SlideShare a Scribd company logo
1 of 13
PM Cell Performance Report Jan-2022
Presented by :
PM Team - Nimbahera
Safety
Safety data Jan '2023
Safety Training conducted / Peoples attended 9/74
TBT Conducted / Peoples attended 27/293
Hazard Identification / Hazard Closed 29
Near miss / Near miss closed 0
CBM- Condition base monitoring activities
• Total 284 equipment covered for
vibration analysis in Jan-23 month.
Vibration
• CM6 outlet blower Z6U01B1 balancing done.
Balancing
• Raw mill 2 elevator head shaft UT.
NDT
• Z2J01 Chain elongation - 0.5% ( Acceptable )
• Z1J01 Chain elongation-0.2% ( Acceptable )
• 514BE620 Chain elongation-0.2 % ( Acceptable )
• 526BE170 Chain elongation – 0.4%( Acceptable )
Elongation
• CHRP group conveyor belts hardness
measurement.
• Elevator - 526BE470 ( 81 Shore A ) , 526BE600 (
78 Shore A ) , 534BE220 ( 85 Shore A ) , 535BE
240 ( 81 Shore A ).
Belt hardness
• 117 equipment scanned. Abnormality found in
P3J01 and 463HY110M2.
Thermography
• Cement Mill 4 and 5 internal inspection and liner
wear measurement.
• CPP Boiler tube thickness measurement.
Wear
• Blower Z6U01B1 vibration reduced after
balancing.
• 333.FN.573 fan vibration reduced after coating
cleaned.
• 526.FN.717 vibration reduced after alignment
work.
CBM corrective
action
Vibration Analysis Summary
Section
Total no
equipment
Status
Satisfactory
Just
Satisfactory
Critical
Crusher 34 32 02 0
Raw mill 37 37 0 0
Kiln 79 70 09 0
Cement mill 106 93 13 0
Packing plant 28 25 03 0
Total 284 257 27 0
CPP Boiler tube thickness
measurement
Mines equipment vibration
measurement
Critical observation during WBI/Stop inspection
A3LO4 Belt joint open from
edge
333RF662 One coupling bolt
loose & coupling gap high
473BF150 suction line wear
out
Kiln – 3 shell temp. diff found
high at 47 m from outlet (150)
D1P30_Auto grease feeder
found empty.
U4J08G1_Take up pulley
bearing cover found missing
Z2M01_CM 2 inlet bearing oil
leakage.
526.RF516_Rotary air lock
coupling bolt found missing.
Lubrication activities
0.00
0.10
0.20
0.30
0.40
0.50
0.60
0.70
0.05 0.03 0.02
0.08
0.04 0.02 0.02
0.05 0.03
0.08
0.41
0.64
OCR
OCR
0.00
1.00
2.00
3.00
4.00
5.00
6.00
7.00 6.04
2.89
1.45
2.99
1.94
1.17 1.18
3.57
1.61
3.04
2.55
4.26
Cost Per Ton
Oil Qty (Ltr) Oil Cost (INR) Oil Qty (Ltr) Oil Cost (INR) Oil Qty (Ltr) Oil Cost (INR)
1026 ₹ 5,07,169.00 289.5 ₹ 43,977.11 2394 ₹ 3,54,991.30
Oil Consumption
LUBRICATION CONSUMPTION STATUS January -2023
LEAKAGES TOPUP REPLACEMENT
Total oil cost ( in lacs) ₹ 9.06
Major Leakage/top up area-
1. RM-2counter shaft bearing 236Ltr ( Leakage) - Servo meshXP-320
2. CHRP roller bearing lubrication tank- 450Ltr ( Bearing seal leakage) - Mobil SHC 636
3. CM2inlet trunion bearing 230Ltr (Leakage) - Servo system 320
MAJOR REPLACEMENT- JAN-23
1. CHRP hydraulic slide gate- 320 Ltr
2. CM-2 MD GB RHS side- 950 Ltr
3. Kiln-2 MD gearbox- 220 Ltr
4. RM-2 MD GB LHS side- 840 Ltr
Kaizen
Before Kaizen (Photo / Sketch)
After Kaizen (Photo / Sketch)
Kaizen Activities: We have provided
½” Ball Valve in-place of drain plug
making ease in draining excess old
grease in coal VRM FK pump
Before Kaizen (Photo / Sketch)
After Kaizen (Photo / Sketch)
Kaizen Activities: Now we have provided a RCC
Floor with Level Increase up to 200mm from
ground level to place Empty & Scrap Oil Drum
in Order. This has been now a designated place
for storing oil/grease drum
Before Kaizen (Photo / Sketch)
After Kaizen (Photo / Sketch)
Kaizen Activities: We have provided civil
Amirah with wooden cover. Now we have
designated Amirah space for Lube Cans &
Fitting Spares in Proper Order. Now overall lube
room 5S is improved.
Work Order Monthly status -Jan’2023
Plant & Dept. Order Total Order Completed Order Open Cost (Lakh) Order Closer %
@plant level Total 1055 961 94 424.39 91%
1001-Nimbahera 988 900 88 408.06 91%
Civil 8 8 4.00 100%
Electrical 285 258 27 28.75 91%
Enviornment 1 1 0.92 0%
Instrument 168 159 9 8.24 95%
Mechanical 266 238 28 173.83 89%
Mechanical-PP 48 42 6 5.18 88%
Mines 68 58 10 58.93 85%
PM Cell 71 71 14.40 100%
Process 50 46 4 108.98 92%
Process-PP 5 3 2 1.83 60%
QC Lab 10 10 1.34 100%
