The document discusses consortium agreements (CAs) for projects with multiple partner institutions. It defines a CA and explains that while templates exist, each CA should reflect the specific project. It describes different types of legal/administrative arrangements that could serve as a CA, including a formal multi-party agreement, separate contracts between institutions, or memoranda of understanding. The key is that the arrangement coherently documents the project management framework, allocates responsibilities, and allows the work to be completed on time.
Speaking to investors? Want to understand how term sheets work? Know how different terms will affect the cap table, what to say when investors propose terms and how you can respond, and what to expect in your term sheet negotiations. Daniel Zimmermann and John Demeter of WilmerHale will lead a Term Sheet Negotiation Simulation with breaks for Q&A. This is an excellent opportunity to learn the nuts and bolts of term sheets.
Drafting Arbitration Clauses commonly involves a lot of mental exercises. Many calibrations are required on the part of the drafters. The slides incorporate some common aspects which should inform the ones involved in drafting of Arbitration Clauses.
Introduction to Commercial Contract DraftingEMLI Indonesia
Materi Workshop Contract Drafting yang disampaikan oleh Bapak Dendi Adisuryo yang memiliki background sebagai commercial lawyer akan memberikan pemahaman dan pandangan kepada peserta workshop mengenai beberapa segi hukum kontrak, norma kepatutan hukum kontrak dalam proses penyusunan kontrak serta mengenai kontrak atas transaksi bisnis yang bersifat lintas negara.
Speaking to investors? Want to understand how term sheets work? Know how different terms will affect the cap table, what to say when investors propose terms and how you can respond, and what to expect in your term sheet negotiations. Daniel Zimmermann and John Demeter of WilmerHale will lead a Term Sheet Negotiation Simulation with breaks for Q&A. This is an excellent opportunity to learn the nuts and bolts of term sheets.
Drafting Arbitration Clauses commonly involves a lot of mental exercises. Many calibrations are required on the part of the drafters. The slides incorporate some common aspects which should inform the ones involved in drafting of Arbitration Clauses.
Introduction to Commercial Contract DraftingEMLI Indonesia
Materi Workshop Contract Drafting yang disampaikan oleh Bapak Dendi Adisuryo yang memiliki background sebagai commercial lawyer akan memberikan pemahaman dan pandangan kepada peserta workshop mengenai beberapa segi hukum kontrak, norma kepatutan hukum kontrak dalam proses penyusunan kontrak serta mengenai kontrak atas transaksi bisnis yang bersifat lintas negara.
Dispute Resolution Boards have proven highly effective (greater than 98% success rate) in resolving disputes in segments of the construction industry and preventing claims from going to arbitration or litigation. While more successful than all other non-binding alternatives, their use has been concentrated in specific project types and limited regions. Dispute and construction professionals will benefit from exploring the principles leading to success, and the practice will benefit from broader dissemination of this exciting method.
TEMPLATE PERJANJIAN KERJASAMA PENGEMBANGAN TEKNOLOGI DAN LAYANAN APLIKASI DIG...GLC
Untuk beli perjanjian ini, silahkan buka link ini:
https://www.sdkpermit.com/products/TEMPLATE-PERJANJIAN-KERJASAMA-PENGEMBANGAN-TEKNOLOGI-DAN-LAYANAN-APLIKASI-DIGITAL-BILLINGUAL-p570989566
تصنيف أنواع العقود في مجال الانشاءات
دورة مجانية في: https://www.udemy.com/contracts-arabic/
الدورة الكاملة: prof.planner.teachable.com/p/contract-management/
Contracts are a part of our everyday life, arising in collaboration, trust, promise and credit.
How are contracts formed? What makes a contract enforceable? What happens when one party breaks a promise?
Perjanjian jual beli saham bersyarat cspa bumn. Beli perjanjian ini melalui link ini:
https://sdklegal.company.site/products/Perjanjian-jual-beli-saham-bersyarat-CSPA-BUMN-p524888674
In the INTERNATIONAL SUPPLY AGREEMENT TEMPLATE the products will be delivered by the Supplier to the Purchaser at the delivery points specified in the Annex of the Agreement.
