SlideShare a Scribd company logo
Dhariwal’s Thermal 
power plant 
A production of CESC Ltd.
 This power plant will be governed by “CESC” 
[calcutta Electric Supply company] ltd. located in 
Tadali, at chandrapur MIDC region. 
 The total estimated power generating capacity of this 
plant is 2*300MW. Presently CESC Ltd is the 
flagship company of RP-SANJIV GOENKA 
GROUP. 
 The project is almost on the verge of completion and 
the commissioning date of its one of the two units is 
somewhere around October 2012. 
Introduction
Electrical system 
Generation Transmission Distribution 
System System System 
Classification of electrical system
Generation process
Coal is unloaded by electric traction system at Coal Yard 
Coal is crushed to finer pieces of order 20 mm 
Pulverization of Coal 
Coal is sent to furnace with the help of FD fan 
Steam is generated at 540°C and 135 kg/sq.m 
Steam is sent to Super heater 
Superheated steam is sent to turbine 
Production of Electricity by the generator coupled with turbine 
Basic idea of Electric generation
 Coal Conveyer 
 Pulverizer 
 Boiler 
 Condenser 
 Cooling towers 
 Economizer 
 Air pre-heater 
 Electrostatic precipitator 
 Generator 
 Transformer. 
Elements of thermal power station
Transmission system
Transmission system 
Overhead 
Transmission 
Underground 
Transmission 
Classification of transmission 
systems
 Electric power can also be transmitted by 
underground power cables instead of overhead power 
lines. 
 This type of transmission is mainly done in 
congested areas where there is no space to set up 
overhead line’s set up. 
 Underground cables take up less right-of-way(ROW) 
than overhead lines, have lower visibility, and are 
less affected by bad weather. 
 This also ensures safety for the commutators on busy 
and congested streets. 
Underground transmission
 Cost of insulated cable and excavation are much 
higher than overhead construction. 
 Faults in buried transmission lines take longer to 
locate and repair. 
 Underground lines are strictly limited by their 
thermal capacity, which permits less overload or re-rating 
than overhead lines. 
 Long underground cables have significant 
capacitance, which may reduce their ability to 
provide useful power to loads. 
Limitations of underground 
systems
 Generally for high voltage transmission purpose OHT system 
is used. 
Conductors 
 The conductors are made up of ACSR material & is not 
insulated. 
 Conductor sizes range from 12 mm2 to750 mm2 with varying 
resistance and current carrying capacity. Use of thicker wires 
may lead to skin effect. 
 Because of this current limitation, multiple parallel 
cables(bundle conductors) are used when higher capacity is 
needed. Bundle conductors are also used at high voltages to 
reduce energy loss caused by corona discharge. 
Overhead transmission systems
Bulk power transmission level
 Efficiency, redundancy, network safety & economical factors must 
be taken care about, during bulk power transmission. 
 This level of transmission system includes transmission grids 
which uses components like power lines, cables, switches, circuit 
breakers & transformers. 
 Transmission efficiency is hugely improved by step-up xmer 
and proportionately reduce the current in the conductors, thus 
keeping the power transmitted nearly equal to the power input. 
 The reduced current flowing through the line reduces the losses in 
the conductors. 
 According to Joule’s Law energy losses are directly proportional to 
the square of the current. Thus, reducing the current by a factor of 2 
will lower the energy lost to conductor resistance by a factor of 4.
 Transmission efficiency plays an important role in 
transmission system. More the efficiency less will be the 
losses. 
 Losses are occurred in transmission mainly bcz of following 
three effects associated with conductors: 
 Resistive effect 
 Inductive effect 
 Capacitive effect 
Transmission line losses
 Transmitting electricity at high voltage reduces the fraction of 
energy lost to resistance. For a given amount of power, a 
higher voltage reduces the current and thus the resistive losses 
in the conductor. 
 In an A.C. circuit, the inductance and capacitance of the phase 
conductors can be significant. 
 The currents that flow in these components of the circuit 
impedance constitute reactive power, which transmits no 
energy to the load. Reactive current causes extra losses in the 
transmission circuit. The ratio of real power to apparent power 
is the power factor. 
 As reactive current increases, the reactive power increases 
and the power factor decreases thereby increase the losses.
 For systems with low power factors, losses are higher than for 
systems with high power factors. 
 Utilities such as capacitor banks and other components such 
as 
1. phase-shifting transformers; 
2. static VAR compensators; 
3. physical transposition of the phase conductors; 
4. flexible AC transmission systems, FACTS 
throughout the system to control reactive power flow for 
reduction of losses and stabilization of system voltage. 
 As the transmission level goes down losses become less than 
what we’ve observed in higher levels.
Sub transmission level
 Sub transmission is part of an electric power transmission 
system that runs at relatively lower voltages. 
 High voltages is stepped down and sent to smaller substations 
in towns and neighborhoods. 
 Sub transmission circuits are usually arranged in loops so that 
a single line failure does not cut off service to a large number 
of customers for more than a short time. 
 While sub transmission circuits are usually carried on 
overhead lines, in urban areas buried cables(Under ground 
cable network) may be used. 
 At the end a step down transformer is used to serve low 
voltage of the ratings 230 volts for residential areas.
Grid Failure on July 31,2012.
States affected by grid failure
Corridor where the fault occurred.
 When the whole northern and north-eastern region 
was facing severe power cut India’s oldest private 
sector operator the 113 year old CESC decoupled 
from the faltering Grids in time isolating itself from 
the chaotic breakdown. 
 Supply from CESC plants operating at full steam was 
back within minutes providing power to both the 
Calcutta Metro and thousands of its consumers when 
most of the nation faced a blackout. 
A point to be noted.
 What CESC achieved was not rocket science. 
 Load sensors at its synchronizing point at Howrah 
detected the demand supply imbalance in the 
connecting WBSEB grid. 
 The Sanjiv Goenka led management was alert 
enough to isolate itself before being sucked into the 
demand surge from the northern grid that caused a 
total collapse. 
How does it happen?
Now the Questions arises that: 
 Why sensors and protective relays of the Power Grid at 
Agra, Lucknow or any other high demand synchronizing 
point in the Northern Grid did not isolate the demand 
centers from the grid on Monday night ? 
 Were the load sensors not operating? 
 Were the protective relays bypassed? 
 Were the Under Frequency Relays out of service? 
 Was the operating staff not empowered to switch off the 
overdrawing units? 
 Or whether the overload detection mechanism did not 
function? 
WHY??????
Thank you  
A presentation by Sandeep A. Jamdar

