By: Shrikant Bhansali
DIAGNOSIS OF UPS
6&8
CONTENT :
• What is ups
• What we want
• Basic configuration
• Load details
• Circuit diagram
• Current status
• Problems occurred due to ups(complains we received due to ups)
• Common causes
• Data analysis
• Changes we did
• What we can do
WHAT IS UPS ?
• Uninterruptible power source is an electrical apparatus
that provides emergency power to a load when the
input power source, typically mains power, fails.
• In our industry ups is used to give the auxiliary supply
sinter machine ,soaking machine ,pt machine , row
draw etc.
• Whenever main supply is stop our ups system provides
6MVA of power to system(critical load ) for 15min .
BASIC CONFIGURATION
• Ups 8 (eaton powerwave 9315)
-KVA 400
-KW 320
-No of modules =1
• Ups 6 (eaton powerwave 9395)
-KVA 825
-KW 742.5
-No of modules=3
LOAD DETAILS
On ups 8 (72% of full load )
Sinter(6)-10’3,26,23,24,35
Pt(6)-33,25,32,1,26,27
Soaking-59/60/61
Sod dual #12
On ups 6 (65% of full load)
Non critical load
CIRCUIT DIAGRAM
CURRENT STATUS
• Ups 6
 No critical load
 totally shut down
 Modules are removed
 Batteries from ups 6 banks are removed
 Panels are removed
• Ups8
 On bypass mode
 Replaced IGBT’s
 Batteries have high internal resistance
PROBLEMS OCCURRED DUE TO UPS(COMPLAINS)
DATA ANALYSIS
• Ups 8(according to the scada 1 min data)
 Fault date 30 jan 2016 time 1:15 to 1:18
 Power loss in KVA 66234
 Phase voltage 416 (constant through out the fault time)
 Phase current 182(at fault time current drop )
 Ups 6
CHANGES WE DID
• Ups 8
IGBT changed on 31 jan
Modules changed
Power supply board, monitor board
• Ups 6
All working modules are removed and shifted to
the workable ups
WHAT WE CAN DO
• As there r all the electronic circuit so for that hire a
electronic circuit expert and check the monitoring board
in the ups
• if possible then buy the new IGBT set and replace it to
the old one
• Battery checking and replacement for reliability of ups
operation
• Replacement of ups directly(which cost more)
Thank
you
Diagnosis of ups 6&8

More Related Content

What's hot

Northstar ace
Northstar aceNorthstar ace
Northstar ace
Tim Jones
 
Proper control plan assessment and the impact of high efficiency motors Dav...
Proper control plan assessment and the impact of high efficiency motors   Dav...Proper control plan assessment and the impact of high efficiency motors   Dav...
Proper control plan assessment and the impact of high efficiency motors Dav...
NSW Environment and Planning
 
His 4
His 4His 4
Continuity of supply means continuity of production
Continuity of supply means continuity of productionContinuity of supply means continuity of production
Continuity of supply means continuity of production
Rusty Roar Enterprises
 
5kW on grid case study, Chennai, India
5kW on grid case study, Chennai, India 5kW on grid case study, Chennai, India
5kW on grid case study, Chennai, India
giridaran123
 
Annual report card Owen Barry
Annual report card   Owen BarryAnnual report card   Owen Barry
Annual report card Owen Barry
NSW Environment and Planning
 
Troubleshooting egt system and tachometer system
Troubleshooting egt system and tachometer systemTroubleshooting egt system and tachometer system
Troubleshooting egt system and tachometer system
Superior Labs Inc
 
Standby power systems for hospitals
Standby power systems for hospitalsStandby power systems for hospitals
Standby power systems for hospitals
michaeljmack
 
Asc 4 data sheet 4921240529 uk (1)
Asc 4 data sheet 4921240529 uk (1)Asc 4 data sheet 4921240529 uk (1)
Asc 4 data sheet 4921240529 uk (1)
Sonu Goyal
 
Guide to Power Supply Testing with MaxBotix
Guide to Power Supply Testing with MaxBotixGuide to Power Supply Testing with MaxBotix
Guide to Power Supply Testing with MaxBotix
MaxBotix Inc
 
Mains operated under voltage over voltage trip switch
Mains operated under voltage over voltage trip switchMains operated under voltage over voltage trip switch
Mains operated under voltage over voltage trip switch
Edgefxkits & Solutions
 
Automotive al5801 led drivers
Automotive al5801 led driversAutomotive al5801 led drivers
Automotive al5801 led drivers
Rabyte
 
To know a microinverter powered by fsp
To know a microinverter powered by fspTo know a microinverter powered by fsp
To know a microinverter powered by fsp
FSP Technology Inc.
 
