The document discusses tariff-based competitive bidding for power projects in India. Some key points:
- Tariff is determined through a competitive bidding process where the lowest bid tariff is awarded the contract.
- There are two types of bidding mechanisms - Case I where the developer bears more risk and Case II where the procurer bears more risk.
- Financial factors like debt-equity ratio, loan tenure, and interest rates can significantly impact the tariff rates determined through bidding. Operational improvements in plant efficiency and reduced auxiliary power consumption through technology upgrades can also lower tariffs.
Wind Force Newsletter January, Edition, 2012rupeshsingh_1
This newsletter provides updates on policy and regulatory developments in the renewable energy sector in India.
It summarizes new draft regulations from the Andhra Pradesh, Rajasthan, and Central Electricity Regulatory Commissions related to renewable purchase obligations, transmission charges, and tariffs for renewable technologies. It also outlines a new order from the Tamil Nadu Electricity Regulatory Commission regarding concessional transmission and wheeling charges.
REC trading data is presented, showing increasing prices and volumes traded on exchanges each month. Electricity prices from bilateral arrangements are generally higher than at power exchanges.
Upcoming renewable energy events are listed. Contact information is provided for questions or feedback on the newsletter.
Practical Problems in Implementation of Open Access : Discom PerspectiveIPPAI
1) Partial open access, where consumers procure only base load power through open access and ask the local distribution company (discom) to provide peak power at regulated rates, increases the discom's power purchase costs and raises overall tariffs for all consumers.
2) Implementing partial open access poses operational challenges like how to supply open access and regulated power through a single meter.
3) If many large consumers shift to open access, discoms will be left with stranded generation assets and higher fixed costs that will need to be recovered through additional surcharges on remaining consumers.
The Need for Regulatory & Policy Framework for Ancillary Services & Alternati...IPPAI
The document discusses the need for a regulatory and policy framework for ancillary services and alternative energy options in the Indian power sector. It defines ancillary services as support services that ensure reliable and stable power delivery. Ancillary services are classified into frequency control and network control services. The issues of stranded generation capacity, renewable energy variability, and peaking power requirements are also discussed. The document suggests examining the roles of grid operators and establishing protocols for ancillary service payments. It also promotes energy storage solutions and incentives to balance the grid and meet demand reliably.
1) Ancillary services are necessary to support power grid operations and maintain power quality, reliability and security. They include frequency support, reactive power support, and black start capabilities.
2) India's power grids currently face issues like frequent unplanned load shedding due to lack of flexibility and reserves. There is a need for ancillary services to harness available generation and relieve congestion.
3) The document proposes a framework for Frequency Support Ancillary Services (FSAS) in India utilizing fragmented generation capacity through competitive bidding on power exchanges. This aims to stabilize grid frequency and reduce load shedding.
The document discusses tariff-based competitive bidding for power projects in India. Some key points:
- Tariff is determined through a competitive bidding process where the lowest bid tariff is awarded the contract.
- There are two types of bidding mechanisms - Case I where the developer bears more risk and Case II where the procurer bears more risk.
- Financial factors like debt-equity ratio, loan tenure, and interest rates can significantly impact the tariff rates determined through bidding. Operational improvements in plant efficiency and reduced auxiliary power consumption through technology upgrades can also lower tariffs.
Wind Force Newsletter January, Edition, 2012rupeshsingh_1
This newsletter provides updates on policy and regulatory developments in the renewable energy sector in India.
It summarizes new draft regulations from the Andhra Pradesh, Rajasthan, and Central Electricity Regulatory Commissions related to renewable purchase obligations, transmission charges, and tariffs for renewable technologies. It also outlines a new order from the Tamil Nadu Electricity Regulatory Commission regarding concessional transmission and wheeling charges.
REC trading data is presented, showing increasing prices and volumes traded on exchanges each month. Electricity prices from bilateral arrangements are generally higher than at power exchanges.
Upcoming renewable energy events are listed. Contact information is provided for questions or feedback on the newsletter.
Practical Problems in Implementation of Open Access : Discom PerspectiveIPPAI
1) Partial open access, where consumers procure only base load power through open access and ask the local distribution company (discom) to provide peak power at regulated rates, increases the discom's power purchase costs and raises overall tariffs for all consumers.
2) Implementing partial open access poses operational challenges like how to supply open access and regulated power through a single meter.
3) If many large consumers shift to open access, discoms will be left with stranded generation assets and higher fixed costs that will need to be recovered through additional surcharges on remaining consumers.
The Need for Regulatory & Policy Framework for Ancillary Services & Alternati...IPPAI
The document discusses the need for a regulatory and policy framework for ancillary services and alternative energy options in the Indian power sector. It defines ancillary services as support services that ensure reliable and stable power delivery. Ancillary services are classified into frequency control and network control services. The issues of stranded generation capacity, renewable energy variability, and peaking power requirements are also discussed. The document suggests examining the roles of grid operators and establishing protocols for ancillary service payments. It also promotes energy storage solutions and incentives to balance the grid and meet demand reliably.
1) Ancillary services are necessary to support power grid operations and maintain power quality, reliability and security. They include frequency support, reactive power support, and black start capabilities.
2) India's power grids currently face issues like frequent unplanned load shedding due to lack of flexibility and reserves. There is a need for ancillary services to harness available generation and relieve congestion.
3) The document proposes a framework for Frequency Support Ancillary Services (FSAS) in India utilizing fragmented generation capacity through competitive bidding on power exchanges. This aims to stabilize grid frequency and reduce load shedding.
The document discusses the need for a regulatory and policy framework for ancillary services and alternative energy options in the Indian power sector. It provides an overview of ancillary services and how they are classified. Frequency control, voltage control, and system restart ancillary services are described. The document also discusses how different technologies, including distributed energy resources, can provide ancillary services. It examines the scope to promote ancillary services in India, including through the use of generators and load serving entities. The conclusion advocates for the design of a market mechanism and proper policy framework to facilitate ancillary services provision.
The document provides information on the distribution franchisee scheme for Ujjain City, Gwalior Town, and Sagar City in Madhya Pradesh, including an agenda, profiles of the franchisee areas, the request for proposal process and requirements, timelines, and the distribution franchisee agreement. Key details include technical criteria for experience in the power sector, manpower strength, and financial criteria for net worth and net cash accrual required to qualify for the bids.
Demand-Side Flexibility for Reliable Ancillary Services in a Smart Grid: Elim...Sean Meyn
A survey of our 2015 HICSS article (reference below), which is largely a survey of demand response technology developed at the University of Florida.
Presented at the Workshop on Electricity Markets and Optimization 27th of November 2014. Aalborg University, Denmark
@inproceedings{barbusmey14,
Address = {Kauai, Hawaii},
Author = {Barooah, Prabir and Bu\v{s}i\'{c}, Ana and Meyn, Sean},
Booktitle = {Proc. {48th Annual Hawaii International Conference on System Sciences (HICSS)}},
Note = {(invited)},
Publisher = {University of Hawaii},
Title = {Spectral Decomposition of Demand-Side Flexibility for Reliable Ancillary Services in a Smart Grid},
Year = {2015}}
Ancillary Services in the United States: Independent System Operator (ISO) Pe...IPPAI
NREL is a national laboratory operated by the U.S. Department of Energy that focuses on energy efficiency and renewable energy. The document discusses ancillary services markets in the United States from the perspective of independent system operators. It provides an overview of the six largest ISOs in the US and describes the types of markets they operate including day-ahead energy, real-time energy, ancillary services, transmission rights, and capacity. The document also defines different types of ancillary services and how ISOs set requirements and procure these services.
The document discusses transmission policies in Texas. It describes how transmission provides reliable delivery of electricity across long distances from generators to customers. Key transmission policies in Texas include open-access, which allows all generators to access and deliver energy across the transmission network, and regional planning to ensure adequate infrastructure. Transmission companies invest in and build infrastructure to support Texas' growing economy and manage grid operations under ERCOT's direction.
Tonbridge Power Inc. is developing a 345 km, 300 MW transmission line (MATL) in the Western United States to transport electricity. MATL has obtained all necessary permits and financing, and transmission line capacity has been fully sold. The project is on schedule, with major equipment ordering and construction starting in Q2 2010 and the entire system commissioning targeted for Q2 2011. MATL has formed a public private partnership with Western Area Power Administration, with MATL taking on most construction and commercial risks and Western agreeing to purchase capacity and ensure the project meets investment grade compliance standards. The MATL project represents a new model for allocating risk between private and public partners to facilitate infrastructure development.
