Here is a deck used to demonstrate the five phases of a residential development project (somewhat applicable to commercial and mixed-use as well). The purpose is to demonstrate the various points at which an engineer or surveyor can become engaged in a project and the top referral partner candidates at each phase.
El Paso City Council Agenda Item 8.2: Zoningepdevelopment
An Ordinance changing the zoning of a portion of Lots 1, 2, 3, 4, 5, 24, 25, 26, a portion of Tract 1 and a portion of a 20 feet alley (vacated), Block 89A, Logan Heights Addition, 5312 Alabama Street, City of El Paso, El Paso County, Texas from R-4 (Residential) and A-2 (Apartment) to C-1 (Commercial), and imposing a condition. The penalty is as provided for in Chapter 20.24 of the El Paso City Code. Subject Property: 5312 Alabama Street. Property Owner: Border Loop Dialysis, LLC. PZRZ14-00014
District 2
El Paso City Council Agenda Item 8.2: Zoningepdevelopment
An Ordinance changing the zoning of a portion of Lots 1, 2, 3, 4, 5, 24, 25, 26, a portion of Tract 1 and a portion of a 20 feet alley (vacated), Block 89A, Logan Heights Addition, 5312 Alabama Street, City of El Paso, El Paso County, Texas from R-4 (Residential) and A-2 (Apartment) to C-1 (Commercial), and imposing a condition. The penalty is as provided for in Chapter 20.24 of the El Paso City Code. Subject Property: 5312 Alabama Street. Property Owner: Border Loop Dialysis, LLC. PZRZ14-00014
District 2
This is a shot presentation of RIBA plan of work based of the pdf provided in the website.
Reference: https://www.architecture.com/knowledge-and-resources/resources-landing-page/riba-plan-of-work
Orange County's fifth developer's forum was held on June 17th, 2016, and the focus was on the Orange Code initiative to update to the land development code.
Orange Code, a vision for the future of Orange County’s places, creates streamlined processes through an easy-to-use format. It ensures sustainable land development that preserves the character of existing communities, celebrates Orange County's diversity and creates vibrant places to live, work and relax. Every city and county has a land development code that describes where and how new buildings and communities may be built. While there have been many updates since Orange County’s Code was written in 1957, now is the time to look at the big picture. Orange Code will refresh and rethink the County’s place-making law to get it ready for the 21st Century.
This is a start to the scope baseline but you seem to have forgott.docxkenth16
This is a start to the scope baseline but you seem to have forgotten who your audience is. The scope statement should be tailored to the people who will use and be affected by this project. I would think that the people living in that community would benefit the most from know what is going to be delivered and what they should expect of this project. Your scope statement is a listing of the project management and project team activities. That isn't correct. The audience for the WBS and dictionary is the project team. It should explain to them what the results of their work should look like or how it should behave. The dictionary descriptions are specific to THIS project and should be enough for the team member to know how to meet expectations. Your dictionary is missing all that. So look through my specific comments in the attached file. They should guide you in the right direction to help you finalize this assignment. Let me know if you have any questions.
Scope baseline
1. Scope Statement.
The scope for this small project consists of two stages:
• Stage 1. Design and project management required to support the new lift station.
Considerations include: Code and standards, Product requirements, utility requirements.
• Procurement, design, construction and start up of the upgraded station.
• Stage 2. Replacement and upgrade of the actual lift station to be executed by employees of
Pandora Moon Town. A team of experts improving stations and familiar with the current
operation of stations at Pandora Moon town.
• Replacement of key equipment, rehabilitation, repair and maintenance of the station. Also,
increasing the capacity of the station
2. Product scope description.
The scope description for this work cover the upgrade of one residential lift station. Also,
proposes the installation of new mechanical equipment such pumps stations, installation and
construction of new assets. Defined stages for this project plus other information will be contained in
the scope baseline.
The improvement of the station includes above ground and below ground modifications. The
above ground are the upgrades of the lift station surrounding and perimeter such flood protection,
new fencing, lighting, landscaping, new electrical wiring and storm water management.
