SlideShare a Scribd company logo
23rd International Conference on Electricity Distribution Lyon, 15-18 June 2015
Paper 1259
CIRED 2015 1/5
NO SMART MV/LV STATION WITHOUT A SMART APPROACH
Elise MORSKIEFT Gerrit SCHARRENBERG
Eaton Industries BV – the Netherlands Rendo – the Netherlands
EliseMorskieft@eaton.com gscharrenberg@rendo.nl
Felix JANSSEN Adriaan van der SCHAAR Alex van de SCHOOTBRUGGE
Reewoud Energietechniek BV Eleq BV Eaton Industries BV
the Netherlands the Netherlands the Netherlands
felix.janssen@reewoud.nl adriaan.vdschaar@eleq.com AlexvandeSchootbrugge@eaton.com
ABSTRACT
At the end of 2014, at several different locations in the
Netherlands, pilot systems for automated substations
were installed. These pilot systems are the result of the
final phase of the KRIS project, an initiative of multiple
Distribution System Operators (DSOs) in the
Netherlands, which started in 2012. What makes the
KRIS Project unique is that these DSOs worked closely
together to establish a list of common functional
requirements. Then the suppliers brought in their
experience and knowledge regarding the technical
feasibility and cost aspect of those requirements.
For engineering the V-model was used. During the
specification phase all parties worked together, sharing
information with a cooperative mentality.
Throughout the pilot phase suppliers, forming coalitions,
were challenged to work on their own solution. The goal
of the project was to come up with a cost effective
instrumentation of MV/LV equipment. Facing the end of
the project, the results show a competitive TCO for
instrumentation used in so-called strategic MV/LV
stations. For non-strategic stations the TCO does not yet
meet the expectations. This paper is written by coalition
ERE, one of the coalitions formed by Eleq, Reewoud
Energietechniek and Eaton Industries.
INTRODUCTION
Starting in 2012 multiple Distribution System Operators
(DSOs) in the Netherlands recognized that the energy
transition requires management of all elements in the
energy network. Therefore intelligent components will be
required on all secondary distribution levels, especially in
the MV/LV substations, the so called Ring Main Units
(RMUs).
Due to the high costs of such instrumentation, a large
scale roll-out was financially not feasible.
In addition, the suppliers were not aware of the DSOs
requirements for these components. The result: no match
between DSOs demands and the suppliers’ solutions.
To break this deadlock, project KRIS was initiated by the
DSOs. The goal of KRIS is defined as to create an open
innovative and competitive instrumentation market
aiming at low cost and modular MV/LV instrumentation,
by stimulating close cooperation between demand and
supply chains.
ORGANISATION KRIS PROJECT
The participants in the KRIS project, as shown in Figure
1, can be grouped in DSOs and Suppliers, supported by
Avans, an academic Educational Institute and
Technolution, a technology partner specialized in
enabling the interpretative step from business to the right
technological solution.
DSO’s Knowledge
Consultancy
Figure 1: Participants of the KRIS project
The project is structured as follows:
 steering committee, formed of representatives of all
parties
 users group, formed by the DSOs
 suppliers group, working together in coalitions
The steering committee acts as the decision-making
platform, has periodical meetings and informs the users
group about the progress of the project.
PROJECT PHASING
To reach the goal of the project, come to a cost effective
instrumentation of MV/LV equipment, a structured
approach for product development, as shown in Figure 2,
was followed.
Figure 2: Systems Engineering V-model
23rd International Conference on Electricity Distribution Lyon, 15-18 June 2015
Paper 1259
CIRED 2015 2/5
Phase 1 – Specifications
In Phase 1, plenary meetings with all participants were
held to build the concept for the specifications document.
With the outcome of these sessions, the Operational
Concept Description (OCD) [1] was set up. This was the
start document and describes all global requirements.
From this, the System/Sub system Specification (SSS) [2]
was written. This document specifies the requirements for
a system or subsystem and the methods to be used.
To fill in all the details of the specifications a number of
Working Groups (WGs) were formed, with specialists
from both the DSOs and the suppliers. Each Working
Group had its own specialized tasks.
 WG Use Cases
- Describe the use cases for MV/LV substations.
- Prioritize the described functionalities according to
the needs of all DSOs.
 WG Security
- Describe the security demands.
- Investigate available information and requirements.
 WG Key Figures
- Investigate the installed base of MV/LS stations in
the Netherlands in terms of total units, configuration
settings, and plans for replacement and/or retrofit.
 WG Environment
- Create an overview of existing projects and
developments in the field of instrumentation
MV/LV stations.
- What are the lessons learned, what should we take
into account?
 WG Measurements
- Specify the technical requirements underlying the
measurements needed to realize the use cases.
 WG Installation and Maintenance
- Investigate the minimum system requirements in
terms of safety, legalisation, standards, climate,
environment, accessibility, electricity and
mechanics.
- Describe a typical MV/LV installation.
 WG Data Communication
- Investigate the needs for Data Communication.
- Set up a long list with possible Data Communication
Protocols.
 WG Architecture
- Describe the preferred system architecture in terms
of structure, behaviour, modularity and interfaces,
both for hardware and software.
 WG Total Cost of Ownership (TCO)
- Develop a tool to validate the costs of acquisition,
installation and maintenance, taking into
consideration the entire life time of the system.
 WG Pilots & Test fields
- Coordinate the implementation and instalment at
the test field locations of the designed systems.
Phase 2 – Development
In Phase 2, the suppliers formed coalitions to develop a
modular system designed to meet the requirements stated
in the OCD [1] and SSS [2]. Each coalition came up with
its own product. One of the requirements was that the
instrumentation should be added to existing MV/LV
systems. Therefore it was very important to have a
flexible solution, with open interfaces to its surrounding.
After testing the developed systems in the laboratory of
one of the DSOs the solutions were then reviewed and
released for the field tests during the pilot phase.
Phase 3 – Pilots
In Phase 3, pilot systems were installed in existing
MV/LV stations at different locations throughout the
Netherlands. During the installation of the systems the
impact of installing instrumentation in an existing
MV/LV station was investigated.
REQUIREMENTS
In the SSS document [2] a set of in total 212
requirements were specified, divided under 13 subjects.
 Required system states
- Specifies the limited number of clearly
distinguishable states: Initializing, Fully Available,
Reduced Availability and Not Available.
 System capability requirements
- Specifies the basic functionality as Data
Acquisition, Control, Process Data, Data Storage,
Data Exchange, Configuration, Logging, Software,
(Self) Test functionality, Diagnostics and Power
Supply.
 System external interface requirements
- Specifies the interfaces to external equipment in
terms of configuration, software, data exchange and
maintenance.
 System internal interface requirements
- Specifies the interface between the sub systems and
MV/LV installation.
 System internal data requirements
- Specifies the integrity of the internal system data in
terms of protection against loss, accessibility and
privacy.
 Adaptation Requirements
- Specifies the ability of the system to be used in
existing and new MV/LV stations.
 Safety Requirements
- Specifies the systems safety requirements.
 Security and Privacy Protection requirements
- Specifies the security and privacy aspects of all data
 System Environment requirements.
- Specifies all requirements regarding the
environment of the system, e.g. EMC/EMI, climate,
shock and bump.
 Computer Resource requirements
- Specifies the computer hardware and software,
including communication interfaces.
23rd International Conference on Electricity Distribution Lyon, 15-18 June 2015
Paper 1259
CIRED 2015 3/5
 System Quality Factors
- Specifies the functionality to monitor the quality of
the MV and LV power, but also the requirements
regarding reliability, availability and upkeep.
 Restrictions Regarding Design and Production
- Specifies the non-functional requirements regarding
modularity, expandability, scalability, reusability,
interconnectivity and future proof. But also
requirements regarding installation and
maintenance.
 Personnel Related Requirements
- Specifies the role and background of the personnel
working with the system.
BENCHMARK
The SSS document [2] contains of a vast number of
requirements. Depending on the level of automation and
the location of the MV/LV station not all requirements
are always relevant.
To be able to prioritize the requirements, all DSOs shared
their vision and motivation regarding instrumentation of
MV/LV stations.
One of the drivers to use instrumentation in MV/LV
stations is to reduce the outage time for the end user.
Common used indicators to calculate the outage time are
SAIFI (System Average Interruption Frequency Index)
and SAIDI (System Average Interruption Duration
Index). In the period from 2001-2011 the average outage
time for an LV customer in the Netherlands was 28
minutes per year, 64 % of this was due to breakdowns in
the MV network [3].
In the Netherlands 95% of the MV networks are 10 kV
with underground cables. The majority of outages due to
breakdown in the MV network are caused by a broken
cable. The moment the fault location is known, the
interruption of the supply can be restored by a number of
switching operations in the MV network.
Automating the fault location detection and remote
control of the MV switch gear will reduce the outage
time.
Another advantage of instrumentation of the MV/LV
station is the possibility to realize more advanced remote
control of the public lights.
To be able to compare the solutions developed by the
coalitions two typical configurations for a KRIS system