- Open access provisions allow consumers to purchase power from electricity suppliers other than their local distribution utility by using the transmission and distribution network.
- The document provides state-wise details on open access regulations, applicable charges like transmission charges, wheeling charges, cross-subsidy surcharges, and banking provisions for states like Andhra Pradesh, Arunachal Pradesh, Assam, Bihar, Chhattisgarh, Delhi, Gujarat, Haryana, Himachal Pradesh, Jammu & Kashmir, Jharkhand, Karnataka, Kerala, Madhya Pradesh, Maharashtra, Odisha, Punjab, Rajasthan, Tamil Nadu, Telangana, Uttar
General Carbon provides advisory services related to energy, environmental commodities, and sustainability across India, Southeast Asia, and Africa. It advises power market participants on sourcing renewable energy, developing carbon offset and renewable energy certificate projects, and complying with energy efficiency regulations. General Carbon has expertise in various renewable technologies including wind, solar, biomass, hydro, and natural gas. It assists clients with energy strategy, regulatory issues, and trading environmental commodities like carbon offsets and renewable energy certificates.
The document discusses developments in the past year following India's coal block auctions. It summarizes that while bidders bid aggressively to secure fuel supply, changes made by the Ministry of Power have made the projects unviable. Fixed charge caps and changes to fuel cost computation undermine project viability and remove competitive bidding. Several state utilities have opted not to procure power from coal block developers due to complications. Linkage-based power is being procured at lower fixed charges than capped rates for coal block-based power.
The Public Utilities Commission of Sri Lanka issued a consultation paper on setting electricity tariffs for the period of 2011-2015. The paper presented key issues for public comment, including sales forecasts and allowed losses for transmission and distribution licensees. Distribution licensees filed sales forecasts and loss allowances between 2011-2015 ranging from 11-14.8% losses. The transmission licensee filed purchases from generation and loss allowances of 11% for 2011. The paper proposed allowed revenues for licensees and the provision for energy sold for street lighting. It analyzed government subsidies to the electricity sector and presented a roadmap for tariff restructuring and rebalancing to achieve cost-reflective tariffs by 2015. Finally, the paper outlined proposed electricity tar
This document discusses rationales for capping fixed charges for coal mine/block projects under DBFOO bidding. It provides:
1) Tables showing recent bid tariffs with average fixed charges ranging from Rs. 2.28-4.47/kWh.
2) Calculations of fixed charges from Rs. 2.26-3.3/kWh based on project costs of Rs. 9,000-14,000 crores per CERC regulations.
3) Arguments that actual costs are higher than CERC norms due to additional railway infrastructure, mine development costs, risk premiums, and assumptions around station heat rate, auxiliary power, and availability penalties in DBFOO documents.
This document provides sample illustrations of transmission and wheeling charges for open access transactions at various voltage levels in India for the fiscal year 2018-2019. It details the transmission charge, wheeling charge, wheeling loss compensation, and total charges paid for a 5 MW solar captive generator injecting power at different voltage points and supplying consumers at different voltages for three distribution companies: MSEDCL, TPC, and REL. The effective rate per kWh is also provided for each case and distribution company.
energy future holindings 2008_EEI_Deck_FINALbfinance29
This presentation provides an overview of Energy Future Holdings Corporation and its subsidiaries. EFH has three distinct business segments: Oncor Electric Delivery, Texas Competitive Electric Holdings, and Luminant. Oncor is the largest transmission and distribution utility in Texas. TCEH includes TXU Energy, the largest retail electricity provider in Texas, and Luminant, the second largest power generator in the state. The presentation discusses key initiatives and value drivers for each business, including large capital expenditure programs. It also reviews the debt structure of EFH and liquidity position of the holding company.
The document discusses regulatory asset build up in Delhi and potential ways to amortize it. Some key points:
- Delhi distribution companies (discoms) have accumulated massive regulatory assets of Rs. 16,000-20,000 crores due to factors like costly long-term PPAs, non-cost reflective tariffs, inadequate PPAC formulas, and losses from selling surplus power.
- Regulatory assets in other states like Tamil Nadu, Rajasthan, Uttar Pradesh and West Bengal also run into thousands of crores. The build up is hampering discoms' ability to raise funds and invest in infrastructure.
- Options proposed to address the issue include time-bound recovery
Grid Connections And PPAs: Tim Foster, Smartest EnergySonia Large
This document discusses power purchase agreements (PPAs) for renewable energy generators connecting to the electricity grid. It provides an overview of the grid connection process, typical technical issues encountered, and elements of PPAs such as pricing electricity, embedded benefits, climate change levy exemptions, and renewable obligation certificates. PPAs establish the risk/reward structure for selling a generator's electricity output and renewable attributes to a licensed supplier over a set contract term.
Toyota -Plug-in-Prius demonstration programaccessio
The document summarizes research from Toyota's Prius Plug-in Hybrid vehicle demonstration program. It finds that participants charged the vehicle more frequently than expected but did not realize it. Most found charging to be as convenient or more convenient than expected, and the cost of electricity to charge was less than anticipated. Driving behaviors changed with participants more closely monitoring their fuel usage, but trip activities did not need to be altered. The program demonstrated that plug-in hybrids can provide an convenient electric driving and charging experience.
The document outlines the open access charges in Chhattisgarh that were approved and made effective from April 1, 2018. This includes transmission charges, energy losses for transmission and distribution, wheeling charges, operating charges, reactive energy charges, cross subsidy surcharge, and standby charges for consumers availing open access. It also provides details on zero transmission, wheeling and SLDC charges for renewable energy transactions, but a 6% energy loss charge and reduced cross subsidy surcharge of 50% for renewable generators. Standby charges are 1.5-2 times the average tariff depending on drawal within or in excess of contracted capacity during outage.
This document provides an overview and agenda for a seminar on solar power purchase agreements (PPAs). It discusses what a PPA is, how it works, and its benefits. It also covers PPA implementation aspects like design, financing, operations and maintenance. Finally, it presents a case study of a 384 kW solar PPA installed for a city's public works campus.
This document provides an overview of how information technology is being used to improve operations in the power sector. It discusses how IT can increase business process efficiency, capacity building, metering and billing accuracy, and customer satisfaction. The document then examines specific challenges around network architecture standards and the case study of KPCL in India. KPCL has established a satellite-based communication network and utilizes MPLS for services like video conferencing. The document also explores how geographic information systems (GIS) can be used to map infrastructure and improve decision making. Finally, it discusses security requirements around availability, confidentiality, integrity and authentication for power sector communication networks.
Effect of Primary Fuels on the Availability and Cost of Power in IndiaIPPAI
Total cost of power (Rs/kWh) 6.33 6.94 7.54 8.14
Savings compared to real cost 2.04 1.43 0.83 0.23
Even at $14/mmbtu LNG price, cost is lower than real cost of power. LNG provides reliable and
economic solution to meet peak demand.
22
Requisite policy/regulatory initiatives
23
Requisite policy/regulatory initiatives
1. Gas grid development and connectivity to all gas based power plants
2. Pricing freedom to gas based power plants to operate as peaking stations
3. Priority sector
This document discusses electricity tariff models and the way forward for the power sector in India. It outlines three main tariff models: cost of service regulation, incentive regulation using price caps, and a hybrid model. It notes the advantages and disadvantages of each approach. The document then discusses issues around taking distribution companies towards a more competitive model, including unbundling distribution companies to separate wiring and supply businesses, privatizing distribution company supply functions, and defining the ongoing role of regulators.
The document discusses the need for a regulatory and policy framework for ancillary services and alternative energy options in the Indian power sector. It provides an overview of ancillary services and how they are classified. Frequency control, voltage control, and system restart ancillary services are described. The document also discusses how different technologies, including distributed energy resources, can provide ancillary services. It examines the scope to promote ancillary services in India, including through the use of generators and load serving entities. The conclusion advocates for the design of a market mechanism and proper policy framework to facilitate ancillary services provision.
The document provides information on the distribution franchisee scheme for Ujjain City, Gwalior Town, and Sagar City in Madhya Pradesh, including an agenda, profiles of the franchisee areas, the request for proposal process and requirements, timelines, and the distribution franchisee agreement. Key details include technical criteria for experience in the power sector, manpower strength, and financial criteria for net worth and net cash accrual required to qualify for the bids.