Advanced Motor Control Technologies – Part 1
Advanced Motor Control Technologies – Part 1Advanced Motor Control Technologies – Part 1
Advanced Motor Control Technologies – Part 1
Design World
 
TDK Lambda LS Series Single Output Power Supplies
TDK Lambda LS Series  Single Output Power SuppliesTDK Lambda LS Series  Single Output Power Supplies
TDK Lambda LS Series Single Output Power Supplies
Premier Farnell
 
Preventing circulating current in parallel generator applications
Preventing circulating current in parallel generator applicationsPreventing circulating current in parallel generator applications
Preventing circulating current in parallel generator applications
Mirus International
 
Acclerometer Part 14
Acclerometer Part 14Acclerometer Part 14
Acclerometer Part 14
Techvilla
 

What's hot (20)

Northstar ace
Northstar aceNorthstar ace
Northstar ace
 
Proper control plan assessment and the impact of high efficiency motors Dav...
Proper control plan assessment and the impact of high efficiency motors   Dav...Proper control plan assessment and the impact of high efficiency motors   Dav...
Proper control plan assessment and the impact of high efficiency motors Dav...
 
His 4
His 4His 4
His 4
 
Continuity of supply means continuity of production
Continuity of supply means continuity of productionContinuity of supply means continuity of production
Continuity of supply means continuity of production
 
Paul smart a
Paul smart aPaul smart a
Paul smart a
 
5kW on grid case study, Chennai, India
5kW on grid case study, Chennai, India 5kW on grid case study, Chennai, India
5kW on grid case study, Chennai, India
 
Before and After Power Conditioner
Before and After Power ConditionerBefore and After Power Conditioner
Before and After Power Conditioner
 
Annual report card Owen Barry
Annual report card   Owen BarryAnnual report card   Owen Barry
Annual report card Owen Barry
 
Troubleshooting egt system and tachometer system
Troubleshooting egt system and tachometer systemTroubleshooting egt system and tachometer system
Troubleshooting egt system and tachometer system
 
Standby power systems for hospitals
Standby power systems for hospitalsStandby power systems for hospitals
Standby power systems for hospitals
 
Asc 4 data sheet 4921240529 uk (1)
Asc 4 data sheet 4921240529 uk (1)Asc 4 data sheet 4921240529 uk (1)
Asc 4 data sheet 4921240529 uk (1)
 
Guide to Power Supply Testing with MaxBotix
Guide to Power Supply Testing with MaxBotixGuide to Power Supply Testing with MaxBotix
Guide to Power Supply Testing with MaxBotix
 
Mains operated under voltage over voltage trip switch
Mains operated under voltage over voltage trip switchMains operated under voltage over voltage trip switch
Mains operated under voltage over voltage trip switch
 
Riello vdc-xeb-flywheel-enery-storage-systems
Riello vdc-xeb-flywheel-enery-storage-systemsRiello vdc-xeb-flywheel-enery-storage-systems
Riello vdc-xeb-flywheel-enery-storage-systems
 
Automotive al5801 led drivers
Automotive al5801 led driversAutomotive al5801 led drivers
Automotive al5801 led drivers
 
To know a microinverter powered by fsp
To know a microinverter powered by fspTo know a microinverter powered by fsp
To know a microinverter powered by fsp
 
Advanced Motor Control Technologies – Part 1
Advanced Motor Control Technologies – Part 1Advanced Motor Control Technologies – Part 1
Advanced Motor Control Technologies – Part 1
 
TDK Lambda LS Series Single Output Power Supplies
TDK Lambda LS Series  Single Output Power SuppliesTDK Lambda LS Series  Single Output Power Supplies
TDK Lambda LS Series Single Output Power Supplies
 
