SlideShare a Scribd company logo
Confirmations and Contradictions
The Leontief Paradox, Reconsidered:
Correction
Iraj Heravi
University of California, Los Arigetes
Leontief (1954) incorrectly inferred that the United States is
revealed
by trade to be relatively more abundant in labor than in capital
from
the fact that the capital per man in imports exceeds the capital
per
man in exports. The counterexample in Leamer (1980) is in
error,
however, since it uses commodity prices at which the first
commodity
is not economically produced. This is easily remedied by setting
the
price vector to (2, 1, 1) instead of (1, 1, 1). Then, by the series
of
calculations outlined in Leamer (1980), it is possible to
compute the
ratio of capital per man in exports to capital per man in imports
to be
0.97, even though capital is the relatively abundant factor.
Incidentally, the error in the choice of prices is revealed by the
computation of the returns to factors, which for the original
numbers
contains a negative return to capital.
References
Heravi, Iraj. "Determination of Patterns of Trade." Ph.D.
dissertation, Univ.
California at Los Angeles, 1984.
Leamer, Edward E. "The Leontief Paradox,
Reconsidered."/.P.£:. 88 (June
1980): 495-503.
Leontief, Wassily W. "Domestic Production and Foreign Trade:
The Ameri-
can Capital Position Re-examined." Econ. Internazionate 7
(February 1954):
9—38. Reprinted in Readings in International Economics,
edited bv Richard E.
Caves and Harry G.Johnson. Homewood, III.: Irwin (for
American Econ.
Assoc), 1968.
Postdoctoral scholar. Graduate School of Management, UCLA. I
am indebted to
Edward Leamer for his advice and encouragement. See my
dissertation (1984) for
further work.
[Jounuil (i/ Piiliiiral Ecimomy. 19R6, vol. 94, no. 5]
© 198(3 by l h e L nivfisuy of Chicago. All rights reserved.
0022-3808/86/9405-0010$01.50
1 12O
#1. DUE Thursday 1/ 22 /2015 NOON…. Continue working
with the company you originally chose from the Fortune’s 500
Best List ( Johnson & Johnson)
http://archive.fortune.com/magazines/fortune/mostadmired/2006
/best_worst/worst8.html
Detail Directions (See Below) – CLASSROOM FORUM
DISCUSSION
1. You have been working with each environment
individually; now it's time to integrate and synthesize.
2. Perform research (minimum of 3 sources in APA format).
3. Analyze each environment collectively by incorporating
theories learned.
4. How are the individual environments working together for
your chosen company?
5. How is each working with the other environments?
6. Is an environment causing limitations on another? If so,
which environments are involved and what are the limitations?
7. What could you change to create synergy? Your answer
cannot be that you wouldn’t change a thing. You must
incorporate critical thinking.
8. Minimum 6 complete paragraphs; a paragraph is a
minimum of 100 words.
*****Use this as one of the References: Use at least one of
the sources provided below in “Reading / Resources: “.
#2 . DUE Saturday 1/ 24 /2015- NOON . Continue working
with your chosen company from Fortune’s 500 Worst List (
Chosen Company is “Google”)
http://archive.fortune.com/magazines/fortune/mostadmired/2006
/best_worst/worst8.html
Detail Directions (See Below) – FORMAL PAPER
Assignment Instructions
Continue working with your chosen least admired company
(Google) for the assignments and complete the following:
1. Identify the company’s domestic environment and discuss
how the government regulations affect its domestic environment
it must operate in.
2. Identify a global environment for the company and
discuss how the government regulations affect its global
environment it must operate in.
3. Identify the hard and soft technology and interpret the
characteristics the company should have/use to be successful in
its domestic and global environment.
4. Identify the political-legal barriers for the company in
both the domestic and global environments. Use business
theory/theorists to illustrate how the company can operate
successfully in its domestic and global environment.
5. Identify, compare, and contrast sociocultural factors of
the domestic and global environments of the company.
6. Compare and contrast two economic theories for both the
domestic and global environments of the company.
7. Develop a strategy of success based on your evaluation of
steps 1-6 by assessing what you’ve learned through your
research and readings and compare what the company has been
doing to what you recommend they should be doing. You cannot
state that you would not change anything.
8. You must incorporate critical thinking (see resources).
9. Research requirement: minimum 5 sources PLUS the text
and Geert Hofstede.
10. Page requirement: 7 pages in APA format (does not count
cover page and reference page).
Note: ALL Assignments are submitted to turnitin.com and
checked for originality.
****Use this as one of the References: Use at least one of the
sources provided below in “Reading / Resources: “.
ADDITIONAL NOTES / INFORMATION:
This is it! Here you will finish integrating the environments of
your chosen company. At this point, you should have all
elements identified in your previous writings ( forums and paper
assignments). Is there anything you would change at this point?
Do you think you would be successful? Why or why not? The
assignment this week will be a final simulation project for your
chosen company. Using your company you’ve been working
with, recognize all the environments you’ve studied – domestic,
global, technological, political/legal, sociocultural, and
economic. All environments must be included. Once you have
each identified, it’s time to analyze and synthesize. What is
each individual environment like? How are they working? What
issues do you see? What would you change and why? It won't be
acceptable to state you wouldn't change anything. Really apply
what you've learned from your research.
Now, take a look at all environments together, as whole and not
individual pieces. Is each working together? Is an environment
causing limitations on another? If so, which environments are
involved and what are the limitations? What could you change
to create synergy?
All Sources must be “Scholarly Article or Book”. A scholarly
article or book generally is based on original research or
experimentation. It is written by a researcher or expert in the
field who is often affiliated with a college or university. Most
scholarly writing includes footnotes and/or a bibliography and
may include graphs or charts as illustrations as opposed to
glossy pictures. In addition, articles that appear in scholarly
journals or book that are published by academic presses, are
subject to a peer-review process, which means that other
"experts" or specialist in the field evaluate the quality and
originality of the research as precondition of publication. The
peer-review (as opposed to editorial review) process is also one
thing that sets scholarly journals apart from journals that may
otherwise seem quite similar. Journals such as Foreign
Affairs, for instance, are generally not considers "scholarly
journals," because many of the articles are solicited by the
magazine's editors; in addition many of the articles are written
by policy-makers who may be expressing an informed view, but
whose article may not be based on original research.Scholarly
research is typically published by a academic association or a
university/academic press. In international relations and
comparative politics, representative scholarly journals
include Asian Survey, Comparative Politics, International
Organization, International Security Studies, Journal of
Comparative Politics, Journal of Democracy, and World
Politics.
Reading / Resources:
You are not limited to the below:
**Review all previous resources provided.
Lin, H., Fan Y., & Newman S. (2009). Manufacturing process
analysis with support of workflow modelling and
simulation (p1773-1790. 18p. 6)
Závadský, J., & Lukáš, T. (2010). Simulation and its purpose in
implementing of business process management. Advances in
Management, 3(3), 9-12
International Journal of Production Research
Vol. 47, No. 7, 1 April 2009, 1773–1790
Manufacturing process analysis with support of workflow
modelling and simulation
Huiping Lin
a,*, Yushun Fan
a
and Stephen T. Newman
b
a
Department of Automation, Tsinghua University, Beijing,
100084, P.R., China;
b
Department of Mechanical
Engineering, University of Bath, Bath, BA2 7AY, UK
(Received 15 December 2005; final version received 14 August
2007)
Process analysis is recognized as a major stage in business
process reengineering
that has developed over the last two decades. Manufacturing
process
analysis (MPA) is defined as performance analysis of the
production process.
A manufacturing process analysis framework is outlined with
emphasis on linking
a company’s strategy to operational process. Two issues,
namely process
modelling and simulation based analysis, are investigated. A
compound workflow
model (CWM) is proposed to provide graphic presentation of
the production
process that can be easily understood. Also it can be used
directly by simulation
to study the impacts of scheduling policy and analyse the
process performance.
A two-stage simulation analysis method is provided to
quantitatively and
efficiently define cause-and-effect relations to identify drivers
for improvement.
The manufacturing environment, PSC (production planning,
scheduling and
control) factors and the process structure are three main
concerns considered in
the simulation. An example is discussed in the final part of the
paper.
Keywords: manufacturing process; performance analysis;
modelling; simulation
1. Introduction
With increasing market competition, more and more companies
recognize the importance
of improving their competitive capability. Over the last two
decades, business process
reengineering (BPR) has been carried out by academic
researchers and industrial
companies to improve performance. It concerns the fundamental
rethinking and radical
redesign of a business process to obtain dramatic and sustained
improvements in quality,
cost, service, lead time and innovation (Hammer and Champy
1993). Process analysis is
recognized as a highly important stage of any BPR project. It
understands the way the
process is done, finds problems and the gaps between current
performance and expected
targets, and identifies changes needed for improvement.
Manufacturing process analysis, which is defined as modelling
and performance analysis
of a production process, is essential for manufacturing
companies to improve their market
competition. Manufacturing is a complicated system that
involves sets of tasks, materials,
resources (including human resources, facilities and software),
products, and information.
Askin and Standridge (1993) divided the manufacturing system
into five interrelated
*Corresponding author. Email: [email protected]
ISSN 0020–7543 print/ISSN 1366–588X online
� 2009 Taylor & Francis
DOI: 10.1080/00207540701644151
http://www.informaworld.com
functions: product design; process planning; production
operations; material flow/facilities
layout; and production planning and control. Product design is
responsible for constructing
the description of the products. Process planning entails the
specification of the sequence of
operations required for product production. Production
operations refer to those
fabrication or assembly actions such as drilling a hole or
inserting a raw material into the
workstation. Facilities layout is concerned with the physical
placing of production process.
Production planning, scheduling and control (PSC) is an
important task within
manufacturing. It generates long/medium term production plans
and disaggregates them
to obtain short term schedules about the tasks’ sequence on the
machine.
The MPA discussed in this paper is mainly concerned with
production process
reengineering. It uses a top down method to associate the
company’s strategy with the
process’s target. By process analysis, it finds out the initiatives
to implement the target.
MPA is not the same as the production scheduling and control
problem. MPA optimizes
the production from the point of view of process structure
redesign. Most PSC methods
optimize the measurements such as time, and cost with the
existing resource or process
constraints. (Readers are referred to a series of review papers
about PSC namely Gupta
et al. 1991, MacCarthy and Liu 1993, Sox et al. 1999, Potts and
Kovalyov 2000, Tan and
Khoshnevis 2000.) MPA can result in adjustments of process
constraints. Process
improvement solutions possibly contain reconstruction of the
process or the organization,
for example, outsourcing some activities, adding a new
resource, reducing an activity’s
processing time by new technology, etc. It considers the
influence of PSC because the
appropriate planning and scheduling methods can also improve
the process performance.
Modelling and simulation based analysis of MPA are discussed
in this paper. Usually
a process model is established to understand the structure of
manufacturing, reveal
relationships among machines, tasks and materials, and learn
how the process works.
In the literature, mathematical models and graphic models are
two major methods to
describe the manufacturing process. For example, fuzzy mixed
integer programming
has provided the ability to model and analyse the manufacturing
cell formation problem
(Tsai et al. 1997). Yun and Gen (2002) used constraint
programming to establish a
pre-emptive and non pre-emptive scheduling model. Cooke et
al. (2004) developed mixed
integer programming formulations with the assumption of a
production precedence
sequence to study the economic lot scheduling problem.
Mathematical models are often
used for production scheduling purposes. Although
mathematical models are convenient
for computing, they do not offer an intuitive understanding to
their users. Petri nets are
a popular graphic method for modelling, scheduling and
analysing the manufacturing
process (Shih and Sekiguchi 1991, Lee and DiCesare 1994,
Proth and Minis 1995, Xiong
et al. 1996, Zhou and Venkatesh 1999). Shih and Sekiguchi
(1991) and Lee and DiCesare
(1994) used a Petri net with heuristic search for FMS (flexible
manufacturing systems)
scheduling. Xiong et al. (1996) and Zhou and Venkatesh (1999)
studied the application of
Petri nets in modelling, simulation and control of flexible
manufacturing systems. The use
of Petri nets has the advantage in describing complicated
process constraints. However,
the major problem is that its state space for searching grows
dramatically with system
complexity (Zhou and Venkatesh 1999). It still lacks a
comprehensive model that has all
following features:
. The capability to describe complicated relations among tasks,
machines, and
production routings;
. Graphic presentation so that the model can be easily
established and used;
1774 H. Lin et al.
. To fulfil requirements of MPA that is concerned with the PSC
and process
planning.
Thus, a workflow modelling and simulation based method is
proposed to solve the
problem in manufacturing process analysis. The contributions of
the paper are:
. Providing a manufacturing analysis framework that emphasizes
on associating
enterprise strategy to process.
. Providing a graphic presentation of a manufacturing process,
not only showing the
structure of a process, but also containing enough information
for dynamic
performance analysis.
. Proposing a structured two-step sensibility analysis to
quantitatively and efficiently
identify cause-and-effect relations to implement the strategy.
The paper is organized as follows: initially, an analysis
framework is introduced. How
production process modelling and simulation are used in MPA
is described. Then a
compound workflow model (CWM) is proposed to describe the
production process.
A two-step simulation method is explained in detail. The final
part of the paper provides
a case study which shows the effectiveness of the proposed
method.
2. Manufacturing process analysis framework
MPA should have a strategic level of thinking about the
objective and target of the
manufacturing process. It encourages people to be more creative
and more focused on
process improvement. More and more people have realized
strategic thinking in a project
will help to identify the desired performance and make
improvements more focused and
purposeful. For example, King (1994) pointed out the lack of
strategy accounted for many
failures in process improvement projects. Kaplan and Norton
(1992, 1996) proposed
a balanced scorecard (BSC) – namely an effective method for
strategy management.
In Kaplan and Norton’s method, four steps are involved: first, a
company’s strategy is
translated into process’ objectives. Second, key indicators are
selected to measure process
performance. Then, targets are associated with indicators at
operational level. Finally,
initiatives to pursue targets are identified and tasks will be
completed. In Kaplan and
Norton’s method, a cause-and-effect analysis served as a core
part in linking strategy to
process. The cause-and-effect relations are a set of hypotheses
about how to achieve
important objectives. Usually, it can be expressed as a sequence
of if-then statements: If we
do actions, then we may be able to achieve objectives.
Although BSC provides a framework for connecting a
company’s strategy to a process,
it does not specify how the connection can be built. Only when
people have a very good
understanding about a process’s structure and performance, can
they know which factors
account for what results. For a complicated manufacturing
process, although some
historical data and employee experience exists, it is very
difficult to quantitatively define
cause-and-effect relations. On the other hand, in Kaplan and
Norton’s straight down four
step method, there was no communication between the decision
making level that set
targets and the operational level that has details about
manufacturing. If the target is too
stressful, it will be expensive or even impossible to realize. It
will not benefit process
improvement projects until the target is appropriately set. Thus,
a target evaluation and
a bridge between the decision making level and the operational
level are needed.
International Journal of Production Research 1775
Moreover, as performance improvement solutions may have
structural change to the
process, feasibility verification of the solutions is required
before it is put into
implementation to avoid unnecessary loss.
Thus, a new manufacturing process analysis framework is
provided (see Figure 1).
An adapted workflow model and its simulation will be used to
clarify the manufacturing
process, understand how the process operates and access
process improvement solutions.
A feedback channel is introduced to help in setting reasonable
targets.
After the company’s strategy is clarified, the following steps
are taken to link the
strategy to the processes.
Step 1: Translating the company’s strategy to processes’
objective.
Connecting strategy directly to the process helps to break
through the boundary of
organizations and focus on process-oriented analysis. At this
stage, the process’s objective
is determined according to the company’s strategy. The
manufacturing process model is
needed for two reasons. Firstly, the manufacturing process
model defines the structure and
constraints for the manufacturing processes. It provides a
platform for employees and
project teams to understand the manufacturing process and
communicate with each other.
Secondly, defining the boundary of the processes also helps the
manager to determine the
objective of the process.
Step 2: Identifying key process measurements according to the
process objective.
Measures for manufacturing performance can to be catalogued
in terms of business,
operational and customer perspectives (Challis et al. 2002). As
performance of the
manufacturing process is our main concern, operational
performance is our major focus.
The following performance measures are widely used in
manufacturing: production
throughput, lead time, reliability, cost, capacity, resource
utilization and product quality.
Readers can refer to Altiok (1996) and Viswanadham (1999) for
definitions of some typical
measurements in manufacturing environments.
Step 3: Associating a rough target with selected indicators.
Figure 1. Manufacturing process analysis framework.
1776 H. Lin et al.
At this point, a rough target is set by estimation of cause-and-
effect relations with historic
data and employees’ experiences.
Step 4: Finding initiatives to complete the process improvement
task and verifying the
feasibility of the target.
Improving the production throughput and then maximizing the
benefit is the most popular
objects for production improvement. There are two major ways
to achieve this. The first
method is to take the existing production capacity as given and
optimize the organization’s
performance within the capacity. According to Goldratt and
Cox’s (1992) theory of
constraints, the manager can increase throughput by relieving
the bottleneck factor of the
production. They often do this by choosing an effective
scheduling method to reduce
the downtime on the constraining resources or buffering this
resource; or reengineering the
production to reduce the demand on constraining factors. The
second method is following
the long term operations strategy to increase capacity. The
process improvement can be
catalogued in four dimensions such as process level, activity
level, resource level and
management level. The typical process improvement actions are
shown in Figure 2.
An evaluation method is needed to study which action is most
effective for the
production process. Simulation is used to study the cause-and-
effect relations at this stage.
The simulation results are also used to verify whether the target
is appropriate. If the target
is too stressful, it will go back to negotiate with the higher
decision making level to discuss
the target. Finally, the process improvement solutions can be
generated.
3. Compound workflow model
It is impossible to describe complicated manufacturing
processes from any single
prospective (Toh et al. 1997). Comparing manufacturing
processes with
business processes, the manufacturing process specification
needs to pay much more
attention to constraints such as resource, time and process. A
compound workflow
model (CWM) that includes the process view, resource view and
order view is proposed.
Process level
- Change logic sequence between activities
- Add/delete activities
Activity level
- Change activity processing
- Reducing activity processing time
- Mapping to another resource
Resource level
Management
Level
- Increasing resource capability
- Adding resource’ functions
- Buffering the resource
- Reducing setup time
- Choosing effective scheduling method
Process improvement actions
Figure 2. Typical process improvement actions.
International Journal of Production Research 1777
In this section, a brief introduction to the workflow modelling
technique is given to answer
the question why it is chosen. Then the definition of CWM is
discussed in detail.
3.1 Workflow modelling technology
Workflow management is one of the research areas that has
attracted much attention from
researchers, developers and industrial users since the 1990s.
Over the years, there have
been a lot of definitions for workflow and what features a
workflow management system
must provide. For example, the Workflow Management
Coalition (1995) defines workflow
as ‘the computerized facilitation or automation of a business
process, in whole or part’.
Giga Groups call workflow ‘the operation aspects of a business
process, the sequence of
tasks and who perform them, the information flow to support
the tasks, and the tracking
and reporting mechanism that measure and control them’
(Mohan 1997). Fan et al. (2001)
defines workflow as ‘computerized process model which can be
operated by workflow
management system in order to realize business process
integration and automation’.
Two similarities can be found from the above definitions. First,
a workflow model
describes three aspects of the business process, namely:
. ‘What’ is a process? – defining activities that build up the
process;
. ‘How’ is the process organized? – defining logic between
activities;
. ‘Who’ performs the activity? – defining relations between
resources and activities.
Secondly, a workflow model is often associated with an
execution software system.
In other words, it is an executable model that can be read,
operated, and controlled by
a workflow simulation or management system. This unique
character differentiates itself
from other process models.
Workflow management research efforts can be classified into
three categories namely
workflow specification, workflow implementation and workflow
application. A number of
workflow specifications are already available in the literature.
Winograd and Flores (1987)
provided a communication based workflow model by using
speech act theory. It describes
every action of workflow in four phases from a viewpoint of
communication between
customers and performers. An activity-based methodology
which focused on modelling
the work instead of modelling the commitments among humans
is more popular than
a communication based modelling method. The Workflow
Management Coalition
(WfMC) provided a basic process definition meta-model
(Workflow Management
Coalition 1995) which included activity, role and workflow
relevant data. IBM defined
FlowMark (Mohan et al. 1995), which used activities,
input/output containers, connectors
and conditions to describe the business process in build up time
and drove process
instances during run-time. Petri net and its extended form have
also been used for
workflow definition. For example, Ellis and Nutt (1993) defined
information control nets
from Petri net for workflow specification. Van der Aalst (1996)
provided WF-nets, where
transitions presented activities and places described enable
condition of activities.
The workflow management system has often been used in
business process automation
and reengineering (Aversano et al. 2002). It enables process
automation through
integration, coordination, and communication of both human
and automatic tasks of a
business process (Workflow Management Coalition 1996).
Despite applications in
business processes, Lin et al. (2004) studied the job shop
scheduling problem based on
workflow modelling and simulation. The research showed that
workflow models can be
1778 H. Lin et al.
used to describe manufacturing processes and study production
planning and scheduling
problems as well.
As workflow specification helps to clarify process definition,
supports the considera-
tion of production planning and scheduling and simulation
based performance analysis,
workflow modelling and simulation technology has been chosen
in this paper for
manufacturing process analysis.
3.2 Compound workflow model (CWM)
The CWM is proposed especially for the manufacturing process
where resource
constraints description is very important. CWM is composed of
the process view, resource
view and order view (see Figure 3). Each view aims to describe
one perspective of the
process, where multiple relations exist among different views.
(1) Process view
The process view is built using an activity-based method. It is
made up of multi-processes,
each of which defines activities and the process logic needed
for one type of product.
Thus, manufacturing of each type of product has its own pre-
defined production route in
a CWM. A directed acyclic activity-on-node diagram, where
nodes indicate activities and
arcs indicate dependencies, is used for each process. In order to
describe five typical
processes, logic such as serial, and-joint, and-split, or-joint and
or-split logic, and indicate
start/end point of a process instance, six logic nodes are
introduced into the CWM.
For each activity node, there are three kinds of description
namely property definition,
resource mapping and behaviour description.
. Property definition: defines static properties and dynamic
properties of each
activity. The former refers to properties that will not be changed
during operation,
i.e., activity ID and activity’s function. The latter refers to
properties associated
with run-time status such as activities’ begin time, complete
time and real time
priority.
. Resource mapping: allocates resources to activities, including
necessary human
resources and physical resources. It establishes a connection
between the process
Trigger
Activity
Process View
Order
Order View
Enable
Process
Process logic
Individual Resource
Resource View
Behaviour
Description
Resource
Mapping
Properties
Definition
Properties
Resource Pool
Properties Properties
Figure 3. Structure of compound workflow model (CWM).
International Journal of Production Research 1779
view and resource view. Cost driver of activities are also
defined via resource
mapping.
. Behaviour description: describes activity’s action by ECA
rules, which are formed
as ‘if Event and Condition then Action’. ‘Event’ refers to
running time events such
as ‘the resource is released’, ‘condition’ refers to activity
enable conditions, and
‘action’ means the activity’s status is transferred from one to
another. It is
behaviour description that enables CWM, has the capability to
describe dynamic
behaviour and makes CWM an executable model. ECA rules
will be explained by
simulation system in the analysis.
(2) Resource view
CWM has an independent resource view so that it can handle
complicated resource
constraints more effectively. Two kinds of resource entities –
individual resources and
resource pools are introduced. The individual resource refers to
a real resource entity that
participates in production. The resource pool is in fact a
classification of individual
resources according to their functions or geographical positions
so that individual
resources in the same resource pool can be substituted for each
other. It makes the model
flexible in dealing with the ‘parallel machine’ problem, which
is very common in
manufacturing.
During the model definition period, static mapping from
individual resources to the
resource pool and resource pool to activities are established
separately. Then during
simulation, individual resources are dynamically allocated to
activities based on static
definition and running time individual resource status. In the
case where there is no
resource pool defined in the resource view, individual resources
will be allocated to
activities directly when building the model.
For an individual resource, properties such as name, function,
capacity, cost, etc. are
considered. For the resource pool, properties such as function
and containing resources
are defined.
(3) Order view
The order view describes properties of orders coming to the
enterprise, which reflects the
market environment that the company is facing. Order instances
are initiated according to
the order view to trigger process instances in simulation.
Properties such as orders’ arrival
time, frequency, type, amount, due date, priority, cost, entry of
the process, etc. are
defined.
(4) Cost specification in the CWM
The cost information is specified in the CWM for two purposes:
first, cost information is
recorded for activity-based costing (ABC). The goal of ABC is
to measure and then price
out all the resources used for activities that support the
production and delivery of
products and services to customers (Kaplan and Atkinson 1998).
CWM provides useful
information for activity based cost (ABC). It clarifies the
activities being performed by the
organization’s resources when establishing the process view.
Then, when the resource is
allocated to the activities, the activity cost drivers and activity
cost driver rate can be
identified. This rate will be used to drive activity costs to
products.
Cost is also an important issue that should be considered in
analysis. Usually the
improvement of the process is often associated with cost
increase. For example,
the decrease of the activity processing time due to the increase
of resource functions or
number of the resources often lead to additional cost of a
resource. Thus, the second
1780 H. Lin et al.
purpose of cost description in the CWM is to record dynamic
changes of activity cost
drivers and their rate in simulation. The process improvement
actions can have impacts on
cost calculating through two ways:
. Spending additional cost on resources, for example, buffering
the resource or