Demand-Side Flexibility for Reliable Ancillary Services in a Smart Grid: Elim...Sean Meyn
A survey of our 2015 HICSS article (reference below), which is largely a survey of demand response technology developed at the University of Florida.
Presented at the Workshop on Electricity Markets and Optimization 27th of November 2014. Aalborg University, Denmark
@inproceedings{barbusmey14,
Address = {Kauai, Hawaii},
Author = {Barooah, Prabir and Bu\v{s}i\'{c}, Ana and Meyn, Sean},
Booktitle = {Proc. {48th Annual Hawaii International Conference on System Sciences (HICSS)}},
Note = {(invited)},
Publisher = {University of Hawaii},
Title = {Spectral Decomposition of Demand-Side Flexibility for Reliable Ancillary Services in a Smart Grid},
Year = {2015}}
Ancillary Services in the United States: Independent System Operator (ISO) Pe...IPPAI
NREL is a national laboratory operated by the U.S. Department of Energy that focuses on energy efficiency and renewable energy. The document discusses ancillary services markets in the United States from the perspective of independent system operators. It provides an overview of the six largest ISOs in the US and describes the types of markets they operate including day-ahead energy, real-time energy, ancillary services, transmission rights, and capacity. The document also defines different types of ancillary services and how ISOs set requirements and procure these services.
The document discusses transmission policies in Texas. It describes how transmission provides reliable delivery of electricity across long distances from generators to customers. Key transmission policies in Texas include open-access, which allows all generators to access and deliver energy across the transmission network, and regional planning to ensure adequate infrastructure. Transmission companies invest in and build infrastructure to support Texas' growing economy and manage grid operations under ERCOT's direction.
Tonbridge Power Inc. is developing a 345 km, 300 MW transmission line (MATL) in the Western United States to transport electricity. MATL has obtained all necessary permits and financing, and transmission line capacity has been fully sold. The project is on schedule, with major equipment ordering and construction starting in Q2 2010 and the entire system commissioning targeted for Q2 2011. MATL has formed a public private partnership with Western Area Power Administration, with MATL taking on most construction and commercial risks and Western agreeing to purchase capacity and ensure the project meets investment grade compliance standards. The MATL project represents a new model for allocating risk between private and public partners to facilitate infrastructure development.
- Open access provisions allow consumers to purchase power from electricity suppliers other than their local distribution utility by using the transmission and distribution network.
- The document provides state-wise details on open access regulations, applicable charges like transmission charges, wheeling charges, cross-subsidy surcharges, and banking provisions for states like Andhra Pradesh, Arunachal Pradesh, Assam, Bihar, Chhattisgarh, Delhi, Gujarat, Haryana, Himachal Pradesh, Jammu & Kashmir, Jharkhand, Karnataka, Kerala, Madhya Pradesh, Maharashtra, Odisha, Punjab, Rajasthan, Tamil Nadu, Telangana, Uttar
General Carbon provides advisory services related to energy, environmental commodities, and sustainability across India, Southeast Asia, and Africa. It advises power market participants on sourcing renewable energy, developing carbon offset and renewable energy certificate projects, and complying with energy efficiency regulations. General Carbon has expertise in various renewable technologies including wind, solar, biomass, hydro, and natural gas. It assists clients with energy strategy, regulatory issues, and trading environmental commodities like carbon offsets and renewable energy certificates.
The document discusses developments in the past year following India's coal block auctions. It summarizes that while bidders bid aggressively to secure fuel supply, changes made by the Ministry of Power have made the projects unviable. Fixed charge caps and changes to fuel cost computation undermine project viability and remove competitive bidding. Several state utilities have opted not to procure power from coal block developers due to complications. Linkage-based power is being procured at lower fixed charges than capped rates for coal block-based power.
The Public Utilities Commission of Sri Lanka issued a consultation paper on setting electricity tariffs for the period of 2011-2015. The paper presented key issues for public comment, including sales forecasts and allowed losses for transmission and distribution licensees. Distribution licensees filed sales forecasts and loss allowances between 2011-2015 ranging from 11-14.8% losses. The transmission licensee filed purchases from generation and loss allowances of 11% for 2011. The paper proposed allowed revenues for licensees and the provision for energy sold for street lighting. It analyzed government subsidies to the electricity sector and presented a roadmap for tariff restructuring and rebalancing to achieve cost-reflective tariffs by 2015. Finally, the paper outlined proposed electricity tar
This document discusses rationales for capping fixed charges for coal mine/block projects under DBFOO bidding. It provides:
1) Tables showing recent bid tariffs with average fixed charges ranging from Rs. 2.28-4.47/kWh.
2) Calculations of fixed charges from Rs. 2.26-3.3/kWh based on project costs of Rs. 9,000-14,000 crores per CERC regulations.
3) Arguments that actual costs are higher than CERC norms due to additional railway infrastructure, mine development costs, risk premiums, and assumptions around station heat rate, auxiliary power, and availability penalties in DBFOO documents.
This document provides sample illustrations of transmission and wheeling charges for open access transactions at various voltage levels in India for the fiscal year 2018-2019. It details the transmission charge, wheeling charge, wheeling loss compensation, and total charges paid for a 5 MW solar captive generator injecting power at different voltage points and supplying consumers at different voltages for three distribution companies: MSEDCL, TPC, and REL. The effective rate per kWh is also provided for each case and distribution company.
energy future holindings 2008_EEI_Deck_FINALbfinance29
This presentation provides an overview of Energy Future Holdings Corporation and its subsidiaries. EFH has three distinct business segments: Oncor Electric Delivery, Texas Competitive Electric Holdings, and Luminant. Oncor is the largest transmission and distribution utility in Texas. TCEH includes TXU Energy, the largest retail electricity provider in Texas, and Luminant, the second largest power generator in the state. The presentation discusses key initiatives and value drivers for each business, including large capital expenditure programs. It also reviews the debt structure of EFH and liquidity position of the holding company.
The document discusses regulatory asset build up in Delhi and potential ways to amortize it. Some key points:
- Delhi distribution companies (discoms) have accumulated massive regulatory assets of Rs. 16,000-20,000 crores due to factors like costly long-term PPAs, non-cost reflective tariffs, inadequate PPAC formulas, and losses from selling surplus power.
- Regulatory assets in other states like Tamil Nadu, Rajasthan, Uttar Pradesh and West Bengal also run into thousands of crores. The build up is hampering discoms' ability to raise funds and invest in infrastructure.
- Options proposed to address the issue include time-bound recovery
Grid Connections And PPAs: Tim Foster, Smartest EnergySonia Large
This document discusses power purchase agreements (PPAs) for renewable energy generators connecting to the electricity grid. It provides an overview of the grid connection process, typical technical issues encountered, and elements of PPAs such as pricing electricity, embedded benefits, climate change levy exemptions, and renewable obligation certificates. PPAs establish the risk/reward structure for selling a generator's electricity output and renewable attributes to a licensed supplier over a set contract term.
Toyota -Plug-in-Prius demonstration programaccessio
The document summarizes research from Toyota's Prius Plug-in Hybrid vehicle demonstration program. It finds that participants charged the vehicle more frequently than expected but did not realize it. Most found charging to be as convenient or more convenient than expected, and the cost of electricity to charge was less than anticipated. Driving behaviors changed with participants more closely monitoring their fuel usage, but trip activities did not need to be altered. The program demonstrated that plug-in hybrids can provide an convenient electric driving and charging experience.
The document outlines the open access charges in Chhattisgarh that were approved and made effective from April 1, 2018. This includes transmission charges, energy losses for transmission and distribution, wheeling charges, operating charges, reactive energy charges, cross subsidy surcharge, and standby charges for consumers availing open access. It also provides details on zero transmission, wheeling and SLDC charges for renewable energy transactions, but a 6% energy loss charge and reduced cross subsidy surcharge of 50% for renewable generators. Standby charges are 1.5-2 times the average tariff depending on drawal within or in excess of contracted capacity during outage.
This document provides an overview and agenda for a seminar on solar power purchase agreements (PPAs). It discusses what a PPA is, how it works, and its benefits. It also covers PPA implementation aspects like design, financing, operations and maintenance. Finally, it presents a case study of a 384 kW solar PPA installed for a city's public works campus.
