SlideShare a Scribd company logo
IOSH Managing Safely
IOSH Managing Safely - Project
Introduction
As part of the Managing Safely course, you have to complete a project and have it
assessed. You will be expected to carry out a risk assessment based on your own
work environment. You need to record the results on the attached sheets and submit
them for marking. Do not submit any additional material in support of your project work
as only the six parts of the project will be assessed. The project can be word
processed or hand written.
When you have completed your work you can upload it via the “Upload Your Project”
section of the IOSH Managing Safely course, or you can post it to:
Tamara Pelley
Santia Training Services
Santia House
Parc Nantgarw
Cardiff
CF15 7QX
Candidates Name: Chris Withers
There is a two week time limit for the return of the project. Your project must be
completed and returned by:
Course Code: H Return Date: 06/06/16
© Santia 2014 - restricted use only Page 1 of 16
Sales ref: sc/1013/v3.2
IOSH Managing Safely
Instructions
Please read all of the instructions before starting work on your project.
The project is broken down into a number of parts. Please complete each section as
detailed below.
Part 1 - description of the work tasks that are your responsibility
Record a brief description of all the work tasks within your work environment including:
 Description/labelled sketch of the location(s).
 People who work in or visit the area on a regular basis or from time to time.
(Think about the different groups of people who may be in the area and how
often they might be there).
 Permanent and temporary items of equipment and substances.
 Activities carried out within your work environment.
Part 2 - a hazard checklist of the location(s)
Record a brief description of three location hazards that may arise in your work
environment. For example, car park, stairs, uneven floor. For each of these hazards
please include:
 A description of the location.
 A description of the hazard – in relation to the location.
 The number and occupation of people who could be affected by the hazard – in
relation to the location.
 Whether a risk assessment is recommended.
Part 3 - a hazard checklist of permanent and/or temporary items of equipment
and substances used in your work environment
Record a brief description of three hazards that may arise from equipment or
substances used. For each of these hazards please include:
 A description of permanent and/or temporary items of equipment and
substances used.
 A description of the hazard – in relation to the equipment/substance.
 The number and occupation of people who could be affected by the hazard – in
relation to the equipment/substance.
© Santia 2014 - restricted use only Page 2 of 16
Sales ref: sc/1013/v3.2
IOSH Managing Safely
 Whether a risk assessment is recommended.
Part 4 - a hazard checklist of the activities carried out within your work
environment
Record a brief description of three hazards that may arise from within your work
environment. For each of these hazards please include:
 A description of the work activity.
 A description of the hazard – in relation to the work activity.
 The number and occupation of people who could be affected by the hazard – in
relation to the work activity.
Note: for the purpose of this exercise all three activity hazards that you are
assessing on part 4 must require a risk assessment.
Part 5 - carrying out a risk assessment
Please carry out a risk assessment on all three of the activity hazards you have listed
on part 4. Please make sure you include:
 A description of the work activity.
 A description of the hazard, hazardous event and expected consequence – in
relation to the work activity.
 The number and occupation of people affected – in relation to the work activity.
 An assessment of risk (please use the 5 x 5 matrix) – in relation to the work
activity.
 Whether risk controls are required.
Note: for the purpose of this exercise all three activity hazards that you are
assessing on part 5 must require risk controls.
Part 6 - risk control recommendations
Please complete the risk control form for all three activity hazards you have listed on
part 4. Please make sure you include:
 A description of the work activity and risk level from the risk assessment.
 Existing risk controls.
 Any further risk controls required – in relation to the work activity.
 The residual risk (please use the 5 x 5 matrix) – in relation to the work activity.
© Santia 2014 - restricted use only Page 3 of 16
Sales ref: sc/1013/v3.2
IOSH Managing Safely
 A description of the type of monitoring required and how often – in relation to the
residual risk.
Note: where you have large numbers of hazards in your work environment you will not
have space to record them all. In these circumstances, select a representative sample
of hazards for the purposes of this project and record only these. Remember that only
three hazards are required for parts 2, 3, and 4.
Each part has a maximum number of marks which can be awarded and details are
given in the table below:
Part Maximum marks
1 18
2 16
3 16
4 13
5 30
6 30
Total 123
Minimum mark 62
Finally, before returning your project, check that your name, the end of course date, the
name of your company, the site name and the name of your training provider are
recorded on the first sheet.
Please also ensure that you sign each sheet to confirm that the work you submit is your
own.
Please note: the small square boxes in the bottom right hand corner of each
section on parts 2 to 6 are for the markers use only.
© Santia 2014 - restricted use only Page 4 of 16
Sales ref: sc/1013/v3.2
IOSH Managing Safely
Part 1 - description of the work tasks that are your responsibility
(continued on the next page)
Delegate Name: Chris Withers End of course date:
Company: K.c.t Energy Site Name: South coast offshore
wind farm
Training provider:Santia Training Services
A description / sketch of the location(s)
The location is offshore wind farm based on the south coast of England asset location is H09
distance approximately 12 kilometres off the Brighton coast line.
Confined
space
The confined space will be in side the monapile just above sea level and we will be working on a
platform that's in the monepile, access to the turbine and different levels on the tp will be by
ladder all personnel to where harness and correct ppe.
A description of the people who work in or visit the area on a regular basis or from
time to time.
The team consists of one supervisor who will supervise the work,
One client rep who will monitor the work,
One top man who will monitor gas detectors and personnel log data board for confined space
entry
4 bolting technicians to carry out the proposed work
Maximum of 3 personnel to work in confined space, there will be no one else present on the
offshore installation.
There will be a captain and deck hand present on the support vessel who will support us.
There will be further contractors to visit the asset when they are required for further
installation work. Not while our work is carried out.
© Santia 2014 - restricted use only Page 5 of 16
Sales ref: sc/1013/v3.2
Marks
allocated
Ho9
IOSH Managing Safely
Please sign to confirm that this is your own work …...........................
Part 1 - description of the work tasks that are your responsibility
A description of permanent and temporary pieces of equipment and substances
used in your work environment
All work will be carried out inside a confined space within the monopile of an offshore wind
turbine foundation. equipment being used,
hydraulic tension heads
hydraulic hoses
pneumatic compressor
emergency escape sets
gas detectors
rigging of electric ventilation system
Tp davit crane
Portable davit crane
pulley systems
compressed air
hydraulic fluid.
Generators
compressor
ladders
inertia reel
communication radios
Transport all equipment from boat to offshore installation using tp davit crane (lifting
operations)
We will be running 13 tension heads on 13 bolts that will be connected via hydraulic hoses and
daisy chained in a 1-7 sequence around the monapile, the heads will be functioned by the
pneumatic compressor which will feed hydraulic oil too each head to tension each bolt, the
ventilation system will be put in place to extract any UN-wanted gases and too feed fresh air
into the confined space. Escapes sets too provide fresh air in case of evacuation or rescue. also