Preventing circulating current in parallel generator applications
Preventing circulating current in parallel generator applicationsPreventing circulating current in parallel generator applications
Preventing circulating current in parallel generator applications
 
Acclerometer Part 14
Acclerometer Part 14Acclerometer Part 14
Acclerometer Part 14
 

Viewers also liked

Maintenance and Troubleshooting of Uninterruptible Power Supply (UPS) Systems...
Maintenance and Troubleshooting of Uninterruptible Power Supply (UPS) Systems...Maintenance and Troubleshooting of Uninterruptible Power Supply (UPS) Systems...
Maintenance and Troubleshooting of Uninterruptible Power Supply (UPS) Systems...
Living Online
 
UPS SCS Case Study
UPS SCS Case StudyUPS SCS Case Study
UPS SCS Case Study
Jessada Jarusasi, MBA, CFSE
 
The working principle of ups
The working principle of upsThe working principle of ups
The working principle of upsjayonline_4u
 
Uninterruptible Power Supply (UPS)
Uninterruptible Power Supply (UPS)Uninterruptible Power Supply (UPS)
Uninterruptible Power Supply (UPS)
Panduit
 
UPS Overview November 1, 2017
UPS Overview November 1, 2017UPS Overview November 1, 2017
UPS Overview November 1, 2017
UPS IR
 
Basics of ups seminar presentation
Basics of ups   seminar presentationBasics of ups   seminar presentation
Basics of ups seminar presentationMurali Krishnan
 

Viewers also liked (9)

Pensamiento sistematico
Pensamiento sistematicoPensamiento sistematico
Pensamiento sistematico
 
Maintenance and Troubleshooting of Uninterruptible Power Supply (UPS) Systems...
Maintenance and Troubleshooting of Uninterruptible Power Supply (UPS) Systems...Maintenance and Troubleshooting of Uninterruptible Power Supply (UPS) Systems...
Maintenance and Troubleshooting of Uninterruptible Power Supply (UPS) Systems...
 
UPS SCS Case Study
UPS SCS Case StudyUPS SCS Case Study
UPS SCS Case Study
 
The working principle of ups
The working principle of upsThe working principle of ups
The working principle of ups
 
Rajesh ppt 1
Rajesh ppt 1Rajesh ppt 1
Rajesh ppt 1
 
Uninterruptible Power Supply (UPS)
Uninterruptible Power Supply (UPS)Uninterruptible Power Supply (UPS)
Uninterruptible Power Supply (UPS)
 
Printer's
Printer'sPrinter's
Printer's
 
UPS Overview November 1, 2017
UPS Overview November 1, 2017UPS Overview November 1, 2017
UPS Overview November 1, 2017
 
Basics of ups seminar presentation
Basics of ups   seminar presentationBasics of ups   seminar presentation
Basics of ups seminar presentation
 

Similar to Diagnosis of ups 6&8

Become a Battery Sizing Guru
Become a Battery Sizing GuruBecome a Battery Sizing Guru
Become a Battery Sizing Guru
Sure Power, Inc.
 
upspresentation-112535108469-phpapp03.pdf
upspresentation-112535108469-phpapp03.pdfupspresentation-112535108469-phpapp03.pdf
upspresentation-112535108469-phpapp03.pdf
UmarHasanMohdAzhar
 
FSP UPS introduction 20150826
FSP UPS introduction 20150826FSP UPS introduction 20150826
FSP UPS introduction 20150826
FSP Technology Inc.
 
Ac supply system
Ac supply systemAc supply system
Ac supply systemankitankesh
 
Introduction to PLC
Introduction to PLCIntroduction to PLC
Introduction to PLC
Sana'a University
 
Rourkela Steel Pant Power System
Rourkela Steel Pant Power System Rourkela Steel Pant Power System
Rourkela Steel Pant Power System Sarthak Panigrahi
 
Knowledge sharing on UPS System (Updated).pptx
Knowledge sharing on UPS System (Updated).pptxKnowledge sharing on UPS System (Updated).pptx
Knowledge sharing on UPS System (Updated).pptx
Rilwan19
 
