Boehm’s [1981] definition of organic,
semidetached, and embedded systems are
elaborated below
• Organic:
A development project can be considered of organic
type, if the project deals with developing a well
understood application program, the size of the
development team is reasonably small, and the
team members are experienced in developing
similar types of projects.
Semidetached
• A development project can be considered of
semidetached type, if the development
consists of a mixture of experienced and
inexperienced staff.
• Team members may have limited experience
on related systems but may be unfamiliar with
some aspects of the system being developed.
Embedded
• A development project is considered to be of
embedded type, if the software being
developed is strongly coupled to complex
hardware, or if the stringent regulations on
the operational procedures exist
COCOMO
• COCOMO (Constructive Cost Estimation
Model) was proposed by Boehm [1981].
According to Boehm, software cost estimation
should be done through three stages: Basic
COCOMO, Intermediate COCOMO, and
Complete COCOMO.
Basic COCOMO Model
• The basic COCOMO model gives an
approximate estimate of the project
parameters. The basic COCOMO estimation
model is given by the following expressions:
• Effort = a1 х (KLOC)a2 PM
• Tdev = b1 x (Effort)b2 Months
Continued..
Where
• KLOC is the estimated size of the software product
expressed in Kilo Lines of Code,
• a1, a2, b1, b2 are constants for each category of software
products,
• Tdev is the estimated time to develop the software,
expressed in months,
• Effort is the total effort required to develop the software
product, expressed in person months (PMs).
Continued..
• The effort estimation is expressed in units of
person-months (PM). It is the area under the
person-month plot (as shown in fig.).
• It should be carefully noted that an effort of
100 PM does not imply that 100 persons
should work for 1 month nor does it imply
that 1 person should be employed for 100
months, but it denotes the area under the
person-month curve.
Continued..
Estimation of
development effort
• For the three classes of software products,
the formulas for estimating the effort based
on the code size are shown below:
• Organic : Effort = 2.4(KLOC)1.05 PM
• Semi-detached : Effort = 3.0(KLOC)1.12 PM
• Embedded : Effort = 3.6(KLOC)1.20 PM
Estimation of
development time
• For the three classes of software products,
the formulas for estimating the development
time based on the effort are given below:
• Organic : Tdev = 2.5(Effort)0.38 Months
• Semi-detached : Tdev = 2.5(Effort)0.35 Months
• Embedded : Tdev = 2.5(Effort)0.32 Months
Example
• Assume that the size of an organic type
software product has been estimated to be
32,000 lines of source code. Assume that the
average salary of software engineers be Rs.
15,000/- per month. Determine the effort
required to develop the software product and
the nominal development time.
Solution
• From the basic COCOMO estimation formula
for organic software:
• Effort = 2.4 х (32)1.05 = 91 PM
• Nominal development time = 2.5 х (91)0.38 =
14 months
• Cost required to develop the product = 14 х
15,000
• = Rs. 210,000/-
ITFT -  Cocomo model

More Related Content

What's hot

Cocomo model (muskan soni)
Cocomo model (muskan soni)Cocomo model (muskan soni)
Cocomo model (muskan soni)
MuskanSony
 
Cocomo models
Cocomo modelsCocomo models
Cocomo models
minhasmushtaqbhatti
 
Software estimation models ii lec .05
Software estimation models ii lec .05Software estimation models ii lec .05
Software estimation models ii lec .05
Noor Ul Hudda Memon
 
COCOMO Model in software project management
COCOMO Model in software project managementCOCOMO Model in software project management
COCOMO Model in software project management
Syed Hassan Ali
 
COCOMO MODEL 1 And 2
COCOMO MODEL 1 And 2COCOMO MODEL 1 And 2
COCOMO MODEL 1 And 2
Awais Siddique
 
COCOMO model | How to calculate effort, staffing and Duration of Project
COCOMO model | How to calculate effort, staffing and Duration of ProjectCOCOMO model | How to calculate effort, staffing and Duration of Project
COCOMO model | How to calculate effort, staffing and Duration of Project
Navjyotsinh Jadeja
 
Cocomo model
Cocomo modelCocomo model
Cocomo model
Devan Thakur
 
Cocomo
CocomoCocomo
Cocomo
Yunis Lone
 
software project management Cocomo model
software project management Cocomo modelsoftware project management Cocomo model
software project management Cocomo model
REHMAT ULLAH
 