having 4 gas detectors to monitor the atmosphere to detect any gases (top man). We will also
have too rig a portable davit crane to lift equipment within the turbine foundations, fall arrest
systems will be put in place above each ladder too prevent any falls from height,
© Santia 2014 - restricted use only Page 6 of 16
Sales ref: sc/1013/v3.2
Marks
allocated
IOSH Managing Safely
A description of the activities carried out within your work environment
Before transferring from boat too offshore installation all equipment must be rigged ready for
lifting.
The generator must be powered up, one technician too stay on vessel too assit deckhand with
lift operations.
All other technicians transfer to offshore installation.
We use power from the boat to operate tp davit crane.
All equipment too be lifted from support vessel using tp davit crane and use pully system if
needed.
Set up of portable davit crane and ventilation system for confined space entry.
Test the confined space area for gases and o2 levels.
Once safe too enter then crane all tension heads, compressor, lighting, and evacuation sets too
confined space area. Ready for tensioning tp bolts.
Monitoring the atmosphere for gases every 15 minutes taking regular intervals to avoid any
long periods of time in confined area.
Working at height will have too be done from transferring too different levels within the the
turbine foundations,
Please sign to confirm that this is your own work ……………………………………
© Santia 2014 - restricted use only Page 7 of 16
Sales ref: sc/1013/v3.2
IOSH Managing Safely
Hazard Checklist: Location(s) Part 2
The location(s) you manage
Company K.c.t Energy Department O&M
Description of the
location
Description of the hazard
(in relation to the location)
Number and occupation of people
affected (in relation to the location)
Risk
assessment
recommend
ed?
(If no, please
explain)
Lifting operations between
Support Vessel
and Offshore installation
Lifting activities from vessel too
offshore installation using tp davit
crane, theres a risk of falling objects,
manual handling, environment, (e.g
weather)
9 perssonels including
7 Offshore Technicians
1 Support Vessel Deckhand
1 Support Vessel Captain
 yes
Climbing ladders
Transfering from vessl to offshore
installation and moving from
diffeernt levels within the turbine
All 7 offshore technicans and 1
deckhand assisting us transfering  yes
Confined space
The confined space is located within
the wind turbine foundation with the
likelihood of h2s gases present.
All 7 Offshore Technicians who will be
working in and around the confined
space
 yes
© Santia 2014 - restricted use only Page 8 of 16
Sales ref: sc/1013/v3.2
IOSH Managing Safely
Please sign to confirm that this is your own work ……………………………………………………
© Santia 2014 - restricted use only Page 9 of 16
Sales ref: sc/1013/v3.2
IOSH Managing Safely
Hazard Checklist: Equipment and Substances Part 3
Permanent and temporary pieces of equipment and substances used in the work environment
Company K.c.t Energy Department O&M Site name: South coast offshore
wind farm
Description of the
equipment / substances
Description of the hazard
(in relation to the
equipment/substance)
Number and occupation of people
affected
(in relation to the equipment/substance)
Risk
assessmen
t
recommen
ded?
(If no, please
explain)
Pneumatic hydraulic pump for
tensioning bolts.
(compressed air)
vessel generator supplying
compressed air , will have a
pressurized system, compressor
malfunction,leaks, leaking oil,
explosion. Struck by unsecured
airlines
7 offshore technicians and
1 support vessel deckhand assisting
with the supply of compressed air.
 yes
Hydraulic oil Leaks and spills are more likely
under pressurized systems,
6 offshore technicians who assist in the
work carried out,
 yes
Davit Crane Heavy lifting to and from vessel to
installation, risk of fallen objects,
stability of the load. Collisions,
failure of lifting equipment,
9 personnel
7 Offshore Technicians.
1 Support Vessel Deckhand and captain
both working on vessel
 yes
© Santia 2014 - restricted use only Page 10 of 16
Sales ref: sc/1013/v3.2
IOSH Managing Safely
lifting operator, electric shock,
Please sign to confirm that this is your own work ……………………………………………
© Santia 2014 - restricted use only Page 11 of 16
Sales ref: sc/1013/v3.2
IOSH Managing Safely
Hazard Checklist: Activities Part 4
Activities carried out within your work environment
Note: for the purpose of this exercise, all three activity hazards must require a risk assessment.
Company K.c.t Energy Department O&M Site name: South coast offshore
wind farm.
Description of the work
activity
Description of the hazard
(in relation to the work activity)
Number and occupation of people
affected (in relation to the work activity)
Risk
assessmen
t
recommen
ded?
Working within confined space
where h2s will be present .
H2s gas will be present all personnel
could be exposed to it, and the
likelihood of explosion,
All technicians in and around the
confined space could come into contact.
7 offshore technicians
√ yes
Installing the Portable davit
crane
Open hatches for access and In-
Correct installation of the davit crane
would result in equipment failure,
falling objects and injury and
damaged to property. Correct
training would be advised.
7 offshore technicians working within the
area will be affected,. √ yes
© Santia 2014 - restricted use only Page 12 of 16
Sales ref: sc/1013/v3.2
IOSH Managing Safely
Climbing ladders which will be
common practice within work
offshore work environment,
Ladders will be used to transfer too
the offshore installation from the
boat, and accessing different levels
of the the offshore turbine
All technicians transferring and one deck
hand assisting the technicians to safely
transfer,
√ yes
Please sign to confirm that this is your own work ………………………………………………………
© Santia 2014 - restricted use only Page 13 of 16
Sales ref: sc/1013/v3.2
IOSH Managing Safely
Risk Assessment Form Part 5
Company Department Site name:South coast offshore
wind farm
Note: For the purpose of this exercise, all three activity hazards must require risk controls.
Work
activity
Hazard, hazardous event and
expected consequence
(in relation to the work activity)
People affected
(in relation to the
work activity)
Assessment of Risk Are Risk
Controls
Required?
Likelihood
level
Conseque
nce level
Risk level
Confined
space work
in offshore
wind
turbine
foundation
- H2s gas present.
 Highly explosive
 toxic inhalation
 severe illness or death
Occupation:
offshore
technicians.
Number: 7
4 5 20
√ yes
Installation
of portable
crane
 Open hatches
 incorrect installation
 fallen objects and slip trips
and falls,
 death or injury
Occupation:
offshore
technicians.
Number:7
3 4 12
√ yes
Climbing
ladders
 Risk of falls
 risk of falls if procedures not
followed,
 serious injury or death
Occupation:
offshore
technicians and
deckhand
Number:8
3 4 12
√ yes
© Santia 2014 - restricted use only Page 14 of 16
Sales ref: sc/1013/v3.2
IOSH Managing Safely
Date: Time: Review period: Date of next review:
Assessor's name: Position: Signature:
Please sign to confirm that this is your own work …………………………………………………….
Risk Control Form Part 6
Company K.c.t Energy Department O&M Site name: South coast offshore wind
farm
Work
activity
and
risk
level
(from
risk
assess
ment
form)
Existing Risk Controls
(in relation to work activity)
Further risk
controls required
(in relation to work
activity)
Residual Risk
(in relation to work activity)
Description of
monitoring
required
(in relation to
residual risk)
Probable
Likelihood
Potential
Consequence
New Risk Level
Risk
level:
20
Correct training, Monitor
atmosphere with gas
monitors. Ventilation with
fresh air and extraction,
Access too escape
sets and rescue
equipment, tripod,
2 4 8
Frequency:
© Santia 2014 - restricted use only Page 15 of 16
Sales ref: sc/1013/v3.2
x =
IOSH Managing Safely
Risk
level:
12
competent persons,
harness and lanyards must
be worn at all time, for fall
protection
On the job training,
full ppe (helmet),
clear instructions
on ow too install
davit, tool box talks
1 2 4 Frequency:
Risk
level:
12
Working at height training,
climbing gloves harness
with fall protection lanyards
and helmets
Inertia fall arrest
must be in place
and used at all
times
1 2 4
Frequency:
Date Time: Review period: Date of next review:
Assessor's name: Position: Signature:
Please sign to confirm that this is your own work ………………………………………………………..
© Santia 2014 - restricted use only Page 16 of 16
Sales ref: sc/1013/v3.2