adding special functions to the resource. The increase of the
total resource cost will
lead to the adjustment of the activity cost driver rate.
. Changing the mapping relations between activity and
resources, for example,
mapping the activity to another resource by process
reengineering. In this case,
both cost driver and its rate can be affected.
CWM is going to provide information for activity based cost
analysis (Figure 4). In the
resource view, the resource cost is defined as one of the
resource properties. When the
resource is allocated to the activities, the activity cost driver
and its rate are identified and
recorded as the properties of the activities. During the
simulation, if the adjustment to the
process model is made, it will determine whether the resource
cost and mapping relation
are affected. Then the cost properties of the resource and
activities will be recalculated.
In conclusion, CWM is an adapted workflow model for a
manufacturing process.
Comparing to other process models, it provides the following
features:
. Provides flexible resource definition that support static and
dynamic resource
mapping. It can handle various resource constraints of the
production process.
. Provides process behaviour description by ECA rules. The
model can be used by
the workflow simulation system directly for performance
analysis.
. Provide easy cost specification to calculate activity based cost
and record cost
adjustment in sensibility analysis.
Establish Activity-Based
Process View
Establish Resource View
Allocate Resource to
Activity
Identify activity being
performed
Identify resource in the
manufacturing
Identify activity cost driver
Calculating driver rate
Build order view for
simulation Calculating cost
Building CWM Activity based Cost
Resource cost or
mapping affected?
Process
Improvement
Yes
Figure 4. Cost specification in CWM.
International Journal of Production Research 1781
. As mentioned in section 2, workflow modelling and simulation
technology can also
be used for production planning and scheduling problems. That
makes it possible
to support the overall manufacturing process analysis with the
same model.
4. Simulation based sensibility analysis
In order to set the target for the process and find possible
initiatives, the following
questions need to be answered:
. Which factors can have impacts on process performance?
. What kind of impacts the factor can cause to the process?
. How much is the impact?
Sensibility analysis is an effective method to answer the above
three questions. It is
completed by adjusting variables and observing their influence
on the system. However,
there are tens, hundreds or even thousands of variables in
manufacturing. If the variables
are studied one by one, sensibility analysis will become
extremely difficult and
time-consuming. In order to improve the efficiency of the
analysis, a two-phase simulation
method is proposed (Figure 5). The objective of the first round
simulation is to identify
a group of variables that potentially have a major influence on
the system. Then in the
second phase those potential key variables will be studied
further to determine which one
has great impacts on production.
In order to select latent key variables, we first watch the
process’s performance under
different manufacturing environments. A different
manufacturing environment is achieved
by setting appropriate simulation parameters. The following
aspects are considered to
present a different simulation environment:
. Environment factors, including orders’ total number, type,
batch size, due date,
patterns, cost, etc. The process’s performance is usually
associated with the orders
First Round
Simulation
Response to
environments
Influence of different
policies
•
•
•
•
•
Quantitative Cause-
effect-relation
Improvement solutions
Target verification
PSC
Environment
Factors
Performance
Measurement
Statistic
Analysis
Sensibility
Analysis
Group of possible
key variables
Process
Strateg
Process
structure
PSC Environment
Factors
Figure 5. Framework of the two-stage simulation analysis.
1782 H. Lin et al.
coming into the system. For instance, a resource’s utility will be
different when the
order types, pattern, batch size, etc. are changed. A process
improvement solution
should meet requirements under all manufacturing
environments.
. Scheduling policy that is often used in manufacturing.
Different from the
scheduling optimization problem where new algorithms are
studied, the main
purpose of setting a different scheduling policy in the first
round simulation is to
investigate the influence of a company’s most often used
scheduling methods.
It also determines whether the strategy can be achieved by
switching to a different
planning and scheduling method. Since using a different
scheduling policy is more
economic than changing the structure of the process, such a
necessity test is carried
out before structural analysis.
After the data analysis, usually by the ANOVA method, the
crucial performances are
identified. The variables within the process model that are
directly or indirectly associated
with them are going to be studied in the next round of
sensibility analysis. The typical
parameters within the process model are:
. Time related variables, such as processing time of the activity,
set up time, etc.
. Process structure related variables, including the number of
activities, resources,
the topology of the activity network, the association between
activities and
resources.
. Cost related variables, for example, set up cost, holding and
backlog cost, resource
using cost.
. Capability related variables, such as resource capability.
The selected group of process parameters will be treated as
variables in sensibility
analysis. The PSC factors and environment factors are also
considered to give
a comprehensive view of the impacts of these variables under
different scenarios.
5. Example study
A workshop within a small manufacturing enterprise (SME) that
produces crankshafts is
used as a case study. It demonstrates the procedure of applying
the method step by step.
(1) Linking strategy to production process
The company is facing an increasing market and its mid-term
strategy is to increase the
company’s production capability. Currently the workshop’s
output is about 500 items per
month. Assume that the company set a rough target of
increasing manufacturing
capability by 15%. The objective of the analysis is to find the
effective and efficient ways to
increase the throughput.
(2) Build CWM model
The workshop provides several types of crankshafts. Their
manufacturing routings can be
classified into two groups: (1) rough milling – milling – milling
– ultrasound test – drilling –
rough lathing – rough lathing – milling – lathing; (2) rough
milling – milling – ultrasound
test – drilling – rough lathing – rough lathing – milling –
lathing. Four milling machines
(M1, M2, M3, M4), three lathes (L1, L2, L3), one drilling press
(D1) and one ultrasound
test tool (U1) are involved. One operation on one machine is
considered as one activity.
The duration of each activity and the resources used are
described in Table 1.
International Journal of Production Research 1783
A two process CWM is built (Figure 6), where each process
describes one
manufacturing route of one product. The resource mapping
between activities and
resources is defined in activity properties.
(3) Simulation based analysis
The following aspects are considered in first round simulation
parameter settings:
. Total order number per month. As the objective is to increase
the process
throughput, the basic rule to set total order number per month is
that it can
cover the situation from current process capability to the target
capability.
Thus, together with the settings of order pattern, the response of
the process to the
manufacturing environment can be watched.
. Order pattern. Three order patterns are considered. Under
pattern A, all the orders
have the same due date for one month. It reflects the stable
market where all the
orders are known in advance and the workshop can arrange the
manufacturing
by a monthly production plan. On the other hand, order patterns
B and C have
10% (B) and 30% (C) urgent orders respectively. The urgent
orders have a due
date of two weeks. Patterns B and C simulate a market with
different degrees of
Table 1. Description of the production route of the case study.
Product 1 Task T1 T2 T3 T4 T5 T6 T7 T8 T9
Machine M1 M2 M3 U1 D1 L1 L2 M4 L3
Duration (hour) 0.3 0.5 0.4 0.5 0.3 0.4 0.5 0.4 0.3
Product 2 Task T11 T12 T13 T14 T15 T16 T17 T18
Machine M1 M3 U1 D1 L1 L2 M4 L3
Duration (hour) 0.3 0.5 0.4 0.4 0.6 0.5 0.3 0.4
T1 T2 T3 T4
T11 T12 T13 T14
P1
P2
T5
Resource View
Activity ID : T13
Activity function : Ultrasound test
Resource: U1
Activity Time : 0.4 hour
Behaviour: If (T13-Previous.Status = completed )
And (Resource.Status = occupied )
Then (T13.Status = initiatived )
If (T13-Previous.Status = completed )
And (Resource.Status = available )
Then (T13.Status = started )
……
Milling
-M1
O-P1
Order
Type:P2
Frequency:
Batch :
Due date:
T6 T7 T8 T9
T15 T16 T17 T18
Process View
O-P2
Milling
-M2
Milling
-M3
Test tool
-U1
Drill Process
-D1
Lathe
-L1
Lathe
-L2
Milling
-M4
Lathe
-L3
Figure 6. CWM model of the case study.
1784 H. Lin et al.
disturbance. According to the historic data, about 65% of the
total order is for
product 1.
. Scheduling policy. The dispatching rules are used in real
production. The three
most used dispatching rules are studied: earliest due date
(EDD), shortest process
time (SPT), and first-in-first-out (FIFO).
The parameters of the simulation are set as in Table 2. Two
performance indicators are
selected:
. Process total throughput which is defined as the number of
units produced per
month.
. Resource utility which is defined as percentage of time a
machine is actually busy.
The result of simulation and ANOVA analysis are given in
Tables 3 and 4 respectively.
The scheduling policy has the highest F-value on the output and
resource utilization
among the three factors. That means the appropriate scheduling
policy can help to
improve the process performance. However, scheduling policy
cannot reduce the demand
on the constraining factors of U1, L1 and L2: in all simulation
runs resources U1, L1 and
L2 have relatively high utilization under all situations. They are
the bottleneck of
production. According to improvement dimensions, activity
level and resource level of
factors are chosen as potential key variables in sensibility
analysis. They are:
. The processing time of activities T4 and T13, T6 and T15, and
T7 and T16, which
are associated with U1, L1 and L2 respectively. Since
technically it is not easy to
dramatically reduce activities’ processing time, two situations
are considered:
reducing processing time 5% and 10%; and reducing the
activities’ processing time
can be achieved through process innovation, using better
material or including
additional functions to the equipment resource (Table 5).
. The number of U1, L1 and L2. One resource will be added.
All three order patterns and three scheduling policies are
considered in sensibility
analysis, it cannot guarantee scheduling policy SPT still has the
best performance, so all
three scheduling policies are considered as well.
Table 2. Description of parameters for first round simulation.
Exp No. Order no.
Order
pattern
Scheduling
policy Exp No. Order no.
Order
pattern
Scheduling
policy
1 525 A EDD 15 575 B SPT
2 550 A EDD 16 525 C SPT
3 575 A EDD 17 550 C SPT
4 525 B EDD 18 575 C SPT
5 550 B EDD 19 525 A FIFO
6 575 B EDD 20 550 A FIFO
7 525 C EDD 21 575 A FIFO
8 550 C EDD 22 525 B FIFO
9 575 C EDD 23 550 B FIFO
10 525 A SPT 24 575 B FIFO
11 550 A SPT 25 525 C FIFO
12 575 A SPT 26 550 C FIFO
13 525 B SPT 27 575 C FIFO
14 550 B SPT
International Journal of Production Research 1785
The simulation results of sensibility analysis are shown in Table
6. It can be seen that
SPT still has the best performance among the three scheduling
policies. Although resource
U1 does not have the highest utilization in the first round
simulation, it has an outstanding
performance in the sensibility analysis. The production
capability can be notably
increased by reducing the processing time of T4 and T13 by
10% (production capability
Table 3. Simulation result of first round simulation.
Resource utilization%
Total
throughput M1 M2 M3 U1 D1 L1 L2 M4 L3
1 470 58 62 84 89 64 90 96 70 64
2 469 58 62 84 89 65 91 96 70 65
3 469 58 62 84 89 65 91 96 70 65
4 471 58 63 84 90 65 91 96 71 65
5 472 58 62 84 90 65 91 97 71 65
6 472 59 63 85 91 66 92 98 71 66
7 479 59 63 85 91 66 93 98 71 66
8 478 59 63 85 91 66 92 98 71 66
9 478 57 62 83 88 64 89 95 69 64
10 521 57 61 83 88 64 89 95 69 64
11 524 57 61 83 88 64 89 95 69 64
12 523 57 62 83 88 64 89 95 69 64
13 521 57 61 83 88 64 89 95 69 64
14 524 57 61 83 88 64 89 95 69 64
15 523 57 62 83 88 64 89 95 69 64
16 521 57 61 83 88 64 90 95 69 64
17 524 57 61 83 88 64 90 95 69 64
18 523 58 62 84 89 64 90 96 70 64
19 470 58 62 84 89 65 91 96 70 65
20 469 58 62 84 89 65 91 96 70 65
21 469 58 62 84 89 64 90 96 70 64
22 470 58 62 84 89 65 91 96 70 65
23 469 58 62 84 89 65 91 96 70 65
24 469 58 62 84 89 64 90 96 70 65
25 470 58 62 84 89 65 91 96 70 65
26 469 58 62 84 89 65 91 96 70 65
27 469 58 62 84 89 65 91 96 70 65
Table 4. ANOVA results (F-value) for the interaction effects of
three control parameters on total
throughput and each machine’s utilization.
Resource utilization%
Total
throughput M1 M2 M3 U1 D1 L1 L2 M4 L3
Order no 0.14 0.00 1.52 0.00 0.08 0.96 1.06 0.08 0.16 0.46
Order pattern 4.20
a
0.53 0.87 0.53 1.29 0.96 1.85 0.98 1.08 1.21
Scheduling policy 1535.21
a
14.74
a
16.52
a
14.74
a
13.63
a
10.82
a
14.37
a
11.13
a
17.37
a
11.90
a
a
With a significance less than 5%.
1786 H. Lin et al.
increase 12.65%) or by adding one U1 (production capability
increase 15.95%). It has
much better performance than adding L2 and L1, or changing
the activity time associated
with them. The reason for this perhaps is that U1 not only has
relative high utilization, but
also has been involved in production in an earlier stage than L2
or L1. The target can be
realized by adding one ultrasound test tool.
6. Conclusions
Manufacturing process analysis is an important stage to improve
a manufacturing
enterprise’s performance. It is a higher level of analysis that
focuses on strategic thinking
of the manufacturing and structure redesign of the process with
the consideration of PSC.
Table 5. Reduce activities’ processing time.
Description Through Cost
1 Reduce T4, T13’s processing
time 5%
Process innovation –
2 Reduce T4, T13’s processing
time 10%
Use better material T4 and T13’s material cost driver rate
"4%
3 Reduce T6, T15’s processing
time 5%
Process innovation –
4 Reduce T6, T15’s processing
time 10%
Add L1’s function T6 and T15’s resource cost driver
rate"6%
5 Reduce T7, T16’s processing
time 5%
Process innovation T7 and T16’s resource cost driver
rate"2%
6 Reduce T7, T16’s processing
time 10%
Adding L2’s function T7 and T16’s resource cost driver
rate"8%
Note: – means not changed.
Table 6. Impacts of select variables on process performance.
EDD SPT FIFO
No. Avg.p IncsR Avg.p IncsR Avg.p IncsR
1 469.29 0.01 562.59 7.52 469.29 0.01
2 469.32 0.01 589.45 12.65 469.32 0.01
3 482.60 2.84 526.65 0.65 482.60 2.84
4 482.73 2.87 525.93 0.51 482.73 2.87
5 469.96 0.15 523.35 0.02 469.96 0.15
6 470.66 0.30 523.43 0.03 470.66 0.30
7 469.26 0.00 606.74 15.95 469.26 0.00
8 482.48 2.82 511.43 2.26 482.37 2.79
9 470.85 0.34 523.26 0.00 471.01 0.37
Note: Avg.p¼average process throughput under all three order
patterns and
IncsR¼Avg.p/current process throughput%.
International Journal of Production Research 1787
The authors provided a useful manufacturing process modelling
method and simulation
based analysis framework to support MPA. It has the following
major advantages:
. The compound workflow model (CWM) provides a graphic
process
description for MPA. It introduces rich model elements, for
example, logic
nodes, resource pool, and ECA rules, to provide a flexible
description of
various constraints in the manufacturing process. Also, it can be
used directly
by simulation to study the impacts of scheduling policy and
analyse the
process performance.
. The analysis framework gives a step-to-step guide for MPA
with process modelling
and simulation techniques. Despite the usual steps of setting
objectives, selecting
key performance measures, setting targets and identifying
initiatives, the target
verification is introduced into the framework to build a bridge
between the
decision making level that sets targets and operation level that
have details about
manufacturing.
. The two-step simulation method provides an effective way to
quantitatively
identify cause-and-effect relations needed in MPA. Also, it
provides a general
framework to take the manufacturing environment and impacts
of scheduling
policy into consideration.
Further work will consider the framework to identify, evaluate
and determine the
process improvement solutions when cause-and-effect relations
are quantitatively defined.
More factors, such as quality, may be studied in the framework
with support of modelling
and simulation technology.
References
Altiok, T., 1996. Performance analysis of manufacturing
systems. New York, NY: Springer-Verlag.
Askin, R. and Standridge, A., 1993. Modeling and analysis of
manufacturing systems. New York,
NY: John Wiley & Sons Inc.
Aversano, L, Canfora, G., De Lucia, A. and Gallucci, P., 2002.
Business process reengineering and
workflow automation: A technology transfer experience. The
Journal of Systems and Software,
63, 29–44.
Challis, D., Samson, D. and Lawson, B., 2002. Integrated
manufacturing, employee and business
performance: Australian and New Zealand evidence.
International Journal of Production
Research, 40, 1941–1964.
Cooke, D.L., Rohleder, T.R. and Silver, E.A., 2004. Finding
effective schedules for the economic lot
scheduling problem: A simple mixed integer programming
approach. International Journal of
Production Research, 42, 21–36.
Ellis, C.A. and Nutt, G.J., 1993, Modeling and enactment of
workflow systems.
In: M.A. Marsan, ed. Application and theory of petri nets.
Berlin, Germany: Springer-
Verlag, 1–16.
Fan, Y., Luo, H.B. and Lin, H.P., 2001. Fundamentals of
workflow management technology. Beijing,
China: Tsinghua University Press/Springer-Verlag (In Chinese).
Goldratt, E.M. and Cox, J., 1992. The goal: a process of
ongoing improvement, 2nd ed. New York,
NY: North River Press.
Gupta, Y.P., Evans, G.W. and Gupta, M.C., 1991. Review of
multi-criterion approaches
to FMS scheduling problems. International Journal of
Production Economics, 22,
13–31.
Hammer, M. and Champy, J., 1993. Reengineering the
corporation: a manifesto for business
revolution. New York, NY: Harper Collins.
1788 H. Lin et al.
Kaplan, R. and Norton, D., (Jan–Feb) 1992. The balanced
scorecard-measures that drive
performance. Harvard Business Review, 70, 71–79.
Kaplan, R. and Norton, D., 1996. The balanced scorecard:
translating strategy into action. Boston,
MA: Harvard Business School Press.
Kaplan, R. and Atkinson, A., 1998. Advanced management
accounting, 3rd ed. Englewood Cliffs, NJ:
Prentice Hall Inc.
King, W.R., 1994. Process reengineering: the strategic
dimensions. Information Systems
Management, 11, 71–73.
Lee, D.Y. and DiCesare, F., 1994. Scheduling FMS using Petri
nets and heuristic search. IEEE
Transactions on Robotics and Automation, 10, 123–132.
Lin, H.P., Fan, Y. and Loiacono, T.E., 2004. A practical
scheduling method based on workflow
management technology. International Journal of Advanced
Manufacturing Technology, 24,
919–924.
MacCarthy, B.L. and Liu, J.Y., 1993. Addressing the gap in
scheduling research: a review of
optimization and heuristic methods in production scheduling.
International Journal of
Production Research, 31, 59–79.
Mohan, C., Agrawal, D., Alonso, G., Abbadi, A.E., Gunthor, R.
and Kamath, M., 1995. Exotica:
a project on advanced transaction management and workflow
systems. SIGOIS Bulletin –
Special Issue on Business Process Management Systems:
Concepts, Methods and Technology,
16, 45–50.
Mohan, C., Recent trends in workflow management products,
standards, and research, 1997.
Available online at:
http://www.almaden.ibm.com/cs/exotica/wfnato97.pdf (accessed
28
August 2007).
Potts, G.N. and Kovalyov, M.Y., 2000. Scheduling with
batching: a review. European Journal of
Operational Research, 120, 228–249.
Proth, J.M. and Minis, I., 1995, Planning and scheduling based
on Petri nets.
In: M.C. Zhou, ed. Petri nets in flexible & agile automation.
Norwell, MA: Kluwer
Academic, 109–148.
Shih, H. and Sekiguchi, T., 1991. A timed Petri net and beam
search based on-line FMS scheduling
system with routing flexibility, in Proceedings of 1991 IEEE
international conference on
robotics and automation, Sacramento, CA, April, pp. 2548–
2553.
Sox, C.R., Jackson, P.L. Bowman, A. and Muckstadt, J.A.,
1999. Review of the stochastic lot
scheduling problem. International Journal of Production
Economics, 62, 181–200.
Tan, W. and Khoshnevis, B., 2000. Integration of process
planning and scheduling-a review. Journal
of Intelligent Manufacturing, 11, 51–63.
Toh, K.T., Newman, S.T. and Bell, R., 1997. An Architecture
for Information Specification Based
on an SME Enterprise Model, in Proceedings of the IEE 5th
international conference factory
2000: the technology exploitation process, Institution of
Electrical Engineers, Cambridge, UK,
pp. 456–463.
Tsai, C.C., Chu, C.H. and Barta, T.A., 1997. Modeling and
analysis of a manufac-
turing cell formation problem with fuzzy mixed-integer
programming. IIE Transactions, 29,
533–547.
Van derAalst, W.M.P., 1998. Three good reasons for using a
Petri-net-based workflow management
system, in Proceedings of the international working conference
on information and
process integration in enterprises (IPIC), edited by S. Navathe
and T. Wakayama,
Cambridge, Massachusetts, Nov, 1996, pp. 179–201. [Also in
Information and process
integration in enterprises: rethinking documents. Kluwer
Academic Publishers: Norwell MA,
pp. 161–182.
Viswanadham, N., 1999. Analysis of manufacturing enterprises:
an approach to leveraging value
delivery processes for competitive advantage. Norwell, MA:
Kluwer Academic Publishers.
Winograd, T. and Flores, R., 1987. Understanding computers
and cognition. Reading, MA: Addison-
Wesley.
Workflow Management Coalition, The workflow reference
model, Document number TC00-1003,
1995.
Workflow Management Coalition, Workflow management
coalition terminology and glossary
(Document number WfMC-TC-1011), Technical Report,
Brussels, 1996.
International Journal of Production Research 1789
Xiong, H.H., Zhou, M.C. and Caudill, R.J., 1996. A hybrid
heuristic search algorithm for scheduling
flexible manufacturing systems, in Proceedings of 1996 IEEE
international conference on
robotics and automation, Minneapolis, MN, April, pp. 2793–
2797.
Yun, Y.S. and Gen, M., 2002. Advanced scheduling problem
using constraint
programming techniques in SCM environment. Computers and
Industrial Engineering, 43,
213–229.
Zhou, M.C. and Venkatesh, K., 1999. Modeling, simulation, and
control of flexible manufacturing
systems: a petri net approach. River Edge, NJ: World Scientific
Publishing Company.
1790 H. Lin et al.
Economica, 57. 485-93
Pattern of Trade between Underemployed Economies
By RAVEENDRA N . BATRA and HAMID BELADI
Southern Methodist University and University of Dayton
Final version received 6 September 1989. Accepted 13
December 1989.
In this paper, we have analysed the factors determining the
pattern of trade between
underemployed economics. We find, among other things, that a
iow-wage, iand-abundant
country exports the iand-using, labour-intensive product to a
high-wage, capital-abundant
country. We also find conditions under which a high-wage,
capital-rich country may export
the labour-iniensive product (the Leontief Paradox).
INTRODUCTION
The following facts should be kept in mind while formulating a
theory of a
country's pattern of trade.
1. The vast majority of trading countries have suffered from
chronic unemploy-
ment throughout this century. Even many developed economies
such as
the UK and USA experienced low to high unemployment during
the eariy
1920s, throughout the 1930s, at the end of the 1950s, during the
eariy 1960s
and throughout the 1970s and 1980s.
2. Some countries rich in natural resources export land-using
(or land-inten-
sive) products, whereas capital-abundant countries mostly
export capital-
intensive goods, but at times export the labour-intensive
products, some-
thing that has inspired the literature on the Leontief Paradox.
3. In spite of the presence of trade, the capital-rich countries
have higher
wages but lower capital rentals than the labour-surplus and/or
land-rich
countries—a fact conflicting with the factor-price equalization
theorems of
the popular Heckscher-Ohlin model.
4. Labour-rich countries usually export either labour-intensive
or iand-using
commodities.
The purpose of this paper is to formulate a theory of trade that
explains
the 'stylized facts" mentioned above. Neither of the two popular
theories, the
Ricardian model and the Heckscher-Ohlin model, is compatible
with these
facts. Both of these models ignore unemployment and are
couched in terms
of one or two factors, whereas a realistic theory of international
trade must
assume at least three factors—labour, capital and land (or
natural resources)—
which have been incorporated into the empirical literature but
not into a theory
of trade patterns.
In order to explain the pattern of trade, we first construct a two-
sector,
three-factor mode! of an underemployed economy. We find that
the specific-
factor model, which has recently regained its lost popularity, is
ideal to
capturing the facts mentioned above.
L ASSUMPTIONS AND THE MODEL
Let us assume that there are two sectors, X and Y, with X using
capital and
labour and Y using capital, labour and land. (X could represent
all manufactur-
ing where land is relatively insignificant, and Y could represent
agriculture,
486 ECONOMICA [NOVEMBER
mining, forestry and fisheries. I Production functions are
linearly homogeneous;
producers face perfect markets in goods, capital and land, but
not in labour,
where real wage is rigid, causing general unemployment in the
economy.
Capital and labour are fully mobile and employed, and all
factors are in
inelastic supply. In short, we make all the assumptions of the
well-known
two-sector, specific-sector model, except that the real wage is
determined
institutionally."
Let Cij be the ratio of the ith factor and thejth product {i = K, U
^ and
j = x,y) where K is capital, L is labour and V is land. With full
employment
of capita] and land, we have
(1) CK.x + C K , y = ^
and
(2) CvvV'= v;
where K and V are inelastic supplies of capital and land. With
producers
producing in perfect markets, the price of each product equals
the unit cost.
Let Y be the numeraire, so that its price equals one, F be the
relative price
of X, w be the real wage rate, r the real rental of capital and p
the real rental
of land. Then
(3) wC
and
(4) H-C, ,
With linearly homogeneous production functions, each input-
output
coefficient depends only on factor prices. Therefore
(5)
and
With this equation, the production side of our model is
complete. This is a
system of nine variables (X, Y, C:,, C , r and p), nine equations
and four
parameters (w, P, K and V).
II. THE FACTOR-PRICE DEFINITION OF FACTOR
ABUNDANCE
Let us assume that there are two countries, a home country (H)
and a foreign
country (F). Since labour is in excess supply in both countries,
we will first
define relative factor abundance in terms of fully utilized
factors. Suppose the
home country is rich in capital but poor in land relative to the
foreign country.
Then we define H to be capital-abundant and F to be land-
abundant if, in the
absence of trade,
(7)
In other words, in the absence of trade, the capital-rich country
has a higher
rental of land relative to that of capital than does the foreign
country. What
1990] PATTERN OF TRADE BETWEEN UNDEREMPLOYED
ECONOMIES 487
about the wage rate? Since usually the capital-rich countries are
high-wage
economies, we assume that
(8) Wft s wj.
In order to use (7) and (S) in our analysis, we need to analyse
the
relationship between factor and commodity prices. Totally
differentiating (3)
and (4), we obtain
(9)
and
( 1 0) d^yW* + dKyr* + Bvyp* = 0
where the asterisk denotes proportional change and $ are the
factor shares.^
Thus, r* = (dr/r) and so on. From (9) and (10), we obtain
- - « . ^ W (
and
In obtaining (11)-(13), we have made use of the fact that factor
shares add
to one. Thus,
Equation (13) shows the effect of P and w on the factor-price
ratio {pi r), as
( p * - r * ) / P * < 0 . For any given w, a rise in P
unambiguously causes a fall in
ip/r), whereas for any P, a rise in w causes a rise in (p/r),
provided 6i_^> Oi^y.
Since w is constant, a rise in P, the relative price of X, must
cause a rise in r,
otherwise average cost in X will not rise; but since Py = 1 is
constant, p must
fall, because with w given, r and p must move opposite to each
other. Otherwise
average cost in Y will not remain constant. On the other hand,
for any P, a
rise in w must cause a fall in r in X and hence in Y as well.
Since w rises and
r falls, the reward of land depends on the labour intensity of Y
relative to X.
If 0Ky0Lx > ^Lv^Kxy then in the physical sense X is labour-
intensive relative to
Y, and ( P * / R ' * ) > 0 . When the capital-labour ratio in X
and Y is the same,
then a rise in w combined with a fall in r equally affects the unit
cost in Y
which is compatible with the fact that P,, is unchanged at one.
However, if Y
is capital-intensive relative to X, then the relative unit cost in Y
falls, and for
its price to remain constant p must rise. Thus, when
then
( P * / H ' * ) > 0 .
On the other hand, when labour share is higher in Y, so that
0LX < ^LV, a rise
in w hurts Y more than X. Here (p/r) must fall as w rises (see
(13)).
488 ECONOMICA [NOVEMBER
The two forces that affect (p/r) are thus P and w, but not factor
supplies.
Figure 1 displays these relationships. The negatively sloped
curve AB shows
that as P rises ip/r) falls for any w. Then as w rises, the curve
AB shifts up
to CD (where di^ > 0^.), or down to EF (where Bu < ^/.y).
The relationships obtained in Figure 1 can be used to analyse
the effect of
factor endowments on the pattern of trade. Let us assume that
production
functions are the same between the two countries. (This is also
an assumption
of the Heckscher-Ohlin (H-0) theory.) For the time being, let us
also assume
that the wage rates are the same as well; that is, ŵ = w,. Under
these assump-
tions, the same relationship between the factor-price ratio and
the commodity-
price ratio applies lo both countries. Let FH be such a common
curve in
Figure 2. Since the home country is relatively capital-abundant,
its factor-price
ratio (p/r) is placed above the factor-price ratio of the foreign
country
(see (7)). As a result,
(14) P,<P^,
which shows that under autarky the home price of X is lower
relative to that
in the foreign country. This means that, in the presence of non-
intersecting
social indifference curves (which we assume hereafter), the
home country will
export X and the foreign country will expon Y, the land-using
product.' The
following theorem is now immediate.
F
FIGURE I
p/r
Ux
FlQURE 2
1990] PATTERN OF TRADE BETWEEN UNDEREMPLOYED
ECONOMIES 489
Theorem 1. If the institutionally determined real wages between
the two
countries are close to each other, then the country relatively
well endowed in
land or natural resources exports the land-using product, and the
relatively
capital-rich country exports the other product.
Note that this is a very general theorem, and factor intensities
play no role
in it. This may explain the trade pattern of most oil-exporting
countries, such
as Saudi Arabia, Kuwait, United Arab Emirates, Mexico,
Venezuela, etc.,
which are rich in oil and export this product abroad. Other
countries, such as
Canada, Australia and some Third World countries, export
minerals for the
same reason. Furthermore, it should be noted that the rigid wage
rate may be
'too low' and the country may have to import labour from
abroad. Thus, the
model may also refer to trade between the Arab countries and
the West. Many
of the Arab countries in fact import labour from Asian
countries.
Let us now relax our assumption of similar wage rates between
the trading