More Related Content

What's hot

Power System Frequency
Power System Frequency Power System Frequency
Power System Frequency
Power System Operation
 
Basics of AC transmission
Basics of AC transmissionBasics of AC transmission
Basics of AC transmission
SonuKumarBairwa
 
Electricity distribution system in india
Electricity distribution system in indiaElectricity distribution system in india
Electricity distribution system in india
Jasgt Singh
 
Application of power electronics in hvdc
Application of power electronics in hvdcApplication of power electronics in hvdc
Application of power electronics in hvdc
Sunny Purani
 
AC Supply system, Comparison Between AC-DC System, Advantage HV transmission
AC Supply system, Comparison Between AC-DC System, Advantage HV transmissionAC Supply system, Comparison Between AC-DC System, Advantage HV transmission
AC Supply system, Comparison Between AC-DC System, Advantage HV transmission
Smit Shah
 
Electric power system
Electric power systemElectric power system
Electric power system
Khurram Burjees
 
Supply system (Electrical Power System)
Supply system (Electrical Power System)Supply system (Electrical Power System)
Supply system (Electrical Power System)
Abhishek Choksi
 
800kv multiterminal system in india
800kv multiterminal system in india800kv multiterminal system in india
800kv multiterminal system in indiaalpna1808
 
Electricity distribution
Electricity distributionElectricity distribution
Electricity distributionghumman88
 
High Voltage Direct Current(Hvdc) transmission
High Voltage Direct Current(Hvdc) transmissionHigh Voltage Direct Current(Hvdc) transmission
High Voltage Direct Current(Hvdc) transmission
University of Gujrat, Pakistan
 
Basic power distribution system007
Basic power distribution system007Basic power distribution system007
Basic power distribution system007
Vaishnavee Patel
 
Typical a.c. supply system
Typical a.c. supply systemTypical a.c. supply system
Typical a.c. supply system
Nisarg Amin
 
Application of power electronics in hvdc copy
Application of power electronics in hvdc   copyApplication of power electronics in hvdc   copy
Application of power electronics in hvdc copySARAVANAN A
 
O&m of hvdc station power grid india
O&m of hvdc station power grid indiaO&m of hvdc station power grid india
O&m of hvdc station power grid india
Vaibhav Jain
 