Cocomo model
Cocomo modelCocomo model
Cocomo model
ZunairaIshtiaq2
 
Software Estimation Part I
Software Estimation Part ISoftware Estimation Part I
Software Estimation Part Isslovepk
 
COCOMO MODEL
COCOMO MODELCOCOMO MODEL
COCOMO MODEL
movie_2009
 
New microsoft office power point presentation
New microsoft office power point presentationNew microsoft office power point presentation
New microsoft office power point presentationMiha Tisca
 
COCOMO model
COCOMO modelCOCOMO model
COCOMO model
hajra azam
 
Software estimation
Software estimationSoftware estimation
Software estimationMd Shakir
 
Cocomo ( cot constrictive model) and capability maturity model
Cocomo ( cot constrictive model) and capability maturity modelCocomo ( cot constrictive model) and capability maturity model
Cocomo ( cot constrictive model) and capability maturity model
Prakash Poudel
 
Software Estimation Techniques
Software Estimation TechniquesSoftware Estimation Techniques
Software Estimation Techniques
kamal
 

What's hot (20)

Cocomo model (muskan soni)
Cocomo model (muskan soni)Cocomo model (muskan soni)
Cocomo model (muskan soni)
 
Cocomo models
Cocomo modelsCocomo models
Cocomo models
 
Software estimation models ii lec .05
Software estimation models ii lec .05Software estimation models ii lec .05
Software estimation models ii lec .05
 
COCOMO Model in software project management
COCOMO Model in software project managementCOCOMO Model in software project management
COCOMO Model in software project management
 
Cocomo model
Cocomo modelCocomo model
Cocomo model
 
COCOMO MODEL 1 And 2
COCOMO MODEL 1 And 2COCOMO MODEL 1 And 2
COCOMO MODEL 1 And 2
 
Cocom ii
Cocom iiCocom ii
Cocom ii
 
COCOMO model | How to calculate effort, staffing and Duration of Project
COCOMO model | How to calculate effort, staffing and Duration of ProjectCOCOMO model | How to calculate effort, staffing and Duration of Project
COCOMO model | How to calculate effort, staffing and Duration of Project
 
Cocomo model
Cocomo modelCocomo model
Cocomo model
 
Cocomo
CocomoCocomo
Cocomo
 
software project management Cocomo model
software project management Cocomo modelsoftware project management Cocomo model
software project management Cocomo model
 
Cocomo model
Cocomo modelCocomo model
Cocomo model
 
Software Estimation Part I
Software Estimation Part ISoftware Estimation Part I
Software Estimation Part I
 
COCOMO MODEL
COCOMO MODELCOCOMO MODEL
COCOMO MODEL
 
New microsoft office power point presentation
New microsoft office power point presentationNew microsoft office power point presentation
New microsoft office power point presentation
 
COCOMO model
COCOMO modelCOCOMO model
COCOMO model
 
Software estimation
Software estimationSoftware estimation
Software estimation
 
Cocomo model
Cocomo modelCocomo model
Cocomo model
 
Cocomo ( cot constrictive model) and capability maturity model
Cocomo ( cot constrictive model) and capability maturity modelCocomo ( cot constrictive model) and capability maturity model
Cocomo ( cot constrictive model) and capability maturity model
 
Software Estimation Techniques
Software Estimation TechniquesSoftware Estimation Techniques
Software Estimation Techniques
 

Viewers also liked

Chapter 4 software project planning
Chapter 4 software project planningChapter 4 software project planning
Chapter 4 software project planningPiyush Gogia
 
USC COCOMO II
USC COCOMO IIUSC COCOMO II
USC COCOMO II
humberthomattar
 
TDC 2015 Porto Alegre - Preciso estimar mesmo?
TDC 2015 Porto Alegre - Preciso estimar mesmo?TDC 2015 Porto Alegre - Preciso estimar mesmo?
TDC 2015 Porto Alegre - Preciso estimar mesmo?
Emerson Schenatto
 
Otimização do Desempenho de Times Ágeis - UaiJUG techdays - Uberlândia - MG
Otimização do Desempenho de Times Ágeis - UaiJUG techdays - Uberlândia - MGOtimização do Desempenho de Times Ágeis - UaiJUG techdays - Uberlândia - MG
Otimização do Desempenho de Times Ágeis - UaiJUG techdays - Uberlândia - MG
Samyr Abdo
 