Exclusive Distributorship Agreement Sample (Purchase this doc, Text: 08118887...GLC
Exclusive Distributorship Agreement Sample, to Purchase this doc, visit this link:
https://sdkpermit.company.site/products/Exclusive-Distributorship-Agreement-Template-p524911304
UNIVERSITY OF PHOENIXCOLLEGE OF EDUCATION AND EXTERNAL STUDIES.docxdickonsondorris
UNIVERSITY OF PHOENIX
COLLEGE OF EDUCATION AND EXTERNAL STUDIES
SCHOOL OF CONTINUING AND DISTANCE EDUCATION
DEPARTMENT OF EXTRA MURAL STUDIES
MASTERS OF ARTS IN PROJECT PLANNING AND MANAGEMENT
LDP 602: – PROJECT FINANCING
CIRCUMSTANCES IN WHICH ENVIRONMENTAL, POLITICAL AND MACROECONOMIC RISKS ARE IMPORTANT FOR PROJECT FINANCIERS BEFORE ADVANCING LOAN TO A PROJECT COMPANY
CESAR DELARIVIER
L50/76492/2014
Term Paper Submitted in Partial Fulfilment of the Requirement for the Award of Master of Arts in Project Planning and Management in the Department of Extra-Mural Studies University of Phoenix.
1. Table of Content page
Explain the circumstances in which environmental, political and macroeconomic risks are important for project financiers before advancing loan to a project company (15marks).
Introduction
Project finance can be characterised in a variety of ways, while there is currently no universally adopted definition, different authors and practitioners articulate it through different definitions. Yescombe (2002 ) states that it is a method of raising long-term debt financing for major projects through “financial engineering,” based on lending against cash flow generated by the project alone: It depends on detailed evaluation of projects construction operating and revenue risks, and their allocation between investors, lenders and other parties through contractual and other agreements.
Gatti (2007) defines it as “… the structured financing of a financial economic entity _the SPV, or special –purpose vehicle, also known as the project company- created by sponsors using equity or mezzanine debt and for which the lender considers cash flows as being the primary source of loan reimbursement…”.
Gardner and Wright (2011) define it as the raising of finance on a limited recourse basis, for the purposes of developing a large capital intensive infrastructure[footnoteRef:1] project, where the borrower is a special purpose vehicle and repayment of the financing by the borrower will be dependent on the internally generated cash flows of the project” [1: In their text, for simplicity, the authors used the term ‘infrastructure’ generically to refer to any capital intensive asset or group of assets which provide essential goods or services (e.g. utilities, petrochemicals, transportation services, housing etc) and can be contractually structured to provide internally generated cashflows.]
Though there are varied definitions a few factors resonate across the board: It is a form of secured lending characterised by intricate, but balanced, risk allocation arrangements (Fletcher and Pendleton 2014) and usually involves lenders extending credit sometimes to the tune of billions of shillings, to a project company whose core assets at the time of lending are likely to consist of little more than a collection of contracts, licences and ambitious plans.
There are no guarantees to financiers from the project company (non-recourse finance ) or ...
Dispute Resolution Boards have proven highly effective (greater than 98% success rate) in resolving disputes in segments of the construction industry and preventing claims from going to arbitration or litigation. While more successful than all other non-binding alternatives, their use has been concentrated in specific project types and limited regions. Dispute and construction professionals will benefit from exploring the principles leading to success, and the practice will benefit from broader dissemination of this exciting method.
TEMPLATE PERJANJIAN KERJASAMA PENGEMBANGAN TEKNOLOGI DAN LAYANAN APLIKASI DIG...GLC
Untuk beli perjanjian ini, silahkan buka link ini:
https://www.sdkpermit.com/products/TEMPLATE-PERJANJIAN-KERJASAMA-PENGEMBANGAN-TEKNOLOGI-DAN-LAYANAN-APLIKASI-DIGITAL-BILLINGUAL-p570989566
تصنيف أنواع العقود في مجال الانشاءات
دورة مجانية في: https://www.udemy.com/contracts-arabic/
الدورة الكاملة: prof.planner.teachable.com/p/contract-management/
Contracts are a part of our everyday life, arising in collaboration, trust, promise and credit.
How are contracts formed? What makes a contract enforceable? What happens when one party breaks a promise?
Perjanjian jual beli saham bersyarat cspa bumn. Beli perjanjian ini melalui link ini:
https://sdklegal.company.site/products/Perjanjian-jual-beli-saham-bersyarat-CSPA-BUMN-p524888674
In the INTERNATIONAL SUPPLY AGREEMENT TEMPLATE the products will be delivered by the Supplier to the Purchaser at the delivery points specified in the Annex of the Agreement.
Exclusive Distributorship Agreement Sample (Purchase this doc, Text: 08118887...GLC
Exclusive Distributorship Agreement Sample, to Purchase this doc, visit this link:
https://sdkpermit.company.site/products/Exclusive-Distributorship-Agreement-Template-p524911304
UNIVERSITY OF PHOENIXCOLLEGE OF EDUCATION AND EXTERNAL STUDIES.docxdickonsondorris
UNIVERSITY OF PHOENIX
COLLEGE OF EDUCATION AND EXTERNAL STUDIES
SCHOOL OF CONTINUING AND DISTANCE EDUCATION
DEPARTMENT OF EXTRA MURAL STUDIES
MASTERS OF ARTS IN PROJECT PLANNING AND MANAGEMENT
LDP 602: – PROJECT FINANCING
CIRCUMSTANCES IN WHICH ENVIRONMENTAL, POLITICAL AND MACROECONOMIC RISKS ARE IMPORTANT FOR PROJECT FINANCIERS BEFORE ADVANCING LOAN TO A PROJECT COMPANY
CESAR DELARIVIER
L50/76492/2014
Term Paper Submitted in Partial Fulfilment of the Requirement for the Award of Master of Arts in Project Planning and Management in the Department of Extra-Mural Studies University of Phoenix.
