The document provides an overview of Team X's risk identification and assessment methodology for space science missions. It describes how risks are identified prior to a study through checklists and discussions with subsystem experts. During a study, risks are scored and categorized through a risk matrix. Key risks are then used to generate a risk-adjusted probabilistic cost estimate curve that reflects cost and schedule uncertainty. An example risk-adjusted cost estimate is provided for a hypothetical EHM orbiter mission.