More Related Content

What's hot

Weekly air compressor check list
Weekly air compressor check listWeekly air compressor check list
Weekly air compressor check list
Azmeel Contracting Company
 
Portable tools risk assessment
Portable tools risk assessment Portable tools risk assessment
Portable tools risk assessment
Nidhin Sajeevan
 
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh RajputJob Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
Gaurav Singh Rajput
 
Working at height slides
Working at height slidesWorking at height slides
Working at height slides
kingsley okeke.
 
Lifting Operation Safety ppt.pptx
Lifting Operation Safety ppt.pptxLifting Operation Safety ppt.pptx
Lifting Operation Safety ppt.pptx
VasudevaRajuDantulur1
 
Job safety Analysis
Job safety Analysis Job safety Analysis
Job safety Analysis
Deepu Rajan
 
AUXILIARY CRANE INSPECTION CHECKLIST Form # HSEQ - AC Rev 2.docx
AUXILIARY CRANE INSPECTION CHECKLIST Form # HSEQ - AC  Rev 2.docxAUXILIARY CRANE INSPECTION CHECKLIST Form # HSEQ - AC  Rev 2.docx
AUXILIARY CRANE INSPECTION CHECKLIST Form # HSEQ - AC Rev 2.docx
Dwarika Bhushan Sharma
 
Lifting plan template
Lifting plan templateLifting plan template
Lifting plan template
Sergio Augusto Esteves
 
3 emergency management risk assessment templates
3 emergency management risk assessment templates3 emergency management risk assessment templates
3 emergency management risk assessment templates
Dwarika Bhushan Sharma
 
Motor vehicle Mechanical repair workshop Risk assessment, safety engineering ...
Motor vehicle Mechanical repair workshop Risk assessment, safety engineering ...Motor vehicle Mechanical repair workshop Risk assessment, safety engineering ...
Motor vehicle Mechanical repair workshop Risk assessment, safety engineering ...
Tarun Kumar Cheddy
 