1. Table of Content page
Explain the circumstances in which environmental, political and macroeconomic risks are important for project financiers before advancing loan to a project company (15marks).
Introduction
Project finance can be characterised in a variety of ways, while there is currently no universally adopted definition, different authors and practitioners articulate it through different definitions. Yescombe (2002 ) states that it is a method of raising long-term debt financing for major projects through “financial engineering,” based on lending against cash flow generated by the project alone: It depends on detailed evaluation of projects construction operating and revenue risks, and their allocation between investors, lenders and other parties through contractual and other agreements.
Gatti (2007) defines it as “… the structured financing of a financial economic entity _the SPV, or special –purpose vehicle, also known as the project company- created by sponsors using equity or mezzanine debt and for which the lender considers cash flows as being the primary source of loan reimbursement…”.
Gardner and Wright (2011) define it as the raising of finance on a limited recourse basis, for the purposes of developing a large capital intensive infrastructure[footnoteRef:1] project, where the borrower is a special purpose vehicle and repayment of the financing by the borrower will be dependent on the internally generated cash flows of the project” [1: In their text, for simplicity, the authors used the term ‘infrastructure’ generically to refer to any capital intensive asset or group of assets which provide essential goods or services (e.g. utilities, petrochemicals, transportation services, housing etc) and can be contractually structured to provide internally generated cashflows.]
Though there are varied definitions a few factors resonate across the board: It is a form of secured lending characterised by intricate, but balanced, risk allocation arrangements (Fletcher and Pendleton 2014) and usually involves lenders extending credit sometimes to the tune of billions of shillings, to a project company whose core assets at the time of lending are likely to consist of little more than a collection of contracts, licences and ambitious plans.
There are no guarantees to financiers from the project company (non-recourse finance ) or ...
Basic Contract Law for project managers webinar series: Part 2: Building a contracts
Tuesday 6 March 2018
APM Contracts and Procurement Specific Interest Group (SIG)
presented by Sarah Schütte, Schutte Consulting Limited
hosted by Dr Jon Broome, Contracts and Procurement SIG Deputy Chair
10 Essentials For An Effective Construction ContractSarah Fox
An overview of the 10 aspects every contract for a construction works package (however large or small) needs to include to make it an effective tool.
These 10 essentials are the foundation to the 500-Word Contract (TM), developed as a basis for construction contracts in England/Wales. They are also a checklist for your own terms and conditions.
For more information go to www.500words.co.uk or send Sarah an email sarah@500words.co.uk
Today’s increasingly complex investment and regulatory landscape places greater pressure on the plan sponsors and fiduciaries overseeing defined contribution plans. Fiduciaries are not only re-examining their current investment decision-making practices, they are also seeking to ensure that those practices allow for enough flexibility in implementation to maximize the likelihood of investment success, while protecting the plan sponsor from potential litigation.
Central to the idea of a well-managed program, a clearly articulated investment policy statement (IPS) serves as the foundation of sound governance and a robust oversight process
Contractual Steps for Smooth Delivery of Infrastructure ProjectsAM Publications
Governments and public entities spend huge public money for purchase of goods, services and construction of works. Therefore, it is vital that procurement system shall not only be efficient but also be transparent, fair & just without compromising the quality of output. Various stakeholders have different interests in influencing the decision-making. This paper elaborates various possible alternative strategies available for procurement. Depending upon environment and various challenges, one can choose the best mode, method & process of procurement. The procurement could be for goods, work, services, consultancy etc. Consultancy contracts are different game altogether, because they have more emphasis on intellectual inputs rather than mere physical outcome. The scope of this paper is limited to works procurement.
Strengthen outcome based capital project deliveryBob Prieto
Over the course of my career I have looked at a number of underperforming mega-projects. In every instance there was a common element of underperformance, the lack of clarity around the strategic business outcomes to be accomplished. Conversely, some of the best performing projects exhibited high clarity of recognized and shared outcomes.
This paper looks at the imperative to continue the shift to outcomes based contracts versus more traditional output based contracting forms. This shift is discussed from the perspective of the engineering and construction industry in the United States but draws upon the experience in other countries and other sectors.
