Prog No
000012.
Revision: A
Comment: Embassy Gardens- Front Of House Revision Date: 05/03/2015
Drawn By
dele
Drawn Date
05/03/2015
Program Status: Embassy Gardens- Front Of House Target Dates
D
S&T Interiors (UK) Ltd
55 Bryanston Street, March Arch Tower
London W1H 7AA tel: 02078598390
www.stcgroups.com
EMBASSY GARDENS FOH
Design, Manufacture and Delivery Programme
Line Name Start Duration Finish
Percent
complete
Slip
2015
February March April May June JulyJanuary August
26 2 9 16 23 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 6 13 20 27 3
2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 291
21 23 27 29 2 4 6 10 12 16 18 20 24 26 2 4 6 10 12 16 18 20 24 26 30 1 3 7 9 13 15 17 21 23 27 29 1 5 7 11 13 15 19 21 25 27 29 2 4 8 10 12 16 18 22 24 26 30 2 6 8 10 14 16 20 22 24 28 30 3 5 7
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
EMBASSY GARDEN FRONT OF HOUSE
L00 - Ground Floor Business Centre
Manufacture
Delivery to site of Joinery
First fix speciality joinery (cupboards,veneered doors,oak frame, fittings/ fixing
Speciality Joinery, of cupboard,Sliding door / gloss lacquered panels
Install all height oak glazed screens with 50mm timber frame
Delivery to site of Joinery shutters
Install oak shutters to glazed screens
Upholstered Ceiling & Wall Panels installation
L00 - Ground Floor Lavatories
Install and painting of Plasterboard Ceiling
Install Bianco Carrara stone around vanity units with polished nickel frames
Install Oak timber floor / Dark grey stone floor finish / Val D' isere
Matt Lacquered frame to ceiling corridor area
Actual Delivery to site
First fix of timber cubicle doors,frameand ironmongery
Delivery to site vanity metal profile,skirting,cornce,mirrors
Installation of Fittings
Final fixes of timber cubicle doors,frame and ironmongery
Installation of wallpaper / Lacquered skirting, Frieze and Polished Nickel frame
Installation of hanging mirrors
L00 - D1 / D2 STAIRS
Manufacture
Actual Delivery to site
Installation
Install timber floor to base of staircase
Timber cladding to staircase
Install timber ceiling cornice
Striped wallpaper to staircase walls
CINEMA GROUND FLOOR
Design drawing
Final issues of drawings
Approvals / Comments
Review and Re- Issue
Manufacture
Actual Delivery to site
22/01/2015
26/01/2015
26/01/2015
16/02/2015
20/02/2015
24/02/2015
03/03/2015
27/02/2015
04/03/2015
09/03/2015
16/02/2015
16/02/2015
23/02/2015
02/03/2015
09/03/2015
09/03/2015
10/03/2015
10/03/2015
13/03/2015
18/03/2015
23/03/2015
26/03/2015
26/01/2015
26/01/2015
11/02/2015
18/02/2015
18/02/2015
23/02/2015
27/02/2015
06/03/2015
26/01/2015
26/01/2015
23/02/2015
23/02/2015
03/03/2015
11/03/2015
15/04/2015
23w
7w
3w
1w 1d
1w
1w 3d
1w 2d
3d
1w 1d
1w
6w 2d
1w
2w
1w 3d
1w 2d
3d
3d
3d
1w 2d
1w
1w
4d
7w 2d
2w 2d
1w
4w
1w
2w
1w 4d
1w 3d
17w 2d
4w
1w 1d
1w 1d
4w 3d
1w
08/07/2015
13/03/2015
13/02/2015
23/02/2015
26/02/2015
05/03/2015
11/03/2015
03/03/2015
11/03/2015
13/03/2015
31/03/2015
20/02/2015
06/03/2015
12/03/2015
17/03/2015
11/03/2015
12/03/2015
12/03/2015
23/03/2015
25/03/2015
27/03/2015
31/03/2015
17/03/2015
10/02/2015
17/02/2015
17/03/2015
24/02/2015
06/03/2015
11/03/2015
17/03/2015
01/06/2015
20/02/2015
23/02/2015
02/03/2015
10/03/2015
14/04/2015
21/04/2015
11.50
74.55
100.00
100.00
100.00
100.00
100.00
15.67
70.00
20.00
100.00
50.00
60.82
100.00
100.00
40.00
100.00
60.00
20.00
13.76
75.00
-1w 2d
1d 5h
2d
1w 1d
-3d
-2d 5h
-1w 4d
-1w 2d
-1d 7h
4d 3h
6d
1w 4h
-1d 48min
-1d 48min
-1d
-1d 2h
-2w 2d
-2w 2d
-1w 2d
-1w 2d
-1d
1 EMBASSY GARDEN FRONT OF HOUSE
2 L00 - Ground Floor Business Centre
3 Manufacture
4 Delivery to site of Joinery
5 First fix speciality joinery (cupboards,veneered doors,oak frame, fittings/ fixing
6 Speciality Joinery, of cupboard,Sliding door / gloss lacquered panels
7 Install all height oak glazed screens with 50mm timber frame
8 Delivery to site of Joinery shutters
9 Install oak shutters to glazed screens
10 Upholstered Ceiling & Wall Panels installation
11 L00 - Ground Floor Lavatories
12 Install and painting of Plasterboard Ceiling
13 Install Bianco Carrara stone around vanity units with polished nickel frames
14 Install Oak timber floor / Dark grey stone floor finish / Val D' isere
15 Matt Lacquered frame to ceiling corridor area
16 Actual Delivery to site
17 First fix of timber cubicle doors,frameand ironmongery
18 Delivery to site vanity metal profile,skirting,cornce,mirrors
19 Installation of Fittings
20 Final fixes of timber cubicle doors,frame and ironmongery
21 Installation of wallpaper / Lacquered skirting, Frieze and Polished Nickel frame
22 Installation of hanging mirrors
23 L00 - D1 / D2 STAIRS
24 Manufacture
25 Actual Delivery to site
26 Installation
27 Install timber floor to base of staircase
28 Timber cladding to staircase
29 Install timber ceiling cornice
30 Striped wallpaper to staircase walls
31 CINEMA GROUND FLOOR
32 Design drawing
33 Final issues of drawings
34 Approvals / Comments
35 Review and Re- Issue
36 Manufacture
37 Actual Delivery to site
1 EMBASSY GARDEN FRONT OF HOUSE
2 L00 - Ground Floor Business Centre
3 Manufacture
4 Delivery to site of Joinery
5 First fix speciality joinery (cupboards,veneered doors,oak frame, fittings/ fixing
6 Speciality Joinery, of cupboard,Sliding door / gloss lacquered panels
7 Install all height oak glazed screens with 50mm timber frame
8 Delivery to site of Joinery shutters
9 Install oak shutters to glazed screens
10 Upholstered Ceiling & Wall Panels installation
11 L00 - Ground Floor Lavatories
12 Install and painting of Plasterboard Ceiling
13 Install Bianco Carrara stone around vanity units with polished nickel frames
14 Install Oak timber floor / Dark grey stone floor finish / Val D' isere
15 Matt Lacquered frame to ceiling corridor area
16 Actual Delivery to site
17 First fix of timber cubicle doors,frameand ironmongery
18 Delivery to site vanity metal profile,skirting,cornce,mirrors
19 Installation of Fittings
20 Final fixes of timber cubicle doors,frame and ironmongery
21 Installation of wallpaper / Lacquered skirting, Frieze and Polished Nickel frame
22 Installation of hanging mirrors
23 L00 - D1 / D2 STAIRS
24 Manufacture
25 Actual Delivery to site
26 Installation
27 Install timber floor to base of staircase
28 Timber cladding to staircase
29 Install timber ceiling cornice
30 Striped wallpaper to staircase walls
31 CINEMA GROUND FLOOR
32 Design drawing
33 Final issues of drawings
34 Approvals / Comments
35 Review and Re- Issue
36 Manufacture
37 Actual Delivery to site
Prog No
000012.
