SlideShare a Scribd company logo
1 of 10
Example Lean Six Sigma Charter
Enclosure 2, LSS Project Charter
Project Name: Improve the effectiveness and efficiency of the
BB computer
acquisition process
Date: November 15, 2014
Organization: CIO Deployment Champion: Mark Laptop
Project Sponsor: John Puter Black/Green Belt: Bill Desktop
Business Impact ($)
This project will address the computer acquisition process for
LSS BB training courses. The first two waves of training have
experienced delays and customer dissatisfaction due to late
delivery of computers and class disruptions to load required
software.
Due to exceptional work by Tom Peoples, the first two waves
were able to receive their computers during week 1 of training,
but
since pre-work is required before attending week 1 of training,
it is ideal for the BB’s to receive properly loaded computers
during
Team Accelerator training in order to complete the Minitab pre-
work and get comfortable with the George Group Virtual Coach
software tool.
The impact of late computers in worker non-productivity costs,
expediting costs, possible higher computer costs, and customer
dissatisfaction estimated at:
• $12K of Type 1
o Assumptions - 6 waves of BB training over the next 12
months following completion of project, $2000/wave of
additional
computer costs for expediting, etc.
• $48K of Type 2
o Assumptions - 6 waves of BB training over the next 12
months following completion of project, 40 hours of extra
expediting
and handling per wave, $75 per hour of labor
• Other Benefits (Type 3)
o Increased student learning and ultimately better project
success
Problem Statement
Where: The problem has been noticed at Shangri-la Higher
Education Training Center, the only training location to-date
When: The problem has been noticed since October 2004 to
date, covering the first two waves of LSS BB training.
What (output metrics):
• Quality metric #1: % of properly loaded laptop computers with
designated software load as measured by % of total
computers loaded correctly the 1st time
• Quality metric #2: % computers delivered by day 1 of Team
Accelerator training as measured by % of total computers
delivered late.
• Speed metric #1: time to prepare BB training computers as
measured by the time from final wave roster to all computers
ready
for delivery.
• Cost metric #1: Cost per fully loaded computer as measured
by total costs of computer readiness divided by total
computers delivered. Costs should not include expediting,
temporary computer costs, or excessive labor costs.
Extent: Baseline Quality metric #1: To date, X% of computers
are loaded correctly first time
Baseline Quality metric #2: To date, 0% of computers are
delivered by day 1 of Team Accelerator Training
Baseline Speed metric #1: To date, the average cycle time to
have a computer ready for delivery is 4 weeks
Baseline Cost metric #1: Current cost is $X,000 per computer
load.
Goal Statement (output metrics)
• Quality metric #1: Increase the percentage of BB computers
correctly loaded to 75% for wave 3, and 100% for all waves
thereafter
• Quality metric #2: Deliver 100% of the computers by day 1
Team Accelerator training for each wave, beginning with Wave
3
• Speed metric #1: Reduce the average cycle time per computer
load to 2 weeks, with minimal variation
• Cost metric #1: Reduce the cost per computer load to $YY,000
per computer
Project Scope (Horizontal and Vertical Scoping)
Start/stop point of process: the computer loading process
begins upon of delivery of BB wave roster to the IT department
and
ends with the delivery of the computer to the BB on the first
day of Team Accelerator training (vertical scoping)
In Scope: This project will address the laptop computer
acquisition process for LSS BB waves 3-10 (horizontal
scoping). The
team will implement process changes. There is a small project
budget of $1000 available for process changes or other project
work.
Out of scope: This project will not address network log-in
logistics, GB courses or any other course requiring computers.
Changes to the overall computer acquisition system are out-of-
scope.
Example Lean Six Sigma Charter
Enclosure 2, LSS Project Charter
Project Plan
Define – 12/5/2004 (Start date, first Monday after first week of
training + 2-4 weeks
Measure – 1/20/05 (allow for holidays and extra time need to
collect data)
Analyze – 2/15/05
Improve – 4/10/05 (allow time for pilot and results)
Control – 5/8/05 (start date plus 5 months)
Team Selection
Project Sponsor: John Puter 10%
Black Belt: Bill Desktop 100%
Master Black Belt coach: Ann C. Drive
Team Members:
IT person, Samual Harddriver 20%
IT person, Willis Thumbdrive 20%
Procurement, Julie Externaldrive 10%
Contracts, TBD 10%
Network Expert, TBD 5%
Signatures:
_______________________ ________________________
________________________
Deployment Champion Project Sponsor Financial
Rep
_______________________ ________________________
Black Belt / Green Belt Master Black Belt
Lean Six Sigma Project Charter
Enclosure 2, LSS Project Charter
Project Name: Date:
Organization: Deployment Champion:
Project Sponsor: Black/Green Belt:
Business Impact ($)
Problem Statement (What and Extent stated in terms of the
project output metrics)
Goal Statement (stated in terms of the project output metrics)
Project Scope (Horizontal and Vertical Scoping)
Project Plan (dates)
Lean Six Sigma Project Charter
Enclosure 2, LSS Project Charter
Team Selection
Signatures:
_______________________ ________________________
________________________
Deployment Champion Project Sponsor Financial
Rep
_______________________ ________________________
Black Belt / Green Belt Master Black Belt
Project Sponsor: John Puter 10%
Project Name: DMOSQDate: 2NOV16Organization: JFHQ-IN-
J3-Training BranchDeployment Champion_2: Mr. Joshua
ClarkProject Sponsor_2: COL Timothy WinslowBlackGreen
Belt: MAJ Chris DalrympleBusiness Impact Row1: The Indiana
Army National Guard must be able to select, retain, and develop
Soldiers throughout their career from initial entry to separation
or retirement. The average cost to train a Soldier is
$150,000.00 just to send a soldier through Basic and AIT, which
is the lowest level of training required to have a DMOSQ'd
soldier. The cost goes up exponentially depending on the
training, level, and length of time of the course. DMOSQ is
part of the 2015-2019 strategic plan p. 10 as objective 3-4 to
obtain NLT 85% DMOSQ and 100% AFSC. Objective 3-4
states, "Train and retain Soldiers, Airmen, and officers who are
qualified in current position. Identify Soldiers, Airmen, and
officers requiring military schools and duty position training
and enroll as required. Ensure that funding is secured and
available for AFSC/DMOSQ schools."Problem Statement What
and Extent stated in terms of the project output metricsRow1:
The percent DMOSQ is currently around 83%, which is below
the NGB goal of 85% and is under performing when compared
with its key competitor states of: California, Georgia, Ohio,
and Pennsylvania. Force structure opportunities, mission
selection, and training opportunity could potentially be missed
due to competitors ability to meet personnel readiness and
training.
Where: The problem has been notice at the state level through
metrics measured internally by JFHQ-IN-J3 and DPROS
database.
When: The problem has been noticed since 7 July 16 as part of
the organizational self assessment.
What: (Output Metrics):
Quality Metric #1: % DMOSQ
Quality Metric #2: Ratio of School Seat Traps to Non MOSQ
Quality Metric #3: %Allocation of school seat traps filled
Speed Metric #1: # of months to obtain DMOSQ for position
once vacancy is filled.
Cost Metric #1: Total cost lost school money due to school
failure and school reservation cancellations.
Goal Statement stated in terms of the project output
metricsRow1: The goal is to increase DMOSQ to exceed the
NGB Goal and to outperform 3 out of 4 of our key competitors
in DMOSQ.
Quality metric #1: 90% DMOSQ
Quality metric #2: 1:1
Quality metric #3: 95% School seats obligated
Speed metric #1: Average of 10 months to obtain DMOSQ
(Certain DMOSQ schools are much longer in length and will
cause average to skew average)
Cost metric #1: To reduce wasted school money by 80%.
Project Scope Horizontal and Vertical ScopingRow1: To
properly trap training allocations, then to allocate training seats
that has the best impact at improving the DMOSQ level in the
INARNG.
In Scope: This project will address the process for how JFHQ-
IN-J3 achieves DMOSQ as part if its strategic plan, Objective
3-4, which the team will recommend process changes to
increase qualification percentages.
Out of scope: This project will not address OES and NCOES
requirement as part of the Service Member's development. This
is an important part of the overall development of the officer or
enlisted soldier but such changes to this system are out-of-
scope. Project Plan datesRow1: Define-11/14/2016 (Starts first
day of course and last for 4 weeks)
Measure-12/15/2016 (Allow for holidays and extra time to
collect data)
Analyze-
Improve-3/15/2017 (Training seat traps conducted annually,
allocation are provided to MSC annually, metric that can be
improved are %DMOSQ, cost reduction, and school seat
obligation)
Control-4/15/2017(start date plus 5 months)Team
SelectionRow1: Project Sponsor: COL Timothy Winslow
Black Belt:
Master Black Belt Coach:
Team Members: (J3 Training shop, BDE S3 Section, Unit S3
and S1) LTC Bradly Compton,Deployment Champion_3: Black
Belt Green Belt_2: Project Sponsor_3: Financial Rep_2: Master
Black Belt_2:
Dominos quality issue (problem)
Break down the company’s operations based upon the
operations management course, making sure to cover the topics
from this course including:
· Strategy, how does their business operation support their
strategy?
· Supply chain, logistics, human resource development,
inventory management, customer service, quality, forecasting
· Include current & projected financial performance and
describe key metrics for their industry/segment
· Provide recommendations for how they might improve
operations for either financial gain or better customer service,
short-term and long-term
Please make sure you address the 10 strategic OM decisions
outlined in table 1.2 of the text.