partners and assume that the capital-rich country has the higher
real wage
than the land-rich country. If the labour share of the two sectors
is the same,
i.e. if L
̂ x = ^Ly., then w has no effect on (p/r). In this case.
Theorem 1 continues
to hold regardless of the inter-country wage differential.
In most countries the land-using sectors, especially agriculture
and fisheries,
also employ larger number of workers per unit of output than
the other sector.
This is certainly true of developing countries, but may also be
valid with some
developed economies. It is interesting to note that the autarkic
values of (p/r)
depends not only on the levels of endowments of different
factors but also on
the level of the given wage rate. This is clear from equation
(13), where {p/r)
is seen to depend on w and P. The endowment effect in this case
is via the
relative price, P. In other words, even if two countries are
endowed with the
same amounts of the various factors, ip/r) can have different
values in
the two countries. Let us then assume that Bt^y> fl^v Here a
rise in w reduces
{p/r) at any P. If w^ > w^, then the home country's curve
relating {p/r) and
P will lie below FH in Figure 2. Suppose it is given by hh',
whereas in the
foreign country this relationship is still given by FH. Then the
home autarky-
price ratio is given by PJ,. Since it is even smaller than before,
we conclude
that the home country will still import the land-using product
and the foreign
country will export it. All this leads to the following theorem.
Theorem 2. A relatively low-wage, land-abundant country
exports the land-
using product if the latter's labour share is no less than the
labour share of
the other product, which in turn is exported by the relatively
high-wage,
capital-abundant country.
What is the role of the factor intensities in this theorem? Factor
intensities
can be defined in the physical sense or in the value sense. In the
value sense,
the factor intensities can be defined in terms of factor shares.
Thus, Y may be
said to be labour-intensive relative to X if ff^. > L
̂ X- But this
implies that
or
490 ECONOMICA [NOVEMBER
(p/r)
Therefore, if Bi_v > Bi_^, then ê x > B^y, which means that X
is capital-intensive
relative to Y in the value sense. In terms of Theorem 2, a high-
wage, capital-
abundant country exports X when fl^ > L
̂ X or &K,. <^KJC-
Theorem 2 then
implies that a high-wage, capjtal-rich country exports the
capital-intensive
product.
On the other hand, a low-wage country may also be defined as a
labour-
abundant country. Thus, a land-abundant country with lower
real wage may
be said to be a labour-abundant country with lower real wage
may be said to
be a labour-abundant country as well. Theorem 2 then implies
also that a
labour-rich country exports the labour-intensive product, as
Biy> Bj^^. AM this
leads to another theorem.
Theorem 3. A high-wage, capital-abundant country exports the
capital-inten-
sive product, and a low-wage, land- and labour-abundant
country exports the
land-using, labour-intensive product.
This theorem is somewhat reminiscent of the Heckscher-Ohlin
theorem
which highlights the role of factor intensities and inter-country
factor
endowments.
What happens if the land-using product is not labour-intensive
in the value
sense, so that 0^ < ^L. ? Here Theorem 3 may not hold, in
which case the
well-known Leontief Paradox can occur*
If ^L.<^tA, then from (13). {p/r) rises with a rise in w. This
case is
illustrated in Figure 3, where, unlike in Figure 2, hh' lies above
FH., and the
home-autarky price ratio may or may not be below the foreign-
autarky price
ratio. Figure 3 illustrates the case where Ph<P,, so that the high-
wage,
capital-abundant home country will stilt export X but X is now
the labour-
intensive product. Similarly, the low-wage, land-abundant
country exports Y,
which is capital-intensive relative to X. This is the Leontief
Paradox.
Thus, our model, which yields a Heckscher-Ohlin type of
theorem, is also
capable of explaining the Leontief Paradox.
III. FACTOR PRICES UNDER FREE TRADE
Under free trade, the Heckscher-Ohlin theorem gives rise to a
single outcome,
namely that absolute and relative factor rewards are completely
equalized
1990] PATTERN OF TRADE BETWEEN UNDEREMPLOYED
ECONOMIES 491
between countries. This is one of the most serious flaws of this
theorem,
because we live in a trading world where factor prices are far
from equal.
In our model, however, a variety of outcomes is possible in the
free trade
equilibrium. Let us first consider the least likely outcome.
Suppose, in the
absence of trade, that real wages are the same internationally. In
this case one
common FH curve applies to both countries in Figure 4. Assume
that transport
costs are zero or negligible; then the same product-price ratio
prevails in both
countries in the free trade equilibrium. Let Pg be such a price
ratio. When FH
applies to both countries, then {p/r) is the same in both
countries in the free
trade equilibrium. This is the case where the absolute factor
prices will also
be equalized. Even if wages differ between H and F, the FH
curve applies to
both countries if 0,^ = 6i^,.. In this case (p/r) will be similar
internationally
but absolute factor prices will differ. Since iv̂ > w,, r,, < rj.
This is because r
and w are negatively related. And since {p/r)h = {p/r)f, then
Ph<pf- Thus,
here is a case where relative factor prices of land and capital are
globally
equal but absolute factor prices are not. All this leads to the
following theorem.
Theorem 4. If wages are the same across the countries, then free
trade leads
to an equalization of all factor prices. If the capital-abundant
country is the
high-wage country but labour shares are the same between the
two sectors,
then the relative factor prices of land and capital are equalized
but the capital
rental and the land rent are lower in the capital-abundant
country than in the
land-abundant country.
When SL^ < 6i_y and w>, > w,, much of Theorem 4 continues
to be valid,
although relative factor prices of land and capital in H and F are
no longer
the same. In this case, the home curve representing the
relationship between
ip/r) and P lies below FH, which now represents F. In Figure 4,
the home
curve is now given by hh and in free trade equilibrium, {p/ r)h
is given by OA
which lies below (p/r)^, the factor-price ratio in F. Still, when
w^ > Wf, r,, < Tf.
This is because, from (11), it is clear that
(15) r = r{P,w)
with Tp = {dr/dP) > 0 and r^. = (dr/dw) < 0, for all values of 0^.
and Ot,.. Thus,
with H';, > Wf, rf<r,. Since (p/r),, <ip/r)j in free trade, clearly
Pf<pi, in the
free trade equilibrium.
p/r
B
p/f).
A
F
s
V
 ^ ^ ^
 .
* 
FIGURE 4
492 ECONOMICA [NOVEMBER
When ^L, > di_y, the home curve (h'h') now lies above FH in
Figure 4. In
the free trade equilibrium,
(16) {plr),>{pfr)f,
but since ŵ > ny, ^s'^^s-'" view of (16), however, p/may no
longer be lower
than ph under free trade. The following theorem is now
immediate.
Theorem 5. Under free trade, the high-wage, capital-rich
country has a lower
rental of capital than the low-wage country, but the
international relationship
of the land rental depends on factor intensities.
IV. TRADE AND FACTOR PRICES
In the Heckseher-Ohlin model, trade benefits the country's
abundant factor
but hurts its relatively scarce factor. In our model, assuming
that the land-
abundant country exports the land-using product and the
capital-abundant
country exports the other product (which is ensured when 0(.,.
^^(_J, trade
will lower the reward of land and raise the reward of capital in
the home
country, and do the opposite in the foreign country. This is
because in this
case, under autarky, P^ < P,. Therefore, in the presence of
profitable trade,
the relative price of X rises in the home country and falls in the
foreign country.
Consequently r will rise in H but fall in F, and p will fall in H
and rise in F.
TTie following theorem is now immediate.
Theorem 6. When the labour share in the land-using sector is no
lower than
that in the other sector, trade benefits a country's abundant
factor and hurts
the scarce factor.''
It should be noted that Theorem 6 may not be valid if 6^^ >
Bi_y.
V. CONCLUSIONS
Using a two-sector, three-factor model in which land is a
specific factor and
wages are institutionally determined, we have analysed the
factors determining
the pattern of trade between underemployed economies. Our
results are com-
patible with many observed facts. Under the assumptions
usually used in the
H-0 model, we find that a low-wage, land-abundant country
exports the
land-using, labour-intensive product to a high-wage, capital-
abundant country.
On the other hand, if the low-wage country is said to be labour-
abundant,
then a labour-abundant country exports the land-using, labour-
intensive
good and the capital-rich country exports the capital-intensive
good. This is
nothing but a version of the Heckscher-Ohlin theorem derived
in a model
of unemployment.
The paper also derives plausible conditions under which a high-
wage,
capital-rich country may export the labour-intensive product.
This tends to
explain the Leontief Paradox.
Under free trade, if wages are the same across countries, all
factor prices
are equalized. However, if the capital-abundant country is a
high-wage country,
then the reward of capital is higher in the low-wage country
even under free
trade. Thus, unlike the Heckscher-Ohlin model, a variety of
outcomes regard-
ing factor prices in free trade is possible in our model.
1 9 9 0 ] PATTERN OF TRADE BETWEEN
UNDEREMPLOYED ECONOMIES 4 9 3
Finally, we conclude that under realistic conditions trade
benefits the
country's relatively abundant factor and hurts its relatively
scarce factor.*
ACKNOWLEDGMENT
We wish to thank two anonymous referees for helpful comments
to a previous draft
of this paper.
NOTES
1. The earlier trade models of rigid wages have mainly involved
the two-sector, two-factor
Heckscher-Ohlin type of model; see e.g. Das (1981). Yu {1982)
and BhandaH (1986). The
main weakness of this type of model is that it leads to a linear
transformation curve or constant
average costs in the industries. The production side thus yields
limited and unrealistic results.
In an earlier paper (1988), Batra and Beladi have shown that,
even with rigid real wages, the
specilic*factor model used here generates increasing average
cost functions for the two indus-
tries. The input-output coefficient lechnique utilized here
greatly simplifies the analysis. For
another application of this technique, see Lahfri (1983).
2. In obtaining these equations, it must be noted that the
competitive producer, facing given
factor prices, equates the derivative of this unit cost to zero,
thereby minimizing his average
cost. Thus,
^y + n/Q,, + pdCvy = dAC, = 0
where 4 C , is the average cost of Y. Similarly for X.
3. In order to see the importance of this assumption in the
context of the factor-price definition
of factor abundance and the Heckscher-Ohlin theorem, see Batra
{1973, Chapter 3).
4. For the latest analysis of the Leontief Paradox, see Casas and
Choi (1985).
5. See Pattanaik (1974) for an application of this type of
analysis to the effects on savings in a
developing economy.
6. In this paper we have ignored [he well-known physical
definition of international factor
abundance, and have focused only on the factor-price definition.
This is because labour is not
fully employed and does not act as a constraint on the two
outputs. However, a physical type
of definition does suggest itself. We could define country H to
be capital-abundant and country
F to be labour-abundant, if
with
By using a fully fledged production model constructed by the
authors elsewhere (1988), it is
possible to show thai ail our results are valid in terms of the
physical definition as well. In the
interest of brevity, however, we leave this task to the reader.
REFERENCES
B A T R A , R. (1973). Studies in the Pure Theory of
International Trade. New York: St Martin's Press.
——and B E L A I J I , H . (1988). Specific factors,
unemployment and trade theory. WeUwirtschaftliches
Archiv, 124,435-43.
B H A N D A R I , J . S. (1986). Commercial Liberalization in
Less-Developed Countries. New York:
Praeger.
CASA.S, F. R. and C H O I , K, E . (1985). The Leontief
Paradox: continued or resolved. Journal of
Political Economy, 93, 610-15.
D A S , S. P, (1981). Effect of foreign investment in the
presence of unemployment. Journal of
International Economics. I I , 2 4 9 - 5 7 .
LAHtRi, S A J A L (1983). Capacity constraints, alternative
technologies and input-output analysis.
European Economic Review, 27, 147-53.
P A T T A N A I K , P. K. (1974). Trade, distribution and
saving. Journal of International Economics, 4,
77-81.
Yu, E D E N (1982). Unemployment and the theory of customs
union. Economic Journal, 92,399-404.
Copyright of American Economic Review is the property of
American Economic Association and its content
may not be copied or emailed to multiple sites or posted to a
listserv without the copyright holder's express
written permission. However, users may print, download, or
email articles for individual use.
How Does the Global Economic Environment Influence
the Demand for IMF Resources?
SELIM ELEKDA�
The main objective of this paper is to quantify the relationship
between the
global economic environment and Stand-By Arrangements
(SBAs) with the
IMF. The results suggest that oil prices, world interest rates,
and the global
business cycle are the most influential indicators that affect the
number of SBAs
being requested. In addition, the empirical model seems to have
reasonable
accuracy when predicting SBAs. Furthermore, when oil prices,
interest rates,
and the global business cycle are adversely shocked by one
standard deviation,
the conditional probability of an SBA nearly doubles, implying
an increase from
about 6 to 12 SBAs. More critically, the model suggests that
even a steady
deterioration of the global economic climate would imply
increasingly harsher
conditions for developing and emerging market countries, which
may in turn
increase the demand for IMF resources significantly. [JEL F01,
F33, F34, F42]
IMF Staff Papers (2008) 55, 624–653.
doi:10.1057/imfsp.2008.4;
published online 17 June 2008
Considering the favorable global economic environment over
the pastfew years, it is probably not much of a surprise that the
number of
IMF arrangements approved recently is well below historical
averages. But
what—if any—is the link between global economic and
financing conditions
and a country’s potential request for IMF financial assistance?
The main
�
Selim Elekdağ is an economist with the IMF Research
Department. The author is
particularly indebted to Bob Flood, Rex Ghosh, Bikas Joshi,
Ayhan Kose, Alan MacArthur,
Gian Maria Milesi-Ferretti, Alex Pitt, Bjorn Rother, and Juan
Zalduendo for their support
and helpful suggestions.
IMF Staff Papers
Vol. 55, No. 4
& 2008 International Monetary Fund
624
objective of this paper is to rigorously quantify the relationship
between the
global economic environment and the number of Stand-By
Arrangements
(SBAs).
Formal econometric analysis is required to quantify the
relationship
between global economic conditions and the potential demand
for SBAs.
Using panel data techniques, this paper reports results based on
412 SBAs
among 169 members over a period spanning 1970–2004. We
focus on
SBAs because they are the main nonconcessional IMF facility
designed to
provide short-term balance of payments (BOP) assistance to
members.
1
Global activity and liquidity indicators as well as country-
specific factors
were used to identify determinants influencing the number of
SBAs. The
three main global factors affecting the probability of requesting
IMF
financial assistance were found to be oil prices, world interest
rates, and
the global business cycle. The most important country-specific
factors
identified include the member’s real GDP growth, the
depreciation of its
currency vis-à-vis the U.S. dollar, its international reserve
cover, and whether
or not it is an energy exporter. The estimates are robust to
changes in model
specification, as well as choice of global and country-specific
explanatory
variables.
Changes in global economic conditions significantly affect the
probability
of a country’s demand for IMF resources. A scenario in which
the three
global factors are adversely shocked from their respective
averages by one
standard deviation nearly doubles the conditional probability of
an SBA.
Furthermore, when oil prices and interest rates are evaluated at
their
respective historical peaks, and the global business cycle is set
at its deepest
trough in the sample, the conditional probability almost
quadruples to about
14 percent, implying an increase from approximately 6 to 23
SBAs.
The results are intuitive and consistent with economic theory.
Among
other things, a rise in world interest rates may increase a
member’s debt
service costs and limit access to capital markets, higher oil
prices would raise
the import bill (for net oil importers), and a global recession
could decrease
international demand for a member’s exports. More critically,
even if global
economic conditions worsen gradually, the probability of an
approved SBA
increases disproportionately owing to the underlying nonlinear
nature of the
econometric model. Such adverse developments would cause a
deterioration
in a member’s current account balance and could lead to acute
BOP
problems. If a country does not have sufficient access to
international capital
markets, that member may request an IMF arrangement to
mitigate the
consequences of potentially severe macroeconomic adjustment.
The estimated regressions may also be used to predict the
numbers of
SBAs. There are indications that the framework has reasonable
predictive
accuracy. Whereas the actual number of SBAs approved in 2004
was 6, the
model predicts between 5 and 5.7 SBAs in 2004. Furthermore,
out-of-sample
1
See the earlier working paper version of this paper, Elekdağ
(2006).
DEMAND FOR IMF RESOURCES
625
predictions for 2005 ranged between 5.7 and 6.1, whereas the
actual number
of approved SBAs was also 6.
Despite the importance of this topic, research on the empirical
link
between global economic conditions and IMF financing is
scarce. In line with
the survey of Joyce (2004), only Bird and Rowlands (2002) and
Conway
(1994) included global economic factors—which was in both
cases only a
measure of world interest rates. In this context, this paper
builds on the
literature by emphasizing the importance of global economic
conditions and
is also the only study that finds a critical role of oil prices in
the demand for
IMF financial assistance. Even though (in contrast to Bird,
Hussain, and
Joyce, 2004; and Marchesi, 2003) Barro and Lee (2005); Joyce
(1992); and
Knight and Santaella (1997) include time dummies to control
for common
effects of external factors, these frameworks may not be well
suited for
prediction.
2
Further review of the literature also indicates that most of the
studies rely
on short sample periods and therefore miss important events,
including the
financial crises of the late 1990s. In fact, only Barro and Lee
(2005); Bird and
Rowlands (2001); Sturm, Berger, and de Haan (2005); and
Trudel (2005)
include a sample period through at least 2000. Furthermore, as
discussed in
detail below, the country coverage in this paper exceeds that in
other studies,
which could be critical to avoid econometric issues such as
selection bias.
Last, other than this paper, only Barro and Lee (2005) and
Oatley and
Yackee (2000) distinguish among the various types of IMF
facilities.
The results of this paper have relevance for the IMF, for
policymakers
throughout the IMF membership, and for capital market
analysts. The
framework developed in this paper underscores cyclical factors
that are
relevant for future IMF lending capacity. This is especially
important
because unusually harsh economic conditions would likely
imply a bunching
of SBA requests—some of which may be exceptional access
cases. In this
context, this paper is also pertinent for assessing the prospects
for the IMF’s
future income position, which depends on the amount of IMF
credit
outstanding.
I. IMF Arrangements from 1970 to 2004
The IMF is best known as a financial institution that provides
resources to
member countries experiencing temporary BOP problems. The
IMF makes
financial resources available to members in the general
resources account
under a range of policies and facilities, including credit
tranches. More than a
decade after its creation, the IMF developed policies on the use
of its
resources in what came to be known as credit tranches. SBAs
were developed
as the main instrument through which members would access
the credit
2
For example, Barro and Lee (2005) partition their sample into
five 5-year periods,
whereas Knight and Santaella (1997) use an indicator variable
that takes the value of unity
from 1979 to 1991 when using a sample spanning only 1973–91.
Selim Elekdağ
626
tranches, and are available for any BOP need. Access under
SBAs is limited
to 100 percent of quota annually and 300 percent of quota
cumulatively,
although in exceptional circumstances access beyond these
limits has been
granted.
Although the IMF has used a variety of instruments to support
members’
BOP needs, the most utilized facility is the SBA. Figure 1
depicts the number
of SBAs, Extended Fund Facilities (EFFs), first credit tranche
arrangements
(FCTAs), and concessional facilities (the Structural Adjustment
Facility,
Enhanced Structural Adjustment Facility, and Poverty
Reduction and
Growth Facility) against the backdrop of the IMF membership.
3
Table 1
provides the distribution of facilities across selected time
periods. Even
though SBAs historically outnumber other facilities,
concessional IMF
financing is increasing in importance. Although not shown,
during the past
decade exceptional access (especially in response to financial
crises) and
precautionary arrangements have gained prominence, whereas
blended
arrangements have been approved much less frequently.
4
Against this
Figure 1. Facilities and IMF Members
0
5
10
15
20
25
30
35
40
1970 1972 1974 1976 1978 1980 1982 1984 1986 1988 1990
1992 1994 1996 1998 2000 2002 2004
0
20
40
60
80
100
120
140
160
180
200
SBAs (left scale) EFFs (left scale)
FCTAs (left scale) SAF, ESAF, and PRGFs (left scale)
Members (right scale)
Source: IMF, Policy Development and Review Department
database.
Note: SBA¼Stand-By Arrangement; EFF¼Extended Fund
Facility; FCTA¼First Credit
Tranche Arrangement; SAF¼Structural Adjustment Facility;
ESAF¼Enhanced Structural
Adjustment Facility; PRGF¼Poverty Reduction and Growth
Facility.
3
Appendix I in the working paper version of this paper provides
further details on IMF
policies and facilities, including the various arrangements used
to access IMF credit. See
Elekdağ (2006).
4
The 412 SBAs identified during 1970–2004 do not include
blended arrangements.
DEMAND FOR IMF RESOURCES
627
background, we explore below how global economic and
financial
developments affect the potential demand for IMF resources.
II. Indicators of the Global Economic Environment
Determinants of the global economic environment can broadly
be grouped
into activity and liquidity indicators. Controlling for country-
specific policies
and developments, the main conjecture of this paper is that
world interest
rates, oil prices, and the global business cycle are the most
robust indicators
of the global economic environment that influence the demand
for IMF
financial resources.
5
Interest Rates
Shown in Figure 2 is the U.S. federal funds rate adjusted by
U.S. consumer
price index (CPI) inflation against the backdrop of SBAs during
1970–2004.
Note that with the onset of the Volker disinflation in the early
1980s, both the
real federal funds rate and the number of SBAs reach their
historic peaks.
The parallel movements between SBAs and the interest rate in
the early 1990s
are also noteworthy.
Table 1. IMF Arrangements, 1970–2004
Total 1970–79 1980–89 1990–99 2000–04 1995–2004
Approved 739 166 243 238 92 212
GRA 556 166 195 154 41 114
SBAs 412 93 153 126 40 95
FCTAs 79 62 15 2 0 1
EFFs 65 11 27 26 1 18
SAFs, ESAFs, and PRGFs 183 0 48 84 51 98
Blended arrangements 33 0 25 7 1 4
Source: IMF, Policy Development and Review Department
Stand-By Operations Division
database.
Note: SBA=Stand-By Arrangement; FCTA=first credit tranche
arrangement;
EFF=Extended Fund Facility; SAF=Structural Adjustment
Facility; ESAF=Enhanced
Structural Adjustment Facility; PRGF=Poverty Reduction and
Growth Facility;
GRA=General Resource Account. Approved refers to the total
number of arrangements
approved in the year under consideration. Blended arrangements
are concessional
arrangements (SAF, ESAF, PRGF) combined with an EFF or
SBA to supplement IMF
financial assistance to a member.
5
Appendix Table 3 in the working paper version of this paper
contains a comprehensive
description of the data. See Elekdağ (2006).
Selim Elekdağ
628
Oil Prices
The monthly nominal and real average petroleum spot prices
(APSP) are
displayed in Figure 3.
6
Even though nominal oil prices have reached record
levels, prices adjusted for inflation are still below the peaks of
the late 1970s.
Against the background of SBAs, Figure 4 shows the real APSP
as a
deviation from trend.
7
Note that with the rise in oil prices, there is a trend
increase in SBAs from the mid-1970s until the early 1980s.
With the spike in
oil prices in 1979, the number of approved SBAs more than
doubles,
increasing from 8 in 1978 to 20 in 1979. It is also worth
highlighting how oil
prices and SBAs move in tandem during the 1990s. With the
gradual decline
in the APSP in the mid-1990s, the number of SBAs decreased
from 21 in 1995
to 5 in 1998.
Figure 2. Interest Rates and Stand-By Arrangements
0
5
10
15
20
25
30
35
1970 1972 1974 1976 1978 1980 1982 1984 1986 1988 1990
1992 1994 1996 1998 2000 2002 2004
-4
-2
0
2
4
6
8
Stand-By Arrangements (left scale)
U.S. real short-term interest rate (right scale)
Sources: IMF, World Economic Outlook and Policy
Development and Review Department
databases; and author’s calculations.
Note: Real U.S. short-term interest rate is calculated by
subtracting U.S. CPI inflation from the
federal funds rate.
6
The APSP is calculated using a simple average of U.K. Brent,
West Texas Intermediate,
and Dubai Fateh spot petroleum prices. The real APSP was
scaled using the U.S. CPI, because
world inflation is contaminated by episodes of hyperinflation.
7
To avoid running spurious regressions, the (log) real APSP is
detrended using a log-
linear trend to ensure stationarity of the real APSP. Deviations
from trend were used rather
than growth rate, for example, to capture the burden of
increased fuel costs more accurately.
Consider Figure 3, which shows that after the 1973 OPEC
shock, when oil prices roughly
tripled, prices did not revert to their original single-digit levels.
The first-differenced series
would not capture this persistence, whereas the linearly
detrended series does.
DEMAND FOR IMF RESOURCES
629
Figure 3. Monthly Average Petroleum Spot Price
(U.S. dollars per barrel)
0
10
20
30
40
50
60
70
80
90
1970M1 1972M5 1974M9 1977M1 1979M5 1981M9 1984M1
1986M5 1988M9 1991M1 1993M5 1995M9 1998M1 2000M5
2002M9
APSP
Real APSP
Sources: IMF, World Economic Outlook database; and author’s
calculations.
Note: APSP¼Average petroleum spot price. Real APSP is
calculated by scaling the APSP by
the U.S. CPI.
Figure 4. Oil Prices and Stand-By Arrangements
0
5
10
15
20
25
30
35
1970 1972 1974 1976 1978 1980 1982 1984 1986 1988 1990
1992 1994 1996 1998 2000 2002 2004
-150
-100
-50
0
50
100
150
Stand-By Arrangements (left scale)
Real Oil Prices (right scale)
Sources: IMF, World Economic Outlook and Policy
Development and Review Department
databases; and author’s calculations.
Note: Real oil prices represented as the deviation from linear
trend, in which average petroleum
spot price (APSP) is calculated by scaling the APSP by U.S.
CPI.
Selim Elekdağ
630
Global Business Cycle
As the main measure of the global business cycle, the deviation
of the
logarithm of real-world GDP from trend is used.
8
Figure 5 displays the
global business cycle with the number of SBAs as the backdrop.
Note that
the two global recessions in the early 1980s and 1990s
correspond to the two
peaks in the number of SBAs approved during 1970–2004.
These figures
provide casual evidence in favor of a link between the global
economic
environment and SBAs, but formal econometric analysis is
required for a
rigorous assessment.
III. Methodology
The objective of this section is to describe the analytical
structure
underpinning the econometric analysis. After the discussion of a
conceptual framework, the section proceeds to discuss the key
determinants that influence the approval of SBAs.
Conceptual Framework
As discussed in Mussa and Savastano (1999), a typical IMF-
supported
program begins with an explicit request from a member. Then
the IMF staff
prepares a blueprint of a program to be used as a basis for
negotiations
between a member’s authorities and the IMF staff. When an
agreement has
been reached, the arrangement has to be cleared by IMF
management and
approved by the IMF Executive Board. This potentially iterative
process
demonstrates how IMF-supported programs depend on joint
decision
making. Using language in line with Knight and Santaella
(1997), a
member’s ‘‘demand’’ for an arrangement, and the IMF’s
‘‘supply’’
(willingness to approve one) are both necessary components of
the process.
9
Most of the literature on IMF arrangements has investigated—
using
binary choice models—the determinants of either participation
in IMF
programs or of program approval in a certain year. Notable
examples of the
former include Joyce (1992); Conway (1994); Vreeland (2004);
and Cerutti
(2007); examples in the latter group of papers include
Przeworski and
Vreeland (2000); Bird and Rowlands (2001); and Barro and Lee
(2005). In
contrast to these studies, Knight and Santaella (1997) explicitly
jointly model
the ‘‘demand’’ and ‘‘supply’’ determinants of IMF program
approval using a
bivariate probit specification. However, they find that a
univariate
specification—which they interpret as a reduced-form demand-
supply
8
The log-linear trend implies an annual real global growth rate of
about 3.4 percent.
9
As emphasized by Cerutti (2007), a similar joint decision
process continues throughout
the life of an arrangement, with the amounts that are finally
drawn while the program is on
track determined in such a manner.
DEMAND FOR IMF RESOURCES
631
model—is superior to the bivariate model.
10
In particular, Knight and
Santaella find that the univariate model predicts the approval of
a financial
arrangement more accurately than the bivariate specification.
11
Therefore,
based on Knight and Santaella, the joint determinants of an SBA
are
modeled using a univariate probit model.
However, the estimation strategy used to uncover the empirical
relationships between global economic conditions and IMF
credit is also
based on two other broad strands of research. The first, based
on
Albuquerque, Loayza, and Servén (2005), uses two sets of
explanatory
variables: global and country-specific. The global variables are
indicators of
the world economic and financial climate, whereas the country-
specific
variables control—among other things—for domestic policies
and
idiosyncratic shocks.
12
The second strand, building on the vast literature
on early warning systems and financial crisis prediction—as
summarized by
Berg, Borensztein, and Pattillo (2004)—regresses a binary
independent
Figure 5. The Global Business Cycle and Stand-By
Arrangements
0
5
10
15
20
25
30
35
1970 1972 1974 1976 1978 1980 1982 1984 1986 1988 1990
1992 1994 1996 1998 2000 2002 2004
-5
-4
-3
-2
-1
0
1
2
3
4
5
Stand-By Arrangements (left scale)
Real world GDP growth (right scale)
Sources: IMF, World Economic Outlook database and author’s
calculations.
Note: Real world GDP measured as the deviation of real world
GDP from a linear trend.
10
One reason may be that many variables that enter the demand
side—for example, BOP
need—are likely to enter the supply side (the IMF’s willingness
to meet that need), thus
complicating the separate identification of the demand and
supply curves.
11
Furthermore, Conway (1994) finds that Tobit and probit
specifications yield similar
results.
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx
Confirmations and ContradictionsThe Leontief Paradox, Reco.docx