were defined. One for a so-called non-strategic MV/LV
installation and one for a so-called strategic installation.
The requirements for a non-strategic station are stated in
Table 1. The labels E.xx in the first column refer to the
detailed descriptions in [2].
KRIS req Description
E.10 Monitor Thermal Load of transformer
E.11 Monitor Power of LV field
E.12 / E.135 Observe failure / short circuit MV cable
E.15 Register Power of Transformer
E.16 Register energy consumption
E.20 Switch Public Lighting
E.21 Monitor environment conditions station
E.22 Monitor contact state
E.23 Change contact state
E.24 Support remote monitoring
E.25 Support remote maintenance
E.27 Support local maintenance activities
Table 1: Requirements non-strategic MV/LV station
The requirements for a strategic station are the same as a
non-strategic station extended with the functionality
stated in Table 2. Basically the difference between the
configurations is the ability to control the MV fields.
Also both configurations should be prepared for Power
Quality measurement of a LV field as stated in Table 3.
KRIS req Description
E.13 Remote switching Circuit Breaker
Table 2: Extra Requirement strategic MV/LV station
KRIS req Description
E.14 Monitor Power Quality
Table 3: Requirement Power Quality
TOTAL COST OF OWNERSHIP
Although the price of the individual instrumentation
components is important, it is only a part of the total cost
of ownership (TCO) of the automated substations over
the years. To develop a tool to calculate the TCO all
aspects influencing the total costs were investigated and
categorized.
 System costs
- miscellaneous instrumentation and other
components
- housing
- assembly
 Engineering costs
- labour costs for engineering and ordering
- labour costs for configuration of hardware and
software
 Installation costs
- for installation of the system in the field
- site acceptance tests
 Maintenance costs
- maintenance cost over 15 years; for example labour
hours and replacement of battery
 Sensors costs
- prime costs for purchasing sensors
Taking into account all expenses during the systems life
time gives the possibility to validate the extra costs for
23rd International Conference on Electricity Distribution Lyon, 15-18 June 2015
Paper 1259
CIRED 2015 4/5
making the system components smart. Spreading these
costs over several years gives the possibility to compare
them with increased costs of installation and maintenance
due to the use of smart components.
The sensors to be used depend strongly on the installed
MV/LV installation and in some of the existing MV/LV
stations sensors are already installed. Therefore these
prime costs are presented in its own category.
For the solution coalition ERE developed, the separation
of the TCO over the categories is shown in Figure 3.
Figure 3: TCO Contribution per category
THE DESIGN
During Phase 2 of the project, each coalition developed
its own solution. Our coalition came up with the modular
design shown in Figure 4. The KRIS box holds all the
functionalities which are required for every RMU.
Sensors
MV Voltage
MV Current
DC-Unit Battery
Meter
LV Voltage
LV Current
Meter
Monitor/
control
Short circuit/
meter
Modbus
24Vdc
230 Vac
1 / 5 A
current
cos phi
cable temp
temperature
humidity
ambient / transformer
Ethernet
Antenna
In (4x) / Out (4x) for Public Light/Tamper
RTU
Meter
Strategic station with
additional functions
Sensors
transformer
Sensors
ambient
I cos phi Box TH BoxMS Box
KRIS Host
Figure 4: Architecture of a KRIS solution
From logistic and maintenance point of view an
advantage, because only one box type can be used for all
applications. Optional functionalities, not needed for
every RMU, are placed in separate boxes.
All boxes are interconnected by instrumentation cabling
using standardized connectors securing Modbus
communication and power supply. In this way for every
application the best combination of boxes can be chosen,
while the KRIS box is always the same.
With this design a standard configuration is offered,
independent of the installed MV/LV installation. Due to
the flexibility of the chosen system architecture,
additional wishes can be realized in an easy and cost
effective way.
Figure 5: KRIS host designed by coalition ERE
The KRIS host includes a power supply with battery
backup, which also powers the separate additional boxes.
The KRIS host itself derives its power from the sensors
used for voltage measurement. These sensors have a
build in high capacity fuse; this guarantees a save and
easy tapping of the voltage from the main bus bar without
downgrading the short circuit resistance of the
installation. They are suitable for fuses with a breaking
capacity up to 70 kA. Standard compact split-core
transformers are used for measuring the current between
the MV transformer and the LV distribution rack. The
secondary leads of these current transformers (CTs) are
prefab mounted on a special connector with an automatic
short circuit mechanism to prevent dangerous voltage
levels due to an open circuit. Also the output leads of the
easy voltage tabs with fuse are prefab mounted in the
connector. The connector, including a locking system, is
shown in Figure 5.
Not only the hardware but also the software has a
modular design. Functions can be activated or de-
activated individually. Calibration, scaling and the setting
of parameters is done centrally in the KRIS box,
including those of the separate additional boxes.
Configuring the system can thus be realized in an easy
way. This increases efficiency and reduces faults.
THE FIELD TESTS
After a short pilot every coalition installed four systems
at different locations for field testing. One of the sites that
coalition ERE equipped was situated in Steenwijk, in the
grid of Rendo, a DSO in the eastern part of the
Netherlands. During the pre-inspection of the site,
dimensions and the positions of the existing MV/LV
installation were examined. With this information the
interfaces between the KRIS system and the existing
MV/LV installation could be chosen. This included the
length of the prefab cabling to the sensors and the exact
type and size of the transformers and the voltage tabs.
Next, the complete KRIS system, including pre-mounted
sensors, was build, configured and tested in the factory.
24%
22%
20%
27%
7%
TCO coalition ERE
System
Engineering
Installation
Maintenance
Sensors
23rd International Conference on Electricity Distribution Lyon, 15-18 June 2015
Paper 1259
CIRED 2015 5/5
Installation work on site was limited to mounting the
individual boxes on the wall and installing the sensors
and cabling in the MV/LV installation. Due to the choice
of the sensors there was no need to switch off the MV/LV
installation.
Figure 6: Installed KRIS system at Rendo site
CONCLUSIONS
Facing the end of the project, the following conclusions
can already be drawn.
Total Cost of Ownership
The goal of the project was to come up with a cost
effective instrumentation of MV/LV equipment. For a
system suitable in a strategic station the results show that
a competitive TCO is put down. However for a system
suitable in a non-strategic station, the TCO does not meet
the expectations of the DCOs. How can we decrease the
TCO? With the underlying specification in mind,
lowering the prime cost of the instrumentation itself is
difficult. Improvement can be achieved by decreasing the
labour hours needed to come to a functioning system. For
example, think of standard configurations to cut back on
engineering hours.
New tools condition for success
The introduction of new technologies as part of our
solution brought us the insight that attention must be paid
to the development of new tools necessary for the
successful installation of the instrumentation.
This involves the availability of hardware tools for the
installation of new components (for example, new type of
sensors in LV-rack and transformer). But certainly also
software tools for configuring and identifying local
hardware and sensors, the local communication between
the separate boxes and remote communication with the
back office of the Operations Centre of the DCOs for
activation, registration and data transfer.
These new tools must be developed and put different
demands on the current installation personnel (additional
training necessary) but also to the logistics (and other
documentation work procedures) of the project.
This is a not to be an underestimated factor that proved to
be a strong influence on the installation time and the
success or failure of the Station Automation.
RECOMMENDATIONS
For future development recommendations can be given.
Total Cost of Ownership
For the non-functional requirements the SSS [1] does not
make distinguish between instrumentation used in
strategic and non-strategic stations. Think of
requirements regarding the environment of the system,
e.g. EMC/EMI, climate, shock and bump.
A discussion should be started to review the desired non-
functional requirements for monitoring-only systems.
This could lead to a lower prime cost of the
instrumentation itself.
Lower prices itself could open new markets and a broader
use of monitoring systems in MV/LV systems.
New possibilities with automated stations
The KRIS system is designed to realize data
communication with external systems as SCADA and
back offices. The availability of actual data gives the
possibility to realize new functionality. Some examples:
 Preventive maintenance
Locate weaknesses in the system based on slowly
changing average measurements. Think of a
transformer which slowly degenerates.
 Balance management
Knowing the actual energy flow in the grid gives the
opportunity to maintain the balance.
 Capacity management
Pricing energy use, based on time and place, gives the
opportunity to flatten the peak.
Roll out of these functions will change the business case
and can result in higher volumes.
REFERENCES
[1] Veenis, Edo, 2015, “Operational Concept
Description; MV/LV Instrumentation Cost
Reduction”, KRIS, the Netherlands,
KRIS.OCD.v1.2.2
[2] Veenis, Edo, 2015, “System Specification; MV/LV
Instrumentation Cost Reduction”, KRIS, the
Netherlands, KRIS.SSS.v1.2.2
[3] Haan de, E.J., 2012, “Betrouwbaarheid van
elektriciteitsnetten in Nederland in 2011” KEMA
Arnhem, the Netherlands, 74101378-ETD/SGO 12-
00616
[4] Website KRIS project: www.projectkris.nl