This document provides an overview of how information technology is being used to improve operations in the power sector. It discusses how IT can increase business process efficiency, capacity building, metering and billing accuracy, and customer satisfaction. The document then examines specific challenges around network architecture standards and the case study of KPCL in India. KPCL has established a satellite-based communication network and utilizes MPLS for services like video conferencing. The document also explores how geographic information systems (GIS) can be used to map infrastructure and improve decision making. Finally, it discusses security requirements around availability, confidentiality, integrity and authentication for power sector communication networks.
Effect of Primary Fuels on the Availability and Cost of Power in IndiaIPPAI
Total cost of power (Rs/kWh) 6.33 6.94 7.54 8.14
Savings compared to real cost 2.04 1.43 0.83 0.23
Even at $14/mmbtu LNG price, cost is lower than real cost of power. LNG provides reliable and
economic solution to meet peak demand.
22
Requisite policy/regulatory initiatives
23
Requisite policy/regulatory initiatives
1. Gas grid development and connectivity to all gas based power plants
2. Pricing freedom to gas based power plants to operate as peaking stations
3. Priority sector
This document discusses electricity tariff models and the way forward for the power sector in India. It outlines three main tariff models: cost of service regulation, incentive regulation using price caps, and a hybrid model. It notes the advantages and disadvantages of each approach. The document then discusses issues around taking distribution companies towards a more competitive model, including unbundling distribution companies to separate wiring and supply businesses, privatizing distribution company supply functions, and defining the ongoing role of regulators.
Day-3, Mr. Ajay Kumar contract sanctity case 1 case 2IPPAI
BSES Rajdhani Power Ltd. discusses issues with competitive bidding and lack of sanctity of contracts in India's power sector. Key topics covered include BSES Rajdhani Power Ltd., tariffs, universal service obligation, power purchase agreements, fuel, projects, finance, policies of electricity regulatory commissions, and their critical linkages.
Power distribution tariff in india 2016 discom wise and consumer wise compre...Sakshi Saini
By meticulously examining the regulation, the latest trends governing the key fuel resources and deeply analysing the possible impacts on all the stakeholders, enincon llp attempts to blend the factual power tariff data and present a dossier which would enable clients with reliable insights and better understanding of the power tariff dynamics in the country.
Financial & operational opportunities for disco ms under udaySakshi Saini
What erstwhile was ignored, has now gained pinnacle importance by Government as the future of power sector at large depends upon better financial health and consistent operations of DISCOMS. To ensure this objective Government did attempted FRPs for struggling Discoms in 2013 which tanked due to lack of timely implementation, forcing yet another scheme to turnaround the fate of state owned distribution utilities which has earned the nomenclature as UDAY (Ujwal DISCOM Assurance Yojana). The scheme is touted as the next paladin to bail out the struggling Discoms, potentially could see them turn green in a time horizon of 3-4 years from 2015/16.
Operational challenges in India's power sectorpradhansushil
The document discusses the operational challenges faced by India's power sector. It notes the complex arrangements between central and state governments and private agencies. It also discusses regulatory inconsistencies, tariff distortions, and the large demand-supply gap. The document provides case studies on specific power plants to illustrate challenges around fuel supply, cost increases, and resource management. It also summarizes the generation sources in India and risks/challenges including fuel shortages, infrastructure issues, and environmental and social factors. Mitigation strategies suggested include careful evaluation, local engagement, risk assessments, and professional project management.
The document outlines India's efforts to reform its power sector through the UDAY program and achieve 24x7 Power For All. Key points:
1) UDAY aims to permanently resolve issues facing power distribution companies (DISCOMs) by having states take over some of their debt, improving operational efficiency to reduce losses, and enabling periodic tariff increases.
2) Operational efficiency will be improved by reducing Aggregate Technical and Commercial (AT&C) losses through better metering, infrastructure upgrades, and public awareness campaigns against theft.
3) Demand side management programs like LED lighting adoption and efficient agricultural pumps will reduce peak load and energy consumption.
4) Transparency in procurement has led to sharp
This document discusses challenges facing India's power sector related to fuel supply and pricing uncertainties. It outlines several solutions to address both short-term and long-term fuel security issues. In the short-term, solutions focus on boosting domestic coal and gas production, rationalizing linkages and imports. Long-term fuel security requires a comprehensive energy policy that maximizes use of domestic fuel reserves and provides affordable fuel to generate low-cost power.
The document summarizes the Financial Restructuring Plan (FRP) of 2012 and Ujwal DISCOM Assurance Yojana (UDAY) scheme launched in 2015. FRP 2012 aimed to restructure discom debt but failed due to lack of clarity on bond interest rates and hidden discom losses. UDAY is aimed at improving the financial health of discoms by having states take over 75% of discom debt over two years, issuing bonds to replace debt, enforcing operational efficiency, and ensuring compliance with renewable purchase targets. Key objectives are reducing discom interest costs and power procurement costs while improving efficiency.
Tariff and Duty of Electricity supply in various State of India-A review by CEAAshish Verma
The Central Electricity Authority- a central autonomous technical planning and regulatory wing under Ministry of Power has released review report on tariff and duties of electricity supply by various distribution companies functioning at various states .
The Report is published for fulfilling the CEA's obligation under section 73(i) and (j) of electricty act 2003 .
The document summarizes electricity regulations in India. It discusses the Central Electricity Regulatory Commission (CERC) and State Electricity Regulatory Commissions (SERCs), which regulate the electricity sector. It also outlines key aspects of the Electricity Act 2003, including provisions related to power generation, transmission, and distribution. The act aims to increase competition and private sector participation in the electricity industry.
The document discusses the key principles of multi-year tariff (MYT) framework for electricity regulation in India. Some key points:
- MYT aims to incentivize efficiency, reduce regulatory uncertainty, assist utilities in planning, and introduce efficient tariff design.
- It determines the regulatory framework for a period of time including principles for regulating returns, costs, and ongoing regulation.
- The framework separates controllable and uncontrollable costs and treats them differently. Uncontrollable costs like fuel costs are passed through while utilities share gains/losses from controllable costs.
- Utilities file multi-year applications covering ARR, revenue, capital plans and performance targets for a control period of typically 5
The document provides an overview of the Indian coal sector, including key facts and trends. It notes that India has the fifth largest coal reserves globally, coal demand has grown over 7% per year, and there is a current demand-supply gap of around 98 million tonnes. The largest consumer of coal is the power sector, followed by iron/steel and cement. The document also discusses trends in coal consumption by industry, imports, major mining companies, and challenges and opportunities in the sector.
The document summarizes the Dabhol power project in India, which was led by the American energy company Enron. It describes India's growing power needs in the 1990s that led the government to pursue private sector investments. Enron proposed a large natural gas power plant in Maharashtra. The project faced issues including a lack of transparency, high costs, and tariffs. This led the new BJP government to cancel the project in 1995, though it was later renegotiated. The deal ultimately failed due to payment disputes, leading to international arbitration proceedings between Enron and the Indian government.
The document provides a case analysis report on the Dabhol Power Plant project in Maharashtra, India. It summarizes that the Maharashtra government signed an agreement with Enron Corporation in 1992 to build a power plant to address the state's power needs. However, political and contractual issues led to repeated cancellations and renegotiations of the project. These issues along with the bankruptcy of Enron ultimately caused the project to fail in 2001. The plant was later revived and commissioned in 2006 under new ownership.
This presentation discusses about Electricity Laws and Regulations. It primarily focuses on India, but a reference to other countries is made at few places.
Presentation On Salient Features Of The Electricity Act , 2003rapper44
The document summarizes the salient features of the Electricity Act 2003, covering areas such as rural electrification, generation, transmission, distribution, role of government, consumer protection, regulatory commissions, tariff principles, measures against theft, and restructuring of state electricity boards. Key points include promoting rural electrification, removing licensing requirements for generation and captive power, establishing regulatory commissions and appellate tribunals, and provisions for open access and distribution reforms.
This document provides an overview of the power sector in India. It discusses the key stages in the development of the power sector from before 1956 to the present day. Some of the key points covered include:
- The power sector has gone through different eras including nationalization (1956-1991), liberalization (1991-2003), and the current growth era (2003-present).
- Key policy initiatives and legislation like the Electricity Act 2003 and National Tariff Policy 2006 have promoted private sector participation and competition.