More Related Content

Similar to Example Lean Six Sigma Charter Enclosure 2, LSS.docx

Assignment 8.14.docx
Assignment 8.14.docxAssignment 8.14.docx
Assignment 8.14.docxssuser562afc1
 
Find an example of a real project with a real project manager. The pr.pdf
Find an example of a real project with a real project manager. The pr.pdfFind an example of a real project with a real project manager. The pr.pdf
Find an example of a real project with a real project manager. The pr.pdfinfomalad
 
IMPORTANT label each projects title page as follow Project 1P.docx
IMPORTANT label each projects title page as follow Project 1P.docxIMPORTANT label each projects title page as follow Project 1P.docx
IMPORTANT label each projects title page as follow Project 1P.docxsheronlewthwaite
 
Unit III Project TopicPlease complete the information below .docx
Unit III Project TopicPlease complete the information below .docxUnit III Project TopicPlease complete the information below .docx
Unit III Project TopicPlease complete the information below .docxouldparis
 
Wedding Case StudyArie McQuarleyCSUWedding.docx
Wedding Case StudyArie McQuarleyCSUWedding.docxWedding Case StudyArie McQuarleyCSUWedding.docx
Wedding Case StudyArie McQuarleyCSUWedding.docxjessiehampson
 
Increasing the probability of program success
Increasing the probability of program successIncreasing the probability of program success
Increasing the probability of program successGlen Alleman
 
Software engineering srs library management assignment
Software engineering srs library management assignmentSoftware engineering srs library management assignment
Software engineering srs library management assignmentRajat Mittal
 
Type Individual ProjectUnit  Models in project management .docx
Type Individual ProjectUnit  Models in project management .docxType Individual ProjectUnit  Models in project management .docx
Type Individual ProjectUnit  Models in project management .docxcandycemidgley
 
Cmgt410
Cmgt410Cmgt410
Cmgt410joituy
 
Cmgt410 Entire Course
Cmgt410 Entire CourseCmgt410 Entire Course
Cmgt410 Entire CourseCMGT410
 
Cmgt 410 Entire Course
Cmgt 410 Entire CourseCmgt 410 Entire Course
Cmgt 410 Entire CourseCMGT410
 