Safety 1 1 0.05 0%
Security 7 7 1.62 100%
1003-WHR & CPP 42 39 3 6.73 93%
Electrical 14 14 0.38 100%
Instrument 14 14 0.00 100%
Mechanical 14 11 3 6.36 79%
1044-Maliyakhera 25 22 3 9.59 88%
Electrical 8 7 1 2.21 88%
Instrument 3 3 0.39 100%
Mechanical 14 12 2 6.99 86%
May be most of jobs has been already
completed, if so make a practice of
closing Notification/orders after
completion of work by usages of
Mworkorder Mobile App for real time
data to be recorded in system.
Notification Monthly Status- Jan’2023
Plant & Dept.
Notification
Total
Notification
Completed
Notification
Open
Notification
Closer %
@plant Level Total 1205 1067 138 89%
1001-Nimbahera 1104 979 125 89%
Civil 26 26 100%
Electrical 181 156 25 86%
Ind.Rel 1 1 0%
Instrument 342 342 100%
Mechanical 290 219 71 76%
Mechanical-PP 64 50 14 78%
Mines 68 58 10 85%
PM Cell 68 67 1 99%
Process 54 53 1 98%
Process-PP 2 2 0%
QC Lab 1 1 100%
Security 7 7 100%
1003-WHR & CPP 50 41 9 82%
Electrical 15 15 100%
Instrument 14 14 100%
Mechanical 21 12 9 57%
1044-Maliyakhera 51 47 4 92%
Electrical 31 30 1 97%
Instrument 6 6 100%
Mechanical 13 10 3 77%
PM Cell 1 1 100%
PMR Schedule Status - Feb’2023
@plant level Feb’2023 PMR’s scheduled 99%, remaining PMR will be schedule after closer of open PMR
Order/Notification
PMR Scheduled
Plant & Dept. PMR Total Notification Order Not Scheduled PMR Scheduled %
@plant Level PMR Total 760 283 470 7 99%
1001-Nimbahera 725 254 464 7 99%
Electrical 125 39 86 100%
Ind.Rel 1 1 100%
Instrument 261 125 130 6 98%
Mechanical 162 10 151 1 99%
Mechanical-PP 21 14 7 100%
PM Cell 106 50 56 100%
Process 17 2 15 100%
QC Lab 19 19 100%
Security 13 13 100%
1003- WHR & CPP 5 5 100%
Electrical 2 2 100%
Mechanical 3 3 100%
1044-Maliyakhera 30 24 6 100%
Electrical 17 13 4 100%
Instrument 6 4 2 100%
Mechanical 6 6 100%
PM Cell 1 1 100%
RCA tracker (FY22-23) summary –Jan’22
@plant level Section wise RCA tracker action point closer Status @plant level Dept. wise RCA action point closer Status
Section
Total RCA
conduct
RCA action
Generate
Action
Completed
Action Not
completed
WIP
CM-1 4 6 5 1
CM-2 8 14 13 1
CM-3 7 22 22
CM-5 HRP 24 56 53 2 1
KILN3ILC 43 115 109 4 2
Packer 1 7 7
RM3HRP 8 22 22
KILN2 2 4 4
‘@ plant
level Total
97 246 235 7 4
Dept. Total Action Completed Not completed WIP
AFR 1 1
Elec 23 23
Inst 74 68 4 2
Mech 111 106 3 2
PM Cell 5 5
Proc 15 15
process 12 12
Quality 5 5
‘@plant level
Total
246 235 7 4
HRP Mills & Kiln3 Performance – Jan’23
109 111
64 53
259
158 161
247
653 664
703
633
518
630 644
741
6 6
11
12
2
4 4
3
0
2
4
6
8
10
12
14
0
100
200
300
400
500
600
700
800
Dec-22 Jan-23 Dec-22 Jan-23 Dec-22 Jan-23 Dec-22 Jan-23
CM-3 CM-3 CM-4/HRP CM-4/HRP RM3HRP RM3HRP KILN3ILC KILN3ILC
MTBF Running Hrs. Freq.
Major reason for low equipment running/MTBF:
Cement Mill-3: Inclined belt overload due to Gypsum flushing (2.40hrs) & Gypsum WF Jack bolt bend (2.40Hr)
CHRP: BE600 bucket elevator trip on BSS due to drum Crowning lower side (5:05Hrs), CM4 BH conveyor trip on overload by
discharge pipe jammed (3:55Hrs)
Kiln-3: Feeder bus fault tripping (freq-2 & 25Minutes), PH Cyclone spreader CN110 trip on Lubrication system interloack (Freq-1 &
15Minutes)
Good Initiatives
Good Initiatives:
1. 5’S program initiated @ TLM room & PM cell Office.
2. Safety WBI start for identification of unsafe condition & circulate to concerned.
3. WBI performed 100% through Mobile App. RDF form.
4. 3Nos. Kaizen done related to Lubrication activities
Way forward
Way forward:
1. @plant level Mobile app. usages & adoptability in improving trend & Weekly department
level adoption w.r.t User ID to be circulated.
2. Mworkorder Reward/ recognition to best Users will be given in month of Feb’23.
3. 100% calibration through RDF form
4. RCA through SAP recording for Nimbahera & Circulate process with all JKC units.
5. PM10-Opertunity order Spares, Duration & manpower make mandatory, report will be
generated CCRO on basis of breakdown duration.
6. HRP Online monitoring system vendor discussion ongoing.
7. Lubricant Oil analysis cloud base recording & for fast analysis report results to take prompt
action at plant level.-Mobil.