BEEE_seminor-1.pdf
BEEE_seminor-1.pdfBEEE_seminor-1.pdf
BEEE_seminor-1.pdf
SureshAnnadurai6
 
BASIC ELECTRO MECHANICAL ARRANGEMENTS.pptx
BASIC ELECTRO MECHANICAL ARRANGEMENTS.pptxBASIC ELECTRO MECHANICAL ARRANGEMENTS.pptx
BASIC ELECTRO MECHANICAL ARRANGEMENTS.pptx
VenkataLokeshMamidis
 
AUTOMATIC THREE PHASE SUPPLY CHANGOVER
AUTOMATIC THREE PHASE SUPPLY CHANGOVERAUTOMATIC THREE PHASE SUPPLY CHANGOVER
AUTOMATIC THREE PHASE SUPPLY CHANGOVER
shiv kapil
 
ups uninterruptable power supply
ups uninterruptable power supplyups uninterruptable power supply
ups uninterruptable power supply
MuhammadMuhaiman1
 
UPS (Uninterruptible Power Supply) on oil and gas industry. pdf
UPS (Uninterruptible Power Supply) on oil and gas industry. pdfUPS (Uninterruptible Power Supply) on oil and gas industry. pdf
UPS (Uninterruptible Power Supply) on oil and gas industry. pdf
lindkw
 
Solar ppt
Solar pptSolar ppt
DigSILENT PF - 03 load flow analysis
DigSILENT PF - 03 load flow analysisDigSILENT PF - 03 load flow analysis
DigSILENT PF - 03 load flow analysis
Himmelstern
 
DigSILENT PF - 03 load flow_analysis
DigSILENT PF - 03 load flow_analysisDigSILENT PF - 03 load flow_analysis
DigSILENT PF - 03 load flow_analysis
Himmelstern
 
Ac supply system
Ac supply systemAc supply system
Ac supply systemankitankesh
 
final presentation 25.ppt
final presentation 25.pptfinal presentation 25.ppt
final presentation 25.ppt
AwadhutMali2
 
Chapter 1 Introduction to power Electronic Devices.pdf
Chapter 1 Introduction to power Electronic Devices.pdfChapter 1 Introduction to power Electronic Devices.pdf
Chapter 1 Introduction to power Electronic Devices.pdf
LiewChiaPing
 
Power supply
Power supplyPower supply
Power supply
sibasis2012
 
Leveraging Open Source Power Measurement Standard Solution
Leveraging Open Source Power Measurement Standard SolutionLeveraging Open Source Power Measurement Standard Solution
Leveraging Open Source Power Measurement Standard Solution
BayLibre
 

Similar to Diagnosis of ups 6&8 (20)

Become a Battery Sizing Guru
Become a Battery Sizing GuruBecome a Battery Sizing Guru
Become a Battery Sizing Guru
 
upspresentation-112535108469-phpapp03.pdf
upspresentation-112535108469-phpapp03.pdfupspresentation-112535108469-phpapp03.pdf
upspresentation-112535108469-phpapp03.pdf
 
FSP UPS introduction 20150826
FSP UPS introduction 20150826FSP UPS introduction 20150826
FSP UPS introduction 20150826
 
Ac supply system
Ac supply systemAc supply system
Ac supply system
 
Introduction to PLC
Introduction to PLCIntroduction to PLC
Introduction to PLC
 
Rourkela Steel Pant Power System
Rourkela Steel Pant Power System Rourkela Steel Pant Power System
Rourkela Steel Pant Power System
 
Knowledge sharing on UPS System (Updated).pptx
Knowledge sharing on UPS System (Updated).pptxKnowledge sharing on UPS System (Updated).pptx
Knowledge sharing on UPS System (Updated).pptx
 
BEEE_seminor-1.pdf
BEEE_seminor-1.pdfBEEE_seminor-1.pdf
BEEE_seminor-1.pdf
 
BASIC ELECTRO MECHANICAL ARRANGEMENTS.pptx
BASIC ELECTRO MECHANICAL ARRANGEMENTS.pptxBASIC ELECTRO MECHANICAL ARRANGEMENTS.pptx
BASIC ELECTRO MECHANICAL ARRANGEMENTS.pptx
 