The below ground improvements consist of replacement of existing pumps, upgraded
monitoring system and new odor control system.
The project includes the following:
• Stage 1. Project management.
• Monthly project updates with sponsor to discuss project budget, update schedule,
improvement specified in the design plan and project issues.
• Meet with project team staff to discuss standards, expectations and project approach.
• Gather information from planning department to review existing station and confirm
recommendations for the proposed updated station to identify advantages and
Commented [BZ1]: You are confusing your terms. The
Scope Stateme.
Manual Project in Public Sector including the stages of initiation, preparation of PC-I,PC-2, Public Private Partnerships, Different modes of Public Private Partnerships, Appraisal including the Risk Assessment, Monitoring and Control and Closure stage of the project.
Regulatory Requisites & Development Cost Analysis in Bangalorepiasi sinha
Regulatory requisites & development cost analysis are the two key components in the development cycle of a real estate project.This presentation covers these components and gives an insight to help key stakeholders throughout the project life cycle.
Presentation slides provided by Robert Holloway from Stantec on 10 May 2022 at the North West Branch Conference in Manchester on the Warrington Western Link project.
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfKamal Acharya
The College Bus Management system is completely developed by Visual Basic .NET Version. The application is connect with most secured database language MS SQL Server. The application is develop by using best combination of front-end and back-end languages. The application is totally design like flat user interface. This flat user interface is more attractive user interface in 2017. The application is gives more important to the system functionality. The application is to manage the student’s details, driver’s details, bus details, bus route details, bus fees details and more. The application has only one unit for admin. The admin can manage the entire application. The admin can login into the application by using username and password of the admin. The application is develop for big and small colleges. It is more user friendly for non-computer person. Even they can easily learn how to manage the application within hours. The application is more secure by the admin. The system will give an effective output for the VB.Net and SQL Server given as input to the system. The compiled java program given as input to the system, after scanning the program will generate different reports. The application generates the report for users. The admin can view and download the report of the data. The application deliver the excel format reports. Because, excel formatted reports is very easy to understand the income and expense of the college bus. This application is mainly develop for windows operating system users. In 2017, 73% of people enterprises are using windows operating system. So the application will easily install for all the windows operating system users. The application-developed size is very low. The application consumes very low space in disk. Therefore, the user can allocate very minimum local disk space for this application.
Welcome to WIPAC Monthly the magazine brought to you by the LinkedIn Group Water Industry Process Automation & Control.
In this month's edition, along with this month's industry news to celebrate the 13 years since the group was created we have articles including
A case study of the used of Advanced Process Control at the Wastewater Treatment works at Lleida in Spain
A look back on an article on smart wastewater networks in order to see how the industry has measured up in the interim around the adoption of Digital Transformation in the Water Industry.
More Related Content
Similar to Development Process - Civil Engineer & Land Surveyor Points of Entry
This is a shot presentation of RIBA plan of work based of the pdf provided in the website.
Reference: https://www.architecture.com/knowledge-and-resources/resources-landing-page/riba-plan-of-work
Orange County's fifth developer's forum was held on June 17th, 2016, and the focus was on the Orange Code initiative to update to the land development code.
Orange Code, a vision for the future of Orange County’s places, creates streamlined processes through an easy-to-use format. It ensures sustainable land development that preserves the character of existing communities, celebrates Orange County's diversity and creates vibrant places to live, work and relax. Every city and county has a land development code that describes where and how new buildings and communities may be built. While there have been many updates since Orange County’s Code was written in 1957, now is the time to look at the big picture. Orange Code will refresh and rethink the County’s place-making law to get it ready for the 21st Century.
