SlideShare a Scribd company logo
1 of 15
Question#1 
Explain “Construction Productivity” and highlight its importance. 
Answer 
Productivity is a term that can be defined in many ways and it is often confused with the term 
“Production” because many people think that the greater the production, the greater the 
productivity but this is not necessarily true. Productivity is concerned with the efficient and 
effective utilization of resources in producing goods and services. In business world, productivity 
measures investment in capital against profit but particularly the term Construction Productivity 
means efficiency in execution process by considering all aspects of competitiveness and 
innovation. As we know that construction productivity largely depends upon human 
performance, it can be simply calculated through the output of any aspect of production per unit 
of input. In an ideal case, perfect productivity (1.0) would be accomplished if all the engineering 
drawings would be 100 percent complete, there would be no delays of any kind, everyone would 
work safely, everything would fit perfectly the first time, the weather would be 70 degrees 
Fahrenheit, and there would be no litigation at the end of the project. 
On this basis we can say that construction productivity decline due to so many factors e.g. design 
complexity, dilution of supervision, high accident rate, jurisdictional disputes, adverse 
temperature and impractical QA/QC tolerances etc. All these factors of productivity can be 
summarize as follows, 
 Project Uniqueness 
 Technology 
 Management 
 Motivation factor 
 Hygiene factor 
Productivity usually measures in terms of 3M (Manpower, Material & Machinery). Two distinct 
and independent methodologies are used to determine productivity changes. The first approach is 
an output-based one, in which real costs per square foot for several buildings types, further 
adjusted for enhancements in quality and content, are compared over the study period. 
PT = [(1+PN) x (1+PL)] -1 
Where PT = total productivity increase, PN = quantitative productivity increase, and PL = qualitative productivity 
increase. 
The second approach, termed the input-based approach, constructs a model based upon 
observable changes in labor productivity at the task level, changes in real materials costs, and 
changes in costs of tools and equipment utilized at the jobsite. 
PL = (0.72 x PG) + (0.16 x PM) + (0.12 x PE) 
Where PL = total labor productivity increase, and PG, PM, and PE = categorical labor productivity increases for 
general, mechanical, and electrical construction respectively.
Importance of Productivity 
Productivity in construction is very important for an individual or for the whole industry 
especially from the economic point of view because construction industry accounts for 3-8% of 
the GDP in most countries. Unfortunately we are living in the world of great uncertainty 
therefore to improve or maintain the construction productivity is very challenging. 
 Higher production output, lower inflation rate and further productivity growth could be 
benefited from productivity improvement. 
 With a higher productivity, the local contractors are able to reduce the construction cost 
and therefore benefit from a higher profit. Also, the contractor can even offer a lower 
bidding price to increase his competitiveness. 
A productivity benefit model is presented by David J. Sumanth in 1980, according to which 
total productivity improvement in organizations benefits everyone consumers, employees, 
owners/stockholders, the society and the nation as a whole. 
Therefore, productivity cycle concept show us that productivity improvement must be preceded 
by measurement, evaluation, and planning. All four phases are important, not just productivity 
measurement or just productivity improvement. Hence it shows that productivity program is not 
a one-time project, but rather a continuous, on-going process.
Question#2 
Explain the process of crane selection for the construction of a multi storey building. What effect 
does it have on the overall productivity? 
Answer 
The selection process of tower crane, for any multistory building, is not an easy task because in 
order to make construction convenient and highly economic we have to consider some important 
factors. Factors affecting the selection of cranes, including: shape, number of floors, the height of 
each floor; total volume; construction progress; ground conditions and construction areas, traffic 
conditions the crane service provision of units and the requirements of economic efficiency. 
Other basic considerations are as follows, 
APPLICATION: You should know the weight of objects that will be lifting and moving, the 
height of the lift, length and width of the move and the duty cycle of the crane including how 
often and for how long it will be used. 
ENVIRONMENT: Will the crane be used indoors or outdoors? Is your environment corrosive or 
have extreme temperatures? Is it going into a sterile environment such a food manufacturing? 
FACILITIES: When determining the type of crane and how it will be installed, you must take 
into consideration the limitations of your facilities. The roof, wall or floor structure must be 
assessed to ensure it will hold the crane and its load. 
QUALITY: Your crane must meet the crane codes. Also consider the classification (C1 to C9) of 
the crane which advises its lifespan and duty cycle. 
COST: The price of the crane is only the first part of this equation. You also must add in the cost 
of installation, maintenance, and the possibility for future expansion. 
As a conclusion, to choose the most affordable tower cranes should follow these steps: 
 Based on the characteristics of the work, technology and mass construction crane to 
choose. 
 Select the correct crane working mode. 
 Select the specifications of the crane in accordance with the real working conditions. 
 Compare the economic and technical indicators to select crane satisfaction.
Effect of Crane on Overall Productivity 
The purpose behind the proper selection of crane is to improve the overall productivity of 
construction but in contrast, operating a crane is a very precise work. The person at the controls 
wields a lot of power, swinging heavy items into place while a crew on the ground assists. 
Hazards at construction sites can change quickly, putting employees who operate cranes or work 
around them at high risk for serious injuries, and even death. Electrocution, falls, moving 
machinery, excavations, and overhead loads are examples of a few common hazards that can 
plague rigging and other activities involving cranes. A Ensuring that equipment and personnel 
meet certification and other safety requirements helps employers prevent accidents and ensure 
that everyone goes home safely at the end of a long day. 
The overall productivity dictated by the efficiency of tower cranes that largely depends on their 
type, number and location. As the number of work tasks and the demand for tower cranes 
increase, planners may experience difficulties in making an appropriate decision about the 
optimum layout of tower cranes. A poor decision, however, is likely to have significant negative 
effects, which will lead to additional costs and possible delays. As a thumb rule, crane usually 
placed at a center location where it can cover the maximum construction area. Where there are 
other cranes on the same site and there is a risk of collision, a crash radio system is to be 
established and be used. This will be determined by the lifting assessment. 
Any other plant (Other cranes, Concrete Booms, Piling Rigs etc) that may be working within the 
radius of a crane, their operator must be made aware of such risks and a system must be put in 
place to control their movements (this may be via the crash radio or a permit to work system).
Question#3 
Explain the term “Work Breakdown”. Does it have any effect on the productivity of a project? 
Explain in detail. 
Answer 
In simple words, work breakdown structure (WBS) is a logical grouping tool that is used for 
better understanding by subdividing the total work scope of a project into small work packages. 
According to Project Management Body of Knowledge “A Work Breakdown Structure is a 
deliverable-oriented hierarchical decomposition of the work to be executed by the project team 
to accomplish the project objectives and create the required deliverables.” In WBS, much larger 
tasks are broken-down to manageable chunks of work. These chunks can be easily supervised 
and estimated but considerable thought and planning should be given to its development and 
implementation so that subsequent changes are minimized. 
Work Breakdown Structure (WBS) generally consist of five level hierarchy describing the entire 
effort to be accomplished by the primary organization, that number may not be appropriate for 
all situations. 
Following are a few reasons for creating a WBS in a project. 
 Accurate assignment of responsibilities to the project team. 
 Indicates the project milestones and control points. 
 Helps to estimate the cost, time, and risk. 
 Illustrate the project scope, so the stakeholders can have a better understanding of the 
same.
Effects of WBS on Construction Productivity 
Construction Productivity is heavily depends upon comprehensive planning and the quality of 
planning is judged by the quality of work breakdown structure. In this sense, Work Breakdown 
Structure (WBS) can affect the productivity up to great extent because more clearly the scope of 
the project is articulated before the actual work begins, the more likely the success of the project. 
Experienced project managers know there are many things that can go wrong in projects 
regardless of how successfully they plan and execute their work. The positive and negative 
effects of WBS over productivity can be explain separately as follow, 
Positive Side: 
The WBS provides the project manager and team with the necessary framework of tasks going 
forward to create detailed cost estimates and also to provide major input to project task 
scheduling at the most detailed and accurate level possible. By going through the WBS motions, 
the project manager and team will have a pretty good idea whether or not they’ve captured all the 
necessary tasks, based on the project requirements, that are going to need to happen to get the job 
done with improve productivity. 
The WBS forces the project manager and team members to delineate the steps required to build 
and deliver the product or service. The exercise alone encourages a dialogue that will help clarify 
ambiguities, bring out assumptions, narrow the scope of the project, and raise critical issues early 
on. 
Negative Side: 
On the other hand, developing a WBS is not easy. It can be a painstaking process. And it can 
take quite a bit of time. A large WBS (one that identifies several thousand activities) can take 
many, many hours to develop. For another, it requires effort. There is a knowledge transfer and 
exercise of brainpower. The larger the scope of the project, the larger the WBS will be. More 
people must provide input and then approve the portion they are responsible to perform. There 
must be some logical pattern to the way in which these pieces are broken off. We don’t want it to 
be like smashing a piece of glass into lots of tiny pieces that can’t be put back together again. No 
we are looking for something more like a jigsaw puzzle, where every piece can be slotted into its 