Near miss awareness for Petroleum Oil Refinery
Near miss awareness  for Petroleum Oil RefineryNear miss awareness  for Petroleum Oil Refinery
Near miss awareness for Petroleum Oil Refinery
ASHOK KUMAR SINGH
 
RA for Hot works at MOE-Ghim Moh (Ceiling support works).pdf
RA for Hot works at MOE-Ghim Moh (Ceiling support works).pdfRA for Hot works at MOE-Ghim Moh (Ceiling support works).pdf
RA for Hot works at MOE-Ghim Moh (Ceiling support works).pdf
MohPhoolay
 
Water cooler monthly
Water cooler monthlyWater cooler monthly
Water cooler monthly
Azmeel Contracting Company
 
Operator Training
Operator TrainingOperator Training
Operator Training
DariusDelon
 
Permit to work training
Permit to work trainingPermit to work training
Permit to work training
Karnav Rana
 
Work Permit System
Work Permit SystemWork Permit System
Work Permit System
Gagan Tanwar
 
Basic safety orientation training
Basic safety orientation trainingBasic safety orientation training
Basic safety orientation training
Tony Bertram
 
Forklift safety
Forklift safetyForklift safety
Forklift safety
shree
 
25 demolition of existing concrete structures risk assessment templates
25 demolition of existing concrete structures risk assessment templates25 demolition of existing concrete structures risk assessment templates
25 demolition of existing concrete structures risk assessment templates
Dwarika Bhushan Sharma
 
New Employee Orientation 05
New Employee Orientation 05New Employee Orientation 05
New Employee Orientation 05
txsafety1
 

What's hot (20)

Weekly air compressor check list
Weekly air compressor check listWeekly air compressor check list
Weekly air compressor check list
 
Portable tools risk assessment
Portable tools risk assessment Portable tools risk assessment
Portable tools risk assessment
 
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh RajputJob Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
 
Working at height slides
Working at height slidesWorking at height slides
Working at height slides
 
Lifting Operation Safety ppt.pptx
Lifting Operation Safety ppt.pptxLifting Operation Safety ppt.pptx
Lifting Operation Safety ppt.pptx
 
Job safety Analysis
Job safety Analysis Job safety Analysis
Job safety Analysis
 
AUXILIARY CRANE INSPECTION CHECKLIST Form # HSEQ - AC Rev 2.docx
AUXILIARY CRANE INSPECTION CHECKLIST Form # HSEQ - AC  Rev 2.docxAUXILIARY CRANE INSPECTION CHECKLIST Form # HSEQ - AC  Rev 2.docx
AUXILIARY CRANE INSPECTION CHECKLIST Form # HSEQ - AC Rev 2.docx
 
Lifting plan template
Lifting plan templateLifting plan template
Lifting plan template
 
3 emergency management risk assessment templates
3 emergency management risk assessment templates3 emergency management risk assessment templates
3 emergency management risk assessment templates
 
Motor vehicle Mechanical repair workshop Risk assessment, safety engineering ...
Motor vehicle Mechanical repair workshop Risk assessment, safety engineering ...Motor vehicle Mechanical repair workshop Risk assessment, safety engineering ...
Motor vehicle Mechanical repair workshop Risk assessment, safety engineering ...
 
Near miss awareness for Petroleum Oil Refinery
Near miss awareness  for Petroleum Oil RefineryNear miss awareness  for Petroleum Oil Refinery
Near miss awareness for Petroleum Oil Refinery
 
RA for Hot works at MOE-Ghim Moh (Ceiling support works).pdf
RA for Hot works at MOE-Ghim Moh (Ceiling support works).pdfRA for Hot works at MOE-Ghim Moh (Ceiling support works).pdf
RA for Hot works at MOE-Ghim Moh (Ceiling support works).pdf
 
Water cooler monthly
Water cooler monthlyWater cooler monthly
Water cooler monthly
 
Operator Training
Operator TrainingOperator Training
Operator Training
 
Permit to work training
Permit to work trainingPermit to work training
Permit to work training
 
Work Permit System
Work Permit SystemWork Permit System
Work Permit System
 
Basic safety orientation training
Basic safety orientation trainingBasic safety orientation training
Basic safety orientation training
 
Forklift safety
Forklift safetyForklift safety
Forklift safety
 
25 demolition of existing concrete structures risk assessment templates
25 demolition of existing concrete structures risk assessment templates25 demolition of existing concrete structures risk assessment templates
25 demolition of existing concrete structures risk assessment templates
 
New Employee Orientation 05
New Employee Orientation 05New Employee Orientation 05
New Employee Orientation 05
 

Similar to Chris Withers Managing Safely Project

Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...
Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...
Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...
MohammedAliQazi
 
Safety Based Estimation FINAL
Safety Based Estimation FINALSafety Based Estimation FINAL
Safety Based Estimation FINAL
Melissa Spencer
 
ig2_forms_electronic_submission_v2__2_.docx.pdf
ig2_forms_electronic_submission_v2__2_.docx.pdfig2_forms_electronic_submission_v2__2_.docx.pdf
ig2_forms_electronic_submission_v2__2_.docx.pdf
ShadyHella1
 
AIGA 039_06 Road transport emergency preparedness_reformated Jan 12.pdf
AIGA 039_06 Road transport emergency preparedness_reformated Jan 12.pdfAIGA 039_06 Road transport emergency preparedness_reformated Jan 12.pdf
AIGA 039_06 Road transport emergency preparedness_reformated Jan 12.pdf
MATSNorthpack
 
IG2 Risk Assessment.for any copany .docx
IG2 Risk Assessment.for any copany .docxIG2 Risk Assessment.for any copany .docx
IG2 Risk Assessment.for any copany .docx
dahomyalshehry
 