This is a start to the scope baseline but you seem to have forgott.docxkenth16
This is a start to the scope baseline but you seem to have forgotten who your audience is. The scope statement should be tailored to the people who will use and be affected by this project. I would think that the people living in that community would benefit the most from know what is going to be delivered and what they should expect of this project. Your scope statement is a listing of the project management and project team activities. That isn't correct. The audience for the WBS and dictionary is the project team. It should explain to them what the results of their work should look like or how it should behave. The dictionary descriptions are specific to THIS project and should be enough for the team member to know how to meet expectations. Your dictionary is missing all that. So look through my specific comments in the attached file. They should guide you in the right direction to help you finalize this assignment. Let me know if you have any questions.
Scope baseline
1. Scope Statement.
The scope for this small project consists of two stages:
• Stage 1. Design and project management required to support the new lift station.
Considerations include: Code and standards, Product requirements, utility requirements.
• Procurement, design, construction and start up of the upgraded station.
• Stage 2. Replacement and upgrade of the actual lift station to be executed by employees of
Pandora Moon Town. A team of experts improving stations and familiar with the current
operation of stations at Pandora Moon town.
• Replacement of key equipment, rehabilitation, repair and maintenance of the station. Also,
increasing the capacity of the station
2. Product scope description.
The scope description for this work cover the upgrade of one residential lift station. Also,
proposes the installation of new mechanical equipment such pumps stations, installation and
construction of new assets. Defined stages for this project plus other information will be contained in
the scope baseline.
The improvement of the station includes above ground and below ground modifications. The
above ground are the upgrades of the lift station surrounding and perimeter such flood protection,
new fencing, lighting, landscaping, new electrical wiring and storm water management.
The below ground improvements consist of replacement of existing pumps, upgraded
monitoring system and new odor control system.
The project includes the following:
• Stage 1. Project management.
• Monthly project updates with sponsor to discuss project budget, update schedule,
improvement specified in the design plan and project issues.
• Meet with project team staff to discuss standards, expectations and project approach.
• Gather information from planning department to review existing station and confirm
recommendations for the proposed updated station to identify advantages and
Commented [BZ1]: You are confusing your terms. The
Scope Stateme.
Manual Project in Public Sector including the stages of initiation, preparation of PC-I,PC-2, Public Private Partnerships, Different modes of Public Private Partnerships, Appraisal including the Risk Assessment, Monitoring and Control and Closure stage of the project.
Regulatory Requisites & Development Cost Analysis in Bangalorepiasi sinha
Regulatory requisites & development cost analysis are the two key components in the development cycle of a real estate project.This presentation covers these components and gives an insight to help key stakeholders throughout the project life cycle.
Presentation slides provided by Robert Holloway from Stantec on 10 May 2022 at the North West Branch Conference in Manchester on the Warrington Western Link project.
Similar to Development Process - Civil Engineer & Land Surveyor Points of Entry (20)
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfKamal Acharya
The College Bus Management system is completely developed by Visual Basic .NET Version. The application is connect with most secured database language MS SQL Server. The application is develop by using best combination of front-end and back-end languages. The application is totally design like flat user interface. This flat user interface is more attractive user interface in 2017. The application is gives more important to the system functionality. The application is to manage the student’s details, driver’s details, bus details, bus route details, bus fees details and more. The application has only one unit for admin. The admin can manage the entire application. The admin can login into the application by using username and password of the admin. The application is develop for big and small colleges. It is more user friendly for non-computer person. Even they can easily learn how to manage the application within hours. The application is more secure by the admin. The system will give an effective output for the VB.Net and SQL Server given as input to the system. The compiled java program given as input to the system, after scanning the program will generate different reports. The application generates the report for users. The admin can view and download the report of the data. The application deliver the excel format reports. Because, excel formatted reports is very easy to understand the income and expense of the college bus. This application is mainly develop for windows operating system users. In 2017, 73% of people enterprises are using windows operating system. So the application will easily install for all the windows operating system users. The application-developed size is very low. The application consumes very low space in disk. Therefore, the user can allocate very minimum local disk space for this application.
Welcome to WIPAC Monthly the magazine brought to you by the LinkedIn Group Water Industry Process Automation & Control.