More Related Content

What's hot

Understanding Open Protocols in Building Automation
Understanding Open Protocols in Building AutomationUnderstanding Open Protocols in Building Automation
Understanding Open Protocols in Building Automation
Schneider Electric
 
The Fieldbus Diagnostics Difference
The Fieldbus Diagnostics DifferenceThe Fieldbus Diagnostics Difference
The Fieldbus Diagnostics Difference
FieldComm Group
 
Schneider Electric Smart City Success Stories (Worldwide)
Schneider Electric Smart City  Success Stories (Worldwide)Schneider Electric Smart City  Success Stories (Worldwide)
Schneider Electric Smart City Success Stories (Worldwide)
Schneider Electric India
 
The smart grid - Supply and demand side equivalent solutions
The smart grid - Supply and demand side equivalent solutionsThe smart grid - Supply and demand side equivalent solutions
The smart grid - Supply and demand side equivalent solutions
Schneider Electric
 
Grid Protection Systems - New Technologies
Grid Protection Systems - New TechnologiesGrid Protection Systems - New Technologies
Grid Protection Systems - New TechnologiesIPPAI
 
Integrating efficiency into healthcare - a life cycle approach
Integrating efficiency into healthcare  - a life cycle approachIntegrating efficiency into healthcare  - a life cycle approach
Integrating efficiency into healthcare - a life cycle approach
Schneider Electric
 
[Oil & Gas White Paper] Control Room Management - Alarm Management
[Oil & Gas White Paper] Control Room Management - Alarm Management [Oil & Gas White Paper] Control Room Management - Alarm Management
[Oil & Gas White Paper] Control Room Management - Alarm Management
Schneider Electric
 
International Standards: The Challenges for an Interoperable Smart Grid
International Standards: The Challenges for an Interoperable Smart GridInternational Standards: The Challenges for an Interoperable Smart Grid
International Standards: The Challenges for an Interoperable Smart Grid
Schneider Electric
 