Drafting a collaborative research agreementKaayathri Devi
Drafting a collaborative research agreement, IPR, Intellectual property rights, Drafting a collaborative research proposal, collaborative research agreement, collaborative research proposal
Vendor Contract Issues for Boards of Common Interest DevelopmentsConstruction Cicerone
Why should a Board consider hiring an attorney for a proposed vendor contract? Even when a contractor performs “vendor” services, or simple maintenance work on a project, let alone major repair work, a number of events that may have significant impact on an association can occur without an agreement prepared by association counsel(see road map slides.
Understanding User Needs and Satisfying ThemAggregage
https://www.productmanagementtoday.com/frs/26903918/understanding-user-needs-and-satisfying-them
We know we want to create products which our customers find to be valuable. Whether we label it as customer-centric or product-led depends on how long we've been doing product management. There are three challenges we face when doing this. The obvious challenge is figuring out what our users need; the non-obvious challenges are in creating a shared understanding of those needs and in sensing if what we're doing is meeting those needs.
In this webinar, we won't focus on the research methods for discovering user-needs. We will focus on synthesis of the needs we discover, communication and alignment tools, and how we operationalize addressing those needs.
Industry expert Scott Sehlhorst will:
• Introduce a taxonomy for user goals with real world examples
• Present the Onion Diagram, a tool for contextualizing task-level goals
• Illustrate how customer journey maps capture activity-level and task-level goals
• Demonstrate the best approach to selection and prioritization of user-goals to address
• Highlight the crucial benchmarks, observable changes, in ensuring fulfillment of customer needs
LA HUG - Video Testimonials with Chynna Morgan - June 2024Lital Barkan
Have you ever heard that user-generated content or video testimonials can take your brand to the next level? We will explore how you can effectively use video testimonials to leverage and boost your sales, content strategy, and increase your CRM data.🤯
We will dig deeper into:
1. How to capture video testimonials that convert from your audience 🎥
2. How to leverage your testimonials to boost your sales 💲
3. How you can capture more CRM data to understand your audience better through video testimonials. 📊
Tata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s DholeraAvirahi City Dholera
The Tata Group, a titan of Indian industry, is making waves with its advanced talks with Taiwanese chipmakers Powerchip Semiconductor Manufacturing Corporation (PSMC) and UMC Group. The goal? Establishing a cutting-edge semiconductor fabrication unit (fab) in Dholera, Gujarat. This isn’t just any project; it’s a potential game changer for India’s chipmaking aspirations and a boon for investors seeking promising residential projects in dholera sir.
Visit : https://www.avirahi.com/blog/tata-group-dials-taiwan-for-its-chipmaking-ambition-in-gujarats-dholera/
Digital Transformation and IT Strategy Toolkit and TemplatesAurelien Domont, MBA
This Digital Transformation and IT Strategy Toolkit was created by ex-McKinsey, Deloitte and BCG Management Consultants, after more than 5,000 hours of work. It is considered the world's best & most comprehensive Digital Transformation and IT Strategy Toolkit. It includes all the Frameworks, Best Practices & Templates required to successfully undertake the Digital Transformation of your organization and define a robust IT Strategy.
Editable Toolkit to help you reuse our content: 700 Powerpoint slides | 35 Excel sheets | 84 minutes of Video training
This PowerPoint presentation is only a small preview of our Toolkits. For more details, visit www.domontconsulting.com
Top mailing list providers in the USA.pptxJeremyPeirce1
Discover the top mailing list providers in the USA, offering targeted lists, segmentation, and analytics to optimize your marketing campaigns and drive engagement.
buy old yahoo accounts buy yahoo accountsSusan Laney
As a business owner, I understand the importance of having a strong online presence and leveraging various digital platforms to reach and engage with your target audience. One often overlooked yet highly valuable asset in this regard is the humble Yahoo account. While many may perceive Yahoo as a relic of the past, the truth is that these accounts still hold immense potential for businesses of all sizes.
3.0 Project 2_ Developing My Brand Identity Kit.pptxtanyjahb
A personal brand exploration presentation summarizes an individual's unique qualities and goals, covering strengths, values, passions, and target audience. It helps individuals understand what makes them stand out, their desired image, and how they aim to achieve it.
B2B payments are rapidly changing. Find out the 5 key questions you need to be asking yourself to be sure you are mastering B2B payments today. Learn more at www.BlueSnap.com.
Building Your Employer Brand with Social MediaLuanWise
Presented at The Global HR Summit, 6th June 2024
In this keynote, Luan Wise will provide invaluable insights to elevate your employer brand on social media platforms including LinkedIn, Facebook, Instagram, X (formerly Twitter) and TikTok. You'll learn how compelling content can authentically showcase your company culture, values, and employee experiences to support your talent acquisition and retention objectives. Additionally, you'll understand the power of employee advocacy to amplify reach and engagement – helping to position your organization as an employer of choice in today's competitive talent landscape.