COCOMO II
COCOMO IICOCOMO II
COCOMO II
FRAYOCALLE
 
Information technology
Information technologyInformation technology
Information technologyHaitham Farouk
 
Cocomo
CocomoCocomo
Cocomo
gmjuan
 
Estimativa de Esforço
Estimativa de EsforçoEstimativa de Esforço
Estimativa de Esforçoelliando dias
 
COCOMO E COCOMO II
COCOMO E COCOMO IICOCOMO E COCOMO II
COCOMO E COCOMO II
IsraelCunha
 
Eng.Software-Métricas
Eng.Software-MétricasEng.Software-Métricas
Eng.Software-Métricaselliando dias
 
Medida de Esforço de Software com Análise de Ponto de Função
Medida de Esforço de Software com Análise de Ponto de FunçãoMedida de Esforço de Software com Análise de Ponto de Função
Medida de Esforço de Software com Análise de Ponto de Função
Álvaro Farias Pinheiro
 
Estimativas em projetos de software
Estimativas em projetos de softwareEstimativas em projetos de software
Estimativas em projetos de software
Synergia - Engenharia de Software e Sistemas
 
Fundamentos APF
Fundamentos APFFundamentos APF
Fundamentos APF
humberthomattar
 
Estimativa de software usando pontos de função
Estimativa de software usando pontos de funçãoEstimativa de software usando pontos de função
Estimativa de software usando pontos de função
Claudio Martins
 
Cocomo II
Cocomo IICocomo II
Cocomo II
Actimel
 
Ch23-Software Engineering 9
Ch23-Software Engineering 9Ch23-Software Engineering 9
Ch23-Software Engineering 9Ian Sommerville
 
Software cost estimation
Software cost estimationSoftware cost estimation
Software cost estimation
Haitham Ahmed
 
Software cost estimation
Software cost estimationSoftware cost estimation
Software cost estimation
Dr. C.V. Suresh Babu
 

Viewers also liked (19)

Chapter 4 software project planning
Chapter 4 software project planningChapter 4 software project planning
Chapter 4 software project planning
 
USC COCOMO II
USC COCOMO IIUSC COCOMO II
USC COCOMO II
 
TDC 2015 Porto Alegre - Preciso estimar mesmo?
TDC 2015 Porto Alegre - Preciso estimar mesmo?TDC 2015 Porto Alegre - Preciso estimar mesmo?
TDC 2015 Porto Alegre - Preciso estimar mesmo?
 
Otimização do Desempenho de Times Ágeis - UaiJUG techdays - Uberlândia - MG
Otimização do Desempenho de Times Ágeis - UaiJUG techdays - Uberlândia - MGOtimização do Desempenho de Times Ágeis - UaiJUG techdays - Uberlândia - MG
Otimização do Desempenho de Times Ágeis - UaiJUG techdays - Uberlândia - MG
 
Fi ti- aula 10
Fi ti- aula 10Fi ti- aula 10
Fi ti- aula 10
 
COCOMO II
COCOMO IICOCOMO II
COCOMO II
 
Information technology
Information technologyInformation technology
Information technology
 
Cocomo
CocomoCocomo
Cocomo
 
Estimativa de Esforço
Estimativa de EsforçoEstimativa de Esforço
Estimativa de Esforço
 
COCOMO E COCOMO II
COCOMO E COCOMO IICOCOMO E COCOMO II
COCOMO E COCOMO II
 
Eng.Software-Métricas
Eng.Software-MétricasEng.Software-Métricas
Eng.Software-Métricas
 
Medida de Esforço de Software com Análise de Ponto de Função
Medida de Esforço de Software com Análise de Ponto de FunçãoMedida de Esforço de Software com Análise de Ponto de Função
Medida de Esforço de Software com Análise de Ponto de Função
 
Estimativas em projetos de software
Estimativas em projetos de softwareEstimativas em projetos de software
Estimativas em projetos de software
 
Fundamentos APF
Fundamentos APFFundamentos APF
Fundamentos APF
 
Estimativa de software usando pontos de função
Estimativa de software usando pontos de funçãoEstimativa de software usando pontos de função
Estimativa de software usando pontos de função
 
Cocomo II
Cocomo IICocomo II
Cocomo II
 
Ch23-Software Engineering 9
Ch23-Software Engineering 9Ch23-Software Engineering 9
Ch23-Software Engineering 9
 