- India has a total installed capacity of 248,509 MW as of 2014, with thermal power making up the largest share at 69%. Renewable energy capacity is also being increased significantly.
This document discusses how Renewable Purchase Obligations (RPO) and Renewable Energy Certificates (REC) can impact organizations in India. RPO is a mandate requiring electricity distributors and large consumers to source a minimum percentage of power from renewable sources. RECs are tradable certificates representing renewable energy generated and can be purchased to meet RPO targets. The document provides an overview of RPO percentages by state, REC pricing trends, and analyzes a case study of an organization's RPO compliance options and costs. It promotes the services of GC Advisors to help organizations develop customized RPO compliance plans.
This document provides an overview of Renewable Purchase Obligation (RPO) and Renewable Energy Certificate (REC) frameworks in India. It discusses the key objectives for introducing the REC mechanism, including effective RPO implementation and increased flexibility. It outlines the entities involved, including central and state-level organizations. It also describes the process for accreditation and registration of renewable energy generators, issuance and redemption of RECs, applicable timelines and fees. Finally, it provides statistics on registered renewable capacity and REC transactions to date in India.
The document discusses India's experience with power procurement through international competitive bidding. It outlines the guiding principles of promoting competition and protecting consumer interests. Case I bidding allows flexibility for developers while Case II bidding specifies project parameters. Early Case I bids saw tariffs around Rs. 2-3/kWh but they have risen to Rs. 4-6/kWh due to fuel supply and cost uncertainties faced by developers over 25-year contracts. Case II bids saw lower initial tariffs of Rs. 1-2.5/kWh but projects like the Tilaiya UMPP face delays from land and clearance issues. Key learnings are a need for mid-term tariff reviews, provisions for uncertainties, and readiness of key
This document provides an overview and summary of Power Holdings Inc.'s (PHI) various business segments. It discusses PHI's regulated electric and gas delivery business, which accounts for 67% of operating income. It also summarizes Conectiv Energy's competitive merchant generation and load service business, which accounts for 33% of operating income. Key highlights from rate cases and recent regulatory activities involving PHI's delivery businesses are also provided. The document contains forward-looking statements and non-GAAP financial measures.
Ewura presentation at the Renewable energy dayandrewmnzava
The document provides an overview of small power producers (SPPs) in Tanzania. It discusses Tanzania's SPP regulatory framework, including goals, required permissions and approval processes. It also outlines the current SPP situation in Tanzania, noting some successes with power purchase agreements and generators in the pipeline, but also challenges around tariffs, land rights, and utility interest. The conclusion emphasizes that renewable energy is important for Tanzania but policy barriers including low tariffs have stalled development of renewable projects, and SPPs could help fill gaps in electrification.
In its MYPD 3 Selective Reopener application hearing starting on June 23, Eskom’s acting CEO Brian Molefe will argue that an increase in tariffs will shorten load shedding and improve overall generation stability.
Variable peak pricing and hedging jun 2006Michaline Todd
Presentation by Dr. Bernie Neenan, and economist with the Electric Power Research Institute.
Referenced in this May 26, 2011 eMeter blog post: http://bit.ly/k1cKVR
The ppt gives an overview on recent policy initiatives on Renwable Energy, like cerc\'s new regulation, national solar mission and renewable energy certificate
Over the years, renewable energy has grown steadily in India but further growth requires major improvements to distribution capabilities. While generation capacity has increased, demand has grown faster, highlighting the need for renewable energy to bridge the gap. However, for renewable energy to provide benefits, an efficient distribution system is needed. A key issue is the poor financial condition of utilities due to delays in tariff hikes to cover actual costs, limiting their ability to manage increasing renewable energy on the grid. Bailouts provide only temporary relief and reforms are needed for long-term viability, including a calibrated increase in tariffs to ensure efficiency.
This document provides an overview of key considerations for evaluating the project costing, economics, and developing a good business case for solar PV rooftop projects. It discusses various project investment models and how they affect components like warranties, taxes, and revenue sources. The document also outlines the major cost components, factors that influence costs, and approaches to determining tariffs and the levelized cost of energy. Sample calculations and scenarios are presented to compare different projects based on variables like tariffs, incentives, and loan terms. The conclusion emphasizes the importance of long-term energy generation, quality components, financing costs, and tariff patterns over the lifetime of the project.
Power procurement strategy--Mr. rohit bajaj Sujoy Das
The document provides an overview of India's power sector, including generation capacity and sources, renewable energy targets, capacity addition plans, financial health of generators and distribution companies, coal production and imports, power procurement strategies, and opportunities for cost optimization. Key points include:
- Coal based plants account for over 60% of installed capacity but are running at reduced plant load factors due to fuel shortages.
- Distribution companies have accumulated losses of over $45 billion due to low tariffs and inability to procure cheaper power.
- Procurement of power through short-term markets and electricity exchanges provides opportunities for cost savings compared to long-term bilateral contracts. Replacing higher cost generation with exchange power could save over $7.
Power procurement strategy-- Mr. Rohit BajajSujoy Das
The document discusses India's power sector and opportunities for cost optimization. It provides an overview of India's power capacity and generation by source. Coal makes up over 60% of installed capacity but 80% of generation. Renewables account for 13% of capacity. The exchange market has grown significantly but long-term PPAs account for over 90% of procurement. The document outlines opportunities for discoms to optimize costs such as utilizing short-term markets to meet peak demand, replacing higher-cost power with exchange power, and following a merit-order dispatch based on variable costs and exchange prices. Specific coal plants with costs above exchange prices are identified that could potentially be replaced to save over Rs 100 crore annually in Bihar.
4fc89288c1399 skm draft-report_-_review_of_lrmc_parameters_for_2013-14Sathish Paul
Sinclair Knight Merz (SKM) has been engaged by the Energy Market Authority (EMA) to review technical parameters for Singapore's vesting contracts for 2013-2014. SKM recommends parameters for a 383.47MW net combined cycle gas turbine plant including capital cost of $1004.21/kW, heat rate of 6886 Btu/kWh, economic life of 20 years, and average utilization of 72.8%. SKM also recommends removing quarterly indexation for overhead costs and conducting annual reviews of capital cost parameters to reduce vesting price volatility.
Wind Force Newsletter May, Edition, 2012rupeshsingh_1
The document discusses various policy developments and regulatory orders related to wind and renewable energy in India:
1) State electricity regulators in Andhra Pradesh and Karnataka announced increased retail tariffs for FY2012-13 which will make third party sale of wind power and open access more attractive.
2) The Ministry of Power is examining legislative and policy changes to accelerate renewable energy development including long term renewable purchase obligations.
3) Electricity regulators issued orders determining pooled power purchase costs, transmission charges, and renewable energy tariffs for FY2012-13.
4) Regulators also announced renewable purchase obligations for utilities, open access consumers, and captive power producers aimed at promoting renewable energy.
This document compares the economics of wind electricity to conventional electricity sources for captive power plants and utility companies. It presents the capital and operating costs of a 15 MW wind farm and different conventional options. Scenario I compares the levelized cost of electricity for wind vs. coal cogeneration, natural gas engines, and fuel oil engines for captive power plants over 20 years. Scenario II evaluates the costs for utility-scale coal, gas, and fuel oil plants vs. a 150 MW wind farm. The wind farm has lower lifetime costs per MWh than all fossil fuel options considered for both scenarios.
energy future holindings 040108ConfCallDeck_FINALfinance29
The document is a transcript from an investor call held by EFH Corp. on April 1, 2008. It includes:
1) A safe harbor statement noting forward-looking statements are subject to risks and uncertainties outlined in SEC filings.
2) Regulation G statement that any non-GAAP measures discussed will be reconciled to GAAP measures in the appendix.
3) An agenda for the call including presentations on strategy/operations highlights and financial overview from the CEO and CFO, followed by Q&A.
energy future holindings 040108_Conf_Call_Deck_FINALfinance29
The document summarizes an investor call for EFH Corp that discusses the company's financial performance in 2007 and operational highlights. It notes that EFH Corp's adjusted EBITDA declined 13% from 2006 to 2007 primarily due to changes at its TCEH business unit. Luminant met operational targets in 2007 including record lignite and nuclear power production. TXU Energy grew its residential customer count for the first time since 2001 and improved customer satisfaction. Both Luminant and TXU Energy committed to sustainability and renewable energy goals as part of the company's strategic objectives.
energy future holindings 040108_Conf_Call_Deck_FINALfinance29
The document is a transcript from an investor call held by EFH Corp. on April 1, 2008. It includes:
1) A safe harbor statement noting discussions of risks and uncertainties that could cause actual results to differ from projections.