right place to make the big picture without affecting the productivity. 
Even after considering the downsides, the overall advantages still outweigh the known 
challenges. A good WBS makes planning and executing a project easier and lays the groundwork 
for the schedule, the tracking, the budgeting, and all the accountability throughout the rest of the 
engagement that finally results productivity improvement.
Question#4 
Explain the process of planning, controlling and managing skilled and unskilled labor for a 
construction site. 
Answer 
A successful project requires careful planning, proper controlling and managing efforts 
throughout for human resource because it is beneficial for both client and contractor in order to 
achieve a timely and satisfactorily outcome. Construction uses more manpower in its activities as 
compared to the other field and the main challenge is to obtain proper mix ratio of work force 
both skilled and unskilled labor. The actual problems that we always face are shortage of skilled 
labor and dynamic work force, lack of effective training and performance in the Construction 
Projects. Productivity can also be defined in terms of labor as a “relative measure of labor 
efficiency, either good or bad, when compared to an established base or norm.” 
Skilled labor is the portion of workers that have specific technical industry skills while unskilled 
labor is the cheaper and less technical portion of the workforce but both are required for any 
construction site. Although skilled workers are more expensive than other workers in the market, 
they provide tremendous value by improving the productivity on the basis of their expertise. 
Similarly, unskilled labor also plays the important part of performing repetitive tasks that do not 
require technical abilities. 
Human resource planning is the process by which an organization attempts to ensure that it has 
the right number and right kind of people in the right jobs at the right time. 
Best practice of Project HR Planning: 
 Fast growth in exchange of Technology and Machinery operations. 
 Organizational structure with right people at right-time. 
 Proper Organization Structure and clear responsible Org. Chart. 
 Proper rewarding-scheme and good incentive wages. 
Positive Impact in performance of the Construction project on: 
 Efficiency of the project execution. 
 Managerial and Organizational Competencies. 
 Personal Capability growth. 
 Technical performance and innovation creativity. 
 Team Performance and interfaces.
Question#5 
Write short notes on the following 
I. Management of Sub Contractors 
II. Site Assembly 
III. Cladding 
IV. Precast Construction Technology 
V. Role of Construction Managers in productivity improvement and management 
VI. Steel Construction 
Answer 
Management of Sub Contractors: Sometimes a major construction project is channeled from 
the prime contractor to other contractors who act as "subcontractors". They are usually required 
when the prime contractor may not have expertise in an area or may not have the physical 
resources to deliver it. 
Managing subcontractors is an important aspect of any project because each component of a 
project can affect the final outcome. Since subcontractors are not directly responsible to client, 
another challenge in managing them is to coordinate schedules to ensure that a project is 
completed in a given time period. Therefore the prime contractor required to follow some 
important instruction which are as follows, 
1. Selecting subcontractors because of their reputation in providing good service in a 
particular area. 
2. Identifying the things that you might do better than a subcontractor. 
3. Arrange a meeting with the subcontractor before the project is set to begin. Discuss 
expectations and costs. This is especially important if you have not worked with this 
subcontractor before. 
4. Have the subcontractor sign a contract. Having everything in writing will ensure that the 
project is done to your satisfaction before the subcontractor can be paid, and will avoid 
any attempt by the subcontractor to break the terms of your agreement. 
5. Working in partnership with subcontractors, building a relationship of trust and co-operation. 
6. Set clear deadlines. One of the most important parts of managing a subcontractor is time 
management, so agree to a start and finish date before beginning any project. 
7. Encourage subcontractors to communicate with each other to help the project go 
smoothly. For example, in a project that has a copywriter and a graphic designer; the two 
subcontractors should have one another's contact information so that questions can be 
answered quickly and efficiently. 
8. Be available if any problems arise. Subcontractors should be able to reach you 
immediately for any questions or problems. 
9. Taking action if a subcontractor's performance falls short.
10. Be flexible, but don't allow subcontractors to take advantage of you. Sometimes other 
projects need to take precedence, so allow subcontractors the ability to do emergency 
work if they need to. At the same time, make sure they know when you expect your 
project to be completed. 
All the above mention instructions can be summarize in two bullets as given below, 
 Good selection of subcontractors 
 Quality monitoring of subcontractors 
Site Assembly: “Prefabrication and modular construction processes have been used for years, 
but today, with the emergence of new technologies and construction practices, we have the 
ability to utilize these strategies to create innovative and quality buildings, while also improving 
construction productivity,” 
The theory behind the method is that time and cost is saved if similar construction tasks can be 
grouped, and assembly line techniques can be employed in prefabrication at a location where 
skilled labor is available, while congestion at the assembly site, which wastes time, can be 
reduced. The method finds application particularly where the structure is composed of repeating 
units or forms, or where multiple copies of the same basic structure are being constructed. 
Prefabrication avoids the need to transport so many skilled workers to the construction site, and 
other restricting conditions such as a lack of power, lack of water, exposure to harsh weather or a 
hazardous environment are avoided. Against these advantages must be weighed the cost of 
transporting prefabricated sections and lifting them into position as they will usually be larger, 
more fragile and more difficult to handle than the materials and components of which they are 
made. 
Some major advantages are as follows, 
1. Self-supporting ready-made components are used, so the need for formwork, shuttering 
and scaffolding is greatly reduced. 
2. Construction time is reduced and buildings are completed sooner, allowing an earlier 
return of the capital invested. 
3. On-site construction and congestion is minimized. 
4. Quality control can be easier in a factory assembly line setting than a construction site 
setting. 
5. Prefabrication can be located where skilled labor is more readily available and costs of 
labor, power, materials, space and overheads are lower. 
6. Time spent in bad weather or hazardous environments at the construction site is 
minimized. 
7. Less waste may occur 
8. Advanced materials such as sandwich-structured composite can be easily used, 
improving thermal and sound insulation and air tightness.
Increased adoption of Building Information Modeling, or “BIM,” is also fueling the reemergence 
of prefabrication and modularization as a critical new trend. Together, BIM and 
prefabrication/modular construction improve worksite productivity. 
Productivity improvements include decreased project schedules (66% report a positive impact— 
35% say it’s by four weeks or more), decreased costs (65% report positive impact— 41% say 
budgets decreased by 6% or more), and decreased construction site waste (77% report a positive 
impact— 44% say waste was decreased by 5% or more). 
Cladding: Cladding can be defined as an exterior finishing system that’s purpose is to protect 
the underlying structure as well as to provide a decorative finish. Cladding is surprisingly 
durable product that will last for up to fifty years, depending on the type of cladding that you 
choose and how it is looked after. It is getting more attention nowadays because it is very quick 
to install and also easy to work with. It is used to complement the architectural style of the 
building while also offering protection from rain, wind, snow, and other outside elements. 
Building cladding can also add insulation to the structure while minimizing sound transmission 
through the walls. 
Before exterior cladding can be installed, the structural framing of the building must be 
complete. This typically involves using wood or steel studs to frame out the exterior walls. These 
walls are then covered with plywood or oriented-strand board (OSB) to help brace against wind 
and other forces. 
Different types of cladding are as follows, 
 Weatherboard cladding: It is made from timber, reconstituted hardwood, fiber cement 
or vinyl. Weatherboards can be fixed to all kinds of substrates. Timber and fiber cement 
weatherboards need periodic maintenance to keep them looking their best while vinyl 
weatherboards are practically zero maintenance. 
 Vinyl cladding: If you’re after a cladding material that requires practically no 
maintenance, then vinyl cladding is for you! Vinyl cladding suits all kinds of homes and 
comes in a range of colors. It is also economical. Vinyl cladding is recyclable and uses 
fewer resources in its manufacturing than other types of cladding. It is easy to add 
insulation to vinyl cladding as well. 
 Fiber cement cladding: this type of cladding is made by compressing sand, cement, and 
cellular fiber into sheets. Fiber cement cladding gives the appearance of wood but it is 
lighter, easier to install, and requires less maintenance. 
 External foam cladding: this is also known as an External Insulated Finish System (EIFS) 
and it is made from expanded polystyrene that has been reinforced with fiberglass mesh
and finished with a render. It comes in panel form, is easy to install, is extremely tough 
and weather resistant, and is extremely energy efficient. 
 Metal cladding: metal cladding is either steel or aluminum cladding. The metal is 
protected through anodizing, galvanizing or powder coating and a range of different 
colors are available to suit any color scheme. A range of looks can be created using 
metal cladding such as sleek flat panels or corrugated looks. Metal cladding is also very 
low maintenance. 
Precast Construction Technology: The building system is the basis of an economy of every 
country. The industrialization demands apply to the need to increase paces of construction 
significantly, to reduce construction costs and improve quality standards. The Precast 
construction technology ensures both, well pace of construction and reduction in costs with 
improve quality, if handle properly. 
Compared with traditional construction methods and other building materials, prefabrication as a 
construction method, and concrete as a material, have a number of positive features. Therefore 
the use of precast concrete in construction is widely regarded as an economic, durable, 
structurally sound and architecturally versatile form of construction. The main features of this 
construction process are given below, 
 The division and specialization of the human workforce 