Software cost estimation
Software cost estimationSoftware cost estimation
Software cost estimation
 
Software cost estimation
Software cost estimationSoftware cost estimation
Software cost estimation
 

Similar to ITFT - Cocomo model

5. COCOMO.pdf
5. COCOMO.pdf5. COCOMO.pdf
5. COCOMO.pdf
PedadaSaikumar
 
Exp 02-COCOMO (1).pptx
Exp 02-COCOMO (1).pptxExp 02-COCOMO (1).pptx
Exp 02-COCOMO (1).pptx
YagnaGummadi
 
Putnam Resource allocation model.ppt
Putnam Resource allocation model.pptPutnam Resource allocation model.ppt
Putnam Resource allocation model.ppt
AnupamaSharma80
 
Effort estimation( software Engineering)
Effort estimation( software Engineering)Effort estimation( software Engineering)
Effort estimation( software Engineering)
kiran Patel
 
cocomo.pptx
cocomo.pptxcocomo.pptx
cocomo.pptx
HarshitPandey134
 
PMansgement-costmanagementforproject.pptx
PMansgement-costmanagementforproject.pptxPMansgement-costmanagementforproject.pptx
PMansgement-costmanagementforproject.pptx
iamasniya07
 
COCOMO (Software Engineering)
COCOMO (Software Engineering)COCOMO (Software Engineering)
COCOMO (Software Engineering)
Biswadeep Mukhopadhyay
 
cocomo-220726173706-141e0dsdsd8f0 (1).pdf
cocomo-220726173706-141e0dsdsd8f0 (1).pdfcocomo-220726173706-141e0dsdsd8f0 (1).pdf
cocomo-220726173706-141e0dsdsd8f0 (1).pdf
ssuser2d043c
 
Software engineering 10 software cost estimation cocomo
Software engineering 10 software cost estimation cocomoSoftware engineering 10 software cost estimation cocomo
Software engineering 10 software cost estimation cocomo
Vaibhav Khanna
 
Cocomo model
Cocomo modelCocomo model
Cocomo model
Baskarkncet
 
Cocomomodel
CocomomodelCocomomodel
Se 381 - lec 25 - 32 - 12 may29 - program size and cost estimation models
Se 381 - lec 25 - 32 - 12 may29 - program size and cost estimation modelsSe 381 - lec 25 - 32 - 12 may29 - program size and cost estimation models
Se 381 - lec 25 - 32 - 12 may29 - program size and cost estimation models
babak danyal
 
COCOMO methods for software size estimation
COCOMO methods for software size estimationCOCOMO methods for software size estimation
COCOMO methods for software size estimation
Pramod Parajuli
 
COCOMO 1 Model ppt AR-1.pdf
COCOMO 1 Model  ppt AR-1.pdfCOCOMO 1 Model  ppt AR-1.pdf
COCOMO 1 Model ppt AR-1.pdf
23017156038
 
COCOMO Model.pptx
COCOMO Model.pptxCOCOMO Model.pptx
COCOMO Model.pptx
suchi70
 
software project management
software project managementsoftware project management
software project management
Jassir4
 
LECT9.ppt
LECT9.pptLECT9.ppt
LECT9.ppt
AnSHiKa187943
 
COCOMO FP COST ESTIMATION TECHNIQUES:NUMERIC
COCOMO FP COST ESTIMATION TECHNIQUES:NUMERICCOCOMO FP COST ESTIMATION TECHNIQUES:NUMERIC
COCOMO FP COST ESTIMATION TECHNIQUES:NUMERIC
Sneha Padhiar
 
COCOMO FP COST ESTIMATION TECHNIQUES:NUMERIC
COCOMO FP COST ESTIMATION TECHNIQUES:NUMERICCOCOMO FP COST ESTIMATION TECHNIQUES:NUMERIC
COCOMO FP COST ESTIMATION TECHNIQUES:NUMERIC
Sneha Padhiar
 
SOFTWARE ESTIMATION COCOMO AND FP CALCULATION
SOFTWARE ESTIMATION COCOMO AND FP CALCULATIONSOFTWARE ESTIMATION COCOMO AND FP CALCULATION
SOFTWARE ESTIMATION COCOMO AND FP CALCULATION
Sneha Padhiar
 

Similar to ITFT - Cocomo model (20)