Airside Observation Statement -24.12.2015.xlsx(A).xlsx01
Airside Observation Statement -24.12.2015.xlsx(A).xlsx01Airside Observation Statement -24.12.2015.xlsx(A).xlsx01
Airside Observation Statement -24.12.2015.xlsx(A).xlsx01
Andrew Louis
 
2017 Heli-Expo - "What the FRAT?" Helicopter Risk Analysis Tool
2017 Heli-Expo - "What the FRAT?" Helicopter Risk Analysis Tool2017 Heli-Expo - "What the FRAT?" Helicopter Risk Analysis Tool
2017 Heli-Expo - "What the FRAT?" Helicopter Risk Analysis Tool
IHSTFAA
 
Airport contractor safety induction
Airport contractor safety inductionAirport contractor safety induction
Airport contractor safety induction
yasirtesters
 
Read the background information and scenario description in sectio.docx
Read the background information and scenario description in sectio.docxRead the background information and scenario description in sectio.docx
Read the background information and scenario description in sectio.docx
catheryncouper
 
Job Safety Analyses For Energization of Substation..doc
Job Safety Analyses For Energization of Substation..docJob Safety Analyses For Energization of Substation..doc
Job Safety Analyses For Energization of Substation..doc
Atif767782
 
Hazard Identification & Control
Hazard Identification & ControlHazard Identification & Control
Hazard Identification & Control
Hasnizam Md Saad
 
abridged CV 2015 Feb
abridged CV 2015 Febabridged CV 2015 Feb
abridged CV 2015 Feb
Mark Howell
 
Safety_Melgar_EEII_2011
Safety_Melgar_EEII_2011Safety_Melgar_EEII_2011
Safety_Melgar_EEII_2011
Andres Galvis
 
Practical assessment 3 - Identify construction work hazards and select risk c...
Practical assessment 3 - Identify construction work hazards and select risk c...Practical assessment 3 - Identify construction work hazards and select risk c...
Practical assessment 3 - Identify construction work hazards and select risk c...
Canberra Institute of technology
 
Const cranes 9 3 10
Const cranes 9 3 10Const cranes 9 3 10
Const cranes 9 3 10
vtsiri
 
3. Assessment Practical.docx
3. Assessment Practical.docx3. Assessment Practical.docx
3. Assessment Practical.docx
Canberra Institute of technology
 
update 20feb1
update 20feb1update 20feb1
AHU.pdf
AHU.pdfAHU.pdf
Specific method of statmeents risk assessment -job hazard analysis for land ...
Specific method of statmeents  risk assessment -job hazard analysis for land ...Specific method of statmeents  risk assessment -job hazard analysis for land ...
Specific method of statmeents risk assessment -job hazard analysis for land ...
Arber Dogani
 
Knowledge Based System (Expert System) : Equipment Safety Control & Management
Knowledge Based System (Expert System) : Equipment Safety Control & ManagementKnowledge Based System (Expert System) : Equipment Safety Control & Management
Knowledge Based System (Expert System) : Equipment Safety Control & Management
Amr El-Ganainy
 

Similar to Chris Withers Managing Safely Project (20)

Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...
Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...
Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...
 
Safety Based Estimation FINAL
Safety Based Estimation FINALSafety Based Estimation FINAL
Safety Based Estimation FINAL
 
ig2_forms_electronic_submission_v2__2_.docx.pdf
ig2_forms_electronic_submission_v2__2_.docx.pdfig2_forms_electronic_submission_v2__2_.docx.pdf
ig2_forms_electronic_submission_v2__2_.docx.pdf
 
AIGA 039_06 Road transport emergency preparedness_reformated Jan 12.pdf
AIGA 039_06 Road transport emergency preparedness_reformated Jan 12.pdfAIGA 039_06 Road transport emergency preparedness_reformated Jan 12.pdf
AIGA 039_06 Road transport emergency preparedness_reformated Jan 12.pdf
 
IG2 Risk Assessment.for any copany .docx
IG2 Risk Assessment.for any copany .docxIG2 Risk Assessment.for any copany .docx
IG2 Risk Assessment.for any copany .docx
 
Airside Observation Statement -24.12.2015.xlsx(A).xlsx01
Airside Observation Statement -24.12.2015.xlsx(A).xlsx01Airside Observation Statement -24.12.2015.xlsx(A).xlsx01
Airside Observation Statement -24.12.2015.xlsx(A).xlsx01
 
2017 Heli-Expo - "What the FRAT?" Helicopter Risk Analysis Tool
2017 Heli-Expo - "What the FRAT?" Helicopter Risk Analysis Tool2017 Heli-Expo - "What the FRAT?" Helicopter Risk Analysis Tool
2017 Heli-Expo - "What the FRAT?" Helicopter Risk Analysis Tool
 
Airport contractor safety induction
Airport contractor safety inductionAirport contractor safety induction
Airport contractor safety induction
 
Read the background information and scenario description in sectio.docx
Read the background information and scenario description in sectio.docxRead the background information and scenario description in sectio.docx
Read the background information and scenario description in sectio.docx
 
Job Safety Analyses For Energization of Substation..doc
Job Safety Analyses For Energization of Substation..docJob Safety Analyses For Energization of Substation..doc
Job Safety Analyses For Energization of Substation..doc
 
Hazard Identification & Control
Hazard Identification & ControlHazard Identification & Control
Hazard Identification & Control
 
abridged CV 2015 Feb
abridged CV 2015 Febabridged CV 2015 Feb
abridged CV 2015 Feb
 
Safety_Melgar_EEII_2011
Safety_Melgar_EEII_2011Safety_Melgar_EEII_2011
Safety_Melgar_EEII_2011
 
Practical assessment 3 - Identify construction work hazards and select risk c...
Practical assessment 3 - Identify construction work hazards and select risk c...Practical assessment 3 - Identify construction work hazards and select risk c...
Practical assessment 3 - Identify construction work hazards and select risk c...
 