Pmp project management professional free sample
Pmp project management professional free samplePmp project management professional free sample
Pmp project management professional free sampleNada Sallam
 
Running head  SIMPLIFIED PROJECT PLAN .docx
Running head  SIMPLIFIED PROJECT PLAN                          .docxRunning head  SIMPLIFIED PROJECT PLAN                          .docx
Running head  SIMPLIFIED PROJECT PLAN .docxrtodd599
 
CaseStudy - Business Analyst Project Objectives
CaseStudy - Business Analyst Project ObjectivesCaseStudy - Business Analyst Project Objectives
CaseStudy - Business Analyst Project ObjectivesZaranTech LLC
 
Systems Analysis & Design Project
Systems Analysis & Design Project Systems Analysis & Design Project
Systems Analysis & Design Project Amanda Blakley
 
Project Overview –Virtual PMO Services for PJM Students and Alum.docx
Project Overview –Virtual PMO Services for PJM Students and Alum.docxProject Overview –Virtual PMO Services for PJM Students and Alum.docx
Project Overview –Virtual PMO Services for PJM Students and Alum.docxwoodruffeloisa
 

Similar to Example Lean Six Sigma Charter Enclosure 2, LSS.docx (20)

Assignment 8.14.docx
Assignment 8.14.docxAssignment 8.14.docx
Assignment 8.14.docx
 
Find an example of a real project with a real project manager. The pr.pdf
Find an example of a real project with a real project manager. The pr.pdfFind an example of a real project with a real project manager. The pr.pdf
Find an example of a real project with a real project manager. The pr.pdf
 
IMPORTANT label each projects title page as follow Project 1P.docx
IMPORTANT label each projects title page as follow Project 1P.docxIMPORTANT label each projects title page as follow Project 1P.docx
IMPORTANT label each projects title page as follow Project 1P.docx
 
Unit III Project TopicPlease complete the information below .docx
Unit III Project TopicPlease complete the information below .docxUnit III Project TopicPlease complete the information below .docx
Unit III Project TopicPlease complete the information below .docx
 
Wedding Case StudyArie McQuarleyCSUWedding.docx
Wedding Case StudyArie McQuarleyCSUWedding.docxWedding Case StudyArie McQuarleyCSUWedding.docx
Wedding Case StudyArie McQuarleyCSUWedding.docx
 
Oscar Padilla, PMP
Oscar Padilla, PMPOscar Padilla, PMP
Oscar Padilla, PMP
 
Increasing the probability of program success
Increasing the probability of program successIncreasing the probability of program success
Increasing the probability of program success
 
Software engineering srs library management assignment
Software engineering srs library management assignmentSoftware engineering srs library management assignment
Software engineering srs library management assignment
 
Type Individual ProjectUnit  Models in project management .docx
Type Individual ProjectUnit  Models in project management .docxType Individual ProjectUnit  Models in project management .docx
Type Individual ProjectUnit  Models in project management .docx
 
Suchasmita Padhi Resume
Suchasmita Padhi ResumeSuchasmita Padhi Resume
Suchasmita Padhi Resume
 
Suchasmita Padhi Resume
Suchasmita Padhi ResumeSuchasmita Padhi Resume
Suchasmita Padhi Resume
 
Pep
PepPep
Pep
 
Cmgt410
Cmgt410Cmgt410
Cmgt410
 
Cmgt410 Entire Course
Cmgt410 Entire CourseCmgt410 Entire Course
Cmgt410 Entire Course
 
Cmgt 410 Entire Course
Cmgt 410 Entire CourseCmgt 410 Entire Course
Cmgt 410 Entire Course
 
Pmp project management professional free sample
Pmp project management professional free samplePmp project management professional free sample
Pmp project management professional free sample
 
Running head  SIMPLIFIED PROJECT PLAN .docx
Running head  SIMPLIFIED PROJECT PLAN                          .docxRunning head  SIMPLIFIED PROJECT PLAN                          .docx
Running head  SIMPLIFIED PROJECT PLAN .docx
 
CaseStudy - Business Analyst Project Objectives
CaseStudy - Business Analyst Project ObjectivesCaseStudy - Business Analyst Project Objectives
CaseStudy - Business Analyst Project Objectives
 
Systems Analysis & Design Project
Systems Analysis & Design Project Systems Analysis & Design Project
Systems Analysis & Design Project
 
Project Overview –Virtual PMO Services for PJM Students and Alum.docx
Project Overview –Virtual PMO Services for PJM Students and Alum.docxProject Overview –Virtual PMO Services for PJM Students and Alum.docx
Project Overview –Virtual PMO Services for PJM Students and Alum.docx
 

More from AASTHA76

(APA 6th Edition Formatting and St.docx
(APA 6th Edition Formatting and St.docx(APA 6th Edition Formatting and St.docx
(APA 6th Edition Formatting and St.docxAASTHA76
 
(a) Thrasymachus’ (the sophist’s) definition of Justice or Right o.docx
(a) Thrasymachus’ (the sophist’s) definition of Justice or Right o.docx(a) Thrasymachus’ (the sophist’s) definition of Justice or Right o.docx
(a) Thrasymachus’ (the sophist’s) definition of Justice or Right o.docxAASTHA76
 
(Glossary of Telemedicine and eHealth)· Teleconsultation Cons.docx
(Glossary of Telemedicine and eHealth)· Teleconsultation Cons.docx(Glossary of Telemedicine and eHealth)· Teleconsultation Cons.docx
(Glossary of Telemedicine and eHealth)· Teleconsultation Cons.docxAASTHA76
 
(Assmt 1; Week 3 paper) Using ecree Doing the paper and s.docx
(Assmt 1; Week 3 paper)  Using ecree        Doing the paper and s.docx(Assmt 1; Week 3 paper)  Using ecree        Doing the paper and s.docx
(Assmt 1; Week 3 paper) Using ecree Doing the paper and s.docxAASTHA76
 
