PENALTY & LIQUIDATED
DAMAGES
Madhusudhan Narasimhamurthy
RA1512002010027
WHY??
1. Breach of contract by any of the two parties in a contract.
2. To compensate the loss suffered.
What?
In a contract, the parties may name a sum to be payable in the event of
breach.
1. Liquidated damages: If such sum is a genuine pre estimate of loss.
2. Penalty: If the sum is not a reflection of loss.
http://www.legalserviceindia.com/articles/li2.htm
Provisions
• Indian Contract Act – Section 73 & 74
• PWD for B-1 & B-2- Cl. 2
• CPWD form - Cl.2
• M.E.S form – Cl.50
• Sec. 73 states that “when a contract has been broken, the aggrieved
party is entitled to get compensation or any loss or damages which has
been inflicted to him/her naturally during the usual course of breach
of contract or about which the parties to the contract has prior
knowledge when they entered the contract .”
• Sec 74 states “When a contract has been broken, and if a sum is
named in the contract as the amount to be paid for such breach, or if
the contract contains any other stipulation by way of penalty, the party
complaining of the breach is entitled, whether or not actual damage or
loss is proved to have been caused thereby, to receive from the party
who has broken the contract reasonable compensation not exceeding
the amount so named or, as the case may be, the penalty stipulated
for”.
http://blog.ipleaders.in/liquidated-damages-and-penalty-in-india/
Law Suit-1: Reasonable Compensation
• ONGC vs. Saw pipes Ltd
• ONGC had claimed the liquidated damages for delay in supply of
casing pipes.
• Saw pipes opposed the action.
• Court directed the arbitral tribunal to assess the case with reference to
Fateh chand, Maula Baux and Rampur distillery
• Lastly, stipulated money was reduced and termed it as reasonable
compensation.
Stipulations in construction contracts
• Transgression – Delay in Handover
• Stipulations
1. General: 0.5-1% of contract price per day/per week
2. Govt. standards: 0.5-10% of contract price per week of delay.
Objections
1. It should be genuine estimate
2. Factors
Law suit-2
• Case: “A” did not supply five machines to “B” in stipulated time.
• Agreed terms: Penalty of 1% on the total value of the supply for
every three days up to 10% .
• A (Plaintiff) filed a suit against B (defendant) to relax the penalty.
• Defendant did not justify the loss, hence, the penalty was relaxed.
Other rules of Penalty/Liquidated damages
• When to evoke: Either during or after completion of contract
• Relaxation:
1. By communication (only for time)
2. Absence of terms
3. Satisfactory completion
• Only a right to sue.
Thank You

Liquadated damages

  • 1.
    PENALTY & LIQUIDATED DAMAGES MadhusudhanNarasimhamurthy RA1512002010027
  • 2.
    WHY?? 1. Breach ofcontract by any of the two parties in a contract. 2. To compensate the loss suffered.
  • 3.
    What? In a contract,the parties may name a sum to be payable in the event of breach. 1. Liquidated damages: If such sum is a genuine pre estimate of loss. 2. Penalty: If the sum is not a reflection of loss. http://www.legalserviceindia.com/articles/li2.htm
  • 4.
    Provisions • Indian ContractAct – Section 73 & 74 • PWD for B-1 & B-2- Cl. 2 • CPWD form - Cl.2 • M.E.S form – Cl.50
  • 5.
    • Sec. 73states that “when a contract has been broken, the aggrieved party is entitled to get compensation or any loss or damages which has been inflicted to him/her naturally during the usual course of breach of contract or about which the parties to the contract has prior knowledge when they entered the contract .” • Sec 74 states “When a contract has been broken, and if a sum is named in the contract as the amount to be paid for such breach, or if the contract contains any other stipulation by way of penalty, the party complaining of the breach is entitled, whether or not actual damage or loss is proved to have been caused thereby, to receive from the party who has broken the contract reasonable compensation not exceeding the amount so named or, as the case may be, the penalty stipulated for”. http://blog.ipleaders.in/liquidated-damages-and-penalty-in-india/
  • 6.
    Law Suit-1: ReasonableCompensation • ONGC vs. Saw pipes Ltd • ONGC had claimed the liquidated damages for delay in supply of casing pipes. • Saw pipes opposed the action. • Court directed the arbitral tribunal to assess the case with reference to Fateh chand, Maula Baux and Rampur distillery • Lastly, stipulated money was reduced and termed it as reasonable compensation.
  • 7.
    Stipulations in constructioncontracts • Transgression – Delay in Handover • Stipulations 1. General: 0.5-1% of contract price per day/per week 2. Govt. standards: 0.5-10% of contract price per week of delay. Objections 1. It should be genuine estimate 2. Factors
  • 8.
    Law suit-2 • Case:“A” did not supply five machines to “B” in stipulated time. • Agreed terms: Penalty of 1% on the total value of the supply for every three days up to 10% . • A (Plaintiff) filed a suit against B (defendant) to relax the penalty. • Defendant did not justify the loss, hence, the penalty was relaxed.
  • 9.
    Other rules ofPenalty/Liquidated damages • When to evoke: Either during or after completion of contract • Relaxation: 1. By communication (only for time) 2. Absence of terms 3. Satisfactory completion • Only a right to sue.
  • 10.

Editor's Notes

  • #8 Heuristic estimates