In this month's edition, along with this month's industry news to celebrate the 13 years since the group was created we have articles including
A case study of the used of Advanced Process Control at the Wastewater Treatment works at Lleida in Spain
A look back on an article on smart wastewater networks in order to see how the industry has measured up in the interim around the adoption of Digital Transformation in the Water Industry.
Overview of the fundamental roles in Hydropower generation and the components involved in wider Electrical Engineering.
This paper presents the design and construction of hydroelectric dams from the hydrologist’s survey of the valley before construction, all aspects and involved disciplines, fluid dynamics, structural engineering, generation and mains frequency regulation to the very transmission of power through the network in the United Kingdom.
Author: Robbie Edward Sayers
Collaborators and co editors: Charlie Sims and Connor Healey.
(C) 2024 Robbie E. Sayers
Cosmetic shop management system project report.pdfKamal Acharya
Buying new cosmetic products is difficult. It can even be scary for those who have sensitive skin and are prone to skin trouble. The information needed to alleviate this problem is on the back of each product, but it's thought to interpret those ingredient lists unless you have a background in chemistry.
Instead of buying and hoping for the best, we can use data science to help us predict which products may be good fits for us. It includes various function programs to do the above mentioned tasks.
Data file handling has been effectively used in the program.
The automated cosmetic shop management system should deal with the automation of general workflow and administration process of the shop. The main processes of the system focus on customer's request where the system is able to search the most appropriate products and deliver it to the customers. It should help the employees to quickly identify the list of cosmetic product that have reached the minimum quantity and also keep a track of expired date for each cosmetic product. It should help the employees to find the rack number in which the product is placed.It is also Faster and more efficient way.
Saudi Arabia stands as a titan in the global energy landscape, renowned for its abundant oil and gas resources. It's the largest exporter of petroleum and holds some of the world's most significant reserves. Let's delve into the top 10 oil and gas projects shaping Saudi Arabia's energy future in 2024.
Vaccine management system project report documentation..pdfKamal Acharya
The Division of Vaccine and Immunization is facing increasing difficulty monitoring vaccines and other commodities distribution once they have been distributed from the national stores. With the introduction of new vaccines, more challenges have been anticipated with this additions posing serious threat to the already over strained vaccine supply chain system in Kenya.
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSEDuvanRamosGarzon1
AIRCRAFT GENERAL
The Single Aisle is the most advanced family aircraft in service today, with fly-by-wire flight controls.
The A318, A319, A320 and A321 are twin-engine subsonic medium range aircraft.
The family offers a choice of engines
2. THE GENERALPROCESS
THESE ARE THE 5 BASIC PHASES IN THE LIFELINE OF A PROJECT
CONCEPT
PLANNING /
ENTITLEMENT
DESIGN /
PERMIT
CONSTRUCTION CLOSEOUT
GTA SERVICES CAN ENTER BEFORE ANY OF THESE PHASES!
3. CONCEPTUALPHASE
GTA SERVICES IN THE CONCEPTUAL PHASE INCLUDE:
• FREE CONSULTATION
• ZONING REVIEW
• BACK OF ENVELOPE SITE PLANS
• TOPOGRAPHIC SURVEY
• BOUNDARY SURVEY
• TITLE REPORT REVIEW
• DEVELOPMENT FEASIBILITY REVIEW
• CONSTRAINTS MAPPING
CONCEPT
PLANNING /
ENTITLEMENT
DESIGN /
PERMIT
CONSTRUCTION CLOSEOUT
REFERRAL
PARTNERS IN THIS
PHASE:
• Homeowner
considering ADU or a
lot split
• Real Estate
professional looking to
improve a listing
• Real Estate BUYER
wanting to check
feasibility on a
property.
