• G a s a n d s t e a m
t u r b i n e s a r e u s e d
together
• The waste heat from
t h e g a s t u r b i n e i s
r o u t e d t o y s t e a m
turbine.
• Gas Turbine
• Heat Recovery Steam Generator (HRSG)
• Steam Turbine
Gas Turbine
•Air is compressed in
Compressor.
•F u e l b u r n s i n
Combustion Chamber.
•Hot air-fuel mixture
moves through the Gas
Turbine Blades
CROSS-SECTION OF GAS TURBINE
MATERIAL OF GAS TURBINE BLADES
TYPES OF GAS TURBINE
• Gas turbine with multistage compressor
• Gas turbine with reheater
GAS TURBINE WITH REHEAT
GAS TURBINE WITH MULTISTAGE
COMPRESSOR
HEAT RECOVERY STEAM GENERATOR
•Captures exhaust heat
from Gas turbine.
•Creates Steam from
and delivers it to steam
turbine.
TYPES OF STEAM GENERATOR
STEAM TURBINE
FUEL OF COMBINE CYCLE POWER
PLANT
CHEMICAL COMPOSITION OF NATURAL
GAS
NATIONAL PRODUCTION OF
ELECTRICITY FROM NATURAL GAS
ANNUAL ELECTRICITY PRODUCTION
FROM NATURAL GAS
GLOBAL GAS RESERVES (2014)
PRODUCTION AND CONSUPTION OF
NATURAL GAS
PRODUCTION AND CONSUPTION OF
NATURAL GAS
STEAMPOWER PLANT
• Steam power plant
operate on Rankine
cycle
• W o r l d w i d e , m o s t
e l e c t r i c p o w e r i s
produced by steam-
electric power plants,
which produce about
86% of all electric
COMBINED CYCLE GAS TURBINE:
• The combined cycle
consists of the following
two cycles:
Brayton cycle
Rankine cycle
• Efficiency of CCPP
35–42%
BRAYTON CYCLE
Rankine Cycle
1. steam generation in a boiler
at constant pressure
2. isentropic expansion in a
steam turbine
3. condensation in a condenser
at constant pressure
4. pressurizing condensate to
boiler pressure by isentropic
compression
EMISSION STANDARDS
CATALYTIC OXIDATION ANS SCR
SYSTEM
OVERNIGHT CAPITAL COST OF CCPP
POWER PLANT IN PAKISTAN
Wapda took over generation, transmission and
distribution of Power in the country(except in
Karachi) in 1959
YEAR PRODUCTION CAPACITY (MW)
1947 17
1959 119
THEMAL POWER PLANTS IN PAKISTAN
• Pakistan is producing 61% of electricity from
Thermal power.
• Total thermal installed capacity of Pakistan is
16599MW.
• The biggest thermal power plants are Guddu with
capacity 2402MW, TPS Muzaffargarh 1350MW, Kot
Addu with 1638MW capacity
Name of
Plants
Province
/City
Work
From
Nominal
Power
(MW)
Mean
Practical
Power(M
W)
Generation
2015(MWh
)
Guddu Sindh/Guddu 1974 2402 1902 5510000
GTPS
Faisalabad
Punjab/
Faisalabad
1967 376 310 76000
Nandipur Punjab/
Nandipur
2014 325 286 244000
GPTS
Kotri
Sindh/
Kotri
1969 144 140 306000