5. COCOMO.pdf
5. COCOMO.pdf5. COCOMO.pdf
5. COCOMO.pdf
 
Exp 02-COCOMO (1).pptx
Exp 02-COCOMO (1).pptxExp 02-COCOMO (1).pptx
Exp 02-COCOMO (1).pptx
 
Putnam Resource allocation model.ppt
Putnam Resource allocation model.pptPutnam Resource allocation model.ppt
Putnam Resource allocation model.ppt
 
Effort estimation( software Engineering)
Effort estimation( software Engineering)Effort estimation( software Engineering)
Effort estimation( software Engineering)
 
cocomo.pptx
cocomo.pptxcocomo.pptx
cocomo.pptx
 
PMansgement-costmanagementforproject.pptx
PMansgement-costmanagementforproject.pptxPMansgement-costmanagementforproject.pptx
PMansgement-costmanagementforproject.pptx
 
COCOMO (Software Engineering)
COCOMO (Software Engineering)COCOMO (Software Engineering)
COCOMO (Software Engineering)
 
cocomo-220726173706-141e0dsdsd8f0 (1).pdf
cocomo-220726173706-141e0dsdsd8f0 (1).pdfcocomo-220726173706-141e0dsdsd8f0 (1).pdf
cocomo-220726173706-141e0dsdsd8f0 (1).pdf
 
Software engineering 10 software cost estimation cocomo
Software engineering 10 software cost estimation cocomoSoftware engineering 10 software cost estimation cocomo
Software engineering 10 software cost estimation cocomo
 
Cocomo model
Cocomo modelCocomo model
Cocomo model
 
Cocomomodel
CocomomodelCocomomodel
Cocomomodel
 
Se 381 - lec 25 - 32 - 12 may29 - program size and cost estimation models
Se 381 - lec 25 - 32 - 12 may29 - program size and cost estimation modelsSe 381 - lec 25 - 32 - 12 may29 - program size and cost estimation models
Se 381 - lec 25 - 32 - 12 may29 - program size and cost estimation models
 
COCOMO methods for software size estimation
COCOMO methods for software size estimationCOCOMO methods for software size estimation
COCOMO methods for software size estimation
 
COCOMO 1 Model ppt AR-1.pdf
COCOMO 1 Model  ppt AR-1.pdfCOCOMO 1 Model  ppt AR-1.pdf
COCOMO 1 Model ppt AR-1.pdf
 
COCOMO Model.pptx
COCOMO Model.pptxCOCOMO Model.pptx
COCOMO Model.pptx
 
software project management
software project managementsoftware project management
software project management
 
LECT9.ppt
LECT9.pptLECT9.ppt
LECT9.ppt
 
COCOMO FP COST ESTIMATION TECHNIQUES:NUMERIC
COCOMO FP COST ESTIMATION TECHNIQUES:NUMERICCOCOMO FP COST ESTIMATION TECHNIQUES:NUMERIC
COCOMO FP COST ESTIMATION TECHNIQUES:NUMERIC
 
COCOMO FP COST ESTIMATION TECHNIQUES:NUMERIC
COCOMO FP COST ESTIMATION TECHNIQUES:NUMERICCOCOMO FP COST ESTIMATION TECHNIQUES:NUMERIC
COCOMO FP COST ESTIMATION TECHNIQUES:NUMERIC
 
SOFTWARE ESTIMATION COCOMO AND FP CALCULATION
SOFTWARE ESTIMATION COCOMO AND FP CALCULATIONSOFTWARE ESTIMATION COCOMO AND FP CALCULATION
SOFTWARE ESTIMATION COCOMO AND FP CALCULATION
 

More from Shruti Kunwar

ITFT - Spiral model
ITFT -    Spiral modelITFT -    Spiral model
ITFT - Spiral model
Shruti Kunwar
 
ITFT - Software
ITFT -  SoftwareITFT -  Software
ITFT - Software
Shruti Kunwar
 
ITFT - Software prototyping
ITFT -  Software prototypingITFT -  Software prototyping
ITFT - Software prototyping
Shruti Kunwar
 
ITFT - Software development life cycle
ITFT  -   Software development life cycleITFT  -   Software development life cycle
ITFT - Software development life cycle
Shruti Kunwar
 
ITFT - Project planning
ITFT  -    Project planningITFT  -    Project planning
ITFT - Project planning
Shruti Kunwar
 
ITFT - Innovation
ITFT -     InnovationITFT -     Innovation
ITFT - Innovation
Shruti Kunwar
 