 The use of tools, machinery, and other equipment, usually automated, in the 
production of standard, interchangeable parts and products. 
Demand for precast concrete buildings continues to increase throughout. The profit potential of 
pre-casting, both in a production facility and on the jobsite, is indeed appealing. In general, labor 
costs are below conventional casting methods. Pre-casting techniques, however, differ 
considerably from conventional site-casting methods. A thorough understanding of this highly 
specialized system of concrete construction is prerequisite to a successful as well as profitable 
pre-casting operation. The growing popularity of the precast concrete frame technology is 
explained by the fact that it has significant advantages over traditional construction techniques: 
 Rapid construction on site 
 High quality because of the controlled conditions in the factory 
 Entire building can be precast-walls, floors, beams, etc. 
Precast construction technology also has some drawbacks which are as follows, 
 Very heavy members 
 Somewhat limited building design flexibility 
 Joints between panels are often expensive and complicated. 
 Skilled workmanship is required in the application of the panel on site. 
 Cranes are required to lift panels.
Role of Construction Managers in productivity improvement and management: In general 
people think that the two terms, Project manager and Construction manager, are the same but 
there is a difference between these two. On a same project considering both equivalents in terms 
of frame works but differs in terms of its scope. So it is very important to first differentiate 
between Project Manager and Construction Manager. 
The title Project manager implies managerial responsibility for all aspects of a project from start 
to finish while the Construction manager have managerial responsibility for a portion of a 
project that require civil work and handles a construction job. The primary role of the 
construction manager is to ensure that the project is completed on time, within budget, and in 
keeping with the original specifications. Hence we can say Construction manager is a sub set of 
Project manager where Project manager is a planner and construction manager is more the doer. 
In the current environment, construction managers are hard pressed to find ways to gain a 
competitive advantage and improve profit. In any given geographic area, construction labor, 
material and equipment cost are essentially the same. One of the few opportunities to improve 
the bottom line is to increase productivity. 
Studies show that workers on a construction project are unproductive for 50 percent of their time 
on site. Waiting eats up more than half of an employees’s unproductive time and about one-third 
of total project time. It can wreck a schedule and reduce the profit. 
There are many other drains of productivity at the construction site that must be consider by the 
construction manager, including: 
 Poorly planned materials management 
 Cleaning up the job site 
 Material waste and theft 
 Accidents 
 Substance abuse 
 Redoing substandard work and completing client punch list. 
Steel Construction: Nowadays more and more construction is being carried with the help of 
steel components all over the world. The reason of metal and steel components' wide distribution 
is simple: they are firm, more or less cheap, aesthetic, do not require further treatment and are 
environmentally friendly. This is not the whole list of their advantages but even these qualities 
are enough to draw attention to metal and steel component. On the other hand, corrosion is one 
of the biggest disadvantages of metal parts used for construction though nowadays most of the 
manufacturers heat-treat metal parts in order they become stainless and stone-like. 
Structural steel enhances construction productivity because of its shop fabrication while 
maintaining tight construction tolerances. Field placed material will always lag behind the 
productivity curve. Productivity enhancements for construction will occur not in labor based 
field activities, but in shop based technology enhancements. Technology exists today in the form
of 3-D interoperability and Building Information Modeling to allow the close cooperation 
between designers and steel specialty contractors in the design, fabrication and erection of 
building structures. This technology allows designs to save both time and cost in the construction 
process by integrating fabricating and erection efficiencies in the design and passing design 
models between analysis, detailing and fabricating operations. 
Today, when competing framing systems are evaluated for projects using comparable, current 
cost data, structural steel remains the cost leader for the majority of construction projects. 
Comparative studies indicate that a structural steel framing system including decking and fire 
protection will typically cost 5% to 7% less than a concrete framing system on a national basis. 
And that is not surprising; structural steel has remained the cost leader for construction materials 
over the past 30+ years. According to the Bureau of Labor Statistics the price for fabricated 
structural steel prices for commercial buildings increased 62% from their base date of 1980. In 
contrast, ready-mix concrete prices have escalated 114% during that same period. Why the 
difference? In 1980, 10 man-hours were required to produce a single ton of steel. Today that 
same ton of structural steel requires substantially less than a single man-hour. While not as 
dramatic, similar productivity enhancements have impacted the cost of detailing and fabrication. 
The end result is that the structural steel component of the construction industry is one of the few 
segments where significant productivity increases have occurred. 
Steel in construction allows the project architect a greater degree of expression and creativity in 
their design than any other construction material as they address both the functional demands of 
the building and unique identity of their client. Architects praise the natural beauty of steel and 
are excited about exposing it in the design of their structures to emphasize grace, slenderness, 
strength and transparency of frame. Column-free clear spans, the use of colored coatings and the 
opportunity for natural lighting highlight the elegant simplicity of using structural steel. 
Structural steel sections can be bent and rolled to create non-linear members to further enhance 
the aesthetic appeal of the structure. 
The following advantages in general may be credited to steel as a structural design material: 
 High strength/weight ratio 
 Good in ductility 
 Fast speed of erection 
 Adaptation of prefabrication 
The following may be considered as disadvantages of steel in certain cases: 
 High General cost 
 Week in Fireproofing. 
 More maintenance required. 
 Susceptibility to buckling.
Question#6 
Explain the role of “Computer Applications” in improving productivity of construction projects 
in terms of: 
I. Architectural Design 
II. Structural Design 
III. Project Planning and Scheduling 
IV. Progress Monitoring and Control 
V. Accounting 
VI. Site Management 
Answer 
The construction industry involves many specialized fields e.g. architectural, structural, 
planning, accounting and management etc. These fields form part of construction engineering. In 
almost all of these fields there is an inter-relationship between the kinds of skills required. In 
order to make work easier and more accurate many computing software and computer generated 
programs and equipments have been developed. 
In today’s environment, computers and the art of computing have revolutionalized the 
construction industry. In order to construct more energy saving buildings it has been imperative 
that computer programs that analyze all the possible outcomes have had to be used. This has led 
to the productivity improvement through reduction of the manual labor required as well as 
reducing the monetary burden. In addition through the use of computerized programs more job 
opportunities have been created in the information technology sector as more people with IT 
skills are entering the market to produce more user friendly and efficient construction 
engineering tools. 
Architectural Design: Architectural design may be aided by using the computer applications 
e.g. Computer Aided Program (CAD), that has both the features drafting as well as modeling. By 
using these software programs, an optimum solution in the architectural design may be reached 
since the architect can use the computer to examine a lot of designs before making a final 
decision. Therefore modern practice of architecture requires much use of the computer in 
applications such as design, creating computerized models, creating 3D models, structural 
integrity testing and layout testing. Architectural models are the ones most benefited by the aid 
of computers because these are jobs much harder when done by hand.
Structural Design: After the architectural design the second phase or the most important phase 
is the structural design which involves complicated calculations on large scale. Structural 
engineers are continually being asked to do more, in less time, and using a disconnected 
workflow eats into profits quickly. Integrating analysis, design, documentation and detailing 
increases productivity and is critical for business growth. Computer applications can be used in 
solving these complicated calculations and in making the design, by an integration of computer 
aided analysis through different software available in market e.g. SAP, E-tab and SAFE etc. 
Project planning, scheduling, monitoring and control: In the area of construction 
management, computers are useful as aids in planning, scheduling, monitoring and controlling 
projects of all sizes. The merits of applying computers in the area of construction management 
are numerous. Firstly it can quickly provide vast amount of information to the planner and 
secondly, it provides the construction manager with the opportunity to simulate a project and 
compare alternative proposal to arrive at a satisfactory solution. The most common software, 
used for planning, scheduling, monitoring and controlling, are Primavera and MS-Project. 
Accounting: The computer applications are beneficial for both office and side administration. 
For instance, with the aid of a computer, a database and financial accounting software system, 
the contractors may execute with ease the cash flow forecasting. The database can conveniently 
store cash and other records of past projects with which the contractor can plan for new projects 
and enables him make better informed decisions. 
Site Management: Computers are also currently being used by quantity surveyors in the 
preparation of bills of quantity and project estimate. Some of the available software systems also 
incorporate the standard methods of measurements (SMM). There are various methods of data 
input available. The input method can incorporate traditionally prepared dimensions, suitably 
coded or the organization can use direct keyboard entry with automated squaring or a fully 
integrated digitizer. Most computer aided estimating systems are either based on spread sheets, 
or estimating packages. The building contractors may also use the computers to keep inventory 
of all equipment, especially where it is necessary to maintain large volumes of equipment.