Revision: A
Comment: Embassy Gardens- Front Of House Revision Date: 05/03/2015
Drawn By
dele
Drawn Date
05/03/2015
Program Status: Embassy Gardens- Front Of House Target Dates
D
S&T Interiors (UK) Ltd
55 Bryanston Street, March Arch Tower
London W1H 7AA tel: 02078598390
www.stcgroups.com
EMBASSY GARDENS FOH
Design, Manufacture and Delivery Programme
Line Name Start Duration Finish
Percent
complete
Slip
2015
February March April May June JulyJanuary August
26 2 9 16 23 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 6 13 20 27 3
2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 291
21 23 27 29 2 4 6 10 12 16 18 20 24 26 2 4 6 10 12 16 18 20 24 26 30 1 3 7 9 13 15 17 21 23 27 29 1 5 7 11 13 15 19 21 25 27 29 2 4 8 10 12 16 18 22 24 26 30 2 6 8 10 14 16 20 22 24 28 30 3 5 7
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
Installation
First fix of perimeter framework Review
Install Upholstered Plasterboard Ceiling
40x170mm oak frames and 40x40mm antique brass frames to upholstered ceiling
Raised Floor installation / floor build up
Install fabric clad acoustic door, leaf & frame
Install vertical, base & head Oak panels to perimeter walls
Install Fabric wall Panelling
Carpet Installation
GYM RECEPTION
Design drawing
Final issues of drawings
Approval / Comments
Review and Re- Issue
Samples Approval
Manufacture
Actual Delivery to site
Installation
Install of oak timber ceiling and painting of Plasterboard Ceiling
Oak Timber Floor strip installation
First fix of Oak timber finished fire doors
Final fixes of Oak timber finish to stairs / fire doors /brass trims
Wall finishes - Oak timber panelling ,skirting and painted plasterboard
Ebonised timber panelling with brass trims / lacquered panelling besides lifts
Red Gloss panelling behind entrance desk,
Polyester flushed Carpet Installation
GYM CHANGING ROOM
Design drawing
Final issues of drawings
Approval / Comments
Review and Re- Issue
Samples Approval
Manufacture
Actual Delivery to site
Installation
Install of oak timber ceiling and painting of Plasterboard Ceiling
Oak Timber Floor strip installation
First fix of Oak timber finished fire doors
Final fixes of Oak timber finish to stairs / fire doors /brass trims
Wall finishes - Oak timber panelling ,skirting and painted plasterboard
22/04/2015
22/04/2015
28/04/2015
30/04/2015
06/05/2015
11/05/2015
13/05/2015
19/05/2015
27/05/2015
05/02/2015
05/02/2015
26/02/2015
26/02/2015
03/03/2015
10/03/2015
10/03/2015
23/04/2015
28/04/2015
28/04/2015
29/04/2015
30/04/2015
06/05/2015
11/05/2015
13/05/2015
14/05/2015
22/05/2015
22/01/2015
22/01/2015
12/02/2015
18/02/2015
23/02/2015
02/03/2015
02/03/2015
15/04/2015
20/04/2015
20/04/2015
21/04/2015
21/04/2015
28/04/2015
28/04/2015
5w 2d
4d
1w 3d
1w 2d
1w 1d
1w 1d
1w 2d
1w 2d
4d
15w 4d
3w
1w
1w
6w
3d
4w 3d
1w 1d
1w 1d
3d
1w 2d
1w 1d
1w 1d
1w 1d
1w 1d
16w 2d
3w
1w
3d
1w
6w
3d
4w 2d
1w 1d
2w
1w
1w 3d
1w
01/06/2015
27/04/2015
08/05/2015
11/05/2015
13/05/2015
18/05/2015
21/05/2015
28/05/2015
01/06/2015
01/06/2015
25/02/2015
26/02/2015
04/03/2015
09/03/2015
10/03/2015
22/04/2015
27/04/2015
01/06/2015
06/05/2015
07/05/2015
05/05/2015
14/05/2015
18/05/2015
20/05/2015
21/05/2015
01/06/2015
20/05/2015
11/02/2015
18/02/2015
20/02/2015
27/02/2015
02/03/2015
14/04/2015
17/04/2015
20/05/2015
27/04/2015
05/05/2015
27/04/2015
08/05/2015
05/05/2015
11.54
80.00
6.47
50.00
-1w 2d
-1w 2d
-4d
-4d
-1d
-4w 2d
-4w 2d
-2w 4d
-2w
-1w 2d
-2d
-2d
38 Installation
39 First fix of perimeter framework Review
40 Install Upholstered Plasterboard Ceiling
41 40x170mm oak frames and 40x40mm antique brass frames to upholstered ceiling
42 Raised Floor installation / floor build up
43 Install fabric clad acoustic door, leaf & frame
44 Install vertical, base & head Oak panels to perimeter walls
45 Install Fabric wall Panelling
46 Carpet Installation
47 GYM RECEPTION
48 Design drawing
49 Final issues of drawings
50 Approval / Comments
51 Review and Re- Issue
52 Samples Approval
53 Manufacture
54 Actual Delivery to site
55 Installation
56 Install of oak timber ceiling and painting of Plasterboard Ceiling
57 Oak Timber Floor strip installation
58 First fix of Oak timber finished fire doors
59 Final fixes of Oak timber finish to stairs / fire doors /brass trims
60 Wall finishes - Oak timber panelling ,skirting and painted plasterboard
61 Ebonised timber panelling with brass trims / lacquered panelling besides lifts
62 Red Gloss panelling behind entrance desk,
63 Polyester flushed Carpet Installation
64 GYM CHANGING ROOM
65 Design drawing
66 Final issues of drawings
67 Approval / Comments
68 Review and Re- Issue
69 Samples Approval
70 Manufacture
71 Actual Delivery to site
72 Installation
73 Install of oak timber ceiling and painting of Plasterboard Ceiling
74 Oak Timber Floor strip installation
75 First fix of Oak timber finished fire doors
76 Final fixes of Oak timber finish to stairs / fire doors /brass trims
77 Wall finishes - Oak timber panelling ,skirting and painted plasterboard
38 Installation
39 First fix of perimeter framework Review
40 Install Upholstered Plasterboard Ceiling
41 40x170mm oak frames and 40x40mm antique brass frames to upholstered ceiling
42 Raised Floor installation / floor build up
43 Install fabric clad acoustic door, leaf & frame
44 Install vertical, base & head Oak panels to perimeter walls
45 Install Fabric wall Panelling
46 Carpet Installation
47 GYM RECEPTION
48 Design drawing
49 Final issues of drawings
50 Approval / Comments
51 Review and Re- Issue
52 Samples Approval
53 Manufacture
54 Actual Delivery to site
55 Installation
56 Install of oak timber ceiling and painting of Plasterboard Ceiling
57 Oak Timber Floor strip installation
58 First fix of Oak timber finished fire doors
59 Final fixes of Oak timber finish to stairs / fire doors /brass trims
60 Wall finishes - Oak timber panelling ,skirting and painted plasterboard
61 Ebonised timber panelling with brass trims / lacquered panelling besides lifts
62 Red Gloss panelling behind entrance desk,
63 Polyester flushed Carpet Installation
64 GYM CHANGING ROOM
65 Design drawing
66 Final issues of drawings
67 Approval / Comments
68 Review and Re- Issue
69 Samples Approval
70 Manufacture
71 Actual Delivery to site
72 Installation
73 Install of oak timber ceiling and painting of Plasterboard Ceiling
74 Oak Timber Floor strip installation
75 First fix of Oak timber finished fire doors
76 Final fixes of Oak timber finish to stairs / fire doors /brass trims
77 Wall finishes - Oak timber panelling ,skirting and painted plasterboard
Prog No
000012.
