency should provide
all maintenance services under one roof.’ because their response mean is
4.22; Where 60 % Companies are agree with this statement and 32 %
Companies are strongly agree with this statement.
0% 1%
7%
60%
32%
0%
10%
20%
30%
40%
50%
60%
70%
SD D N A SA
68
Statement 8: Maintenance agency should provide 24x7 maintenance
services.
Table 5.27 Likert Scale: Statement 8
Particulars Frequency Mean
Strongly Disagree 0
4.16
Disagree 4
Neutral 52
Agree 222
Strongly Agree 122
Fig 5.26 Likert Scale: Statement 8
Interpretation:
This question is used to measure Interest, Based on responces, Companies
in Baroda are agree with the statement ‘Maintenance agency should provide
24x7 maintenance services.’ because their response mean is 4.16; Where 56
% Companies are agree with this statement and 30 % Companies are
strongly agree with this statement.
0% 1%
13%
56%
30%
0%
10%
20%
30%
40%
50%
60%
SD D N A SA
69
Statement 9: Maintenance agency should provide installment payment option.
Table 5.28 Likert Scale: Statement 9
Particulars Frequency Mean
Strongly Disagree 0
4.04
Disagree 8
Neutral 68
Agree 225
Strongly Agree 99
Fig 5.27 Likert Scale: Statement 9
Interpretation:
This question is used to measure Interest, Based on responces, Companies
in Baroda are agree with the statement ‘Maintenance agency should provide
installment payment option.’ because their response mean is 4.04; Where 56
% Companies are agree with this statement and 25 % Companies are
strongly agree with this statement.
0%
2%
17%
56%
25%
0%
10%
20%
30%
40%
50%
60%
SD D N A SA
70
Statement 10: Maintenance agency should visit regularly every month either
breakdown or not, in an organization.
Table 5.29 Likert Scale: Statement 10
Particulars Frequency Mean
Strongly Disagree 0
3.88
Disagree 4
Neutral 80
Agree 276
Strongly Agree 40
Fig 5.28 Likert Scale: Statement 10
Interpretation:
This question is used to measure Interest, Based on responces, Companies
in Baroda are agree with the statement ‘Maintenance agency should visit
regularly every month either breakdown or not, in an organization.’ because
their response mean is 3.88; Where 69 % Companies are agree with this
statement.
0% 1%
20%
69%
10%
0%
10%
20%
30%
40%
50%
60%
70%
80%
SD D N A SA
71
Statement 11: Maintenance agency has more expertise in comparison to
internal maintenance department.
Table 5.30 Likert Scale: Statement 11
Particulars Frequency Mean
Strongly Disagree 0
3.94
Disagree 4
Neutral 60
Agree 292
Strongly Agree 44
Fig 5.29 Likert Scale: Statement 11
Interpretation:
This question is used to measure Perception, Based on responces,
Companies in Baroda are agree with the statement ‘Maintenance agency has
more expertise in comparison to internal maintenance department.’ because
their response mean is 3.94; Where 73 % Companies are agree with this
statement.
0% 1%
15%
73%
11%
0%
10%
20%
30%
40%
50%
60%
70%
80%
SD D N A SA
72
Statement 12: Maintenance agency is able to solve maintenance problem in
different no. of ways.
Table 5.31 Likert Scale: Statement 12
Particulars Frequency Mean
Strongly Disagree 0
3.87
Disagree 0
Neutral 76
Agree 300
Strongly Agree 24
Fig 5.30 Likert Scale: Statement 12
Interpretation:
This question is used to measure Perception, Based on responces,
Companies in Baroda are agree with the statement ‘Maintenance agency is
able to solve maintenance problem in different no. of ways.’ because their
response mean is 3.87; Where 75 % Companies are agree with this
statement.
0% 0%
19%
75%
6%
0%
10%
20%
30%
40%
50%
60%
70%
80%
SD D N A SA
73
Statement 13: Maintenance agency is economical.
Table 5.32 Likert Scale: Statement 13
Particulars Frequency Mean
Strongly Disagree 0
3.57
Disagree 4
Neutral 179
Agree 201
Strongly Agree 16
Fig 5.31 Likert Scale: Statement 13
Interpretation:
This question is used to measure Perception, Based on responces,
Companies in Baroda are agree with the statement ‘Maintenance agency is
economical.’ because their response mean is 3.57; Where 50 % Companies
are agree with this statement.
0% 1%
45%
50%
4%
0%
10%
20%
30%
40%
50%
60%
SD D N A SA
74
Statement 14: Maintenance agency is able to solve maintenance problem
quickly compare to maintenance department.
Table 5.33 Likert Scale: Statement 14
Particulars Frequency Mean
Strongly Disagree 0
3.73
Disagree 20
Neutral 91
Agree 266
Strongly Agree 23
Fig 5.32 Likert Scale: Statement 14
Interpretation:
This question is used to measure Perception, Based on responces,
Companies in Baroda are agree with the statement ‘Maintenance agency is
able to solve maintenance problem quickly compare to maintenance
department.’ because their response mean is 3.73; Where 67 % Companies
are agree with this statement.
0%
5%
22%
67%
6%
0%
10%
20%
30%
40%
50%
60%
70%
SD D N A SA
75
Statement 15: Maintenance agencies don’t response on time when required.
Table 5.34 Likert Scale: Statement 15
Particulars Frequency Mean
Strongly Disagree 0
2.9
Disagree 140
Neutral 172
Agree 76
Strongly Agree 12
Fig 5.33 Likert Scale: Statement 15
Interpretation:
This question is used to measure Perception, Based on responces,
Companies in Baroda are neutral with the statement ‘Maintenance agencies
don’t response on time when required.’ because their response mean is 2.9;
Where 19 % Companies are agree with this statement and 35 % Companies
are disagree with this statement
0%
35%
43%
19%
3%
0%
5%
10%
15%
20%
25%
30%
35%
40%
45%
50%
SD D N A SA
76
Statement 16: Maintenance agency is better option compare to internal
maintenance department.
Table 5.35 Likert Scale: Statement 16
Particulars Frequency Mean
Strongly Disagree 0
2.79
Disagree 4
Neutral 92
Agree 288
Strongly Agree 16
Fig 5.34 Likert Scale: Statement 16
Interpretation:
This question is used to measure Perception, Based on responces,
Companies in Baroda are neutral with the statement ‘Maintenance agency is
better option compare to internal maintenance department.’ because their
response mean is 2.79; Where 72 % Companies are agree with this
statement.
0% 1%
23%
72%
4%
0%
10%
20%
30%
40%
50%
60%
70%
80%
SD D N A SA
77
Statement 17: Maintenance agency is required for maintenance.
Table 5.36 Likert Scale: Statement 17
Particulars Frequency Mean
Strongly Disagree 0
3.89
Disagree 4
Neutral 64
Agree 304
Strongly Agree 28
Fig 5.35 Likert Scale: Statement 17
Interpretation:
This question is used to measure Attitude, Based on responces, Companies
in Baroda are agree with the statement ‘Maintenance agency is required for
maintenance.’ because their response mean is 3.89; Where 76 % Companies
are agree with this statement.
0% 1%
16%
76%
7%
0%
10%
20%
30%
40%
50%
60%
70%
80%
SD D N A SA
78
Q-11: Will you purchase maintenance agency services in
future?
Table 5.37 Purchase Maintenance agency services in Future
Particulars Frequency
Yes 336
No 64
Fig 5.36 Purchase Maintenance agency services in Future
Interpretation:
This question is used to measure Attitude, Based on responces around 84 %
companies in Baroda will purchase maintenance agency services in future
(Positive attitude towards Maintenance agency services) and 16 %
companies in Baroda will not purchase maintenance agency services in future
(Negative attitude towards Maintenance agency services).
84%
16%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
Yes No
Chapter 6
Hypothesis Testing
79
Hypothesis 1:
H0: Existing industries are not having positive intension towards
maintenance agency services.
H1: Existing industries are having positive intension towards
maintenance agency services.
Table 6.1 Hypothesis 1
No. Statement Mean
1
Company is satisfied with current maintenance
practice.
3.03
3.45
2
Company is planning to improve its maintenance
practices.
3.87
Fig 6.1 Hypothesis 1
Interpretation:
From above Table 6.1 and Fig. 6.1, it can be interpreted that Existing
industries are having positive intension towards maintenance agency services
(Null Hypothesis will be rejected) because Intention likert scale statement
mean is 3.45 greater than scale middle value 3.
80
Hypothesis 2:
H0: Company Intension towards Maintenance agency services is not
independent of the type of Industry and Company annual
maintenance budget.
H1: Company Intension towards Maintenance agency services is
independent of the type of Industry and Company annual
maintenance budget.
Table 6.2 Hypothesis 2 (Chi-Square Tests)
No. Statement Pearson Chi-Square
Type of Industry Annual Budget
1 Company is satisfied with
current maintenance practice.
.000 .000
2 Company is planning to improve
its maintenance practices.
.000 .000
With 15 Degree of freedom
Interpretation:
From above Table 6.3, it can be interpreted that Company Intension towards
Maintenance agency services is independent of the type of Industry and
Company annual maintenance budget. (All value of chi-square (alpha) is less
than 0.05)
81
Hypothesis 3:
H0: Company interest level towards Maintenance agency services is not
independent of the type of Industry and Company annual
maintenance budget.
H1: Company interest level towards Maintenance agency services is
independent of the type of Industry and Company annual
maintenance budget.
Table 6.3 Hypothesis 3 (Chi-Square Tests)
No. Statement Pearson Chi-Square
Type of
Industry
Annual
Budget
1
Company machine manufacturer provides excellent
maintenance services.
.000 .000
2
Company is paying reasonable price to current
maintenance agency for servicing machinery.
.000 .000
3 Breakdown leads to shutdown in your company. .000 .000
4
For Company, prevention of breakdown is important
aspect.
.000 .002
5
Maintenance agency should provide all maintenance
services under one roof.
.000 .001
6
Maintenance agency should provide 24x7
maintenance services.
.000 .000
7
Maintenance agency should provide installment
payment option.
.000 .000
8
Maintenance agency should visit regularly every
month either breakdown or not, in an organization.
.000 .000
Interpretation:
From above Table 6.3, it can be interpreted that Company interest level
towards Maintenance agency services is independent of the type of Industry
and Company annual maintenance budget. (All value of chi-square (alpha) is
less than 0.05)
82
Hypothesis 4:
H0: Existing industries are not interested in services provided by
maintenance agency.
H1: Existing industries are interested in services provided by
maintenance agency.
Table 6.4 Hypothesis 4
No. Statement Mean
1
Company machine manufacturer provides excellent
maintenance services.
3.14
3.76
2
Company is paying reasonable price to current maintenance
agency for servicing machinery.
3.46
3 Breakdown leads to shutdown in your company. 3.05
4 For Company, prevention of breakdown is important aspect. 4.12
5
Maintenance agency should provide all maintenance services
under one roof.
4.22
6
Maintenance agency should provide 24x7 maintenance
services.
4.15
7
Maintenance agency should provide installment payment
option.
4.03
8
Maintenance agency should visit regularly every month either
breakdown or not, in an organization.
3.88
Interpretation:
From above Table 6.3 and Fig. 6.2, it can be interpreted that Existing
industries are interested in services provided by maintenance agency (Null
Hypothesis will be rejected) because Interest likert scale statement mean is
3.76 greater than scale middle value 3.
83
Fig 6.2 Hypothesis 4
Fig 6.3 Hypothesis 5
84
Hypothesis 5:
H0: Existing industries are not having good perception towards
maintenance agency.
H1: Existing industries are having good perception towards maintenance
agency.
Table 6.5 Hypothesis 5
No. Statement Mean
1
Maintenance agency has more expertise in comparison to
internal maintenance department
3.94
3.63
2
Maintenance agency is able to solve maintenance problem in
different no. of ways.
3.87
3 Maintenance agency is economical. 3.57
4
Maintenance agency is able to solve maintenance problem
quickly compare to maintenance department.
3.73
5 Maintenance agencies don’t response on time when required. 2.90
6
Maintenance agency is better option compare to internal
maintenance department.
3.79
Interpretation:
From above Table 6.5 and Fig. 6.3, it can be interpreted that Existing
industries are having good perception towards maintenance agency. (Null
Hypothesis will be rejected) because Interest likert scale statement mean is
3.63 greater than scale middle value 3.
85
Hypothesis 6:
H0: Company Perception towards Maintenance Agency is not
independent of the type of Industry and Company annual
maintenance budget.
H1: Company Perception towards Maintenance Agency is independent
of the type of Industry and Company annual maintenance budget.
Table 6.6 Hypothesis 6 (Chi-Square Tests)
No. Statement Pearson Chi-Square
Type of
Industry
Annual
Budget
1
Maintenance agency has more expertise in
comparison to internal maintenance department
.000 .000
2
Maintenance agency is able to solve maintenance
problem in different no. of ways.
.000 .004
3 Maintenance agency is economical. .004 .000
4
Maintenance agency is able to solve maintenance
problem quickly compare to maintenance department.
.000 .001
5
Maintenance agencies don’t response on time when
required.
.000 .000
6
Maintenance agency is better option compare to
internal maintenance department.
.000 .000
Interpretation:
From above Table 6.6, it can be interpreted that Company interest level
towards Maintenance agency services is independent of the type of Industry
and Company annual maintenance budget. (All value of chi-square (alpha) is
less than 0.05)
86
Hypothesis 7:
H0: There is no significant difference among type of Industry or company
annual maintenance budget regarding decision of purchasing
maintenance agency services.
H1: There is significant difference among type of Industry or company
annual maintenance budget regarding decision of purchasing
maintenance agency services.
Table 6.7 Hypothesis 7 (One way Anova)
Sum of
Squares df
Mean
Square F Sig.
Type of Industry
Between Groups 1.543 5 .309 2.329 .042
Within Groups 52.217 394 .133
Total 53.760 399
Company annual maintenance budget
Between Groups 1.375 5 .275 2.069 .068
Within Groups 52.385 394 .133
Total 53.760 399
Interpretation:
From above Table 6.7, Null hypotheses will be rejected for Type of Industry
and it can be interpreted that there is significant difference among type of
Industry regarding decision of purchasing maintenance agency services. (For
Type of Industry value of significant is less than 0.05)
From above Table 6.7, Null hypotheses will not be rejected for Company
annual maintenance budget and it can be interpreted that there is no
significant difference among company annual maintenance budget regarding
decision of purchasing maintenance agency services. (For Company annual
maintenance budget value of significant is greater than 0.05)
87
Hypothesis 8:
H0: Existing industries are not purchased services provided by
maintenance agency.
H1: Existing industries are purchased services provided by maintenance
agency.
Table 6.8 Hypothesis 8
No. Statement Mean
1 Maintenance agency is required for maintenance. 3.89
Fig 6.4 Hypothesis 8
Interpretation:
From above Table 6.8, Fig. 6.4, and Fig. 5.36 where Based on responces
around 84 % companies in Baroda will purchase maintenance agency
services in future (Positive attitude towards Maintenance agency services), it
can be interpreted that Existing industries are purchased services provided by
maintenance agency (Null Hypothesis will be rejected) because Interest likert
scale statement mean is 3.89 greater than scale middle value 3.
Chapter 7
Maintenance agency Profitability and Feasibility
Analysis
88
7.1. Cost of Project
7.1.1. Fixed Investment Cost requirement for next 3 Years
Table 7.1 Fixed Investment Cost requirement for next 3 Years
All Amount in Rs.
1 Year 2 Year 3 Year
unit Rs. Unit Rs. Unit Rs.
Shop Deposit - 50000 - - - -
Website
charges
- 15000 - - - -
Toolbox 3 15000 - - 1 5000
Hand Drill 3 10000 - - 1 3000
Welding
Machine
3 26500 - - 1 6000
Grinder/cutter 3 6000 - - 1000
Hacksaw 3 6000 - - 1 2000
Computer 1 22000 - - - -
Printer 1 4500 - - - -
Shop Furniture/
chairs
- 30000 - - - -
Vehicles
Tata Chhota
Hathi
2 560000 - - 1 280000
Cycle 1 1500 - - 1 1500
Total 746500 - 298000
To start any business initial amount is required for investment and to start
maintenance agency as shown in Table 7.1 initially Rs. 746500 is required as
fixed initial cost. During second year other investment is not required but
during 3 year to match demand rate investment is required in equipments and
vehicles around Rs. 298000.
89
7.1.2. Variable Cost requirement for next 3 Years
Table 7.2 Variable Cost requirement for next 3 Years
All Amount in Rs.
1 Year
Monthly
Cost
1 Year 2 Year
Monthly
Cost
2 Year 3 Year
Monthly
Cost
3 Year
Shop Rent 5000 60000 5500 66000 6000 72000
Petrol/ Diesel 8000 96000 10000 120000 15000 180000
Electricity Bill 2500 30000 2500 30000 2500 3000
Telephone Bill 3000 36000 3000 36000 4000 48000
Stationary Cost 500 6000 700 8400 1000 12000
Hand drill - - - 1000 - -
Welding Machine - - - 1000 - -
Grinder/cutter - - - 500 - 1000
Employee Salary
Diploma
Mechanical
>15 yr
experience
38500 462000 40500 486000 43500 522000
>1 yr
experience
5000 60000 6000 72000 8000 96000
>1 yr
experience
- - - - 5000 60000
Diploma electrical
>2 yr
experience
6000 72000 7000 84000 9000 108000
>2 yr
experience
- - - - 6000 72000
Computer
operator
4500 54000 5500 66000 6500 78000
Telephone
operator
4500 54000 5500 66000 6500 78000
Feasibility of Maintenance Agency in Baroda
Feasibility of Maintenance Agency in Baroda
Feasibility of Maintenance Agency in Baroda
Feasibility of Maintenance Agency in Baroda
Feasibility of Maintenance Agency in Baroda
Feasibility of Maintenance Agency in Baroda
Feasibility of Maintenance Agency in Baroda
Feasibility of Maintenance Agency in Baroda
Feasibility of Maintenance Agency in Baroda
Feasibility of Maintenance Agency in Baroda
Feasibility of Maintenance Agency in Baroda
Feasibility of Maintenance Agency in Baroda
Feasibility of Maintenance Agency in Baroda
Feasibility of Maintenance Agency in Baroda
Feasibility of Maintenance Agency in Baroda
Feasibility of Maintenance Agency in Baroda
Feasibility of Maintenance Agency in Baroda
Feasibility of Maintenance Agency in Baroda
Feasibility of Maintenance Agency in Baroda
Feasibility of Maintenance Agency in Baroda