More Related Content

What's hot

022 Construction Productivity (PART 1)
022 Construction Productivity (PART 1)022 Construction Productivity (PART 1)
022 Construction Productivity (PART 1)Dr Fereidoun Dejahang
 
The Study of Measurement of Over-Engineering in Construction Project
The Study of Measurement of Over-Engineering in Construction ProjectThe Study of Measurement of Over-Engineering in Construction Project
The Study of Measurement of Over-Engineering in Construction ProjectIRJET Journal
 
Performance evaluation of design build projects with and without agency const...
Performance evaluation of design build projects with and without agency const...Performance evaluation of design build projects with and without agency const...
Performance evaluation of design build projects with and without agency const...IAEME Publication
 
IRJET- Study on Scope Variances in Construction Projects
IRJET- Study on Scope Variances in Construction ProjectsIRJET- Study on Scope Variances in Construction Projects
IRJET- Study on Scope Variances in Construction ProjectsIRJET Journal
 
AMTS Construction Management, Project Management, Facility Solutions Expertise
AMTS Construction Management, Project Management, Facility Solutions ExpertiseAMTS Construction Management, Project Management, Facility Solutions Expertise
AMTS Construction Management, Project Management, Facility Solutions ExpertiseAM Technical Solutions, Inc
 
construction project managment_civileng
construction project managment_civilengconstruction project managment_civileng
construction project managment_civilengsulaiman khan
 
Probabilistic fatigue design of shaft for bending and torsion
Probabilistic fatigue design of shaft for bending and torsionProbabilistic fatigue design of shaft for bending and torsion
Probabilistic fatigue design of shaft for bending and torsioneSAT Publishing House
 
Main Contractors' Strategies in Managing Construction Quality of Sub Contract...
Main Contractors' Strategies in Managing Construction Quality of Sub Contract...Main Contractors' Strategies in Managing Construction Quality of Sub Contract...
Main Contractors' Strategies in Managing Construction Quality of Sub Contract...IRJET Journal
 
Tc iv submited paper risk analysis and managements large epc projects
Tc iv submited paper risk analysis and managements  large epc projectsTc iv submited paper risk analysis and managements  large epc projects
Tc iv submited paper risk analysis and managements large epc projectsPALLA NARASIMHUDU
 
Construction Management Final Exam Essay
Construction Management Final Exam EssayConstruction Management Final Exam Essay
Construction Management Final Exam EssayHARLAND MIMS
 
Cae technologies for efficient vibro acoustic vehicle
Cae technologies for efficient vibro acoustic vehicleCae technologies for efficient vibro acoustic vehicle
Cae technologies for efficient vibro acoustic vehicleCec deMille
 
Academic paper and supporting document on fast track construction (1)
Academic paper and supporting document on fast track construction (1)Academic paper and supporting document on fast track construction (1)
Academic paper and supporting document on fast track construction (1)Ahmed Rushdhie
 
Fast track projects experiences and overview by Rajesh Prasad
Fast track projects   experiences and overview by Rajesh PrasadFast track projects   experiences and overview by Rajesh Prasad
Fast track projects experiences and overview by Rajesh PrasadRajesh Prasad
 
Risk Management In Construction Projects Of Developing Countries
Risk Management In Construction Projects Of Developing CountriesRisk Management In Construction Projects Of Developing Countries
Risk Management In Construction Projects Of Developing CountriesIJERA Editor
 
Value Management Assignment (Report)
Value Management Assignment (Report)Value Management Assignment (Report)
Value Management Assignment (Report)Pang Khai Shuen
 
Internship
InternshipInternship
InternshipIsa Ma
 
Value engineering practical
Value engineering practicalValue engineering practical
Value engineering practicalAbada Saad
 

What's hot (17)

022 Construction Productivity (PART 1)
022 Construction Productivity (PART 1)022 Construction Productivity (PART 1)
022 Construction Productivity (PART 1)
 
The Study of Measurement of Over-Engineering in Construction Project
The Study of Measurement of Over-Engineering in Construction ProjectThe Study of Measurement of Over-Engineering in Construction Project
The Study of Measurement of Over-Engineering in Construction Project
 
Performance evaluation of design build projects with and without agency const...
Performance evaluation of design build projects with and without agency const...Performance evaluation of design build projects with and without agency const...
Performance evaluation of design build projects with and without agency const...
 
IRJET- Study on Scope Variances in Construction Projects
IRJET- Study on Scope Variances in Construction ProjectsIRJET- Study on Scope Variances in Construction Projects
IRJET- Study on Scope Variances in Construction Projects
 
AMTS Construction Management, Project Management, Facility Solutions Expertise
AMTS Construction Management, Project Management, Facility Solutions ExpertiseAMTS Construction Management, Project Management, Facility Solutions Expertise
AMTS Construction Management, Project Management, Facility Solutions Expertise
 
construction project managment_civileng
construction project managment_civilengconstruction project managment_civileng
construction project managment_civileng
 
Probabilistic fatigue design of shaft for bending and torsion
Probabilistic fatigue design of shaft for bending and torsionProbabilistic fatigue design of shaft for bending and torsion
Probabilistic fatigue design of shaft for bending and torsion
 
Main Contractors' Strategies in Managing Construction Quality of Sub Contract...
Main Contractors' Strategies in Managing Construction Quality of Sub Contract...Main Contractors' Strategies in Managing Construction Quality of Sub Contract...
Main Contractors' Strategies in Managing Construction Quality of Sub Contract...
 
Tc iv submited paper risk analysis and managements large epc projects
Tc iv submited paper risk analysis and managements  large epc projectsTc iv submited paper risk analysis and managements  large epc projects
Tc iv submited paper risk analysis and managements large epc projects
 
Construction Management Final Exam Essay
Construction Management Final Exam EssayConstruction Management Final Exam Essay
Construction Management Final Exam Essay
 
Cae technologies for efficient vibro acoustic vehicle
Cae technologies for efficient vibro acoustic vehicleCae technologies for efficient vibro acoustic vehicle
Cae technologies for efficient vibro acoustic vehicle
 
Academic paper and supporting document on fast track construction (1)
Academic paper and supporting document on fast track construction (1)Academic paper and supporting document on fast track construction (1)
Academic paper and supporting document on fast track construction (1)
 
Fast track projects experiences and overview by Rajesh Prasad
Fast track projects   experiences and overview by Rajesh PrasadFast track projects   experiences and overview by Rajesh Prasad
Fast track projects experiences and overview by Rajesh Prasad
 
Risk Management In Construction Projects Of Developing Countries
Risk Management In Construction Projects Of Developing CountriesRisk Management In Construction Projects Of Developing Countries
Risk Management In Construction Projects Of Developing Countries
 
Value Management Assignment (Report)
Value Management Assignment (Report)Value Management Assignment (Report)
Value Management Assignment (Report)
 
Internship
InternshipInternship
Internship
 
Value engineering practical
Value engineering practicalValue engineering practical
Value engineering practical
 

Viewers also liked

Commercial j party customers
Commercial j party   customersCommercial j party   customers
Commercial j party customersprincevalium
 
Programme formation nanon côte d'ivoire2013
Programme formation nanon côte d'ivoire2013Programme formation nanon côte d'ivoire2013
Programme formation nanon côte d'ivoire2013Franck Joel DAGO
 
Film marketing and distribution
Film marketing and distributionFilm marketing and distribution
Film marketing and distributionotyrrell10
 
Theisraeltruth 1231872498141069-1
Theisraeltruth 1231872498141069-1Theisraeltruth 1231872498141069-1
Theisraeltruth 1231872498141069-1Al-Quds
 
Maths in daily core
Maths in daily coreMaths in daily core
Maths in daily coreIshaan Jain
 
PIDC Strategic Mgt
PIDC Strategic Mgt PIDC Strategic Mgt
PIDC Strategic Mgt small_nomi
 
51 (chico xavier)-andreluis-entreaterraeocéu
51 (chico xavier)-andreluis-entreaterraeocéu51 (chico xavier)-andreluis-entreaterraeocéu
51 (chico xavier)-andreluis-entreaterraeocéucentrodeestudos1987
 