More Related Content

Similar to Confirmations and ContradictionsThe Leontief Paradox, Reco.docx

Running head (NAME OF THE COMPANY)’S IT PROJECT(NAME OF THE C.docx
Running head (NAME OF THE COMPANY)’S IT PROJECT(NAME OF THE C.docxRunning head (NAME OF THE COMPANY)’S IT PROJECT(NAME OF THE C.docx
Running head (NAME OF THE COMPANY)’S IT PROJECT(NAME OF THE C.docx
healdkathaleen
 
Business Model and Strategic Planning OutlineI. Title Page.docx
Business Model and Strategic Planning OutlineI. Title Page.docxBusiness Model and Strategic Planning OutlineI. Title Page.docx
Business Model and Strategic Planning OutlineI. Title Page.docx
humphrieskalyn
 
Project 2  Tool AnalysisDonetello KelleyBMGT .docx
Project 2  Tool AnalysisDonetello KelleyBMGT .docxProject 2  Tool AnalysisDonetello KelleyBMGT .docx
Project 2  Tool AnalysisDonetello KelleyBMGT .docx
stilliegeorgiana
 
Topic Employee DiscriminationYou are an IO Consultant prepar.docx
Topic Employee DiscriminationYou are an IO Consultant prepar.docxTopic Employee DiscriminationYou are an IO Consultant prepar.docx
Topic Employee DiscriminationYou are an IO Consultant prepar.docx
edwardmarivel
 
InstructionsPurposeThis project is the second of four projec.docx
InstructionsPurposeThis project is the second of four projec.docxInstructionsPurposeThis project is the second of four projec.docx
InstructionsPurposeThis project is the second of four projec.docx
LaticiaGrissomzz
 
FASB Ongoing ProjectThe mission of the Financial Accounting Sta.docx
FASB Ongoing ProjectThe mission of the Financial Accounting Sta.docxFASB Ongoing ProjectThe mission of the Financial Accounting Sta.docx
FASB Ongoing ProjectThe mission of the Financial Accounting Sta.docx
mydrynan
 
For this two-part assessment, you will create an Excel spreadsheet o.docx
For this two-part assessment, you will create an Excel spreadsheet o.docxFor this two-part assessment, you will create an Excel spreadsheet o.docx
For this two-part assessment, you will create an Excel spreadsheet o.docx
mckellarhastings
 
Deductive vs Inductive ReasoningDeductive reasoning starts out w.docx
Deductive vs Inductive ReasoningDeductive reasoning starts out w.docxDeductive vs Inductive ReasoningDeductive reasoning starts out w.docx
Deductive vs Inductive ReasoningDeductive reasoning starts out w.docx
simonithomas47935
 
BUSA 2185 BUSINESS RESEARCHSpring 2019Research Project (Assig.docx
BUSA 2185 BUSINESS RESEARCHSpring 2019Research Project (Assig.docxBUSA 2185 BUSINESS RESEARCHSpring 2019Research Project (Assig.docx
BUSA 2185 BUSINESS RESEARCHSpring 2019Research Project (Assig.docx
felicidaddinwoodie
 
BUSI 505Final Project Overall Assignment InstructionsOverview
BUSI 505Final Project Overall Assignment InstructionsOverviewBUSI 505Final Project Overall Assignment InstructionsOverview
BUSI 505Final Project Overall Assignment InstructionsOverview
VannaSchrader3
 
ABCD Analysis As Research Methodology In Company Case Studies
ABCD Analysis As Research Methodology In Company Case StudiesABCD Analysis As Research Methodology In Company Case Studies
ABCD Analysis As Research Methodology In Company Case Studies
Amanda Summers
 
Group Management Concepts Analysis PaperPresentation(100 Points
Group Management Concepts Analysis PaperPresentation(100 PointsGroup Management Concepts Analysis PaperPresentation(100 Points
Group Management Concepts Analysis PaperPresentation(100 Points
ShainaBoling829
 
92315, 648 PMPage 1 of 3httpstlc.trident.educontent.docx
92315, 648 PMPage 1 of 3httpstlc.trident.educontent.docx92315, 648 PMPage 1 of 3httpstlc.trident.educontent.docx
92315, 648 PMPage 1 of 3httpstlc.trident.educontent.docx
evonnehoggarth79783
 
Basic Social Math - Research Proposal
Basic Social Math - Research ProposalBasic Social Math - Research Proposal
Basic Social Math - Research Proposal
Jared Lee Hanson
 
PAD 502 Organizational Dynamics Final Project – Learning As.docx
PAD 502 Organizational Dynamics Final Project – Learning As.docxPAD 502 Organizational Dynamics Final Project – Learning As.docx
PAD 502 Organizational Dynamics Final Project – Learning As.docx
gerardkortney
 

Similar to Confirmations and ContradictionsThe Leontief Paradox, Reco.docx (15)

Running head (NAME OF THE COMPANY)’S IT PROJECT(NAME OF THE C.docx
Running head (NAME OF THE COMPANY)’S IT PROJECT(NAME OF THE C.docxRunning head (NAME OF THE COMPANY)’S IT PROJECT(NAME OF THE C.docx
Running head (NAME OF THE COMPANY)’S IT PROJECT(NAME OF THE C.docx
 
Business Model and Strategic Planning OutlineI. Title Page.docx
Business Model and Strategic Planning OutlineI. Title Page.docxBusiness Model and Strategic Planning OutlineI. Title Page.docx
Business Model and Strategic Planning OutlineI. Title Page.docx
 
Project 2  Tool AnalysisDonetello KelleyBMGT .docx
Project 2  Tool AnalysisDonetello KelleyBMGT .docxProject 2  Tool AnalysisDonetello KelleyBMGT .docx
Project 2  Tool AnalysisDonetello KelleyBMGT .docx
 
Topic Employee DiscriminationYou are an IO Consultant prepar.docx
Topic Employee DiscriminationYou are an IO Consultant prepar.docxTopic Employee DiscriminationYou are an IO Consultant prepar.docx
Topic Employee DiscriminationYou are an IO Consultant prepar.docx
 
InstructionsPurposeThis project is the second of four projec.docx
InstructionsPurposeThis project is the second of four projec.docxInstructionsPurposeThis project is the second of four projec.docx
InstructionsPurposeThis project is the second of four projec.docx
 
FASB Ongoing ProjectThe mission of the Financial Accounting Sta.docx
FASB Ongoing ProjectThe mission of the Financial Accounting Sta.docxFASB Ongoing ProjectThe mission of the Financial Accounting Sta.docx
FASB Ongoing ProjectThe mission of the Financial Accounting Sta.docx
 
For this two-part assessment, you will create an Excel spreadsheet o.docx
For this two-part assessment, you will create an Excel spreadsheet o.docxFor this two-part assessment, you will create an Excel spreadsheet o.docx
For this two-part assessment, you will create an Excel spreadsheet o.docx
 
Deductive vs Inductive ReasoningDeductive reasoning starts out w.docx
Deductive vs Inductive ReasoningDeductive reasoning starts out w.docxDeductive vs Inductive ReasoningDeductive reasoning starts out w.docx
Deductive vs Inductive ReasoningDeductive reasoning starts out w.docx
 
BUSA 2185 BUSINESS RESEARCHSpring 2019Research Project (Assig.docx
BUSA 2185 BUSINESS RESEARCHSpring 2019Research Project (Assig.docxBUSA 2185 BUSINESS RESEARCHSpring 2019Research Project (Assig.docx
BUSA 2185 BUSINESS RESEARCHSpring 2019Research Project (Assig.docx
 
BUSI 505Final Project Overall Assignment InstructionsOverview
BUSI 505Final Project Overall Assignment InstructionsOverviewBUSI 505Final Project Overall Assignment InstructionsOverview
BUSI 505Final Project Overall Assignment InstructionsOverview
 
ABCD Analysis As Research Methodology In Company Case Studies
ABCD Analysis As Research Methodology In Company Case StudiesABCD Analysis As Research Methodology In Company Case Studies
ABCD Analysis As Research Methodology In Company Case Studies
 
Group Management Concepts Analysis PaperPresentation(100 Points
Group Management Concepts Analysis PaperPresentation(100 PointsGroup Management Concepts Analysis PaperPresentation(100 Points
Group Management Concepts Analysis PaperPresentation(100 Points
 
92315, 648 PMPage 1 of 3httpstlc.trident.educontent.docx
92315, 648 PMPage 1 of 3httpstlc.trident.educontent.docx92315, 648 PMPage 1 of 3httpstlc.trident.educontent.docx
92315, 648 PMPage 1 of 3httpstlc.trident.educontent.docx
 
Basic Social Math - Research Proposal
Basic Social Math - Research ProposalBasic Social Math - Research Proposal
Basic Social Math - Research Proposal
 
PAD 502 Organizational Dynamics Final Project – Learning As.docx
PAD 502 Organizational Dynamics Final Project – Learning As.docxPAD 502 Organizational Dynamics Final Project – Learning As.docx
PAD 502 Organizational Dynamics Final Project – Learning As.docx
 

More from maxinesmith73660

You have been chosen to present in front of your local governing boa.docx
You have been chosen to present in front of your local governing boa.docxYou have been chosen to present in front of your local governing boa.docx
You have been chosen to present in front of your local governing boa.docx
maxinesmith73660
 
You have been charged with overseeing the implementation of cybersec.docx
You have been charged with overseeing the implementation of cybersec.docxYou have been charged with overseeing the implementation of cybersec.docx
You have been charged with overseeing the implementation of cybersec.docx
maxinesmith73660
 
You have been commissioned to create a manual covering the installat.docx
You have been commissioned to create a manual covering the installat.docxYou have been commissioned to create a manual covering the installat.docx
You have been commissioned to create a manual covering the installat.docx
maxinesmith73660
 
You have been challenged by a mentor you respect and admire to demon.docx
You have been challenged by a mentor you respect and admire to demon.docxYou have been challenged by a mentor you respect and admire to demon.docx
You have been challenged by a mentor you respect and admire to demon.docx
maxinesmith73660
 
You have been chosen as the consultant group to assess the organizat.docx
You have been chosen as the consultant group to assess the organizat.docxYou have been chosen as the consultant group to assess the organizat.docx
You have been chosen as the consultant group to assess the organizat.docx
maxinesmith73660
 
You have been assigned a reading by WMF Petrie; Diospolis Parva (.docx
You have been assigned a reading by WMF Petrie; Diospolis Parva (.docxYou have been assigned a reading by WMF Petrie; Diospolis Parva (.docx
You have been assigned a reading by WMF Petrie; Diospolis Parva (.docx
maxinesmith73660
 
You have been asked to speak to city, municipal, and state elected a.docx
You have been asked to speak to city, municipal, and state elected a.docxYou have been asked to speak to city, municipal, and state elected a.docx
You have been asked to speak to city, municipal, and state elected a.docx
maxinesmith73660
 