More Related Content

What's hot

Introduction to Scrum.ppt
Introduction to Scrum.pptIntroduction to Scrum.ppt
Introduction to Scrum.ppt
Mohan Late
 
Project Report on Study Of BPO HR Consultancy
Project Report on Study Of BPO HR ConsultancyProject Report on Study Of BPO HR Consultancy
Project Report on Study Of BPO HR Consultancy
Kumari Swati
 
PMI-ACP Lesson 01 Nugget 2 Agile Methodologies-ii
PMI-ACP Lesson 01 Nugget 2 Agile Methodologies-iiPMI-ACP Lesson 01 Nugget 2 Agile Methodologies-ii
PMI-ACP Lesson 01 Nugget 2 Agile Methodologies-ii
Thanh Nguyen
 
vishnu internship Project
vishnu internship Projectvishnu internship Project
vishnu internship Project
vishnu singh
 
User stories in agile software development
User stories in agile software developmentUser stories in agile software development
User stories in agile software development
Sandra Svanidzaitė, PhD, CBAP
 
Dlf2
Dlf2Dlf2
Dlf2
ANANDU KB
 
INTERNSHIP REPORT ON BIRLA SUNLIFE
INTERNSHIP REPORT ON BIRLA SUNLIFEINTERNSHIP REPORT ON BIRLA SUNLIFE
INTERNSHIP REPORT ON BIRLA SUNLIFE
ANSHU SINGH
 
Summer internship taining project report kotak life insurance
Summer internship taining project report   kotak life insuranceSummer internship taining project report   kotak life insurance
Summer internship taining project report kotak life insurance
Shubham Aggarwal
 
Sip report
Sip reportSip report
Sip report
pp1990
 
A study on reward and recognition program 2016
A study on reward and recognition program  2016A study on reward and recognition program  2016
A study on reward and recognition program 2016
Anand Yogesh
 
Introduction to Agile Software Development
Introduction to Agile Software DevelopmentIntroduction to Agile Software Development
Introduction to Agile Software Development
Life Cycle Engineering
 
Atlassian jira как полностью раскрыть возможности
Atlassian jira   как полностью раскрыть возможностиAtlassian jira   как полностью раскрыть возможности
Atlassian jira как полностью раскрыть возможности
Andrew Fadeev
 
Effective user stories for your agile or Scrum team
Effective user stories for your agile or Scrum teamEffective user stories for your agile or Scrum team
Effective user stories for your agile or Scrum team
DigitalCatapultDevelopmentPractices
 
What is a user story?
What is a user story?What is a user story?
What is a user story?
Lean Apps
 
Summer training project for finance
Summer training project for financeSummer training project for finance
Summer training project for finance
jaiswal123456789
 
Blue print of HDFC bank.pptx
Blue print of HDFC bank.pptxBlue print of HDFC bank.pptx
Blue print of HDFC bank.pptx
JawedKhan41
 
Kotak life insurance Project Report
Kotak life insurance Project ReportKotak life insurance Project Report
Kotak life insurance Project Report
Abhishek Keshri
 
Story of user story
Story of user storyStory of user story
Story of user story
Balaji Sathram
 
Businese research project on mobile shops
Businese research project on mobile shopsBusinese research project on mobile shops
Businese research project on mobile shops
MOHD ARISH
 
Internship Report _ Akhilesh Kr Vasisht
Internship Report _ Akhilesh Kr VasishtInternship Report _ Akhilesh Kr Vasisht
Internship Report _ Akhilesh Kr Vasisht
Akhilesh Vasisht
 

What's hot (20)

Introduction to Scrum.ppt
Introduction to Scrum.pptIntroduction to Scrum.ppt
Introduction to Scrum.ppt
 
Project Report on Study Of BPO HR Consultancy
Project Report on Study Of BPO HR ConsultancyProject Report on Study Of BPO HR Consultancy
Project Report on Study Of BPO HR Consultancy
 
PMI-ACP Lesson 01 Nugget 2 Agile Methodologies-ii
PMI-ACP Lesson 01 Nugget 2 Agile Methodologies-iiPMI-ACP Lesson 01 Nugget 2 Agile Methodologies-ii
PMI-ACP Lesson 01 Nugget 2 Agile Methodologies-ii
 
vishnu internship Project
vishnu internship Projectvishnu internship Project
vishnu internship Project
 
User stories in agile software development
User stories in agile software developmentUser stories in agile software development
User stories in agile software development
 
Dlf2
Dlf2Dlf2
Dlf2
 
INTERNSHIP REPORT ON BIRLA SUNLIFE
INTERNSHIP REPORT ON BIRLA SUNLIFEINTERNSHIP REPORT ON BIRLA SUNLIFE
INTERNSHIP REPORT ON BIRLA SUNLIFE
 
Summer internship taining project report kotak life insurance
Summer internship taining project report   kotak life insuranceSummer internship taining project report   kotak life insurance
Summer internship taining project report kotak life insurance
 
Sip report
Sip reportSip report
Sip report
 
A study on reward and recognition program 2016
A study on reward and recognition program  2016A study on reward and recognition program  2016
A study on reward and recognition program 2016
 
Introduction to Agile Software Development
Introduction to Agile Software DevelopmentIntroduction to Agile Software Development
Introduction to Agile Software Development
 
Atlassian jira как полностью раскрыть возможности
Atlassian jira   как полностью раскрыть возможностиAtlassian jira   как полностью раскрыть возможности
Atlassian jira как полностью раскрыть возможности
 
Effective user stories for your agile or Scrum team
Effective user stories for your agile or Scrum teamEffective user stories for your agile or Scrum team
Effective user stories for your agile or Scrum team
 
What is a user story?
What is a user story?What is a user story?
What is a user story?
 
Summer training project for finance
Summer training project for financeSummer training project for finance
Summer training project for finance
 
Blue print of HDFC bank.pptx
Blue print of HDFC bank.pptxBlue print of HDFC bank.pptx
Blue print of HDFC bank.pptx
 
Kotak life insurance Project Report
Kotak life insurance Project ReportKotak life insurance Project Report
Kotak life insurance Project Report
 
Story of user story
Story of user storyStory of user story
Story of user story
 
Businese research project on mobile shops
Businese research project on mobile shopsBusinese research project on mobile shops
Businese research project on mobile shops
 
Internship Report _ Akhilesh Kr Vasisht
Internship Report _ Akhilesh Kr VasishtInternship Report _ Akhilesh Kr Vasisht
Internship Report _ Akhilesh Kr Vasisht
 

Viewers also liked

Feasibility Study (Water Refilling Station)
Feasibility Study (Water Refilling Station)Feasibility Study (Water Refilling Station)
Feasibility Study (Water Refilling Station)
Darlene Enderez
 
Feasibility Study (Veggie Bread)
Feasibility Study (Veggie Bread)Feasibility Study (Veggie Bread)
Feasibility Study (Veggie Bread)
Bryan Agustin Oculam
 
Feasibility Study on the Use of Mobile Positioning Data in Tourism Statistics...
Feasibility Study on the Use of Mobile Positioning Data in Tourism Statistics...Feasibility Study on the Use of Mobile Positioning Data in Tourism Statistics...
Feasibility Study on the Use of Mobile Positioning Data in Tourism Statistics...
Tilastokeskus
 
Summary Of Uptown Feasibility Study
Summary Of Uptown Feasibility StudySummary Of Uptown Feasibility Study
Summary Of Uptown Feasibility Study
cmc128
 
Srs
SrsSrs
Feasibility study for Tourist Destination and Attraction
Feasibility study for Tourist Destination and AttractionFeasibility study for Tourist Destination and Attraction
Feasibility study for Tourist Destination and Attraction
Widodo Heru Santoso
 
0601043 feasibility study for diversification & market survey
0601043 feasibility study for diversification & market survey0601043 feasibility study for diversification & market survey
0601043 feasibility study for diversification & market survey
Supa Buoy
 
Acknowledgement
AcknowledgementAcknowledgement
Acknowledgement
ferdzzz
 
Feasibility Study Product Proposals
Feasibility Study Product ProposalsFeasibility Study Product Proposals
Feasibility Study Product Proposals
Bryan Agustin Oculam
 
Madcom offers a Broadband Feasibility Study Toolkit for Municipalities and Ec...
Madcom offers a Broadband Feasibility Study Toolkit for Municipalities and Ec...Madcom offers a Broadband Feasibility Study Toolkit for Municipalities and Ec...
Madcom offers a Broadband Feasibility Study Toolkit for Municipalities and Ec...
Rich Frank
 
SYNOPSIS ON BANK MANAGEMENT SYSTEM
SYNOPSIS ON BANK MANAGEMENT SYSTEMSYNOPSIS ON BANK MANAGEMENT SYSTEM
SYNOPSIS ON BANK MANAGEMENT SYSTEM
Nitish Xavier Tirkey
 
Feasibility Study- Bakery
Feasibility Study- BakeryFeasibility Study- Bakery
Feasibility Study- Bakery
sakurashu28
 
Feasibility Study
Feasibility StudyFeasibility Study
Feasibility Study
Centro Escolar University
 
Feasibility report -basic concepts with example
Feasibility report -basic concepts with exampleFeasibility report -basic concepts with example
Feasibility report -basic concepts with example
Abhijeet Bhosale
 
Library Management System
Library Management SystemLibrary Management System
Library Management System
Aditya Shah
 
Project planning and feasibility study
Project planning and feasibility studyProject planning and feasibility study
Project planning and feasibility study
Mars Mfyam
 

Viewers also liked (16)

Feasibility Study (Water Refilling Station)
Feasibility Study (Water Refilling Station)Feasibility Study (Water Refilling Station)
Feasibility Study (Water Refilling Station)
 
Feasibility Study (Veggie Bread)
Feasibility Study (Veggie Bread)Feasibility Study (Veggie Bread)
Feasibility Study (Veggie Bread)
 
Feasibility Study on the Use of Mobile Positioning Data in Tourism Statistics...
Feasibility Study on the Use of Mobile Positioning Data in Tourism Statistics...Feasibility Study on the Use of Mobile Positioning Data in Tourism Statistics...
Feasibility Study on the Use of Mobile Positioning Data in Tourism Statistics...
 
Summary Of Uptown Feasibility Study
Summary Of Uptown Feasibility StudySummary Of Uptown Feasibility Study
Summary Of Uptown Feasibility Study
 
Srs
SrsSrs
Srs
 
Feasibility study for Tourist Destination and Attraction
Feasibility study for Tourist Destination and AttractionFeasibility study for Tourist Destination and Attraction
Feasibility study for Tourist Destination and Attraction
 
0601043 feasibility study for diversification & market survey
0601043 feasibility study for diversification & market survey0601043 feasibility study for diversification & market survey
0601043 feasibility study for diversification & market survey
 
Acknowledgement
AcknowledgementAcknowledgement
Acknowledgement
 
Feasibility Study Product Proposals
Feasibility Study Product ProposalsFeasibility Study Product Proposals
Feasibility Study Product Proposals
 
Madcom offers a Broadband Feasibility Study Toolkit for Municipalities and Ec...
Madcom offers a Broadband Feasibility Study Toolkit for Municipalities and Ec...Madcom offers a Broadband Feasibility Study Toolkit for Municipalities and Ec...
Madcom offers a Broadband Feasibility Study Toolkit for Municipalities and Ec...
 
SYNOPSIS ON BANK MANAGEMENT SYSTEM
SYNOPSIS ON BANK MANAGEMENT SYSTEMSYNOPSIS ON BANK MANAGEMENT SYSTEM
SYNOPSIS ON BANK MANAGEMENT SYSTEM
 
Feasibility Study- Bakery
Feasibility Study- BakeryFeasibility Study- Bakery
Feasibility Study- Bakery
 
Feasibility Study
Feasibility StudyFeasibility Study
Feasibility Study
 
Feasibility report -basic concepts with example
Feasibility report -basic concepts with exampleFeasibility report -basic concepts with example
Feasibility report -basic concepts with example
 
Library Management System
Library Management SystemLibrary Management System
Library Management System
 
Project planning and feasibility study
Project planning and feasibility studyProject planning and feasibility study
Project planning and feasibility study
 

Similar to Feasibility of Maintenance Agency in Baroda

FINAL PROJECT-MBA
FINAL PROJECT-MBAFINAL PROJECT-MBA
FINAL PROJECT-MBA
Abhineet Bhardwaj
 
IRJET- Optimization of Cycle Time by using Various Techniques: A Review
IRJET- Optimization of Cycle Time by using Various Techniques: A ReviewIRJET- Optimization of Cycle Time by using Various Techniques: A Review
IRJET- Optimization of Cycle Time by using Various Techniques: A Review
IRJET Journal
 
Maintenance system, inspections & audits
Maintenance system, inspections & auditsMaintenance system, inspections & audits
Maintenance system, inspections & audits
Neeraj Kumar
 
Working of depository system in india with research and analysis by hiresh ah...
Working of depository system in india with research and analysis by hiresh ah...Working of depository system in india with research and analysis by hiresh ah...
Working of depository system in india with research and analysis by hiresh ah...
333jack333
 
Application of industrial engineering in garments sewing floor
Application of industrial engineering in garments sewing floorApplication of industrial engineering in garments sewing floor
Application of industrial engineering in garments sewing floor
Rakibul Hasan
 
Evolution of maintenance_practices
Evolution of maintenance_practicesEvolution of maintenance_practices
Evolution of maintenance_practices
Danny Khudu
 
Analysis and optimization of maintenances management of instruments
Analysis and optimization of maintenances management of instrumentsAnalysis and optimization of maintenances management of instruments
Analysis and optimization of maintenances management of instruments
Projects Kart
 
Maintenance
MaintenanceMaintenance
Maintenance
Rachmat Sudrajat
 
Subham Internship
Subham InternshipSubham Internship
Subham Internship
Subham Chauhan
 
IRJET- Enhance the Capacity of Outer Tube Machining Cell
IRJET-  	  Enhance the Capacity of Outer Tube Machining CellIRJET-  	  Enhance the Capacity of Outer Tube Machining Cell
IRJET- Enhance the Capacity of Outer Tube Machining Cell
IRJET Journal
 
Petrol on wheels
Petrol on wheelsPetrol on wheels
Petrol on wheels
Sthitaprajna Das
 
Root Cause Failure Analysis by Eugene Cottle-Lifecycle Engineering
Root Cause Failure Analysis by Eugene Cottle-Lifecycle EngineeringRoot Cause Failure Analysis by Eugene Cottle-Lifecycle Engineering
Root Cause Failure Analysis by Eugene Cottle-Lifecycle Engineering
Abdulrahman Alkhowaiter
 
Gis on vikash industry
Gis on  vikash industryGis on  vikash industry
Gis on vikash industry
Saurabh Kumar
 
Prioritised Engineering Design Requirements of Gas Turbine Engine by QFD
Prioritised Engineering Design Requirements of Gas Turbine Engine by QFDPrioritised Engineering Design Requirements of Gas Turbine Engine by QFD
Prioritised Engineering Design Requirements of Gas Turbine Engine by QFD
IRJET Journal
 
2019 Caterpillar Mining Equipment Management Metrics Document V4.pdf
2019 Caterpillar Mining Equipment Management Metrics Document V4.pdf2019 Caterpillar Mining Equipment Management Metrics Document V4.pdf
2019 Caterpillar Mining Equipment Management Metrics Document V4.pdf
AlexanderRamos482228
 
IRJET- A Holistic Review of the Elements and the Tools of Lean Manufacturing
IRJET- A Holistic Review of the Elements and the Tools of Lean ManufacturingIRJET- A Holistic Review of the Elements and the Tools of Lean Manufacturing
IRJET- A Holistic Review of the Elements and the Tools of Lean Manufacturing
IRJET Journal
 
The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...
The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...
The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...
ijsrd.com
 
A Guide to Partnering with Industrial Lubrication Experts
A Guide to Partnering with Industrial Lubrication ExpertsA Guide to Partnering with Industrial Lubrication Experts
A Guide to Partnering with Industrial Lubrication Experts
Angela Morrow
 
Procedure Based Maintenance
Procedure Based MaintenanceProcedure Based Maintenance
Procedure Based Maintenance
Ricky Smith CMRP, CMRT
 
Procedure Based Maintenance White Paper
Procedure Based Maintenance White PaperProcedure Based Maintenance White Paper
Procedure Based Maintenance White Paper
Ricky Smith CMRP, CMRT
 

Similar to Feasibility of Maintenance Agency in Baroda (20)

FINAL PROJECT-MBA
FINAL PROJECT-MBAFINAL PROJECT-MBA
FINAL PROJECT-MBA
 
IRJET- Optimization of Cycle Time by using Various Techniques: A Review
IRJET- Optimization of Cycle Time by using Various Techniques: A ReviewIRJET- Optimization of Cycle Time by using Various Techniques: A Review
IRJET- Optimization of Cycle Time by using Various Techniques: A Review
 
Maintenance system, inspections & audits
Maintenance system, inspections & auditsMaintenance system, inspections & audits
Maintenance system, inspections & audits
 
Working of depository system in india with research and analysis by hiresh ah...
Working of depository system in india with research and analysis by hiresh ah...Working of depository system in india with research and analysis by hiresh ah...
Working of depository system in india with research and analysis by hiresh ah...
 