Fisk lter comp
Fisk lter compFisk lter comp
Fisk lter compmelnhe
 
TuneWolf Intro
TuneWolf IntroTuneWolf Intro
TuneWolf IntroWolflead
 
About Spaceavatar
About SpaceavatarAbout Spaceavatar
About Spaceavatarspaceavatar
 
Nss fellowship presentation final
Nss fellowship presentation final  Nss fellowship presentation final
Nss fellowship presentation final sunnychheda
 
Eyvindson iufro
Eyvindson iufroEyvindson iufro
Eyvindson iufromelnhe
 
Palestra Ministrada no 3 Encontro do GTS-CE
Palestra Ministrada no 3 Encontro do GTS-CEPalestra Ministrada no 3 Encontro do GTS-CE
Palestra Ministrada no 3 Encontro do GTS-CEHedley Luna
 
The effect of P and N addition on red maple seed production
The effect of P and N addition on red maple seed productionThe effect of P and N addition on red maple seed production
The effect of P and N addition on red maple seed productionmelnhe
 
Hb2015 swindon-carbon
Hb2015 swindon-carbonHb2015 swindon-carbon
Hb2015 swindon-carbonmelnhe
 

Viewers also liked (20)

Commercial j party customers
Commercial j party   customersCommercial j party   customers
Commercial j party customers
 
Student_Parent Handbook
Student_Parent HandbookStudent_Parent Handbook
Student_Parent Handbook
 
Bio Newsletter - Ball
Bio Newsletter - BallBio Newsletter - Ball
Bio Newsletter - Ball
 
4 iso 9001 2000 standard
4 iso 9001 2000 standard4 iso 9001 2000 standard
4 iso 9001 2000 standard
 
Programme formation nanon côte d'ivoire2013
Programme formation nanon côte d'ivoire2013Programme formation nanon côte d'ivoire2013
Programme formation nanon côte d'ivoire2013
 
Film marketing and distribution
Film marketing and distributionFilm marketing and distribution
Film marketing and distribution
 
Theisraeltruth 1231872498141069-1
Theisraeltruth 1231872498141069-1Theisraeltruth 1231872498141069-1
Theisraeltruth 1231872498141069-1
 
Maths in daily core
Maths in daily coreMaths in daily core
Maths in daily core
 
PIDC Strategic Mgt
PIDC Strategic Mgt PIDC Strategic Mgt
PIDC Strategic Mgt
 
The Prince
The PrinceThe Prince
The Prince
 
51 (chico xavier)-andreluis-entreaterraeocéu
51 (chico xavier)-andreluis-entreaterraeocéu51 (chico xavier)-andreluis-entreaterraeocéu
51 (chico xavier)-andreluis-entreaterraeocéu
 
Fisk lter comp
Fisk lter compFisk lter comp
Fisk lter comp
 
TuneWolf Intro
TuneWolf IntroTuneWolf Intro
TuneWolf Intro
 
About Spaceavatar
About SpaceavatarAbout Spaceavatar
About Spaceavatar
 
Nss fellowship presentation final
Nss fellowship presentation final  Nss fellowship presentation final
Nss fellowship presentation final
 
Eyvindson iufro
Eyvindson iufroEyvindson iufro
Eyvindson iufro
 
Palestra Ministrada no 3 Encontro do GTS-CE
Palestra Ministrada no 3 Encontro do GTS-CEPalestra Ministrada no 3 Encontro do GTS-CE
Palestra Ministrada no 3 Encontro do GTS-CE
 
The effect of P and N addition on red maple seed production
The effect of P and N addition on red maple seed productionThe effect of P and N addition on red maple seed production
The effect of P and N addition on red maple seed production
 
Conics 2
Conics 2Conics 2
Conics 2
 
Hb2015 swindon-carbon
Hb2015 swindon-carbonHb2015 swindon-carbon
Hb2015 swindon-carbon
 

Similar to Const. Productivity Management

Project management chapter 9
Project management chapter 9Project management chapter 9
Project management chapter 9VancityInstitute
 
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...IRJET Journal
 
Risk Management and Cost Overruns due to delays in Construction Project using...
Risk Management and Cost Overruns due to delays in Construction Project using...Risk Management and Cost Overruns due to delays in Construction Project using...
Risk Management and Cost Overruns due to delays in Construction Project using...IRJET Journal
 
Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Gregoire Lesecq
 
Construction project management
Construction project managementConstruction project management
Construction project managementsaif hasan
 
Research paper on TQM
Research paper on TQM Research paper on TQM
Research paper on TQM Mital Damani
 
Pm0011 project planning and scheduling
Pm0011  project planning and schedulingPm0011  project planning and scheduling
Pm0011 project planning and schedulingsmumbahelp
 
Lec.1 Introduction to Estimation
Lec.1   Introduction to EstimationLec.1   Introduction to Estimation
Lec.1 Introduction to EstimationMuthanna Abbu
 
Reinforce your working domain with leading-edge BIM training.pdf
Reinforce your working domain with leading-edge BIM training.pdfReinforce your working domain with leading-edge BIM training.pdf
Reinforce your working domain with leading-edge BIM training.pdfnibtedu
 
Reinforce your working domain with leading-edge BIM training and skills to th...
Reinforce your working domain with leading-edge BIM training and skills to th...Reinforce your working domain with leading-edge BIM training and skills to th...
Reinforce your working domain with leading-edge BIM training and skills to th...nibtedu
 
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET Journal
 
IRJET- Prediction Model of Factors Causing Increase in Overhead Cost in C...
IRJET-  	  Prediction Model of Factors Causing Increase in Overhead Cost in C...IRJET-  	  Prediction Model of Factors Causing Increase in Overhead Cost in C...
IRJET- Prediction Model of Factors Causing Increase in Overhead Cost in C...IRJET Journal
 
A Synergistic Approach To Information Systems Project Management
A Synergistic Approach To Information Systems Project ManagementA Synergistic Approach To Information Systems Project Management
A Synergistic Approach To Information Systems Project ManagementJoe Osborn
 
OR&A - Bridging the gap
OR&A - Bridging the gapOR&A - Bridging the gap
OR&A - Bridging the gapuak10
 
Demystifying Designing for ‘X’ by ProTek Medical
Demystifying Designing for ‘X’ by ProTek Medical Demystifying Designing for ‘X’ by ProTek Medical
Demystifying Designing for ‘X’ by ProTek Medical ProtekMedical
 
1. Response needed for the below postBased on the sophisticated .docx
1. Response needed for the below postBased on the sophisticated .docx1. Response needed for the below postBased on the sophisticated .docx
1. Response needed for the below postBased on the sophisticated .docxjeremylockett77
 
How to Navigate the Commissioning Process: From Planning to Post-Construction
How to Navigate the Commissioning Process: From Planning to Post-ConstructionHow to Navigate the Commissioning Process: From Planning to Post-Construction
How to Navigate the Commissioning Process: From Planning to Post-ConstructionOlivia Wilson
 

Similar to Const. Productivity Management (20)

Project management chapter 9
Project management chapter 9Project management chapter 9
Project management chapter 9
 
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
 
Risk Management and Cost Overruns due to delays in Construction Project using...
Risk Management and Cost Overruns due to delays in Construction Project using...Risk Management and Cost Overruns due to delays in Construction Project using...
Risk Management and Cost Overruns due to delays in Construction Project using...
 
Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016
 
Construction project management
Construction project managementConstruction project management
Construction project management
 
Research paper on TQM
Research paper on TQM Research paper on TQM
Research paper on TQM
 
Pm0011 project planning and scheduling
Pm0011  project planning and schedulingPm0011  project planning and scheduling
Pm0011 project planning and scheduling
 
Duration
DurationDuration
Duration
 
Lec.1 Introduction to Estimation
Lec.1   Introduction to EstimationLec.1   Introduction to Estimation
Lec.1 Introduction to Estimation
 
Reinforce your working domain with leading-edge BIM training.pdf
Reinforce your working domain with leading-edge BIM training.pdfReinforce your working domain with leading-edge BIM training.pdf
Reinforce your working domain with leading-edge BIM training.pdf
 
Reinforce your working domain with leading-edge BIM training and skills to th...
Reinforce your working domain with leading-edge BIM training and skills to th...Reinforce your working domain with leading-edge BIM training and skills to th...
Reinforce your working domain with leading-edge BIM training and skills to th...
 
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
 
IRJET- Prediction Model of Factors Causing Increase in Overhead Cost in C...
IRJET-  	  Prediction Model of Factors Causing Increase in Overhead Cost in C...IRJET-  	  Prediction Model of Factors Causing Increase in Overhead Cost in C...
IRJET- Prediction Model of Factors Causing Increase in Overhead Cost in C...
 