Const cranes 9 3 10
Const cranes 9 3 10Const cranes 9 3 10
Const cranes 9 3 10
 
3. Assessment Practical.docx
3. Assessment Practical.docx3. Assessment Practical.docx
3. Assessment Practical.docx
 
update 20feb1
update 20feb1update 20feb1
update 20feb1
 
AHU.pdf
AHU.pdfAHU.pdf
AHU.pdf
 
Specific method of statmeents risk assessment -job hazard analysis for land ...
Specific method of statmeents  risk assessment -job hazard analysis for land ...Specific method of statmeents  risk assessment -job hazard analysis for land ...
Specific method of statmeents risk assessment -job hazard analysis for land ...
 
Knowledge Based System (Expert System) : Equipment Safety Control & Management
Knowledge Based System (Expert System) : Equipment Safety Control & ManagementKnowledge Based System (Expert System) : Equipment Safety Control & Management
Knowledge Based System (Expert System) : Equipment Safety Control & Management
 

More from Chris Withers

Iosh Managing Safely Certificate
Iosh Managing Safely CertificateIosh Managing Safely Certificate
Iosh Managing Safely Certificate
Chris Withers
 
Hydraulic Torque & Tension Bolted Connection
Hydraulic Torque & Tension Bolted ConnectionHydraulic Torque & Tension Bolted Connection
Hydraulic Torque & Tension Bolted Connection
Chris Withers
 
cityguilds level2 pro
cityguilds level2 procityguilds level2 pro
cityguilds level2 proChris Withers
 
Engineering Certificate
Engineering CertificateEngineering Certificate
Engineering CertificateChris Withers
 

More from Chris Withers (6)

Iosh Managing Safely Certificate
Iosh Managing Safely CertificateIosh Managing Safely Certificate
Iosh Managing Safely Certificate
 
Hydraulic Torque & Tension Bolted Connection
Hydraulic Torque & Tension Bolted ConnectionHydraulic Torque & Tension Bolted Connection
Hydraulic Torque & Tension Bolted Connection
 
cityguilds level2 pro
cityguilds level2 procityguilds level2 pro
cityguilds level2 pro
 
NVQ Level 1
NVQ Level 1NVQ Level 1
NVQ Level 1
 
Engineering Certificate
Engineering CertificateEngineering Certificate
Engineering Certificate
 