More Related Content

Similar to PM Performamnec report- Jan'23.pptx

GWOS_Week_of_03-23-2015
GWOS_Week_of_03-23-2015GWOS_Week_of_03-23-2015
GWOS_Week_of_03-23-2015
William Irving
 
ANNUAL REPORT 2015
ANNUAL REPORT 2015ANNUAL REPORT 2015
ANNUAL REPORT 2015
Eko Untung
 
Review Week_12_Customer_PulauPanggung (PT.BAS).pptx
Review Week_12_Customer_PulauPanggung (PT.BAS).pptxReview Week_12_Customer_PulauPanggung (PT.BAS).pptx
Review Week_12_Customer_PulauPanggung (PT.BAS).pptx
noelmanroe1
 
POWER POINT PRESENTATION-MSC PROJECT
POWER POINT PRESENTATION-MSC PROJECTPOWER POINT PRESENTATION-MSC PROJECT
POWER POINT PRESENTATION-MSC PROJECT
Wasiu Oseni
 
WO5A CS1A Construction Progress Status Report Week #25
WO5A CS1A Construction Progress Status Report Week #25WO5A CS1A Construction Progress Status Report Week #25
WO5A CS1A Construction Progress Status Report Week #25
Tofik Nazirov, B.Sc., PhD
 