A Synergistic Approach To Information Systems Project Management
A Synergistic Approach To Information Systems Project ManagementA Synergistic Approach To Information Systems Project Management
A Synergistic Approach To Information Systems Project Management
 
OR&A - Bridging the gap
OR&A - Bridging the gapOR&A - Bridging the gap
OR&A - Bridging the gap
 
concurrent engineering.pdf
concurrent engineering.pdfconcurrent engineering.pdf
concurrent engineering.pdf
 
H1303055462
H1303055462H1303055462
H1303055462
 
Demystifying Designing for ‘X’ by ProTek Medical
Demystifying Designing for ‘X’ by ProTek Medical Demystifying Designing for ‘X’ by ProTek Medical
Demystifying Designing for ‘X’ by ProTek Medical
 
1. Response needed for the below postBased on the sophisticated .docx
1. Response needed for the below postBased on the sophisticated .docx1. Response needed for the below postBased on the sophisticated .docx
1. Response needed for the below postBased on the sophisticated .docx
 
How to Navigate the Commissioning Process: From Planning to Post-Construction
How to Navigate the Commissioning Process: From Planning to Post-ConstructionHow to Navigate the Commissioning Process: From Planning to Post-Construction
How to Navigate the Commissioning Process: From Planning to Post-Construction
 

Recently uploaded

CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacingjaychoudhary37
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 

Recently uploaded (20)

CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacing
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 