You have been asked to provide a presentation, covering the history .docx
You have been asked to provide a presentation, covering the history .docxYou have been asked to provide a presentation, covering the history .docx
You have been asked to provide a presentation, covering the history .docx
maxinesmith73660
 
You have been asked to organize a community health fair at a loc.docx
You have been asked to organize a community health fair at a loc.docxYou have been asked to organize a community health fair at a loc.docx
You have been asked to organize a community health fair at a loc.docx
maxinesmith73660
 
You have been asked to explain the differences between certain categ.docx
You have been asked to explain the differences between certain categ.docxYou have been asked to explain the differences between certain categ.docx
You have been asked to explain the differences between certain categ.docx
maxinesmith73660
 
You have been asked to evaluate a 3-year-old child in your clinic.  .docx
You have been asked to evaluate a 3-year-old child in your clinic.  .docxYou have been asked to evaluate a 3-year-old child in your clinic.  .docx
You have been asked to evaluate a 3-year-old child in your clinic.  .docx
maxinesmith73660
 
You have been asked to develop UML diagrams to graphically depict .docx
You have been asked to develop UML diagrams to graphically depict .docxYou have been asked to develop UML diagrams to graphically depict .docx
You have been asked to develop UML diagrams to graphically depict .docx
maxinesmith73660
 
You have been asked to develop UML diagrams to graphically depict an.docx
You have been asked to develop UML diagrams to graphically depict an.docxYou have been asked to develop UML diagrams to graphically depict an.docx
You have been asked to develop UML diagrams to graphically depict an.docx
maxinesmith73660
 
You have been asked to develop a quality improvement (QI) process fo.docx
You have been asked to develop a quality improvement (QI) process fo.docxYou have been asked to develop a quality improvement (QI) process fo.docx
You have been asked to develop a quality improvement (QI) process fo.docx
maxinesmith73660
 
You have been asked to design and deliver a Microsoft PowerPoint pre.docx
You have been asked to design and deliver a Microsoft PowerPoint pre.docxYou have been asked to design and deliver a Microsoft PowerPoint pre.docx
You have been asked to design and deliver a Microsoft PowerPoint pre.docx
maxinesmith73660
 
You have been asked to be the project manager for the development of.docx
You have been asked to be the project manager for the development of.docxYou have been asked to be the project manager for the development of.docx
You have been asked to be the project manager for the development of.docx
maxinesmith73660
 
You have been asked to conduct research on a past forensic case to a.docx
You have been asked to conduct research on a past forensic case to a.docxYou have been asked to conduct research on a past forensic case to a.docx
You have been asked to conduct research on a past forensic case to a.docx
maxinesmith73660
 
You have been asked for the summary to include the following compone.docx
You have been asked for the summary to include the following compone.docxYou have been asked for the summary to include the following compone.docx
You have been asked for the summary to include the following compone.docx
maxinesmith73660
 
You have been asked to be the project manager for the developmen.docx
You have been asked to be the project manager for the developmen.docxYou have been asked to be the project manager for the developmen.docx
You have been asked to be the project manager for the developmen.docx
maxinesmith73660
 
You have been asked by management, as a senior member of your co.docx
You have been asked by management, as a senior member of your co.docxYou have been asked by management, as a senior member of your co.docx
You have been asked by management, as a senior member of your co.docx
maxinesmith73660
 

More from maxinesmith73660 (20)

You have been chosen to present in front of your local governing boa.docx
You have been chosen to present in front of your local governing boa.docxYou have been chosen to present in front of your local governing boa.docx
You have been chosen to present in front of your local governing boa.docx
 
You have been charged with overseeing the implementation of cybersec.docx
You have been charged with overseeing the implementation of cybersec.docxYou have been charged with overseeing the implementation of cybersec.docx
You have been charged with overseeing the implementation of cybersec.docx
 
You have been commissioned to create a manual covering the installat.docx
You have been commissioned to create a manual covering the installat.docxYou have been commissioned to create a manual covering the installat.docx
You have been commissioned to create a manual covering the installat.docx
 
You have been challenged by a mentor you respect and admire to demon.docx
You have been challenged by a mentor you respect and admire to demon.docxYou have been challenged by a mentor you respect and admire to demon.docx
You have been challenged by a mentor you respect and admire to demon.docx
 
You have been chosen as the consultant group to assess the organizat.docx
You have been chosen as the consultant group to assess the organizat.docxYou have been chosen as the consultant group to assess the organizat.docx
You have been chosen as the consultant group to assess the organizat.docx
 
You have been assigned a reading by WMF Petrie; Diospolis Parva (.docx
You have been assigned a reading by WMF Petrie; Diospolis Parva (.docxYou have been assigned a reading by WMF Petrie; Diospolis Parva (.docx
You have been assigned a reading by WMF Petrie; Diospolis Parva (.docx
 
You have been asked to speak to city, municipal, and state elected a.docx
You have been asked to speak to city, municipal, and state elected a.docxYou have been asked to speak to city, municipal, and state elected a.docx
You have been asked to speak to city, municipal, and state elected a.docx
 
You have been asked to provide a presentation, covering the history .docx
You have been asked to provide a presentation, covering the history .docxYou have been asked to provide a presentation, covering the history .docx
You have been asked to provide a presentation, covering the history .docx
 
You have been asked to organize a community health fair at a loc.docx
You have been asked to organize a community health fair at a loc.docxYou have been asked to organize a community health fair at a loc.docx
You have been asked to organize a community health fair at a loc.docx
 
You have been asked to explain the differences between certain categ.docx
You have been asked to explain the differences between certain categ.docxYou have been asked to explain the differences between certain categ.docx
You have been asked to explain the differences between certain categ.docx
 
You have been asked to evaluate a 3-year-old child in your clinic.  .docx
You have been asked to evaluate a 3-year-old child in your clinic.  .docxYou have been asked to evaluate a 3-year-old child in your clinic.  .docx
You have been asked to evaluate a 3-year-old child in your clinic.  .docx
 
You have been asked to develop UML diagrams to graphically depict .docx
You have been asked to develop UML diagrams to graphically depict .docxYou have been asked to develop UML diagrams to graphically depict .docx
You have been asked to develop UML diagrams to graphically depict .docx
 
You have been asked to develop UML diagrams to graphically depict an.docx
You have been asked to develop UML diagrams to graphically depict an.docxYou have been asked to develop UML diagrams to graphically depict an.docx
You have been asked to develop UML diagrams to graphically depict an.docx
 
You have been asked to develop a quality improvement (QI) process fo.docx
You have been asked to develop a quality improvement (QI) process fo.docxYou have been asked to develop a quality improvement (QI) process fo.docx
You have been asked to develop a quality improvement (QI) process fo.docx
 
You have been asked to design and deliver a Microsoft PowerPoint pre.docx
You have been asked to design and deliver a Microsoft PowerPoint pre.docxYou have been asked to design and deliver a Microsoft PowerPoint pre.docx
You have been asked to design and deliver a Microsoft PowerPoint pre.docx
 
You have been asked to be the project manager for the development of.docx
You have been asked to be the project manager for the development of.docxYou have been asked to be the project manager for the development of.docx
You have been asked to be the project manager for the development of.docx
 
You have been asked to conduct research on a past forensic case to a.docx
You have been asked to conduct research on a past forensic case to a.docxYou have been asked to conduct research on a past forensic case to a.docx
You have been asked to conduct research on a past forensic case to a.docx
 
You have been asked for the summary to include the following compone.docx
You have been asked for the summary to include the following compone.docxYou have been asked for the summary to include the following compone.docx
You have been asked for the summary to include the following compone.docx
 
You have been asked to be the project manager for the developmen.docx
You have been asked to be the project manager for the developmen.docxYou have been asked to be the project manager for the developmen.docx
You have been asked to be the project manager for the developmen.docx
 
You have been asked by management, as a senior member of your co.docx
You have been asked by management, as a senior member of your co.docxYou have been asked by management, as a senior member of your co.docx
You have been asked by management, as a senior member of your co.docx
 

Recently uploaded

Types of Herbal Cosmetics its standardization.
Types of Herbal Cosmetics its standardization.Types of Herbal Cosmetics its standardization.
Types of Herbal Cosmetics its standardization.
Ashokrao Mane college of Pharmacy Peth-Vadgaon
 
A Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdfA Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdf
Jean Carlos Nunes Paixão
 
Smart-Money for SMC traders good time and ICT
Smart-Money for SMC traders good time and ICTSmart-Money for SMC traders good time and ICT
Smart-Money for SMC traders good time and ICT
simonomuemu
 
The History of Stoke Newington Street Names
The History of Stoke Newington Street NamesThe History of Stoke Newington Street Names
The History of Stoke Newington Street Names
History of Stoke Newington
 
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptxC1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
mulvey2
 
Natural birth techniques - Mrs.Akanksha Trivedi Rama University
Natural birth techniques - Mrs.Akanksha Trivedi Rama UniversityNatural birth techniques - Mrs.Akanksha Trivedi Rama University
Natural birth techniques - Mrs.Akanksha Trivedi Rama University
Akanksha trivedi rama nursing college kanpur.
 
Pride Month Slides 2024 David Douglas School District
Pride Month Slides 2024 David Douglas School DistrictPride Month Slides 2024 David Douglas School District
Pride Month Slides 2024 David Douglas School District
David Douglas School District
 
S1-Introduction-Biopesticides in ICM.pptx
S1-Introduction-Biopesticides in ICM.pptxS1-Introduction-Biopesticides in ICM.pptx
S1-Introduction-Biopesticides in ICM.pptx
tarandeep35
 
How to Build a Module in Odoo 17 Using the Scaffold Method
How to Build a Module in Odoo 17 Using the Scaffold MethodHow to Build a Module in Odoo 17 Using the Scaffold Method
How to Build a Module in Odoo 17 Using the Scaffold Method
Celine George
 
World environment day ppt For 5 June 2024
World environment day ppt For 5 June 2024World environment day ppt For 5 June 2024
World environment day ppt For 5 June 2024
ak6969907
 
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
Dr. Vinod Kumar Kanvaria
 
Digital Artifact 1 - 10VCD Environments Unit
Digital Artifact 1 - 10VCD Environments UnitDigital Artifact 1 - 10VCD Environments Unit
Digital Artifact 1 - 10VCD Environments Unit
chanes7
 
Liberal Approach to the Study of Indian Politics.pdf
Liberal Approach to the Study of Indian Politics.pdfLiberal Approach to the Study of Indian Politics.pdf
Liberal Approach to the Study of Indian Politics.pdf
WaniBasim
 
writing about opinions about Australia the movie
writing about opinions about Australia the moviewriting about opinions about Australia the movie
writing about opinions about Australia the movie
Nicholas Montgomery
 
Chapter 4 - Islamic Financial Institutions in Malaysia.pptx
Chapter 4 - Islamic Financial Institutions in Malaysia.pptxChapter 4 - Islamic Financial Institutions in Malaysia.pptx
Chapter 4 - Islamic Financial Institutions in Malaysia.pptx
Mohd Adib Abd Muin, Senior Lecturer at Universiti Utara Malaysia
 
Hindi varnamala | hindi alphabet PPT.pdf
Hindi varnamala | hindi alphabet PPT.pdfHindi varnamala | hindi alphabet PPT.pdf
Hindi varnamala | hindi alphabet PPT.pdf
Dr. Mulla Adam Ali
 
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdfবাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
eBook.com.bd (প্রয়োজনীয় বাংলা বই)
 
Life upper-Intermediate B2 Workbook for student
Life upper-Intermediate B2 Workbook for studentLife upper-Intermediate B2 Workbook for student
Life upper-Intermediate B2 Workbook for student
NgcHiNguyn25
 
How to Add Chatter in the odoo 17 ERP Module
How to Add Chatter in the odoo 17 ERP ModuleHow to Add Chatter in the odoo 17 ERP Module
How to Add Chatter in the odoo 17 ERP Module
Celine George
 
CACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdfCACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdf
camakaiclarkmusic
 

Recently uploaded (20)

Types of Herbal Cosmetics its standardization.
Types of Herbal Cosmetics its standardization.Types of Herbal Cosmetics its standardization.
Types of Herbal Cosmetics its standardization.
 
A Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdfA Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdf
 
Smart-Money for SMC traders good time and ICT
Smart-Money for SMC traders good time and ICTSmart-Money for SMC traders good time and ICT
Smart-Money for SMC traders good time and ICT
 
The History of Stoke Newington Street Names
The History of Stoke Newington Street NamesThe History of Stoke Newington Street Names
The History of Stoke Newington Street Names
 
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptxC1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
 
Natural birth techniques - Mrs.Akanksha Trivedi Rama University
Natural birth techniques - Mrs.Akanksha Trivedi Rama UniversityNatural birth techniques - Mrs.Akanksha Trivedi Rama University
Natural birth techniques - Mrs.Akanksha Trivedi Rama University
 
Pride Month Slides 2024 David Douglas School District
Pride Month Slides 2024 David Douglas School DistrictPride Month Slides 2024 David Douglas School District
Pride Month Slides 2024 David Douglas School District
 
S1-Introduction-Biopesticides in ICM.pptx
S1-Introduction-Biopesticides in ICM.pptxS1-Introduction-Biopesticides in ICM.pptx
S1-Introduction-Biopesticides in ICM.pptx
 
How to Build a Module in Odoo 17 Using the Scaffold Method
How to Build a Module in Odoo 17 Using the Scaffold MethodHow to Build a Module in Odoo 17 Using the Scaffold Method
How to Build a Module in Odoo 17 Using the Scaffold Method
 
World environment day ppt For 5 June 2024
World environment day ppt For 5 June 2024World environment day ppt For 5 June 2024
World environment day ppt For 5 June 2024
 
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...
 
Digital Artifact 1 - 10VCD Environments Unit
Digital Artifact 1 - 10VCD Environments UnitDigital Artifact 1 - 10VCD Environments Unit
Digital Artifact 1 - 10VCD Environments Unit
 
Liberal Approach to the Study of Indian Politics.pdf
Liberal Approach to the Study of Indian Politics.pdfLiberal Approach to the Study of Indian Politics.pdf
Liberal Approach to the Study of Indian Politics.pdf
 
writing about opinions about Australia the movie
writing about opinions about Australia the moviewriting about opinions about Australia the movie
writing about opinions about Australia the movie
 
Chapter 4 - Islamic Financial Institutions in Malaysia.pptx
Chapter 4 - Islamic Financial Institutions in Malaysia.pptxChapter 4 - Islamic Financial Institutions in Malaysia.pptx
Chapter 4 - Islamic Financial Institutions in Malaysia.pptx
 
Hindi varnamala | hindi alphabet PPT.pdf
Hindi varnamala | hindi alphabet PPT.pdfHindi varnamala | hindi alphabet PPT.pdf
Hindi varnamala | hindi alphabet PPT.pdf
 
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdfবাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
 
Life upper-Intermediate B2 Workbook for student
Life upper-Intermediate B2 Workbook for studentLife upper-Intermediate B2 Workbook for student
Life upper-Intermediate B2 Workbook for student
 
How to Add Chatter in the odoo 17 ERP Module
How to Add Chatter in the odoo 17 ERP ModuleHow to Add Chatter in the odoo 17 ERP Module
How to Add Chatter in the odoo 17 ERP Module
 
CACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdfCACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdf
 