2) Information on EFH Corp.'s adjusted EBITDA for 2006-2007, which dropped 13% due to factors including price discounts, increased fuel costs, and lower customer volumes.
3) Details on operational highlights and commitments from Luminant, TXU Energy, and Oncor regarding goals like emissions reductions, customer assistance programs, and capital investment.
Similar to Competitive bidding in the Power Sector: Is it working or not? (20)
The Move Towards Sustainable Transport in London - Mr. Steve KearnsIPPAI
This document discusses transport issues in London and strategies to promote more sustainable transport. It summarizes:
1) London faces significant transport challenges due to its growing population and over 23 million daily trips.
2) Transport for London is taking steps to encourage more sustainable modes of transport like walking, cycling, and public transit to reduce congestion. This includes upgrading infrastructure for buses, trains, and cycling.
3) Major events like the 2012 Olympics required extensive planning to manage large crowds and keep London moving, demonstrating how transport systems can be adapted to handle peak demand. Lessons from the Olympics are helping to inform ongoing improvements.
Standards – building blocks of the Smart City - Michael MulquinIPPAI
Standards are important building blocks for smart cities that can help at various levels. Benefits of smart city standards include enabling integration between different city systems, underpinning common understanding, helping to obtain funding and prevent vendor lock-in, and enabling scale. Many international standards organizations are working on smart city standards, including ISO, IEC, ITU, JTC1, CEN, and CENELEC. Their work includes areas like cybersecurity, resilience, and risk assessment. Key lessons are that India has much to learn from these efforts but also contribute through the Bureau of Indian Standards.
This document discusses principles for sustainable urban development in the 21st century. It outlines 5 principles: 1) adequate and efficient street networks, 2) mixed land use, 3) social mix, 4) adequate density, and 5) connectivity. It also discusses a 3-legged approach involving rules and regulations, urban design, and financial plans. Case studies from various cities around the world illustrate how these principles have been applied. The document argues that applying these principles along with new technologies can help address challenges of rapid urban growth and create more livable, connected, and economically vibrant cities.
Smart, Secure and Sustainable Cities India – Mr. Trevor GibsonIPPAI
Cities face complex challenges due to diverse populations and multiple stakeholders, but standards can help cities achieve their smart goals. Standards guide rather than constrain and address objectives, shared understanding, data sharing, and risks. Current BSI standards cover frameworks, vocabularies, planning, data concepts, and data sharing. A maturity assessment engages leaders to evaluate a city's "smartness" and positions standards as useful tools. While cities define "smart" differently, collaboration and shared vision are key to success, as is citizen involvement and trust. Standards that provide guidance rather than prescription can support varied city approaches lacking clear direction.
Industry Qualifications India - Cdr(Retd.) Kartik VigIPPAI
This document discusses Industry Qualifications India (IQ), which aims to bring stringent quality norms and international standards to vocational training in India. It notes that India needs to significantly increase skills training to meet its growing workforce needs. IQ plans to map existing Indian courses to international standards, develop new niche qualifications, and offer international certification for its qualifications. The benefits mentioned include increasing employment, income, and international experience for India; assuring quality and skills for industries; and providing credibility and career prospects for educational institutes. Going forward, IQ intends to expand nationwide, develop specialized courses, and help link industries and training providers.
The document discusses the Future Cities Catapult, which is one of seven innovation centers in the UK that aims to commercialize innovations and take them to markets around the world. Specifically, the Future Cities Catapult focuses on addressing challenges facing urban areas, such as increasing populations, inequality, and resource pressures. It plans to create a market for solutions to urban issues by establishing a housing lab for data analytics and modeling, building digital strategy demonstrators in cities, and creating an economic impact database to prove viability and demand to businesses and cities.
Can the dream of 100% renewable energy be a reality? - Mr. Ken DragoonIPPAI
This document summarizes a report on transforming power systems to derive most or all energy from variable renewable energy sources. It identifies three main challenges in relying primarily on renewable resources: rapidly adjusting supply and demand, filling in during low renewable output, and absorbing surplus energy. The document outlines a three-part transformation involving near, mid, and long-term changes to address these challenges through strategies like exploiting demand flexibility, enabling energy markets, controlling renewable generators, deploying energy storage, and establishing new energy uses.
Smart Cities, Smart Consequences? - Mr. Devdutt PattanaikIPPAI
The document discusses the evolution of cities from hunter-gatherer communities to modern cities and proposes futuristic smart cities as the next stage. It notes how early human settlements developed forests for protection, farming, trade, crafts, arts, sciences, script, power structures and governance as populations grew. The author argues smart cities could solve complex urban problems but also raises the issue of unintended consequences that require consideration.
1) The document discusses what is required for cities to be considered "smart cities" on a global scale. It examines trends in ecological footprints and biodiversity loss as well as the role of cities as centers of economic growth and urbanization.
2) Smart cities need to transition to low-carbon development through sustainable urban planning, renewable energy, green buildings, and engaging citizens to make sustainable lifestyle choices. The Earth Hour City Challenge recognizes cities that demonstrate global leadership in committing to and taking ambitious actions on climate change.
3) Cities require national and global support through knowledge sharing and financial innovation, as well as engaging citizens, to make progress toward becoming globally recognized smart cities that improve quality of life through sustainable urban solutions
From Smart Grid to Smart Cities - Richard SchombergIPPAI
Richard Schomberg discusses how smart cities use embedded sensors and a shared digital infrastructure across various systems like power, water, and transportation. This allows for the collection and analysis of data to improve operations in areas like traffic congestion prediction and crime reduction. However, smart cities also require long-term energy planning during their design to optimize renewable energy use, energy efficiency, and electric vehicle integration in a sustainable way. System modeling and simulation can help discover solutions and optimize goals like costs, emissions, and livability when planning new urban developments and infrastructure. Ultimately, smart city design should have an integrated systems approach and prioritize understanding human needs.
Mr. Harry Dhaul, Director General of Security Watch India, delivered an inaugural address thanking the audience. The address did not contain any other information beyond introducing Mr. Dhaul and expressing gratitude.
Future Cities: Innovation, Investment and Transformation - Professor Sir Dav...IPPAI
The document discusses future challenges facing cities including population growth, resource constraints, climate change, and their interactions. It notes that over 70% of the world's population will live in urban areas by 2050 and cities face challenges around food, water, energy security, health, and climate change. The document outlines rising global temperatures, sea level rise, extreme weather events, and crop failures as impacts of climate change. It advocates for smart, secure, and sustainable cities through innovation, investment, and transformation to address these challenges through approaches like circular economies, low-carbon vehicles, and prioritizing people over cars.
Smart Water and Waste Management for Smart Cities - Mr. James DunningIPPAI
The document discusses smart water and waste management technologies for smart cities. It describes some of the barriers to implementing smart water systems, such as too many alarms overwhelming operators. The document also provides examples of smart water deployments by Thames Water and Anglian Water. Anglian Water deployed monitoring units that helped locate leaks and bursts. After repair work, the units showed a reduction in bursts and leaks, saving water.
Smart Water and Wastewater Management For Smart Cities - Mr. Anjum ParwezIPPAI
The document discusses smart water and wastewater management in Indian cities. It provides data on water availability, sources of drinking water, wastewater treatment, and initiatives to improve services in various cities. It highlights challenges like inadequate and inequitable water supply, high non-revenue water, and lack of sewerage infrastructure. Recent initiatives by organizations like BWSSB and under programs like AMRUT and JnNURM aim to ensure regular water supply, reduce losses, recycle wastewater, and improve cost recovery through measures like metering and tariffs. Public-private partnerships are also being used to enhance water and sanitation services in cities.
Cosa hanno in comune un mattoncino Lego e la backdoor XZ?Speck&Tech
ABSTRACT: A prima vista, un mattoncino Lego e la backdoor XZ potrebbero avere in comune il fatto di essere entrambi blocchi di costruzione, o dipendenze di progetti creativi e software. La realtà è che un mattoncino Lego e il caso della backdoor XZ hanno molto di più di tutto ciò in comune.