(Image retrieved at httpswww.google.comsearchhl=en&biw=122.docx
(Image retrieved at  httpswww.google.comsearchhl=en&biw=122.docx(Image retrieved at  httpswww.google.comsearchhl=en&biw=122.docx
(Image retrieved at httpswww.google.comsearchhl=en&biw=122.docxAASTHA76
 
(Dis) Placing Culture and Cultural Space Chapter 4.docx
(Dis) Placing Culture and Cultural Space Chapter 4.docx(Dis) Placing Culture and Cultural Space Chapter 4.docx
(Dis) Placing Culture and Cultural Space Chapter 4.docxAASTHA76
 
(1) Define the time value of money.  Do you believe that the ave.docx
(1) Define the time value of money.  Do you believe that the ave.docx(1) Define the time value of money.  Do you believe that the ave.docx
(1) Define the time value of money.  Do you believe that the ave.docxAASTHA76
 
(chapter taken from Learning Power)From Social Class and t.docx
(chapter taken from Learning Power)From Social Class and t.docx(chapter taken from Learning Power)From Social Class and t.docx
(chapter taken from Learning Power)From Social Class and t.docxAASTHA76
 
(Accessible at httpswww.hatchforgood.orgexplore102nonpro.docx
(Accessible at httpswww.hatchforgood.orgexplore102nonpro.docx(Accessible at httpswww.hatchforgood.orgexplore102nonpro.docx
(Accessible at httpswww.hatchforgood.orgexplore102nonpro.docxAASTHA76
 
(a) The current ratio of a company is 61 and its acid-test ratio .docx
(a) The current ratio of a company is 61 and its acid-test ratio .docx(a) The current ratio of a company is 61 and its acid-test ratio .docx
(a) The current ratio of a company is 61 and its acid-test ratio .docxAASTHA76
 
(1) How does quantum cryptography eliminate the problem of eaves.docx
(1) How does quantum cryptography eliminate the problem of eaves.docx(1) How does quantum cryptography eliminate the problem of eaves.docx
(1) How does quantum cryptography eliminate the problem of eaves.docxAASTHA76
 
#transformation10EventTrendsfor 201910 Event.docx
#transformation10EventTrendsfor 201910 Event.docx#transformation10EventTrendsfor 201910 Event.docx
#transformation10EventTrendsfor 201910 Event.docxAASTHA76
 
$10 now and $10 when complete Use resources from the required .docx
$10 now and $10 when complete Use resources from the required .docx$10 now and $10 when complete Use resources from the required .docx
$10 now and $10 when complete Use resources from the required .docxAASTHA76
 
#MicroXplorer Configuration settings - do not modifyFile.Versio.docx
#MicroXplorer Configuration settings - do not modifyFile.Versio.docx#MicroXplorer Configuration settings - do not modifyFile.Versio.docx
#MicroXplorer Configuration settings - do not modifyFile.Versio.docxAASTHA76
 
#include string.h#include stdlib.h#include systypes.h.docx
#include string.h#include stdlib.h#include systypes.h.docx#include string.h#include stdlib.h#include systypes.h.docx
#include string.h#include stdlib.h#include systypes.h.docxAASTHA76
 
$ stated in thousands)Net Assets, Controlling Interest.docx
$ stated in thousands)Net Assets, Controlling Interest.docx$ stated in thousands)Net Assets, Controlling Interest.docx
$ stated in thousands)Net Assets, Controlling Interest.docxAASTHA76
 
#include stdio.h#include stdlib.h#include pthread.h#in.docx
#include stdio.h#include stdlib.h#include pthread.h#in.docx#include stdio.h#include stdlib.h#include pthread.h#in.docx
#include stdio.h#include stdlib.h#include pthread.h#in.docxAASTHA76
 
#include customer.h#include heap.h#include iostream.docx
#include customer.h#include heap.h#include iostream.docx#include customer.h#include heap.h#include iostream.docx
#include customer.h#include heap.h#include iostream.docxAASTHA76
 
#Assessment BriefDiploma of Business Eco.docx
#Assessment BriefDiploma of Business Eco.docx#Assessment BriefDiploma of Business Eco.docx
#Assessment BriefDiploma of Business Eco.docxAASTHA76
 
#include stdio.h#include stdint.h#include stdbool.h.docx
#include stdio.h#include stdint.h#include stdbool.h.docx#include stdio.h#include stdint.h#include stdbool.h.docx
#include stdio.h#include stdint.h#include stdbool.h.docxAASTHA76
 

More from AASTHA76 (20)

(APA 6th Edition Formatting and St.docx
(APA 6th Edition Formatting and St.docx(APA 6th Edition Formatting and St.docx
(APA 6th Edition Formatting and St.docx
 
(a) Thrasymachus’ (the sophist’s) definition of Justice or Right o.docx
(a) Thrasymachus’ (the sophist’s) definition of Justice or Right o.docx(a) Thrasymachus’ (the sophist’s) definition of Justice or Right o.docx
(a) Thrasymachus’ (the sophist’s) definition of Justice or Right o.docx
 
(Glossary of Telemedicine and eHealth)· Teleconsultation Cons.docx
(Glossary of Telemedicine and eHealth)· Teleconsultation Cons.docx(Glossary of Telemedicine and eHealth)· Teleconsultation Cons.docx
(Glossary of Telemedicine and eHealth)· Teleconsultation Cons.docx
 
(Assmt 1; Week 3 paper) Using ecree Doing the paper and s.docx
(Assmt 1; Week 3 paper)  Using ecree        Doing the paper and s.docx(Assmt 1; Week 3 paper)  Using ecree        Doing the paper and s.docx
(Assmt 1; Week 3 paper) Using ecree Doing the paper and s.docx
 
(Image retrieved at httpswww.google.comsearchhl=en&biw=122.docx
(Image retrieved at  httpswww.google.comsearchhl=en&biw=122.docx(Image retrieved at  httpswww.google.comsearchhl=en&biw=122.docx
(Image retrieved at httpswww.google.comsearchhl=en&biw=122.docx
 