Electrical Power system structure
Electrical Power system structureElectrical Power system structure
Electrical Power system structure
Jyoti Bhonsale
 
Supply systems
Supply systemsSupply systems
Supply systems
Md. Rimon Mia
 
POWER LOSS REDUCTION IN ELECTRICAL DISTRIBUTION SYSTEMS USING CAPACITOR PLACE...
POWER LOSS REDUCTION IN ELECTRICAL DISTRIBUTION SYSTEMS USING CAPACITOR PLACE...POWER LOSS REDUCTION IN ELECTRICAL DISTRIBUTION SYSTEMS USING CAPACITOR PLACE...
POWER LOSS REDUCTION IN ELECTRICAL DISTRIBUTION SYSTEMS USING CAPACITOR PLACE...
International Journal of Technical Research & Application
 
HVDC & FACTS
HVDC & FACTSHVDC & FACTS
HVDC & FACTS
Brunda R
 
L2 introduction to power system
L2   introduction to  power systemL2   introduction to  power system
L2 introduction to power systemSatyakam
 

What's hot (20)

Power System Frequency
Power System Frequency Power System Frequency
Power System Frequency
 
Basics of AC transmission
Basics of AC transmissionBasics of AC transmission
Basics of AC transmission
 
Electricity distribution system in india
Electricity distribution system in indiaElectricity distribution system in india
Electricity distribution system in india
 
Application of power electronics in hvdc
Application of power electronics in hvdcApplication of power electronics in hvdc
Application of power electronics in hvdc
 
AC Supply system, Comparison Between AC-DC System, Advantage HV transmission
AC Supply system, Comparison Between AC-DC System, Advantage HV transmissionAC Supply system, Comparison Between AC-DC System, Advantage HV transmission
AC Supply system, Comparison Between AC-DC System, Advantage HV transmission
 
Electric power system
Electric power systemElectric power system
Electric power system
 
Supply system (Electrical Power System)
Supply system (Electrical Power System)Supply system (Electrical Power System)
Supply system (Electrical Power System)
 
800kv multiterminal system in india
800kv multiterminal system in india800kv multiterminal system in india
800kv multiterminal system in india
 
Electricity distribution
Electricity distributionElectricity distribution
Electricity distribution
 
High Voltage Direct Current(Hvdc) transmission
High Voltage Direct Current(Hvdc) transmissionHigh Voltage Direct Current(Hvdc) transmission
High Voltage Direct Current(Hvdc) transmission
 
Basic power distribution system007
Basic power distribution system007Basic power distribution system007
Basic power distribution system007
 
Typical a.c. supply system
Typical a.c. supply systemTypical a.c. supply system
Typical a.c. supply system
 
Application of power electronics in hvdc copy
Application of power electronics in hvdc   copyApplication of power electronics in hvdc   copy
Application of power electronics in hvdc copy
 
O&m of hvdc station power grid india
O&m of hvdc station power grid indiaO&m of hvdc station power grid india
O&m of hvdc station power grid india
 
Electrical Power system structure
Electrical Power system structureElectrical Power system structure
Electrical Power system structure
 
Supply systems
Supply systemsSupply systems
Supply systems
 
POWER LOSS REDUCTION IN ELECTRICAL DISTRIBUTION SYSTEMS USING CAPACITOR PLACE...
POWER LOSS REDUCTION IN ELECTRICAL DISTRIBUTION SYSTEMS USING CAPACITOR PLACE...POWER LOSS REDUCTION IN ELECTRICAL DISTRIBUTION SYSTEMS USING CAPACITOR PLACE...
POWER LOSS REDUCTION IN ELECTRICAL DISTRIBUTION SYSTEMS USING CAPACITOR PLACE...
 