Application of industrial engineering in garments sewing floor
Application of industrial engineering in garments sewing floorApplication of industrial engineering in garments sewing floor
Application of industrial engineering in garments sewing floor
 
Evolution of maintenance_practices
Evolution of maintenance_practicesEvolution of maintenance_practices
Evolution of maintenance_practices
 
Analysis and optimization of maintenances management of instruments
Analysis and optimization of maintenances management of instrumentsAnalysis and optimization of maintenances management of instruments
Analysis and optimization of maintenances management of instruments
 
Maintenance
MaintenanceMaintenance
Maintenance
 
Subham Internship
Subham InternshipSubham Internship
Subham Internship
 
IRJET- Enhance the Capacity of Outer Tube Machining Cell
IRJET-  	  Enhance the Capacity of Outer Tube Machining CellIRJET-  	  Enhance the Capacity of Outer Tube Machining Cell
IRJET- Enhance the Capacity of Outer Tube Machining Cell
 
Petrol on wheels
Petrol on wheelsPetrol on wheels
Petrol on wheels
 
Root Cause Failure Analysis by Eugene Cottle-Lifecycle Engineering
Root Cause Failure Analysis by Eugene Cottle-Lifecycle EngineeringRoot Cause Failure Analysis by Eugene Cottle-Lifecycle Engineering
Root Cause Failure Analysis by Eugene Cottle-Lifecycle Engineering
 
Gis on vikash industry
Gis on  vikash industryGis on  vikash industry
Gis on vikash industry
 
Prioritised Engineering Design Requirements of Gas Turbine Engine by QFD
Prioritised Engineering Design Requirements of Gas Turbine Engine by QFDPrioritised Engineering Design Requirements of Gas Turbine Engine by QFD
Prioritised Engineering Design Requirements of Gas Turbine Engine by QFD
 
2019 Caterpillar Mining Equipment Management Metrics Document V4.pdf
2019 Caterpillar Mining Equipment Management Metrics Document V4.pdf2019 Caterpillar Mining Equipment Management Metrics Document V4.pdf
2019 Caterpillar Mining Equipment Management Metrics Document V4.pdf
 
IRJET- A Holistic Review of the Elements and the Tools of Lean Manufacturing
IRJET- A Holistic Review of the Elements and the Tools of Lean ManufacturingIRJET- A Holistic Review of the Elements and the Tools of Lean Manufacturing
IRJET- A Holistic Review of the Elements and the Tools of Lean Manufacturing
 
The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...
The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...
The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...
 
A Guide to Partnering with Industrial Lubrication Experts
A Guide to Partnering with Industrial Lubrication ExpertsA Guide to Partnering with Industrial Lubrication Experts
A Guide to Partnering with Industrial Lubrication Experts
 
Procedure Based Maintenance
Procedure Based MaintenanceProcedure Based Maintenance
Procedure Based Maintenance
 
Procedure Based Maintenance White Paper
Procedure Based Maintenance White PaperProcedure Based Maintenance White Paper
Procedure Based Maintenance White Paper
 

More from Utkarsh Amaravat

Operation, Failure and Safety Analysis along with Inventory Management
Operation, Failure and Safety Analysis along with Inventory Management Operation, Failure and Safety Analysis along with Inventory Management
Operation, Failure and Safety Analysis along with Inventory Management
Utkarsh Amaravat
 
Investment Opportunity in France and Oil and Gas Industry STEEPLED Analysis i...
Investment Opportunity in France and Oil and Gas Industry STEEPLED Analysis i...Investment Opportunity in France and Oil and Gas Industry STEEPLED Analysis i...
Investment Opportunity in France and Oil and Gas Industry STEEPLED Analysis i...
Utkarsh Amaravat
 
Satisfaction level and parameters considered by dealer’s with reference to Sy...
Satisfaction level and parameters considered by dealer’s with reference to Sy...Satisfaction level and parameters considered by dealer’s with reference to Sy...
Satisfaction level and parameters considered by dealer’s with reference to Sy...
Utkarsh Amaravat
 
Trend in Maintenance Management
Trend in Maintenance ManagementTrend in Maintenance Management
Trend in Maintenance Management
Utkarsh Amaravat
 
Trend in Maintenance Management
Trend in Maintenance ManagementTrend in Maintenance Management
Trend in Maintenance Management
Utkarsh Amaravat
 
Selection of steel manufacturing factory location in Gujarat and factor analy...
Selection of steel manufacturing factory location in Gujarat and factor analy...Selection of steel manufacturing factory location in Gujarat and factor analy...
Selection of steel manufacturing factory location in Gujarat and factor analy...
Utkarsh Amaravat
 
Interviewing Candidates
Interviewing CandidatesInterviewing Candidates
Interviewing Candidates
Utkarsh Amaravat
 
Design and Model of Bucket Elevator
Design and Model of Bucket ElevatorDesign and Model of Bucket Elevator
Design and Model of Bucket Elevator
Utkarsh Amaravat
 
Method of Data Collection
Method of Data CollectionMethod of Data Collection
Method of Data Collection
Utkarsh Amaravat
 
Method of Data Collection
Method of Data CollectionMethod of Data Collection
Method of Data Collection
Utkarsh Amaravat
 

More from Utkarsh Amaravat (10)

Operation, Failure and Safety Analysis along with Inventory Management
Operation, Failure and Safety Analysis along with Inventory Management Operation, Failure and Safety Analysis along with Inventory Management
Operation, Failure and Safety Analysis along with Inventory Management
 
Investment Opportunity in France and Oil and Gas Industry STEEPLED Analysis i...
Investment Opportunity in France and Oil and Gas Industry STEEPLED Analysis i...Investment Opportunity in France and Oil and Gas Industry STEEPLED Analysis i...
Investment Opportunity in France and Oil and Gas Industry STEEPLED Analysis i...
 
Satisfaction level and parameters considered by dealer’s with reference to Sy...
Satisfaction level and parameters considered by dealer’s with reference to Sy...Satisfaction level and parameters considered by dealer’s with reference to Sy...
Satisfaction level and parameters considered by dealer’s with reference to Sy...
 
Trend in Maintenance Management
Trend in Maintenance ManagementTrend in Maintenance Management
Trend in Maintenance Management
 
Trend in Maintenance Management
Trend in Maintenance ManagementTrend in Maintenance Management
Trend in Maintenance Management
 
Selection of steel manufacturing factory location in Gujarat and factor analy...
Selection of steel manufacturing factory location in Gujarat and factor analy...Selection of steel manufacturing factory location in Gujarat and factor analy...
Selection of steel manufacturing factory location in Gujarat and factor analy...
 
Interviewing Candidates
Interviewing CandidatesInterviewing Candidates
Interviewing Candidates
 
Design and Model of Bucket Elevator
Design and Model of Bucket ElevatorDesign and Model of Bucket Elevator
Design and Model of Bucket Elevator
 
Method of Data Collection
Method of Data CollectionMethod of Data Collection
Method of Data Collection
 
Method of Data Collection
Method of Data CollectionMethod of Data Collection
Method of Data Collection
 

Recently uploaded

Get Off the Bandwagon - Separating Digital Marketing Myths from Truth - Scott...
Get Off the Bandwagon - Separating Digital Marketing Myths from Truth - Scott...Get Off the Bandwagon - Separating Digital Marketing Myths from Truth - Scott...
Get Off the Bandwagon - Separating Digital Marketing Myths from Truth - Scott...
DigiMarCon - Digital Marketing, Media and Advertising Conferences & Exhibitions
 
Consumer Journey Mapping & Personalization Master Class - Sabrina Killgo
Consumer Journey Mapping & Personalization Master Class - Sabrina KillgoConsumer Journey Mapping & Personalization Master Class - Sabrina Killgo
Consumer Journey Mapping & Personalization Master Class - Sabrina Killgo
DigiMarCon - Digital Marketing, Media and Advertising Conferences & Exhibitions
 
Efficient Website Management for Digital Marketing Pros
Efficient Website Management for Digital Marketing ProsEfficient Website Management for Digital Marketing Pros
Efficient Website Management for Digital Marketing Pros
Lauren Polinsky
 
PickUp_conversational AI_Capex, Inc._20240611
PickUp_conversational AI_Capex, Inc._20240611PickUp_conversational AI_Capex, Inc._20240611
PickUp_conversational AI_Capex, Inc._20240611
Shuntaro Kogame
 
Playlist and Paint Event with Sony Music U
Playlist and Paint Event with Sony Music UPlaylist and Paint Event with Sony Music U
Playlist and Paint Event with Sony Music U
SemajahParker
 
How to Use a Free Book Funnel to Drive Highly Qualified Buyers Into Your Busi...
How to Use a Free Book Funnel to Drive Highly Qualified Buyers Into Your Busi...How to Use a Free Book Funnel to Drive Highly Qualified Buyers Into Your Busi...
How to Use a Free Book Funnel to Drive Highly Qualified Buyers Into Your Busi...
DigiMarCon - Digital Marketing, Media and Advertising Conferences & Exhibitions
 
Story Telling Master Class - Jennifer Morilla
Story Telling Master Class - Jennifer MorillaStory Telling Master Class - Jennifer Morilla
Mastering Your Online Visibility - Fernando Angulo
Mastering Your Online Visibility - Fernando AnguloMastering Your Online Visibility - Fernando Angulo
Digital Marketing Trends - Experts Insights on How to Gain a Competitive Edge...
Digital Marketing Trends - Experts Insights on How to Gain a Competitive Edge...Digital Marketing Trends - Experts Insights on How to Gain a Competitive Edge...
Digital Marketing Trends - Experts Insights on How to Gain a Competitive Edge...
DigiMarCon - Digital Marketing, Media and Advertising Conferences & Exhibitions
 
Grow Your Business Online: Introduction to Digital Marketing
Grow Your Business Online: Introduction to Digital MarketingGrow Your Business Online: Introduction to Digital Marketing
Grow Your Business Online: Introduction to Digital Marketing
Digital Discovery Institute
 
Gokila digital marketing| consultant| Coimbatore
Gokila digital marketing| consultant| CoimbatoreGokila digital marketing| consultant| Coimbatore
Gokila digital marketing| consultant| Coimbatore
dmgokila
 
Smart Tools, Smarter Business -15 AI Tools to Optimize Your Workflows from Id...
Smart Tools, Smarter Business -15 AI Tools to Optimize Your Workflows from Id...Smart Tools, Smarter Business -15 AI Tools to Optimize Your Workflows from Id...
Smart Tools, Smarter Business -15 AI Tools to Optimize Your Workflows from Id...
DigiMarCon - Digital Marketing, Media and Advertising Conferences & Exhibitions
 
Email Marketing Master Class - Chris Ferris
Email Marketing Master Class - Chris FerrisEmail Marketing Master Class - Chris Ferris
How to Kickstart Content Marketing With A Small Team - Dennis Shiao
How to Kickstart Content Marketing With A Small Team - Dennis ShiaoHow to Kickstart Content Marketing With A Small Team - Dennis Shiao
How to Kickstart Content Marketing With A Small Team - Dennis Shiao
DigiMarCon - Digital Marketing, Media and Advertising Conferences & Exhibitions
 
Digital Marketing Trends - Experts Insights on How to Gain a Competitive Edge...
Digital Marketing Trends - Experts Insights on How to Gain a Competitive Edge...Digital Marketing Trends - Experts Insights on How to Gain a Competitive Edge...
Digital Marketing Trends - Experts Insights on How to Gain a Competitive Edge...
DigiMarCon - Digital Marketing, Media and Advertising Conferences & Exhibitions
 
SEO in the AI Era - Trust, Quality and Content Discovery - Andy Crestodina
SEO in the AI Era - Trust, Quality and Content Discovery - Andy CrestodinaSEO in the AI Era - Trust, Quality and Content Discovery - Andy Crestodina
SEO in the AI Era - Trust, Quality and Content Discovery - Andy Crestodina
DigiMarCon - Digital Marketing, Media and Advertising Conferences & Exhibitions
 
How American Bath Group Leveraged Kontent
How American Bath Group Leveraged KontentHow American Bath Group Leveraged Kontent
WTS-Berlin-2024-Veronika-Höller-Innovate-NextGEN-SEO-Merging-AI-Multimedia-an...
WTS-Berlin-2024-Veronika-Höller-Innovate-NextGEN-SEO-Merging-AI-Multimedia-an...WTS-Berlin-2024-Veronika-Höller-Innovate-NextGEN-SEO-Merging-AI-Multimedia-an...
WTS-Berlin-2024-Veronika-Höller-Innovate-NextGEN-SEO-Merging-AI-Multimedia-an...
Veronika Höller
 
PickUp_conversational AI_Capex, Inc._20240610
PickUp_conversational AI_Capex, Inc._20240610PickUp_conversational AI_Capex, Inc._20240610
PickUp_conversational AI_Capex, Inc._20240610
Shuntaro Kogame
 

Recently uploaded (20)

Get Off the Bandwagon - Separating Digital Marketing Myths from Truth - Scott...
Get Off the Bandwagon - Separating Digital Marketing Myths from Truth - Scott...Get Off the Bandwagon - Separating Digital Marketing Myths from Truth - Scott...
Get Off the Bandwagon - Separating Digital Marketing Myths from Truth - Scott...
 
Consumer Journey Mapping & Personalization Master Class - Sabrina Killgo
Consumer Journey Mapping & Personalization Master Class - Sabrina KillgoConsumer Journey Mapping & Personalization Master Class - Sabrina Killgo
Consumer Journey Mapping & Personalization Master Class - Sabrina Killgo
 
Efficient Website Management for Digital Marketing Pros
Efficient Website Management for Digital Marketing ProsEfficient Website Management for Digital Marketing Pros
Efficient Website Management for Digital Marketing Pros
 
PickUp_conversational AI_Capex, Inc._20240611
PickUp_conversational AI_Capex, Inc._20240611PickUp_conversational AI_Capex, Inc._20240611
PickUp_conversational AI_Capex, Inc._20240611
 
Playlist and Paint Event with Sony Music U
Playlist and Paint Event with Sony Music UPlaylist and Paint Event with Sony Music U
Playlist and Paint Event with Sony Music U
 
How to Use a Free Book Funnel to Drive Highly Qualified Buyers Into Your Busi...
How to Use a Free Book Funnel to Drive Highly Qualified Buyers Into Your Busi...How to Use a Free Book Funnel to Drive Highly Qualified Buyers Into Your Busi...
How to Use a Free Book Funnel to Drive Highly Qualified Buyers Into Your Busi...
 
Story Telling Master Class - Jennifer Morilla
Story Telling Master Class - Jennifer MorillaStory Telling Master Class - Jennifer Morilla
Story Telling Master Class - Jennifer Morilla
 
Mastering Your Online Visibility - Fernando Angulo
Mastering Your Online Visibility - Fernando AnguloMastering Your Online Visibility - Fernando Angulo
Mastering Your Online Visibility - Fernando Angulo
 
Digital Marketing Trends - Experts Insights on How to Gain a Competitive Edge...
Digital Marketing Trends - Experts Insights on How to Gain a Competitive Edge...Digital Marketing Trends - Experts Insights on How to Gain a Competitive Edge...
Digital Marketing Trends - Experts Insights on How to Gain a Competitive Edge...
 
Grow Your Business Online: Introduction to Digital Marketing
Grow Your Business Online: Introduction to Digital MarketingGrow Your Business Online: Introduction to Digital Marketing
Grow Your Business Online: Introduction to Digital Marketing
 
Gokila digital marketing| consultant| Coimbatore
Gokila digital marketing| consultant| CoimbatoreGokila digital marketing| consultant| Coimbatore
Gokila digital marketing| consultant| Coimbatore
 
Smart Tools, Smarter Business -15 AI Tools to Optimize Your Workflows from Id...
Smart Tools, Smarter Business -15 AI Tools to Optimize Your Workflows from Id...Smart Tools, Smarter Business -15 AI Tools to Optimize Your Workflows from Id...
Smart Tools, Smarter Business -15 AI Tools to Optimize Your Workflows from Id...
 
Email Marketing Master Class - Chris Ferris
Email Marketing Master Class - Chris FerrisEmail Marketing Master Class - Chris Ferris
Email Marketing Master Class - Chris Ferris
 
How to Kickstart Content Marketing With A Small Team - Dennis Shiao
How to Kickstart Content Marketing With A Small Team - Dennis ShiaoHow to Kickstart Content Marketing With A Small Team - Dennis Shiao
How to Kickstart Content Marketing With A Small Team - Dennis Shiao
 
Digital Marketing Trends - Experts Insights on How to Gain a Competitive Edge...
Digital Marketing Trends - Experts Insights on How to Gain a Competitive Edge...Digital Marketing Trends - Experts Insights on How to Gain a Competitive Edge...
Digital Marketing Trends - Experts Insights on How to Gain a Competitive Edge...
 