ITFT - Henderson clark model
ITFT  -  Henderson clark modelITFT  -  Henderson clark model
ITFT - Henderson clark model
Shruti Kunwar
 
ITFT - Fourth generation techniques
ITFT  -  Fourth generation techniquesITFT  -  Fourth generation techniques
ITFT - Fourth generation techniques
Shruti Kunwar
 
ITFT - Design
ITFT -   DesignITFT -   Design
ITFT - Design
Shruti Kunwar
 

More from Shruti Kunwar (9)

ITFT - Spiral model
ITFT -    Spiral modelITFT -    Spiral model
ITFT - Spiral model
 
ITFT - Software
ITFT -  SoftwareITFT -  Software
ITFT - Software
 
ITFT - Software prototyping
ITFT -  Software prototypingITFT -  Software prototyping
ITFT - Software prototyping
 
ITFT - Software development life cycle
ITFT  -   Software development life cycleITFT  -   Software development life cycle
ITFT - Software development life cycle
 
ITFT - Project planning
ITFT  -    Project planningITFT  -    Project planning
ITFT - Project planning
 
ITFT - Innovation
ITFT -     InnovationITFT -     Innovation
ITFT - Innovation
 
ITFT - Henderson clark model
ITFT  -  Henderson clark modelITFT  -  Henderson clark model
ITFT - Henderson clark model
 
ITFT - Fourth generation techniques
ITFT  -  Fourth generation techniquesITFT  -  Fourth generation techniques
ITFT - Fourth generation techniques
 
ITFT - Design
ITFT -   DesignITFT -   Design
ITFT - Design
 

Recently uploaded

2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...
Sandy Millin
 
Adversarial Attention Modeling for Multi-dimensional Emotion Regression.pdf
Adversarial Attention Modeling for Multi-dimensional Emotion Regression.pdfAdversarial Attention Modeling for Multi-dimensional Emotion Regression.pdf
Adversarial Attention Modeling for Multi-dimensional Emotion Regression.pdf
Po-Chuan Chen
 
A Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in EducationA Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in Education
Peter Windle
 
How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...
Jisc
 
"Protectable subject matters, Protection in biotechnology, Protection of othe...
"Protectable subject matters, Protection in biotechnology, Protection of othe..."Protectable subject matters, Protection in biotechnology, Protection of othe...
"Protectable subject matters, Protection in biotechnology, Protection of othe...
SACHIN R KONDAGURI
 
CACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdfCACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdf
camakaiclarkmusic
 
The Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdfThe Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdf
kaushalkr1407
 
Additional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdfAdditional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdf
joachimlavalley1
 
How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17
Celine George
 
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
Levi Shapiro
 
The Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official PublicationThe Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official Publication
Delapenabediema
 
Acetabularia Information For Class 9 .docx
Acetabularia Information For Class 9  .docxAcetabularia Information For Class 9  .docx
Acetabularia Information For Class 9 .docx
vaibhavrinwa19
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
siemaillard
 
Operation Blue Star - Saka Neela Tara
Operation Blue Star   -  Saka Neela TaraOperation Blue Star   -  Saka Neela Tara
Operation Blue Star - Saka Neela Tara
Balvir Singh
 
Home assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdfHome assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdf
Tamralipta Mahavidyalaya
 
The geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideasThe geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideas
GeoBlogs
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
Celine George
 
Introduction to AI for Nonprofits with Tapp Network
Introduction to AI for Nonprofits with Tapp NetworkIntroduction to AI for Nonprofits with Tapp Network
Introduction to AI for Nonprofits with Tapp Network
TechSoup
 
Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.
Ashokrao Mane college of Pharmacy Peth-Vadgaon
 
Honest Reviews of Tim Han LMA Course Program.pptx
Honest Reviews of Tim Han LMA Course Program.pptxHonest Reviews of Tim Han LMA Course Program.pptx
Honest Reviews of Tim Han LMA Course Program.pptx
timhan337
 

Recently uploaded (20)

2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...
 
Adversarial Attention Modeling for Multi-dimensional Emotion Regression.pdf
Adversarial Attention Modeling for Multi-dimensional Emotion Regression.pdfAdversarial Attention Modeling for Multi-dimensional Emotion Regression.pdf
Adversarial Attention Modeling for Multi-dimensional Emotion Regression.pdf
 
A Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in EducationA Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in Education
 
How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...
 