Revision: A
Comment: Embassy Gardens- Front Of House Revision Date: 05/03/2015
Drawn By
dele
Drawn Date
05/03/2015
Program Status: Embassy Gardens- Front Of House Target Dates
D
S&T Interiors (UK) Ltd
55 Bryanston Street, March Arch Tower
London W1H 7AA tel: 02078598390
www.stcgroups.com
EMBASSY GARDENS FOH
Design, Manufacture and Delivery Programme
Line Name Start Duration Finish
Percent
complete
Slip
2015
February March April May June JulyJanuary August
26 2 9 16 23 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 6 13 20 27 3
2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 291
21 23 27 29 2 4 6 10 12 16 18 20 24 26 2 4 6 10 12 16 18 20 24 26 30 1 3 7 9 13 15 17 21 23 27 29 1 5 7 11 13 15 19 21 25 27 29 2 4 8 10 12 16 18 22 24 26 30 2 6 8 10 14 16 20 22 24 28 30 3 5 7
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108
109
110
111
112
113
114
115
116
117
Ebonised timber panelling with brass trims / lacquered panelling besides lifts
Red Gloss panelling behind entrance desk,
Polyester flushed Carpet Installation
GYM
Design drawing
Final issues of drawings
Approval / Comments
Review and Re- Issue
Samples Approval
Manufacture
Actual Delivery to site
Installation
CLUB LOUNGE
Design drawing
Final issues of drawings
Approval / Comments
Review and Re- Issue
Samples Approval
Manufacture
Actual Delivery to site
Delivery of carpet
Delivery of Fabric for upholstered panels
Installation
CLUB LOUNGE/ LAVATORIES
Approval to proceed on GA's
GA Design drawing
Final issues of drawings
Approval / Comments
Review and Re- Issue
Samples Approval
Manufacture
Actual Delivery to site
Installation
Painted Plasterboard / MDF Lacquered Ceiling
Stone & Oak Floor installation
Installation of Painted architrave /skirting Vanity Basin
Installation of single lacquered door, frame with lacquered architrave / Ironmongery
Marble cladding / Wall finishes Installation
POOL VESTIBULE / FEATURE STAIRS
Approval to proceed on GA's
01/05/2015
06/05/2015
12/05/2015
22/01/2015
22/01/2015
16/02/2015
20/02/2015
25/02/2015
04/03/2015
04/03/2015
17/04/2015
22/04/2015
22/01/2015
22/01/2015
16/02/2015
20/02/2015
27/02/2015
06/03/2015
06/03/2015
21/04/2015
07/04/2015
13/04/2015
24/04/2015
27/02/2015
27/02/2015
27/02/2015
06/03/2015
12/03/2015
17/03/2015
20/03/2015
20/03/2015
07/05/2015
12/05/2015
12/05/2015
14/05/2015
14/05/2015
20/05/2015
28/05/2015
16/02/2015
16/02/2015
1w 1d
1w 3d
1w 2d
15w
3w 2d
1w
3d
1w
6w
3d
2w 3d
15w 4d
3w 2d
1w
1w
1w
6w
3d
4d
1w 1d
3w
14w 2d
1w
1w
3d
3d
6w 1d
3d
4w 3d
1w 3d
1w 2d
2w
2w 3d
2w 2d
17w 3d
11/05/2015
15/05/2015
20/05/2015
11/05/2015
13/02/2015
20/02/2015
24/02/2015
03/03/2015
04/03/2015
16/04/2015
21/04/2015
11/05/2015
15/05/2015
13/02/2015
20/02/2015
26/02/2015
05/03/2015
06/03/2015
20/04/2015
23/04/2015
10/04/2015
20/04/2015
15/05/2015
12/06/2015
27/02/2015
05/03/2015
12/03/2015
16/03/2015
19/03/2015
20/03/2015
06/05/2015
11/05/2015
12/06/2015
21/05/2015
22/05/2015
28/05/2015
08/06/2015
12/06/2015
23/06/2015
16/02/2015
11.18
50.00
9.44
50.00
5.56
100.00
-4w 4h
-4w 4h
-2w 2d
-1w 3d
-1w
-4w 4h
-4w 4h
-2w 2d
-1w 3d
-3d
-3d
-3d
-3d
-3d
78 Ebonised timber panelling with brass trims / lacquered panelling besides lifts
79 Red Gloss panelling behind entrance desk,
80 Polyester flushed Carpet Installation
81 GYM
82 Design drawing
83 Final issues of drawings
84 Approval / Comments
85 Review and Re- Issue
86 Samples Approval
87 Manufacture
88 Actual Delivery to site
89 Installation
90 CLUB LOUNGE
91 Design drawing
92 Final issues of drawings
93 Approval / Comments
94 Review and Re- Issue
95 Samples Approval
96 Manufacture
97 Actual Delivery to site
98 Delivery of carpet
99 Delivery of Fabric for upholstered panels
100 Installation
101 CLUB LOUNGE/ LAVATORIES
102 Approval to proceed on GA's
103 GA Design drawing
104 Final issues of drawings
105 Approval / Comments
106 Review and Re- Issue
107 Samples Approval
108 Manufacture
109 Actual Delivery to site
110 Installation
111 Painted Plasterboard / MDF Lacquered Ceiling
112 Stone & Oak Floor installation
113 Installation of Painted architrave /skirting Vanity Basin
114 Installation of single lacquered door, frame with lacquered architrave / Ironmongery
115 Marble cladding / Wall finishes Installation
116 POOL VESTIBULE / FEATURE STAIRS
117 Approval to proceed on GA's
78 Ebonised timber panelling with brass trims / lacquered panelling besides lifts
79 Red Gloss panelling behind entrance desk,
80 Polyester flushed Carpet Installation
81 GYM
82 Design drawing
83 Final issues of drawings
84 Approval / Comments
85 Review and Re- Issue
86 Samples Approval
87 Manufacture
88 Actual Delivery to site
89 Installation
90 CLUB LOUNGE
91 Design drawing
92 Final issues of drawings
93 Approval / Comments
94 Review and Re- Issue
95 Samples Approval
96 Manufacture
97 Actual Delivery to site
98 Delivery of carpet
99 Delivery of Fabric for upholstered panels
100 Installation
101 CLUB LOUNGE/ LAVATORIES
102 Approval to proceed on GA's
103 GA Design drawing
104 Final issues of drawings
105 Approval / Comments
106 Review and Re- Issue
107 Samples Approval
108 Manufacture
109 Actual Delivery to site
110 Installation
111 Painted Plasterboard / MDF Lacquered Ceiling
112 Stone & Oak Floor installation
113 Installation of Painted architrave /skirting Vanity Basin
114 Installation of single lacquered door, frame with lacquered architrave / Ironmongery
115 Marble cladding / Wall finishes Installation
116 POOL VESTIBULE / FEATURE STAIRS
117 Approval to proceed on GA's
Prog No
000012.
Revision: A
Comment: Embassy Gardens- Front Of House Revision Date: 05/03/2015
Drawn By
dele
Drawn Date
05/03/2015
Program Status: Embassy Gardens- Front Of House Target Dates
D
S&T Interiors (UK) Ltd
55 Bryanston Street, March Arch Tower
London W1H 7AA tel: 02078598390
www.stcgroups.com
EMBASSY GARDENS FOH
Design, Manufacture and Delivery Programme
Line Name Start Duration Finish
Percent
complete
Slip
2015
February March April May June JulyJanuary August
26 2 9 16 23 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 6 13 20 27 3
2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 291
21 23 27 29 2 4 6 10 12 16 18 20 24 26 2 4 6 10 12 16 18 20 24 26 30 1 3 7 9 13 15 17 21 23 27 29 1 5 7 11 13 15 19 21 25 27 29 2 4 8 10 12 16 18 22 24 26 30 2 6 8 10 14 16 20 22 24 28 30 3 5 7
118
119
120
121
122
123
124
125
126
127
128
129
130
131
132
133
134
135
136
137
138
139
140
141
142
143
144
145
146
147
148
149
150
151
152
153
154
155
156
157
GA Design drawing
Final issues of drawings
Approval / Comments
Review and Re- Issue
Samples Approval
Manufacture
Actual Delivery to site
Installation
Installation of Oak Timber Ceilings
Oak veneered ceiling
Oak timber ceiling edge mouldings
Oak Timber Floor Installation
Bianco perlino stone Floor Installation
First fix installation oak timber skirting,frame,all height shutters,Pivot set and Fitting
Final fix installation oak timber skirting,frame,all height shutters,Pivot set and Fittings
Install all height Palisandro stone cladding / Lift lobby timber skirting and frieze
Install all height oak lattice with lacquered panel /timber slats ,Mullions / skirting
Install laminated glass stair railing / timber stair cladding
Install oak door frame,door, trims,oak blinds,ironmongery
Installation of Stuccoed columns with skirting
Carpet installation
POOL CHANGING ROOM
Approval to proceed on GA's
GA Design drawing
Final issues of drawings
Approval / Comments
Review and Re- Issue
Samples Approval
Manufacture
Delivery to site
Installation
POOL HALL / SAUNA / STEAM ROOM
Submission of preliminaries detail for approval
Review of details
Approval to proceed on GA's
GA Design drawing
Final issues of drawings
Approval / Comments
Review and Re- Issue
Samples Approval
16/02/2015
12/03/2015
18/03/2015
23/03/2015
26/03/2015
26/03/2015
12/05/2015
15/05/2015
15/05/2015
15/05/2015
19/05/2015
21/05/2015
21/05/2015
26/05/2015
01/06/2015
05/06/2015
05/06/2015
09/06/2015
09/06/2015
16/06/2015
19/06/2015
23/02/2015
23/02/2015
23/02/2015
12/03/2015
18/03/2015
23/03/2015
26/03/2015
26/03/2015
12/05/2015
15/05/2015
02/03/2015
02/03/2015
02/03/2015
05/03/2015
05/03/2015
12/03/2015
18/03/2015
24/03/2015
27/03/2015
3w 3d
1w
3d
3d
6w
3d
5w 2d
1w 1d
1w 4d
1w
1w 2d
4w 1d
1w
1w 3d
1w 1d
1w 3d
1w 3d
1w 4d
1w
3d
14w 1d
2w 3d
4d
3d
3d
6w
3d
3w
15w 1d
3d
1w
1w
4d
3d
11/03/2015
18/03/2015
20/03/2015
25/03/2015
26/03/2015
11/05/2015
14/05/2015
23/06/2015
22/05/2015
28/05/2015
26/05/2015
01/06/2015
19/06/2015
01/06/2015
10/06/2015
12/06/2015
16/06/2015
18/06/2015
19/06/2015
22/06/2015
23/06/2015
05/06/2015
23/02/2015
11/03/2015
17/03/2015
20/03/2015