SEO in the AI Era - Trust, Quality and Content Discovery - Andy Crestodina
SEO in the AI Era - Trust, Quality and Content Discovery - Andy CrestodinaSEO in the AI Era - Trust, Quality and Content Discovery - Andy Crestodina
SEO in the AI Era - Trust, Quality and Content Discovery - Andy Crestodina
 
Unleash the Power of Storytelling - Win Hearts, Change Minds, Get Results - R...
Unleash the Power of Storytelling - Win Hearts, Change Minds, Get Results - R...Unleash the Power of Storytelling - Win Hearts, Change Minds, Get Results - R...
Unleash the Power of Storytelling - Win Hearts, Change Minds, Get Results - R...
 
How American Bath Group Leveraged Kontent
How American Bath Group Leveraged KontentHow American Bath Group Leveraged Kontent
How American Bath Group Leveraged Kontent
 
WTS-Berlin-2024-Veronika-Höller-Innovate-NextGEN-SEO-Merging-AI-Multimedia-an...
WTS-Berlin-2024-Veronika-Höller-Innovate-NextGEN-SEO-Merging-AI-Multimedia-an...WTS-Berlin-2024-Veronika-Höller-Innovate-NextGEN-SEO-Merging-AI-Multimedia-an...
WTS-Berlin-2024-Veronika-Höller-Innovate-NextGEN-SEO-Merging-AI-Multimedia-an...
 
PickUp_conversational AI_Capex, Inc._20240610
PickUp_conversational AI_Capex, Inc._20240610PickUp_conversational AI_Capex, Inc._20240610
PickUp_conversational AI_Capex, Inc._20240610
 