Confirmations and ContradictionsThe Leontief Paradox, Reco.docx

  • 1. Confirmations and Contradictions The Leontief Paradox, Reconsidered: Correction Iraj Heravi University of California, Los Arigetes Leontief (1954) incorrectly inferred that the United States is revealed by trade to be relatively more abundant in labor than in capital from the fact that the capital per man in imports exceeds the capital per man in exports. The counterexample in Leamer (1980) is in error, however, since it uses commodity prices at which the first commodity is not economically produced. This is easily remedied by setting the price vector to (2, 1, 1) instead of (1, 1, 1). Then, by the series of calculations outlined in Leamer (1980), it is possible to compute the ratio of capital per man in exports to capital per man in imports to be 0.97, even though capital is the relatively abundant factor. Incidentally, the error in the choice of prices is revealed by the computation of the returns to factors, which for the original numbers contains a negative return to capital.
  • 2. References Heravi, Iraj. "Determination of Patterns of Trade." Ph.D. dissertation, Univ. California at Los Angeles, 1984. Leamer, Edward E. "The Leontief Paradox, Reconsidered."/.P.£:. 88 (June 1980): 495-503. Leontief, Wassily W. "Domestic Production and Foreign Trade: The Ameri- can Capital Position Re-examined." Econ. Internazionate 7 (February 1954): 9—38. Reprinted in Readings in International Economics, edited bv Richard E. Caves and Harry G.Johnson. Homewood, III.: Irwin (for American Econ. Assoc), 1968. Postdoctoral scholar. Graduate School of Management, UCLA. I am indebted to Edward Leamer for his advice and encouragement. See my dissertation (1984) for further work. [Jounuil (i/ Piiliiiral Ecimomy. 19R6, vol. 94, no. 5] © 198(3 by l h e L nivfisuy of Chicago. All rights reserved. 0022-3808/86/9405-0010$01.50 1 12O
  • 3. #1. DUE Thursday 1/ 22 /2015 NOON…. Continue working with the company you originally chose from the Fortune’s 500 Best List ( Johnson & Johnson) http://archive.fortune.com/magazines/fortune/mostadmired/2006 /best_worst/worst8.html Detail Directions (See Below) – CLASSROOM FORUM DISCUSSION 1. You have been working with each environment individually; now it's time to integrate and synthesize. 2. Perform research (minimum of 3 sources in APA format). 3. Analyze each environment collectively by incorporating theories learned. 4. How are the individual environments working together for your chosen company? 5. How is each working with the other environments? 6. Is an environment causing limitations on another? If so, which environments are involved and what are the limitations? 7. What could you change to create synergy? Your answer cannot be that you wouldn’t change a thing. You must incorporate critical thinking. 8. Minimum 6 complete paragraphs; a paragraph is a minimum of 100 words. *****Use this as one of the References: Use at least one of the sources provided below in “Reading / Resources: “. #2 . DUE Saturday 1/ 24 /2015- NOON . Continue working with your chosen company from Fortune’s 500 Worst List ( Chosen Company is “Google”) http://archive.fortune.com/magazines/fortune/mostadmired/2006 /best_worst/worst8.html Detail Directions (See Below) – FORMAL PAPER Assignment Instructions Continue working with your chosen least admired company
  • 4. (Google) for the assignments and complete the following: 1. Identify the company’s domestic environment and discuss how the government regulations affect its domestic environment it must operate in. 2. Identify a global environment for the company and discuss how the government regulations affect its global environment it must operate in. 3. Identify the hard and soft technology and interpret the characteristics the company should have/use to be successful in its domestic and global environment. 4. Identify the political-legal barriers for the company in both the domestic and global environments. Use business theory/theorists to illustrate how the company can operate successfully in its domestic and global environment. 5. Identify, compare, and contrast sociocultural factors of the domestic and global environments of the company. 6. Compare and contrast two economic theories for both the domestic and global environments of the company. 7. Develop a strategy of success based on your evaluation of steps 1-6 by assessing what you’ve learned through your research and readings and compare what the company has been
  • 5. doing to what you recommend they should be doing. You cannot state that you would not change anything. 8. You must incorporate critical thinking (see resources). 9. Research requirement: minimum 5 sources PLUS the text and Geert Hofstede. 10. Page requirement: 7 pages in APA format (does not count cover page and reference page). Note: ALL Assignments are submitted to turnitin.com and checked for originality. ****Use this as one of the References: Use at least one of the sources provided below in “Reading / Resources: “. ADDITIONAL NOTES / INFORMATION: This is it! Here you will finish integrating the environments of your chosen company. At this point, you should have all elements identified in your previous writings ( forums and paper assignments). Is there anything you would change at this point? Do you think you would be successful? Why or why not? The assignment this week will be a final simulation project for your chosen company. Using your company you’ve been working with, recognize all the environments you’ve studied – domestic, global, technological, political/legal, sociocultural, and economic. All environments must be included. Once you have each identified, it’s time to analyze and synthesize. What is each individual environment like? How are they working? What
  • 6. issues do you see? What would you change and why? It won't be acceptable to state you wouldn't change anything. Really apply what you've learned from your research. Now, take a look at all environments together, as whole and not individual pieces. Is each working together? Is an environment causing limitations on another? If so, which environments are involved and what are the limitations? What could you change to create synergy? All Sources must be “Scholarly Article or Book”. A scholarly article or book generally is based on original research or experimentation. It is written by a researcher or expert in the field who is often affiliated with a college or university. Most scholarly writing includes footnotes and/or a bibliography and may include graphs or charts as illustrations as opposed to glossy pictures. In addition, articles that appear in scholarly journals or book that are published by academic presses, are subject to a peer-review process, which means that other "experts" or specialist in the field evaluate the quality and originality of the research as precondition of publication. The peer-review (as opposed to editorial review) process is also one thing that sets scholarly journals apart from journals that may otherwise seem quite similar. Journals such as Foreign Affairs, for instance, are generally not considers "scholarly journals," because many of the articles are solicited by the magazine's editors; in addition many of the articles are written by policy-makers who may be expressing an informed view, but whose article may not be based on original research.Scholarly research is typically published by a academic association or a university/academic press. In international relations and comparative politics, representative scholarly journals include Asian Survey, Comparative Politics, International Organization, International Security Studies, Journal of Comparative Politics, Journal of Democracy, and World Politics. Reading / Resources:
  • 7. You are not limited to the below: **Review all previous resources provided. Lin, H., Fan Y., & Newman S. (2009). Manufacturing process analysis with support of workflow modelling and simulation (p1773-1790. 18p. 6) Závadský, J., & Lukáš, T. (2010). Simulation and its purpose in implementing of business process management. Advances in Management, 3(3), 9-12 International Journal of Production Research Vol. 47, No. 7, 1 April 2009, 1773–1790 Manufacturing process analysis with support of workflow modelling and simulation Huiping Lin a,*, Yushun Fan a and Stephen T. Newman b a Department of Automation, Tsinghua University, Beijing, 100084, P.R., China; b Department of Mechanical Engineering, University of Bath, Bath, BA2 7AY, UK
  • 8. (Received 15 December 2005; final version received 14 August 2007) Process analysis is recognized as a major stage in business process reengineering that has developed over the last two decades. Manufacturing process analysis (MPA) is defined as performance analysis of the production process. A manufacturing process analysis framework is outlined with emphasis on linking a company’s strategy to operational process. Two issues, namely process modelling and simulation based analysis, are investigated. A compound workflow model (CWM) is proposed to provide graphic presentation of the production process that can be easily understood. Also it can be used directly by simulation to study the impacts of scheduling policy and analyse the process performance. A two-stage simulation analysis method is provided to quantitatively and efficiently define cause-and-effect relations to identify drivers for improvement. The manufacturing environment, PSC (production planning, scheduling and control) factors and the process structure are three main concerns considered in the simulation. An example is discussed in the final part of the paper. Keywords: manufacturing process; performance analysis; modelling; simulation
  • 9. 1. Introduction With increasing market competition, more and more companies recognize the importance of improving their competitive capability. Over the last two decades, business process reengineering (BPR) has been carried out by academic researchers and industrial companies to improve performance. It concerns the fundamental rethinking and radical redesign of a business process to obtain dramatic and sustained improvements in quality, cost, service, lead time and innovation (Hammer and Champy 1993). Process analysis is recognized as a highly important stage of any BPR project. It understands the way the process is done, finds problems and the gaps between current performance and expected targets, and identifies changes needed for improvement. Manufacturing process analysis, which is defined as modelling and performance analysis of a production process, is essential for manufacturing companies to improve their market competition. Manufacturing is a complicated system that involves sets of tasks, materials, resources (including human resources, facilities and software), products, and information. Askin and Standridge (1993) divided the manufacturing system into five interrelated *Corresponding author. Email: [email protected] ISSN 0020–7543 print/ISSN 1366–588X online � 2009 Taylor & Francis DOI: 10.1080/00207540701644151
  • 10. http://www.informaworld.com functions: product design; process planning; production operations; material flow/facilities layout; and production planning and control. Product design is responsible for constructing the description of the products. Process planning entails the specification of the sequence of operations required for product production. Production operations refer to those fabrication or assembly actions such as drilling a hole or inserting a raw material into the workstation. Facilities layout is concerned with the physical placing of production process. Production planning, scheduling and control (PSC) is an important task within manufacturing. It generates long/medium term production plans and disaggregates them to obtain short term schedules about the tasks’ sequence on the machine. The MPA discussed in this paper is mainly concerned with production process reengineering. It uses a top down method to associate the company’s strategy with the process’s target. By process analysis, it finds out the initiatives to implement the target. MPA is not the same as the production scheduling and control problem. MPA optimizes the production from the point of view of process structure redesign. Most PSC methods optimize the measurements such as time, and cost with the existing resource or process
  • 11. constraints. (Readers are referred to a series of review papers about PSC namely Gupta et al. 1991, MacCarthy and Liu 1993, Sox et al. 1999, Potts and Kovalyov 2000, Tan and Khoshnevis 2000.) MPA can result in adjustments of process constraints. Process improvement solutions possibly contain reconstruction of the process or the organization, for example, outsourcing some activities, adding a new resource, reducing an activity’s processing time by new technology, etc. It considers the influence of PSC because the appropriate planning and scheduling methods can also improve the process performance. Modelling and simulation based analysis of MPA are discussed in this paper. Usually a process model is established to understand the structure of manufacturing, reveal relationships among machines, tasks and materials, and learn how the process works. In the literature, mathematical models and graphic models are two major methods to describe the manufacturing process. For example, fuzzy mixed integer programming has provided the ability to model and analyse the manufacturing cell formation problem (Tsai et al. 1997). Yun and Gen (2002) used constraint programming to establish a pre-emptive and non pre-emptive scheduling model. Cooke et al. (2004) developed mixed integer programming formulations with the assumption of a production precedence sequence to study the economic lot scheduling problem. Mathematical models are often used for production scheduling purposes. Although
  • 12. mathematical models are convenient for computing, they do not offer an intuitive understanding to their users. Petri nets are a popular graphic method for modelling, scheduling and analysing the manufacturing process (Shih and Sekiguchi 1991, Lee and DiCesare 1994, Proth and Minis 1995, Xiong et al. 1996, Zhou and Venkatesh 1999). Shih and Sekiguchi (1991) and Lee and DiCesare (1994) used a Petri net with heuristic search for FMS (flexible manufacturing systems) scheduling. Xiong et al. (1996) and Zhou and Venkatesh (1999) studied the application of Petri nets in modelling, simulation and control of flexible manufacturing systems. The use of Petri nets has the advantage in describing complicated process constraints. However, the major problem is that its state space for searching grows dramatically with system complexity (Zhou and Venkatesh 1999). It still lacks a comprehensive model that has all following features: . The capability to describe complicated relations among tasks, machines, and production routings; . Graphic presentation so that the model can be easily established and used; 1774 H. Lin et al. . To fulfil requirements of MPA that is concerned with the PSC and process
  • 13. planning. Thus, a workflow modelling and simulation based method is proposed to solve the problem in manufacturing process analysis. The contributions of the paper are: . Providing a manufacturing analysis framework that emphasizes on associating enterprise strategy to process. . Providing a graphic presentation of a manufacturing process, not only showing the structure of a process, but also containing enough information for dynamic performance analysis. . Proposing a structured two-step sensibility analysis to quantitatively and efficiently identify cause-and-effect relations to implement the strategy. The paper is organized as follows: initially, an analysis framework is introduced. How production process modelling and simulation are used in MPA is described. Then a compound workflow model (CWM) is proposed to describe the production process. A two-step simulation method is explained in detail. The final part of the paper provides a case study which shows the effectiveness of the proposed method. 2. Manufacturing process analysis framework MPA should have a strategic level of thinking about the objective and target of the
  • 14. manufacturing process. It encourages people to be more creative and more focused on process improvement. More and more people have realized strategic thinking in a project will help to identify the desired performance and make improvements more focused and purposeful. For example, King (1994) pointed out the lack of strategy accounted for many failures in process improvement projects. Kaplan and Norton (1992, 1996) proposed a balanced scorecard (BSC) – namely an effective method for strategy management. In Kaplan and Norton’s method, four steps are involved: first, a company’s strategy is translated into process’ objectives. Second, key indicators are selected to measure process performance. Then, targets are associated with indicators at operational level. Finally, initiatives to pursue targets are identified and tasks will be completed. In Kaplan and Norton’s method, a cause-and-effect analysis served as a core part in linking strategy to process. The cause-and-effect relations are a set of hypotheses about how to achieve important objectives. Usually, it can be expressed as a sequence of if-then statements: If we do actions, then we may be able to achieve objectives. Although BSC provides a framework for connecting a company’s strategy to a process, it does not specify how the connection can be built. Only when people have a very good understanding about a process’s structure and performance, can they know which factors account for what results. For a complicated manufacturing process, although some
  • 15. historical data and employee experience exists, it is very difficult to quantitatively define cause-and-effect relations. On the other hand, in Kaplan and Norton’s straight down four step method, there was no communication between the decision making level that set targets and the operational level that has details about manufacturing. If the target is too stressful, it will be expensive or even impossible to realize. It will not benefit process improvement projects until the target is appropriately set. Thus, a target evaluation and a bridge between the decision making level and the operational level are needed. International Journal of Production Research 1775 Moreover, as performance improvement solutions may have structural change to the process, feasibility verification of the solutions is required before it is put into implementation to avoid unnecessary loss. Thus, a new manufacturing process analysis framework is provided (see Figure 1). An adapted workflow model and its simulation will be used to clarify the manufacturing process, understand how the process operates and access process improvement solutions. A feedback channel is introduced to help in setting reasonable targets. After the company’s strategy is clarified, the following steps are taken to link the
  • 16. strategy to the processes. Step 1: Translating the company’s strategy to processes’ objective. Connecting strategy directly to the process helps to break through the boundary of organizations and focus on process-oriented analysis. At this stage, the process’s objective is determined according to the company’s strategy. The manufacturing process model is needed for two reasons. Firstly, the manufacturing process model defines the structure and constraints for the manufacturing processes. It provides a platform for employees and project teams to understand the manufacturing process and communicate with each other. Secondly, defining the boundary of the processes also helps the manager to determine the objective of the process. Step 2: Identifying key process measurements according to the process objective. Measures for manufacturing performance can to be catalogued in terms of business, operational and customer perspectives (Challis et al. 2002). As performance of the manufacturing process is our main concern, operational performance is our major focus. The following performance measures are widely used in manufacturing: production throughput, lead time, reliability, cost, capacity, resource utilization and product quality. Readers can refer to Altiok (1996) and Viswanadham (1999) for definitions of some typical measurements in manufacturing environments.
  • 17. Step 3: Associating a rough target with selected indicators. Figure 1. Manufacturing process analysis framework. 1776 H. Lin et al. At this point, a rough target is set by estimation of cause-and- effect relations with historic data and employees’ experiences. Step 4: Finding initiatives to complete the process improvement task and verifying the feasibility of the target. Improving the production throughput and then maximizing the benefit is the most popular objects for production improvement. There are two major ways to achieve this. The first method is to take the existing production capacity as given and optimize the organization’s performance within the capacity. According to Goldratt and Cox’s (1992) theory of constraints, the manager can increase throughput by relieving the bottleneck factor of the production. They often do this by choosing an effective scheduling method to reduce
  • 18. the downtime on the constraining resources or buffering this resource; or reengineering the production to reduce the demand on constraining factors. The second method is following the long term operations strategy to increase capacity. The process improvement can be catalogued in four dimensions such as process level, activity level, resource level and management level. The typical process improvement actions are shown in Figure 2. An evaluation method is needed to study which action is most effective for the production process. Simulation is used to study the cause-and- effect relations at this stage. The simulation results are also used to verify whether the target is appropriate. If the target is too stressful, it will go back to negotiate with the higher decision making level to discuss the target. Finally, the process improvement solutions can be generated. 3. Compound workflow model It is impossible to describe complicated manufacturing processes from any single prospective (Toh et al. 1997). Comparing manufacturing processes with
  • 19. business processes, the manufacturing process specification needs to pay much more attention to constraints such as resource, time and process. A compound workflow model (CWM) that includes the process view, resource view and order view is proposed. Process level - Change logic sequence between activities - Add/delete activities Activity level - Change activity processing - Reducing activity processing time - Mapping to another resource Resource level Management Level - Increasing resource capability - Adding resource’ functions - Buffering the resource - Reducing setup time - Choosing effective scheduling method Process improvement actions Figure 2. Typical process improvement actions.
  • 20. International Journal of Production Research 1777 In this section, a brief introduction to the workflow modelling technique is given to answer the question why it is chosen. Then the definition of CWM is discussed in detail. 3.1 Workflow modelling technology Workflow management is one of the research areas that has attracted much attention from researchers, developers and industrial users since the 1990s. Over the years, there have been a lot of definitions for workflow and what features a workflow management system must provide. For example, the Workflow Management Coalition (1995) defines workflow as ‘the computerized facilitation or automation of a business process, in whole or part’. Giga Groups call workflow ‘the operation aspects of a business process, the sequence of tasks and who perform them, the information flow to support the tasks, and the tracking and reporting mechanism that measure and control them’ (Mohan 1997). Fan et al. (2001) defines workflow as ‘computerized process model which can be operated by workflow management system in order to realize business process integration and automation’. Two similarities can be found from the above definitions. First, a workflow model describes three aspects of the business process, namely:
  • 21. . ‘What’ is a process? – defining activities that build up the process; . ‘How’ is the process organized? – defining logic between activities; . ‘Who’ performs the activity? – defining relations between resources and activities. Secondly, a workflow model is often associated with an execution software system. In other words, it is an executable model that can be read, operated, and controlled by a workflow simulation or management system. This unique character differentiates itself from other process models. Workflow management research efforts can be classified into three categories namely workflow specification, workflow implementation and workflow application. A number of workflow specifications are already available in the literature. Winograd and Flores (1987) provided a communication based workflow model by using speech act theory. It describes every action of workflow in four phases from a viewpoint of communication between customers and performers. An activity-based methodology which focused on modelling the work instead of modelling the commitments among humans is more popular than a communication based modelling method. The Workflow Management Coalition (WfMC) provided a basic process definition meta-model (Workflow Management
  • 22. Coalition 1995) which included activity, role and workflow relevant data. IBM defined FlowMark (Mohan et al. 1995), which used activities, input/output containers, connectors and conditions to describe the business process in build up time and drove process instances during run-time. Petri net and its extended form have also been used for workflow definition. For example, Ellis and Nutt (1993) defined information control nets from Petri net for workflow specification. Van der Aalst (1996) provided WF-nets, where transitions presented activities and places described enable condition of activities. The workflow management system has often been used in business process automation and reengineering (Aversano et al. 2002). It enables process automation through integration, coordination, and communication of both human and automatic tasks of a business process (Workflow Management Coalition 1996). Despite applications in business processes, Lin et al. (2004) studied the job shop scheduling problem based on workflow modelling and simulation. The research showed that workflow models can be 1778 H. Lin et al. used to describe manufacturing processes and study production planning and scheduling problems as well.
  • 23. As workflow specification helps to clarify process definition, supports the considera- tion of production planning and scheduling and simulation based performance analysis, workflow modelling and simulation technology has been chosen in this paper for manufacturing process analysis. 3.2 Compound workflow model (CWM) The CWM is proposed especially for the manufacturing process where resource constraints description is very important. CWM is composed of the process view, resource view and order view (see Figure 3). Each view aims to describe one perspective of the process, where multiple relations exist among different views. (1) Process view The process view is built using an activity-based method. It is made up of multi-processes, each of which defines activities and the process logic needed for one type of product. Thus, manufacturing of each type of product has its own pre- defined production route in a CWM. A directed acyclic activity-on-node diagram, where nodes indicate activities and arcs indicate dependencies, is used for each process. In order to describe five typical processes, logic such as serial, and-joint, and-split, or-joint and or-split logic, and indicate start/end point of a process instance, six logic nodes are introduced into the CWM. For each activity node, there are three kinds of description
  • 24. namely property definition, resource mapping and behaviour description. . Property definition: defines static properties and dynamic properties of each activity. The former refers to properties that will not be changed during operation, i.e., activity ID and activity’s function. The latter refers to properties associated with run-time status such as activities’ begin time, complete time and real time priority. . Resource mapping: allocates resources to activities, including necessary human resources and physical resources. It establishes a connection between the process Trigger Activity Process View Order Order View Enable Process Process logic Individual Resource Resource View
  • 25. Behaviour Description Resource Mapping Properties Definition Properties Resource Pool Properties Properties Figure 3. Structure of compound workflow model (CWM). International Journal of Production Research 1779 view and resource view. Cost driver of activities are also defined via resource mapping. . Behaviour description: describes activity’s action by ECA rules, which are formed as ‘if Event and Condition then Action’. ‘Event’ refers to running time events such as ‘the resource is released’, ‘condition’ refers to activity enable conditions, and ‘action’ means the activity’s status is transferred from one to another. It is behaviour description that enables CWM, has the capability to describe dynamic
  • 26. behaviour and makes CWM an executable model. ECA rules will be explained by simulation system in the analysis. (2) Resource view CWM has an independent resource view so that it can handle complicated resource constraints more effectively. Two kinds of resource entities – individual resources and resource pools are introduced. The individual resource refers to a real resource entity that participates in production. The resource pool is in fact a classification of individual resources according to their functions or geographical positions so that individual resources in the same resource pool can be substituted for each other. It makes the model flexible in dealing with the ‘parallel machine’ problem, which is very common in manufacturing. During the model definition period, static mapping from individual resources to the resource pool and resource pool to activities are established separately. Then during simulation, individual resources are dynamically allocated to activities based on static definition and running time individual resource status. In the case where there is no resource pool defined in the resource view, individual resources will be allocated to activities directly when building the model. For an individual resource, properties such as name, function, capacity, cost, etc. are
  • 27. considered. For the resource pool, properties such as function and containing resources are defined. (3) Order view The order view describes properties of orders coming to the enterprise, which reflects the market environment that the company is facing. Order instances are initiated according to the order view to trigger process instances in simulation. Properties such as orders’ arrival time, frequency, type, amount, due date, priority, cost, entry of the process, etc. are defined. (4) Cost specification in the CWM The cost information is specified in the CWM for two purposes: first, cost information is recorded for activity-based costing (ABC). The goal of ABC is to measure and then price out all the resources used for activities that support the production and delivery of products and services to customers (Kaplan and Atkinson 1998). CWM provides useful information for activity based cost (ABC). It clarifies the activities being performed by the organization’s resources when establishing the process view. Then, when the resource is allocated to the activities, the activity cost drivers and activity cost driver rate can be identified. This rate will be used to drive activity costs to products. Cost is also an important issue that should be considered in
  • 28. analysis. Usually the improvement of the process is often associated with cost increase. For example, the decrease of the activity processing time due to the increase of resource functions or number of the resources often lead to additional cost of a resource. Thus, the second 1780 H. Lin et al. purpose of cost description in the CWM is to record dynamic changes of activity cost drivers and their rate in simulation. The process improvement actions can have impacts on cost calculating through two ways: . Spending additional cost on resources, for example, buffering the resource or adding special functions to the resource. The increase of the total resource cost will lead to the adjustment of the activity cost driver rate. . Changing the mapping relations between activity and resources, for example, mapping the activity to another resource by process reengineering. In this case, both cost driver and its rate can be affected. CWM is going to provide information for activity based cost analysis (Figure 4). In the