AUTOMATIC THREE PHASE SUPPLY CHANGOVER
AUTOMATIC THREE PHASE SUPPLY CHANGOVERAUTOMATIC THREE PHASE SUPPLY CHANGOVER
AUTOMATIC THREE PHASE SUPPLY CHANGOVER
 
ups uninterruptable power supply
ups uninterruptable power supplyups uninterruptable power supply
ups uninterruptable power supply
 
UPS (Uninterruptible Power Supply) on oil and gas industry. pdf
UPS (Uninterruptible Power Supply) on oil and gas industry. pdfUPS (Uninterruptible Power Supply) on oil and gas industry. pdf
UPS (Uninterruptible Power Supply) on oil and gas industry. pdf
 
Solar ppt
Solar pptSolar ppt
Solar ppt
 
DigSILENT PF - 03 load flow analysis
DigSILENT PF - 03 load flow analysisDigSILENT PF - 03 load flow analysis
DigSILENT PF - 03 load flow analysis
 
DigSILENT PF - 03 load flow_analysis
DigSILENT PF - 03 load flow_analysisDigSILENT PF - 03 load flow_analysis
DigSILENT PF - 03 load flow_analysis
 
Ac supply system
Ac supply systemAc supply system
Ac supply system
 
final presentation 25.ppt
final presentation 25.pptfinal presentation 25.ppt
final presentation 25.ppt
 
Chapter 1 Introduction to power Electronic Devices.pdf
Chapter 1 Introduction to power Electronic Devices.pdfChapter 1 Introduction to power Electronic Devices.pdf
Chapter 1 Introduction to power Electronic Devices.pdf
 
Power supply
Power supplyPower supply
Power supply
 
Leveraging Open Source Power Measurement Standard Solution
Leveraging Open Source Power Measurement Standard SolutionLeveraging Open Source Power Measurement Standard Solution
Leveraging Open Source Power Measurement Standard Solution
 

Recently uploaded

DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
BrazilAccount1
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 

Recently uploaded (20)

DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 

Diagnosis of ups 6&8

  • 2. CONTENT : • What is ups • What we want • Basic configuration • Load details • Circuit diagram • Current status • Problems occurred due to ups(complains we received due to ups) • Common causes • Data analysis • Changes we did • What we can do
  • 3. WHAT IS UPS ? • Uninterruptible power source is an electrical apparatus that provides emergency power to a load when the input power source, typically mains power, fails. • In our industry ups is used to give the auxiliary supply sinter machine ,soaking machine ,pt machine , row draw etc. • Whenever main supply is stop our ups system provides 6MVA of power to system(critical load ) for 15min .
  • 4. BASIC CONFIGURATION • Ups 8 (eaton powerwave 9315) -KVA 400 -KW 320 -No of modules =1 • Ups 6 (eaton powerwave 9395) -KVA 825 -KW 742.5 -No of modules=3
  • 5. LOAD DETAILS On ups 8 (72% of full load ) Sinter(6)-10’3,26,23,24,35 Pt(6)-33,25,32,1,26,27 Soaking-59/60/61 Sod dual #12 On ups 6 (65% of full load) Non critical load
  • 7. CURRENT STATUS • Ups 6  No critical load  totally shut down  Modules are removed  Batteries from ups 6 banks are removed  Panels are removed • Ups8  On bypass mode  Replaced IGBT’s  Batteries have high internal resistance
  • 8. PROBLEMS OCCURRED DUE TO UPS(COMPLAINS)
  • 9. DATA ANALYSIS • Ups 8(according to the scada 1 min data)  Fault date 30 jan 2016 time 1:15 to 1:18  Power loss in KVA 66234  Phase voltage 416 (constant through out the fault time)  Phase current 182(at fault time current drop )  Ups 6
  • 10. CHANGES WE DID • Ups 8 IGBT changed on 31 jan Modules changed Power supply board, monitor board • Ups 6 All working modules are removed and shifted to the workable ups
  • 11. WHAT WE CAN DO • As there r all the electronic circuit so for that hire a electronic circuit expert and check the monitoring board in the ups • if possible then buy the new IGBT set and replace it to the old one • Battery checking and replacement for reliability of ups operation • Replacement of ups directly(which cost more)