Feasibility of Maintenance Agency in Baroda

  • 1. A Comprehensive Project Report ON “FEASIBILITY OF MAINTENANCE AGENCY IN BARODA” Submitted to Anand Institute of Management, Anand Under The Guidance Of SNEHAL BHATT Assistant Professor, AIM In partial Fulfilment of the Requirement of the award of the degree of Master of Business Administration Offered by Gujarat Technological University, Ahmadabad Prepared By UTKARSH AMARAVAT (127020592003) MBA SEMESTER IV May, 2014
  • 2. i Declaration I, UTKARSH AMARAVAT hereby declare that the report on entitled “Feasibility of Maintenance Agency in Baroda” is a result of my own work and my indebtedness to other work Publications, if any, have been duly acknowledgment. Place: - Anand, Gujarat, India Date: - 6th May, 2014 Utkarsh Amaravat
  • 3. ii Preface As undergoing the course of Masters of Business Administration in Gujarat Technological University, This comprehensive project report has been prepared in partial fulfilment of the requirement of academic where one can get opportunity to meet the real working people of different industries and to learn practical aspect of management. Before finishing MBA and going in practical world, it is necessary to learn how actually Company do any feasibility study for new project. I take Marketing as specialization in MBA and to do marketing it’s necessary to find product or service feasibility in market. It was a complete learning and research process throughout this project. I had a very memorable and worthy experience. The rationale behind doing the project work is to study, analyze and find feasibility of blue ocean maintenance agency idea in real world.
  • 4. iii Acknowledgement It was indeed an opportunity for me to prepare a feasibility study project report. during M.B.A. programme. My heartful thanks to Mr. Snehal Bhatt, my project guide and Mr. Akash Shah and Miss. Suchi Patel who helped me to bring out this project in good manner with them precise suggestion and rich experience. I gratefully acknowledge my sincere thanks to my friends Specifically Mr. Bharat Gohil who help me in this project when needed. I am extremely thankful to all companies who participate as respondent in this research; and Makarpura, Pore, Ranoli, Salvi, Nandesari and Vagodia GIDC offices to provide helpful guidance and materials.
  • 5. iv LIST OF TABLES Table No. Table Description Page No. 1.1 Maintenance Agency Fixed Cost or Initial Investment 13 1.2 Maintenance Agency Variable Cost per month 14 2.1 Content Analysis 23 5.1 Demographic Profile 39 5.2 Machinery basic Data 40 5.3 Type of Machinery 41 5.4 Operational Machinery Usage 42 5.5 No. of Operational Machinery 44 5.6 Average age of Operational Machinery 46 5.7 Conveying Machinery Usage 48 5.8 No. of Conveying Machinery 49 5.9 Average age of Conveying Machinery 50 5.10 Power supply Machinery Usage 51 5.11 No. of Power supply Machinery 52 5.12 Average age of Power supply Machinery 53 5.13 Different Manufacturer machinery usage 54 5.14 Maintenance Department Inquiry 55 5.15 Maintenance Department Ability 56 5.16 Maintenance Department Man power 57 5.17 Awareness of other Maintenance agency 58 5.18 Other Maintenance agency AMC 59 5.19 Machinery warranty period Inquiry 60 5.20 Likert Scale: Statement 1 61 5.21 Likert Scale: Statement 2 62 5.22 Likert Scale: Statement 3 63 5.23 Likert Scale: Statement 4 64 5.24 Likert Scale: Statement 5 65 5.25 Likert Scale: Statement 6 66 5.26 Likert Scale: Statement 7 67
  • 6. v 5.27 Likert Scale: Statement 8 68 5.28 Likert Scale: Statement 9 69 5.29 Likert Scale: Statement 10 70 5.30 Likert Scale: Statement 11 71 5.31 Likert Scale: Statement 12 72 5.32 Likert Scale: Statement 13 73 5.33 Likert Scale: Statement 14 74 5.34 Likert Scale: Statement 15 75 5.35 Likert Scale: Statement 16 76 5.36 Likert Scale: Statement 17 77 5.37 Purchase Maintenance agency services in Future 78 6.1 Hypothesis 1 79 6.2 Hypothesis 2 80 6.3 Hypothesis 3 81 6.4 Hypothesis 4 82 6.5 Hypothesis 5 84 6.6 Hypothesis 6 85 6.7 Hypothesis 7 86 6.8 Hypothesis 8 87 7.1 Fixed Investment Cost requirement for next 3 Years 88 7.2 Variable Cost requirement for next 3 Years 89 7.3 Future customer analysis 91 7.4 Estimated Cash inflow 93 7.5 Estimated P/L Accounts 93 7.6 Payback Period 95 7.7 PV of Cash Inflow 95 7.8 PV of Cash Outflow 96
  • 7. vi LIST OF FIGURES Figure No. Figure Description Page No. 1.1 Flow Diagram of Breakdown Maintenance 2 1.2 Preventive Maintenance Process Flow 3 1.3 Comparison of Breakdown, Predictive and Routine Maintenance 4 5.1 Machinery basic Data 40 5.2 Type of Machinery 41 5.3 Operational Machinery Usage 43 5.4 No. of Operational Machinery 45 5.5 Average age of Operational Machinery 47 5.6 Conveying Machinery Usage 48 5.7 No. of Conveying Machinery 49 5.8 Average age of Conveying Machinery 50 5.9 Power supply Machinery Usage 51 5.10 No. of Power supply Machinery 52 5.11 Average age of Power supply Machinery 53 5.12 Different Manufacturer machinery usage 54 5.13 Maintenance Department Inquiry 55 5.14 Maintenance Department Ability 56 5.15 Maintenance Department Man power 57 5.16 Awareness of other Maintenance agency 58 5.17 Other Maintenance agency AMC 59 5.18 Machinery warranty period Inquiry 60 5.19 Likert Scale: Statement 1 61 5.20 Likert Scale: Statement 2 62 5.21 Likert Scale: Statement 3 63 5.22 Likert Scale: Statement 4 64 5.23 Likert Scale: Statement 5 65 5.24 Likert Scale: Statement 6 66 5.25 Likert Scale: Statement 7 67
  • 8. vii 5.26 Likert Scale: Statement 8 68 5.27 Likert Scale: Statement 9 69 5.28 Likert Scale: Statement 10 70 5.29 Likert Scale: Statement 11 71 5.30 Likert Scale: Statement 12 72 5.31 Likert Scale: Statement 13 73 5.32 Likert Scale: Statement 14 74 5.33 Likert Scale: Statement 15 75 5.34 Likert Scale: Statement 16 76 5.35 Likert Scale: Statement 17 77 5.36 Purchase Maintenance agency services in Future 78 6.1 Hypothesis 1 79 6.2 Hypothesis 4 83 6.3 Hypothesis 5 83 6.4 Hypothesis 8 87 7.1 Estimated PAT 94
  • 9. viii TABLE OF CONTENTS Page No. Declaration i Preface ii Acknowledgement iii List of Tables iv List of Figures vi Table of Contents viii 1 About Industry 1.1 Maintenance 1 1.2 Maintenance Agency 6 1.3 Maintenance Agency Service Mix 9 1.4 Maintenance Agency Cost 13 2 Secondary Data Analysis 2.1 Literature Review 15 2.2 Content Analysis 23 2.3 Research Gap 34 3 Signification of Study 35 4 Research Methodology 4.1 Research Statement 36 4.2 Objective of Study 36 4.3 Research Hypothesis 36 4.4 Research Design 38 4.5 Sampling Method 38 4.6 Data Collection Instruments 38 4.7 Sampling Unit 38 4.8 Sample Size 38
  • 10. ix 5 Data Analysis 5.1 Demographic Profile 39 5.2 Response Rate 39 5.3 Questionnaire Analysis 40 6 Hypothesis Testing 79 7 Maintenance agency Profitability and Feasibility Analysis 7.1 Cost of Project 88 7.2 Means of Financing 90 7.3 Estimated Cash Flow for next 3 years 91 7.4 Estimated Profit and Loss Accounts 93 7.5 Feasibility Analysis 95 8 Finding 97 9 Conclusion 98 Annexure I x Bibliography xiv
  • 12. 1 1.1. Maintenance The old concept of Maintenance was “Maintenance is about preserving physical asset”. However, the new concept is that “Maintenance is about preserving the functions of assets”. Maintenance can be define as “It is a routine or a recurring process of keeping a particular machine or asset in its normal operating condition, so that it can deliver its expected performance or service without causing any loss of time on account of accidental damage or breakdown.” Main function is to keep the equipment in working condition by replacing or repairing some of the component of the machine and increased availability of production system, with increased safety and optimized cost. 1.1.1. Maintenance Concepts Actually, Maintenance is an age old function, which developed and progressed, knowingly or unknowingly, along with the operation of the equipment/ machines. In early ages, maintenance was not a separate identity but the job of maintenance was considered as part and parcel of operator’s job. This was possible because of simplicity and openness of the machines. Here some concepts of Maintenance given as per there generation which are followed by Industries: 1. Breakdown Maintenance Concept (Before 1950) Breakdown Maintenance concept/system is oldest concept in Maintenance management. In this not do anything as long as everything is going well and maintenance repair is done after failure has already occurred. The equipment allowed running undisturbed till it fails. This maintenance concept also called as Reactive Maintenance Concept or Unplanned Maintenance or Operate to failure concept. Breakdown maintenance can only be suitable for small scale industries where numbers of equipments are few and sudden failure of equipment will not
  • 13. 2 cause several financial losses in term of delivery commitment. This system look to be simple and less expensive, but is not really so. It does not provide any guarantee of reliability to the smooth production running. In breakdown maintenance downtime of equipment is high after breakdown. Fig. 1.1 Flow Diagram of Breakdown Maintenance 2. Preventive Maintenance Concept (Between 1950 to 1960) Some group of Japanese engineers started a new concept/system in maintenance that consisted on following the manufactures recommendation about the care that should be taken in the operation and maintenance of machine and devices. That new concept was called Preventive Maintenance or Schedule Maintenance Concept. This Maintenance program is scheduled in consultation with the production/operation department so that relevant equipment is made available for maintenance work and utilizes idle time of equipment. In this maintenance action such as inspection, lubrication, cleaning, adjustment and replacement are undertaken at fixed interval of number of hours or kilometres. Although it reduces downtime it was an expensive alternative. The reason many parts were replaced on a time basis, while they could have lasted longer. Also many unnecessary man-hours were put into it and in not few cases excess lubrication caused more damage than good.
  • 14. 3 Fig. 1.2 Preventive Maintenance Process Flow 3. Predictive Maintenance Concept (Between 1960 to 1970) With time change new concept/system established which determined a more professional approach. This assign of higher responsibility to all the people related to maintenance consisted of series of considerations about the reliability and design of equipment and plant itself. When equipment/system is taken down for maintenance, changing one or few warn out component opportunity can be utilized for maintenance, changing other wearing out component even though they have not failed. This would probably be economical in the long run. It is very beneficial for non-monitored component which are inaccessible for inspection. This maintenance concept also called as Productive Maintenance Concept or Opportunity Maintenance Concept or Reliability Maintenance Management Concept. 4. Condition based Maintenance Concept (Between 1960 to 1970) Condition monitoring detects and diagnoses faults and it helps in planned maintenance based on equipment condition. This condition based on maintenance strategy is preferred for critical system and for such system breakdown maintenance is to be avoided. A number of condition based maintenance techniques such as vibration, temperature, oil analysis, etc. Have been developed, which guide the users in planned maintenance.
  • 15. 4 5. Total Productive Maintenance Concept (Between 1970 to 1985) This concept is about the involvement and participation of each and every one of the members in the organizations toward optimizing the outcome of each piece of equipment. This is a completely new philosophy is different approach that will keep updated by itself. It implies a continuous improvement in all aspect and is also called Total Participation Maintenance. The purpose is to transform the attitude of all the members of the industrial community, all kinds and levels of workers, operators, supervisors, engineers, administrators are included in this major responsibility. TPM implementation is a goal that all company members share. It also generates benefits for all. Through this effort, all are responsible for the up keeping of the equipment. It becomes more productive, safer and easier to operate and even looks nicer. The participation of people, who are not familiar with the equipment and its operation, enriches the result because their observations are in many cases more objective than those of the people who live with equipment in a daily basis. 6. Routine Maintenance Concept (Between 1970 to 1985) It is the Simplest form of part maintenance but very essential which Carrying out minor maintenance job such as cleaning, lubrication, inspection, minor adjustment of pressure, flow, tightness, etc. or inspection of bearing, belts, coupling, joints, foundations, bolts, earthings, etc. at regular intervals. Small/Critical effects using such inspection are rectified immediately. It is not need base, all equipment are inspected. It may consider small portion of preventive maintenance. It needs very little investment in terms of time and money. The duration routine maintenance is generally so small that it does not affect the output of machine appreciably. However, the cost of not doing routine maintenance may be very high as a small develop in big and catastrophic failure.
  • 16. 5 Fig. 1.3 Comparison of Breakdown, Predictive and Routine Maintenance 7. Computerized Maintenance Management System – CMMS (After 1985) It is also known as Enterprise Asset Management and Computerized Maintenance Management Information System (CMMIS). A CMMS software package maintains a computer database of information about an organization’s maintenance operations. This information is intended to help maintenance worker do their jobs more effectively and to help management make informed decisions. CMMS data may also be used to verify regulatory compliance. CMMS package may be used by any organization that must perform maintenance on equipment, assets and property. CMMS packages can produce status reports and documents giving details or summaries of maintenance activities. The more sophisticated the package, the more analysis facilities are available. Many CMMS packages can be either web based meaning they are hosted by the company selling the product on an outside server or LAN based meaning that the company buying the software hosts the product on their own server.
  • 17. 6 1.1.2. Selection criteria for selection of Maintenance Concept in Industries Presently many maintenance concepts are in use in industries and selection has to be made depending the need, complexity and reliability needed and also considering techno-economics. Criteria must consider are- 1) Work Procedures (Maintenance and Operation etc.) 2) Problems, Defect and Fault Reports 3) Work Schedules, Job Orders etc. 4) Work History 5) Assets 6) Inventory 7) Finance, etc. 1.2. Maintenance Agency “Maintenance Agency is the Organization provides service to the Industries to maintain their asset.” Asset involves infrastructure, machinery, equipment, hardware, software, etc. Here consider maintenance agency which deals with machinery and equipment means mechanical elements any industry. Maintenance agency involves managing function of maintenance. Maintaining equipment in the field has been a challenging task since the beginning of industrial revolution. Since then, a significant of progress has been made to maintain equipment effectively in the field. As the engineering equipment becomes sophisticated and expensive to produce and maintain, maintenance work has face even more challenging situations to maintain effectively such equipments in industrial environment, And Maintenance agency are outside agency doing this work for any industry. 1.2.1. Why Maintenance agency is needed? In Industries now a day’s various companies such as Fanuc, Siemens, Motorola, etc. machines are used such as lathe machine, milling machine,
  • 18. 7 shaper machine, drilling machine, etc. Now a day’s machine are two type numerical and computer control CNCs machine which are more complicated in nature. Today robot used also increased and that’s why in industry various robotic machines or equipment are used such as welding robot, painting robot, etc. All machineries run due to electricity that’s why maintaining of generator and motor is also important aspect. Other than these complex machineries on work station to transfer work in progress material from one work station to another various different type of material conveying system are used and sometime it is particularly made for that industry only. To deal with this type of modern machineries and equipments maintenance experience maintenance department is needed by any industries which can able to deal with any type of maintenance problem. Small scale industries are purchased advance machinery such as CNCs, robot, etc. to survive in market by increasing productivity with higher quality but these industries don’t have separate maintenance department or expertise worker who can deal with machine problems so these industries mostly deals with breakdown maintenance concept which increase downtime of machine and affect overall productivity of industries. Thus these industries always need outside support for their machineries maintenance. Medium scale industries have separate maintenance department or not but these industry people are not that much expertise like particular maintenance agency people who can able to solve any problem related to maintenance because Industry maintenance department people deals with limited existing machinery so don’t have more knowledge about new machinery and due to less man power sometime these people deals with other function of Industry also other than maintenance. Industry can give training to their maintenance department people but if industry gives more focus on maintenance training than its affect on industry productivity, thus these industries always need outside support for their machineries maintenance.
  • 19. 8 Large scale industries mostly have well expertise separate maintenance department but these industries always try to cut their cost, so if these industries find better option in terms of maintenance agency for maintenance so in place of go to the maintenance department where monthly salary and training expenses are needed these industries like to go with expertise maintenance agency out sourcing services so that these industries more focus on effective production in place of machinery maintenance. Maintenance agency is important aspect because, 1. It lowers down production unit cost for industries. 2. It minimizes downtime for industries. 3. It improves total availability of system in any industry. 4. It extended useful life of equipment which used in industries. 5. It increases safety of personals who work in industries. 6. It helps in reducing overtime in industries which reflect in terms of cost saving. 7. It provides better process stability in any industry. 8. It reduce maintenance part inventory which stored in industry if that industry have maintenance department. Actually equipment or machinery manufacturer provides maintenance services for their products during warranty period and after that through contract, But now a day’s industries are having more than one company machinery or equipment for example same industry having lathe machine of two different company Fanuc and Siemens so after completing of warranty period doing contract of maintenance with more than one company its quite difficult where these manufacturer service station are not located at nearer place (In Gujarat all machine manufacturer service station are located in Ahmadabad so for industry which located in Ahmadabad its feasible to use manufacturer maintenance services) and take almost two days to come after complaining which affect production. Thus after completing warranty period all industries are like to go with one maintenance agency who is expertise in maintenance which provide them all type of machinery and equipment maintenance service for any manufacturer machinery and equipment, But
  • 20. 9 these type of maintenance agency is not present in India actually in world for machinery and equipment maintenance that’s why this business idea to start maintenance agency is blue ocean business idea where maximum chances for success. 1.3. Maintenance Agency Service Mix 1.3.1. Product Maintenance agency should provide all machinery maintenance services under one roof on 24X7 bases to industries for various maintenance problems and also provide services in term of annual maintenance contract. 13.2. Place This maintenance agency should start in Baroda city in initial basis and based on success in future will try to increase service area from Baroda region to Baroda District and then will try to capturing whole Gujarat then move towards India. Why Maintenance agency in Baroda? Baroda is headquarters of Baroda District and after Ahmadabad and Surat now main attraction for investor for further development. In Baroda District total 15 Industrial area (GIDC) where total 5466 no. of units in production. The industrial clusters include Chemicals & fertilizers, Pharmaceuticals, Biotechnology, Cotton Textiles, Machine Tools, Glass, Engineering, Tobacco, Fisheries and Dairy. There are over 18,000 small scale industrial units in Baroda, in which repairs & services units are maximum in numbers accounting nearly 5,713 units, 1,923 textiles, 1,615 metal works, 1,357 chemicals, 1,316 equipmentsmachinery, 1,145 rubber & its products, 1,047 food products and 3,840 are misc. units . Other key small scale industries include textiles, metal works, chemicals, equipments, rubber products and food products etc.885 glass, ceramics & cement, 829 equipments related to
  • 21. 10 electricity, 753 papers & its products, 601 non ferrous metals, 543 leathers, 173 tobacco and 56 are misc. units. In Baroda district 18067 units are registered and total investment is of Rs. 223250.54 lakhs. While in Baroda region 15534 units are registered and total investment is of Rs. 99435.21 lakhs, which shows lots of business opportunity for maintenance agency in Baroda region where small scale, medium scale and large scale means all type of Industries having their present and more investor are move towards Baroda region for investment and building strong industrial culture. For maintenance agency for machinery maintenance machine spare part are required and machine spare part main market is located in Ahmadabad which near to Baroda so to arrange required spare part in shorter period of time is easy if maintenance agency is located in Baroda and in Gujarat all machine manufacturer industries service station are located in Ahmadabad so for industry machine which maintenance is quite difficult for maintenance agency than if maintenance agency is in Baroda can used out source service of main machine manufacturer easily. 1.3.3.Process  Any Industry belong in Baroda region can contact this maintenance agency for any type of maintenance problem in their machinery or equipment.  Any Industry can registered maintenance problem to maintenance agency through mail, through website, through call or through personnel contact for any type of problem.  Maintenance problems registration should open for 24x7 and maintenance agency should provide services 24x7.  For any maintenance problem, that industry should get response in terms of visit from maintenance agency within 24 hours after registering their maintenance problem.