(Dis) Placing Culture and Cultural Space Chapter 4.docx
(Dis) Placing Culture and Cultural Space Chapter 4.docx(Dis) Placing Culture and Cultural Space Chapter 4.docx
(Dis) Placing Culture and Cultural Space Chapter 4.docx
 
(1) Define the time value of money.  Do you believe that the ave.docx
(1) Define the time value of money.  Do you believe that the ave.docx(1) Define the time value of money.  Do you believe that the ave.docx
(1) Define the time value of money.  Do you believe that the ave.docx
 
(chapter taken from Learning Power)From Social Class and t.docx
(chapter taken from Learning Power)From Social Class and t.docx(chapter taken from Learning Power)From Social Class and t.docx
(chapter taken from Learning Power)From Social Class and t.docx
 
(Accessible at httpswww.hatchforgood.orgexplore102nonpro.docx
(Accessible at httpswww.hatchforgood.orgexplore102nonpro.docx(Accessible at httpswww.hatchforgood.orgexplore102nonpro.docx
(Accessible at httpswww.hatchforgood.orgexplore102nonpro.docx
 
(a) The current ratio of a company is 61 and its acid-test ratio .docx
(a) The current ratio of a company is 61 and its acid-test ratio .docx(a) The current ratio of a company is 61 and its acid-test ratio .docx
(a) The current ratio of a company is 61 and its acid-test ratio .docx
 
(1) How does quantum cryptography eliminate the problem of eaves.docx
(1) How does quantum cryptography eliminate the problem of eaves.docx(1) How does quantum cryptography eliminate the problem of eaves.docx
(1) How does quantum cryptography eliminate the problem of eaves.docx
 
#transformation10EventTrendsfor 201910 Event.docx
#transformation10EventTrendsfor 201910 Event.docx#transformation10EventTrendsfor 201910 Event.docx
#transformation10EventTrendsfor 201910 Event.docx
 
$10 now and $10 when complete Use resources from the required .docx
$10 now and $10 when complete Use resources from the required .docx$10 now and $10 when complete Use resources from the required .docx
$10 now and $10 when complete Use resources from the required .docx
 
#MicroXplorer Configuration settings - do not modifyFile.Versio.docx
#MicroXplorer Configuration settings - do not modifyFile.Versio.docx#MicroXplorer Configuration settings - do not modifyFile.Versio.docx
#MicroXplorer Configuration settings - do not modifyFile.Versio.docx
 
#include string.h#include stdlib.h#include systypes.h.docx
#include string.h#include stdlib.h#include systypes.h.docx#include string.h#include stdlib.h#include systypes.h.docx
#include string.h#include stdlib.h#include systypes.h.docx
 
$ stated in thousands)Net Assets, Controlling Interest.docx
$ stated in thousands)Net Assets, Controlling Interest.docx$ stated in thousands)Net Assets, Controlling Interest.docx
$ stated in thousands)Net Assets, Controlling Interest.docx
 
#include stdio.h#include stdlib.h#include pthread.h#in.docx
#include stdio.h#include stdlib.h#include pthread.h#in.docx#include stdio.h#include stdlib.h#include pthread.h#in.docx
#include stdio.h#include stdlib.h#include pthread.h#in.docx
 
#include customer.h#include heap.h#include iostream.docx
#include customer.h#include heap.h#include iostream.docx#include customer.h#include heap.h#include iostream.docx
#include customer.h#include heap.h#include iostream.docx
 
#Assessment BriefDiploma of Business Eco.docx
#Assessment BriefDiploma of Business Eco.docx#Assessment BriefDiploma of Business Eco.docx
#Assessment BriefDiploma of Business Eco.docx
 
#include stdio.h#include stdint.h#include stdbool.h.docx
#include stdio.h#include stdint.h#include stdbool.h.docx#include stdio.h#include stdint.h#include stdbool.h.docx
#include stdio.h#include stdint.h#include stdbool.h.docx
 

Recently uploaded

Observing-Correct-Grammar-in-Making-Definitions.pptx
Observing-Correct-Grammar-in-Making-Definitions.pptxObserving-Correct-Grammar-in-Making-Definitions.pptx
Observing-Correct-Grammar-in-Making-Definitions.pptxAdelaideRefugio
 
male presentation...pdf.................
male presentation...pdf.................male presentation...pdf.................
male presentation...pdf.................MirzaAbrarBaig5
 
Sternal Fractures & Dislocations - EMGuidewire Radiology Reading Room
Sternal Fractures & Dislocations - EMGuidewire Radiology Reading RoomSternal Fractures & Dislocations - EMGuidewire Radiology Reading Room
Sternal Fractures & Dislocations - EMGuidewire Radiology Reading RoomSean M. Fox
 
How To Create Editable Tree View in Odoo 17
How To Create Editable Tree View in Odoo 17How To Create Editable Tree View in Odoo 17
How To Create Editable Tree View in Odoo 17Celine George
 
Spellings Wk 4 and Wk 5 for Grade 4 at CAPS
Spellings Wk 4 and Wk 5 for Grade 4 at CAPSSpellings Wk 4 and Wk 5 for Grade 4 at CAPS
Spellings Wk 4 and Wk 5 for Grade 4 at CAPSAnaAcapella
 
SURVEY I created for uni project research
SURVEY I created for uni project researchSURVEY I created for uni project research
SURVEY I created for uni project researchCaitlinCummins3
 
FICTIONAL SALESMAN/SALESMAN SNSW 2024.pdf
FICTIONAL SALESMAN/SALESMAN SNSW 2024.pdfFICTIONAL SALESMAN/SALESMAN SNSW 2024.pdf
FICTIONAL SALESMAN/SALESMAN SNSW 2024.pdfPondicherry University
 