25/03/2015
26/03/2015
11/05/2015
14/05/2015
05/06/2015
19/06/2015
02/03/2015
04/03/2015
05/03/2015
11/03/2015
18/03/2015
23/03/2015
26/03/2015
27/03/2015
50.00
9.15
100.00
50.00
-3d
-4h
-4h
-2d
-2d
-2d
118 GA Design drawing
119 Final issues of drawings
120 Approval / Comments
121 Review and Re- Issue
122 Samples Approval
123 Manufacture
124 Actual Delivery to site
125 Installation
126 Installation of Oak Timber Ceilings
127 Oak veneered ceiling
128 Oak timber ceiling edge mouldings
129 Oak Timber Floor Installation
130 Bianco perlino stone Floor Installation
131 First fix installation oak timber skirting,frame,all height shutters,Pivot set and Fitting
132 Final fix installation oak timber skirting,frame,all height shutters,Pivot set and Fittings
133 Install all height Palisandro stone cladding / Lift lobby timber skirting and frieze
134 Install all height oak lattice with lacquered panel /timber slats ,Mullions / skirting
135 Install laminated glass stair railing / timber stair cladding
136 Install oak door frame,door, trims,oak blinds,ironmongery
137 Installation of Stuccoed columns with skirting
138 Carpet installation
139 POOL CHANGING ROOM
140 Approval to proceed on GA's
141 GA Design drawing
142 Final issues of drawings
143 Approval / Comments
144 Review and Re- Issue
145 Samples Approval
146 Manufacture
147 Delivery to site
148 Installation
149 POOL HALL / SAUNA / STEAM ROOM
150 Submission of preliminaries detail for approval
151 Review of details
152 Approval to proceed on GA's
153 GA Design drawing
154 Final issues of drawings
155 Approval / Comments
156 Review and Re- Issue
157 Samples Approval
118 GA Design drawing
119 Final issues of drawings
120 Approval / Comments
121 Review and Re- Issue
122 Samples Approval
123 Manufacture
124 Actual Delivery to site
125 Installation
126 Installation of Oak Timber Ceilings
127 Oak veneered ceiling
128 Oak timber ceiling edge mouldings
129 Oak Timber Floor Installation
130 Bianco perlino stone Floor Installation
131 First fix installation oak timber skirting,frame,all height shutters,Pivot set and Fitting
132 Final fix installation oak timber skirting,frame,all height shutters,Pivot set and Fittings
133 Install all height Palisandro stone cladding / Lift lobby timber skirting and frieze
134 Install all height oak lattice with lacquered panel /timber slats ,Mullions / skirting
135 Install laminated glass stair railing / timber stair cladding
136 Install oak door frame,door, trims,oak blinds,ironmongery
137 Installation of Stuccoed columns with skirting
138 Carpet installation
139 POOL CHANGING ROOM
140 Approval to proceed on GA's
141 GA Design drawing
142 Final issues of drawings
143 Approval / Comments
144 Review and Re- Issue
145 Samples Approval
146 Manufacture
147 Delivery to site
148 Installation
149 POOL HALL / SAUNA / STEAM ROOM
150 Submission of preliminaries detail for approval
151 Review of details
152 Approval to proceed on GA's
153 GA Design drawing
154 Final issues of drawings
155 Approval / Comments
156 Review and Re- Issue
157 Samples Approval
Prog No
000012.
Revision: A
Comment: Embassy Gardens- Front Of House Revision Date: 05/03/2015
Drawn By
dele
Drawn Date
05/03/2015
Program Status: Embassy Gardens- Front Of House Target Dates
D
S&T Interiors (UK) Ltd
55 Bryanston Street, March Arch Tower
London W1H 7AA tel: 02078598390
www.stcgroups.com
EMBASSY GARDENS FOH
Design, Manufacture and Delivery Programme
Line Name Start Duration Finish
Percent
complete
Slip
2015
February March April May June JulyJanuary August
26 2 9 16 23 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 6 13 20 27 3
2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 291
21 23 27 29 2 4 6 10 12 16 18 20 24 26 2 4 6 10 12 16 18 20 24 26 30 1 3 7 9 13 15 17 21 23 27 29 1 5 7 11 13 15 19 21 25 27 29 2 4 8 10 12 16 18 22 24 26 30 2 6 8 10 14 16 20 22 24 28 30 3 5 7
158
159
160
161
162
163
164
165
166
167
168
169
170
171
172
173
174
175
176
177
178
179
180
181
182
183
184
185
186
187
188
189
190
191
192
193
Manufacture
Actual Delivery to site
Installation of timber sauna system
Stone Sauna steam room
GYM STUDIO
Definition of scope and area
Approval to proceed on GA's
GA Design drawing
Final issues of drawings
Approval / Comments
Review and Re- Issue
Samples Approval
Manufacture
Actual Delivery to site
Installation
Install Oak Timber Flooring with foam beneath
Install oak timber banquette, timber trim, skirting
Install all height partition wall / cupboard, mirror
Install Oak timber fire rated door,oak skirting, frame,leaf and Ironmongery
Install plant room door, Vanity mirror, supports / Lattice panel
Install all height mirror panel with timber frame / skirting
Install felt upholstered planels/Linen upholstered walls
Install upholstered panel with timber from bench top to ceiling
Carpet / PVC Flooring Installation
POOL HALL (SEPARATE AREA)
Definition of scope and area
Approval to proceed on GA's
GA Design drawing
Final issues of drawings
Approval / Comments
Review and Re- Issue
Samples Approval
Manufacture
Delivery to site
Installation
Project Completion (08/07/2015)
27/03/2015
13/05/2015
15/05/2015
28/05/2015
23/02/2015
23/02/2015
05/03/2015
05/03/2015
12/03/2015
18/03/2015
24/03/2015
27/03/2015
30/03/2015
14/05/2015
19/05/2015
19/05/2015
21/05/2015
26/05/2015
26/05/2015
01/06/2015
01/06/2015
08/06/2015
10/06/2015
17/06/2015
09/03/2015
09/03/2015
19/03/2015
19/03/2015
02/04/2015
09/04/2015
14/04/2015
17/04/2015
17/04/2015
02/06/2015
05/06/2015
08/07/2015
6w
3d
3w
3w 2d
16w 3d
1w 3d
1w
1w
4d
3d
1d
6w
3d
5w
1w 2d
1w 4d
1w 4d
2w
1w 2d
2w
1w 3d
1w 3d
1w
14w 1d
1w 3d
2w
3d
3d
3d
6w
3d
2w 1d
12/05/2015
15/05/2015
05/06/2015
19/06/2015
23/06/2015
04/03/2015
05/03/2015
11/03/2015
18/03/2015
23/03/2015
26/03/2015
27/03/2015
13/05/2015
18/05/2015
23/06/2015
28/05/2015
03/06/2015
05/06/2015
08/06/2015
09/06/2015
12/06/2015
17/06/2015
19/06/2015
23/06/2015
19/06/2015
18/03/2015
19/03/2015
01/04/2015
08/04/2015
13/04/2015
16/04/2015
17/04/2015
01/06/2015
04/06/2015
19/06/2015
08/07/2015
-1w 2d
-1w 2d
158 Manufacture
159 Actual Delivery to site
160 Installation of timber sauna system
161 Stone Sauna steam room
162 GYM STUDIO
163 Definition of scope and area
164 Approval to proceed on GA's
165 GA Design drawing
166 Final issues of drawings
167 Approval / Comments
168 Review and Re- Issue
169 Samples Approval
170 Manufacture
171 Actual Delivery to site
172 Installation
173 Install Oak Timber Flooring with foam beneath
174 Install oak timber banquette, timber trim, skirting
175 Install all height partition wall / cupboard, mirror
176 Install Oak timber fire rated door,oak skirting, frame,leaf and Ironmongery
177 Install plant room door, Vanity mirror, supports / Lattice panel
178 Install all height mirror panel with timber frame / skirting
179 Install felt upholstered planels/Linen upholstered walls
180 Install upholstered panel with timber from bench top to ceiling
181 Carpet / PVC Flooring Installation
182 POOL HALL (SEPARATE AREA)
183 Definition of scope and area
184 Approval to proceed on GA's
185 GA Design drawing
186 Final issues of drawings
187 Approval / Comments
188 Review and Re- Issue
189 Samples Approval
190 Manufacture
191 Delivery to site
192 Installation
193 Project Completion (08/07/2015)
158 Manufacture
159 Actual Delivery to site
160 Installation of timber sauna system
161 Stone Sauna steam room
162 GYM STUDIO
163 Definition of scope and area
164 Approval to proceed on GA's
165 GA Design drawing
166 Final issues of drawings
167 Approval / Comments
168 Review and Re- Issue
169 Samples Approval
170 Manufacture
171 Actual Delivery to site
172 Installation
173 Install Oak Timber Flooring with foam beneath
174 Install oak timber banquette, timber trim, skirting
175 Install all height partition wall / cupboard, mirror
176 Install Oak timber fire rated door,oak skirting, frame,leaf and Ironmongery
177 Install plant room door, Vanity mirror, supports / Lattice panel
178 Install all height mirror panel with timber frame / skirting
179 Install felt upholstered planels/Linen upholstered walls
180 Install upholstered panel with timber from bench top to ceiling
181 Carpet / PVC Flooring Installation
182 POOL HALL (SEPARATE AREA)
183 Definition of scope and area
184 Approval to proceed on GA's
185 GA Design drawing
186 Final issues of drawings
187 Approval / Comments
188 Review and Re- Issue
189 Samples Approval
190 Manufacture
191 Delivery to site
192 Installation
193 Project Completion (08/07/2015)
Procurement Stages
Actual Delivery Date by IP

EMBASSY GARDENS FOH CONSTRUCTION PROGRAMME REV E

  • 1.