Operation - OR for JAN 23.pptx
Operation - OR for JAN 23.pptxOperation - OR for JAN 23.pptx
Operation - OR for JAN 23.pptx
PowerMurugan
 
Report Antenna Refinement Site TNR054_TMBT_MELAYU-Rev1.2_rev2.pptx
Report Antenna Refinement Site  TNR054_TMBT_MELAYU-Rev1.2_rev2.pptxReport Antenna Refinement Site  TNR054_TMBT_MELAYU-Rev1.2_rev2.pptx
Report Antenna Refinement Site TNR054_TMBT_MELAYU-Rev1.2_rev2.pptx
monangpardede1
 

Similar to PM Performamnec report- Jan'23.pptx (20)

Energy conservation Activites of thermal power plant
Energy conservation Activites of thermal power plantEnergy conservation Activites of thermal power plant
Energy conservation Activites of thermal power plant
 
Cash Flow Portfolio
Cash Flow PortfolioCash Flow Portfolio
Cash Flow Portfolio
 
Dmi performance analysis Flettner rotor updated_t_hiii_nk_220112
Dmi performance analysis Flettner rotor updated_t_hiii_nk_220112Dmi performance analysis Flettner rotor updated_t_hiii_nk_220112
Dmi performance analysis Flettner rotor updated_t_hiii_nk_220112
 
GWOS_Week_of_03-23-2015
GWOS_Week_of_03-23-2015GWOS_Week_of_03-23-2015
GWOS_Week_of_03-23-2015
 
ANNUAL REPORT 2015
ANNUAL REPORT 2015ANNUAL REPORT 2015
ANNUAL REPORT 2015
 
coal handling plant
coal handling plantcoal handling plant
coal handling plant
 
23. CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)
23.  CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)23.  CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)
23. CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)
 
236D3 CATERPILLAR SKID STEER LOADER SERVICE REPAIR MANUAL F9C
236D3 CATERPILLAR SKID STEER LOADER SERVICE REPAIR MANUAL F9C236D3 CATERPILLAR SKID STEER LOADER SERVICE REPAIR MANUAL F9C
236D3 CATERPILLAR SKID STEER LOADER SERVICE REPAIR MANUAL F9C
 
Performance Evaluation of 830kW Wind Turbine and an Analysis of Various Param...
Performance Evaluation of 830kW Wind Turbine and an Analysis of Various Param...Performance Evaluation of 830kW Wind Turbine and an Analysis of Various Param...
Performance Evaluation of 830kW Wind Turbine and an Analysis of Various Param...
 
Review Week 1 Oktober 2022.pptx
Review Week 1 Oktober 2022.pptxReview Week 1 Oktober 2022.pptx
Review Week 1 Oktober 2022.pptx
 
Review Week_12_Customer_PulauPanggung (PT.BAS).pptx
Review Week_12_Customer_PulauPanggung (PT.BAS).pptxReview Week_12_Customer_PulauPanggung (PT.BAS).pptx
Review Week_12_Customer_PulauPanggung (PT.BAS).pptx
 
POWER POINT PRESENTATION-MSC PROJECT
POWER POINT PRESENTATION-MSC PROJECTPOWER POINT PRESENTATION-MSC PROJECT
POWER POINT PRESENTATION-MSC PROJECT
 
Analysing shovel dumper productivity for coal mine
Analysing shovel dumper productivity for coal mineAnalysing shovel dumper productivity for coal mine
Analysing shovel dumper productivity for coal mine
 
WO5A CS1A Construction Progress Status Report Week #25
WO5A CS1A Construction Progress Status Report Week #25WO5A CS1A Construction Progress Status Report Week #25
WO5A CS1A Construction Progress Status Report Week #25
 
Operation - OR for JAN 23.pptx
Operation - OR for JAN 23.pptxOperation - OR for JAN 23.pptx
Operation - OR for JAN 23.pptx
 
Report Antenna Refinement Site TNR054_TMBT_MELAYU-Rev1.2_rev2.pptx
Report Antenna Refinement Site  TNR054_TMBT_MELAYU-Rev1.2_rev2.pptxReport Antenna Refinement Site  TNR054_TMBT_MELAYU-Rev1.2_rev2.pptx
Report Antenna Refinement Site TNR054_TMBT_MELAYU-Rev1.2_rev2.pptx
 