The 10 Most Influential Leaders Guiding Corporate Evolution, 2024.pdfthesiliconleaders
In the recent edition, The 10 Most Influential Leaders Guiding Corporate Evolution, 2024, The Silicon Leaders magazine gladly features Dejan Štancer, President of the Global Chamber of Business Leaders (GCBL), along with other leaders.
How to Implement a Real Estate CRM SoftwareSalesTown
To implement a CRM for real estate, set clear goals, choose a CRM with key real estate features, and customize it to your needs. Migrate your data, train your team, and use automation to save time. Monitor performance, ensure data security, and use the CRM to enhance marketing. Regularly check its effectiveness to improve your business.
Best practices for project execution and deliveryCLIVE MINCHIN
A select set of project management best practices to keep your project on-track, on-cost and aligned to scope. Many firms have don't have the necessary skills, diligence, methods and oversight of their projects; this leads to slippage, higher costs and longer timeframes. Often firms have a history of projects that simply failed to move the needle. These best practices will help your firm avoid these pitfalls but they require fortitude to apply.
At Techbox Square, in Singapore, we're not just creative web designers and developers, we're the driving force behind your brand identity. Contact us today.
1. V0.5
1 | P a g e
Consortium Agreements
Creating a Consortium Agreement
JISC/Higher Education Academy OER Pilot Programme
Andrew Charlesworth, Centre for IT & Law, University of Bristol.
Introduction
This document discusses the concept of Consortium Agreements (CA) and, in particular, their use by
projects within JISC Programmes. It discusses the types of legal/administrative arrangements that
could be utilised to meet the CA requirements of JISC’s Generic Terms and Conditions of Grant, and
answers some common questions about developing an appropriate CA for your project. It does not
contain a CA template. JISC has previously produced such a document, but the variety of JISC-
funded projects means that it is not possible to create a meaningful generic template for general use
– each CA should ideally reflect the context in which it is being created and used.
Defining a ‘Consortium Agreement’?
A common perception is that a Consortium Agreement is a single formal legal document, agreed and
signed by all the parties to a project, and which imposes a set of standard conditions on those
signatories. These conditions would include, amongst other things, agreements as to ownership and
exploitation of IPRs, and a set of warranties and disclaimers allocating risk between the parties. This
interpretation of the term “Consortium Agreement” as a formal multi-signatory document is
common across the research/development environment.1
JISC’s Generic Terms and Conditions of Grant state that:
6. The lead institution must also supply a core set of documents to indicate how the project work
will be planned and implemented, to report on progress, and to inform future auditing and
evaluation. It is the responsibility of the lead institution to agree these documents with its
project partners prior to submission.
7. The core project documents are listed below and further information about each document is
provided in the Project Management Guidelines.
8. Core project documents are subject to approval by the Programme Manger, and the
framework for approval is outlined in the Project Management Guidelines.
9. Core project documents will be deposited in the appropriate records management system
and/or project information management system so they are accessible to the JISC and Academy
Executive.
Included in the Core Project Document Set is a requirement that projects involving more than one
institution should have a Consortium Agreement, and that this should be completed within 3 months
of the start date of a successful project.
However, between and within JISC Programmes, there can be significant differences in the nature
and scope of multi-partner projects. As a result, the precise content of a CA may need to be varied
according to the nature and scope of the project at issue, and the respective roles of the project
partners. Thus, while templates do exist for drawing up ‘formal’ CAs, project partners must avoid
the temptation of simply adopting a basic CA template and ‘filling in the blanks’. This approach runs
the risk of failing to address important issues which are specific to an individual project, or which
1
See, for example, the Lambert Agreements documentation at:
http://www.innovation.gov.uk/lambertagreements/
2. V0.5
2 | P a g e
stem from the nature of the Programme within which it sits. Rather, it is important for the project
partners to spend adequate time assessing the requirements for, and construction of, a project
Consortium Agreement in order that they can to work through and understand the implications of
the precise agreement mechanism chosen, as regards their particular participation in the project.
