Erection and commissioning of the new compressor package.pptx
1. ERECTION AND
COMMISSIONING OF THE NEW
GAS COMPRESSOR PACKAGE
PRESENTED BY:
JOGANI DHRUVIKKUMAR ASHOKBHAI (OIL ID : 204588)
SENIOR OFFICER ON PROBATION
GAS MANAGEMENT SERVICES DEPARTMENT
MENTOR:
MR. TASRIQUE HAQUE,
DEPUTY CHIEF ENGINEER
GAS MANAGEMENT SERVICES DEPARTMENT
Fourth Quarterly Assessment
2. NEW GAS COMPRESSOR PACKAGE
SPECIFICATION
MODEL WAUKESHA
F3514
DISPLACEMENT
VOLUME
3520
BHP 493
COMPRESSION
RATIO
8:1
BORE AND
STROKE
9.375” & 8.5”
IGNITION Turbo Charged
Intercool
NO. OF
CYLINDER
6
RATED RPM 900
ENGINE
MODEL 8” & 4.7
5” x 6HOS2-2
NO. OF THROW 2
CYLINDER TYPE HOS
SERVICE Gas Lift
TOTAL
COMPRESSION
BHP
287 KW
NO. OF STAGE 2
RATED
DISCHARGE
PRESSURE
1450 PSIG
COMPRESSOR
MODEL 60F4
FAN DIAMETER 60 inch
DIRVE ENGINE
DRIVE
FAN
ORIENTATION
VERTICAL
TOTAL NOS. FAN 4
AERIAL COOLER
4. TYPES OF FOUNDATION
CC METRESS GRAVEL PACK
Construction Old Compressor Package
Replacement job
Material Cement and Concrete
Anti Vibration
Pad
YES
Job
Completion
Time
10-11 days + 5-6 days + 35-40
days +
20 – 25 days = 70-75 days
Construction New Compressor Package
Installation job
Material Gavel Pack(15mm gravel+75 mm
Gravel + Brick Soil)
Anti Vibration
Pad
NO
Job
Completion
Time
35-40 days + 20 – 25 days = 60-62
days
5. Compressor Skid
Placement On The
Foundation
• Compressor skid placed on the
foundation
• Alignment of compressor skid on
the foundation
Compressor Skid
6. ENGINE
PLACEMENT ON
SKID AND
ALINGNMENT
• Engine placement behind
the compressor
• Rough alignment
• Coupling Fitting
• Final alignment
F-3514 Engine
Engine Placement On
7. Erection of the Aerial
Cooler Assembly
• Dimension verification of
the Aerial cooler assembly
foundation
• Proper Alignment between
engine shaft and aerial
cooler
Aerial Cooler Assembly
Foundation
Placement of Aerial Cooler Assembly
Upliftment of Aerial
Cooler
8. INSTALLATION
OF CYLINDER
ASSEMBLY AND
PULSATION
BOTTLE
• Shaft alignment of Engine
and Compressor
• Installation of the cylinder
assembly on both side
• Installation of pulsation bottle
on the both cylinder .
• Head end and Crank End
clearance measurement in
both stages cylinder.
Crank-Frame without
Cylinder
Cylinder Bottle
Crank-Frame with
Cylinder
9. FIRST
PRE-LUBE OF
ENGINE
- Checking of the clean Engine
oil filter
- Filling of the lube oil in Engine
oil filter
- Level check of lube oil engine
sump
- Instrument air connection to
Pre-lube pump
- Start of pre-lube pump and
verification lube oil circulation
in rocker arm.
Rocker Arm Filling of Lube Oil
Pre-Lube Pump
10. Erection of Cooling
System Tank And
Silencer Assembly
• Foundation marking for
the both assembly on the
ground
• Preparation of the
foundation
Silencer Erection Foundation Marking
Engine Jacket and Auxiliary water expansion
Tank
11. PIPE
CONNECTION &
MAIN LINE HOOK
UP
• Pipe connection between the
compressor cooling system
and engine cooling system
to the Aerial Cooler.
• Fuel line, Suction and
Discharge Line connection,
Blowdown line, Instrument
air, Drain Line and Starting
Air Line connection to
respective main header line.
• Last stage grounting Flange
leakage check
Main Line Header
12. PRECONDITIONING
OF CONTROL
PANEL
• 230 V A.C. to 24 V D.C.
• Cold loop test
• MCB Check
• Software installation
• Trip test
Control Panel
Configuration
Float Cum Booster Panel
13. COMISSIONING OF THE NEW GAS
COMPRESSOR PACKAGE
• Mechanical Run Test
- Starting Air Line And Fuel Line
Flushed Out
- Removal Of Discharge Valve Cover
- Removal Of Spark Plug With Ignition Coil
- Manual Pre-lube Of Compressor
Discharge Valve Cover
Removed
Dry Cranking
Spark Plug Removed
Cylinder
14. LOAD AND
UNLOAD
TEST • 2 Hour Unload Run Test Without Gas Charge
• 2 Hour Load Run Test With Gas Charge
• Hot Alignment Of Engine And Compressor Shaft
• Final 72 Hour Full Load Run Test
Hot Alignment Process And Equipment
15. Monitoring Of
Crucial Parameters
• Suction & Discharge pressure
of both stages.
• Suction & Discharge
temperature of both stages.
• Compressor and Engine Lube
Oil pressure
• Exhaust Manifold Temperature
• Engine RPM
Control Panel Screen