C Withers SMSTS
C Withers SMSTSC Withers SMSTS
C Withers SMSTS
 

Chris Withers Managing Safely Project

  • 1. IOSH Managing Safely IOSH Managing Safely - Project Introduction As part of the Managing Safely course, you have to complete a project and have it assessed. You will be expected to carry out a risk assessment based on your own work environment. You need to record the results on the attached sheets and submit them for marking. Do not submit any additional material in support of your project work as only the six parts of the project will be assessed. The project can be word processed or hand written. When you have completed your work you can upload it via the “Upload Your Project” section of the IOSH Managing Safely course, or you can post it to: Tamara Pelley Santia Training Services Santia House Parc Nantgarw Cardiff CF15 7QX Candidates Name: Chris Withers There is a two week time limit for the return of the project. Your project must be completed and returned by: Course Code: H Return Date: 06/06/16 © Santia 2014 - restricted use only Page 1 of 16 Sales ref: sc/1013/v3.2
  • 2. IOSH Managing Safely Instructions Please read all of the instructions before starting work on your project. The project is broken down into a number of parts. Please complete each section as detailed below. Part 1 - description of the work tasks that are your responsibility Record a brief description of all the work tasks within your work environment including:  Description/labelled sketch of the location(s).  People who work in or visit the area on a regular basis or from time to time. (Think about the different groups of people who may be in the area and how often they might be there).  Permanent and temporary items of equipment and substances.  Activities carried out within your work environment. Part 2 - a hazard checklist of the location(s) Record a brief description of three location hazards that may arise in your work environment. For example, car park, stairs, uneven floor. For each of these hazards please include:  A description of the location.  A description of the hazard – in relation to the location.  The number and occupation of people who could be affected by the hazard – in relation to the location.  Whether a risk assessment is recommended. Part 3 - a hazard checklist of permanent and/or temporary items of equipment and substances used in your work environment Record a brief description of three hazards that may arise from equipment or substances used. For each of these hazards please include:  A description of permanent and/or temporary items of equipment and substances used.  A description of the hazard – in relation to the equipment/substance.  The number and occupation of people who could be affected by the hazard – in relation to the equipment/substance. © Santia 2014 - restricted use only Page 2 of 16 Sales ref: sc/1013/v3.2
  • 3. IOSH Managing Safely  Whether a risk assessment is recommended. Part 4 - a hazard checklist of the activities carried out within your work environment Record a brief description of three hazards that may arise from within your work environment. For each of these hazards please include:  A description of the work activity.  A description of the hazard – in relation to the work activity.  The number and occupation of people who could be affected by the hazard – in relation to the work activity. Note: for the purpose of this exercise all three activity hazards that you are assessing on part 4 must require a risk assessment. Part 5 - carrying out a risk assessment Please carry out a risk assessment on all three of the activity hazards you have listed on part 4. Please make sure you include:  A description of the work activity.  A description of the hazard, hazardous event and expected consequence – in relation to the work activity.  The number and occupation of people affected – in relation to the work activity.  An assessment of risk (please use the 5 x 5 matrix) – in relation to the work activity.  Whether risk controls are required. Note: for the purpose of this exercise all three activity hazards that you are assessing on part 5 must require risk controls. Part 6 - risk control recommendations Please complete the risk control form for all three activity hazards you have listed on part 4. Please make sure you include:  A description of the work activity and risk level from the risk assessment.  Existing risk controls.  Any further risk controls required – in relation to the work activity.  The residual risk (please use the 5 x 5 matrix) – in relation to the work activity. © Santia 2014 - restricted use only Page 3 of 16 Sales ref: sc/1013/v3.2
  • 4. IOSH Managing Safely  A description of the type of monitoring required and how often – in relation to the residual risk. Note: where you have large numbers of hazards in your work environment you will not have space to record them all. In these circumstances, select a representative sample of hazards for the purposes of this project and record only these. Remember that only three hazards are required for parts 2, 3, and 4. Each part has a maximum number of marks which can be awarded and details are given in the table below: Part Maximum marks 1 18 2 16 3 16 4 13 5 30 6 30 Total 123 Minimum mark 62 Finally, before returning your project, check that your name, the end of course date, the name of your company, the site name and the name of your training provider are recorded on the first sheet. Please also ensure that you sign each sheet to confirm that the work you submit is your own. Please note: the small square boxes in the bottom right hand corner of each section on parts 2 to 6 are for the markers use only. © Santia 2014 - restricted use only Page 4 of 16 Sales ref: sc/1013/v3.2
  • 5. IOSH Managing Safely Part 1 - description of the work tasks that are your responsibility (continued on the next page) Delegate Name: Chris Withers End of course date: Company: K.c.t Energy Site Name: South coast offshore wind farm Training provider:Santia Training Services A description / sketch of the location(s) The location is offshore wind farm based on the south coast of England asset location is H09 distance approximately 12 kilometres off the Brighton coast line. Confined space The confined space will be in side the monapile just above sea level and we will be working on a platform that's in the monepile, access to the turbine and different levels on the tp will be by ladder all personnel to where harness and correct ppe. A description of the people who work in or visit the area on a regular basis or from time to time. The team consists of one supervisor who will supervise the work, One client rep who will monitor the work, One top man who will monitor gas detectors and personnel log data board for confined space entry 4 bolting technicians to carry out the proposed work Maximum of 3 personnel to work in confined space, there will be no one else present on the offshore installation. There will be a captain and deck hand present on the support vessel who will support us. There will be further contractors to visit the asset when they are required for further installation work. Not while our work is carried out. © Santia 2014 - restricted use only Page 5 of 16 Sales ref: sc/1013/v3.2 Marks allocated Ho9
  • 6. IOSH Managing Safely Please sign to confirm that this is your own work …........................... Part 1 - description of the work tasks that are your responsibility A description of permanent and temporary pieces of equipment and substances used in your work environment All work will be carried out inside a confined space within the monopile of an offshore wind turbine foundation. equipment being used, hydraulic tension heads hydraulic hoses pneumatic compressor emergency escape sets gas detectors rigging of electric ventilation system Tp davit crane Portable davit crane pulley systems compressed air hydraulic fluid. Generators compressor ladders inertia reel communication radios Transport all equipment from boat to offshore installation using tp davit crane (lifting operations) We will be running 13 tension heads on 13 bolts that will be connected via hydraulic hoses and daisy chained in a 1-7 sequence around the monapile, the heads will be functioned by the pneumatic compressor which will feed hydraulic oil too each head to tension each bolt, the ventilation system will be put in place to extract any UN-wanted gases and too feed fresh air into the confined space. Escapes sets too provide fresh air in case of evacuation or rescue. also having 4 gas detectors to monitor the atmosphere to detect any gases (top man). We will also have too rig a portable davit crane to lift equipment within the turbine foundations, fall arrest systems will be put in place above each ladder too prevent any falls from height, © Santia 2014 - restricted use only Page 6 of 16 Sales ref: sc/1013/v3.2 Marks allocated