HVDC & FACTS
HVDC & FACTSHVDC & FACTS
HVDC & FACTS
 
L2 introduction to power system
L2   introduction to  power systemL2   introduction to  power system
L2 introduction to power system
 
MUSTAFA MASS HVDC PPT
MUSTAFA MASS HVDC PPTMUSTAFA MASS HVDC PPT
MUSTAFA MASS HVDC PPT
 

Similar to Thermal power plant working

HVDC & FACTS
HVDC & FACTSHVDC & FACTS
HVDC & FACTS
Pritesh Priyadarshi
 
Edited hvdc2222upload
Edited hvdc2222uploadEdited hvdc2222upload
Edited hvdc2222upload
Mayuresh Vichare
 
POWER SYSTEMS – II chapter 1 transmission line modelling.pptx
POWER SYSTEMS – II chapter 1 transmission line modelling.pptxPOWER SYSTEMS – II chapter 1 transmission line modelling.pptx
POWER SYSTEMS – II chapter 1 transmission line modelling.pptx
MaipaliJyoshnaDevi
 
315564438 hvdc-transmission-ppt
315564438 hvdc-transmission-ppt315564438 hvdc-transmission-ppt
315564438 hvdc-transmission-ppt
Laveen Raghunam
 
Hvdc notes
Hvdc notesHvdc notes
Hvdc notes
mahesh babu
 
Hvdc system.pptx
Hvdc system.pptxHvdc system.pptx
Hvdc system.pptx
Ashfaque Yoosuf
 
Minimization of Overall Losses of a Distribution System under Contingency Con...
Minimization of Overall Losses of a Distribution System under Contingency Con...Minimization of Overall Losses of a Distribution System under Contingency Con...
Minimization of Overall Losses of a Distribution System under Contingency Con...
paperpublications3
 
Minimization of Overall Losses of a Distribution System under Contingency Con...
Minimization of Overall Losses of a Distribution System under Contingency Con...Minimization of Overall Losses of a Distribution System under Contingency Con...
Minimization of Overall Losses of a Distribution System under Contingency Con...
paperpublications3
 
Chapter 2 transmission line parameters
Chapter 2  transmission line parametersChapter 2  transmission line parameters
Chapter 2 transmission line parameters
firaoltemesgen1
 
1 elecrical systems
1 elecrical systems1 elecrical systems
1 elecrical systems
Salil Mukundan
 
ch_introduction to power1 part 1_ppt[1].pdf
ch_introduction to power1 part 1_ppt[1].pdfch_introduction to power1 part 1_ppt[1].pdf
ch_introduction to power1 part 1_ppt[1].pdf
abelchernet1627
 
Overview of power purchase
Overview of power purchaseOverview of power purchase
Overview of power purchase
C.A. Neeraj Singh
 
seminar on_HVDC.pdf ppt
 seminar on_HVDC.pdf ppt seminar on_HVDC.pdf ppt
seminar on_HVDC.pdf ppt
AKHILESHYADAV311436
 
Simulation of different power transmission systems and their capacity of redu...
Simulation of different power transmission systems and their capacity of redu...Simulation of different power transmission systems and their capacity of redu...
Simulation of different power transmission systems and their capacity of redu...
eSAT Publishing House
 
Pdu 2021 s2
Pdu 2021 s2Pdu 2021 s2
Pdu 2021 s2
tahainam2
 
Lec 6.pptx hjshkjadfhiuhiusdghsiudgfsdkuskus
Lec 6.pptx hjshkjadfhiuhiusdghsiudgfsdkuskusLec 6.pptx hjshkjadfhiuhiusdghsiudgfsdkuskus
Lec 6.pptx hjshkjadfhiuhiusdghsiudgfsdkuskus
poetanonymous11
 
Comparative evaluation of hvdc
Comparative evaluation of hvdcComparative evaluation of hvdc
Comparative evaluation of hvdc
shivamverma394
 
High Voltage Direct Current Transmission System Report
High Voltage Direct Current Transmission System ReportHigh Voltage Direct Current Transmission System Report
High Voltage Direct Current Transmission System Report
Nadeem Khilji
 
introduction on high voltage engineering
introduction on high voltage engineeringintroduction on high voltage engineering
introduction on high voltage engineering
jesusgarland
 

Similar to Thermal power plant working (20)

HVDC & FACTS
HVDC & FACTSHVDC & FACTS
HVDC & FACTS
 
Edited hvdc2222upload
Edited hvdc2222uploadEdited hvdc2222upload
Edited hvdc2222upload
 
POWER SYSTEMS – II chapter 1 transmission line modelling.pptx
POWER SYSTEMS – II chapter 1 transmission line modelling.pptxPOWER SYSTEMS – II chapter 1 transmission line modelling.pptx
POWER SYSTEMS – II chapter 1 transmission line modelling.pptx
 
Advances in power systems
Advances in power systemsAdvances in power systems
Advances in power systems
 
315564438 hvdc-transmission-ppt
315564438 hvdc-transmission-ppt315564438 hvdc-transmission-ppt
315564438 hvdc-transmission-ppt
 
Hvdc notes
Hvdc notesHvdc notes
Hvdc notes
 
Hvdc system.pptx
Hvdc system.pptxHvdc system.pptx
Hvdc system.pptx
 
Minimization of Overall Losses of a Distribution System under Contingency Con...
Minimization of Overall Losses of a Distribution System under Contingency Con...Minimization of Overall Losses of a Distribution System under Contingency Con...
Minimization of Overall Losses of a Distribution System under Contingency Con...
 