A New Language for Specifying Modular Data Centers
A New Language for Specifying Modular Data CentersA New Language for Specifying Modular Data Centers
A New Language for Specifying Modular Data Centers
Schneider Electric
 
[Case Study] Stedin (The Netherlands) - Underground Self-Healing Network
[Case Study] Stedin (The Netherlands) - Underground Self-Healing Network[Case Study] Stedin (The Netherlands) - Underground Self-Healing Network
[Case Study] Stedin (The Netherlands) - Underground Self-Healing Network
Schneider Electric
 
Water solution delivers an affordable upgrade and future-proof control
Water solution delivers an affordable upgrade and future-proof controlWater solution delivers an affordable upgrade and future-proof control
Water solution delivers an affordable upgrade and future-proof control
Schneider Electric
 
Wp data center standards (final)
Wp   data center standards (final)Wp   data center standards (final)
Wp data center standards (final)
Sri Chalasani
 
[Industry report] U.S. Grid Automation Report
[Industry report] U.S. Grid Automation Report[Industry report] U.S. Grid Automation Report
[Industry report] U.S. Grid Automation Report
Schneider Electric
 
SEI Smart City Offers Catalogue
SEI Smart City Offers CatalogueSEI Smart City Offers Catalogue
SEI Smart City Offers Catalogue
Schneider Electric India
 
Managerof managerarchitecture
Managerof managerarchitectureManagerof managerarchitecture
Managerof managerarchitecture
Ganesh Kumar Veerla
 
Are your industrial networks protected...Ethernet Security Firewalls
Are your industrial networks protected...Ethernet Security Firewalls Are your industrial networks protected...Ethernet Security Firewalls
Are your industrial networks protected...Ethernet Security Firewalls
Schneider Electric
 
A framework for converting hotel guestroom energy management into ROI
A framework for converting hotel guestroom energy management into ROIA framework for converting hotel guestroom energy management into ROI
A framework for converting hotel guestroom energy management into ROI
Schneider Electric
 
Carrier ethernet-services-the-future-public-multivendor1976
Carrier ethernet-services-the-future-public-multivendor1976Carrier ethernet-services-the-future-public-multivendor1976
Carrier ethernet-services-the-future-public-multivendor1976Newlink
 
Energy solutions for federal facilities : How to harness sustainable savings ...
Energy solutions for federal facilities : How to harness sustainable savings ...Energy solutions for federal facilities : How to harness sustainable savings ...
Energy solutions for federal facilities : How to harness sustainable savings ...
Schneider Electric
 
Types of Prefabricated Modular Data Centers
Types of Prefabricated Modular Data CentersTypes of Prefabricated Modular Data Centers
Types of Prefabricated Modular Data Centers
Schneider Electric
 

What's hot (20)

Understanding Open Protocols in Building Automation
Understanding Open Protocols in Building AutomationUnderstanding Open Protocols in Building Automation
Understanding Open Protocols in Building Automation
 
The Fieldbus Diagnostics Difference
The Fieldbus Diagnostics DifferenceThe Fieldbus Diagnostics Difference
The Fieldbus Diagnostics Difference
 
Schneider Electric Smart City Success Stories (Worldwide)
Schneider Electric Smart City  Success Stories (Worldwide)Schneider Electric Smart City  Success Stories (Worldwide)
Schneider Electric Smart City Success Stories (Worldwide)
 
The smart grid - Supply and demand side equivalent solutions
The smart grid - Supply and demand side equivalent solutionsThe smart grid - Supply and demand side equivalent solutions
The smart grid - Supply and demand side equivalent solutions
 
Grid Protection Systems - New Technologies
Grid Protection Systems - New TechnologiesGrid Protection Systems - New Technologies
Grid Protection Systems - New Technologies
 
Integrating efficiency into healthcare - a life cycle approach
Integrating efficiency into healthcare  - a life cycle approachIntegrating efficiency into healthcare  - a life cycle approach
Integrating efficiency into healthcare - a life cycle approach
 
[Oil & Gas White Paper] Control Room Management - Alarm Management
[Oil & Gas White Paper] Control Room Management - Alarm Management [Oil & Gas White Paper] Control Room Management - Alarm Management
[Oil & Gas White Paper] Control Room Management - Alarm Management
 
International Standards: The Challenges for an Interoperable Smart Grid
International Standards: The Challenges for an Interoperable Smart GridInternational Standards: The Challenges for an Interoperable Smart Grid
International Standards: The Challenges for an Interoperable Smart Grid
 
A New Language for Specifying Modular Data Centers
A New Language for Specifying Modular Data CentersA New Language for Specifying Modular Data Centers
A New Language for Specifying Modular Data Centers
 
[Case Study] Stedin (The Netherlands) - Underground Self-Healing Network
[Case Study] Stedin (The Netherlands) - Underground Self-Healing Network[Case Study] Stedin (The Netherlands) - Underground Self-Healing Network
[Case Study] Stedin (The Netherlands) - Underground Self-Healing Network
 
Water solution delivers an affordable upgrade and future-proof control
Water solution delivers an affordable upgrade and future-proof controlWater solution delivers an affordable upgrade and future-proof control
Water solution delivers an affordable upgrade and future-proof control
 
Wp data center standards (final)
Wp   data center standards (final)Wp   data center standards (final)
Wp data center standards (final)
 
[Industry report] U.S. Grid Automation Report
[Industry report] U.S. Grid Automation Report[Industry report] U.S. Grid Automation Report
[Industry report] U.S. Grid Automation Report
 
SEI Smart City Offers Catalogue
SEI Smart City Offers CatalogueSEI Smart City Offers Catalogue
SEI Smart City Offers Catalogue
 
Managerof managerarchitecture
Managerof managerarchitectureManagerof managerarchitecture
Managerof managerarchitecture
 
Are your industrial networks protected...Ethernet Security Firewalls
Are your industrial networks protected...Ethernet Security Firewalls Are your industrial networks protected...Ethernet Security Firewalls
Are your industrial networks protected...Ethernet Security Firewalls
 
A framework for converting hotel guestroom energy management into ROI
A framework for converting hotel guestroom energy management into ROIA framework for converting hotel guestroom energy management into ROI
A framework for converting hotel guestroom energy management into ROI
 
Carrier ethernet-services-the-future-public-multivendor1976
Carrier ethernet-services-the-future-public-multivendor1976Carrier ethernet-services-the-future-public-multivendor1976
Carrier ethernet-services-the-future-public-multivendor1976
 
Energy solutions for federal facilities : How to harness sustainable savings ...
Energy solutions for federal facilities : How to harness sustainable savings ...Energy solutions for federal facilities : How to harness sustainable savings ...
Energy solutions for federal facilities : How to harness sustainable savings ...
 