  • 29. resource view, the resource cost is defined as one of the resource properties. When the resource is allocated to the activities, the activity cost driver and its rate are identified and recorded as the properties of the activities. During the simulation, if the adjustment to the process model is made, it will determine whether the resource cost and mapping relation are affected. Then the cost properties of the resource and activities will be recalculated. In conclusion, CWM is an adapted workflow model for a manufacturing process. Comparing to other process models, it provides the following features: . Provides flexible resource definition that support static and dynamic resource mapping. It can handle various resource constraints of the production process. . Provides process behaviour description by ECA rules. The model can be used by the workflow simulation system directly for performance analysis. . Provide easy cost specification to calculate activity based cost and record cost adjustment in sensibility analysis. Establish Activity-Based
  • 30. Process View Establish Resource View Allocate Resource to Activity Identify activity being performed Identify resource in the manufacturing Identify activity cost driver Calculating driver rate Build order view for simulation Calculating cost Building CWM Activity based Cost Resource cost or mapping affected? Process Improvement Yes Figure 4. Cost specification in CWM. International Journal of Production Research 1781 . As mentioned in section 2, workflow modelling and simulation
  • 31. technology can also be used for production planning and scheduling problems. That makes it possible to support the overall manufacturing process analysis with the same model. 4. Simulation based sensibility analysis In order to set the target for the process and find possible initiatives, the following questions need to be answered: . Which factors can have impacts on process performance? . What kind of impacts the factor can cause to the process? . How much is the impact? Sensibility analysis is an effective method to answer the above three questions. It is completed by adjusting variables and observing their influence on the system. However, there are tens, hundreds or even thousands of variables in manufacturing. If the variables are studied one by one, sensibility analysis will become extremely difficult and time-consuming. In order to improve the efficiency of the analysis, a two-phase simulation method is proposed (Figure 5). The objective of the first round simulation is to identify a group of variables that potentially have a major influence on the system. Then in the second phase those potential key variables will be studied further to determine which one has great impacts on production.
  • 32. In order to select latent key variables, we first watch the process’s performance under different manufacturing environments. A different manufacturing environment is achieved by setting appropriate simulation parameters. The following aspects are considered to present a different simulation environment: . Environment factors, including orders’ total number, type, batch size, due date, patterns, cost, etc. The process’s performance is usually associated with the orders First Round Simulation Response to environments Influence of different policies • • • • • Quantitative Cause- effect-relation Improvement solutions Target verification PSC
  • 33. Environment Factors Performance Measurement Statistic Analysis Sensibility Analysis Group of possible key variables Process Strateg Process structure PSC Environment Factors Figure 5. Framework of the two-stage simulation analysis. 1782 H. Lin et al. coming into the system. For instance, a resource’s utility will be different when the order types, pattern, batch size, etc. are changed. A process improvement solution
  • 34. should meet requirements under all manufacturing environments. . Scheduling policy that is often used in manufacturing. Different from the scheduling optimization problem where new algorithms are studied, the main purpose of setting a different scheduling policy in the first round simulation is to investigate the influence of a company’s most often used scheduling methods. It also determines whether the strategy can be achieved by switching to a different planning and scheduling method. Since using a different scheduling policy is more economic than changing the structure of the process, such a necessity test is carried out before structural analysis. After the data analysis, usually by the ANOVA method, the crucial performances are identified. The variables within the process model that are directly or indirectly associated with them are going to be studied in the next round of sensibility analysis. The typical parameters within the process model are: . Time related variables, such as processing time of the activity, set up time, etc. . Process structure related variables, including the number of activities, resources, the topology of the activity network, the association between activities and resources.
  • 35. . Cost related variables, for example, set up cost, holding and backlog cost, resource using cost. . Capability related variables, such as resource capability. The selected group of process parameters will be treated as variables in sensibility analysis. The PSC factors and environment factors are also considered to give a comprehensive view of the impacts of these variables under different scenarios. 5. Example study A workshop within a small manufacturing enterprise (SME) that produces crankshafts is used as a case study. It demonstrates the procedure of applying the method step by step. (1) Linking strategy to production process The company is facing an increasing market and its mid-term strategy is to increase the company’s production capability. Currently the workshop’s output is about 500 items per month. Assume that the company set a rough target of increasing manufacturing capability by 15%. The objective of the analysis is to find the effective and efficient ways to increase the throughput. (2) Build CWM model The workshop provides several types of crankshafts. Their manufacturing routings can be
  • 36. classified into two groups: (1) rough milling – milling – milling – ultrasound test – drilling – rough lathing – rough lathing – milling – lathing; (2) rough milling – milling – ultrasound test – drilling – rough lathing – rough lathing – milling – lathing. Four milling machines (M1, M2, M3, M4), three lathes (L1, L2, L3), one drilling press (D1) and one ultrasound test tool (U1) are involved. One operation on one machine is considered as one activity. The duration of each activity and the resources used are described in Table 1. International Journal of Production Research 1783 A two process CWM is built (Figure 6), where each process describes one manufacturing route of one product. The resource mapping between activities and resources is defined in activity properties. (3) Simulation based analysis The following aspects are considered in first round simulation parameter settings: . Total order number per month. As the objective is to increase the process throughput, the basic rule to set total order number per month is that it can cover the situation from current process capability to the target
  • 37. capability. Thus, together with the settings of order pattern, the response of the process to the manufacturing environment can be watched. . Order pattern. Three order patterns are considered. Under pattern A, all the orders have the same due date for one month. It reflects the stable market where all the orders are known in advance and the workshop can arrange the manufacturing by a monthly production plan. On the other hand, order patterns B and C have 10% (B) and 30% (C) urgent orders respectively. The urgent orders have a due date of two weeks. Patterns B and C simulate a market with different degrees of Table 1. Description of the production route of the case study. Product 1 Task T1 T2 T3 T4 T5 T6 T7 T8 T9 Machine M1 M2 M3 U1 D1 L1 L2 M4 L3 Duration (hour) 0.3 0.5 0.4 0.5 0.3 0.4 0.5 0.4 0.3 Product 2 Task T11 T12 T13 T14 T15 T16 T17 T18 Machine M1 M3 U1 D1 L1 L2 M4 L3 Duration (hour) 0.3 0.5 0.4 0.4 0.6 0.5 0.3 0.4 T1 T2 T3 T4
  • 38. T11 T12 T13 T14 P1 P2 T5 Resource View Activity ID : T13 Activity function : Ultrasound test Resource: U1 Activity Time : 0.4 hour Behaviour: If (T13-Previous.Status = completed ) And (Resource.Status = occupied ) Then (T13.Status = initiatived ) If (T13-Previous.Status = completed ) And (Resource.Status = available ) Then (T13.Status = started ) …… Milling -M1 O-P1 Order Type:P2 Frequency: Batch : Due date: T6 T7 T8 T9
  • 39. T15 T16 T17 T18 Process View O-P2 Milling -M2 Milling -M3 Test tool -U1 Drill Process -D1 Lathe -L1 Lathe -L2 Milling -M4 Lathe -L3 Figure 6. CWM model of the case study. 1784 H. Lin et al.
  • 40. disturbance. According to the historic data, about 65% of the total order is for product 1. . Scheduling policy. The dispatching rules are used in real production. The three most used dispatching rules are studied: earliest due date (EDD), shortest process time (SPT), and first-in-first-out (FIFO). The parameters of the simulation are set as in Table 2. Two performance indicators are selected: . Process total throughput which is defined as the number of units produced per month. . Resource utility which is defined as percentage of time a machine is actually busy. The result of simulation and ANOVA analysis are given in Tables 3 and 4 respectively. The scheduling policy has the highest F-value on the output and resource utilization among the three factors. That means the appropriate scheduling policy can help to improve the process performance. However, scheduling policy cannot reduce the demand
  • 41. on the constraining factors of U1, L1 and L2: in all simulation runs resources U1, L1 and L2 have relatively high utilization under all situations. They are the bottleneck of production. According to improvement dimensions, activity level and resource level of factors are chosen as potential key variables in sensibility analysis. They are: . The processing time of activities T4 and T13, T6 and T15, and T7 and T16, which are associated with U1, L1 and L2 respectively. Since technically it is not easy to dramatically reduce activities’ processing time, two situations are considered: reducing processing time 5% and 10%; and reducing the activities’ processing time can be achieved through process innovation, using better material or including additional functions to the equipment resource (Table 5). . The number of U1, L1 and L2. One resource will be added. All three order patterns and three scheduling policies are considered in sensibility analysis, it cannot guarantee scheduling policy SPT still has the best performance, so all three scheduling policies are considered as well.
  • 42. Table 2. Description of parameters for first round simulation. Exp No. Order no. Order pattern Scheduling policy Exp No. Order no. Order pattern Scheduling policy 1 525 A EDD 15 575 B SPT 2 550 A EDD 16 525 C SPT 3 575 A EDD 17 550 C SPT 4 525 B EDD 18 575 C SPT 5 550 B EDD 19 525 A FIFO 6 575 B EDD 20 550 A FIFO 7 525 C EDD 21 575 A FIFO 8 550 C EDD 22 525 B FIFO 9 575 C EDD 23 550 B FIFO 10 525 A SPT 24 575 B FIFO 11 550 A SPT 25 525 C FIFO 12 575 A SPT 26 550 C FIFO 13 525 B SPT 27 575 C FIFO 14 550 B SPT International Journal of Production Research 1785 The simulation results of sensibility analysis are shown in Table
  • 43. 6. It can be seen that SPT still has the best performance among the three scheduling policies. Although resource U1 does not have the highest utilization in the first round simulation, it has an outstanding performance in the sensibility analysis. The production capability can be notably increased by reducing the processing time of T4 and T13 by 10% (production capability Table 3. Simulation result of first round simulation. Resource utilization% Total throughput M1 M2 M3 U1 D1 L1 L2 M4 L3 1 470 58 62 84 89 64 90 96 70 64 2 469 58 62 84 89 65 91 96 70 65 3 469 58 62 84 89 65 91 96 70 65 4 471 58 63 84 90 65 91 96 71 65 5 472 58 62 84 90 65 91 97 71 65 6 472 59 63 85 91 66 92 98 71 66 7 479 59 63 85 91 66 93 98 71 66 8 478 59 63 85 91 66 92 98 71 66 9 478 57 62 83 88 64 89 95 69 64 10 521 57 61 83 88 64 89 95 69 64 11 524 57 61 83 88 64 89 95 69 64 12 523 57 62 83 88 64 89 95 69 64 13 521 57 61 83 88 64 89 95 69 64 14 524 57 61 83 88 64 89 95 69 64 15 523 57 62 83 88 64 89 95 69 64 16 521 57 61 83 88 64 90 95 69 64 17 524 57 61 83 88 64 90 95 69 64 18 523 58 62 84 89 64 90 96 70 64 19 470 58 62 84 89 65 91 96 70 65
  • 44. 20 469 58 62 84 89 65 91 96 70 65 21 469 58 62 84 89 64 90 96 70 64 22 470 58 62 84 89 65 91 96 70 65 23 469 58 62 84 89 65 91 96 70 65 24 469 58 62 84 89 64 90 96 70 65 25 470 58 62 84 89 65 91 96 70 65 26 469 58 62 84 89 65 91 96 70 65 27 469 58 62 84 89 65 91 96 70 65 Table 4. ANOVA results (F-value) for the interaction effects of three control parameters on total throughput and each machine’s utilization. Resource utilization% Total throughput M1 M2 M3 U1 D1 L1 L2 M4 L3 Order no 0.14 0.00 1.52 0.00 0.08 0.96 1.06 0.08 0.16 0.46 Order pattern 4.20 a 0.53 0.87 0.53 1.29 0.96 1.85 0.98 1.08 1.21 Scheduling policy 1535.21 a 14.74 a 16.52 a 14.74 a
  • 45. 13.63 a 10.82 a 14.37 a 11.13 a 17.37 a 11.90 a a With a significance less than 5%. 1786 H. Lin et al. increase 12.65%) or by adding one U1 (production capability increase 15.95%). It has much better performance than adding L2 and L1, or changing the activity time associated with them. The reason for this perhaps is that U1 not only has relative high utilization, but also has been involved in production in an earlier stage than L2 or L1. The target can be
  • 46. realized by adding one ultrasound test tool. 6. Conclusions Manufacturing process analysis is an important stage to improve a manufacturing enterprise’s performance. It is a higher level of analysis that focuses on strategic thinking of the manufacturing and structure redesign of the process with the consideration of PSC. Table 5. Reduce activities’ processing time. Description Through Cost 1 Reduce T4, T13’s processing time 5% Process innovation – 2 Reduce T4, T13’s processing time 10% Use better material T4 and T13’s material cost driver rate "4% 3 Reduce T6, T15’s processing time 5% Process innovation – 4 Reduce T6, T15’s processing time 10% Add L1’s function T6 and T15’s resource cost driver
  • 47. rate"6% 5 Reduce T7, T16’s processing time 5% Process innovation T7 and T16’s resource cost driver rate"2% 6 Reduce T7, T16’s processing time 10% Adding L2’s function T7 and T16’s resource cost driver rate"8% Note: – means not changed. Table 6. Impacts of select variables on process performance. EDD SPT FIFO No. Avg.p IncsR Avg.p IncsR Avg.p IncsR 1 469.29 0.01 562.59 7.52 469.29 0.01 2 469.32 0.01 589.45 12.65 469.32 0.01 3 482.60 2.84 526.65 0.65 482.60 2.84 4 482.73 2.87 525.93 0.51 482.73 2.87 5 469.96 0.15 523.35 0.02 469.96 0.15 6 470.66 0.30 523.43 0.03 470.66 0.30 7 469.26 0.00 606.74 15.95 469.26 0.00 8 482.48 2.82 511.43 2.26 482.37 2.79 9 470.85 0.34 523.26 0.00 471.01 0.37 Note: Avg.p¼average process throughput under all three order patterns and IncsR¼Avg.p/current process throughput%.
  • 48. International Journal of Production Research 1787 The authors provided a useful manufacturing process modelling method and simulation based analysis framework to support MPA. It has the following major advantages: . The compound workflow model (CWM) provides a graphic process description for MPA. It introduces rich model elements, for example, logic nodes, resource pool, and ECA rules, to provide a flexible description of various constraints in the manufacturing process. Also, it can be used directly by simulation to study the impacts of scheduling policy and analyse the process performance. . The analysis framework gives a step-to-step guide for MPA with process modelling and simulation techniques. Despite the usual steps of setting objectives, selecting key performance measures, setting targets and identifying initiatives, the target verification is introduced into the framework to build a bridge between the decision making level that sets targets and operation level that have details about manufacturing. . The two-step simulation method provides an effective way to quantitatively identify cause-and-effect relations needed in MPA. Also, it
  • 49. provides a general framework to take the manufacturing environment and impacts of scheduling policy into consideration. Further work will consider the framework to identify, evaluate and determine the process improvement solutions when cause-and-effect relations are quantitatively defined. More factors, such as quality, may be studied in the framework with support of modelling and simulation technology. References Altiok, T., 1996. Performance analysis of manufacturing systems. New York, NY: Springer-Verlag. Askin, R. and Standridge, A., 1993. Modeling and analysis of manufacturing systems. New York, NY: John Wiley & Sons Inc. Aversano, L, Canfora, G., De Lucia, A. and Gallucci, P., 2002. Business process reengineering and workflow automation: A technology transfer experience. The Journal of Systems and Software, 63, 29–44. Challis, D., Samson, D. and Lawson, B., 2002. Integrated manufacturing, employee and business performance: Australian and New Zealand evidence. International Journal of Production Research, 40, 1941–1964. Cooke, D.L., Rohleder, T.R. and Silver, E.A., 2004. Finding effective schedules for the economic lot
  • 50. scheduling problem: A simple mixed integer programming approach. International Journal of Production Research, 42, 21–36. Ellis, C.A. and Nutt, G.J., 1993, Modeling and enactment of workflow systems. In: M.A. Marsan, ed. Application and theory of petri nets. Berlin, Germany: Springer- Verlag, 1–16. Fan, Y., Luo, H.B. and Lin, H.P., 2001. Fundamentals of workflow management technology. Beijing, China: Tsinghua University Press/Springer-Verlag (In Chinese). Goldratt, E.M. and Cox, J., 1992. The goal: a process of ongoing improvement, 2nd ed. New York, NY: North River Press. Gupta, Y.P., Evans, G.W. and Gupta, M.C., 1991. Review of multi-criterion approaches to FMS scheduling problems. International Journal of Production Economics, 22, 13–31. Hammer, M. and Champy, J., 1993. Reengineering the corporation: a manifesto for business revolution. New York, NY: Harper Collins. 1788 H. Lin et al. Kaplan, R. and Norton, D., (Jan–Feb) 1992. The balanced scorecard-measures that drive performance. Harvard Business Review, 70, 71–79.
  • 51. Kaplan, R. and Norton, D., 1996. The balanced scorecard: translating strategy into action. Boston, MA: Harvard Business School Press. Kaplan, R. and Atkinson, A., 1998. Advanced management accounting, 3rd ed. Englewood Cliffs, NJ: Prentice Hall Inc. King, W.R., 1994. Process reengineering: the strategic dimensions. Information Systems Management, 11, 71–73. Lee, D.Y. and DiCesare, F., 1994. Scheduling FMS using Petri nets and heuristic search. IEEE Transactions on Robotics and Automation, 10, 123–132. Lin, H.P., Fan, Y. and Loiacono, T.E., 2004. A practical scheduling method based on workflow management technology. International Journal of Advanced Manufacturing Technology, 24, 919–924. MacCarthy, B.L. and Liu, J.Y., 1993. Addressing the gap in scheduling research: a review of optimization and heuristic methods in production scheduling. International Journal of Production Research, 31, 59–79. Mohan, C., Agrawal, D., Alonso, G., Abbadi, A.E., Gunthor, R. and Kamath, M., 1995. Exotica: a project on advanced transaction management and workflow systems. SIGOIS Bulletin – Special Issue on Business Process Management Systems: Concepts, Methods and Technology, 16, 45–50.
  • 52. Mohan, C., Recent trends in workflow management products, standards, and research, 1997. Available online at: http://www.almaden.ibm.com/cs/exotica/wfnato97.pdf (accessed 28 August 2007). Potts, G.N. and Kovalyov, M.Y., 2000. Scheduling with batching: a review. European Journal of Operational Research, 120, 228–249. Proth, J.M. and Minis, I., 1995, Planning and scheduling based on Petri nets. In: M.C. Zhou, ed. Petri nets in flexible & agile automation. Norwell, MA: Kluwer Academic, 109–148. Shih, H. and Sekiguchi, T., 1991. A timed Petri net and beam search based on-line FMS scheduling system with routing flexibility, in Proceedings of 1991 IEEE international conference on robotics and automation, Sacramento, CA, April, pp. 2548– 2553. Sox, C.R., Jackson, P.L. Bowman, A. and Muckstadt, J.A., 1999. Review of the stochastic lot scheduling problem. International Journal of Production Economics, 62, 181–200. Tan, W. and Khoshnevis, B., 2000. Integration of process planning and scheduling-a review. Journal of Intelligent Manufacturing, 11, 51–63. Toh, K.T., Newman, S.T. and Bell, R., 1997. An Architecture for Information Specification Based on an SME Enterprise Model, in Proceedings of the IEE 5th
  • 53. international conference factory 2000: the technology exploitation process, Institution of Electrical Engineers, Cambridge, UK, pp. 456–463. Tsai, C.C., Chu, C.H. and Barta, T.A., 1997. Modeling and analysis of a manufac- turing cell formation problem with fuzzy mixed-integer programming. IIE Transactions, 29, 533–547. Van derAalst, W.M.P., 1998. Three good reasons for using a Petri-net-based workflow management system, in Proceedings of the international working conference on information and process integration in enterprises (IPIC), edited by S. Navathe and T. Wakayama, Cambridge, Massachusetts, Nov, 1996, pp. 179–201. [Also in Information and process integration in enterprises: rethinking documents. Kluwer Academic Publishers: Norwell MA, pp. 161–182. Viswanadham, N., 1999. Analysis of manufacturing enterprises: an approach to leveraging value delivery processes for competitive advantage. Norwell, MA: Kluwer Academic Publishers. Winograd, T. and Flores, R., 1987. Understanding computers and cognition. Reading, MA: Addison- Wesley. Workflow Management Coalition, The workflow reference model, Document number TC00-1003, 1995.
  • 54. Workflow Management Coalition, Workflow management coalition terminology and glossary (Document number WfMC-TC-1011), Technical Report, Brussels, 1996. International Journal of Production Research 1789 Xiong, H.H., Zhou, M.C. and Caudill, R.J., 1996. A hybrid heuristic search algorithm for scheduling flexible manufacturing systems, in Proceedings of 1996 IEEE international conference on robotics and automation, Minneapolis, MN, April, pp. 2793– 2797. Yun, Y.S. and Gen, M., 2002. Advanced scheduling problem using constraint programming techniques in SCM environment. Computers and Industrial Engineering, 43, 213–229. Zhou, M.C. and Venkatesh, K., 1999. Modeling, simulation, and control of flexible manufacturing systems: a petri net approach. River Edge, NJ: World Scientific Publishing Company. 1790 H. Lin et al. Economica, 57. 485-93
  • 55. Pattern of Trade between Underemployed Economies By RAVEENDRA N . BATRA and HAMID BELADI Southern Methodist University and University of Dayton Final version received 6 September 1989. Accepted 13 December 1989. In this paper, we have analysed the factors determining the pattern of trade between underemployed economics. We find, among other things, that a iow-wage, iand-abundant country exports the iand-using, labour-intensive product to a high-wage, capital-abundant country. We also find conditions under which a high-wage, capital-rich country may export the labour-iniensive product (the Leontief Paradox). INTRODUCTION The following facts should be kept in mind while formulating a theory of a country's pattern of trade. 1. The vast majority of trading countries have suffered from chronic unemploy- ment throughout this century. Even many developed economies such as the UK and USA experienced low to high unemployment during the eariy 1920s, throughout the 1930s, at the end of the 1950s, during the eariy 1960s and throughout the 1970s and 1980s. 2. Some countries rich in natural resources export land-using
  • 56. (or land-inten- sive) products, whereas capital-abundant countries mostly export capital- intensive goods, but at times export the labour-intensive products, some- thing that has inspired the literature on the Leontief Paradox. 3. In spite of the presence of trade, the capital-rich countries have higher wages but lower capital rentals than the labour-surplus and/or land-rich countries—a fact conflicting with the factor-price equalization theorems of the popular Heckscher-Ohlin model. 4. Labour-rich countries usually export either labour-intensive or iand-using commodities. The purpose of this paper is to formulate a theory of trade that explains the 'stylized facts" mentioned above. Neither of the two popular theories, the Ricardian model and the Heckscher-Ohlin model, is compatible with these facts. Both of these models ignore unemployment and are couched in terms of one or two factors, whereas a realistic theory of international trade must assume at least three factors—labour, capital and land (or natural resources)— which have been incorporated into the empirical literature but not into a theory of trade patterns. In order to explain the pattern of trade, we first construct a two-
  • 57. sector, three-factor mode! of an underemployed economy. We find that the specific- factor model, which has recently regained its lost popularity, is ideal to capturing the facts mentioned above. L ASSUMPTIONS AND THE MODEL Let us assume that there are two sectors, X and Y, with X using capital and labour and Y using capital, labour and land. (X could represent all manufactur- ing where land is relatively insignificant, and Y could represent agriculture, 486 ECONOMICA [NOVEMBER mining, forestry and fisheries. I Production functions are linearly homogeneous; producers face perfect markets in goods, capital and land, but not in labour, where real wage is rigid, causing general unemployment in the economy. Capital and labour are fully mobile and employed, and all factors are in inelastic supply. In short, we make all the assumptions of the well-known two-sector, specific-sector model, except that the real wage is determined institutionally." Let Cij be the ratio of the ith factor and thejth product {i = K, U ^ and
  • 58. j = x,y) where K is capital, L is labour and V is land. With full employment of capita] and land, we have (1) CK.x + C K , y = ^ and (2) CvvV'= v; where K and V are inelastic supplies of capital and land. With producers producing in perfect markets, the price of each product equals the unit cost. Let Y be the numeraire, so that its price equals one, F be the relative price of X, w be the real wage rate, r the real rental of capital and p the real rental of land. Then (3) wC and (4) H-C, , With linearly homogeneous production functions, each input- output coefficient depends only on factor prices. Therefore (5) and With this equation, the production side of our model is complete. This is a
  • 59. system of nine variables (X, Y, C:,, C , r and p), nine equations and four parameters (w, P, K and V). II. THE FACTOR-PRICE DEFINITION OF FACTOR ABUNDANCE Let us assume that there are two countries, a home country (H) and a foreign country (F). Since labour is in excess supply in both countries, we will first define relative factor abundance in terms of fully utilized factors. Suppose the home country is rich in capital but poor in land relative to the foreign country. Then we define H to be capital-abundant and F to be land- abundant if, in the absence of trade, (7) In other words, in the absence of trade, the capital-rich country has a higher rental of land relative to that of capital than does the foreign country. What 1990] PATTERN OF TRADE BETWEEN UNDEREMPLOYED ECONOMIES 487 about the wage rate? Since usually the capital-rich countries are high-wage economies, we assume that (8) Wft s wj.
  • 60. In order to use (7) and (S) in our analysis, we need to analyse the relationship between factor and commodity prices. Totally differentiating (3) and (4), we obtain (9) and ( 1 0) d^yW* + dKyr* + Bvyp* = 0 where the asterisk denotes proportional change and $ are the factor shares.^ Thus, r* = (dr/r) and so on. From (9) and (10), we obtain - - « . ^ W ( and In obtaining (11)-(13), we have made use of the fact that factor shares add to one. Thus, Equation (13) shows the effect of P and w on the factor-price ratio {pi r), as ( p * - r * ) / P * < 0 . For any given w, a rise in P unambiguously causes a fall in ip/r), whereas for any P, a rise in w causes a rise in (p/r), provided 6i_^> Oi^y. Since w is constant, a rise in P, the relative price of X, must cause a rise in r, otherwise average cost in X will not rise; but since Py = 1 is constant, p must fall, because with w given, r and p must move opposite to each
  • 61. other. Otherwise average cost in Y will not remain constant. On the other hand, for any P, a rise in w must cause a fall in r in X and hence in Y as well. Since w rises and r falls, the reward of land depends on the labour intensity of Y relative to X. If 0Ky0Lx > ^Lv^Kxy then in the physical sense X is labour- intensive relative to Y, and ( P * / R ' * ) > 0 . When the capital-labour ratio in X and Y is the same, then a rise in w combined with a fall in r equally affects the unit cost in Y which is compatible with the fact that P,, is unchanged at one. However, if Y is capital-intensive relative to X, then the relative unit cost in Y falls, and for its price to remain constant p must rise. Thus, when then ( P * / H ' * ) > 0 . On the other hand, when labour share is higher in Y, so that 0LX < ^LV, a rise in w hurts Y more than X. Here (p/r) must fall as w rises (see (13)). 488 ECONOMICA [NOVEMBER The two forces that affect (p/r) are thus P and w, but not factor supplies. Figure 1 displays these relationships. The negatively sloped curve AB shows
  • 62. that as P rises ip/r) falls for any w. Then as w rises, the curve AB shifts up to CD (where di^ > 0^.), or down to EF (where Bu < ^/.y). The relationships obtained in Figure 1 can be used to analyse the effect of factor endowments on the pattern of trade. Let us assume that production functions are the same between the two countries. (This is also an assumption of the Heckscher-Ohlin (H-0) theory.) For the time being, let us also assume that the wage rates are the same as well; that is, ŵ = w,. Under these assump- tions, the same relationship between the factor-price ratio and the commodity- price ratio applies lo both countries. Let FH be such a common curve in Figure 2. Since the home country is relatively capital-abundant, its factor-price ratio (p/r) is placed above the factor-price ratio of the foreign country (see (7)). As a result, (14) P,<P^, which shows that under autarky the home price of X is lower relative to that in the foreign country. This means that, in the presence of non- intersecting social indifference curves (which we assume hereafter), the home country will export X and the foreign country will expon Y, the land-using product.' The following theorem is now immediate.
  • 63. F FIGURE I p/r Ux FlQURE 2 1990] PATTERN OF TRADE BETWEEN UNDEREMPLOYED ECONOMIES 489 Theorem 1. If the institutionally determined real wages between the two countries are close to each other, then the country relatively well endowed in land or natural resources exports the land-using product, and the relatively capital-rich country exports the other product. Note that this is a very general theorem, and factor intensities play no role in it. This may explain the trade pattern of most oil-exporting countries, such as Saudi Arabia, Kuwait, United Arab Emirates, Mexico, Venezuela, etc., which are rich in oil and export this product abroad. Other countries, such as Canada, Australia and some Third World countries, export minerals for the same reason. Furthermore, it should be noted that the rigid wage rate may be 'too low' and the country may have to import labour from