Function over Form
The main problem with CA templates is that they tend to focus project staff on the ‘form’ of the
agreement between parties rather than upon its ‘function’. In other words, in some circumstances it
may be less important to have a ‘formal’ multiparty CA, than it is to have a series of documented
agreements, or documented administrative arrangements, that together effectively and efficiently
achieve the project’s stated aims and objectives, including providing for appropriate project
management and resource/risk allocation. Having such agreements or administrative arrangements
in documented form can be invaluable in helping JISC Programme Managers and project
administrators identify, evaluate and tackle problems during the lifetime of the project, and also in
ensuring that appropriate and timely solutions can be reached to disputes between project
members on the basis of pre-agreed processes, or dispute management. (see p.7)
By way of example, a documented agreement approach might consist of separate legal contracts
between a Lead Institution and the other parties to the project linked to an administrative strategy
document outlining the rationale for such a contract framework. A documented administrative
arrangement approach might consist of letters of agreement and memoranda of understanding
between a Lead Institution and the other parties to the project, which may or may not have
elements which are legally binding, similarly linked to an administrative strategy document outlining
the rationale for that method of constructing a consortium.
The use of one approach need not foreclose the use of others. For example, a large project with
major partners who will be producing the primary outputs and receiving significant funding, and
minor partners with smaller roles and limited or no financing, might use a combination of formal CA
(between major partners), legal contracts (between Lead Institution and minor partners) and/or
documented non-binding administrative arrangement (between Lead Institution and minor
partners).
The important issues from the point of view of JISC, as a Funder, are that whatever its form, an
Agreement between parties to a project should:
be coherently documented;
provide an appropriate project management framework;
clearly allocate responsibility for resource allocation and risk management;
reflect the understandings of the parties as to their role, rights and responsibilities;
ensure that the work for which funding is allocated is completed in a timely fashion.
The main focus for ensuring the achievement of those elements will usually be the Lead Institution
which received the funding. A Lead Institution needs to be able to ensure that it can meet its
obligations to JISC: failure to meet those obligations would usually mean JISC seeking repayment of
funding, and would potentially damage the Lead Institution’s ability to successfully bid for future
funding. It is thus in the interests of the Lead Institution to have some form of written agreement
with other parties working on the project, that enables it to meet its obligation to JISC. In certain
circumstances this may go as far as explicitly permitting the JISC to intervene in the arrangements
under the agreement between Lead Institution and other Project parties. Whether a Lead
Institution will require a highly detailed legal agreement, or something less formal, between itself
and another Project party, will usually depend upon the extent to which the Lead Institution
considers that relationship to expose it to legal/financial risk in the event of, for example, significant
non-performance by the other Project party.
3. V0.5
3 | P a g e
The type of written agreement with a Lead Institution that a Project party will be likely to finds
acceptable will obviously depend upon their assessment of the obligations and risk allocated to
them by that agreement, as against the benefits which they are likely to receive under it. Where the
benefit is slight (e.g. limited funding, or simply acknowledgement of participation and donation of
materials) a Project party may refuse to accept significant binding obligations, or more than minimal
levels of legal/financial risk.
Types of legal/administrative arrangement capable of classification as a Consortium Agreement
under JISC’s Generic Terms and Conditions of Grant
Figure 1. Formal Consortium Agreement
In this arrangement, the whole Consortium Agreement is contained in one ‘multi-lateral’ legal
document.
This type of agreement may be appropriate where the Parties wish to play a role in the adminstration of
a Project, e.g. as part of the Project management team or through a Steering Committeee arrangement;
or where the Lead Institution requires a uniform approach to key risk issues such as funding, warranties,
IPR etc between the Parties. For example:
the Parties all have important roles to play in the delivery of the Project aims and objectives, and
any Party’s failure to deliver may jeopardise the Project’s success;
the Parties are all receiving significant funding under the Project, making uniform treatment of the
Parties’ liability for failure to deliver, financial mismangement etc. an appropriate approach;
4. V0.5
4 | P a g e
the lead Instituion intends, or is obliged by JISC, to arrange a uniform approach to IPRs, such as
assignment of Project IPRs to itself or to JISC/HEFCE, in order to facilitate the Project’s aims and
objectives.
This type of agreement may not be appropriate where there are factors which make a uniform
approach to risk factors less appropriate. For example:
the Parties vary widely in their roles and criticallity to the Project, or Parties are expected or are
likely to frequently join or leave during the life of the Project;
the Project is of short duration and/or of limited financial value to some of the Parties;
the nature of the Project is such that project risks cannot be shared amongst the Parties in a
uniform manner, e.g. where the funding is primarily for a Lead Institution to manage/co-ordinate
the actions of other parties who are receiving minimal funding.
Figure 2. Contractual Framework-based Consortium Agreement
In this arrangement, the Consortium Agreement consists of the ‘bi-lateral’ contracts negotiated
between the Lead Institution and the other parties, in combination with the Project Administration
Document (PAD). The PAD will contain details of the centralised administrative/management
framework, funding information, details of the individual contracts (and, ultimately, their outcomes),
and such other issues as are necessary for the Lead Institution to effectively and efficiently provide
appropriate project management, resource and risk allocation for the purpose of meeting JISC’s
objectives in funding the Project.