Types of Prefabricated Modular Data Centers
Types of Prefabricated Modular Data CentersTypes of Prefabricated Modular Data Centers
Types of Prefabricated Modular Data Centers
 

Similar to CIRED1259-No Smart MV-LV station without a smart approach - final

Design of Low Cost Line Impedance Stabilization Network Using RLC Components ...
Design of Low Cost Line Impedance Stabilization Network Using RLC Components ...Design of Low Cost Line Impedance Stabilization Network Using RLC Components ...
Design of Low Cost Line Impedance Stabilization Network Using RLC Components ...
IRJET Journal
 
PV LEGAL: Key recommendations
PV LEGAL: Key recommendationsPV LEGAL: Key recommendations
PV LEGAL: Key recommendations
BISOL Solar Company
 
5 cired2013 planning of power distribution systems
5   cired2013 planning of power distribution systems5   cired2013 planning of power distribution systems
5 cired2013 planning of power distribution systemsDutch Power
 
15 03-25-wallom-cloudwatch-wp2
15 03-25-wallom-cloudwatch-wp215 03-25-wallom-cloudwatch-wp2
15 03-25-wallom-cloudwatch-wp2David Wallom
 
SCADA_SYSTEM in industrial automation .pptx
SCADA_SYSTEM in industrial automation .pptxSCADA_SYSTEM in industrial automation .pptx
SCADA_SYSTEM in industrial automation .pptx
Viju Jigajinni
 
SCADA_SYSTEM in Industrial Autiomation.pptx
SCADA_SYSTEM in Industrial Autiomation.pptxSCADA_SYSTEM in Industrial Autiomation.pptx
SCADA_SYSTEM in Industrial Autiomation.pptx
Viju Jigajinni
 
TESTING AND COMMISSIONING OF VSC HVDC SYSTEMS
TESTING AND COMMISSIONING OF VSC HVDC SYSTEMSTESTING AND COMMISSIONING OF VSC HVDC SYSTEMS
TESTING AND COMMISSIONING OF VSC HVDC SYSTEMS
Power System Operation
 
Controller selection in software defined networks using best-worst multi-crit...
Controller selection in software defined networks using best-worst multi-crit...Controller selection in software defined networks using best-worst multi-crit...
Controller selection in software defined networks using best-worst multi-crit...
journalBEEI
 
Autonomous sensor nodes for Structural Health Monitoring of bridges
Autonomous sensor nodes for Structural Health Monitoring of bridgesAutonomous sensor nodes for Structural Health Monitoring of bridges
Autonomous sensor nodes for Structural Health Monitoring of bridges
IRJET Journal
 
Requirements engineering in Fennovoima nuclear power plant program
Requirements engineering in Fennovoima nuclear power plant programRequirements engineering in Fennovoima nuclear power plant program
Requirements engineering in Fennovoima nuclear power plant program
Pekka Mäkinen
 
2018 10-distribution automation-trends-andchallenges
2018 10-distribution automation-trends-andchallenges2018 10-distribution automation-trends-andchallenges
2018 10-distribution automation-trends-andchallenges
Abhilash Gopalakrishnan
 
Sdmo telecoms-generator-solutions
Sdmo telecoms-generator-solutionsSdmo telecoms-generator-solutions
Sdmo telecoms-generator-solutions
Electrical and renewable energy engineering
 
IRJET- Build SDN with Openflow Controller
IRJET-  	  Build SDN with Openflow ControllerIRJET-  	  Build SDN with Openflow Controller
IRJET- Build SDN with Openflow Controller
IRJET Journal
 
EMBEDDED SYSTEM
EMBEDDED  SYSTEMEMBEDDED  SYSTEM
EMBEDDED SYSTEM
AIRTEL
 
Crypto Mark Scheme for Fast Pollution Detection and Resistance over Networking
Crypto Mark Scheme for Fast Pollution Detection and Resistance over NetworkingCrypto Mark Scheme for Fast Pollution Detection and Resistance over Networking
Crypto Mark Scheme for Fast Pollution Detection and Resistance over Networking
IRJET Journal
 
ISA Energy - VPS - Corporate Presentation
ISA Energy - VPS - Corporate PresentationISA Energy - VPS - Corporate Presentation
ISA Energy - VPS - Corporate PresentationNuno Torrado Francisco
 
InteGrid Scalability & Replicability results and Replication Roadmap
InteGrid Scalability & Replicability results and Replication RoadmapInteGrid Scalability & Replicability results and Replication Roadmap
InteGrid Scalability & Replicability results and Replication Roadmap
Sergio Potenciano Menci
 
Safety System Modularity
Safety System ModularitySafety System Modularity
Safety System Modularity
Fasiul Alam
 
IRJET-Complete Industrial Solution for Automation in Temperature and Humidity...
IRJET-Complete Industrial Solution for Automation in Temperature and Humidity...IRJET-Complete Industrial Solution for Automation in Temperature and Humidity...
IRJET-Complete Industrial Solution for Automation in Temperature and Humidity...
IRJET Journal
 
Performance Evolution of LTE Cellular Technology
Performance Evolution of LTE Cellular TechnologyPerformance Evolution of LTE Cellular Technology
Performance Evolution of LTE Cellular Technology
IRJET Journal
 

Similar to CIRED1259-No Smart MV-LV station without a smart approach - final (20)

Design of Low Cost Line Impedance Stabilization Network Using RLC Components ...
Design of Low Cost Line Impedance Stabilization Network Using RLC Components ...Design of Low Cost Line Impedance Stabilization Network Using RLC Components ...
Design of Low Cost Line Impedance Stabilization Network Using RLC Components ...
 
PV LEGAL: Key recommendations
PV LEGAL: Key recommendationsPV LEGAL: Key recommendations
PV LEGAL: Key recommendations
 
5 cired2013 planning of power distribution systems
5   cired2013 planning of power distribution systems5   cired2013 planning of power distribution systems
5 cired2013 planning of power distribution systems
 
15 03-25-wallom-cloudwatch-wp2
15 03-25-wallom-cloudwatch-wp215 03-25-wallom-cloudwatch-wp2
15 03-25-wallom-cloudwatch-wp2
 
SCADA_SYSTEM in industrial automation .pptx
SCADA_SYSTEM in industrial automation .pptxSCADA_SYSTEM in industrial automation .pptx
SCADA_SYSTEM in industrial automation .pptx
 
SCADA_SYSTEM in Industrial Autiomation.pptx
SCADA_SYSTEM in Industrial Autiomation.pptxSCADA_SYSTEM in Industrial Autiomation.pptx
SCADA_SYSTEM in Industrial Autiomation.pptx
 
TESTING AND COMMISSIONING OF VSC HVDC SYSTEMS
TESTING AND COMMISSIONING OF VSC HVDC SYSTEMSTESTING AND COMMISSIONING OF VSC HVDC SYSTEMS
TESTING AND COMMISSIONING OF VSC HVDC SYSTEMS
 
Controller selection in software defined networks using best-worst multi-crit...
Controller selection in software defined networks using best-worst multi-crit...Controller selection in software defined networks using best-worst multi-crit...
Controller selection in software defined networks using best-worst multi-crit...
 