    Prog No 000012. Revision: A Comment:Embassy Gardens- Front Of House Revision Date: 05/03/2015 Drawn By dele Drawn Date 05/03/2015 Program Status: Embassy Gardens- Front Of House Target Dates D S&T Interiors (UK) Ltd 55 Bryanston Street, March Arch Tower London W1H 7AA tel: 02078598390 www.stcgroups.com EMBASSY GARDENS FOH Design, Manufacture and Delivery Programme Line Name Start Duration Finish Percent complete Slip 2015 February March April May June JulyJanuary August 26 2 9 16 23 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 6 13 20 27 3 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 291 21 23 27 29 2 4 6 10 12 16 18 20 24 26 2 4 6 10 12 16 18 20 24 26 30 1 3 7 9 13 15 17 21 23 27 29 1 5 7 11 13 15 19 21 25 27 29 2 4 8 10 12 16 18 22 24 26 30 2 6 8 10 14 16 20 22 24 28 30 3 5 7 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 EMBASSY GARDEN FRONT OF HOUSE L00 - Ground Floor Business Centre Manufacture Delivery to site of Joinery First fix speciality joinery (cupboards,veneered doors,oak frame, fittings/ fixing Speciality Joinery, of cupboard,Sliding door / gloss lacquered panels Install all height oak glazed screens with 50mm timber frame Delivery to site of Joinery shutters Install oak shutters to glazed screens Upholstered Ceiling & Wall Panels installation L00 - Ground Floor Lavatories Install and painting of Plasterboard Ceiling Install Bianco Carrara stone around vanity units with polished nickel frames Install Oak timber floor / Dark grey stone floor finish / Val D' isere Matt Lacquered frame to ceiling corridor area Actual Delivery to site First fix of timber cubicle doors,frameand ironmongery Delivery to site vanity metal profile,skirting,cornce,mirrors Installation of Fittings Final fixes of timber cubicle doors,frame and ironmongery Installation of wallpaper / Lacquered skirting, Frieze and Polished Nickel frame Installation of hanging mirrors L00 - D1 / D2 STAIRS Manufacture Actual Delivery to site Installation Install timber floor to base of staircase Timber cladding to staircase Install timber ceiling cornice Striped wallpaper to staircase walls CINEMA GROUND FLOOR Design drawing Final issues of drawings Approvals / Comments Review and Re- Issue Manufacture Actual Delivery to site 22/01/2015 26/01/2015 26/01/2015 16/02/2015 20/02/2015 24/02/2015 03/03/2015 27/02/2015 04/03/2015 09/03/2015 16/02/2015 16/02/2015 23/02/2015 02/03/2015 09/03/2015 09/03/2015 10/03/2015 10/03/2015 13/03/2015 18/03/2015 23/03/2015 26/03/2015 26/01/2015 26/01/2015 11/02/2015 18/02/2015 18/02/2015 23/02/2015 27/02/2015 06/03/2015 26/01/2015 26/01/2015 23/02/2015 23/02/2015 03/03/2015 11/03/2015 15/04/2015 23w 7w 3w 1w 1d 1w 1w 3d 1w 2d 3d 1w 1d 1w 6w 2d 1w 2w 1w 3d 1w 2d 3d 3d 3d 1w 2d 1w 1w 4d 7w 2d 2w 2d 1w 4w 1w 2w 1w 4d 1w 3d 17w 2d 4w 1w 1d 1w 1d 4w 3d 1w 08/07/2015 13/03/2015 13/02/2015 23/02/2015 26/02/2015 05/03/2015 11/03/2015 03/03/2015 11/03/2015 13/03/2015 31/03/2015 20/02/2015 06/03/2015 12/03/2015 17/03/2015 11/03/2015 12/03/2015 12/03/2015 23/03/2015 25/03/2015 27/03/2015 31/03/2015 17/03/2015 10/02/2015 17/02/2015 17/03/2015 24/02/2015 06/03/2015 11/03/2015 17/03/2015 01/06/2015 20/02/2015 23/02/2015 02/03/2015 10/03/2015 14/04/2015 21/04/2015 11.50 74.55 100.00 100.00 100.00 100.00 100.00 15.67 70.00 20.00 100.00 50.00 60.82 100.00 100.00 40.00 100.00 60.00 20.00 13.76 75.00 -1w 2d 1d 5h 2d 1w 1d -3d -2d 5h -1w 4d -1w 2d -1d 7h 4d 3h 6d 1w 4h -1d 48min -1d 48min -1d -1d 2h -2w 2d -2w 2d -1w 2d -1w 2d -1d 1 EMBASSY GARDEN FRONT OF HOUSE 2 L00 - Ground Floor Business Centre 3 Manufacture 4 Delivery to site of Joinery 5 First fix speciality joinery (cupboards,veneered doors,oak frame, fittings/ fixing 6 Speciality Joinery, of cupboard,Sliding door / gloss lacquered panels 7 Install all height oak glazed screens with 50mm timber frame 8 Delivery to site of Joinery shutters 9 Install oak shutters to glazed screens 10 Upholstered Ceiling & Wall Panels installation 11 L00 - Ground Floor Lavatories 12 Install and painting of Plasterboard Ceiling 13 Install Bianco Carrara stone around vanity units with polished nickel frames 14 Install Oak timber floor / Dark grey stone floor finish / Val D' isere 15 Matt Lacquered frame to ceiling corridor area 16 Actual Delivery to site 17 First fix of timber cubicle doors,frameand ironmongery 18 Delivery to site vanity metal profile,skirting,cornce,mirrors 19 Installation of Fittings 20 Final fixes of timber cubicle doors,frame and ironmongery 21 Installation of wallpaper / Lacquered skirting, Frieze and Polished Nickel frame 22 Installation of hanging mirrors 23 L00 - D1 / D2 STAIRS 24 Manufacture 25 Actual Delivery to site 26 Installation 27 Install timber floor to base of staircase 28 Timber cladding to staircase 29 Install timber ceiling cornice 30 Striped wallpaper to staircase walls 31 CINEMA GROUND FLOOR 32 Design drawing 33 Final issues of drawings 34 Approvals / Comments 35 Review and Re- Issue 36 Manufacture 37 Actual Delivery to site 1 EMBASSY GARDEN FRONT OF HOUSE 2 L00 - Ground Floor Business Centre 3 Manufacture 4 Delivery to site of Joinery 5 First fix speciality joinery (cupboards,veneered doors,oak frame, fittings/ fixing 6 Speciality Joinery, of cupboard,Sliding door / gloss lacquered panels 7 Install all height oak glazed screens with 50mm timber frame 8 Delivery to site of Joinery shutters 9 Install oak shutters to glazed screens 10 Upholstered Ceiling & Wall Panels installation 11 L00 - Ground Floor Lavatories 12 Install and painting of Plasterboard Ceiling 13 Install Bianco Carrara stone around vanity units with polished nickel frames 14 Install Oak timber floor / Dark grey stone floor finish / Val D' isere 15 Matt Lacquered frame to ceiling corridor area 16 Actual Delivery to site 17 First fix of timber cubicle doors,frameand ironmongery 18 Delivery to site vanity metal profile,skirting,cornce,mirrors 19 Installation of Fittings 20 Final fixes of timber cubicle doors,frame and ironmongery 21 Installation of wallpaper / Lacquered skirting, Frieze and Polished Nickel frame 22 Installation of hanging mirrors 23 L00 - D1 / D2 STAIRS 24 Manufacture 25 Actual Delivery to site 26 Installation 27 Install timber floor to base of staircase 28 Timber cladding to staircase 29 Install timber ceiling cornice 30 Striped wallpaper to staircase walls 31 CINEMA GROUND FLOOR 32 Design drawing 33 Final issues of drawings 34 Approvals / Comments 35 Review and Re- Issue 36 Manufacture 37 Actual Delivery to site
  • 2.
