Helps in understanding the interpretation or authoring of contract conditions. The 'Why' of most contract conditions can be understand by understanding the basics.
2. Definitions
When you define a word in a contract, normal English meaning no longer applies to
that word wherever it appears in the contract with first letter uppercase.
Observe the usage of word Statement in a clause with ‘S’ in uppercase meaning it’s a
defined word and one should refer to definitions for its meaning.
Defined Word
Usage of defined word with first letter in
uppercase
3. Definitions
Maintain uniformity while writing definitions
▪ Bold the defined word
▪ Put the defined word inside double quotation marks
▪ Maintain ‘means’ after the word and then the actual definition
▪ maintain alphabetical order for easy navigation
4. Risk Balancing
One of the main objective of any contract document is to balance risks of both
parties.
▪ Client’s risks
▪ Contractor’s risks
▪ Risks that can’t be estimated shall able covered by an insurance cover
▪ Risks that can’t be covered by insurance shall be in the client scope.
5. Risk Balancing - Client Risks
Event
▪ Issue of Tender
Risk
▪ Non receipt of sufficient offers may delay contract finalization
Mitigation provision
▪ Send expression of interest (EOI)
▪ Levy Tender fee
6. Risk Balancing - Client Risks
Event
▪ Performance or Default
Risk
▪ Contractor not performing as per agreed conditions
Mitigation provision
▪ ‘Performance Security’ valid until expiry of Defects Liability Period
7. Risk Balancing - Client Risks
Event
▪ Advance Payment
Risk
▪ Couldn’t recover the advance amount paid to contractor
Mitigation provision
▪ Advance bank guarantee clause
8. Risk Balancing - Client Risks
Event
▪ Schedule Delay
Risk
▪ Delay in Project completion
Mitigation provision
▪ Liquidated damages clause
▪ Define Start and End dates of contract unambigiously
9. Risk Balancing - Client Risks
Event
▪ Tax payment
Risk
▪ Contractor doesn’t pay taxes for which client may be held responsible
Mitigation provision
▪ Clarify who pay what under taxation clause
▪ Make it mandatory to submit documentary evidence of tax payments
along with monthly invoice
10. Risk Balancing - Client Risks
Event
▪ Labour compliance
Risk
▪ Client may be responsible as per local authorities to ensure compliance
Mitigation provision
▪ Make it mandatory to submit documentary evidence of all labour
payments and statutory compliances along with monthly invoice
11. Risk Balancing - Client Risks
Event
▪ Remedying of defects
Risk
▪ Defects realized after Taking over of the Works
Mitigation provision
▪ Defects Liability Period
12. Risk Balancing - Client Risks
Event
▪ Remedying of defects
Risk
▪ Contractor not remedying the defects during Defects Liability Period
Mitigation provision
▪ Retention money
13. Risk Balancing - Contractor Risks
Event
▪ Payment
Risk
▪ Delay in making payment by client
Mitigation provision
▪ ‘Delayed Payment’ clause under Payment terms indicating interest
payable for payment delay
14. Risk Balancing - Contractor Risks
Event
▪ Client inputs
Risk
▪ Delay in providing clarifications, approvals etc. in time
Mitigation provision
▪ Time frame to provide response
▪ Provision for extension of time (EOT) for response delay
15. Risk Balancing - Contractor Risks
Event
▪ Prolonged delay
Risk
▪ Prolonged delay by Employer; Employer becomes bankrupt etc.
Mitigation provision
▪ ‘Termination by Contractor’ detailing the events that can lead to
Contractor exercising his right to Terminate.
17. Risks that can’t be estimated by contractor: cover by insurance or shall be in
the client scope.
Activity Risk Clause to mitigate the risk
1 Injury / Damages Injury / damage to men, machine &
materials
Can be covered by taking insurance: YES
Proper insurance clause specifying who buys
what.
2 Damage to underground tools Damage to drilling tools that can’t be
retrieved out for damage inspection.
Can be covered by taking insurance: NO
Compensation in the client scope
3 Material / manpower price
increase
Can be estimated by Contractor: NO
Can be covered by taking insurance: NO
Escalation clause. Cost impact in the client scope.
4 Changes in Legislation Can be estimated by Contractor: NO
Can be covered by taking insurance: NO
Compensation (both time and cost) in the client
scope
5 Force Majeure events (other than
floods)
Can be estimated by Contractor: NO
Can be covered by taking insurance: NO
Compensation (both time and cost) in the client
scope
6 Force Majeure events (floods) Can be estimated by Contractor: NO
Can be covered by taking insurance: YES
Compensation (only for time) in the client scope.
Cost can be covered by insurance
7 Unforeseeable Physical
conditions
Can be estimated by Contractor: NO
Can be covered by taking insurance: NO
Compensation (both time and cost) in the client
scope
18. Web: www.rightvendors.in
Email: info@rightvendors.in
Linkedin: www.linkedin.com/company/rightvendors/
Facebook: www.facebook.com/rightvendors/
A cloud based vendor management, vendor discovery and
proposal management platform for making construction procurement easy.