Autonomous sensor nodes for Structural Health Monitoring of bridges
Autonomous sensor nodes for Structural Health Monitoring of bridgesAutonomous sensor nodes for Structural Health Monitoring of bridges
Autonomous sensor nodes for Structural Health Monitoring of bridges
 
Requirements engineering in Fennovoima nuclear power plant program
Requirements engineering in Fennovoima nuclear power plant programRequirements engineering in Fennovoima nuclear power plant program
Requirements engineering in Fennovoima nuclear power plant program
 
2018 10-distribution automation-trends-andchallenges
2018 10-distribution automation-trends-andchallenges2018 10-distribution automation-trends-andchallenges
2018 10-distribution automation-trends-andchallenges
 
Sdmo telecoms-generator-solutions
Sdmo telecoms-generator-solutionsSdmo telecoms-generator-solutions
Sdmo telecoms-generator-solutions
 
IRJET- Build SDN with Openflow Controller
IRJET-  	  Build SDN with Openflow ControllerIRJET-  	  Build SDN with Openflow Controller
IRJET- Build SDN with Openflow Controller
 
EMBEDDED SYSTEM
EMBEDDED  SYSTEMEMBEDDED  SYSTEM
EMBEDDED SYSTEM
 
Crypto Mark Scheme for Fast Pollution Detection and Resistance over Networking
Crypto Mark Scheme for Fast Pollution Detection and Resistance over NetworkingCrypto Mark Scheme for Fast Pollution Detection and Resistance over Networking
Crypto Mark Scheme for Fast Pollution Detection and Resistance over Networking
 
ISA Energy - VPS - Corporate Presentation
ISA Energy - VPS - Corporate PresentationISA Energy - VPS - Corporate Presentation
ISA Energy - VPS - Corporate Presentation
 
InteGrid Scalability & Replicability results and Replication Roadmap
InteGrid Scalability & Replicability results and Replication RoadmapInteGrid Scalability & Replicability results and Replication Roadmap
InteGrid Scalability & Replicability results and Replication Roadmap
 
Safety System Modularity
Safety System ModularitySafety System Modularity
Safety System Modularity
 
IRJET-Complete Industrial Solution for Automation in Temperature and Humidity...
IRJET-Complete Industrial Solution for Automation in Temperature and Humidity...IRJET-Complete Industrial Solution for Automation in Temperature and Humidity...
IRJET-Complete Industrial Solution for Automation in Temperature and Humidity...
 
Performance Evolution of LTE Cellular Technology
Performance Evolution of LTE Cellular TechnologyPerformance Evolution of LTE Cellular Technology
Performance Evolution of LTE Cellular Technology
 