Stl Algorithms in C++ jjjjjjjjjjjjjjjjjj
Stl Algorithms in C++ jjjjjjjjjjjjjjjjjjStl Algorithms in C++ jjjjjjjjjjjjjjjjjj
Stl Algorithms in C++ jjjjjjjjjjjjjjjjjjMohammed Sikander
 
DEMONSTRATION LESSON IN ENGLISH 4 MATATAG CURRICULUM
DEMONSTRATION LESSON IN ENGLISH 4 MATATAG CURRICULUMDEMONSTRATION LESSON IN ENGLISH 4 MATATAG CURRICULUM
DEMONSTRATION LESSON IN ENGLISH 4 MATATAG CURRICULUMELOISARIVERA8
 
MuleSoft Integration with AWS Textract | Calling AWS Textract API |AWS - Clou...
MuleSoft Integration with AWS Textract | Calling AWS Textract API |AWS - Clou...MuleSoft Integration with AWS Textract | Calling AWS Textract API |AWS - Clou...
MuleSoft Integration with AWS Textract | Calling AWS Textract API |AWS - Clou...MysoreMuleSoftMeetup
 
Improved Approval Flow in Odoo 17 Studio App
Improved Approval Flow in Odoo 17 Studio AppImproved Approval Flow in Odoo 17 Studio App
Improved Approval Flow in Odoo 17 Studio AppCeline George
 
Graduate Outcomes Presentation Slides - English (v3).pptx
Graduate Outcomes Presentation Slides - English (v3).pptxGraduate Outcomes Presentation Slides - English (v3).pptx
Graduate Outcomes Presentation Slides - English (v3).pptxneillewis46
 
TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...
TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...
TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...Nguyen Thanh Tu Collection
 
Spring gala 2024 photo slideshow - Celebrating School-Community Partnerships
Spring gala 2024 photo slideshow - Celebrating School-Community PartnershipsSpring gala 2024 photo slideshow - Celebrating School-Community Partnerships
Spring gala 2024 photo slideshow - Celebrating School-Community Partnershipsexpandedwebsite
 
8 Tips for Effective Working Capital Management
8 Tips for Effective Working Capital Management8 Tips for Effective Working Capital Management
8 Tips for Effective Working Capital ManagementMBA Assignment Experts
 
Trauma-Informed Leadership - Five Practical Principles
Trauma-Informed Leadership - Five Practical PrinciplesTrauma-Informed Leadership - Five Practical Principles
Trauma-Informed Leadership - Five Practical PrinciplesPooky Knightsmith
 
AIM of Education-Teachers Training-2024.ppt
AIM of Education-Teachers Training-2024.pptAIM of Education-Teachers Training-2024.ppt
AIM of Education-Teachers Training-2024.pptNishitharanjan Rout
 
Analyzing and resolving a communication crisis in Dhaka textiles LTD.pptx
Analyzing and resolving a communication crisis in Dhaka textiles LTD.pptxAnalyzing and resolving a communication crisis in Dhaka textiles LTD.pptx
Analyzing and resolving a communication crisis in Dhaka textiles LTD.pptxLimon Prince
 
e-Sealing at EADTU by Kamakshi Rajagopal
e-Sealing at EADTU by Kamakshi Rajagopale-Sealing at EADTU by Kamakshi Rajagopal
e-Sealing at EADTU by Kamakshi RajagopalEADTU
 

Recently uploaded (20)

Observing-Correct-Grammar-in-Making-Definitions.pptx
Observing-Correct-Grammar-in-Making-Definitions.pptxObserving-Correct-Grammar-in-Making-Definitions.pptx
Observing-Correct-Grammar-in-Making-Definitions.pptx
 
male presentation...pdf.................
male presentation...pdf.................male presentation...pdf.................
male presentation...pdf.................
 
Sternal Fractures & Dislocations - EMGuidewire Radiology Reading Room
Sternal Fractures & Dislocations - EMGuidewire Radiology Reading RoomSternal Fractures & Dislocations - EMGuidewire Radiology Reading Room
Sternal Fractures & Dislocations - EMGuidewire Radiology Reading Room
 
How To Create Editable Tree View in Odoo 17
How To Create Editable Tree View in Odoo 17How To Create Editable Tree View in Odoo 17
How To Create Editable Tree View in Odoo 17
 
Spellings Wk 4 and Wk 5 for Grade 4 at CAPS
Spellings Wk 4 and Wk 5 for Grade 4 at CAPSSpellings Wk 4 and Wk 5 for Grade 4 at CAPS
Spellings Wk 4 and Wk 5 for Grade 4 at CAPS
 
SURVEY I created for uni project research
SURVEY I created for uni project researchSURVEY I created for uni project research
SURVEY I created for uni project research
 
FICTIONAL SALESMAN/SALESMAN SNSW 2024.pdf
FICTIONAL SALESMAN/SALESMAN SNSW 2024.pdfFICTIONAL SALESMAN/SALESMAN SNSW 2024.pdf
FICTIONAL SALESMAN/SALESMAN SNSW 2024.pdf
 
Stl Algorithms in C++ jjjjjjjjjjjjjjjjjj
Stl Algorithms in C++ jjjjjjjjjjjjjjjjjjStl Algorithms in C++ jjjjjjjjjjjjjjjjjj
Stl Algorithms in C++ jjjjjjjjjjjjjjjjjj
 
DEMONSTRATION LESSON IN ENGLISH 4 MATATAG CURRICULUM
DEMONSTRATION LESSON IN ENGLISH 4 MATATAG CURRICULUMDEMONSTRATION LESSON IN ENGLISH 4 MATATAG CURRICULUM
DEMONSTRATION LESSON IN ENGLISH 4 MATATAG CURRICULUM
 
MuleSoft Integration with AWS Textract | Calling AWS Textract API |AWS - Clou...
MuleSoft Integration with AWS Textract | Calling AWS Textract API |AWS - Clou...MuleSoft Integration with AWS Textract | Calling AWS Textract API |AWS - Clou...
MuleSoft Integration with AWS Textract | Calling AWS Textract API |AWS - Clou...
 