  • 22. 11  During visit of particular industry maintenance agency experts should try to solve problem at a time and if at that time it is not possible to solve the problems at a time then always try to solve problem as early as possible by giving correct estimated time.  After repairing or solving any problem, Maintenance agency person should verify it from that industry person, take that person signature on document and collect those service charges.  Maintenance agency should take annual contract for maintenance if any industry wants, Annual contract on two ways- - Half annual Contract where provide servicing facility to all machinery but spare part or other replacement charges are chargeable. - Full annual contract where provide all type of services including servicing of machinery to replacement in one predefined annual amount only. 1.3.4.Price To get success in Baroda region maintenance agency will take minimum charges compare to other manufacturer charges and provide all machinery maintenance services. Also maintenance agency should provide instalment payment option. Maintenance agency experts should visit particular industry after their problem registration, and which charges will be Rs. 450/ machine and Rs. 800/ two machines to that industry to check problem and correct problem if possible. This rate should be changed based on market. Other charges for maintenance like spare part and other out sourcing services should be taken based on those market values. To built long term relation maintenance agency should provide discount to regular clients. If industry will increase service level then maintenance agency
  • 23. 12 should provide them more benefit in terms of additional discount in service charges. 1.3.5. Promotion To get success marketing is important aspect, and this maintenance agency will used direct marketing approach and mailed relevant information and website link with contact information to all industries mail id and also as physical evidence send pamphlet to all industries in Baroda region. 1.3.6. People In service Industry trust towards service provider is important aspect and people who work as service provider can build trust towards company in the mind of consumer. Here in this maintenance agency people means employee of agency are required to attain or register customer maintenance complains, visit customer place and using expertise solve customer maintenance problem. If Maintenance agency employee behaves in such way and creating impression in the mind of customer in such way about maintenance agency service then customer will buy again and again maintenance agency service and convert it into annual contract in terms of long term professional relationship. 1.3.7. Physical Evidence In Maintenance agency services are provided at place of customer so physical evidence are not matter more compare to other service industry, In terms of physical evidence one shop is required at ground floor where storing agency spare parts and tool; and where agency person sit and received order in terms of maintenance problem through internet or telephone.
  • 24. 13 1.4. Maintenance Agency Cost 1.4.1. Fixed Cost/ Investment To start any business initial amount is required for investment and to start maintenance agency as shown in Table 1.1. Rs. 746500 is required as fixed initial cost. Table 1.1 Maintenance Agency Fixed Cost or Initial Investment unit Rs. Shop Deposit - 50000 Website charges - 15000 Toolbox 3 15000 Hand Drill 3 10000 Welding Machine 3 26500 Grinder/cutter 3 6000 Hacksaw 3 6000 Computer 1 22000 Printer 1 4500 Shop Furniture/ chairs - 30000 Vehicles Tata Chhota Hathi 2 560000 Cycle 1 1500 Total 746500 1.4.2.. Variable Cost To run any business and deal with it expanse certain amount is required on monthly bases; and here as shown in Table 1.2. Rs. 123400 is required as monthly working capital money to run maintenance agency.
  • 25. 14 Table 1.2 Maintenance Agency Variable Cost per month Rs. Shop Rent 5000 Petrol/ Diesel 8000 Electricity Bill 2500 Telephone Bill 3000 Stationary Cost 500 Employee Salary Diploma Mechanical >15 yr experience 38500 >1 yr experience 5000 Diploma electrical >2 yr experience 6000 Computer operator 4500 Telephone operator 4500 Wages ITI >10 yr experience 320*2 Worker 19200 >5 yr experience 255*2 Worker 15300 Helper 190*2 Helper 11400 Total (Rs. Required per Month) 123400
  • 27. 15 2.1. Literature Review 1. The Economic Times (2013, November 25), “RIL shuts secondary unit at its Jamnagar refinery for planned maintenance” which suggest importance of maintenance for any industry as big industry like Reliance close it one unit where diesel is produced and which affect Reliance diesel stock. 2. Dilanthi M G S (2013) studied on improving productivity with maintenance function in manufacturing industry of Sri Lanka: literature review. The researcher reviewed literature and develop strategy to improve productivity in manufacturing industry in country by improving maintenance operation. 3. Department of Education and Early Childhood Development (2013) measured feasibility of secondary education in to the broader Sandringham area and concluded that high level of interest in discussion about secondary education options in the Sandringham and Beaumaris area. 4. Rexroad APG (2013) checked Colorado Springs public market feasibility and find out that the members of the Colorado Springs Public Market Project (CSPMP) founding organization, become increasingly exposed as the effort becomes more and more real. Awareness and support are important elements to making the Public Market a success. The establishment of the market is a long and sometimes arduous process that the public generally has little tolerance for. In order to sustain fickle public attention without the burden of detail, communication of progress and public involvement should be carefully managed. This is increasingly difficult when factored to the demands of public financial support. 5. Ghaffari H et al (2012) studied on alax copper/gold feasibility projects in Kamloops, British Columbia.
  • 28. 16 The researchers find out that documentation for the drilling campaigns completed in the Ajax area before 1980 is limited or not available. Because of the limited documentation, the pre-1980 drill campaigns were not included in the 2011 resource model database. No factors were identified with the data collection from the drill programs used that could affect Mineral Resource or Mineral Reserve estimation. The Ajax deposits have been sampled at drill-hole spacing appropriate for a property at this level of development. Because of the irregular shape of the mineralized body, the orientation of the mineralization with respect to drill intercepts is unknown. The Ajax concentrator has been designed to produce a saleable copper concentrate. The complete processing circuit has been designed according to metallurgical test work conducted over the years and proven equipment. 6. Tito D A et al (2012) studied on feasibility analysis for a manned mars free return mission in 2018. The researchers concluded that a manned Mars free-return mission is a useful precursor mission to other planned Mars missions. It will develop and demonstrate many critical technologies and capabilities needed for manned Mars orbit and landing missions. The technology and other capabilities needed for this mission are needed for any future manned Mars missions. Investments in pursuing this development now would not be wasted even if this mission were to miss its launch date. 7. Riccetti S (2011) studied on Product safety and equipment reliability in the food industry through maintenance engineering. The researcher reviewed that Failure mode and effect analysis is important aspect for reducing maintenance problem. 8. Tahboub K K (2011) studied on an assessment of maintenance practice and problem in Jordanian industries. The researcher concluded that maintenance problem is mainly because of unavailability of spare part and lack of specialities in maintenance field.
  • 29. 17 9. Pophaley M and Vyas R K (2010) studied on plant maintenance management practices in automobile industries: A retrospective and literature review. The researchers concluded that the current work gives a broader view of maintenance practices and research carried across the globe, but now maintenance is the widely accepted philosophy for competitive advantage. 10.Bliss G (2010) studied on feasibility study of services needed for aging in place in steuben country. The researcher find out that there is a general lack of knowledge/understanding in people who might use the services and about services currently being provided by the Office for the Aging and other area service providers. There are further innovative in delivery required for services. 11.Kalensky D and Johnson F (2010) studied on technical feasibility study Carbon Monoxide sensing safety system foe appliances. The researchers concluded that CO sensors would be able to operate in the combustion chamber or the flue of a gas-fired appliance for a length of time to be used for safety or combustion control. Smaller surfaces improve heating and cooling times and reduce the power requirements. 12.AECOM Australia Pvt. Ltd. (2010) done pre feasibility study for a solar power precinct and concluded that large scale solar projects are unlikely to be financially viable for the next 10-20 years and it is hard to see a developer making financial investments in large scale solar power plants in the short term. 13.Transportation Economics and Management Systems, Inc. (2010) Measured feasibility of High speed rail and concluded that The feasibility of high-speed rail in Colorado represents a tremendous transportation and development opportunity for the Colorado and the Rocky Mountain west High-speed rail can provide a more efficient and cost-effective
  • 30. 18 means of connecting Colorado’s commercial centers with one another as well as the national and international destinations served by the state’s airports. High-speed rail also provides a more reliable, enjoyable and convenient way for tourists from all over the globe to get to some of the most important and popular recreational resort destinations in North America and the world. The economic benefits of such an investment are considerable. While the costs of implementing high-speed rail are large, as would be expected given the mountainous conditions in the I-70 corridor ($16 billion to $21 billion for service in both corridors), analysis indicates that investing in high-speed rail would generate an impressive $33 billion of benefits to Colorado. These benefits are generated by the rapid growth of the state and its need to accommodate a doubling of its population over the next 30-40 years. High-speed rail is by no means the silver bullet that solves all of Colorado’s transportation challenges. But, as this study clearly shows, it is a critical part of that solution and will be invaluable to the growth of the state’s economy. 14.Wilson R J (2010) studied on 2009‐2010 Feasibility and Market Research Study for Commercial Hop Production in New England. The researcher determined that is feasible to grow a commercial hop crop in New England. There is sufficient demand, there is sufficient price elasticity, and there is now the information, technology, supplies, and equipment available to meet the needs of a 1‐10 acre commercial hop yard. 15.Fonollera D L (2009) studied on feasibility study, project plan and business plan. The researcher concluded that feasibility study is used as a means of exploring the viability of an idea. The viability of an idea, its accuracy and its reliability depends on the information gathered through market research and analysis which used mainly to support project feasibility. 16.Lepelle-Nkumpi Local Municipality (2009) studied goat meat production feasibility study and find out that each co-operative member and/or
  • 31. 19 worker will be required to register for a goat management-training course offered by the Agricultural Research Council of South Africa. 17.Sautter F C et al (2008) studied on an integrated Maintenance management information system is the key to enabling condition based maintenance. The researchers find that the maintenance management information systems are the foundation for the data that support effective management decision. 18.Reis N, Sydness G S and Barton D N (2007) studied feasibility of payment for water services. The researchers concluded that In India, PWS programmes that increase employment opportunities by stimulating the demand in agricultural labour are likely to have the greatest benefits for the poor. If too many of the constraints consider in this work are present in a watershed, market-like arrangements will not be likely to offer the optimal way of achieving environmental conservation and solving water-related conflicts. 19.Hopwood V et al (2007) studied feasibility of the prevalence of home education in England. The researchers find out that it is not feasible to reliably ascertain the prevalence of home educated children through a national survey of LAs and home education organizations (as a route through which to access parents/careers). This is because despite improvements in LA records, there could be significant numbers of home educated children who are not known to an LA. 20.Pe’re’setal F and Noyes D (2006) studied on envisioning e-logistics developments: Making spare parts in situ and on demand: State of art and guideline for future developments. The researchers expressed the problem of supplying the spare part by automobile manufacturers. Thus effective maintenance system need is further increases.
  • 32. 20 21.Firmansyah A, Veronika A and Trigunarsyah B (2006) studied on risk analysis in feasibility study of building construction projects. The researchers find out that Feasibility study analysis with calculating risk factors cause a decrease in investment feasibility parameters and if treatments are done against the risks, hence the parameters will increase. Risk factors give a significant influence to the investment plan of research object. Risk factors that have the highest influence to the construction project are those that have relation with economical and financial aspect. The economic factors that have high sensitivity of investment feasibility are loan interest rate and increments of sales. Meanwhile, the factors that have low sensitivity are inflation changes and equity percentage. 22.Batson R G and Wan Q (2004) studied on quality of assembly assurance. The researchers find out that Quality of assembly is complex issue and four management systems are important namely production, quality, maintenance and human resources. 23.Chelbi A and Aitkadi D (2004) studied on analysis of a production/inventory system with randomly failing production unit submitted to regular preventive maintenance The researcher concluded that a repairable production unit subject to a random failures, such as in automobile manufacturing, a mathematical model has been developed to support maintenance strategy. 24.Batson R, Hall D and Hauer D (2001) studied on the role of equipment maintenance in lean assembly system. The researchers concluded that the excellence in equipment maintenance is essential to lean assembly. 25.Hoagland W H and Williamson L (2000) overviewed feasibility studies.
  • 33. 21 The researcher concluded that a feasibility study is an important tool for making the right decisions in starting of new business and a wrong decision at this point often leads to business failure. 26.Wadswoeth B (1999) studied on factor affecting forestland conversion and the feasibility of cooperative land management efforts at king countries urban/rural interface. The researcher concluded that King County's urban/rural interface presents a complex problem for planners and natural resource managers. The changing population and the associated fragmentation of large ownerships into small residential home sites has resulted in an increasing spectrum of landowner values and objectives that makes planning for the interface a difficult and potentially frustrating task. If King County leaders are committed to preserving the forest land base, they cannot ignore the problem, and they must act to set policy with this commitment in mind. Hopefully, this research can provide direction for King County’s planners and elected officials as they strive to work with forest landowners at the urban/rural interface to preserve forestland. The issue of forestland conversion at the urban/rural interface is not unique to King County, and many of the results from this study may well apply to other interface areas throughout the country. 27.Novak L R (1996) studied on guiding way for market feasibility study. The researcher concluded that Market and feasibility studies are quite complex. The best way to learn about market and feasibility studies, like most things, is by doing. If you don't have the opportunity to work on a study acquire and review a couple. The importance of market studies is not going to decrease. Capital is becoming more difficult to acquire and regulatory considerations are becoming more complex. In the competitive world of real estate development, the investor with the best information is going to be the most successful. 28.Murry R J and Mitchell B F (1994) studied on cost saving from practical preventive maintenance program.
  • 34. 22 The researchers showed the importance of predictive maintenance in effective maintenance management. 29.Meade B W and Hunsucker D Q (1991) studied on Cost effective maintenance Contracting – A literature review. The researchers find out that routine maintenance approaches reduce maintenance problem in highways which done on activity based. 30.Reichelderfer K (1984) studied on factor affecting the economic feasibility of the biological control of the weeds. The researcher the individual or group responsible for application and/or maintenance of the potential bio control approach perceive the target weed problem, the economic activity impacted by the weed has high value, and the biological control agent’s effect on the weed is neither slow nor highly variable, There either no current affective control available for the target weed or current control is very costly and the net economic returns to users of the bio control tactic are expected to equal or exceed those for alternative control.
  • 38. 26 Table2.1(Continue...) Remark NA NA NA Gap Maintenanceis necessarytoget competitive advantagebutno machinemaintenance agencypresentin world. Researchisnot carriedoutfor measuring maintenanceagency feasibility. Researchisnot carriedoutfor measuring maintenanceagency feasibility. Finding Thecurrentworkgivesa broaderviewofmaintenance practicesandresearch carriedacrosstheglobe,but nowmaintenanceisthe widelyacceptedphilosophy forcompetitiveadvantage. Lackofknowledgeinpeople whomightusetheservices andaboutservicescurrently beingprovidedbytheOffice fortheAgingandotherarea serviceproviders. COsensorswouldbeableto operateinthecombustion chamberortheflueofagas- firedapplianceforalengthof timetobeusedforsafetyor combustioncontrol.Smaller surfacesimproveheatingand coolingtimesandreducethe powerrequirements. Test Appeared NA NA NA Sample Size NA 3038 NA Country India USA USA Year 2010 2010 2010 Author PophaleyM VyasRK BliseG KalenskyD JohnsonF Sr. No. 9 10 11
  • 39. 27 Table2.1(Continue...) Remark NA NA NA Gap Researchisnot carriedoutfor measuring maintenance agencyfeasibility. Researchisnot carriedoutfor measuring maintenance agencyfeasibility. Researchisnot carriedoutfor measuring maintenance agencyfeasibility. Finding Largescalesolarprojectsare unlikelytobefinanciallyviablefor thenext10-20yearsanditis hardtoseeadevelopermaking financialinvestmentsinlarge scalesolarpowerplantsinthe shortterm. Investinginhigh-speedrailwould generateanimpressive$33billion ofbenefitstoColorado. Feasibletogrowacommercial hopcropinNewEngland.There issufficientdemand,thereis sufficientpriceelasticity,and thereisnowtheinformation, technology,supplies,and equipmentavailabletomeetthe needsofa1‐10acrecommercial hopyard. Test Appeared NA NA NA Sample Size NA 3038 NA Country Australia USA UK Year 2010 2010 2010 Author AECOM AustraliaPvt. Ltd. Transportation Economicsand Management Systems,Inc. WilsonRJ Sr. No. 12 13 14
  • 40. 28 Table2.1(Continue...) Remark NA NA NA Gap Todayintheworld nomachine maintenance agencyexistingso tocheckviability ofmaintenance agency,its feasibilitystudyis necessary. Researchisnot carriedoutfor measuring maintenance agencyfeasibility. Maintenance agencyisrequired formanaging maintenance information. Finding Feasibilitystudyisusedasa meansofexploringtheviability ofanidea.Theviabilityofan idea,itsaccuracyandits reliabilitydependsonthe informationgatheredthrough marketresearchandanalysis whichusedmainlytosupport projectfeasibility. Eachco-operativemember and/orworkerwillberequired toregisterforagoat management-trainingcourse offeredbytheAgricultural ResearchCouncilofSouth Africa. Themaintenance managementinformation systemsarethefoundationfor thedatathatsupporteffective maintenancedecision. Test Appeared NA NA NA Sample Size NA NA NA Country Philippines SouthAfrica USA Year 2009 2009 2008 Author FonolleraDL Lepelle-Nkumpi Local Municipality SautterFCetal Sr. No. 15 16 17
  • 41. 29 Table2.1(Continue...) Remark NA NA NA Gap Researchisnot carriedoutfor measuring maintenanceagency feasibility. Researchisnot carriedoutfor measuring maintenanceagency feasibility. Scopefor Maintenanceagency whichhaveall necessarysparepart atthetimeof maintenance. Finding PWSprogrammesthat increaseemployment opportunitiesbystimulating thedemandinagricultural labourarelikelytohavethe greatestbenefitsforthepoor people. itisnotfeasibletoreliably ascertaintheprevalenceof homeeducatedchildren throughanationalsurveyof LAsandhomeeducation organizations Automobilemanufacturer facingprobleminsupplying sparepart.Thuseffective maintenancesystemneedis increases. Test Appeared NA NA NA Sample Size NA NA NA Country India UK NA Year 2007 2007 2006 Author ReisN SydnessGS BartonDN HopwoodV O’NeillL CastroG HodgsonB Pe’re’setalF NoyesD Sr. No. 18 19 20
  • 42. 30 Table2.1(Continue...) Remark NA NA NA Gap Maintenanceagency feasibilitystudyis necessarytominimize itsrisk. Maintenanceisan importantaspectfor managementbutno machinemaintenance agencypresentin world. Todevelopeffective mathematicalmodel formaintenance machinemaintenance agencyisrequired. Finding Riskfactorsgiveasignificant influencetotheinvestment planofresearchobject.Risk factorsthathavethehighest influencetotheconstruction projectarethosethathave relationwitheconomicaland financialaspect. Qualityofassemblyiscomplex issueandfourmanagement systemareimportantnamely production,quality, maintenanceandhuman resources. Arepairableproductionunit subjecttoarandomfailures, suchasinautomobile manufacturing,amathematical modelhasbeendevelopedto supportmaintenancestrategy. Test Appeared NA NA NA Sample Size NA NA NA Country Thailand USA USA Year 2006 2004 2004 Author FirmansyahA VeronikaA TrigunarsyahB BatsonRG WanQ ChelbiA AitkadiD Sr. No. 21 22 23