    Prog No 000012. Revision: A Comment:Embassy Gardens- Front Of House Revision Date: 05/03/2015 Drawn By dele Drawn Date 05/03/2015 Program Status: Embassy Gardens- Front Of House Target Dates D S&T Interiors (UK) Ltd 55 Bryanston Street, March Arch Tower London W1H 7AA tel: 02078598390 www.stcgroups.com EMBASSY GARDENS FOH Design, Manufacture and Delivery Programme Line Name Start Duration Finish Percent complete Slip 2015 February March April May June JulyJanuary August 26 2 9 16 23 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 6 13 20 27 3 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 291 21 23 27 29 2 4 6 10 12 16 18 20 24 26 2 4 6 10 12 16 18 20 24 26 30 1 3 7 9 13 15 17 21 23 27 29 1 5 7 11 13 15 19 21 25 27 29 2 4 8 10 12 16 18 22 24 26 30 2 6 8 10 14 16 20 22 24 28 30 3 5 7 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 Installation First fix of perimeter framework Review Install Upholstered Plasterboard Ceiling 40x170mm oak frames and 40x40mm antique brass frames to upholstered ceiling Raised Floor installation / floor build up Install fabric clad acoustic door, leaf & frame Install vertical, base & head Oak panels to perimeter walls Install Fabric wall Panelling Carpet Installation GYM RECEPTION Design drawing Final issues of drawings Approval / Comments Review and Re- Issue Samples Approval Manufacture Actual Delivery to site Installation Install of oak timber ceiling and painting of Plasterboard Ceiling Oak Timber Floor strip installation First fix of Oak timber finished fire doors Final fixes of Oak timber finish to stairs / fire doors /brass trims Wall finishes - Oak timber panelling ,skirting and painted plasterboard Ebonised timber panelling with brass trims / lacquered panelling besides lifts Red Gloss panelling behind entrance desk, Polyester flushed Carpet Installation GYM CHANGING ROOM Design drawing Final issues of drawings Approval / Comments Review and Re- Issue Samples Approval Manufacture Actual Delivery to site Installation Install of oak timber ceiling and painting of Plasterboard Ceiling Oak Timber Floor strip installation First fix of Oak timber finished fire doors Final fixes of Oak timber finish to stairs / fire doors /brass trims Wall finishes - Oak timber panelling ,skirting and painted plasterboard 22/04/2015 22/04/2015 28/04/2015 30/04/2015 06/05/2015 11/05/2015 13/05/2015 19/05/2015 27/05/2015 05/02/2015 05/02/2015 26/02/2015 26/02/2015 03/03/2015 10/03/2015 10/03/2015 23/04/2015 28/04/2015 28/04/2015 29/04/2015 30/04/2015 06/05/2015 11/05/2015 13/05/2015 14/05/2015 22/05/2015 22/01/2015 22/01/2015 12/02/2015 18/02/2015 23/02/2015 02/03/2015 02/03/2015 15/04/2015 20/04/2015 20/04/2015 21/04/2015 21/04/2015 28/04/2015 28/04/2015 5w 2d 4d 1w 3d 1w 2d 1w 1d 1w 1d 1w 2d 1w 2d 4d 15w 4d 3w 1w 1w 6w 3d 4w 3d 1w 1d 1w 1d 3d 1w 2d 1w 1d 1w 1d 1w 1d 1w 1d 16w 2d 3w 1w 3d 1w 6w 3d 4w 2d 1w 1d 2w 1w 1w 3d 1w 01/06/2015 27/04/2015 08/05/2015 11/05/2015 13/05/2015 18/05/2015 21/05/2015 28/05/2015 01/06/2015 01/06/2015 25/02/2015 26/02/2015 04/03/2015 09/03/2015 10/03/2015 22/04/2015 27/04/2015 01/06/2015 06/05/2015 07/05/2015 05/05/2015 14/05/2015 18/05/2015 20/05/2015 21/05/2015 01/06/2015 20/05/2015 11/02/2015 18/02/2015 20/02/2015 27/02/2015 02/03/2015 14/04/2015 17/04/2015 20/05/2015 27/04/2015 05/05/2015 27/04/2015 08/05/2015 05/05/2015 11.54 80.00 6.47 50.00 -1w 2d -1w 2d -4d -4d -1d -4w 2d -4w 2d -2w 4d -2w -1w 2d -2d -2d 38 Installation 39 First fix of perimeter framework Review 40 Install Upholstered Plasterboard Ceiling 41 40x170mm oak frames and 40x40mm antique brass frames to upholstered ceiling 42 Raised Floor installation / floor build up 43 Install fabric clad acoustic door, leaf & frame 44 Install vertical, base & head Oak panels to perimeter walls 45 Install Fabric wall Panelling 46 Carpet Installation 47 GYM RECEPTION 48 Design drawing 49 Final issues of drawings 50 Approval / Comments 51 Review and Re- Issue 52 Samples Approval 53 Manufacture 54 Actual Delivery to site 55 Installation 56 Install of oak timber ceiling and painting of Plasterboard Ceiling 57 Oak Timber Floor strip installation 58 First fix of Oak timber finished fire doors 59 Final fixes of Oak timber finish to stairs / fire doors /brass trims 60 Wall finishes - Oak timber panelling ,skirting and painted plasterboard 61 Ebonised timber panelling with brass trims / lacquered panelling besides lifts 62 Red Gloss panelling behind entrance desk, 63 Polyester flushed Carpet Installation 64 GYM CHANGING ROOM 65 Design drawing 66 Final issues of drawings 67 Approval / Comments 68 Review and Re- Issue 69 Samples Approval 70 Manufacture 71 Actual Delivery to site 72 Installation 73 Install of oak timber ceiling and painting of Plasterboard Ceiling 74 Oak Timber Floor strip installation 75 First fix of Oak timber finished fire doors 76 Final fixes of Oak timber finish to stairs / fire doors /brass trims 77 Wall finishes - Oak timber panelling ,skirting and painted plasterboard 38 Installation 39 First fix of perimeter framework Review 40 Install Upholstered Plasterboard Ceiling 41 40x170mm oak frames and 40x40mm antique brass frames to upholstered ceiling 42 Raised Floor installation / floor build up 43 Install fabric clad acoustic door, leaf & frame 44 Install vertical, base & head Oak panels to perimeter walls 45 Install Fabric wall Panelling 46 Carpet Installation 47 GYM RECEPTION 48 Design drawing 49 Final issues of drawings 50 Approval / Comments 51 Review and Re- Issue 52 Samples Approval 53 Manufacture 54 Actual Delivery to site 55 Installation 56 Install of oak timber ceiling and painting of Plasterboard Ceiling 57 Oak Timber Floor strip installation 58 First fix of Oak timber finished fire doors 59 Final fixes of Oak timber finish to stairs / fire doors /brass trims 60 Wall finishes - Oak timber panelling ,skirting and painted plasterboard 61 Ebonised timber panelling with brass trims / lacquered panelling besides lifts 62 Red Gloss panelling behind entrance desk, 63 Polyester flushed Carpet Installation 64 GYM CHANGING ROOM 65 Design drawing 66 Final issues of drawings 67 Approval / Comments 68 Review and Re- Issue 69 Samples Approval 70 Manufacture 71 Actual Delivery to site 72 Installation 73 Install of oak timber ceiling and painting of Plasterboard Ceiling 74 Oak Timber Floor strip installation 75 First fix of Oak timber finished fire doors 76 Final fixes of Oak timber finish to stairs / fire doors /brass trims 77 Wall finishes - Oak timber panelling ,skirting and painted plasterboard
  • 3.