Const. Productivity Management

  • 1. Question#1 Explain “Construction Productivity” and highlight its importance. Answer Productivity is a term that can be defined in many ways and it is often confused with the term “Production” because many people think that the greater the production, the greater the productivity but this is not necessarily true. Productivity is concerned with the efficient and effective utilization of resources in producing goods and services. In business world, productivity measures investment in capital against profit but particularly the term Construction Productivity means efficiency in execution process by considering all aspects of competitiveness and innovation. As we know that construction productivity largely depends upon human performance, it can be simply calculated through the output of any aspect of production per unit of input. In an ideal case, perfect productivity (1.0) would be accomplished if all the engineering drawings would be 100 percent complete, there would be no delays of any kind, everyone would work safely, everything would fit perfectly the first time, the weather would be 70 degrees Fahrenheit, and there would be no litigation at the end of the project. On this basis we can say that construction productivity decline due to so many factors e.g. design complexity, dilution of supervision, high accident rate, jurisdictional disputes, adverse temperature and impractical QA/QC tolerances etc. All these factors of productivity can be summarize as follows,  Project Uniqueness  Technology  Management  Motivation factor  Hygiene factor Productivity usually measures in terms of 3M (Manpower, Material & Machinery). Two distinct and independent methodologies are used to determine productivity changes. The first approach is an output-based one, in which real costs per square foot for several buildings types, further adjusted for enhancements in quality and content, are compared over the study period. PT = [(1+PN) x (1+PL)] -1 Where PT = total productivity increase, PN = quantitative productivity increase, and PL = qualitative productivity increase. The second approach, termed the input-based approach, constructs a model based upon observable changes in labor productivity at the task level, changes in real materials costs, and changes in costs of tools and equipment utilized at the jobsite. PL = (0.72 x PG) + (0.16 x PM) + (0.12 x PE) Where PL = total labor productivity increase, and PG, PM, and PE = categorical labor productivity increases for general, mechanical, and electrical construction respectively.
  • 2. Importance of Productivity Productivity in construction is very important for an individual or for the whole industry especially from the economic point of view because construction industry accounts for 3-8% of the GDP in most countries. Unfortunately we are living in the world of great uncertainty therefore to improve or maintain the construction productivity is very challenging.  Higher production output, lower inflation rate and further productivity growth could be benefited from productivity improvement.  With a higher productivity, the local contractors are able to reduce the construction cost and therefore benefit from a higher profit. Also, the contractor can even offer a lower bidding price to increase his competitiveness. A productivity benefit model is presented by David J. Sumanth in 1980, according to which total productivity improvement in organizations benefits everyone consumers, employees, owners/stockholders, the society and the nation as a whole. Therefore, productivity cycle concept show us that productivity improvement must be preceded by measurement, evaluation, and planning. All four phases are important, not just productivity measurement or just productivity improvement. Hence it shows that productivity program is not a one-time project, but rather a continuous, on-going process.
  • 3. Question#2 Explain the process of crane selection for the construction of a multi storey building. What effect does it have on the overall productivity? Answer The selection process of tower crane, for any multistory building, is not an easy task because in order to make construction convenient and highly economic we have to consider some important factors. Factors affecting the selection of cranes, including: shape, number of floors, the height of each floor; total volume; construction progress; ground conditions and construction areas, traffic conditions the crane service provision of units and the requirements of economic efficiency. Other basic considerations are as follows, APPLICATION: You should know the weight of objects that will be lifting and moving, the height of the lift, length and width of the move and the duty cycle of the crane including how often and for how long it will be used. ENVIRONMENT: Will the crane be used indoors or outdoors? Is your environment corrosive or have extreme temperatures? Is it going into a sterile environment such a food manufacturing? FACILITIES: When determining the type of crane and how it will be installed, you must take into consideration the limitations of your facilities. The roof, wall or floor structure must be assessed to ensure it will hold the crane and its load. QUALITY: Your crane must meet the crane codes. Also consider the classification (C1 to C9) of the crane which advises its lifespan and duty cycle. COST: The price of the crane is only the first part of this equation. You also must add in the cost of installation, maintenance, and the possibility for future expansion. As a conclusion, to choose the most affordable tower cranes should follow these steps:  Based on the characteristics of the work, technology and mass construction crane to choose.  Select the correct crane working mode.  Select the specifications of the crane in accordance with the real working conditions.  Compare the economic and technical indicators to select crane satisfaction.
  • 4. Effect of Crane on Overall Productivity The purpose behind the proper selection of crane is to improve the overall productivity of construction but in contrast, operating a crane is a very precise work. The person at the controls wields a lot of power, swinging heavy items into place while a crew on the ground assists. Hazards at construction sites can change quickly, putting employees who operate cranes or work around them at high risk for serious injuries, and even death. Electrocution, falls, moving machinery, excavations, and overhead loads are examples of a few common hazards that can plague rigging and other activities involving cranes. A Ensuring that equipment and personnel meet certification and other safety requirements helps employers prevent accidents and ensure that everyone goes home safely at the end of a long day. The overall productivity dictated by the efficiency of tower cranes that largely depends on their type, number and location. As the number of work tasks and the demand for tower cranes increase, planners may experience difficulties in making an appropriate decision about the optimum layout of tower cranes. A poor decision, however, is likely to have significant negative effects, which will lead to additional costs and possible delays. As a thumb rule, crane usually placed at a center location where it can cover the maximum construction area. Where there are other cranes on the same site and there is a risk of collision, a crash radio system is to be established and be used. This will be determined by the lifting assessment. Any other plant (Other cranes, Concrete Booms, Piling Rigs etc) that may be working within the radius of a crane, their operator must be made aware of such risks and a system must be put in place to control their movements (this may be via the crash radio or a permit to work system).
  • 5. Question#3 Explain the term “Work Breakdown”. Does it have any effect on the productivity of a project? Explain in detail. Answer In simple words, work breakdown structure (WBS) is a logical grouping tool that is used for better understanding by subdividing the total work scope of a project into small work packages. According to Project Management Body of Knowledge “A Work Breakdown Structure is a deliverable-oriented hierarchical decomposition of the work to be executed by the project team to accomplish the project objectives and create the required deliverables.” In WBS, much larger tasks are broken-down to manageable chunks of work. These chunks can be easily supervised and estimated but considerable thought and planning should be given to its development and implementation so that subsequent changes are minimized. Work Breakdown Structure (WBS) generally consist of five level hierarchy describing the entire effort to be accomplished by the primary organization, that number may not be appropriate for all situations. Following are a few reasons for creating a WBS in a project.  Accurate assignment of responsibilities to the project team.  Indicates the project milestones and control points.  Helps to estimate the cost, time, and risk.  Illustrate the project scope, so the stakeholders can have a better understanding of the same.
  • 6. Effects of WBS on Construction Productivity Construction Productivity is heavily depends upon comprehensive planning and the quality of planning is judged by the quality of work breakdown structure. In this sense, Work Breakdown Structure (WBS) can affect the productivity up to great extent because more clearly the scope of the project is articulated before the actual work begins, the more likely the success of the project. Experienced project managers know there are many things that can go wrong in projects regardless of how successfully they plan and execute their work. The positive and negative effects of WBS over productivity can be explain separately as follow, Positive Side: The WBS provides the project manager and team with the necessary framework of tasks going forward to create detailed cost estimates and also to provide major input to project task scheduling at the most detailed and accurate level possible. By going through the WBS motions, the project manager and team will have a pretty good idea whether or not they’ve captured all the necessary tasks, based on the project requirements, that are going to need to happen to get the job done with improve productivity. The WBS forces the project manager and team members to delineate the steps required to build and deliver the product or service. The exercise alone encourages a dialogue that will help clarify ambiguities, bring out assumptions, narrow the scope of the project, and raise critical issues early on. Negative Side: On the other hand, developing a WBS is not easy. It can be a painstaking process. And it can take quite a bit of time. A large WBS (one that identifies several thousand activities) can take many, many hours to develop. For another, it requires effort. There is a knowledge transfer and exercise of brainpower. The larger the scope of the project, the larger the WBS will be. More people must provide input and then approve the portion they are responsible to perform. There must be some logical pattern to the way in which these pieces are broken off. We don’t want it to be like smashing a piece of glass into lots of tiny pieces that can’t be put back together again. No we are looking for something more like a jigsaw puzzle, where every piece can be slotted into its right place to make the big picture without affecting the productivity. Even after considering the downsides, the overall advantages still outweigh the known challenges. A good WBS makes planning and executing a project easier and lays the groundwork for the schedule, the tracking, the budgeting, and all the accountability throughout the rest of the engagement that finally results productivity improvement.
  • 7. Question#4 Explain the process of planning, controlling and managing skilled and unskilled labor for a construction site. Answer A successful project requires careful planning, proper controlling and managing efforts throughout for human resource because it is beneficial for both client and contractor in order to achieve a timely and satisfactorily outcome. Construction uses more manpower in its activities as compared to the other field and the main challenge is to obtain proper mix ratio of work force both skilled and unskilled labor. The actual problems that we always face are shortage of skilled labor and dynamic work force, lack of effective training and performance in the Construction Projects. Productivity can also be defined in terms of labor as a “relative measure of labor efficiency, either good or bad, when compared to an established base or norm.” Skilled labor is the portion of workers that have specific technical industry skills while unskilled labor is the cheaper and less technical portion of the workforce but both are required for any construction site. Although skilled workers are more expensive than other workers in the market, they provide tremendous value by improving the productivity on the basis of their expertise. Similarly, unskilled labor also plays the important part of performing repetitive tasks that do not require technical abilities. Human resource planning is the process by which an organization attempts to ensure that it has the right number and right kind of people in the right jobs at the right time. Best practice of Project HR Planning:  Fast growth in exchange of Technology and Machinery operations.  Organizational structure with right people at right-time.  Proper Organization Structure and clear responsible Org. Chart.  Proper rewarding-scheme and good incentive wages. Positive Impact in performance of the Construction project on:  Efficiency of the project execution.  Managerial and Organizational Competencies.  Personal Capability growth.  Technical performance and innovation creativity.  Team Performance and interfaces.
  • 8. Question#5 Write short notes on the following I. Management of Sub Contractors II. Site Assembly III. Cladding IV. Precast Construction Technology V. Role of Construction Managers in productivity improvement and management VI. Steel Construction Answer Management of Sub Contractors: Sometimes a major construction project is channeled from the prime contractor to other contractors who act as "subcontractors". They are usually required when the prime contractor may not have expertise in an area or may not have the physical resources to deliver it. Managing subcontractors is an important aspect of any project because each component of a project can affect the final outcome. Since subcontractors are not directly responsible to client, another challenge in managing them is to coordinate schedules to ensure that a project is completed in a given time period. Therefore the prime contractor required to follow some important instruction which are as follows, 1. Selecting subcontractors because of their reputation in providing good service in a particular area. 2. Identifying the things that you might do better than a subcontractor. 3. Arrange a meeting with the subcontractor before the project is set to begin. Discuss expectations and costs. This is especially important if you have not worked with this subcontractor before. 4. Have the subcontractor sign a contract. Having everything in writing will ensure that the project is done to your satisfaction before the subcontractor can be paid, and will avoid any attempt by the subcontractor to break the terms of your agreement. 5. Working in partnership with subcontractors, building a relationship of trust and co-operation. 6. Set clear deadlines. One of the most important parts of managing a subcontractor is time management, so agree to a start and finish date before beginning any project. 7. Encourage subcontractors to communicate with each other to help the project go smoothly. For example, in a project that has a copywriter and a graphic designer; the two subcontractors should have one another's contact information so that questions can be answered quickly and efficiently. 8. Be available if any problems arise. Subcontractors should be able to reach you immediately for any questions or problems. 9. Taking action if a subcontractor's performance falls short.