2001 Infiniti I30 Service Repair Manual.pdf
2001 Infiniti I30 Service Repair Manual.pdf2001 Infiniti I30 Service Repair Manual.pdf
2001 Infiniti I30 Service Repair Manual.pdf
 
2001 Infiniti I30 Service Repair Manual.pdf
2001 Infiniti I30 Service Repair Manual.pdf2001 Infiniti I30 Service Repair Manual.pdf
2001 Infiniti I30 Service Repair Manual.pdf
 
2001 Infiniti I30 Service Repair Manual.pdf
2001 Infiniti I30 Service Repair Manual.pdf2001 Infiniti I30 Service Repair Manual.pdf
2001 Infiniti I30 Service Repair Manual.pdf
 
2001 Infiniti I30 Service Repair Manual.pdf
2001 Infiniti I30 Service Repair Manual.pdf2001 Infiniti I30 Service Repair Manual.pdf
2001 Infiniti I30 Service Repair Manual.pdf
 

Recently uploaded

FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
dollysharma2066
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Dr.Costas Sachpazis
 

Recently uploaded (20)

FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
NFPA 5000 2024 standard .
NFPA 5000 2024 standard                                  .NFPA 5000 2024 standard                                  .
NFPA 5000 2024 standard .
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdf
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
Vivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design SpainVivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design Spain
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 