  • 44. 32 Table2.1(Continue...) Remark NA NA NA Gap Researchisnot carriedoutfor measuring maintenanceagency feasibility. TolearnMaintenance agencyfeasibilityits necessarytomeasure itbydoingmarket research. Maintenanceisan importantaspectfor managementbutno machinemaintenance agencypresentin world. Finding Thechangingpopulationand theassociatedfragmentationof largeownershipsintosmall residentialhomesiteshas resultedinanincreasing spectrumoflandownervalues andobjectivesthatmakes planningfortheinterfacea difficultandpotentially frustratingtask. Thebestwaytolearnabout marketandfeasibilitystudies, likemostthings,isbydoing. theimportanceofpredictive maintenanceineffective maintenancemanagement Test Appeared NA NA NA Sample Size 1830 NA NA Country NA USA USA Year 1999 1996 1994 Author WadswoethB NovakLR MurryRJ MitchellBF Sr. No. 26 27 28
  • 46. 34 2.3. Research Gap Literature Review Conclusion: Scope of Maintenance is increasing to get competitive advantage. Maintenance management support management to take effective management decision and for effective maintenance management computer based maintenance information system and mathematical model is required now a days. In Maintenance machine spare part availability and maintenance person expertise is major problem. Maintenance is important for any industry as big industry like Reliance close it one unit where diesel is produced and which affect Reliance diesel stock. Maintenance is important aspect for industries but today in world no machinery maintenance agency presents which provides all type of expertise, 24x7 availability for all type of machinery under one roof. So here try to find out this type of maintenance agency is feasible in actual industrial environment or not based on industries review.
  • 48. 35 1. This study is used to know which types of machinery are mostly used in Baroda region. 2. This study is help to know the intention of the existing industries towards services provide by maintenance agency. 3. This study is help to know the interest of the existing industries in services provided by maintenance agency. 4. This study is help to know the perception of the existing industries towards maintenance agency. 5. This study is help to know existing industries purchasing attitude towards service provide by maintenance agency. 6. This study is help to measure profitability of maintenance agency based on responses.
  • 50. 36 4.1. Problem Statement “To study the feasibility of Maintenance agency in Baroda.” 4.2. Objective of the Study 1. To know the intention of the existing industries towards services provide by maintenance agency. 2. To know the interest of the existing industries in services provided by maintenance agency. 3. To know the perception of the existing industries towards maintenance agency. 4. To know existing industries purchasing attitude towards service provide by maintenance agency. 5. To measure profitability of maintenance agency based on responses. 4.3. Research Hypothesis Intension 1 H0: Existing industries are not having positive intension towards maintenance agency services. H1: Existing industries are having positive intension towards maintenance agency services. 2 H0: Company Intension towards Maintenance agency services is not independent of the type of Industry and Company annual maintenance budget. H1: Company Intension towards Maintenance agency services is independent of the type of Industry and Company annual maintenance budget.
  • 51. 37 Interest 3 H0: Company interest level towards Maintenance agency services is not independent of the type of Industry and Company annual maintenance budget. H1: Company interest level towards Maintenance agency services is independent of the type of Industry and Company annual maintenance budget. 4 H0: Existing industries are not interested in services provided by maintenance agency. H1: Existing industries are interested in services provided by maintenance agency. Perception 5 H0: Existing industries are not having good perception towards maintenance agency. H1: Existing industries are having good perception towards maintenance agency. 6 H0: Company Perception towards Maintenance Agency is not independent of the type of Industry and Company annual maintenance budget. H1: Company Perception towards Maintenance Agency is independent of the type of Industry and Company annual maintenance budget. Attitude 7 H0: There is no significant difference among type of Industry or company annual maintenance budget regarding decision of purchasing maintenance agency services. H1: There is significant difference among type of Industry or company annual maintenance budget regarding decision of purchasing maintenance agency services.
  • 52. 38 8 H0: Existing industries are not purchased services provided by maintenance agency. H1: Existing industries are purchased services provided by maintenance agency. 4.4. Research Design For this research we used Descriptive type research Design. 4.5. Sampling Method We used simple random sampling method to select Company plot in GIDCs but if in one plot more than one company used convenience sampling method to select sample from that particular plot for completing quota for our research. 4.6. Data collection Instrument For this research we used questionnaire for collecting the information from the respondents. (Refer Annexure I) 4.7. Sampling Unit All 15534 industrial units which are registered in Baroda region are able to became sample. 4.8. Sample Size We are taken 400 industries as respondents for collecting the information for the research.
  • 54. 39 5.1. Demographic Profile Table 5.1 Demographic Profile Frequency Percentage Area Makarpura GIDC 86 21.50 Pore GIDC 40 10.00 Nandesari GIDC 18 4.50 Ranoli GIDC 97 24.25 Salvi GIDC 63 15.75 Vagodia GIDC 96 24.00 Type of Industry Machine work Industry 256 64.00 Fabrication Industry 48 12.00 Sheet Metal Work Industry 20 5.00 Foundry Industry 40 10.00 Service Industry 12 3.00 Others 24 6 Cement Industry Chemical Industry Paint Industry Pharmaceutical Industry Annual Maintenance Budget (Rs.) Below 4999 55 13.75 5000 to 14999 192 48.00 15000 to 24999 82 20.50 25000 to 34999 20 5.00 35000 to 44999 27 6.75 Above 45000 24 6.00 5.2. Response Rate = 400 ∗ 100 435 = 90.9 %
  • 55. 40 5.3. Questionnaire Analysis Q-1: Do you have machinery in your company? Table 5.2 Machinery basic Data Particulars Frequency Yes 400 No 0 Fig 5.1 Machinery basic Data Interpretation: This question is one of the basic filter question, If answer is Yes then one can consider further response of that respondent otherwise rejected that questionnaire. So 400 means 100 % respondent whose answer is Yes are consider as respondent in this research. 100% 0% 0% 20% 40% 60% 80% 100% 120% Yes No
  • 56. 41 Q-2: Rank following type of machinery based on number of machine you have of that type. Table 5.3 Type of Machinery Particulars Rank Mean Conventional 1 2.65 Semi Automatic 2 1.29 Automatic 3 0.25 Fig 5.2 Type of Machinery Interpretation: This question is used to generate interaest and to know which type of machinery expertise required by maintenance agency to get success in future. Based on responces companies have 63.19% conventional machinery, 30.85 % Semi Automatic machinery and 5.96 % Automatic machinery in Baroda. 63.19% 30.85% 5.96% 0.00% 10.00% 20.00% 30.00% 40.00% 50.00% 60.00% 70.00% Conventional Semi Automatic Automatic
  • 57. 42 Q-3: For Operational Machinery, Rank based on usage in operation. Table 5.4 Operational Machinery Usage Particulars Rank Mean Percentage Lathe m/c 1 9.90 16.46 Milling m/c 4 5.88 9.77 Boring m/c 5 4.26 7.08 Shaper m/c 7 3.70 6.15 Drilling m/c 2 8.92 14.83 Hobbing m/c 13 1.07 1.78 Cutting m/c 3 8.09 13.45 Wire cut m/c 17 0.54 0.89 Heating Equipments 9 2.42 4.02 Polishing/Grinding m/c 8 2.89 4.80 Moulding m/c 12 1.14 1.89 Sand Mixer 14 1.00 1.66 Knockout m/c 18 0.43 0.71 Forging m/c 16 0.68 1.13 Rolling m/c 10 2.25 3.74 Welding Equipments 6 4.09 6.79 Sort blasting m/c 15 0.83 1.37 Bending/Punching m/c 11 2.06 3.42 Interpretation: If machinery usage is incresed then its maintenance problem occuring rate also increase. By knowing which Operational machinery used more here try to find which machinery expertise will be required mainly by Maintenance agency in future. Based on responces companies are maximum using Operational machinery like Lathe m/c (16.46 %), Drilling m/c (14.83 %), Cutting m/c (13.45 %), Milling m/c (9.77 %), Boring m/c (7.08 %), Welding Equipments (6.79 %) and Shaper m/c (6.15 %) in Baroda; Companies are
  • 58. 43 Fig 5.3 Operational Machinery Usage moderate way using Operational machinery like Polishing/Grinding m/c (4.80 %), Heating Equipments (4.02 %), Rolling m/c (3.74 %) and Bending/Punching m/c (3.42 % ) in Baroda; While Companies are very less using Operational machinery like Moulding m/c (1.89 % ), Hobbing m/c (1.78 % ), Sand Mixer (1.66 % ), Sort blasting m/c (1.37 % ), Forging m/c (1.13 % ), Wire cut m/c (0.89 % ) and Knockout m/c (0.71 %) in Baroda. By using Table 5.4 it can be interpreted that to get success in Baroda initial stage Maintenance agency should get expertise in Operational machinery like Lathe m/c, Drilling m/c, Cutting m/c, Milling m/c, Boring m/c, Welding Equipments and Shaper m/c maintenance works; then move towards other Operational machinery expertise. 0.00% 2.00% 4.00% 6.00% 8.00% 10.00% 12.00% 14.00% 16.00% 18.00% Lathem/c Millingm/c Boringm/c Shaperm/c Drillingm/c Hobbingm/c Cuttingm/c Wirecutm/c HeatingEquipments Polishing/Grindingm/c Mouldingm/c SandMixer Knockoutm/c Forgingm/c Rollingm/c WeldingEquipments Sortblastingm/c Bending/Punchingm/c
  • 59. 44 No. of Operational machinery In Companies. Table 5.5 No. of Operational Machinery Particulars Mean (Units) Percentage Lathe m/c 2.92 20.15 Milling m/c 1.50 10.37 Boring m/c 1.05 7.26 Shaper m/c 0.88 6.08 Drilling m/c 2.02 13.96 Hobbing m/c 0.38 2.63 Cutting m/c 1.14 7.88 Wire cut m/c 0.07 0.48 Heating Equipments 0.43 2.97 Polishing/Grinding m/c 0.70 4.84 Moulding m/c 0.24 1.66 Sand Mixer 0.18 1.24 Knockout m/c 0.09 0.63 Forging m/c 0.15 1.04 Rolling m/c 0.75 5.18 Welding Equipments 1.42 9.82 Sort blasting m/c 0.23 1.59 Bending/Punching m/c 0.32 2.22 Interpretation: If no. of machinery is more then only generate expertise to solve it maintenance problem become worthful. By knowing which Operational machinery is more in number Maintenance agency should try to develop more expertise for that type of machinery. Based on responces companies have Operational machinery like Lathe m/c (20.15 %), Drilling m/c (13.96 %), Milling m/c (10.37 %), Welding Equipments (9.82 %), Cutting m/c (7.88 %), Boring m/c (7.26 %), Shaper m/c (7.08 %), Rolling m/c (5.18 %), Polishing/Grinding m/c (4.84 %), Heating Equipments (2.97 %), Hobbing m/c
  • 60. 45 Fig 5.4 No. of Operational Machinery (2.63 % ), Bending/Punching m/c (2.22 %), Moulding m/c (1.66 %), Sort blasting m/c (1.59 %), Sand Mixer (1.24 %), Forging m/c (1.04 %), Knockout m/c (0.63 %) and Wire cut m/c (0.48 %) in Baroda. By using Table 5.5 it can be interpreted that to get success in Baroda initial stage Maintenance agency should get expertise in Operational machinery like Lathe m/c, Drilling m/c, Milling m/c, Welding Equipments, Cutting m/c, Boring m/c, Shaper m/c, Rolling m/c and Polishing/Grinding m/c maintenance works; then move towards other operational machinery expertise. 0.00% 5.00% 10.00% 15.00% 20.00% 25.00% Lathem/c Millingm/c Boringm/c Shaperm/c Drillingm/c Hobbingm/c Cuttingm/c Wirecutm/c HeatingEquipments Polishing/Grindingm/c Mouldingm/c SandMixer Knockoutm/c Forgingm/c Rollingm/c WeldingEquipments Sortblastingm/c Bending/Punchingm/c
  • 61. 46 Average age of Operational machinery in Companies. Table 5.6 Average age of Operational Machinery Particulars Mean (Years) Lathe m/c 7.24 Milling m/c 6.83 Boring m/c 6.73 Shaper m/c 6.04 Drilling m/c 8.05 Hobbing m/c 7.00 Cutting m/c 7.37 Wire cut m/c 5.67 Heating Equipments 8.87 Polishing/Grinding m/c 8.95 Moulding m/c 9.14 Sand Mixer 9.67 Knockout m/c 7.33 Forging m/c 6.00 Rolling m/c 8.11 Welding Equipments 7.07 Sort blasting m/c 8.20 Bending/Punching m/c 9.46 Interpretation: If machinery age is more then chances of its break down in high means more scope for its maintenance problem. By knowing which Operational machinery age is more, Maintenance agency should try to develop more expertise for that type of machinery. Based on responces companies have Operational machinery of with average age of 9.67 years old Sand Mixer, 9.46 years old Bending/Punching m/c, 9.14 years old Moulding m/c, 8.95 years old Polishing/Grinding m/c, 8.87 years old Heating Equipments, 8.20 years old Sort blasting m/c, 8.11 years old Rolling m/c, 8.05 years old Drilling m/c, 7.37 years old Cutting m/c, 7.33 years old Knockout m/c, 7.24 years old Lathe m/c,
  • 62. 47 Fig 5.5 Average age of Operational Machinery 7.07 years old Welding Equipments, 7.00 years old Hobbing m/c, 6.83 years old Milling m/c, 6.73 years old Boring m/c, 6.04 years old Shaper m/c, 6.00 years old Forging m/c, and 5.67 years old Wire cut m/c in Baroda. Based on this data it interpreted that all Operational machinery have age is around more than 6 years so warranty periods are over and good scope for maintenance works so Maintenance agency will try to develop expertise for all Operational machinery. 0 2 4 6 8 10 12 Lathem/c Millingm/c Boringm/c Shaperm/c Drillingm/c Hobbingm/c Cuttingm/c Wirecutm/c HeatingEquipments Polishing/Grindingm/c Mouldingm/c SandMixer Knockoutm/c Forgingm/c Rollingm/c WeldingEquipments Sortblastingm/c Bending/Punchingm/c Years
  • 63. 48 Q-4: For Conveying Machinery, Rank based on usage in operation. Table 5.7 Conveying Machinery Usage Particulars Rank Mean Percentage Crain 1 1.73 74.92 Bucket Elevator 2 0.27 11.62 Belt Conveyor 3 0.24 10.42 Pipe Line 4 0.07 3.04 Fig 5.6 Conveying Machinery Usage Interpretation: If machinery usage is incresed then its maintenance problem occuring rate also increase. By knowing which Conveying machinery used more here try to find which machinery expertise will be required mainly by Maintenance agency in future. Based on responces companies are maximum using Crain (74.92 %) for Conveying purpose in Baroda. Companies are also using Buckete Elevator (11.62 %), Belt Conveyor (10.42 %) and Pipeline (3.04 %) for Conveying purpose in Baroda. Thus to get success in Baroda Crain maintenance work expertise is essential for Maintenance agency. 0.00% 10.00% 20.00% 30.00% 40.00% 50.00% 60.00% 70.00% 80.00% Crain Bucket Elevator Belt Conveyor Pipe Line
  • 64. 49 No. of Conveying machinery In Companies. Table 5.8 No. of Conveying Machinery Particulars Mean (Unit) Percentage Crain 1.28 42.51 Bucket Elevator 0.23 7.61 Belt Conveyor 0.42 13.73 Pipe Line 1.09 36.14 Fig 5.7 No. of Conveying Machinery Interpretation: If no. of machinery is more then only generate expertise to solve it maintenance problem become worthful. By knowing which Conveying machinery is more in number Maintenance agency should try to develop more expertise for that type of machinery. Based on responces companies have mainly Crain (42.51) % and Pipe line (36.14 % - used in Chemical industries mainly but in large quantity) as Conveying machinery in Baroda; Companies also have Belt conveyor (13.74 %) and Bucket Elevator (7.61 %) for Conveying purpose in Baroda. Thus to get success in Baroda Crain maintenance work expertise is essential for Maintenance agency at initial stage and then move towards other Conveying machinery expertise. 0.00% 5.00% 10.00% 15.00% 20.00% 25.00% 30.00% 35.00% 40.00% 45.00% Crain Bucket Elevator Belt Conveyor Pipe Line
  • 65. 50 Average age of Conveying machinery in Companies. Table 5.9 Average age of Conveying Machinery Particulars Mean (Years) Crain 7.22 Bucket Elevator 8.48 Belt Conveyor 8.23 Pipe Line 6.85 Fig 5.8 Average age of Conveying Machinery Interpretation: If machinery age is more then chances of its break down in high means more scope for its maintenance problem. By knowing which Conveying machinery age is more, Maintenance agency should try to develop more expertise for that type of machinery. Based on responces companies have 8.48 years old Bucket Elevator, 8.23 years old Belt conveyor, 7.22 years old Crain and 6.85 years old pipelines as Conveying machinery in Baroda. All Conveying machinery have age is around more than 7 years so warranty periods are over and good scope for maintenance works so Maintenance agency will try to develop expertise for all Conveying machinery. 0 1 2 3 4 5 6 7 8 9 Crain Bucket Elevator Belt Conveyor Pipe Line Years
  • 66. 51 Q-5: For Power supply Machinery, Rank based on usage in operation. Table 5.10 Power supply Machinery Usage Particulars Rank Mean Percentage Motor 2 0.07 22.05 Generator 1 0.16 50.39 Transformer 3 0.05 14.96 Electric Panel 4 0.04 12.59 Fig 5.9 Power supply Machinery Usage Interpretation: If machinery usage is incresed then its maintenance problem occuring rate also increase. By knowing which Power supply machinery used more here try to find which machinery expertise will be required mainly by Maintenance agency in future. Based on responces companies are maximum using Generator (50.39 %) for Power supply purpose in Baroda. Companies are also using Motor (22.05 %), Transformer (14.96 %) and Electric Panel (12.59 %) for Power supply purpose in Baroda. Thus to get success in Baroda Generator maintenance work expertise is essential for Maintenance agency. 0.00% 10.00% 20.00% 30.00% 40.00% 50.00% 60.00% Motor Generator Transformer ElectricPanel
  • 67. 52 No. of Power supply machinery In Companies. Table 5.11 No. of Power supply Machinery Particulars Mean (Unit) Percentage Motor 0.35 81.28 Generator 0.06 14.04 Transformer 0.01 2.34 Electric Panel 0.01 2.34 Fig 5.10 No. of Power supply Machinery Interpretation: If no. of machinery is more then only generate expertise to solve it maintenance problem become worthful. By knowing which Power supply machinery is more in number Maintenance agency should try to develop more expertise for that type of machinery. Based on responces companies have mainly motor (81.28 %) as Power supply machinery in Baroda; Companies also have Generator (14.04 %), Transformer (2.34 %) and Electric panel (2.34 %) for Power supply purpose in Baroda. Thus to get success in Baroda Motor maintenance work expertise is essential for Maintenance agency at initial stage and then move towards other Power supply machinery expertise. 0.00% 10.00% 20.00% 30.00% 40.00% 50.00% 60.00% 70.00% 80.00% 90.00% Motor Generator Transformer ElectricPanel
  • 68. 53 Average age of Power supply machinery in Companies. Table 5.12 Average age of Power supply Machinery Particulars Mean (Years) Motor 6.86 Generator 9.5 Transformer 5 Electric Panel 5 Fig 5.11 Average age of Power supply Machinery Interpretation: If machinery age is more then chances of its break down in high means more scope for its maintenance problem. By knowing which Power supply machinery age is more, Maintenance agency should try to develop more expertise for that type of machinery. Based on responces companies have 9.5 years old Generator, 6.86 years old Motor, 5.00 years old Transformer and Electric panel as Power supply machinery in Baroda. All Power supply machinery have age is around more than 5 years so warranty periods are over and good scope for maintenance works so Maintenance agency will try to develop expertise for all Power supply machinery. 0 1 2 3 4 5 6 7 8 9 10 Motor Generator Transformer ElectricPanel Years
  • 69. 54 Q-6: Do you use machinery of different manufacturer? Table 5.13 Different Manufacturer machinery usage Particulars Frequency Yes 365 No 35 Fig 5.12 Different Manufacturer machinery usage Interpretation: This question is used to measure Intention, because if company have only one manufacturer machinery then manufacturer maintenance services are better option and do not easily purchase Maintenance agency services. Based on responces around 91.25 % companies in Baroda are using machinery of different manufacture and 8.75 % companies in Baroda are using machinery of same different manufacture. 91.25% 8.75% 0.00% 10.00% 20.00% 30.00% 40.00% 50.00% 60.00% 70.00% 80.00% 90.00% 100.00% Yes No
  • 70. 55 Q-7: Do you have maintenance department in your company? Table 5.14 Maintenance Department Inquiry Particulars Frequency Yes 55 No 345 Fig 5.13 Maintenance Department Inquiry Interpretation: This question is used to measure Intention, because if company have own maintenance department then company do not easily purchase Maintenance agency services. Based on responces around 13.75 % companies in Baroda have own maintenance department and 86.25 % companies in Baroda do not have own maintenance department which are prospected target at initial stage. 13.75% 86.25% 0.00% 10.00% 20.00% 30.00% 40.00% 50.00% 60.00% 70.00% 80.00% 90.00% 100.00% Yes No
  • 71. 56 If Yes then your maintenance department, Table 5.15 Maintenance Department Ability Particulars Frequency Within specific time solve all maintenance problems 36 Take more time to solve all maintenance problems 11 Don’t able to solve all maintenance problems 8 Fig 5.14 Maintenance Department Ability Interpretation: This question is used to measure Intention of company having maintenance department, because if company having own maintenance department but do not satisfied with their maintenance department then posibility they will purchase Maintenance agency services. Out of 55 companies which having maintenance department around 65.45 % maintenance department within specific time solve all maintenance problems; 20 % maintenance department take more time to solve all maintenance problems and 14.55 % maintenance department don’t able to solve all maintenance problems. So all companies which have maintenance deparetment which take more time to solve all maintenance problems and don’t able to solve all maintenance problems are also prospected target at initial stage. 65.45% 20% 14.55% 0.00% 10.00% 20.00% 30.00% 40.00% 50.00% 60.00% 70.00% Within specific time solve all maintenanceproblems Take more time to solve all maintenanceproblems Don’t able to solve all maintenanceproblems
  • 72. 57 How many man powers in your maintenance department? Table 5.16 Maintenance Department Man power Particulars Only Permanent Both Permanent and Contract Only Contract Less than 5 39 12 0 Between 5 to 10 0 0 4 Fig 5.15 Maintenance Department Man power Interpretation: This question is used to measure Intention of company having maintenance department, because if company having own maintenance department but required more man power and having more man power also dont able to solve company maintenance problem effectivly then they they will purchase Maintenance agency services. Out of 55 companies which having maintenance department around 70.91 % maintenance department have only parmenent maintenance employess in quantity of less than 5; 7.27 % maintenance department have both parmenent and contract based maintenance employess in quantity of less than 5 each and 81.82 % maintenance department have only contract based maintenance employess in quantity between 5 to 10. 70.91% 7.27% 00 0 81.82% 0.00% 10.00% 20.00% 30.00% 40.00% 50.00% 60.00% 70.00% 80.00% 90.00% Only Permanent Both Permanent and Contract Only Contract Less than 5 Between 5 to 10
  • 73. 58 Q-8: Are you aware about other maintenance agency? Table 5.17 Awareness of other Maintenance agency Particulars Frequency Yes 400 No 0 Fig 5.16 Awareness of other Maintenance agency Interpretation: This question is used to measure Intention, because if company is aware about other maintenance agency then might be company is using that other maintenance agency services means manufacturer maintenance services then company do not easily purchase Maintenance agency services unless find more benefit in it. Based on responces of 400 companies all 100 % companies in Baroda are aware about other maintenance agency, so they can purchase Maintenance agency services if Maintenance agency is able to provide extra benefit. 100% 0% 0% 20% 40% 60% 80% 100% 120% Yes No