Improved Approval Flow in Odoo 17 Studio App
Improved Approval Flow in Odoo 17 Studio AppImproved Approval Flow in Odoo 17 Studio App
Improved Approval Flow in Odoo 17 Studio App
 
Graduate Outcomes Presentation Slides - English (v3).pptx
Graduate Outcomes Presentation Slides - English (v3).pptxGraduate Outcomes Presentation Slides - English (v3).pptx
Graduate Outcomes Presentation Slides - English (v3).pptx
 
TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...
TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...
TỔNG HỢP HƠN 100 ĐỀ THI THỬ TỐT NGHIỆP THPT TOÁN 2024 - TỪ CÁC TRƯỜNG, TRƯỜNG...
 
OS-operating systems- ch05 (CPU Scheduling) ...
OS-operating systems- ch05 (CPU Scheduling) ...OS-operating systems- ch05 (CPU Scheduling) ...
OS-operating systems- ch05 (CPU Scheduling) ...
 
Spring gala 2024 photo slideshow - Celebrating School-Community Partnerships
Spring gala 2024 photo slideshow - Celebrating School-Community PartnershipsSpring gala 2024 photo slideshow - Celebrating School-Community Partnerships
Spring gala 2024 photo slideshow - Celebrating School-Community Partnerships
 
8 Tips for Effective Working Capital Management
8 Tips for Effective Working Capital Management8 Tips for Effective Working Capital Management
8 Tips for Effective Working Capital Management
 
Trauma-Informed Leadership - Five Practical Principles
Trauma-Informed Leadership - Five Practical PrinciplesTrauma-Informed Leadership - Five Practical Principles
Trauma-Informed Leadership - Five Practical Principles
 
AIM of Education-Teachers Training-2024.ppt
AIM of Education-Teachers Training-2024.pptAIM of Education-Teachers Training-2024.ppt
AIM of Education-Teachers Training-2024.ppt
 
Analyzing and resolving a communication crisis in Dhaka textiles LTD.pptx
Analyzing and resolving a communication crisis in Dhaka textiles LTD.pptxAnalyzing and resolving a communication crisis in Dhaka textiles LTD.pptx
Analyzing and resolving a communication crisis in Dhaka textiles LTD.pptx
 
e-Sealing at EADTU by Kamakshi Rajagopal
e-Sealing at EADTU by Kamakshi Rajagopale-Sealing at EADTU by Kamakshi Rajagopal
e-Sealing at EADTU by Kamakshi Rajagopal
 