5. PLANNING&ENTITLEMENTPHASE
GTA SERVICES IN THE ENTITLEMENT PHASE INCLUDE:
• FREE CONSULTATION
• TOPOGRAPHIC SURVEY / BOUNDARY SURVEY
• MAPS, LOT LINE ADJUSTMENTS, ETC. AS NECESSARY
• PRELIMINARY SITE PLAN, GRADING AND UTILITY PLANS
• PRELMINARY STORMWATER STUDY, REPORT & PLANNING
• BECOME PROJECT POINT GUARD (ONE-STOP COORDINATION SHOP)
• GEOTECH / BIOLOGIST / ARCHAELOGIST
• ARCHITECT
• BECOME CLIENT’S ADVOCATE AT THE AGENCY
CONCEPT
PLANNING /
ENTITLEMENT
DESIGN /
PERMIT
CONSTRUCTION CLOSEOUT
REFERRAL PARTNERS
IN THIS PHASE:
• Homeowner w/ a Concept
• Real Estate Developer
• Architect
• Someone wanting to get
their feet wet in real estate
development / investment
6. DESIGN&PERMITTINGPHASE
GTA SERVICES IN THE PERMITTING PHASE INCLUDE:
• FREE CONSULTATION
• SUPPLEMENTAL TOPOGRAPHIC SURVEY / BOUNDARY VERIFICATION
• PUBLIC IMPROVEMENT PLANS
• STREET, CURB, GUTTER, SIDEWALK & DRAINAGE IMPROVEMENTS
• PUBLIC UTILITY DESIGN TO SERVICE SITE
• SITE DEVELOPMENT PLANS
• INCORPORATE CONDITIONS OF APPROVAL
• CONSULTANT COORDINATION
• ADD NECESSARY DETAIL TO DESIGNS
• STORMWATER CONROL PLAN (SWCP) AND POLLUTION PREVENTION PLAN (SWPPP)
• CONTINUE AS PROJECT POINT GUARD (ONE-STOP COORDINATION SHOP)
• GEOTECH / BIOLOGIST / ARCHAELOGIST
• ARCHITECT, MECHANICAL, ELECTRICAL & PLUMBING
• LANDSCAPE ARCHITECT
• CLIENT ADVOCACYAT AGENCIES AND UTILITY PROVIDERS!
CONCEPT
PLANNING /
ENTITLEMENT
DESIGN /
PERMIT
CONSTRUCTION CLOSEOUT
REFERRAL PARTNERS
IN THIS PHASE:
• Homeowner or Developer
that had a rough
experience during
entitlement phase
• Engineer not interested in
construction documents
• Architect
7. CONSTRUCTIONPHASE
CONCEPT
PLANNING /
ENTITLEMENT
DESIGN /
PERMIT
CONSTRUCTION CLOSEOUT
GTA SERVICES IN THE CONSTRUCTION PHASE INCLUDE:
• FREE CONSULTATION
• CONSTRUCTION STAKING
• PAD, FORM AND BUILDING HEIGHT CERTIFICATIONS
• RESPOND TO CONTRACTOR REQUESTS FOR INFORMATION
• CONSTRUCTION INSPECTION AND OBSERVATION
• STORMWATER MONITORING & INSPECTIONS
REFERRAL PARTNERS
IN THIS PHASE:
• Homeowner / Developer
• General Contractor
8. CLOSEOUTPHASE
CONCEPT
PLANNING /
ENTITLEMENT
DESIGN /
PERMIT
CONSTRUCTION CLOSEOUT
GTA SERVICES IN THE CLOSEOUT PHASE INCLUDE:
• FREE CONSULTATION
• ASSUME ENGINEER OF RECORD (EOR)
• PREPARE AND/OR VERIFY AS-BUILT RECORD DRAWINGS
• AGENCYAND OWNER PUNCHLIST WALKS AND FINAL WALKS
• ENGINEER’S CERTIFICATION OF SUBSTANTIAL CONFORMANCE
• STORMWATER
• CERTIFY SWCP MEASURES INSTALLED ARE EQUAL OR GREATER THAN THOSE
DESIGNED AND PERMITTED
• FILE ANNUAL REPORT AND NOTICE OF TERMINATION FOR SWPPP
REFERRAL PARTNERS
IN THIS PHASE:
• Home Builder
• Developer that has been
left high and dry by
original EOR