This type of agreement effectively leaves the organisation of the Project’s development, its
management structure, and its records management to the Lead Institution. It is likely to be
appropriate for projects where:
5. V0.5
5 | P a g e
the other Parties have widely varying roles and funding with regard to the project aims and
objectives;
the project is of relatively short duration and rapid resolution of the CA process is thus
required;
partners have varying tolerance of risk, given their respective roles, and thus attempting to
impose a blanket set of warranties and liabilities will be unsuitable.
Figure 3: Memorandum of Understanding/Letter of Agreement-based Consortium Agreement
In this arrangement, the Consortium Agreement consists of the ‘bi-lateral’ agreements negotiated
between the Lead Institution and the other parties and expressed as Mou/LoA, in combination with
the Project Administration Document (PAD) The PAD will contain details of the centralised
administrative/management framework, funding information, details of the individual agreements
(and, ultimately, their outcomes), and such other issues as are necessary for the Lead Institution to
effectively and efficiently provide appropriate project management, resource and risk allocation for
the purpose of meeting JISC’s objectives in funding the Project.
As with the contract-based CA in figure 2, this type of agreement effectively leaves the organisation
of the Project’s development, its management structure, and its records management to the Lead
Institution. It is likely to be appropriate for projects where:
the project is of relatively short duration and rapid resolution of the CA process is thus
required;
the Parties involved are receiving little or no direct funding for their inputs to the project and
are thus unlikely to want to sign up to either a formal CA or a bilateral contract with the Lead
Institution.
6. V0.5
6 | P a g e
Figure 4: A hybrid model Consortium Agreement
7. V0.5
7 | P a g e
In the hybrid arrangement, the full ‘Consortium Agreement’ consists of:
the formal CA negotiated jointly between the Lead Institution and Parties 1-5;
the ‘bi-lateral’ contracts negotiated between the Lead Institution and Parties 6-8;
the ‘bi-lateral’ agreements negotiated between the Lead Institution and Parties 9-11
expressed as Mou/LoA;
the Project Administration Document (PAD).
The formal CA might document that the Lead Institution may enter into the bi-lateral contracts and
agreements with other parties for the purpose of the Project. In some circumstances, it might
formally authorise the Lead institution to do so and/or allow the other parties to exercise some
degree of oversight of such contracts or arrangements. As with figures 2 and 3, the PAD will contain
details of the centralised administrative/management framework, funding information, details of
the individual contracts and agreements (and, ultimately, their outcomes), and such other issues as
are necessary for the Lead Institution to effectively and efficiently provide appropriate project
management, resource and risk allocation for the purpose of meeting JISC’s objectives in funding the
Project.
FAQs
For the purpose of the following discussion, the term ‘Consortium Agreement’ should be taken to
mean not just a formal multiparty document (as per Figure 1 above), but also “any combination of
documented agreements, and/or documented administrative arrangements, which the Lead
Institution considers to be capable of effectively and efficiently providing appropriate project
management, resource and risk allocation for the purpose of meeting the Funder’s objectives, in the
circumstances of a particular Programme.”
Q: Why do we need a Consortium Agreement (apart from the fact that JISC wants us to
have one)?
A: An effectively developed Consortium Agreement can, and should, fulfil multiple purposes
within a project that will help to ensure that the process of producing project deliverables and
the achievement of project outcomes are made as efficient as possible. It should not be
viewed as simply a piece of administrative paperwork to be completed as an afterthought to
the main work of the project – it should be drafted in advance of that work and serve to
underpin the process.
When constructing a JISC project with multiple parties, a Consortium Agreement should
provide both the institutions and the project team with a clear set of rules for managing the
project, and for regulating issues relating to its operation amongst the project partners. If
there is no Consortium Agreement, or the Consortium Agreement is unclear or inadequate,
project partners and project staff may be unaware of the extent of institutional rights and
obligations within the project, including ownership of existing and newly created intellectual
property, and the project is likely to lack an effective management structure for its
operational, technical and financial aspects. This may result in, for example:
inappropriate decisions being made as regards the internal organisation and management
of the project, including improper allocation of financial responsibilities;
failure to properly assess the risk and liability accruing to project partners, leading to
failure to make adequate provision, including insurance, for those risks and liabilities;
an inability to settle internal disputes between project partners in a clearly understood,
efficient and cost-effective manner;
8. V0.5
8 | P a g e
difficulties in handling the exit of existing project partners and the inclusion of new project
partners;
inadequate attention being paid to intellectual property rights, with the result that the
usefulness and exploitability of project deliverables is compromised;
difficulties in continuing the work of the project after the initial funding period has ended,
due to lack of mechanisms for agreeing future development and funding options.
Project teams are often assembled after the funding has been obtained. A clear Consortium
Agreement between partner institutions will set out clearly, at the earliest possible stage, the
management and regulatory framework within which the project team members are to work.