    Prog No 000012. Revision: A Comment:Embassy Gardens- Front Of House Revision Date: 05/03/2015 Drawn By dele Drawn Date 05/03/2015 Program Status: Embassy Gardens- Front Of House Target Dates D S&T Interiors (UK) Ltd 55 Bryanston Street, March Arch Tower London W1H 7AA tel: 02078598390 www.stcgroups.com EMBASSY GARDENS FOH Design, Manufacture and Delivery Programme Line Name Start Duration Finish Percent complete Slip 2015 February March April May June JulyJanuary August 26 2 9 16 23 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 6 13 20 27 3 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 291 21 23 27 29 2 4 6 10 12 16 18 20 24 26 2 4 6 10 12 16 18 20 24 26 30 1 3 7 9 13 15 17 21 23 27 29 1 5 7 11 13 15 19 21 25 27 29 2 4 8 10 12 16 18 22 24 26 30 2 6 8 10 14 16 20 22 24 28 30 3 5 7 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108 109 110 111 112 113 114 115 116 117 Ebonised timber panelling with brass trims / lacquered panelling besides lifts Red Gloss panelling behind entrance desk, Polyester flushed Carpet Installation GYM Design drawing Final issues of drawings Approval / Comments Review and Re- Issue Samples Approval Manufacture Actual Delivery to site Installation CLUB LOUNGE Design drawing Final issues of drawings Approval / Comments Review and Re- Issue Samples Approval Manufacture Actual Delivery to site Delivery of carpet Delivery of Fabric for upholstered panels Installation CLUB LOUNGE/ LAVATORIES Approval to proceed on GA's GA Design drawing Final issues of drawings Approval / Comments Review and Re- Issue Samples Approval Manufacture Actual Delivery to site Installation Painted Plasterboard / MDF Lacquered Ceiling Stone & Oak Floor installation Installation of Painted architrave /skirting Vanity Basin Installation of single lacquered door, frame with lacquered architrave / Ironmongery Marble cladding / Wall finishes Installation POOL VESTIBULE / FEATURE STAIRS Approval to proceed on GA's 01/05/2015 06/05/2015 12/05/2015 22/01/2015 22/01/2015 16/02/2015 20/02/2015 25/02/2015 04/03/2015 04/03/2015 17/04/2015 22/04/2015 22/01/2015 22/01/2015 16/02/2015 20/02/2015 27/02/2015 06/03/2015 06/03/2015 21/04/2015 07/04/2015 13/04/2015 24/04/2015 27/02/2015 27/02/2015 27/02/2015 06/03/2015 12/03/2015 17/03/2015 20/03/2015 20/03/2015 07/05/2015 12/05/2015 12/05/2015 14/05/2015 14/05/2015 20/05/2015 28/05/2015 16/02/2015 16/02/2015 1w 1d 1w 3d 1w 2d 15w 3w 2d 1w 3d 1w 6w 3d 2w 3d 15w 4d 3w 2d 1w 1w 1w 6w 3d 4d 1w 1d 3w 14w 2d 1w 1w 3d 3d 6w 1d 3d 4w 3d 1w 3d 1w 2d 2w 2w 3d 2w 2d 17w 3d 11/05/2015 15/05/2015 20/05/2015 11/05/2015 13/02/2015 20/02/2015 24/02/2015 03/03/2015 04/03/2015 16/04/2015 21/04/2015 11/05/2015 15/05/2015 13/02/2015 20/02/2015 26/02/2015 05/03/2015 06/03/2015 20/04/2015 23/04/2015 10/04/2015 20/04/2015 15/05/2015 12/06/2015 27/02/2015 05/03/2015 12/03/2015 16/03/2015 19/03/2015 20/03/2015 06/05/2015 11/05/2015 12/06/2015 21/05/2015 22/05/2015 28/05/2015 08/06/2015 12/06/2015 23/06/2015 16/02/2015 11.18 50.00 9.44 50.00 5.56 100.00 -4w 4h -4w 4h -2w 2d -1w 3d -1w -4w 4h -4w 4h -2w 2d -1w 3d -3d -3d -3d -3d -3d 78 Ebonised timber panelling with brass trims / lacquered panelling besides lifts 79 Red Gloss panelling behind entrance desk, 80 Polyester flushed Carpet Installation 81 GYM 82 Design drawing 83 Final issues of drawings 84 Approval / Comments 85 Review and Re- Issue 86 Samples Approval 87 Manufacture 88 Actual Delivery to site 89 Installation 90 CLUB LOUNGE 91 Design drawing 92 Final issues of drawings 93 Approval / Comments 94 Review and Re- Issue 95 Samples Approval 96 Manufacture 97 Actual Delivery to site 98 Delivery of carpet 99 Delivery of Fabric for upholstered panels 100 Installation 101 CLUB LOUNGE/ LAVATORIES 102 Approval to proceed on GA's 103 GA Design drawing 104 Final issues of drawings 105 Approval / Comments 106 Review and Re- Issue 107 Samples Approval 108 Manufacture 109 Actual Delivery to site 110 Installation 111 Painted Plasterboard / MDF Lacquered Ceiling 112 Stone & Oak Floor installation 113 Installation of Painted architrave /skirting Vanity Basin 114 Installation of single lacquered door, frame with lacquered architrave / Ironmongery 115 Marble cladding / Wall finishes Installation 116 POOL VESTIBULE / FEATURE STAIRS 117 Approval to proceed on GA's 78 Ebonised timber panelling with brass trims / lacquered panelling besides lifts 79 Red Gloss panelling behind entrance desk, 80 Polyester flushed Carpet Installation 81 GYM 82 Design drawing 83 Final issues of drawings 84 Approval / Comments 85 Review and Re- Issue 86 Samples Approval 87 Manufacture 88 Actual Delivery to site 89 Installation 90 CLUB LOUNGE 91 Design drawing 92 Final issues of drawings 93 Approval / Comments 94 Review and Re- Issue 95 Samples Approval 96 Manufacture 97 Actual Delivery to site 98 Delivery of carpet 99 Delivery of Fabric for upholstered panels 100 Installation 101 CLUB LOUNGE/ LAVATORIES 102 Approval to proceed on GA's 103 GA Design drawing 104 Final issues of drawings 105 Approval / Comments 106 Review and Re- Issue 107 Samples Approval 108 Manufacture 109 Actual Delivery to site 110 Installation 111 Painted Plasterboard / MDF Lacquered Ceiling 112 Stone & Oak Floor installation 113 Installation of Painted architrave /skirting Vanity Basin 114 Installation of single lacquered door, frame with lacquered architrave / Ironmongery 115 Marble cladding / Wall finishes Installation 116 POOL VESTIBULE / FEATURE STAIRS 117 Approval to proceed on GA's
  • 4.
    Prog No 000012. Revision: A Comment:Embassy Gardens- Front Of House Revision Date: 05/03/2015 Drawn By dele Drawn Date 05/03/2015 Program Status: Embassy Gardens- Front Of House Target Dates D S&T Interiors (UK) Ltd 55 Bryanston Street, March Arch Tower London W1H 7AA tel: 02078598390 www.stcgroups.com EMBASSY GARDENS FOH Design, Manufacture and Delivery Programme Line Name Start Duration Finish Percent complete Slip 2015 February March April May June JulyJanuary August 26 2 9 16 23 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 6 13 20 27 3 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 291 21 23 27 29 2 4 6 10 12 16 18 20 24 26 2 4 6 10 12 16 18 20 24 26 30 1 3 7 9 13 15 17 21 23 27 29 1 5 7 11 13 15 19 21 25 27 29 2 4 8 10 12 16 18 22 24 26 30 2 6 8 10 14 16 20 22 24 28 30 3 5 7 118 119 120 121 122 123 124 125 126 127 128 129 130 131 132 133 134 135 136 137 138 139 140 141 142 143 144 145 146 147 148 149 150 151 152 153 154 155 156 157 GA Design drawing Final issues of drawings Approval / Comments Review and Re- Issue Samples Approval Manufacture Actual Delivery to site Installation Installation of Oak Timber Ceilings Oak veneered ceiling Oak timber ceiling edge mouldings Oak Timber Floor Installation Bianco perlino stone Floor Installation First fix installation oak timber skirting,frame,all height shutters,Pivot set and Fitting Final fix installation oak timber skirting,frame,all height shutters,Pivot set and Fittings Install all height Palisandro stone cladding / Lift lobby timber skirting and frieze Install all height oak lattice with lacquered panel /timber slats ,Mullions / skirting Install laminated glass stair railing / timber stair cladding Install oak door frame,door, trims,oak blinds,ironmongery Installation of Stuccoed columns with skirting Carpet installation POOL CHANGING ROOM Approval to proceed on GA's GA Design drawing Final issues of drawings Approval / Comments Review and Re- Issue Samples Approval Manufacture Delivery to site Installation POOL HALL / SAUNA / STEAM ROOM Submission of preliminaries detail for approval Review of details Approval to proceed on GA's GA Design drawing Final issues of drawings Approval / Comments Review and Re- Issue Samples Approval 16/02/2015 12/03/2015 18/03/2015 23/03/2015 26/03/2015 26/03/2015 12/05/2015 15/05/2015 15/05/2015 15/05/2015 19/05/2015 21/05/2015 21/05/2015 26/05/2015 01/06/2015 05/06/2015 05/06/2015 09/06/2015 09/06/2015 16/06/2015 19/06/2015 23/02/2015 23/02/2015 23/02/2015 12/03/2015 18/03/2015 23/03/2015 26/03/2015 26/03/2015 12/05/2015 15/05/2015 02/03/2015 02/03/2015 02/03/2015 05/03/2015 05/03/2015 12/03/2015 18/03/2015 24/03/2015 27/03/2015 3w 3d 1w 3d 3d 6w 3d 5w 2d 1w 1d 1w 4d 1w 1w 2d 4w 1d 1w 1w 3d 1w 1d 1w 3d 1w 3d 1w 4d 1w 3d 14w 1d 2w 3d 4d 3d 3d 6w 3d 3w 15w 1d 3d 1w 1w 4d 3d 11/03/2015 18/03/2015 20/03/2015 25/03/2015 26/03/2015 11/05/2015 14/05/2015 23/06/2015 22/05/2015 28/05/2015 26/05/2015 01/06/2015 19/06/2015 01/06/2015 10/06/2015 12/06/2015 16/06/2015 18/06/2015 19/06/2015 22/06/2015 23/06/2015 05/06/2015 23/02/2015 11/03/2015 17/03/2015 20/03/2015 25/03/2015 26/03/2015 11/05/2015 14/05/2015 05/06/2015 19/06/2015 02/03/2015 04/03/2015 05/03/2015 11/03/2015 18/03/2015 23/03/2015 26/03/2015 27/03/2015 50.00 9.15 100.00 50.00 -3d -4h -4h -2d -2d -2d 118 GA Design drawing 119 Final issues of drawings 120 Approval / Comments 121 Review and Re- Issue 122 Samples Approval 123 Manufacture 124 Actual Delivery to site 125 Installation 126 Installation of Oak Timber Ceilings 127 Oak veneered ceiling 128 Oak timber ceiling edge mouldings 129 Oak Timber Floor Installation 130 Bianco perlino stone Floor Installation 131 First fix installation oak timber skirting,frame,all height shutters,Pivot set and Fitting 132 Final fix installation oak timber skirting,frame,all height shutters,Pivot set and Fittings 133 Install all height Palisandro stone cladding / Lift lobby timber skirting and frieze 134 Install all height oak lattice with lacquered panel /timber slats ,Mullions / skirting 135 Install laminated glass stair railing / timber stair cladding 136 Install oak door frame,door, trims,oak blinds,ironmongery 137 Installation of Stuccoed columns with skirting 138 Carpet installation 139 POOL CHANGING ROOM 140 Approval to proceed on GA's 141 GA Design drawing 142 Final issues of drawings 143 Approval / Comments 144 Review and Re- Issue 145 Samples Approval 146 Manufacture 147 Delivery to site 148 Installation 149 POOL HALL / SAUNA / STEAM ROOM 150 Submission of preliminaries detail for approval 151 Review of details 152 Approval to proceed on GA's 153 GA Design drawing 154 Final issues of drawings 155 Approval / Comments 156 Review and Re- Issue 157 Samples Approval 118 GA Design drawing 119 Final issues of drawings 120 Approval / Comments 121 Review and Re- Issue 122 Samples Approval 123 Manufacture 124 Actual Delivery to site 125 Installation 126 Installation of Oak Timber Ceilings 127 Oak veneered ceiling 128 Oak timber ceiling edge mouldings 129 Oak Timber Floor Installation 130 Bianco perlino stone Floor Installation 131 First fix installation oak timber skirting,frame,all height shutters,Pivot set and Fitting 132 Final fix installation oak timber skirting,frame,all height shutters,Pivot set and Fittings 133 Install all height Palisandro stone cladding / Lift lobby timber skirting and frieze 134 Install all height oak lattice with lacquered panel /timber slats ,Mullions / skirting 135 Install laminated glass stair railing / timber stair cladding 136 Install oak door frame,door, trims,oak blinds,ironmongery 137 Installation of Stuccoed columns with skirting 138 Carpet installation 139 POOL CHANGING ROOM 140 Approval to proceed on GA's 141 GA Design drawing 142 Final issues of drawings 143 Approval / Comments 144 Review and Re- Issue 145 Samples Approval 146 Manufacture 147 Delivery to site 148 Installation 149 POOL HALL / SAUNA / STEAM ROOM 150 Submission of preliminaries detail for approval 151 Review of details 152 Approval to proceed on GA's 153 GA Design drawing 154 Final issues of drawings 155 Approval / Comments 156 Review and Re- Issue 157 Samples Approval
  • 5.