Partecipate alla presentazione per immergervi in una storia di interoperabilità, standard e formati aperti, per poi discutere del ruolo importante che i contributori hanno in una comunità open source sostenibile.
BIO: Sostenitrice del software libero e dei formati standard e aperti. È stata un membro attivo dei progetti Fedora e openSUSE e ha co-fondato l'Associazione LibreItalia dove è stata coinvolta in diversi eventi, migrazioni e formazione relativi a LibreOffice. In precedenza ha lavorato a migrazioni e corsi di formazione su LibreOffice per diverse amministrazioni pubbliche e privati. Da gennaio 2020 lavora in SUSE come Software Release Engineer per Uyuni e SUSE Manager e quando non segue la sua passione per i computer e per Geeko coltiva la sua curiosità per l'astronomia (da cui deriva il suo nickname deneb_alpha).
Digital Marketing Trends in 2024 | Guide for Staying AheadWask
https://www.wask.co/ebooks/digital-marketing-trends-in-2024
Feeling lost in the digital marketing whirlwind of 2024? Technology is changing, consumer habits are evolving, and staying ahead of the curve feels like a never-ending pursuit. This e-book is your compass. Dive into actionable insights to handle the complexities of modern marketing. From hyper-personalization to the power of user-generated content, learn how to build long-term relationships with your audience and unlock the secrets to success in the ever-shifting digital landscape.
HCL Notes and Domino License Cost Reduction in the World of DLAUpanagenda
Webinar Recording: https://www.panagenda.com/webinars/hcl-notes-and-domino-license-cost-reduction-in-the-world-of-dlau/
The introduction of DLAU and the CCB & CCX licensing model caused quite a stir in the HCL community. As a Notes and Domino customer, you may have faced challenges with unexpected user counts and license costs. You probably have questions on how this new licensing approach works and how to benefit from it. Most importantly, you likely have budget constraints and want to save money where possible. Don’t worry, we can help with all of this!
We’ll show you how to fix common misconfigurations that cause higher-than-expected user counts, and how to identify accounts which you can deactivate to save money. There are also frequent patterns that can cause unnecessary cost, like using a person document instead of a mail-in for shared mailboxes. We’ll provide examples and solutions for those as well. And naturally we’ll explain the new licensing model.
Join HCL Ambassador Marc Thomas in this webinar with a special guest appearance from Franz Walder. It will give you the tools and know-how to stay on top of what is going on with Domino licensing. You will be able lower your cost through an optimized configuration and keep it low going forward.
These topics will be covered
- Reducing license cost by finding and fixing misconfigurations and superfluous accounts
- How do CCB and CCX licenses really work?
- Understanding the DLAU tool and how to best utilize it
- Tips for common problem areas, like team mailboxes, functional/test users, etc
- Practical examples and best practices to implement right away
Project Management Semester Long Project - Acuityjpupo2018
Acuity is an innovative learning app designed to transform the way you engage with knowledge. Powered by AI technology, Acuity takes complex topics and distills them into concise, interactive summaries that are easy to read & understand. Whether you're exploring the depths of quantum mechanics or seeking insight into historical events, Acuity provides the key information you need without the burden of lengthy texts.
Introduction of Cybersecurity with OSS at Code Europe 2024Hiroshi SHIBATA
I develop the Ruby programming language, RubyGems, and Bundler, which are package managers for Ruby. Today, I will introduce how to enhance the security of your application using open-source software (OSS) examples from Ruby and RubyGems.
The first topic is CVE (Common Vulnerabilities and Exposures). I have published CVEs many times. But what exactly is a CVE? I'll provide a basic understanding of CVEs and explain how to detect and handle vulnerabilities in OSS.
Next, let's discuss package managers. Package managers play a critical role in the OSS ecosystem. I'll explain how to manage library dependencies in your application.
I'll share insights into how the Ruby and RubyGems core team works to keep our ecosystem safe. By the end of this talk, you'll have a better understanding of how to safeguard your code.
For the full video of this presentation, please visit: https://www.edge-ai-vision.com/2024/06/building-and-scaling-ai-applications-with-the-nx-ai-manager-a-presentation-from-network-optix/
Robin van Emden, Senior Director of Data Science at Network Optix, presents the “Building and Scaling AI Applications with the Nx AI Manager,” tutorial at the May 2024 Embedded Vision Summit.
In this presentation, van Emden covers the basics of scaling edge AI solutions using the Nx tool kit. He emphasizes the process of developing AI models and deploying them globally. He also showcases the conversion of AI models and the creation of effective edge AI pipelines, with a focus on pre-processing, model conversion, selecting the appropriate inference engine for the target hardware and post-processing.
van Emden shows how Nx can simplify the developer’s life and facilitate a rapid transition from concept to production-ready applications.He provides valuable insights into developing scalable and efficient edge AI solutions, with a strong focus on practical implementation.
Skybuffer SAM4U tool for SAP license adoptionTatiana Kojar
Manage and optimize your license adoption and consumption with SAM4U, an SAP free customer software asset management tool.
SAM4U, an SAP complimentary software asset management tool for customers, delivers a detailed and well-structured overview of license inventory and usage with a user-friendly interface. We offer a hosted, cost-effective, and performance-optimized SAM4U setup in the Skybuffer Cloud environment. You retain ownership of the system and data, while we manage the ABAP 7.58 infrastructure, ensuring fixed Total Cost of Ownership (TCO) and exceptional services through the SAP Fiori interface.
HCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAUpanagenda
Webinar Recording: https://www.panagenda.com/webinars/hcl-notes-und-domino-lizenzkostenreduzierung-in-der-welt-von-dlau/
DLAU und die Lizenzen nach dem CCB- und CCX-Modell sind für viele in der HCL-Community seit letztem Jahr ein heißes Thema. Als Notes- oder Domino-Kunde haben Sie vielleicht mit unerwartet hohen Benutzerzahlen und Lizenzgebühren zu kämpfen. Sie fragen sich vielleicht, wie diese neue Art der Lizenzierung funktioniert und welchen Nutzen sie Ihnen bringt. Vor allem wollen Sie sicherlich Ihr Budget einhalten und Kosten sparen, wo immer möglich. Das verstehen wir und wir möchten Ihnen dabei helfen!
Wir erklären Ihnen, wie Sie häufige Konfigurationsprobleme lösen können, die dazu führen können, dass mehr Benutzer gezählt werden als nötig, und wie Sie überflüssige oder ungenutzte Konten identifizieren und entfernen können, um Geld zu sparen. Es gibt auch einige Ansätze, die zu unnötigen Ausgaben führen können, z. B. wenn ein Personendokument anstelle eines Mail-Ins für geteilte Mailboxen verwendet wird. Wir zeigen Ihnen solche Fälle und deren Lösungen. Und natürlich erklären wir Ihnen das neue Lizenzmodell.
Nehmen Sie an diesem Webinar teil, bei dem HCL-Ambassador Marc Thomas und Gastredner Franz Walder Ihnen diese neue Welt näherbringen. Es vermittelt Ihnen die Tools und das Know-how, um den Überblick zu bewahren. Sie werden in der Lage sein, Ihre Kosten durch eine optimierte Domino-Konfiguration zu reduzieren und auch in Zukunft gering zu halten.
Diese Themen werden behandelt
- Reduzierung der Lizenzkosten durch Auffinden und Beheben von Fehlkonfigurationen und überflüssigen Konten
- Wie funktionieren CCB- und CCX-Lizenzen wirklich?
- Verstehen des DLAU-Tools und wie man es am besten nutzt
- Tipps für häufige Problembereiche, wie z. B. Team-Postfächer, Funktions-/Testbenutzer usw.
- Praxisbeispiele und Best Practices zum sofortigen Umsetzen
Driving Business Innovation: Latest Generative AI Advancements & Success StorySafe Software
Are you ready to revolutionize how you handle data? Join us for a webinar where we’ll bring you up to speed with the latest advancements in Generative AI technology and discover how leveraging FME with tools from giants like Google Gemini, Amazon, and Microsoft OpenAI can supercharge your workflow efficiency.