It also provides clear guidance to newcomers to the project team on the roles, rights and
responsibilities within the project, in the event of staff turnover during the project lifetime.
The need for clarity and comprehensibility in a Consortium Agreement cannot be overstressed
– all project partners and project team members should be aware of their Consortium
Agreement’s content and its implications for their work.
Q: When should we draw up our Consortium Agreement?
A: As early as possible in the project development process. As already noted, a well drafted
Consortium Agreement can play a key role in the project process by providing a coherent
framework for operational development by the project team. It also requires the project
partners to think carefully at an early stage about what they see their role within the project
as being, and, if appropriate, where they would like it to go in the future. If the creation of a
Consortium Agreement is left until later in the project process, it may become increasingly
difficult to obtain agreement from project partners as to their respective responsibilities and
future ambitions for project outcomes and deliverables. Equally, failure to agree issues
relating to intellectual property at an early stage may result in unnecessary difficulties in use of
intellectual property brought to the project by a project partner (often called ‘background’
intellectual property), and intellectual property created in the course of the project (often
called ‘foreground’ intellectual property) during and after the project.
Q: What should a Consortium Agreement contain?
A: It is very important that project partners consider carefully at an early stage not just the
operational elements of a Consortium Agreement (e.g. the terms which address the internal
organisation and management of the project), but also the possible longer-term strategic
elements – for example:
what outputs and deliverables do the project partners intend to create, and what is the
intended exploitation strategy for those outputs and deliverables?
are the project partners likely to seek further funding to continue the work of the project
after the initial funding ceases, and if so, from what sources?
An effective Consortium Agreement should allow the project partners the opportunity to
review and address these strategic questions, and make provision for agreed adjustments to
the terms of the Consortium Agreement to take account of future strategic developments.
In broad terms, the types of issues that it would be normal to expect a Consortium Agreement
to address would include provisions to:
ensure the technical implementation of the project, including the management structure
and composition (e.g. project management, steering groups, etc.) required to ensure
efficient and effective management of the operational, technical and financial aspects of
the project;
9. V0.5
9 | P a g e
identify the lead institution, detail its role in administering the project funding according to
decisions taken by the project partners, and describe the allocation of funding to project
participants and to identified activities, including how, when and where funding will be
allocated as well as to whom;
provide potential solutions to problems relating to technical implementation (e.g. failure
of a project partner to perform) and solutions to potential financial problems;
allow for changes in project partner membership, including modification or extension of
the Consortium Agreement to include further contributing partners;
to describe, as precisely as possible, the way in which ‘background’ and ‘foreground’
intellectual property, will be used and/or disseminated by the project partners during, and
where appropriate after, the course of the project. This will normally include at least
some of the following issues:
o allocation and exercise of ownership, including joint ownership;
o setting out the terms of ‘use’ in a detailed and verifiable manner: e.g. who will
exploit what, when and how, and such access rights as may be necessary;
o granting additional or more favourable access rights, e.g. access rights to third
parties, or specifying the requirements applicable to access rights, or excluding
specific pre-existing know-how from the obligation to grant access rights
o granting of sub-licenses (with the agreement of the party owning the licensed rights)
o payment of royalties on access rights to the results or background
o extending the period within which access rights are to be granted between project
parties after the end of the project.
Q: Who should we consult in our Institution?
A: All HE institutions are likely to have institutional contracts officers (e.g. people who oversee
the institution’s legal relationships with third parties) and research/ development officers who
are usually able to advise on project development, including legal issues.
As part of preparing for a project bid, it is useful to identify the individuals within your
organisation who perform these functions. Such people often have significant demands on
their time, and it is always worth giving them advance warning of the fact that you may need
help in deciding the best model for your Consortium Agreement; and, in the event that you
decide that the nature of your project requires a formal Consortium Agreement, that you may
need guidance on appropriate drafting.
In-house advisors will have experience of how your institution handles particular types of
projects; for example, for particular types of research work, or where funding is above a
particular level, an institution may require formal contracts signed off by a Contract Officer or
Senior Administrator. Equally where funding is limited, your institution may not wish to take a
formal CA/contract route (perhaps for cost or time reasons), and may instead be willing to
operate on the basis of a MoU/LoA signed off by a Head of Department. It may be helpful to
establish these issues (ideally in writing) in advance of beginning CA discussions with other
project partners, as this can save significant time and reduce the need for a formal multi-party
CA, if the parties can agree that this approach is unnecessary or undesirable.
Simply dropping your project bid on an in-house advisor’s desk is not usually the best way to
proceed with your search for advice. When discussing how to develop an appropriate CA for
your project bids and projects with in-house advisors it is important to ensure that you have