  • 64. abroad. Thus, the model may also refer to trade between the Arab countries and the West. Many of the Arab countries in fact import labour from Asian countries. Let us now relax our assumption of similar wage rates between the trading partners and assume that the capital-rich country has the higher real wage than the land-rich country. If the labour share of the two sectors is the same, i.e. if L ̂ x = ^Ly., then w has no effect on (p/r). In this case. Theorem 1 continues to hold regardless of the inter-country wage differential. In most countries the land-using sectors, especially agriculture and fisheries, also employ larger number of workers per unit of output than the other sector. This is certainly true of developing countries, but may also be valid with some developed economies. It is interesting to note that the autarkic values of (p/r) depends not only on the levels of endowments of different factors but also on the level of the given wage rate. This is clear from equation (13), where {p/r) is seen to depend on w and P. The endowment effect in this case is via the relative price, P. In other words, even if two countries are endowed with the same amounts of the various factors, ip/r) can have different values in the two countries. Let us then assume that Bt^y> fl^v Here a rise in w reduces
  • 65. {p/r) at any P. If w^ > w^, then the home country's curve relating {p/r) and P will lie below FH in Figure 2. Suppose it is given by hh', whereas in the foreign country this relationship is still given by FH. Then the home autarky- price ratio is given by PJ,. Since it is even smaller than before, we conclude that the home country will still import the land-using product and the foreign country will export it. All this leads to the following theorem. Theorem 2. A relatively low-wage, land-abundant country exports the land- using product if the latter's labour share is no less than the labour share of the other product, which in turn is exported by the relatively high-wage, capital-abundant country. What is the role of the factor intensities in this theorem? Factor intensities can be defined in the physical sense or in the value sense. In the value sense, the factor intensities can be defined in terms of factor shares. Thus, Y may be said to be labour-intensive relative to X if ff^. > L ̂ X- But this implies that or 490 ECONOMICA [NOVEMBER (p/r)
  • 66. Therefore, if Bi_v > Bi_^, then ê x > B^y, which means that X is capital-intensive relative to Y in the value sense. In terms of Theorem 2, a high- wage, capital- abundant country exports X when fl^ > L ̂ X or &K,. <^KJC- Theorem 2 then implies that a high-wage, capjtal-rich country exports the capital-intensive product. On the other hand, a low-wage country may also be defined as a labour- abundant country. Thus, a land-abundant country with lower real wage may be said to be a labour-abundant country with lower real wage may be said to be a labour-abundant country as well. Theorem 2 then implies also that a labour-rich country exports the labour-intensive product, as Biy> Bj^^. AM this leads to another theorem. Theorem 3. A high-wage, capital-abundant country exports the capital-inten- sive product, and a low-wage, land- and labour-abundant country exports the land-using, labour-intensive product. This theorem is somewhat reminiscent of the Heckscher-Ohlin theorem which highlights the role of factor intensities and inter-country factor endowments. What happens if the land-using product is not labour-intensive
  • 67. in the value sense, so that 0^ < ^L. ? Here Theorem 3 may not hold, in which case the well-known Leontief Paradox can occur* If ^L.<^tA, then from (13). {p/r) rises with a rise in w. This case is illustrated in Figure 3, where, unlike in Figure 2, hh' lies above FH., and the home-autarky price ratio may or may not be below the foreign- autarky price ratio. Figure 3 illustrates the case where Ph<P,, so that the high- wage, capital-abundant home country will stilt export X but X is now the labour- intensive product. Similarly, the low-wage, land-abundant country exports Y, which is capital-intensive relative to X. This is the Leontief Paradox. Thus, our model, which yields a Heckscher-Ohlin type of theorem, is also capable of explaining the Leontief Paradox. III. FACTOR PRICES UNDER FREE TRADE Under free trade, the Heckscher-Ohlin theorem gives rise to a single outcome, namely that absolute and relative factor rewards are completely equalized 1990] PATTERN OF TRADE BETWEEN UNDEREMPLOYED ECONOMIES 491 between countries. This is one of the most serious flaws of this
  • 68. theorem, because we live in a trading world where factor prices are far from equal. In our model, however, a variety of outcomes is possible in the free trade equilibrium. Let us first consider the least likely outcome. Suppose, in the absence of trade, that real wages are the same internationally. In this case one common FH curve applies to both countries in Figure 4. Assume that transport costs are zero or negligible; then the same product-price ratio prevails in both countries in the free trade equilibrium. Let Pg be such a price ratio. When FH applies to both countries, then {p/r) is the same in both countries in the free trade equilibrium. This is the case where the absolute factor prices will also be equalized. Even if wages differ between H and F, the FH curve applies to both countries if 0,^ = 6i^,.. In this case (p/r) will be similar internationally but absolute factor prices will differ. Since iv̂ > w,, r,, < rj. This is because r and w are negatively related. And since {p/r)h = {p/r)f, then Ph<pf- Thus, here is a case where relative factor prices of land and capital are globally equal but absolute factor prices are not. All this leads to the following theorem. Theorem 4. If wages are the same across the countries, then free trade leads to an equalization of all factor prices. If the capital-abundant
  • 69. country is the high-wage country but labour shares are the same between the two sectors, then the relative factor prices of land and capital are equalized but the capital rental and the land rent are lower in the capital-abundant country than in the land-abundant country. When SL^ < 6i_y and w>, > w,, much of Theorem 4 continues to be valid, although relative factor prices of land and capital in H and F are no longer the same. In this case, the home curve representing the relationship between ip/r) and P lies below FH, which now represents F. In Figure 4, the home curve is now given by hh and in free trade equilibrium, {p/ r)h is given by OA which lies below (p/r)^, the factor-price ratio in F. Still, when w^ > Wf, r,, < Tf. This is because, from (11), it is clear that (15) r = r{P,w) with Tp = {dr/dP) > 0 and r^. = (dr/dw) < 0, for all values of 0^. and Ot,.. Thus, with H';, > Wf, rf<r,. Since (p/r),, <ip/r)j in free trade, clearly Pf<pi, in the free trade equilibrium. p/r B p/f).
  • 70. A F s V ^ ^ ^ . * FIGURE 4 492 ECONOMICA [NOVEMBER When ^L, > di_y, the home curve (h'h') now lies above FH in Figure 4. In the free trade equilibrium, (16) {plr),>{pfr)f, but since ŵ > ny, ^s'^^s-'" view of (16), however, p/may no longer be lower than ph under free trade. The following theorem is now immediate. Theorem 5. Under free trade, the high-wage, capital-rich country has a lower rental of capital than the low-wage country, but the international relationship of the land rental depends on factor intensities.
  • 71. IV. TRADE AND FACTOR PRICES In the Heckseher-Ohlin model, trade benefits the country's abundant factor but hurts its relatively scarce factor. In our model, assuming that the land- abundant country exports the land-using product and the capital-abundant country exports the other product (which is ensured when 0(.,. ^^(_J, trade will lower the reward of land and raise the reward of capital in the home country, and do the opposite in the foreign country. This is because in this case, under autarky, P^ < P,. Therefore, in the presence of profitable trade, the relative price of X rises in the home country and falls in the foreign country. Consequently r will rise in H but fall in F, and p will fall in H and rise in F. TTie following theorem is now immediate. Theorem 6. When the labour share in the land-using sector is no lower than that in the other sector, trade benefits a country's abundant factor and hurts the scarce factor.'' It should be noted that Theorem 6 may not be valid if 6^^ > Bi_y. V. CONCLUSIONS Using a two-sector, three-factor model in which land is a specific factor and
  • 72. wages are institutionally determined, we have analysed the factors determining the pattern of trade between underemployed economies. Our results are com- patible with many observed facts. Under the assumptions usually used in the H-0 model, we find that a low-wage, land-abundant country exports the land-using, labour-intensive product to a high-wage, capital- abundant country. On the other hand, if the low-wage country is said to be labour- abundant, then a labour-abundant country exports the land-using, labour- intensive good and the capital-rich country exports the capital-intensive good. This is nothing but a version of the Heckscher-Ohlin theorem derived in a model of unemployment. The paper also derives plausible conditions under which a high- wage, capital-rich country may export the labour-intensive product. This tends to explain the Leontief Paradox. Under free trade, if wages are the same across countries, all factor prices are equalized. However, if the capital-abundant country is a high-wage country, then the reward of capital is higher in the low-wage country even under free trade. Thus, unlike the Heckscher-Ohlin model, a variety of outcomes regard- ing factor prices in free trade is possible in our model.
  • 73. 1 9 9 0 ] PATTERN OF TRADE BETWEEN UNDEREMPLOYED ECONOMIES 4 9 3 Finally, we conclude that under realistic conditions trade benefits the country's relatively abundant factor and hurts its relatively scarce factor.* ACKNOWLEDGMENT We wish to thank two anonymous referees for helpful comments to a previous draft of this paper. NOTES 1. The earlier trade models of rigid wages have mainly involved the two-sector, two-factor Heckscher-Ohlin type of model; see e.g. Das (1981). Yu {1982) and BhandaH (1986). The main weakness of this type of model is that it leads to a linear transformation curve or constant average costs in the industries. The production side thus yields limited and unrealistic results. In an earlier paper (1988), Batra and Beladi have shown that, even with rigid real wages, the specilic*factor model used here generates increasing average cost functions for the two indus- tries. The input-output coefficient lechnique utilized here greatly simplifies the analysis. For another application of this technique, see Lahfri (1983). 2. In obtaining these equations, it must be noted that the competitive producer, facing given
  • 74. factor prices, equates the derivative of this unit cost to zero, thereby minimizing his average cost. Thus, ^y + n/Q,, + pdCvy = dAC, = 0 where 4 C , is the average cost of Y. Similarly for X. 3. In order to see the importance of this assumption in the context of the factor-price definition of factor abundance and the Heckscher-Ohlin theorem, see Batra {1973, Chapter 3). 4. For the latest analysis of the Leontief Paradox, see Casas and Choi (1985). 5. See Pattanaik (1974) for an application of this type of analysis to the effects on savings in a developing economy. 6. In this paper we have ignored [he well-known physical definition of international factor abundance, and have focused only on the factor-price definition. This is because labour is not fully employed and does not act as a constraint on the two outputs. However, a physical type of definition does suggest itself. We could define country H to be capital-abundant and country F to be labour-abundant, if with By using a fully fledged production model constructed by the authors elsewhere (1988), it is possible to show thai ail our results are valid in terms of the physical definition as well. In the interest of brevity, however, we leave this task to the reader.
  • 75. REFERENCES B A T R A , R. (1973). Studies in the Pure Theory of International Trade. New York: St Martin's Press. ——and B E L A I J I , H . (1988). Specific factors, unemployment and trade theory. WeUwirtschaftliches Archiv, 124,435-43. B H A N D A R I , J . S. (1986). Commercial Liberalization in Less-Developed Countries. New York: Praeger. CASA.S, F. R. and C H O I , K, E . (1985). The Leontief Paradox: continued or resolved. Journal of Political Economy, 93, 610-15. D A S , S. P, (1981). Effect of foreign investment in the presence of unemployment. Journal of International Economics. I I , 2 4 9 - 5 7 . LAHtRi, S A J A L (1983). Capacity constraints, alternative technologies and input-output analysis. European Economic Review, 27, 147-53. P A T T A N A I K , P. K. (1974). Trade, distribution and saving. Journal of International Economics, 4, 77-81. Yu, E D E N (1982). Unemployment and the theory of customs union. Economic Journal, 92,399-404.
  • 76. Copyright of American Economic Review is the property of American Economic Association and its content may not be copied or emailed to multiple sites or posted to a listserv without the copyright holder's express written permission. However, users may print, download, or email articles for individual use. How Does the Global Economic Environment Influence the Demand for IMF Resources? SELIM ELEKDAĞ� The main objective of this paper is to quantify the relationship between the global economic environment and Stand-By Arrangements (SBAs) with the IMF. The results suggest that oil prices, world interest rates, and the global business cycle are the most influential indicators that affect the number of SBAs being requested. In addition, the empirical model seems to have reasonable accuracy when predicting SBAs. Furthermore, when oil prices, interest rates, and the global business cycle are adversely shocked by one
  • 77. standard deviation, the conditional probability of an SBA nearly doubles, implying an increase from about 6 to 12 SBAs. More critically, the model suggests that even a steady deterioration of the global economic climate would imply increasingly harsher conditions for developing and emerging market countries, which may in turn increase the demand for IMF resources significantly. [JEL F01, F33, F34, F42] IMF Staff Papers (2008) 55, 624–653. doi:10.1057/imfsp.2008.4; published online 17 June 2008 Considering the favorable global economic environment over the pastfew years, it is probably not much of a surprise that the number of IMF arrangements approved recently is well below historical averages. But what—if any—is the link between global economic and financing conditions and a country’s potential request for IMF financial assistance? The main � Selim Elekdağ is an economist with the IMF Research Department. The author is particularly indebted to Bob Flood, Rex Ghosh, Bikas Joshi, Ayhan Kose, Alan MacArthur, Gian Maria Milesi-Ferretti, Alex Pitt, Bjorn Rother, and Juan Zalduendo for their support and helpful suggestions.
  • 78. IMF Staff Papers Vol. 55, No. 4 & 2008 International Monetary Fund 624 objective of this paper is to rigorously quantify the relationship between the global economic environment and the number of Stand-By Arrangements (SBAs). Formal econometric analysis is required to quantify the relationship between global economic conditions and the potential demand for SBAs. Using panel data techniques, this paper reports results based on 412 SBAs among 169 members over a period spanning 1970–2004. We focus on SBAs because they are the main nonconcessional IMF facility designed to provide short-term balance of payments (BOP) assistance to members. 1 Global activity and liquidity indicators as well as country- specific factors were used to identify determinants influencing the number of SBAs. The three main global factors affecting the probability of requesting IMF financial assistance were found to be oil prices, world interest
  • 79. rates, and the global business cycle. The most important country-specific factors identified include the member’s real GDP growth, the depreciation of its currency vis-à-vis the U.S. dollar, its international reserve cover, and whether or not it is an energy exporter. The estimates are robust to changes in model specification, as well as choice of global and country-specific explanatory variables. Changes in global economic conditions significantly affect the probability of a country’s demand for IMF resources. A scenario in which the three global factors are adversely shocked from their respective averages by one standard deviation nearly doubles the conditional probability of an SBA. Furthermore, when oil prices and interest rates are evaluated at their respective historical peaks, and the global business cycle is set at its deepest trough in the sample, the conditional probability almost quadruples to about 14 percent, implying an increase from approximately 6 to 23 SBAs. The results are intuitive and consistent with economic theory. Among other things, a rise in world interest rates may increase a member’s debt service costs and limit access to capital markets, higher oil prices would raise
  • 80. the import bill (for net oil importers), and a global recession could decrease international demand for a member’s exports. More critically, even if global economic conditions worsen gradually, the probability of an approved SBA increases disproportionately owing to the underlying nonlinear nature of the econometric model. Such adverse developments would cause a deterioration in a member’s current account balance and could lead to acute BOP problems. If a country does not have sufficient access to international capital markets, that member may request an IMF arrangement to mitigate the consequences of potentially severe macroeconomic adjustment. The estimated regressions may also be used to predict the numbers of SBAs. There are indications that the framework has reasonable predictive accuracy. Whereas the actual number of SBAs approved in 2004 was 6, the model predicts between 5 and 5.7 SBAs in 2004. Furthermore, out-of-sample 1 See the earlier working paper version of this paper, Elekdağ (2006). DEMAND FOR IMF RESOURCES 625
  • 81. predictions for 2005 ranged between 5.7 and 6.1, whereas the actual number of approved SBAs was also 6. Despite the importance of this topic, research on the empirical link between global economic conditions and IMF financing is scarce. In line with the survey of Joyce (2004), only Bird and Rowlands (2002) and Conway (1994) included global economic factors—which was in both cases only a measure of world interest rates. In this context, this paper builds on the literature by emphasizing the importance of global economic conditions and is also the only study that finds a critical role of oil prices in the demand for IMF financial assistance. Even though (in contrast to Bird, Hussain, and Joyce, 2004; and Marchesi, 2003) Barro and Lee (2005); Joyce (1992); and Knight and Santaella (1997) include time dummies to control for common effects of external factors, these frameworks may not be well suited for prediction. 2 Further review of the literature also indicates that most of the studies rely on short sample periods and therefore miss important events, including the financial crises of the late 1990s. In fact, only Barro and Lee
  • 82. (2005); Bird and Rowlands (2001); Sturm, Berger, and de Haan (2005); and Trudel (2005) include a sample period through at least 2000. Furthermore, as discussed in detail below, the country coverage in this paper exceeds that in other studies, which could be critical to avoid econometric issues such as selection bias. Last, other than this paper, only Barro and Lee (2005) and Oatley and Yackee (2000) distinguish among the various types of IMF facilities. The results of this paper have relevance for the IMF, for policymakers throughout the IMF membership, and for capital market analysts. The framework developed in this paper underscores cyclical factors that are relevant for future IMF lending capacity. This is especially important because unusually harsh economic conditions would likely imply a bunching of SBA requests—some of which may be exceptional access cases. In this context, this paper is also pertinent for assessing the prospects for the IMF’s future income position, which depends on the amount of IMF credit outstanding. I. IMF Arrangements from 1970 to 2004 The IMF is best known as a financial institution that provides resources to
  • 83. member countries experiencing temporary BOP problems. The IMF makes financial resources available to members in the general resources account under a range of policies and facilities, including credit tranches. More than a decade after its creation, the IMF developed policies on the use of its resources in what came to be known as credit tranches. SBAs were developed as the main instrument through which members would access the credit 2 For example, Barro and Lee (2005) partition their sample into five 5-year periods, whereas Knight and Santaella (1997) use an indicator variable that takes the value of unity from 1979 to 1991 when using a sample spanning only 1973–91. Selim Elekdağ 626 tranches, and are available for any BOP need. Access under SBAs is limited to 100 percent of quota annually and 300 percent of quota cumulatively, although in exceptional circumstances access beyond these limits has been granted. Although the IMF has used a variety of instruments to support
  • 84. members’ BOP needs, the most utilized facility is the SBA. Figure 1 depicts the number of SBAs, Extended Fund Facilities (EFFs), first credit tranche arrangements (FCTAs), and concessional facilities (the Structural Adjustment Facility, Enhanced Structural Adjustment Facility, and Poverty Reduction and Growth Facility) against the backdrop of the IMF membership. 3 Table 1 provides the distribution of facilities across selected time periods. Even though SBAs historically outnumber other facilities, concessional IMF financing is increasing in importance. Although not shown, during the past decade exceptional access (especially in response to financial crises) and precautionary arrangements have gained prominence, whereas blended arrangements have been approved much less frequently. 4 Against this Figure 1. Facilities and IMF Members 0 5 10
  • 85. 15 20 25 30 35 40 1970 1972 1974 1976 1978 1980 1982 1984 1986 1988 1990 1992 1994 1996 1998 2000 2002 2004 0 20 40 60 80 100 120 140 160 180 200
  • 86. SBAs (left scale) EFFs (left scale) FCTAs (left scale) SAF, ESAF, and PRGFs (left scale) Members (right scale) Source: IMF, Policy Development and Review Department database. Note: SBA¼Stand-By Arrangement; EFF¼Extended Fund Facility; FCTA¼First Credit Tranche Arrangement; SAF¼Structural Adjustment Facility; ESAF¼Enhanced Structural Adjustment Facility; PRGF¼Poverty Reduction and Growth Facility. 3 Appendix I in the working paper version of this paper provides further details on IMF policies and facilities, including the various arrangements used to access IMF credit. See Elekdağ (2006). 4 The 412 SBAs identified during 1970–2004 do not include blended arrangements. DEMAND FOR IMF RESOURCES 627 background, we explore below how global economic and financial developments affect the potential demand for IMF resources.
  • 87. II. Indicators of the Global Economic Environment Determinants of the global economic environment can broadly be grouped into activity and liquidity indicators. Controlling for country- specific policies and developments, the main conjecture of this paper is that world interest rates, oil prices, and the global business cycle are the most robust indicators of the global economic environment that influence the demand for IMF financial resources. 5 Interest Rates Shown in Figure 2 is the U.S. federal funds rate adjusted by U.S. consumer price index (CPI) inflation against the backdrop of SBAs during 1970–2004. Note that with the onset of the Volker disinflation in the early 1980s, both the real federal funds rate and the number of SBAs reach their historic peaks. The parallel movements between SBAs and the interest rate in the early 1990s are also noteworthy. Table 1. IMF Arrangements, 1970–2004 Total 1970–79 1980–89 1990–99 2000–04 1995–2004 Approved 739 166 243 238 92 212
  • 88. GRA 556 166 195 154 41 114 SBAs 412 93 153 126 40 95 FCTAs 79 62 15 2 0 1 EFFs 65 11 27 26 1 18 SAFs, ESAFs, and PRGFs 183 0 48 84 51 98 Blended arrangements 33 0 25 7 1 4 Source: IMF, Policy Development and Review Department Stand-By Operations Division database. Note: SBA=Stand-By Arrangement; FCTA=first credit tranche arrangement; EFF=Extended Fund Facility; SAF=Structural Adjustment Facility; ESAF=Enhanced Structural Adjustment Facility; PRGF=Poverty Reduction and Growth Facility; GRA=General Resource Account. Approved refers to the total number of arrangements approved in the year under consideration. Blended arrangements are concessional arrangements (SAF, ESAF, PRGF) combined with an EFF or SBA to supplement IMF financial assistance to a member. 5 Appendix Table 3 in the working paper version of this paper contains a comprehensive description of the data. See Elekdağ (2006).
  • 89. Selim Elekdağ 628 Oil Prices The monthly nominal and real average petroleum spot prices (APSP) are displayed in Figure 3. 6 Even though nominal oil prices have reached record levels, prices adjusted for inflation are still below the peaks of the late 1970s. Against the background of SBAs, Figure 4 shows the real APSP as a deviation from trend. 7 Note that with the rise in oil prices, there is a trend increase in SBAs from the mid-1970s until the early 1980s. With the spike in oil prices in 1979, the number of approved SBAs more than doubles, increasing from 8 in 1978 to 20 in 1979. It is also worth highlighting how oil prices and SBAs move in tandem during the 1990s. With the gradual decline in the APSP in the mid-1990s, the number of SBAs decreased from 21 in 1995 to 5 in 1998.
  • 90. Figure 2. Interest Rates and Stand-By Arrangements 0 5 10 15 20 25 30 35 1970 1972 1974 1976 1978 1980 1982 1984 1986 1988 1990 1992 1994 1996 1998 2000 2002 2004 -4 -2 0 2 4 6 8 Stand-By Arrangements (left scale) U.S. real short-term interest rate (right scale)
  • 91. Sources: IMF, World Economic Outlook and Policy Development and Review Department databases; and author’s calculations. Note: Real U.S. short-term interest rate is calculated by subtracting U.S. CPI inflation from the federal funds rate. 6 The APSP is calculated using a simple average of U.K. Brent, West Texas Intermediate, and Dubai Fateh spot petroleum prices. The real APSP was scaled using the U.S. CPI, because world inflation is contaminated by episodes of hyperinflation. 7 To avoid running spurious regressions, the (log) real APSP is detrended using a log- linear trend to ensure stationarity of the real APSP. Deviations from trend were used rather than growth rate, for example, to capture the burden of increased fuel costs more accurately. Consider Figure 3, which shows that after the 1973 OPEC shock, when oil prices roughly tripled, prices did not revert to their original single-digit levels. The first-differenced series would not capture this persistence, whereas the linearly detrended series does. DEMAND FOR IMF RESOURCES 629
  • 92. Figure 3. Monthly Average Petroleum Spot Price (U.S. dollars per barrel) 0 10 20 30 40 50 60 70 80 90 1970M1 1972M5 1974M9 1977M1 1979M5 1981M9 1984M1 1986M5 1988M9 1991M1 1993M5 1995M9 1998M1 2000M5 2002M9 APSP Real APSP Sources: IMF, World Economic Outlook database; and author’s calculations. Note: APSP¼Average petroleum spot price. Real APSP is calculated by scaling the APSP by
  • 93. the U.S. CPI. Figure 4. Oil Prices and Stand-By Arrangements 0 5 10 15 20 25 30 35 1970 1972 1974 1976 1978 1980 1982 1984 1986 1988 1990 1992 1994 1996 1998 2000 2002 2004 -150 -100 -50 0 50 100 150
  • 94. Stand-By Arrangements (left scale) Real Oil Prices (right scale) Sources: IMF, World Economic Outlook and Policy Development and Review Department databases; and author’s calculations. Note: Real oil prices represented as the deviation from linear trend, in which average petroleum spot price (APSP) is calculated by scaling the APSP by U.S. CPI. Selim Elekdağ 630 Global Business Cycle As the main measure of the global business cycle, the deviation of the logarithm of real-world GDP from trend is used. 8 Figure 5 displays the global business cycle with the number of SBAs as the backdrop. Note that the two global recessions in the early 1980s and 1990s correspond to the two peaks in the number of SBAs approved during 1970–2004. These figures provide casual evidence in favor of a link between the global
  • 95. economic environment and SBAs, but formal econometric analysis is required for a rigorous assessment. III. Methodology The objective of this section is to describe the analytical structure underpinning the econometric analysis. After the discussion of a conceptual framework, the section proceeds to discuss the key determinants that influence the approval of SBAs. Conceptual Framework As discussed in Mussa and Savastano (1999), a typical IMF- supported program begins with an explicit request from a member. Then the IMF staff prepares a blueprint of a program to be used as a basis for negotiations between a member’s authorities and the IMF staff. When an agreement has been reached, the arrangement has to be cleared by IMF management and approved by the IMF Executive Board. This potentially iterative process demonstrates how IMF-supported programs depend on joint decision making. Using language in line with Knight and Santaella (1997), a member’s ‘‘demand’’ for an arrangement, and the IMF’s ‘‘supply’’ (willingness to approve one) are both necessary components of the process.
  • 96. 9 Most of the literature on IMF arrangements has investigated— using binary choice models—the determinants of either participation in IMF programs or of program approval in a certain year. Notable examples of the former include Joyce (1992); Conway (1994); Vreeland (2004); and Cerutti (2007); examples in the latter group of papers include Przeworski and Vreeland (2000); Bird and Rowlands (2001); and Barro and Lee (2005). In contrast to these studies, Knight and Santaella (1997) explicitly jointly model the ‘‘demand’’ and ‘‘supply’’ determinants of IMF program approval using a bivariate probit specification. However, they find that a univariate specification—which they interpret as a reduced-form demand- supply 8 The log-linear trend implies an annual real global growth rate of about 3.4 percent. 9 As emphasized by Cerutti (2007), a similar joint decision process continues throughout the life of an arrangement, with the amounts that are finally drawn while the program is on track determined in such a manner. DEMAND FOR IMF RESOURCES
  • 97. 631 model—is superior to the bivariate model. 10 In particular, Knight and Santaella find that the univariate model predicts the approval of a financial arrangement more accurately than the bivariate specification. 11 Therefore, based on Knight and Santaella, the joint determinants of an SBA are modeled using a univariate probit model. However, the estimation strategy used to uncover the empirical relationships between global economic conditions and IMF credit is also based on two other broad strands of research. The first, based on Albuquerque, Loayza, and Servén (2005), uses two sets of explanatory variables: global and country-specific. The global variables are indicators of the world economic and financial climate, whereas the country- specific variables control—among other things—for domestic policies and idiosyncratic shocks. 12
  • 98. The second strand, building on the vast literature on early warning systems and financial crisis prediction—as summarized by Berg, Borensztein, and Pattillo (2004)—regresses a binary independent Figure 5. The Global Business Cycle and Stand-By Arrangements 0 5 10 15 20 25 30 35 1970 1972 1974 1976 1978 1980 1982 1984 1986 1988 1990 1992 1994 1996 1998 2000 2002 2004 -5 -4 -3 -2
  • 99. -1 0 1 2 3 4 5 Stand-By Arrangements (left scale) Real world GDP growth (right scale) Sources: IMF, World Economic Outlook database and author’s calculations. Note: Real world GDP measured as the deviation of real world GDP from a linear trend. 10 One reason may be that many variables that enter the demand side—for example, BOP need—are likely to enter the supply side (the IMF’s willingness to meet that need), thus complicating the separate identification of the demand and supply curves. 11 Furthermore, Conway (1994) finds that Tobit and probit specifications yield similar results.