Example Lean Six Sigma Charter Enclosure 2, LSS.docx

  • 1. Example Lean Six Sigma Charter Enclosure 2, LSS Project Charter Project Name: Improve the effectiveness and efficiency of the BB computer acquisition process Date: November 15, 2014 Organization: CIO Deployment Champion: Mark Laptop Project Sponsor: John Puter Black/Green Belt: Bill Desktop Business Impact ($) This project will address the computer acquisition process for LSS BB training courses. The first two waves of training have experienced delays and customer dissatisfaction due to late delivery of computers and class disruptions to load required software. Due to exceptional work by Tom Peoples, the first two waves were able to receive their computers during week 1 of training, but since pre-work is required before attending week 1 of training, it is ideal for the BB’s to receive properly loaded computers during Team Accelerator training in order to complete the Minitab pre- work and get comfortable with the George Group Virtual Coach software tool. The impact of late computers in worker non-productivity costs,
  • 2. expediting costs, possible higher computer costs, and customer dissatisfaction estimated at: • $12K of Type 1 o Assumptions - 6 waves of BB training over the next 12 months following completion of project, $2000/wave of additional computer costs for expediting, etc. • $48K of Type 2 o Assumptions - 6 waves of BB training over the next 12 months following completion of project, 40 hours of extra expediting and handling per wave, $75 per hour of labor • Other Benefits (Type 3) o Increased student learning and ultimately better project success Problem Statement Where: The problem has been noticed at Shangri-la Higher Education Training Center, the only training location to-date When: The problem has been noticed since October 2004 to date, covering the first two waves of LSS BB training. What (output metrics): • Quality metric #1: % of properly loaded laptop computers with designated software load as measured by % of total computers loaded correctly the 1st time • Quality metric #2: % computers delivered by day 1 of Team Accelerator training as measured by % of total computers delivered late. • Speed metric #1: time to prepare BB training computers as measured by the time from final wave roster to all computers
  • 3. ready for delivery. • Cost metric #1: Cost per fully loaded computer as measured by total costs of computer readiness divided by total computers delivered. Costs should not include expediting, temporary computer costs, or excessive labor costs. Extent: Baseline Quality metric #1: To date, X% of computers are loaded correctly first time Baseline Quality metric #2: To date, 0% of computers are delivered by day 1 of Team Accelerator Training Baseline Speed metric #1: To date, the average cycle time to have a computer ready for delivery is 4 weeks Baseline Cost metric #1: Current cost is $X,000 per computer load. Goal Statement (output metrics) • Quality metric #1: Increase the percentage of BB computers correctly loaded to 75% for wave 3, and 100% for all waves thereafter • Quality metric #2: Deliver 100% of the computers by day 1 Team Accelerator training for each wave, beginning with Wave 3 • Speed metric #1: Reduce the average cycle time per computer load to 2 weeks, with minimal variation • Cost metric #1: Reduce the cost per computer load to $YY,000 per computer Project Scope (Horizontal and Vertical Scoping) Start/stop point of process: the computer loading process begins upon of delivery of BB wave roster to the IT department
  • 4. and ends with the delivery of the computer to the BB on the first day of Team Accelerator training (vertical scoping) In Scope: This project will address the laptop computer acquisition process for LSS BB waves 3-10 (horizontal scoping). The team will implement process changes. There is a small project budget of $1000 available for process changes or other project work. Out of scope: This project will not address network log-in logistics, GB courses or any other course requiring computers. Changes to the overall computer acquisition system are out-of- scope. Example Lean Six Sigma Charter Enclosure 2, LSS Project Charter Project Plan Define – 12/5/2004 (Start date, first Monday after first week of training + 2-4 weeks Measure – 1/20/05 (allow for holidays and extra time need to collect data) Analyze – 2/15/05 Improve – 4/10/05 (allow time for pilot and results) Control – 5/8/05 (start date plus 5 months) Team Selection Project Sponsor: John Puter 10% Black Belt: Bill Desktop 100% Master Black Belt coach: Ann C. Drive Team Members:
  • 5. IT person, Samual Harddriver 20% IT person, Willis Thumbdrive 20% Procurement, Julie Externaldrive 10% Contracts, TBD 10% Network Expert, TBD 5% Signatures: _______________________ ________________________ ________________________ Deployment Champion Project Sponsor Financial Rep _______________________ ________________________ Black Belt / Green Belt Master Black Belt Lean Six Sigma Project Charter Enclosure 2, LSS Project Charter Project Name: Date: Organization: Deployment Champion: Project Sponsor: Black/Green Belt: Business Impact ($)
  • 6. Problem Statement (What and Extent stated in terms of the project output metrics) Goal Statement (stated in terms of the project output metrics) Project Scope (Horizontal and Vertical Scoping) Project Plan (dates)
  • 7. Lean Six Sigma Project Charter Enclosure 2, LSS Project Charter Team Selection Signatures: _______________________ ________________________ ________________________ Deployment Champion Project Sponsor Financial Rep _______________________ ________________________ Black Belt / Green Belt Master Black Belt Project Sponsor: John Puter 10% Project Name: DMOSQDate: 2NOV16Organization: JFHQ-IN- J3-Training BranchDeployment Champion_2: Mr. Joshua ClarkProject Sponsor_2: COL Timothy WinslowBlackGreen Belt: MAJ Chris DalrympleBusiness Impact Row1: The Indiana Army National Guard must be able to select, retain, and develop Soldiers throughout their career from initial entry to separation or retirement. The average cost to train a Soldier is $150,000.00 just to send a soldier through Basic and AIT, which is the lowest level of training required to have a DMOSQ'd soldier. The cost goes up exponentially depending on the training, level, and length of time of the course. DMOSQ is part of the 2015-2019 strategic plan p. 10 as objective 3-4 to obtain NLT 85% DMOSQ and 100% AFSC. Objective 3-4
  • 8. states, "Train and retain Soldiers, Airmen, and officers who are qualified in current position. Identify Soldiers, Airmen, and officers requiring military schools and duty position training and enroll as required. Ensure that funding is secured and available for AFSC/DMOSQ schools."Problem Statement What and Extent stated in terms of the project output metricsRow1: The percent DMOSQ is currently around 83%, which is below the NGB goal of 85% and is under performing when compared with its key competitor states of: California, Georgia, Ohio, and Pennsylvania. Force structure opportunities, mission selection, and training opportunity could potentially be missed due to competitors ability to meet personnel readiness and training. Where: The problem has been notice at the state level through metrics measured internally by JFHQ-IN-J3 and DPROS database. When: The problem has been noticed since 7 July 16 as part of the organizational self assessment. What: (Output Metrics): Quality Metric #1: % DMOSQ Quality Metric #2: Ratio of School Seat Traps to Non MOSQ Quality Metric #3: %Allocation of school seat traps filled Speed Metric #1: # of months to obtain DMOSQ for position once vacancy is filled. Cost Metric #1: Total cost lost school money due to school failure and school reservation cancellations. Goal Statement stated in terms of the project output metricsRow1: The goal is to increase DMOSQ to exceed the NGB Goal and to outperform 3 out of 4 of our key competitors in DMOSQ. Quality metric #1: 90% DMOSQ Quality metric #2: 1:1 Quality metric #3: 95% School seats obligated Speed metric #1: Average of 10 months to obtain DMOSQ
  • 9. (Certain DMOSQ schools are much longer in length and will cause average to skew average) Cost metric #1: To reduce wasted school money by 80%. Project Scope Horizontal and Vertical ScopingRow1: To properly trap training allocations, then to allocate training seats that has the best impact at improving the DMOSQ level in the INARNG. In Scope: This project will address the process for how JFHQ- IN-J3 achieves DMOSQ as part if its strategic plan, Objective 3-4, which the team will recommend process changes to increase qualification percentages. Out of scope: This project will not address OES and NCOES requirement as part of the Service Member's development. This is an important part of the overall development of the officer or enlisted soldier but such changes to this system are out-of- scope. Project Plan datesRow1: Define-11/14/2016 (Starts first day of course and last for 4 weeks) Measure-12/15/2016 (Allow for holidays and extra time to collect data) Analyze- Improve-3/15/2017 (Training seat traps conducted annually, allocation are provided to MSC annually, metric that can be improved are %DMOSQ, cost reduction, and school seat obligation) Control-4/15/2017(start date plus 5 months)Team SelectionRow1: Project Sponsor: COL Timothy Winslow Black Belt: Master Black Belt Coach: Team Members: (J3 Training shop, BDE S3 Section, Unit S3 and S1) LTC Bradly Compton,Deployment Champion_3: Black Belt Green Belt_2: Project Sponsor_3: Financial Rep_2: Master Black Belt_2: Dominos quality issue (problem)
  • 10. Break down the company’s operations based upon the operations management course, making sure to cover the topics from this course including: · Strategy, how does their business operation support their strategy? · Supply chain, logistics, human resource development, inventory management, customer service, quality, forecasting · Include current & projected financial performance and describe key metrics for their industry/segment · Provide recommendations for how they might improve operations for either financial gain or better customer service, short-term and long-term Please make sure you address the 10 strategic OM decisions outlined in table 1.2 of the text.