  • 74. 59 If Yes then are you having annual maintenance contract? Table 5.18 Other Maintenance agency AMC Particulars Frequency Yes 64 No 336 Fig 5.17 Other Maintenance agency AMC Interpretation: This question is used to measure Intention, because if company have annual maintenance contact of other maintenance agency means manufacturer maintenance contract then company do not able to purchase Maintenance agency services at initial basis and if company is satisfied with that contract then company dont purchase Maintenance agency services in future also. Based on responces around 16 % companies in Baroda have annual maintenance contract of other maintenance agency and 84 % companies in Baroda do not have annual maintenance contract of other maintenance agency. So companies which do not have AMC are prospected target at initial stage and companies which dissatisfied with current AMC are prospected target for Maintenance Agency. 16% 84% 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% Yes No
  • 75. 60 Q-9: Do your most of the machinery come under warranty period? Table 5.19 Machinery warranty period Inquiry Particulars Frequency Yes 64 No 336 Fig 5.18 Machinery warranty period Inquiry Interpretation: This question is used to measure Intention, because if company machinery come under warrenty period then company use manufacturer maintenance services and do not purchase Maintenance agency servies at initial stage. Based on responces around 3 % companies in Baroda having machinery which come under warrenty periods and 97 % companies in Baroda do not having machinery which come under warrenty periods which are prospected target for Maintenance Agency. 3% 97% 0% 20% 40% 60% 80% 100% 120% Yes No
  • 76. 61 Q-10: Likert Scale Analysis, Statement 1: Company is satisfied with current maintenance practice. Table 5.20 Likert Scale: Statement 1 Particulars Frequency Mean Strongly Disagree 0 3.03 Disagree 144 Neutral 104 Agree 148 Strongly Agree 4 Fig 5.19 Likert Scale: Statement 1 Interpretation: This question is used to measure Intention, Based on responces, Companies in Baroda are neutral with the statement ‘Company is satisfied with current maintenance practice.’ because their response mean is 3.03; Where 37 % Companies are agree with this statement and 36 % Companies are disagree with this statement. 0% 36% 26% 37% 1% 0% 5% 10% 15% 20% 25% 30% 35% 40% SD D N A SA
  • 77. 62 Statement 2: Company is planning to improve its maintenance practices. Table 5.21 Likert Scale: Statement 2 Particulars Frequency Mean Strongly Disagree 0 3.87 Disagree 4 Neutral 60 Agree 320 Strongly Agree 16 Table 5.20 Likert Scale: Statement 2 Interpretation: This question is used to measure Intention, Based on responces, Companies in Baroda are agree with the statement ‘Company is planning to improve its maintenance practices.’ because their response mean is 3.87; Where 87 % Companies are agree with this statement. 0% 1% 15% 80% 4% 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% SD D N A SA
  • 78. 63 Statement 3: Company machine manufacturer provides excellent maintenance services. Table 5.22 Likert Scale: Statement 3 Particulars Frequency Mean Strongly Disagree 0 3.14 Disagree 75 Neutral 197 Agree 124 Strongly Agree 4 Fig 5.21 Likert Scale: Statement 3 Interpretation: This question is used to measure Interest, Based on responces, Companies in Baroda are neutral with the statement ‘Company machine manufacturer provides excellent maintenance services.’ because their response mean is 3.14; Where 31 % Companies are agree with this statement. 0% 19% 49% 31% 1% 0% 10% 20% 30% 40% 50% 60% SD D N A SA
  • 79. 64 Statement 4: Company is paying reasonable price to current maintenance agency for servicing machinery. Table 5.23 Likert Scale: Statement 4 Particulars Frequency Mean Strongly Disagree 0 3.46 Disagree 24 Neutral 168 Agree 198 Strongly Agree 8 Fig 5.22 Likert Scale: Statement 4 Interpretation: This question is used to measure Interest, Based on responces, Companies in Baroda are neutral with the statement ‘Company is paying reasonable price to current maintenance agency for servicing machinery.’ because their response mean is 3.46; Where 49 % Companies are agree with this statement. 1% 6% 42% 49% 2% 0% 10% 20% 30% 40% 50% 60% SD D N A SA
  • 80. 65 Statement 5: Breakdown leads to shutdown in your company. Table 5.24 Likert Scale: Statement 5 Particulars Frequency Mean Strongly Disagree 8 3.05 Disagree 151 Neutral 80 Agree 133 Strongly Agree 28 Fig 5.23 Likert Scale: Statement 5 Interpretation: This question is used to measure Interest, Based on responces, Companies in Baroda are neutral with the statement ‘Breakdown leads to shutdown in your company.’ because their response mean is 3.05; Where 33 % Companies are agree with this statement and 38 % Companies are disagree with this statement. 2% 38% 20% 33% 7% 0% 5% 10% 15% 20% 25% 30% 35% 40% SD D N A SA
  • 81. 66 Statement 6: For Company, prevention of breakdown is important aspect. Table 5.25 Likert Scale: Statement 6 Particulars Frequency Mean Strongly Disagree 0 4.12 Disagree 4 Neutral 24 Agree 292 Strongly Agree 80 Fig 5.24 Likert Scale: Statement 6 Interpretation: This question is used to measure Interest, Based on responces, Companies in Baroda are agree with the statement ‘For Company, prevention of breakdown is important aspect.’ because their response mean is 4.12; Where 73 % Companies are agree with this statement and 20 % Companies are strongly agree with this statement. 0% 1% 6% 73% 20% 0% 10% 20% 30% 40% 50% 60% 70% 80% SD D N A SA
  • 82. 67 Statement 7: Maintenance agency should provide all maintenance services under one roof. Table 5.26 Likert Scale: Statement 7 Particulars Frequency Mean Strongly Disagree 0 4.22 Disagree 4 Neutral 28 Agree 241 Strongly Agree 127 Table 5.25 Likert Scale: Statement 7 Interpretation: This question is used to measure Interest, Based on responces, Companies in Baroda are agree with the statement ‘Maintenance agency should provide all maintenance services under one roof.’ because their response mean is 4.22; Where 60 % Companies are agree with this statement and 32 % Companies are strongly agree with this statement. 0% 1% 7% 60% 32% 0% 10% 20% 30% 40% 50% 60% 70% SD D N A SA
  • 83. 68 Statement 8: Maintenance agency should provide 24x7 maintenance services. Table 5.27 Likert Scale: Statement 8 Particulars Frequency Mean Strongly Disagree 0 4.16 Disagree 4 Neutral 52 Agree 222 Strongly Agree 122 Fig 5.26 Likert Scale: Statement 8 Interpretation: This question is used to measure Interest, Based on responces, Companies in Baroda are agree with the statement ‘Maintenance agency should provide 24x7 maintenance services.’ because their response mean is 4.16; Where 56 % Companies are agree with this statement and 30 % Companies are strongly agree with this statement. 0% 1% 13% 56% 30% 0% 10% 20% 30% 40% 50% 60% SD D N A SA
  • 84. 69 Statement 9: Maintenance agency should provide installment payment option. Table 5.28 Likert Scale: Statement 9 Particulars Frequency Mean Strongly Disagree 0 4.04 Disagree 8 Neutral 68 Agree 225 Strongly Agree 99 Fig 5.27 Likert Scale: Statement 9 Interpretation: This question is used to measure Interest, Based on responces, Companies in Baroda are agree with the statement ‘Maintenance agency should provide installment payment option.’ because their response mean is 4.04; Where 56 % Companies are agree with this statement and 25 % Companies are strongly agree with this statement. 0% 2% 17% 56% 25% 0% 10% 20% 30% 40% 50% 60% SD D N A SA
  • 85. 70 Statement 10: Maintenance agency should visit regularly every month either breakdown or not, in an organization. Table 5.29 Likert Scale: Statement 10 Particulars Frequency Mean Strongly Disagree 0 3.88 Disagree 4 Neutral 80 Agree 276 Strongly Agree 40 Fig 5.28 Likert Scale: Statement 10 Interpretation: This question is used to measure Interest, Based on responces, Companies in Baroda are agree with the statement ‘Maintenance agency should visit regularly every month either breakdown or not, in an organization.’ because their response mean is 3.88; Where 69 % Companies are agree with this statement. 0% 1% 20% 69% 10% 0% 10% 20% 30% 40% 50% 60% 70% 80% SD D N A SA
  • 86. 71 Statement 11: Maintenance agency has more expertise in comparison to internal maintenance department. Table 5.30 Likert Scale: Statement 11 Particulars Frequency Mean Strongly Disagree 0 3.94 Disagree 4 Neutral 60 Agree 292 Strongly Agree 44 Fig 5.29 Likert Scale: Statement 11 Interpretation: This question is used to measure Perception, Based on responces, Companies in Baroda are agree with the statement ‘Maintenance agency has more expertise in comparison to internal maintenance department.’ because their response mean is 3.94; Where 73 % Companies are agree with this statement. 0% 1% 15% 73% 11% 0% 10% 20% 30% 40% 50% 60% 70% 80% SD D N A SA
  • 87. 72 Statement 12: Maintenance agency is able to solve maintenance problem in different no. of ways. Table 5.31 Likert Scale: Statement 12 Particulars Frequency Mean Strongly Disagree 0 3.87 Disagree 0 Neutral 76 Agree 300 Strongly Agree 24 Fig 5.30 Likert Scale: Statement 12 Interpretation: This question is used to measure Perception, Based on responces, Companies in Baroda are agree with the statement ‘Maintenance agency is able to solve maintenance problem in different no. of ways.’ because their response mean is 3.87; Where 75 % Companies are agree with this statement. 0% 0% 19% 75% 6% 0% 10% 20% 30% 40% 50% 60% 70% 80% SD D N A SA
  • 88. 73 Statement 13: Maintenance agency is economical. Table 5.32 Likert Scale: Statement 13 Particulars Frequency Mean Strongly Disagree 0 3.57 Disagree 4 Neutral 179 Agree 201 Strongly Agree 16 Fig 5.31 Likert Scale: Statement 13 Interpretation: This question is used to measure Perception, Based on responces, Companies in Baroda are agree with the statement ‘Maintenance agency is economical.’ because their response mean is 3.57; Where 50 % Companies are agree with this statement. 0% 1% 45% 50% 4% 0% 10% 20% 30% 40% 50% 60% SD D N A SA
  • 89. 74 Statement 14: Maintenance agency is able to solve maintenance problem quickly compare to maintenance department. Table 5.33 Likert Scale: Statement 14 Particulars Frequency Mean Strongly Disagree 0 3.73 Disagree 20 Neutral 91 Agree 266 Strongly Agree 23 Fig 5.32 Likert Scale: Statement 14 Interpretation: This question is used to measure Perception, Based on responces, Companies in Baroda are agree with the statement ‘Maintenance agency is able to solve maintenance problem quickly compare to maintenance department.’ because their response mean is 3.73; Where 67 % Companies are agree with this statement. 0% 5% 22% 67% 6% 0% 10% 20% 30% 40% 50% 60% 70% SD D N A SA
  • 90. 75 Statement 15: Maintenance agencies don’t response on time when required. Table 5.34 Likert Scale: Statement 15 Particulars Frequency Mean Strongly Disagree 0 2.9 Disagree 140 Neutral 172 Agree 76 Strongly Agree 12 Fig 5.33 Likert Scale: Statement 15 Interpretation: This question is used to measure Perception, Based on responces, Companies in Baroda are neutral with the statement ‘Maintenance agencies don’t response on time when required.’ because their response mean is 2.9; Where 19 % Companies are agree with this statement and 35 % Companies are disagree with this statement 0% 35% 43% 19% 3% 0% 5% 10% 15% 20% 25% 30% 35% 40% 45% 50% SD D N A SA
  • 91. 76 Statement 16: Maintenance agency is better option compare to internal maintenance department. Table 5.35 Likert Scale: Statement 16 Particulars Frequency Mean Strongly Disagree 0 2.79 Disagree 4 Neutral 92 Agree 288 Strongly Agree 16 Fig 5.34 Likert Scale: Statement 16 Interpretation: This question is used to measure Perception, Based on responces, Companies in Baroda are neutral with the statement ‘Maintenance agency is better option compare to internal maintenance department.’ because their response mean is 2.79; Where 72 % Companies are agree with this statement. 0% 1% 23% 72% 4% 0% 10% 20% 30% 40% 50% 60% 70% 80% SD D N A SA
  • 92. 77 Statement 17: Maintenance agency is required for maintenance. Table 5.36 Likert Scale: Statement 17 Particulars Frequency Mean Strongly Disagree 0 3.89 Disagree 4 Neutral 64 Agree 304 Strongly Agree 28 Fig 5.35 Likert Scale: Statement 17 Interpretation: This question is used to measure Attitude, Based on responces, Companies in Baroda are agree with the statement ‘Maintenance agency is required for maintenance.’ because their response mean is 3.89; Where 76 % Companies are agree with this statement. 0% 1% 16% 76% 7% 0% 10% 20% 30% 40% 50% 60% 70% 80% SD D N A SA
  • 93. 78 Q-11: Will you purchase maintenance agency services in future? Table 5.37 Purchase Maintenance agency services in Future Particulars Frequency Yes 336 No 64 Fig 5.36 Purchase Maintenance agency services in Future Interpretation: This question is used to measure Attitude, Based on responces around 84 % companies in Baroda will purchase maintenance agency services in future (Positive attitude towards Maintenance agency services) and 16 % companies in Baroda will not purchase maintenance agency services in future (Negative attitude towards Maintenance agency services). 84% 16% 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% Yes No
  • 95. 79 Hypothesis 1: H0: Existing industries are not having positive intension towards maintenance agency services. H1: Existing industries are having positive intension towards maintenance agency services. Table 6.1 Hypothesis 1 No. Statement Mean 1 Company is satisfied with current maintenance practice. 3.03 3.45 2 Company is planning to improve its maintenance practices. 3.87 Fig 6.1 Hypothesis 1 Interpretation: From above Table 6.1 and Fig. 6.1, it can be interpreted that Existing industries are having positive intension towards maintenance agency services (Null Hypothesis will be rejected) because Intention likert scale statement mean is 3.45 greater than scale middle value 3.
  • 96. 80 Hypothesis 2: H0: Company Intension towards Maintenance agency services is not independent of the type of Industry and Company annual maintenance budget. H1: Company Intension towards Maintenance agency services is independent of the type of Industry and Company annual maintenance budget. Table 6.2 Hypothesis 2 (Chi-Square Tests) No. Statement Pearson Chi-Square Type of Industry Annual Budget 1 Company is satisfied with current maintenance practice. .000 .000 2 Company is planning to improve its maintenance practices. .000 .000 With 15 Degree of freedom Interpretation: From above Table 6.3, it can be interpreted that Company Intension towards Maintenance agency services is independent of the type of Industry and Company annual maintenance budget. (All value of chi-square (alpha) is less than 0.05)
  • 97. 81 Hypothesis 3: H0: Company interest level towards Maintenance agency services is not independent of the type of Industry and Company annual maintenance budget. H1: Company interest level towards Maintenance agency services is independent of the type of Industry and Company annual maintenance budget. Table 6.3 Hypothesis 3 (Chi-Square Tests) No. Statement Pearson Chi-Square Type of Industry Annual Budget 1 Company machine manufacturer provides excellent maintenance services. .000 .000 2 Company is paying reasonable price to current maintenance agency for servicing machinery. .000 .000 3 Breakdown leads to shutdown in your company. .000 .000 4 For Company, prevention of breakdown is important aspect. .000 .002 5 Maintenance agency should provide all maintenance services under one roof. .000 .001 6 Maintenance agency should provide 24x7 maintenance services. .000 .000 7 Maintenance agency should provide installment payment option. .000 .000 8 Maintenance agency should visit regularly every month either breakdown or not, in an organization. .000 .000 Interpretation: From above Table 6.3, it can be interpreted that Company interest level towards Maintenance agency services is independent of the type of Industry and Company annual maintenance budget. (All value of chi-square (alpha) is less than 0.05)
  • 98. 82 Hypothesis 4: H0: Existing industries are not interested in services provided by maintenance agency. H1: Existing industries are interested in services provided by maintenance agency. Table 6.4 Hypothesis 4 No. Statement Mean 1 Company machine manufacturer provides excellent maintenance services. 3.14 3.76 2 Company is paying reasonable price to current maintenance agency for servicing machinery. 3.46 3 Breakdown leads to shutdown in your company. 3.05 4 For Company, prevention of breakdown is important aspect. 4.12 5 Maintenance agency should provide all maintenance services under one roof. 4.22 6 Maintenance agency should provide 24x7 maintenance services. 4.15 7 Maintenance agency should provide installment payment option. 4.03 8 Maintenance agency should visit regularly every month either breakdown or not, in an organization. 3.88 Interpretation: From above Table 6.3 and Fig. 6.2, it can be interpreted that Existing industries are interested in services provided by maintenance agency (Null Hypothesis will be rejected) because Interest likert scale statement mean is 3.76 greater than scale middle value 3.
  • 99. 83 Fig 6.2 Hypothesis 4 Fig 6.3 Hypothesis 5
  • 100. 84 Hypothesis 5: H0: Existing industries are not having good perception towards maintenance agency. H1: Existing industries are having good perception towards maintenance agency. Table 6.5 Hypothesis 5 No. Statement Mean 1 Maintenance agency has more expertise in comparison to internal maintenance department 3.94 3.63 2 Maintenance agency is able to solve maintenance problem in different no. of ways. 3.87 3 Maintenance agency is economical. 3.57 4 Maintenance agency is able to solve maintenance problem quickly compare to maintenance department. 3.73 5 Maintenance agencies don’t response on time when required. 2.90 6 Maintenance agency is better option compare to internal maintenance department. 3.79 Interpretation: From above Table 6.5 and Fig. 6.3, it can be interpreted that Existing industries are having good perception towards maintenance agency. (Null Hypothesis will be rejected) because Interest likert scale statement mean is 3.63 greater than scale middle value 3.
  • 101. 85 Hypothesis 6: H0: Company Perception towards Maintenance Agency is not independent of the type of Industry and Company annual maintenance budget. H1: Company Perception towards Maintenance Agency is independent of the type of Industry and Company annual maintenance budget. Table 6.6 Hypothesis 6 (Chi-Square Tests) No. Statement Pearson Chi-Square Type of Industry Annual Budget 1 Maintenance agency has more expertise in comparison to internal maintenance department .000 .000 2 Maintenance agency is able to solve maintenance problem in different no. of ways. .000 .004 3 Maintenance agency is economical. .004 .000 4 Maintenance agency is able to solve maintenance problem quickly compare to maintenance department. .000 .001 5 Maintenance agencies don’t response on time when required. .000 .000 6 Maintenance agency is better option compare to internal maintenance department. .000 .000 Interpretation: From above Table 6.6, it can be interpreted that Company interest level towards Maintenance agency services is independent of the type of Industry and Company annual maintenance budget. (All value of chi-square (alpha) is less than 0.05)
  • 102. 86 Hypothesis 7: H0: There is no significant difference among type of Industry or company annual maintenance budget regarding decision of purchasing maintenance agency services. H1: There is significant difference among type of Industry or company annual maintenance budget regarding decision of purchasing maintenance agency services. Table 6.7 Hypothesis 7 (One way Anova) Sum of Squares df Mean Square F Sig. Type of Industry Between Groups 1.543 5 .309 2.329 .042 Within Groups 52.217 394 .133 Total 53.760 399 Company annual maintenance budget Between Groups 1.375 5 .275 2.069 .068 Within Groups 52.385 394 .133 Total 53.760 399 Interpretation: From above Table 6.7, Null hypotheses will be rejected for Type of Industry and it can be interpreted that there is significant difference among type of Industry regarding decision of purchasing maintenance agency services. (For Type of Industry value of significant is less than 0.05) From above Table 6.7, Null hypotheses will not be rejected for Company annual maintenance budget and it can be interpreted that there is no significant difference among company annual maintenance budget regarding decision of purchasing maintenance agency services. (For Company annual maintenance budget value of significant is greater than 0.05)
  • 103. 87 Hypothesis 8: H0: Existing industries are not purchased services provided by maintenance agency. H1: Existing industries are purchased services provided by maintenance agency. Table 6.8 Hypothesis 8 No. Statement Mean 1 Maintenance agency is required for maintenance. 3.89 Fig 6.4 Hypothesis 8 Interpretation: From above Table 6.8, Fig. 6.4, and Fig. 5.36 where Based on responces around 84 % companies in Baroda will purchase maintenance agency services in future (Positive attitude towards Maintenance agency services), it can be interpreted that Existing industries are purchased services provided by maintenance agency (Null Hypothesis will be rejected) because Interest likert scale statement mean is 3.89 greater than scale middle value 3.
  • 104. Chapter 7 Maintenance agency Profitability and Feasibility Analysis
  • 105. 88 7.1. Cost of Project 7.1.1. Fixed Investment Cost requirement for next 3 Years Table 7.1 Fixed Investment Cost requirement for next 3 Years All Amount in Rs. 1 Year 2 Year 3 Year unit Rs. Unit Rs. Unit Rs. Shop Deposit - 50000 - - - - Website charges - 15000 - - - - Toolbox 3 15000 - - 1 5000 Hand Drill 3 10000 - - 1 3000 Welding Machine 3 26500 - - 1 6000 Grinder/cutter 3 6000 - - 1000 Hacksaw 3 6000 - - 1 2000 Computer 1 22000 - - - - Printer 1 4500 - - - - Shop Furniture/ chairs - 30000 - - - - Vehicles Tata Chhota Hathi 2 560000 - - 1 280000 Cycle 1 1500 - - 1 1500 Total 746500 - 298000 To start any business initial amount is required for investment and to start maintenance agency as shown in Table 7.1 initially Rs. 746500 is required as fixed initial cost. During second year other investment is not required but during 3 year to match demand rate investment is required in equipments and vehicles around Rs. 298000.
  • 106. 89 7.1.2. Variable Cost requirement for next 3 Years Table 7.2 Variable Cost requirement for next 3 Years All Amount in Rs. 1 Year Monthly Cost 1 Year 2 Year Monthly Cost 2 Year 3 Year Monthly Cost 3 Year Shop Rent 5000 60000 5500 66000 6000 72000 Petrol/ Diesel 8000 96000 10000 120000 15000 180000 Electricity Bill 2500 30000 2500 30000 2500 3000 Telephone Bill 3000 36000 3000 36000 4000 48000 Stationary Cost 500 6000 700 8400 1000 12000 Hand drill - - - 1000 - - Welding Machine - - - 1000 - - Grinder/cutter - - - 500 - 1000 Employee Salary Diploma Mechanical >15 yr experience 38500 462000 40500 486000 43500 522000 >1 yr experience 5000 60000 6000 72000 8000 96000 >1 yr experience - - - - 5000 60000 Diploma electrical >2 yr experience 6000 72000 7000 84000 9000 108000 >2 yr experience - - - - 6000 72000 Computer operator 4500 54000 5500 66000 6500 78000 Telephone operator 4500 54000 5500 66000 6500 78000