PM Performamnec report- Jan'23.pptx

  • 1. PM Cell Performance Report Jan-2022 Presented by : PM Team - Nimbahera
  • 2. Safety Safety data Jan '2023 Safety Training conducted / Peoples attended 9/74 TBT Conducted / Peoples attended 27/293 Hazard Identification / Hazard Closed 29 Near miss / Near miss closed 0
  • 3. CBM- Condition base monitoring activities • Total 284 equipment covered for vibration analysis in Jan-23 month. Vibration • CM6 outlet blower Z6U01B1 balancing done. Balancing • Raw mill 2 elevator head shaft UT. NDT • Z2J01 Chain elongation - 0.5% ( Acceptable ) • Z1J01 Chain elongation-0.2% ( Acceptable ) • 514BE620 Chain elongation-0.2 % ( Acceptable ) • 526BE170 Chain elongation – 0.4%( Acceptable ) Elongation • CHRP group conveyor belts hardness measurement. • Elevator - 526BE470 ( 81 Shore A ) , 526BE600 ( 78 Shore A ) , 534BE220 ( 85 Shore A ) , 535BE 240 ( 81 Shore A ). Belt hardness • 117 equipment scanned. Abnormality found in P3J01 and 463HY110M2. Thermography • Cement Mill 4 and 5 internal inspection and liner wear measurement. • CPP Boiler tube thickness measurement. Wear • Blower Z6U01B1 vibration reduced after balancing. • 333.FN.573 fan vibration reduced after coating cleaned. • 526.FN.717 vibration reduced after alignment work. CBM corrective action Vibration Analysis Summary Section Total no equipment Status Satisfactory Just Satisfactory Critical Crusher 34 32 02 0 Raw mill 37 37 0 0 Kiln 79 70 09 0 Cement mill 106 93 13 0 Packing plant 28 25 03 0 Total 284 257 27 0 CPP Boiler tube thickness measurement Mines equipment vibration measurement
  • 4. Critical observation during WBI/Stop inspection A3LO4 Belt joint open from edge 333RF662 One coupling bolt loose & coupling gap high 473BF150 suction line wear out Kiln – 3 shell temp. diff found high at 47 m from outlet (150) D1P30_Auto grease feeder found empty. U4J08G1_Take up pulley bearing cover found missing Z2M01_CM 2 inlet bearing oil leakage. 526.RF516_Rotary air lock coupling bolt found missing.
  • 5. Lubrication activities 0.00 0.10 0.20 0.30 0.40 0.50 0.60 0.70 0.05 0.03 0.02 0.08 0.04 0.02 0.02 0.05 0.03 0.08 0.41 0.64 OCR OCR 0.00 1.00 2.00 3.00 4.00 5.00 6.00 7.00 6.04 2.89 1.45 2.99 1.94 1.17 1.18 3.57 1.61 3.04 2.55 4.26 Cost Per Ton Oil Qty (Ltr) Oil Cost (INR) Oil Qty (Ltr) Oil Cost (INR) Oil Qty (Ltr) Oil Cost (INR) 1026 ₹ 5,07,169.00 289.5 ₹ 43,977.11 2394 ₹ 3,54,991.30 Oil Consumption LUBRICATION CONSUMPTION STATUS January -2023 LEAKAGES TOPUP REPLACEMENT Total oil cost ( in lacs) ₹ 9.06 Major Leakage/top up area- 1. RM-2counter shaft bearing 236Ltr ( Leakage) - Servo meshXP-320 2. CHRP roller bearing lubrication tank- 450Ltr ( Bearing seal leakage) - Mobil SHC 636 3. CM2inlet trunion bearing 230Ltr (Leakage) - Servo system 320 MAJOR REPLACEMENT- JAN-23 1. CHRP hydraulic slide gate- 320 Ltr 2. CM-2 MD GB RHS side- 950 Ltr 3. Kiln-2 MD gearbox- 220 Ltr 4. RM-2 MD GB LHS side- 840 Ltr
  • 6. Kaizen Before Kaizen (Photo / Sketch) After Kaizen (Photo / Sketch) Kaizen Activities: We have provided ½” Ball Valve in-place of drain plug making ease in draining excess old grease in coal VRM FK pump Before Kaizen (Photo / Sketch) After Kaizen (Photo / Sketch) Kaizen Activities: Now we have provided a RCC Floor with Level Increase up to 200mm from ground level to place Empty & Scrap Oil Drum in Order. This has been now a designated place for storing oil/grease drum Before Kaizen (Photo / Sketch) After Kaizen (Photo / Sketch) Kaizen Activities: We have provided civil Amirah with wooden cover. Now we have designated Amirah space for Lube Cans & Fitting Spares in Proper Order. Now overall lube room 5S is improved.
  • 7. Work Order Monthly status -Jan’2023 Plant & Dept. Order Total Order Completed Order Open Cost (Lakh) Order Closer % @plant level Total 1055 961 94 424.39 91% 1001-Nimbahera 988 900 88 408.06 91% Civil 8 8 4.00 100% Electrical 285 258 27 28.75 91% Enviornment 1 1 0.92 0% Instrument 168 159 9 8.24 95% Mechanical 266 238 28 173.83 89% Mechanical-PP 48 42 6 5.18 88% Mines 68 58 10 58.93 85% PM Cell 71 71 14.40 100% Process 50 46 4 108.98 92% Process-PP 5 3 2 1.83 60% QC Lab 10 10 1.34 100% Safety 1 1 0.05 0% Security 7 7 1.62 100% 1003-WHR & CPP 42 39 3 6.73 93% Electrical 14 14 0.38 100% Instrument 14 14 0.00 100% Mechanical 14 11 3 6.36 79% 1044-Maliyakhera 25 22 3 9.59 88% Electrical 8 7 1 2.21 88% Instrument 3 3 0.39 100% Mechanical 14 12 2 6.99 86% May be most of jobs has been already completed, if so make a practice of closing Notification/orders after completion of work by usages of Mworkorder Mobile App for real time data to be recorded in system.