    Prog No 000012. Revision: A Comment:Embassy Gardens- Front Of House Revision Date: 05/03/2015 Drawn By dele Drawn Date 05/03/2015 Program Status: Embassy Gardens- Front Of House Target Dates D S&T Interiors (UK) Ltd 55 Bryanston Street, March Arch Tower London W1H 7AA tel: 02078598390 www.stcgroups.com EMBASSY GARDENS FOH Design, Manufacture and Delivery Programme Line Name Start Duration Finish Percent complete Slip 2015 February March April May June JulyJanuary August 26 2 9 16 23 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 6 13 20 27 3 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 291 21 23 27 29 2 4 6 10 12 16 18 20 24 26 2 4 6 10 12 16 18 20 24 26 30 1 3 7 9 13 15 17 21 23 27 29 1 5 7 11 13 15 19 21 25 27 29 2 4 8 10 12 16 18 22 24 26 30 2 6 8 10 14 16 20 22 24 28 30 3 5 7 158 159 160 161 162 163 164 165 166 167 168 169 170 171 172 173 174 175 176 177 178 179 180 181 182 183 184 185 186 187 188 189 190 191 192 193 Manufacture Actual Delivery to site Installation of timber sauna system Stone Sauna steam room GYM STUDIO Definition of scope and area Approval to proceed on GA's GA Design drawing Final issues of drawings Approval / Comments Review and Re- Issue Samples Approval Manufacture Actual Delivery to site Installation Install Oak Timber Flooring with foam beneath Install oak timber banquette, timber trim, skirting Install all height partition wall / cupboard, mirror Install Oak timber fire rated door,oak skirting, frame,leaf and Ironmongery Install plant room door, Vanity mirror, supports / Lattice panel Install all height mirror panel with timber frame / skirting Install felt upholstered planels/Linen upholstered walls Install upholstered panel with timber from bench top to ceiling Carpet / PVC Flooring Installation POOL HALL (SEPARATE AREA) Definition of scope and area Approval to proceed on GA's GA Design drawing Final issues of drawings Approval / Comments Review and Re- Issue Samples Approval Manufacture Delivery to site Installation Project Completion (08/07/2015) 27/03/2015 13/05/2015 15/05/2015 28/05/2015 23/02/2015 23/02/2015 05/03/2015 05/03/2015 12/03/2015 18/03/2015 24/03/2015 27/03/2015 30/03/2015 14/05/2015 19/05/2015 19/05/2015 21/05/2015 26/05/2015 26/05/2015 01/06/2015 01/06/2015 08/06/2015 10/06/2015 17/06/2015 09/03/2015 09/03/2015 19/03/2015 19/03/2015 02/04/2015 09/04/2015 14/04/2015 17/04/2015 17/04/2015 02/06/2015 05/06/2015 08/07/2015 6w 3d 3w 3w 2d 16w 3d 1w 3d 1w 1w 4d 3d 1d 6w 3d 5w 1w 2d 1w 4d 1w 4d 2w 1w 2d 2w 1w 3d 1w 3d 1w 14w 1d 1w 3d 2w 3d 3d 3d 6w 3d 2w 1d 12/05/2015 15/05/2015 05/06/2015 19/06/2015 23/06/2015 04/03/2015 05/03/2015 11/03/2015 18/03/2015 23/03/2015 26/03/2015 27/03/2015 13/05/2015 18/05/2015 23/06/2015 28/05/2015 03/06/2015 05/06/2015 08/06/2015 09/06/2015 12/06/2015 17/06/2015 19/06/2015 23/06/2015 19/06/2015 18/03/2015 19/03/2015 01/04/2015 08/04/2015 13/04/2015 16/04/2015 17/04/2015 01/06/2015 04/06/2015 19/06/2015 08/07/2015 -1w 2d -1w 2d 158 Manufacture 159 Actual Delivery to site 160 Installation of timber sauna system 161 Stone Sauna steam room 162 GYM STUDIO 163 Definition of scope and area 164 Approval to proceed on GA's 165 GA Design drawing 166 Final issues of drawings 167 Approval / Comments 168 Review and Re- Issue 169 Samples Approval 170 Manufacture 171 Actual Delivery to site 172 Installation 173 Install Oak Timber Flooring with foam beneath 174 Install oak timber banquette, timber trim, skirting 175 Install all height partition wall / cupboard, mirror 176 Install Oak timber fire rated door,oak skirting, frame,leaf and Ironmongery 177 Install plant room door, Vanity mirror, supports / Lattice panel 178 Install all height mirror panel with timber frame / skirting 179 Install felt upholstered planels/Linen upholstered walls 180 Install upholstered panel with timber from bench top to ceiling 181 Carpet / PVC Flooring Installation 182 POOL HALL (SEPARATE AREA) 183 Definition of scope and area 184 Approval to proceed on GA's 185 GA Design drawing 186 Final issues of drawings 187 Approval / Comments 188 Review and Re- Issue 189 Samples Approval 190 Manufacture 191 Delivery to site 192 Installation 193 Project Completion (08/07/2015) 158 Manufacture 159 Actual Delivery to site 160 Installation of timber sauna system 161 Stone Sauna steam room 162 GYM STUDIO 163 Definition of scope and area 164 Approval to proceed on GA's 165 GA Design drawing 166 Final issues of drawings 167 Approval / Comments 168 Review and Re- Issue 169 Samples Approval 170 Manufacture 171 Actual Delivery to site 172 Installation 173 Install Oak Timber Flooring with foam beneath 174 Install oak timber banquette, timber trim, skirting 175 Install all height partition wall / cupboard, mirror 176 Install Oak timber fire rated door,oak skirting, frame,leaf and Ironmongery 177 Install plant room door, Vanity mirror, supports / Lattice panel 178 Install all height mirror panel with timber frame / skirting 179 Install felt upholstered planels/Linen upholstered walls 180 Install upholstered panel with timber from bench top to ceiling 181 Carpet / PVC Flooring Installation 182 POOL HALL (SEPARATE AREA) 183 Definition of scope and area 184 Approval to proceed on GA's 185 GA Design drawing 186 Final issues of drawings 187 Approval / Comments 188 Review and Re- Issue 189 Samples Approval 190 Manufacture 191 Delivery to site 192 Installation 193 Project Completion (08/07/2015) Procurement Stages Actual Delivery Date by IP