CIRED1259-No Smart MV-LV station without a smart approach - final

  • 1. 23rd International Conference on Electricity Distribution Lyon, 15-18 June 2015 Paper 1259 CIRED 2015 1/5 NO SMART MV/LV STATION WITHOUT A SMART APPROACH Elise MORSKIEFT Gerrit SCHARRENBERG Eaton Industries BV – the Netherlands Rendo – the Netherlands EliseMorskieft@eaton.com gscharrenberg@rendo.nl Felix JANSSEN Adriaan van der SCHAAR Alex van de SCHOOTBRUGGE Reewoud Energietechniek BV Eleq BV Eaton Industries BV the Netherlands the Netherlands the Netherlands felix.janssen@reewoud.nl adriaan.vdschaar@eleq.com AlexvandeSchootbrugge@eaton.com ABSTRACT At the end of 2014, at several different locations in the Netherlands, pilot systems for automated substations were installed. These pilot systems are the result of the final phase of the KRIS project, an initiative of multiple Distribution System Operators (DSOs) in the Netherlands, which started in 2012. What makes the KRIS Project unique is that these DSOs worked closely together to establish a list of common functional requirements. Then the suppliers brought in their experience and knowledge regarding the technical feasibility and cost aspect of those requirements. For engineering the V-model was used. During the specification phase all parties worked together, sharing information with a cooperative mentality. Throughout the pilot phase suppliers, forming coalitions, were challenged to work on their own solution. The goal of the project was to come up with a cost effective instrumentation of MV/LV equipment. Facing the end of the project, the results show a competitive TCO for instrumentation used in so-called strategic MV/LV stations. For non-strategic stations the TCO does not yet meet the expectations. This paper is written by coalition ERE, one of the coalitions formed by Eleq, Reewoud Energietechniek and Eaton Industries. INTRODUCTION Starting in 2012 multiple Distribution System Operators (DSOs) in the Netherlands recognized that the energy transition requires management of all elements in the energy network. Therefore intelligent components will be required on all secondary distribution levels, especially in the MV/LV substations, the so called Ring Main Units (RMUs). Due to the high costs of such instrumentation, a large scale roll-out was financially not feasible. In addition, the suppliers were not aware of the DSOs requirements for these components. The result: no match between DSOs demands and the suppliers’ solutions. To break this deadlock, project KRIS was initiated by the DSOs. The goal of KRIS is defined as to create an open innovative and competitive instrumentation market aiming at low cost and modular MV/LV instrumentation, by stimulating close cooperation between demand and supply chains. ORGANISATION KRIS PROJECT The participants in the KRIS project, as shown in Figure 1, can be grouped in DSOs and Suppliers, supported by Avans, an academic Educational Institute and Technolution, a technology partner specialized in enabling the interpretative step from business to the right technological solution. DSO’s Knowledge Consultancy Figure 1: Participants of the KRIS project The project is structured as follows:  steering committee, formed of representatives of all parties  users group, formed by the DSOs  suppliers group, working together in coalitions The steering committee acts as the decision-making platform, has periodical meetings and informs the users group about the progress of the project. PROJECT PHASING To reach the goal of the project, come to a cost effective instrumentation of MV/LV equipment, a structured approach for product development, as shown in Figure 2, was followed. Figure 2: Systems Engineering V-model
  • 2. 23rd International Conference on Electricity Distribution Lyon, 15-18 June 2015 Paper 1259 CIRED 2015 2/5 Phase 1 – Specifications In Phase 1, plenary meetings with all participants were held to build the concept for the specifications document. With the outcome of these sessions, the Operational Concept Description (OCD) [1] was set up. This was the start document and describes all global requirements. From this, the System/Sub system Specification (SSS) [2] was written. This document specifies the requirements for a system or subsystem and the methods to be used. To fill in all the details of the specifications a number of Working Groups (WGs) were formed, with specialists from both the DSOs and the suppliers. Each Working Group had its own specialized tasks.  WG Use Cases - Describe the use cases for MV/LV substations. - Prioritize the described functionalities according to the needs of all DSOs.  WG Security - Describe the security demands. - Investigate available information and requirements.  WG Key Figures - Investigate the installed base of MV/LS stations in the Netherlands in terms of total units, configuration settings, and plans for replacement and/or retrofit.  WG Environment - Create an overview of existing projects and developments in the field of instrumentation MV/LV stations. - What are the lessons learned, what should we take into account?  WG Measurements - Specify the technical requirements underlying the measurements needed to realize the use cases.  WG Installation and Maintenance - Investigate the minimum system requirements in terms of safety, legalisation, standards, climate, environment, accessibility, electricity and mechanics. - Describe a typical MV/LV installation.  WG Data Communication - Investigate the needs for Data Communication. - Set up a long list with possible Data Communication Protocols.  WG Architecture - Describe the preferred system architecture in terms of structure, behaviour, modularity and interfaces, both for hardware and software.  WG Total Cost of Ownership (TCO) - Develop a tool to validate the costs of acquisition, installation and maintenance, taking into consideration the entire life time of the system.  WG Pilots & Test fields - Coordinate the implementation and instalment at the test field locations of the designed systems. Phase 2 – Development In Phase 2, the suppliers formed coalitions to develop a modular system designed to meet the requirements stated in the OCD [1] and SSS [2]. Each coalition came up with its own product. One of the requirements was that the instrumentation should be added to existing MV/LV systems. Therefore it was very important to have a flexible solution, with open interfaces to its surrounding. After testing the developed systems in the laboratory of one of the DSOs the solutions were then reviewed and released for the field tests during the pilot phase. Phase 3 – Pilots In Phase 3, pilot systems were installed in existing MV/LV stations at different locations throughout the Netherlands. During the installation of the systems the impact of installing instrumentation in an existing MV/LV station was investigated. REQUIREMENTS In the SSS document [2] a set of in total 212 requirements were specified, divided under 13 subjects.  Required system states - Specifies the limited number of clearly distinguishable states: Initializing, Fully Available, Reduced Availability and Not Available.  System capability requirements - Specifies the basic functionality as Data Acquisition, Control, Process Data, Data Storage, Data Exchange, Configuration, Logging, Software, (Self) Test functionality, Diagnostics and Power Supply.  System external interface requirements - Specifies the interfaces to external equipment in terms of configuration, software, data exchange and maintenance.  System internal interface requirements - Specifies the interface between the sub systems and MV/LV installation.  System internal data requirements - Specifies the integrity of the internal system data in terms of protection against loss, accessibility and privacy.  Adaptation Requirements - Specifies the ability of the system to be used in existing and new MV/LV stations.  Safety Requirements - Specifies the systems safety requirements.  Security and Privacy Protection requirements - Specifies the security and privacy aspects of all data  System Environment requirements. - Specifies all requirements regarding the environment of the system, e.g. EMC/EMI, climate, shock and bump.  Computer Resource requirements - Specifies the computer hardware and software, including communication interfaces.
  • 3. 23rd International Conference on Electricity Distribution Lyon, 15-18 June 2015 Paper 1259 CIRED 2015 3/5  System Quality Factors - Specifies the functionality to monitor the quality of the MV and LV power, but also the requirements regarding reliability, availability and upkeep.  Restrictions Regarding Design and Production - Specifies the non-functional requirements regarding modularity, expandability, scalability, reusability, interconnectivity and future proof. But also requirements regarding installation and maintenance.  