  • 8. Notification Monthly Status- Jan’2023 Plant & Dept. Notification Total Notification Completed Notification Open Notification Closer % @plant Level Total 1205 1067 138 89% 1001-Nimbahera 1104 979 125 89% Civil 26 26 100% Electrical 181 156 25 86% Ind.Rel 1 1 0% Instrument 342 342 100% Mechanical 290 219 71 76% Mechanical-PP 64 50 14 78% Mines 68 58 10 85% PM Cell 68 67 1 99% Process 54 53 1 98% Process-PP 2 2 0% QC Lab 1 1 100% Security 7 7 100% 1003-WHR & CPP 50 41 9 82% Electrical 15 15 100% Instrument 14 14 100% Mechanical 21 12 9 57% 1044-Maliyakhera 51 47 4 92% Electrical 31 30 1 97% Instrument 6 6 100% Mechanical 13 10 3 77% PM Cell 1 1 100%
  • 9. PMR Schedule Status - Feb’2023 @plant level Feb’2023 PMR’s scheduled 99%, remaining PMR will be schedule after closer of open PMR Order/Notification PMR Scheduled Plant & Dept. PMR Total Notification Order Not Scheduled PMR Scheduled % @plant Level PMR Total 760 283 470 7 99% 1001-Nimbahera 725 254 464 7 99% Electrical 125 39 86 100% Ind.Rel 1 1 100% Instrument 261 125 130 6 98% Mechanical 162 10 151 1 99% Mechanical-PP 21 14 7 100% PM Cell 106 50 56 100% Process 17 2 15 100% QC Lab 19 19 100% Security 13 13 100% 1003- WHR & CPP 5 5 100% Electrical 2 2 100% Mechanical 3 3 100% 1044-Maliyakhera 30 24 6 100% Electrical 17 13 4 100% Instrument 6 4 2 100% Mechanical 6 6 100% PM Cell 1 1 100%
  • 10. RCA tracker (FY22-23) summary –Jan’22 @plant level Section wise RCA tracker action point closer Status @plant level Dept. wise RCA action point closer Status Section Total RCA conduct RCA action Generate Action Completed Action Not completed WIP CM-1 4 6 5 1 CM-2 8 14 13 1 CM-3 7 22 22 CM-5 HRP 24 56 53 2 1 KILN3ILC 43 115 109 4 2 Packer 1 7 7 RM3HRP 8 22 22 KILN2 2 4 4 ‘@ plant level Total 97 246 235 7 4 Dept. Total Action Completed Not completed WIP AFR 1 1 Elec 23 23 Inst 74 68 4 2 Mech 111 106 3 2 PM Cell 5 5 Proc 15 15 process 12 12 Quality 5 5 ‘@plant level Total 246 235 7 4
  • 11. HRP Mills & Kiln3 Performance – Jan’23 109 111 64 53 259 158 161 247 653 664 703 633 518 630 644 741 6 6 11 12 2 4 4 3 0 2 4 6 8 10 12 14 0 100 200 300 400 500 600 700 800 Dec-22 Jan-23 Dec-22 Jan-23 Dec-22 Jan-23 Dec-22 Jan-23 CM-3 CM-3 CM-4/HRP CM-4/HRP RM3HRP RM3HRP KILN3ILC KILN3ILC MTBF Running Hrs. Freq. Major reason for low equipment running/MTBF: Cement Mill-3: Inclined belt overload due to Gypsum flushing (2.40hrs) & Gypsum WF Jack bolt bend (2.40Hr) CHRP: BE600 bucket elevator trip on BSS due to drum Crowning lower side (5:05Hrs), CM4 BH conveyor trip on overload by discharge pipe jammed (3:55Hrs) Kiln-3: Feeder bus fault tripping (freq-2 & 25Minutes), PH Cyclone spreader CN110 trip on Lubrication system interloack (Freq-1 & 15Minutes)
  • 12. Good Initiatives Good Initiatives: 1. 5’S program initiated @ TLM room & PM cell Office. 2. Safety WBI start for identification of unsafe condition & circulate to concerned. 3. WBI performed 100% through Mobile App. RDF form. 4. 3Nos. Kaizen done related to Lubrication activities
  • 13. Way forward Way forward: 1. @plant level Mobile app. usages & adoptability in improving trend & Weekly department level adoption w.r.t User ID to be circulated. 2. Mworkorder Reward/ recognition to best Users will be given in month of Feb’23. 3. 100% calibration through RDF form 4. RCA through SAP recording for Nimbahera & Circulate process with all JKC units. 5. PM10-Opertunity order Spares, Duration & manpower make mandatory, report will be generated CCRO on basis of breakdown duration. 6. HRP Online monitoring system vendor discussion ongoing. 7. Lubricant Oil analysis cloud base recording & for fast analysis report results to take prompt action at plant level.-Mobil.