"Protectable subject matters, Protection in biotechnology, Protection of othe...
"Protectable subject matters, Protection in biotechnology, Protection of othe..."Protectable subject matters, Protection in biotechnology, Protection of othe...
"Protectable subject matters, Protection in biotechnology, Protection of othe...
 
CACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdfCACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdf
 
The Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdfThe Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdf
 
Additional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdfAdditional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdf
 
How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17
 
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
 
The Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official PublicationThe Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official Publication
 
Acetabularia Information For Class 9 .docx
Acetabularia Information For Class 9  .docxAcetabularia Information For Class 9  .docx
Acetabularia Information For Class 9 .docx
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
 
Operation Blue Star - Saka Neela Tara
Operation Blue Star   -  Saka Neela TaraOperation Blue Star   -  Saka Neela Tara
Operation Blue Star - Saka Neela Tara
 
Home assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdfHome assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdf
 
The geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideasThe geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideas
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
 
Introduction to AI for Nonprofits with Tapp Network
Introduction to AI for Nonprofits with Tapp NetworkIntroduction to AI for Nonprofits with Tapp Network
Introduction to AI for Nonprofits with Tapp Network
 
Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.
 
Honest Reviews of Tim Han LMA Course Program.pptx
Honest Reviews of Tim Han LMA Course Program.pptxHonest Reviews of Tim Han LMA Course Program.pptx
Honest Reviews of Tim Han LMA Course Program.pptx
 

ITFT - Cocomo model

  • 2. organic, semidetached, and embedded systems Boehm’s [1981] definition of organic, semidetached, and embedded systems are elaborated below • Organic: A development project can be considered of organic type, if the project deals with developing a well understood application program, the size of the development team is reasonably small, and the team members are experienced in developing similar types of projects.
  • 3. Semidetached • A development project can be considered of semidetached type, if the development consists of a mixture of experienced and inexperienced staff. • Team members may have limited experience on related systems but may be unfamiliar with some aspects of the system being developed.
  • 4. Embedded • A development project is considered to be of embedded type, if the software being developed is strongly coupled to complex hardware, or if the stringent regulations on the operational procedures exist
  • 5. COCOMO • COCOMO (Constructive Cost Estimation Model) was proposed by Boehm [1981]. According to Boehm, software cost estimation should be done through three stages: Basic COCOMO, Intermediate COCOMO, and Complete COCOMO.
  • 6. Basic COCOMO Model • The basic COCOMO model gives an approximate estimate of the project parameters. The basic COCOMO estimation model is given by the following expressions: • Effort = a1 х (KLOC)a2 PM • Tdev = b1 x (Effort)b2 Months
  • 7. Continued.. Where • KLOC is the estimated size of the software product expressed in Kilo Lines of Code, • a1, a2, b1, b2 are constants for each category of software products, • Tdev is the estimated time to develop the software, expressed in months, • Effort is the total effort required to develop the software product, expressed in person months (PMs).
  • 8. Continued.. • The effort estimation is expressed in units of person-months (PM). It is the area under the person-month plot (as shown in fig.). • It should be carefully noted that an effort of 100 PM does not imply that 100 persons should work for 1 month nor does it imply that 1 person should be employed for 100 months, but it denotes the area under the person-month curve.
  • 10. Estimation of development effort • For the three classes of software products, the formulas for estimating the effort based on the code size are shown below: • Organic : Effort = 2.4(KLOC)1.05 PM • Semi-detached : Effort = 3.0(KLOC)1.12 PM • Embedded : Effort = 3.6(KLOC)1.20 PM
  • 11. Estimation of development time • For the three classes of software products, the formulas for estimating the development time based on the effort are given below: • Organic : Tdev = 2.5(Effort)0.38 Months • Semi-detached : Tdev = 2.5(Effort)0.35 Months • Embedded : Tdev = 2.5(Effort)0.32 Months
  • 12. Example • Assume that the size of an organic type software product has been estimated to be 32,000 lines of source code. Assume that the average salary of software engineers be Rs. 15,000/- per month. Determine the effort required to develop the software product and the nominal development time.
  • 13. Solution • From the basic COCOMO estimation formula for organic software: • Effort = 2.4 х (32)1.05 = 91 PM • Nominal development time = 2.5 х (91)0.38 = 14 months • Cost required to develop the product = 14 х 15,000 • = Rs. 210,000/-