  • 9. 10. Be flexible, but don't allow subcontractors to take advantage of you. Sometimes other projects need to take precedence, so allow subcontractors the ability to do emergency work if they need to. At the same time, make sure they know when you expect your project to be completed. All the above mention instructions can be summarize in two bullets as given below,  Good selection of subcontractors  Quality monitoring of subcontractors Site Assembly: “Prefabrication and modular construction processes have been used for years, but today, with the emergence of new technologies and construction practices, we have the ability to utilize these strategies to create innovative and quality buildings, while also improving construction productivity,” The theory behind the method is that time and cost is saved if similar construction tasks can be grouped, and assembly line techniques can be employed in prefabrication at a location where skilled labor is available, while congestion at the assembly site, which wastes time, can be reduced. The method finds application particularly where the structure is composed of repeating units or forms, or where multiple copies of the same basic structure are being constructed. Prefabrication avoids the need to transport so many skilled workers to the construction site, and other restricting conditions such as a lack of power, lack of water, exposure to harsh weather or a hazardous environment are avoided. Against these advantages must be weighed the cost of transporting prefabricated sections and lifting them into position as they will usually be larger, more fragile and more difficult to handle than the materials and components of which they are made. Some major advantages are as follows, 1. Self-supporting ready-made components are used, so the need for formwork, shuttering and scaffolding is greatly reduced. 2. Construction time is reduced and buildings are completed sooner, allowing an earlier return of the capital invested. 3. On-site construction and congestion is minimized. 4. Quality control can be easier in a factory assembly line setting than a construction site setting. 5. Prefabrication can be located where skilled labor is more readily available and costs of labor, power, materials, space and overheads are lower. 6. Time spent in bad weather or hazardous environments at the construction site is minimized. 7. Less waste may occur 8. Advanced materials such as sandwich-structured composite can be easily used, improving thermal and sound insulation and air tightness.
  • 10. Increased adoption of Building Information Modeling, or “BIM,” is also fueling the reemergence of prefabrication and modularization as a critical new trend. Together, BIM and prefabrication/modular construction improve worksite productivity. Productivity improvements include decreased project schedules (66% report a positive impact— 35% say it’s by four weeks or more), decreased costs (65% report positive impact— 41% say budgets decreased by 6% or more), and decreased construction site waste (77% report a positive impact— 44% say waste was decreased by 5% or more). Cladding: Cladding can be defined as an exterior finishing system that’s purpose is to protect the underlying structure as well as to provide a decorative finish. Cladding is surprisingly durable product that will last for up to fifty years, depending on the type of cladding that you choose and how it is looked after. It is getting more attention nowadays because it is very quick to install and also easy to work with. It is used to complement the architectural style of the building while also offering protection from rain, wind, snow, and other outside elements. Building cladding can also add insulation to the structure while minimizing sound transmission through the walls. Before exterior cladding can be installed, the structural framing of the building must be complete. This typically involves using wood or steel studs to frame out the exterior walls. These walls are then covered with plywood or oriented-strand board (OSB) to help brace against wind and other forces. Different types of cladding are as follows,  Weatherboard cladding: It is made from timber, reconstituted hardwood, fiber cement or vinyl. Weatherboards can be fixed to all kinds of substrates. Timber and fiber cement weatherboards need periodic maintenance to keep them looking their best while vinyl weatherboards are practically zero maintenance.  Vinyl cladding: If you’re after a cladding material that requires practically no maintenance, then vinyl cladding is for you! Vinyl cladding suits all kinds of homes and comes in a range of colors. It is also economical. Vinyl cladding is recyclable and uses fewer resources in its manufacturing than other types of cladding. It is easy to add insulation to vinyl cladding as well.  Fiber cement cladding: this type of cladding is made by compressing sand, cement, and cellular fiber into sheets. Fiber cement cladding gives the appearance of wood but it is lighter, easier to install, and requires less maintenance.  External foam cladding: this is also known as an External Insulated Finish System (EIFS) and it is made from expanded polystyrene that has been reinforced with fiberglass mesh
  • 11. and finished with a render. It comes in panel form, is easy to install, is extremely tough and weather resistant, and is extremely energy efficient.  Metal cladding: metal cladding is either steel or aluminum cladding. The metal is protected through anodizing, galvanizing or powder coating and a range of different colors are available to suit any color scheme. A range of looks can be created using metal cladding such as sleek flat panels or corrugated looks. Metal cladding is also very low maintenance. Precast Construction Technology: The building system is the basis of an economy of every country. The industrialization demands apply to the need to increase paces of construction significantly, to reduce construction costs and improve quality standards. The Precast construction technology ensures both, well pace of construction and reduction in costs with improve quality, if handle properly. Compared with traditional construction methods and other building materials, prefabrication as a construction method, and concrete as a material, have a number of positive features. Therefore the use of precast concrete in construction is widely regarded as an economic, durable, structurally sound and architecturally versatile form of construction. The main features of this construction process are given below,  The division and specialization of the human workforce  The use of tools, machinery, and other equipment, usually automated, in the production of standard, interchangeable parts and products. Demand for precast concrete buildings continues to increase throughout. The profit potential of pre-casting, both in a production facility and on the jobsite, is indeed appealing. In general, labor costs are below conventional casting methods. Pre-casting techniques, however, differ considerably from conventional site-casting methods. A thorough understanding of this highly specialized system of concrete construction is prerequisite to a successful as well as profitable pre-casting operation. The growing popularity of the precast concrete frame technology is explained by the fact that it has significant advantages over traditional construction techniques:  Rapid construction on site  High quality because of the controlled conditions in the factory  Entire building can be precast-walls, floors, beams, etc. Precast construction technology also has some drawbacks which are as follows,  Very heavy members  Somewhat limited building design flexibility  Joints between panels are often expensive and complicated.  Skilled workmanship is required in the application of the panel on site.  Cranes are required to lift panels.
  • 12. Role of Construction Managers in productivity improvement and management: In general people think that the two terms, Project manager and Construction manager, are the same but there is a difference between these two. On a same project considering both equivalents in terms of frame works but differs in terms of its scope. So it is very important to first differentiate between Project Manager and Construction Manager. The title Project manager implies managerial responsibility for all aspects of a project from start to finish while the Construction manager have managerial responsibility for a portion of a project that require civil work and handles a construction job. The primary role of the construction manager is to ensure that the project is completed on time, within budget, and in keeping with the original specifications. Hence we can say Construction manager is a sub set of Project manager where Project manager is a planner and construction manager is more the doer. In the current environment, construction managers are hard pressed to find ways to gain a competitive advantage and improve profit. In any given geographic area, construction labor, material and equipment cost are essentially the same. One of the few opportunities to improve the bottom line is to increase productivity. Studies show that workers on a construction project are unproductive for 50 percent of their time on site. Waiting eats up more than half of an employees’s unproductive time and about one-third of total project time. It can wreck a schedule and reduce the profit. There are many other drains of productivity at the construction site that must be consider by the construction manager, including:  Poorly planned materials management  Cleaning up the job site  Material waste and theft  Accidents  Substance abuse  Redoing substandard work and completing client punch list. Steel Construction: Nowadays more and more construction is being carried with the help of steel components all over the world. The reason of metal and steel components' wide distribution is simple: they are firm, more or less cheap, aesthetic, do not require further treatment and are environmentally friendly. This is not the whole list of their advantages but even these qualities are enough to draw attention to metal and steel component. On the other hand, corrosion is one of the biggest disadvantages of metal parts used for construction though nowadays most of the manufacturers heat-treat metal parts in order they become stainless and stone-like. Structural steel enhances construction productivity because of its shop fabrication while maintaining tight construction tolerances. Field placed material will always lag behind the productivity curve. Productivity enhancements for construction will occur not in labor based field activities, but in shop based technology enhancements. Technology exists today in the form
  • 13. of 3-D interoperability and Building Information Modeling to allow the close cooperation between designers and steel specialty contractors in the design, fabrication and erection of building structures. This technology allows designs to save both time and cost in the construction process by integrating fabricating and erection efficiencies in the design and passing design models between analysis, detailing and fabricating operations. Today, when competing framing systems are evaluated for projects using comparable, current cost data, structural steel remains the cost leader for the majority of construction projects. Comparative studies indicate that a structural steel framing system including decking and fire protection will typically cost 5% to 7% less than a concrete framing system on a national basis. And that is not surprising; structural steel has remained the cost leader for construction materials over the past 30+ years. According to the Bureau of Labor Statistics the price for fabricated structural steel prices for commercial buildings increased 62% from their base date of 1980. In contrast, ready-mix concrete prices have escalated 114% during that same period. Why the difference? In 1980, 10 man-hours were required to produce a single ton of steel. Today that same ton of structural steel requires substantially less than a single man-hour. While not as dramatic, similar productivity enhancements have impacted the cost of detailing and fabrication. The end result is that the structural steel component of the construction industry is one of the few segments where significant productivity increases have occurred. Steel in construction allows the project architect a greater degree of expression and creativity in their design than any other construction material as they address both the functional demands of the building and unique identity of their client. Architects praise the natural beauty of steel and are excited about exposing it in the design of their structures to emphasize grace, slenderness, strength and transparency of frame. Column-free clear spans, the use of colored coatings and the opportunity for natural lighting highlight the elegant simplicity of using structural steel. Structural steel sections can be bent and rolled to create non-linear members to further enhance the aesthetic appeal of the structure. The following advantages in general may be credited to steel as a structural design material:  High strength/weight ratio  Good in ductility  Fast speed of erection  Adaptation of prefabrication The following may be considered as disadvantages of steel in certain cases:  High General cost  Week in Fireproofing.  More maintenance required.  Susceptibility to buckling.
  • 14. Question#6 Explain the role of “Computer Applications” in improving productivity of construction projects in terms of: I. Architectural Design II. Structural Design III. Project Planning and Scheduling IV. Progress Monitoring and Control V. Accounting VI. Site Management Answer The construction industry involves many specialized fields e.g. architectural, structural, planning, accounting and management etc. These fields form part of construction engineering. In almost all of these fields there is an inter-relationship between the kinds of skills required. In order to make work easier and more accurate many computing software and computer generated programs and equipments have been developed. In today’s environment, computers and the art of computing have revolutionalized the construction industry. In order to construct more energy saving buildings it has been imperative that computer programs that analyze all the possible outcomes have had to be used. This has led to the productivity improvement through reduction of the manual labor required as well as reducing the monetary burden. In addition through the use of computerized programs more job opportunities have been created in the information technology sector as more people with IT skills are entering the market to produce more user friendly and efficient construction engineering tools. Architectural Design: Architectural design may be aided by using the computer applications e.g. Computer Aided Program (CAD), that has both the features drafting as well as modeling. By using these software programs, an optimum solution in the architectural design may be reached since the architect can use the computer to examine a lot of designs before making a final decision. Therefore modern practice of architecture requires much use of the computer in applications such as design, creating computerized models, creating 3D models, structural integrity testing and layout testing. Architectural models are the ones most benefited by the aid of computers because these are jobs much harder when done by hand.
  • 15. Structural Design: After the architectural design the second phase or the most important phase is the structural design which involves complicated calculations on large scale. Structural engineers are continually being asked to do more, in less time, and using a disconnected workflow eats into profits quickly. Integrating analysis, design, documentation and detailing increases productivity and is critical for business growth. Computer applications can be used in solving these complicated calculations and in making the design, by an integration of computer aided analysis through different software available in market e.g. SAP, E-tab and SAFE etc. Project planning, scheduling, monitoring and control: In the area of construction management, computers are useful as aids in planning, scheduling, monitoring and controlling projects of all sizes. The merits of applying computers in the area of construction management are numerous. Firstly it can quickly provide vast amount of information to the planner and secondly, it provides the construction manager with the opportunity to simulate a project and compare alternative proposal to arrive at a satisfactory solution. The most common software, used for planning, scheduling, monitoring and controlling, are Primavera and MS-Project. Accounting: The computer applications are beneficial for both office and side administration. For instance, with the aid of a computer, a database and financial accounting software system, the contractors may execute with ease the cash flow forecasting. The database can conveniently store cash and other records of past projects with which the contractor can plan for new projects and enables him make better informed decisions. Site Management: Computers are also currently being used by quantity surveyors in the preparation of bills of quantity and project estimate. Some of the available software systems also incorporate the standard methods of measurements (SMM). There are various methods of data input available. The input method can incorporate traditionally prepared dimensions, suitably coded or the organization can use direct keyboard entry with automated squaring or a fully integrated digitizer. Most computer aided estimating systems are either based on spread sheets, or estimating packages. The building contractors may also use the computers to keep inventory of all equipment, especially where it is necessary to maintain large volumes of equipment.