Minimization of Overall Losses of a Distribution System under Contingency Con...
Minimization of Overall Losses of a Distribution System under Contingency Con...Minimization of Overall Losses of a Distribution System under Contingency Con...
Minimization of Overall Losses of a Distribution System under Contingency Con...
 
Chapter 2 transmission line parameters
Chapter 2  transmission line parametersChapter 2  transmission line parameters
Chapter 2 transmission line parameters
 
1 elecrical systems
1 elecrical systems1 elecrical systems
1 elecrical systems
 
ch_introduction to power1 part 1_ppt[1].pdf
ch_introduction to power1 part 1_ppt[1].pdfch_introduction to power1 part 1_ppt[1].pdf
ch_introduction to power1 part 1_ppt[1].pdf
 
Overview of power purchase
Overview of power purchaseOverview of power purchase
Overview of power purchase
 
seminar on_HVDC.pdf ppt
 seminar on_HVDC.pdf ppt seminar on_HVDC.pdf ppt
seminar on_HVDC.pdf ppt
 
Simulation of different power transmission systems and their capacity of redu...
Simulation of different power transmission systems and their capacity of redu...Simulation of different power transmission systems and their capacity of redu...
Simulation of different power transmission systems and their capacity of redu...
 
Pdu 2021 s2
Pdu 2021 s2Pdu 2021 s2
Pdu 2021 s2
 
Lec 6.pptx hjshkjadfhiuhiusdghsiudgfsdkuskus
Lec 6.pptx hjshkjadfhiuhiusdghsiudgfsdkuskusLec 6.pptx hjshkjadfhiuhiusdghsiudgfsdkuskus
Lec 6.pptx hjshkjadfhiuhiusdghsiudgfsdkuskus
 
Comparative evaluation of hvdc
Comparative evaluation of hvdcComparative evaluation of hvdc
Comparative evaluation of hvdc
 
High Voltage Direct Current Transmission System Report
High Voltage Direct Current Transmission System ReportHigh Voltage Direct Current Transmission System Report
High Voltage Direct Current Transmission System Report
 
introduction on high voltage engineering
introduction on high voltage engineeringintroduction on high voltage engineering
introduction on high voltage engineering
 

Recently uploaded

Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
BrazilAccount1
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 

Recently uploaded (20)

Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 

Thermal power plant working

  • 1. Dhariwal’s Thermal power plant A production of CESC Ltd.
  • 2.  This power plant will be governed by “CESC” [calcutta Electric Supply company] ltd. located in Tadali, at chandrapur MIDC region.  The total estimated power generating capacity of this plant is 2*300MW. Presently CESC Ltd is the flagship company of RP-SANJIV GOENKA GROUP.  The project is almost on the verge of completion and the commissioning date of its one of the two units is somewhere around October 2012. Introduction
  • 3. Electrical system Generation Transmission Distribution System System System Classification of electrical system
  • 5. Coal is unloaded by electric traction system at Coal Yard Coal is crushed to finer pieces of order 20 mm Pulverization of Coal Coal is sent to furnace with the help of FD fan Steam is generated at 540°C and 135 kg/sq.m Steam is sent to Super heater Superheated steam is sent to turbine Production of Electricity by the generator coupled with turbine Basic idea of Electric generation
  • 6.  Coal Conveyer  Pulverizer  Boiler  Condenser  Cooling towers  Economizer  Air pre-heater  Electrostatic precipitator  Generator  Transformer. Elements of thermal power station
  • 8. Transmission system Overhead Transmission Underground Transmission Classification of transmission systems
  • 9.  Electric power can also be transmitted by underground power cables instead of overhead power lines.  This type of transmission is mainly done in congested areas where there is no space to set up overhead line’s set up.  Underground cables take up less right-of-way(ROW) than overhead lines, have lower visibility, and are less affected by bad weather.  This also ensures safety for the commutators on busy and congested streets. Underground transmission
  • 10.  Cost of insulated cable and excavation are much higher than overhead construction.  Faults in buried transmission lines take longer to locate and repair.  Underground lines are strictly limited by their thermal capacity, which permits less overload or re-rating than overhead lines.  Long underground cables have significant capacitance, which may reduce their ability to provide useful power to loads. Limitations of underground systems
  • 11.  Generally for high voltage transmission purpose OHT system is used. Conductors  The conductors are made up of ACSR material & is not insulated.  Conductor sizes range from 12 mm2 to750 mm2 with varying resistance and current carrying capacity. Use of thicker wires may lead to skin effect.  Because of this current limitation, multiple parallel cables(bundle conductors) are used when higher capacity is needed. Bundle conductors are also used at high voltages to reduce energy loss caused by corona discharge. Overhead transmission systems
  • 13.  Efficiency, redundancy, network safety & economical factors must be taken care about, during bulk power transmission.  This level of transmission system includes transmission grids which uses components like power lines, cables, switches, circuit breakers & transformers.  Transmission efficiency is hugely improved by step-up xmer and proportionately reduce the current in the conductors, thus keeping the power transmitted nearly equal to the power input.  The reduced current flowing through the line reduces the losses in the conductors.  According to Joule’s Law energy losses are directly proportional to the square of the current. Thus, reducing the current by a factor of 2 will lower the energy lost to conductor resistance by a factor of 4.
  • 14.  Transmission efficiency plays an important role in transmission system. More the efficiency less will be the losses.  Losses are occurred in transmission mainly bcz of following three effects associated with conductors:  Resistive effect  Inductive effect  Capacitive effect Transmission line losses
  • 15.  Transmitting electricity at high voltage reduces the fraction of energy lost to resistance. For a given amount of power, a higher voltage reduces the current and thus the resistive losses in the conductor.  In an A.C. circuit, the inductance and capacitance of the phase conductors can be significant.  The currents that flow in these components of the circuit impedance constitute reactive power, which transmits no energy to the load. Reactive current causes extra losses in the transmission circuit. The ratio of real power to apparent power is the power factor.  As reactive current increases, the reactive power increases and the power factor decreases thereby increase the losses.
  • 16.  For systems with low power factors, losses are higher than for systems with high power factors.  Utilities such as capacitor banks and other components such as 1. phase-shifting transformers; 2. static VAR compensators; 3. physical transposition of the phase conductors; 4. flexible AC transmission systems, FACTS throughout the system to control reactive power flow for reduction of losses and stabilization of system voltage.  As the transmission level goes down losses become less than what we’ve observed in higher levels.
  • 18.  Sub transmission is part of an electric power transmission system that runs at relatively lower voltages.  High voltages is stepped down and sent to smaller substations in towns and neighborhoods.  Sub transmission circuits are usually arranged in loops so that a single line failure does not cut off service to a large number of customers for more than a short time.  While sub transmission circuits are usually carried on overhead lines, in urban areas buried cables(Under ground cable network) may be used.  At the end a step down transformer is used to serve low voltage of the ratings 230 volts for residential areas.
  • 19. Grid Failure on July 31,2012.
  • 20. States affected by grid failure
  • 21. Corridor where the fault occurred.
  • 22.  When the whole northern and north-eastern region was facing severe power cut India’s oldest private sector operator the 113 year old CESC decoupled from the faltering Grids in time isolating itself from the chaotic breakdown.  Supply from CESC plants operating at full steam was back within minutes providing power to both the Calcutta Metro and thousands of its consumers when most of the nation faced a blackout. A point to be noted.
  • 23.  What CESC achieved was not rocket science.  Load sensors at its synchronizing point at Howrah detected the demand supply imbalance in the connecting WBSEB grid.  The Sanjiv Goenka led management was alert enough to isolate itself before being sucked into the demand surge from the northern grid that caused a total collapse. How does it happen?
  • 24. Now the Questions arises that:  Why sensors and protective relays of the Power Grid at Agra, Lucknow or any other high demand synchronizing point in the Northern Grid did not isolate the demand centers from the grid on Monday night ?  Were the load sensors not operating?  Were the protective relays bypassed?  Were the Under Frequency Relays out of service?  Was the operating staff not empowered to switch off the overdrawing units?  Or whether the overload detection mechanism did not function? WHY??????
  • 25. Thank you  A presentation by Sandeep A. Jamdar