During the hour, we’ll take you through:
Guest Speaker Segment with Hannah Barrington: Dive into the world of dynamic real estate marketing with Hannah, the Marketing Manager at Workspace Group. Hear firsthand how their team generates engaging descriptions for thousands of office units by integrating diverse data sources—from PDF floorplans to web pages—using FME transformers, like OpenAIVisionConnector and AnthropicVisionConnector. This use case will show you how GenAI can streamline content creation for marketing across the board.
Ollama Use Case: Learn how Scenario Specialist Dmitri Bagh has utilized Ollama within FME to input data, create custom models, and enhance security protocols. This segment will include demos to illustrate the full capabilities of FME in AI-driven processes.
Custom AI Models: Discover how to leverage FME to build personalized AI models using your data. Whether it’s populating a model with local data for added security or integrating public AI tools, find out how FME facilitates a versatile and secure approach to AI.
We’ll wrap up with a live Q&A session where you can engage with our experts on your specific use cases, and learn more about optimizing your data workflows with AI.
This webinar is ideal for professionals seeking to harness the power of AI within their data management systems while ensuring high levels of customization and security. Whether you're a novice or an expert, gain actionable insights and strategies to elevate your data processes. Join us to see how FME and AI can revolutionize how you work with data!
Building Production Ready Search Pipelines with Spark and MilvusZilliz
Spark is the widely used ETL tool for processing, indexing and ingesting data to serving stack for search. Milvus is the production-ready open-source vector database. In this talk we will show how to use Spark to process unstructured data to extract vector representations, and push the vectors to Milvus vector database for search serving.
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slackshyamraj55
Discover the seamless integration of RPA (Robotic Process Automation), COMPOSER, and APM with AWS IDP enhanced with Slack notifications. Explore how these technologies converge to streamline workflows, optimize performance, and ensure secure access, all while leveraging the power of AWS IDP and real-time communication via Slack notifications.
Monitoring and Managing Anomaly Detection on OpenShift.pdfTosin Akinosho
Monitoring and Managing Anomaly Detection on OpenShift
Overview
Dive into the world of anomaly detection on edge devices with our comprehensive hands-on tutorial. This SlideShare presentation will guide you through the entire process, from data collection and model training to edge deployment and real-time monitoring. Perfect for those looking to implement robust anomaly detection systems on resource-constrained IoT/edge devices.
Key Topics Covered
1. Introduction to Anomaly Detection
- Understand the fundamentals of anomaly detection and its importance in identifying unusual behavior or failures in systems.
2. Understanding Edge (IoT)
- Learn about edge computing and IoT, and how they enable real-time data processing and decision-making at the source.
3. What is ArgoCD?
- Discover ArgoCD, a declarative, GitOps continuous delivery tool for Kubernetes, and its role in deploying applications on edge devices.
4. Deployment Using ArgoCD for Edge Devices
- Step-by-step guide on deploying anomaly detection models on edge devices using ArgoCD.
5. Introduction to Apache Kafka and S3
- Explore Apache Kafka for real-time data streaming and Amazon S3 for scalable storage solutions.
6. Viewing Kafka Messages in the Data Lake
- Learn how to view and analyze Kafka messages stored in a data lake for better insights.
7. What is Prometheus?
- Get to know Prometheus, an open-source monitoring and alerting toolkit, and its application in monitoring edge devices.
8. Monitoring Application Metrics with Prometheus
- Detailed instructions on setting up Prometheus to monitor the performance and health of your anomaly detection system.
9. What is Camel K?
- Introduction to Camel K, a lightweight integration framework built on Apache Camel, designed for Kubernetes.
10. Configuring Camel K Integrations for Data Pipelines
- Learn how to configure Camel K for seamless data pipeline integrations in your anomaly detection workflow.
11. What is a Jupyter Notebook?
- Overview of Jupyter Notebooks, an open-source web application for creating and sharing documents with live code, equations, visualizations, and narrative text.
12. Jupyter Notebooks with Code Examples
- Hands-on examples and code snippets in Jupyter Notebooks to help you implement and test anomaly detection models.
TrustArc Webinar - 2024 Global Privacy SurveyTrustArc
How does your privacy program stack up against your peers? What challenges are privacy teams tackling and prioritizing in 2024?
In the fifth annual Global Privacy Benchmarks Survey, we asked over 1,800 global privacy professionals and business executives to share their perspectives on the current state of privacy inside and outside of their organizations. This year’s report focused on emerging areas of importance for privacy and compliance professionals, including considerations and implications of Artificial Intelligence (AI) technologies, building brand trust, and different approaches for achieving higher privacy competence scores.
See how organizational priorities and strategic approaches to data security and privacy are evolving around the globe.
This webinar will review:
- The top 10 privacy insights from the fifth annual Global Privacy Benchmarks Survey
- The top challenges for privacy leaders, practitioners, and organizations in 2024
- Key themes to consider in developing and maintaining your privacy program
2. Power Procurement – Competitive Bidding Process
Bid Evaluation
The bids are evaluated for each escalable and non-escalable components of
capacity charge, energy charge and transportation charges
The levelised tariff of each bidders are compared incorporating the transmission
charges from the point of injection to point of supply, accordingly, the bidders
need to adjust their escalable and non-escalable components as part of their
winning strategies
Confidential Slide 2
3. Power Procurement – Competitive Bidding Process
Key Aspects of PPA
Risk allocation between parties
Land Acquisition
Fuel Supply
Technical requirements on minimum load condition
Assured off take levels
Force majeure clauses as per industry standards
Change in Law in state/country or cross country level
Lead times for scheduling of power
Default conditions and cure thereof, and penalties
Payment security proposed to be offered by the procurer
Confidential Slide 3
4. Case I bidding: Observed tariff ranges…
Evolution of weighted average Case I bids
Weighted Average Case I Tariffs (Rs./kWh)
5
4.5
4
Rs/kWh
3.5
3
2.5
2
Sept Dec Dec Nov Nov Feb Dec Aug Aug Jan Jan Jan Mar Sept Oct Oct Dec Dec
2006 2006 2006 2007 2007 2008 2008 2009 2009 2010 2010 2010 2010 2010 2010 2010 2010 2010
Bids have observed a linear growth trend owing to:
o Increased costs of fuel and financing
o Higher risk perception on fuel availability and payment front
Confidential Slide 4
5. Long Term Bid Process - Tariff Quotes
Capacity Offered Levellized Tariff
Rank Name of Bidder and Project
(MW) (Rs./kWh)
L1 RPG Group - Dhariwal Infrastructure Ltd. 200 3.513
L2 Reliance Power Ltd. 1000 4.311
L3 Vandana Vidyut Ltd. 150 4.493
L4 PTC - MB Power MP 200 4.590
L5 RKM PowerGen Pvt. Ltd. 300 4.670
L6 Indiabulls Power Limited 490 4.800
L7 PTC - DB Power 150 5.593
Result of Financial Bid Opening held on 09-Dec-11
Confidential Slide 5
7. Power Procurement – Medium Term
Tariff Components for Medium Term Power tied-up from FY12 to FY14
PPA Date: 16-Jun-10,
MTPP PPA Date: 04-Jun-10 PPA Date: 04-Aug-10
Addendum: 21-Jan-11*
KSK-WPCL (260MW) Abhijeet (55MW) VIPL (134MW)
FY-11-12 FY-12-13 FY-13-14 FY-11-12 FY-12-13 FY-13-14 FY-12-13 FY-13-14
Fixed Cost (FC) 4.00 3.90 3.00 3.414 3.001 2.47 3.194 2.945
Variable Cost (VC) 1.465 1.02 1.025 1.75 1.811 1.875 0.989 0.989
Total 5.465 4.92 4.025 5.164 4.812 4.345 4.183 3.934
Fixed Cost - % age 73% 79% 75% 66% 62% 57% 76% 75%
Low Variable Component poses risk of DTPS backing down
Confidential Slide 7
8. Success or Failure – Probably limited success –WHY?
GENERATOR:
Fuel Availability and price uncertainity
Project Execution risk – Land/Environment/logistics etc
Assured off take levels
Inability to get financing at fixed cost matching with the PPA term (Limited access to
Development Banking resources)
Payment Security
DISTRIBUTION LICENSEE:
Cost reflective timely tariff and Fuel cost variation recovery
Freedom to change consumption by consumer and consequential losses (under
recovery of fixed cost for lower off take or loss on alternate disposal/sale)
Low collection efficiency due inability to pay or due to unwillingness to pay (Socio-
political issues)
Confidential Slide 8