Personnel Related Requirements - Specifies the role and background of the personnel working with the system. BENCHMARK The SSS document [2] contains of a vast number of requirements. Depending on the level of automation and the location of the MV/LV station not all requirements are always relevant. To be able to prioritize the requirements, all DSOs shared their vision and motivation regarding instrumentation of MV/LV stations. One of the drivers to use instrumentation in MV/LV stations is to reduce the outage time for the end user. Common used indicators to calculate the outage time are SAIFI (System Average Interruption Frequency Index) and SAIDI (System Average Interruption Duration Index). In the period from 2001-2011 the average outage time for an LV customer in the Netherlands was 28 minutes per year, 64 % of this was due to breakdowns in the MV network [3]. In the Netherlands 95% of the MV networks are 10 kV with underground cables. The majority of outages due to breakdown in the MV network are caused by a broken cable. The moment the fault location is known, the interruption of the supply can be restored by a number of switching operations in the MV network. Automating the fault location detection and remote control of the MV switch gear will reduce the outage time. Another advantage of instrumentation of the MV/LV station is the possibility to realize more advanced remote control of the public lights. To be able to compare the solutions developed by the coalitions two typical configurations for a KRIS system were defined. One for a so-called non-strategic MV/LV installation and one for a so-called strategic installation. The requirements for a non-strategic station are stated in Table 1. The labels E.xx in the first column refer to the detailed descriptions in [2]. KRIS req Description E.10 Monitor Thermal Load of transformer E.11 Monitor Power of LV field E.12 / E.135 Observe failure / short circuit MV cable E.15 Register Power of Transformer E.16 Register energy consumption E.20 Switch Public Lighting E.21 Monitor environment conditions station E.22 Monitor contact state E.23 Change contact state E.24 Support remote monitoring E.25 Support remote maintenance E.27 Support local maintenance activities Table 1: Requirements non-strategic MV/LV station The requirements for a strategic station are the same as a non-strategic station extended with the functionality stated in Table 2. Basically the difference between the configurations is the ability to control the MV fields. Also both configurations should be prepared for Power Quality measurement of a LV field as stated in Table 3. KRIS req Description E.13 Remote switching Circuit Breaker Table 2: Extra Requirement strategic MV/LV station KRIS req Description E.14 Monitor Power Quality Table 3: Requirement Power Quality TOTAL COST OF OWNERSHIP Although the price of the individual instrumentation components is important, it is only a part of the total cost of ownership (TCO) of the automated substations over the years. To develop a tool to calculate the TCO all aspects influencing the total costs were investigated and categorized.  System costs - miscellaneous instrumentation and other components - housing - assembly  Engineering costs - labour costs for engineering and ordering - labour costs for configuration of hardware and software  Installation costs - for installation of the system in the field - site acceptance tests  Maintenance costs - maintenance cost over 15 years; for example labour hours and replacement of battery  Sensors costs - prime costs for purchasing sensors Taking into account all expenses during the systems life time gives the possibility to validate the extra costs for
  • 4. 23rd International Conference on Electricity Distribution Lyon, 15-18 June 2015 Paper 1259 CIRED 2015 4/5 making the system components smart. Spreading these costs over several years gives the possibility to compare them with increased costs of installation and maintenance due to the use of smart components. The sensors to be used depend strongly on the installed MV/LV installation and in some of the existing MV/LV stations sensors are already installed. Therefore these prime costs are presented in its own category. For the solution coalition ERE developed, the separation of the TCO over the categories is shown in Figure 3. Figure 3: TCO Contribution per category THE DESIGN During Phase 2 of the project, each coalition developed its own solution. Our coalition came up with the modular design shown in Figure 4. The KRIS box holds all the functionalities which are required for every RMU. Sensors MV Voltage MV Current DC-Unit Battery Meter LV Voltage LV Current Meter Monitor/ control Short circuit/ meter Modbus 24Vdc 230 Vac 1 / 5 A current cos phi cable temp temperature humidity ambient / transformer Ethernet Antenna In (4x) / Out (4x) for Public Light/Tamper RTU Meter Strategic station with additional functions Sensors transformer Sensors ambient I cos phi Box TH BoxMS Box KRIS Host Figure 4: Architecture of a KRIS solution From logistic and maintenance point of view an advantage, because only one box type can be used for all applications. Optional functionalities, not needed for every RMU, are placed in separate boxes. All boxes are interconnected by instrumentation cabling using standardized connectors securing Modbus communication and power supply. In this way for every application the best combination of boxes can be chosen, while the KRIS box is always the same. With this design a standard configuration is offered, independent of the installed MV/LV installation. Due to the flexibility of the chosen system architecture, additional wishes can be realized in an easy and cost effective way. Figure 5: KRIS host designed by coalition ERE The KRIS host includes a power supply with battery backup, which also powers the separate additional boxes. The KRIS host itself derives its power from the sensors used for voltage measurement. These sensors have a build in high capacity fuse; this guarantees a save and easy tapping of the voltage from the main bus bar without downgrading the short circuit resistance of the installation. They are suitable for fuses with a breaking capacity up to 70 kA. Standard compact split-core transformers are used for measuring the current between the MV transformer and the LV distribution rack. The secondary leads of these current transformers (CTs) are prefab mounted on a special connector with an automatic short circuit mechanism to prevent dangerous voltage levels due to an open circuit. Also the output leads of the easy voltage tabs with fuse are prefab mounted in the connector. The connector, including a locking system, is shown in Figure 5. Not only the hardware but also the software has a modular design. Functions can be activated or de- activated individually. Calibration, scaling and the setting of parameters is done centrally in the KRIS box, including those of the separate additional boxes. Configuring the system can thus be realized in an easy way. This increases efficiency and reduces faults. THE FIELD TESTS After a short pilot every coalition installed four systems at different locations for field testing. One of the sites that coalition ERE equipped was situated in Steenwijk, in the grid of Rendo, a DSO in the eastern part of the Netherlands. During the pre-inspection of the site, dimensions and the positions of the existing MV/LV installation were examined. With this information the interfaces between the KRIS system and the existing MV/LV installation could be chosen. This included the length of the prefab cabling to the sensors and the exact type and size of the transformers and the voltage tabs. Next, the complete KRIS system, including pre-mounted sensors, was build, configured and tested in the factory. 24% 22% 20% 27% 7% TCO coalition ERE System Engineering Installation Maintenance Sensors
  • 5. 23rd International Conference on Electricity Distribution Lyon, 15-18 June 2015 Paper 1259 CIRED 2015 5/5 Installation work on site was limited to mounting the individual boxes on the wall and installing the sensors and cabling in the MV/LV installation. Due to the choice of the sensors there was no need to switch off the MV/LV installation. Figure 6: Installed KRIS system at Rendo site CONCLUSIONS Facing the end of the project, the following conclusions can already be drawn. Total Cost of Ownership The goal of the project was to come up with a cost effective instrumentation of MV/LV equipment. For a system suitable in a strategic station the results show that a competitive TCO is put down. However for a system suitable in a non-strategic station, the TCO does not meet the expectations of the DCOs. How can we decrease the TCO? With the underlying specification in mind, lowering the prime cost of the instrumentation itself is difficult. Improvement can be achieved by decreasing the labour hours needed to come to a functioning system. For example, think of standard configurations to cut back on engineering hours. New tools condition for success The introduction of new technologies as part of our solution brought us the insight that attention must be paid to the development of new tools necessary for the successful installation of the instrumentation. This involves the availability of hardware tools for the installation of new components (for example, new type of sensors in LV-rack and transformer). But certainly also software tools for configuring and identifying local hardware and sensors, the local communication between the separate boxes and remote communication with the back office of the Operations Centre of the DCOs for activation, registration and data transfer. These new tools must be developed and put different demands on the current installation personnel (additional training necessary) but also to the logistics (and other documentation work procedures) of the project. This is a not to be an underestimated factor that proved to be a strong influence on the installation time and the success or failure of the Station Automation. RECOMMENDATIONS For future development recommendations can be given. Total Cost of Ownership For the non-functional requirements the SSS [1] does not make distinguish between instrumentation used in strategic and non-strategic stations. Think of requirements regarding the environment of the system, e.g. EMC/EMI, climate, shock and bump. A discussion should be started to review the desired non- functional requirements for monitoring-only systems. This could lead to a lower prime cost of the instrumentation itself. Lower prices itself could open new markets and a broader use of monitoring systems in MV/LV systems. New possibilities with automated stations The KRIS system is designed to realize data communication with external systems as SCADA and back offices. The availability of actual data gives the possibility to realize new functionality. Some examples:  Preventive maintenance Locate weaknesses in the system based on slowly changing average measurements. Think of a transformer which slowly degenerates.  Balance management Knowing the actual energy flow in the grid gives the opportunity to maintain the balance.  Capacity management Pricing energy use, based on time and place, gives the opportunity to flatten the peak. Roll out of these functions will change the business case and can result in higher volumes. REFERENCES [1] Veenis, Edo, 2015, “Operational Concept Description; MV/LV Instrumentation Cost Reduction”, KRIS, the Netherlands, KRIS.OCD.v1.2.2 [2] Veenis, Edo, 2015, “System Specification; MV/LV Instrumentation Cost Reduction”, KRIS, the Netherlands, KRIS.SSS.v1.2.2 [3] Haan de, E.J., 2012, “Betrouwbaarheid van elektriciteitsnetten in Nederland in 2011” KEMA Arnhem, the Netherlands, 74101378-ETD/SGO 12- 00616 [4] Website KRIS project: www.projectkris.nl