  • 7. IOSH Managing Safely A description of the activities carried out within your work environment Before transferring from boat too offshore installation all equipment must be rigged ready for lifting. The generator must be powered up, one technician too stay on vessel too assit deckhand with lift operations. All other technicians transfer to offshore installation. We use power from the boat to operate tp davit crane. All equipment too be lifted from support vessel using tp davit crane and use pully system if needed. Set up of portable davit crane and ventilation system for confined space entry. Test the confined space area for gases and o2 levels. Once safe too enter then crane all tension heads, compressor, lighting, and evacuation sets too confined space area. Ready for tensioning tp bolts. Monitoring the atmosphere for gases every 15 minutes taking regular intervals to avoid any long periods of time in confined area. Working at height will have too be done from transferring too different levels within the the turbine foundations, Please sign to confirm that this is your own work …………………………………… © Santia 2014 - restricted use only Page 7 of 16 Sales ref: sc/1013/v3.2
  • 8. IOSH Managing Safely Hazard Checklist: Location(s) Part 2 The location(s) you manage Company K.c.t Energy Department O&M Description of the location Description of the hazard (in relation to the location) Number and occupation of people affected (in relation to the location) Risk assessment recommend ed? (If no, please explain) Lifting operations between Support Vessel and Offshore installation Lifting activities from vessel too offshore installation using tp davit crane, theres a risk of falling objects, manual handling, environment, (e.g weather) 9 perssonels including 7 Offshore Technicians 1 Support Vessel Deckhand 1 Support Vessel Captain  yes Climbing ladders Transfering from vessl to offshore installation and moving from diffeernt levels within the turbine All 7 offshore technicans and 1 deckhand assisting us transfering  yes Confined space The confined space is located within the wind turbine foundation with the likelihood of h2s gases present. All 7 Offshore Technicians who will be working in and around the confined space  yes © Santia 2014 - restricted use only Page 8 of 16 Sales ref: sc/1013/v3.2
  • 9. IOSH Managing Safely Please sign to confirm that this is your own work …………………………………………………… © Santia 2014 - restricted use only Page 9 of 16 Sales ref: sc/1013/v3.2
  • 10. IOSH Managing Safely Hazard Checklist: Equipment and Substances Part 3 Permanent and temporary pieces of equipment and substances used in the work environment Company K.c.t Energy Department O&M Site name: South coast offshore wind farm Description of the equipment / substances Description of the hazard (in relation to the equipment/substance) Number and occupation of people affected (in relation to the equipment/substance) Risk assessmen t recommen ded? (If no, please explain) Pneumatic hydraulic pump for tensioning bolts. (compressed air) vessel generator supplying compressed air , will have a pressurized system, compressor malfunction,leaks, leaking oil, explosion. Struck by unsecured airlines 7 offshore technicians and 1 support vessel deckhand assisting with the supply of compressed air.  yes Hydraulic oil Leaks and spills are more likely under pressurized systems, 6 offshore technicians who assist in the work carried out,  yes Davit Crane Heavy lifting to and from vessel to installation, risk of fallen objects, stability of the load. Collisions, failure of lifting equipment, 9 personnel 7 Offshore Technicians. 1 Support Vessel Deckhand and captain both working on vessel  yes © Santia 2014 - restricted use only Page 10 of 16 Sales ref: sc/1013/v3.2
  • 11. IOSH Managing Safely lifting operator, electric shock, Please sign to confirm that this is your own work …………………………………………… © Santia 2014 - restricted use only Page 11 of 16 Sales ref: sc/1013/v3.2
  • 12. IOSH Managing Safely Hazard Checklist: Activities Part 4 Activities carried out within your work environment Note: for the purpose of this exercise, all three activity hazards must require a risk assessment. Company K.c.t Energy Department O&M Site name: South coast offshore wind farm. Description of the work activity Description of the hazard (in relation to the work activity) Number and occupation of people affected (in relation to the work activity) Risk assessmen t recommen ded? Working within confined space where h2s will be present . H2s gas will be present all personnel could be exposed to it, and the likelihood of explosion, All technicians in and around the confined space could come into contact. 7 offshore technicians √ yes Installing the Portable davit crane Open hatches for access and In- Correct installation of the davit crane would result in equipment failure, falling objects and injury and damaged to property. Correct training would be advised. 7 offshore technicians working within the area will be affected,. √ yes © Santia 2014 - restricted use only Page 12 of 16 Sales ref: sc/1013/v3.2
  • 13. IOSH Managing Safely Climbing ladders which will be common practice within work offshore work environment, Ladders will be used to transfer too the offshore installation from the boat, and accessing different levels of the the offshore turbine All technicians transferring and one deck hand assisting the technicians to safely transfer, √ yes Please sign to confirm that this is your own work ……………………………………………………… © Santia 2014 - restricted use only Page 13 of 16 Sales ref: sc/1013/v3.2
  • 14. IOSH Managing Safely Risk Assessment Form Part 5 Company Department Site name:South coast offshore wind farm Note: For the purpose of this exercise, all three activity hazards must require risk controls. Work activity Hazard, hazardous event and expected consequence (in relation to the work activity) People affected (in relation to the work activity) Assessment of Risk Are Risk Controls Required? Likelihood level Conseque nce level Risk level Confined space work in offshore wind turbine foundation - H2s gas present.  Highly explosive  toxic inhalation  severe illness or death Occupation: offshore technicians. Number: 7 4 5 20 √ yes Installation of portable crane  Open hatches  incorrect installation  fallen objects and slip trips and falls,  death or injury Occupation: offshore technicians. Number:7 3 4 12 √ yes Climbing ladders  Risk of falls  risk of falls if procedures not followed,  serious injury or death Occupation: offshore technicians and deckhand Number:8 3 4 12 √ yes © Santia 2014 - restricted use only Page 14 of 16 Sales ref: sc/1013/v3.2
  • 15. IOSH Managing Safely Date: Time: Review period: Date of next review: Assessor's name: Position: Signature: Please sign to confirm that this is your own work ……………………………………………………. Risk Control Form Part 6 Company K.c.t Energy Department O&M Site name: South coast offshore wind farm Work activity and risk level (from risk assess ment form) Existing Risk Controls (in relation to work activity) Further risk controls required (in relation to work activity) Residual Risk (in relation to work activity) Description of monitoring required (in relation to residual risk) Probable Likelihood Potential Consequence New Risk Level Risk level: 20 Correct training, Monitor atmosphere with gas monitors. Ventilation with fresh air and extraction, Access too escape sets and rescue equipment, tripod, 2 4 8 Frequency: © Santia 2014 - restricted use only Page 15 of 16 Sales ref: sc/1013/v3.2 x =
  • 16. IOSH Managing Safely Risk level: 12 competent persons, harness and lanyards must be worn at all time, for fall protection On the job training, full ppe (helmet), clear instructions on ow too install davit, tool box talks 1 2 4 Frequency: Risk level: 12 Working at height training, climbing gloves harness with fall protection lanyards and helmets Inertia fall arrest must be in place and used at all times 1 2 4 Frequency: Date Time: Review period: Date of next review: Assessor's name: Position: Signature: Please sign to confirm that this is your own work ……………………………………………………….. © Santia 2014 - restricted use only Page 16 of 16 Sales ref: sc/1013/v3.2