Copyright © 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5–1
Estimating Project
Times and Costs
CHAPTER FIVE
Where We Are Now
Estimating Projects
Copyright © 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5–3
• Estimating
–The process of forecasting or approximating the time
and cost of completing project deliverables.
–The task of balancing the expectations of stakeholders
and the need for control while the project is
implemented
• Types of Estimates
–Top-down (macro) estimates: analogy, group
consensus, or mathematical relationships
–Bottom-up (micro) estimates: estimates of elements of
the work breakdown structure
Why Estimating Time and Cost Are Important
EXHIBIT 5.1
• Estimates are needed to support good decisions.
• Estimates are needed to schedule work.
• Estimates are needed to determine how long the project
should take and its cost.
• Estimates are needed to determine whether the project
is worth doing.
• Estimates are needed to develop cash flow needs.
• Estimates are needed to determine how well the project
is progressing.
• Estimates are needed to develop time-phased budgets
and establish the project baseline.
Copyright © 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5–4
Factors Influencing the Quality of Estimates
Quality of
Estimates
Copyright © 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5–5
Project
complexity
People
Project Structure
and Organization
Padding
Estimates
Organization
Culture
Other (Nonproject)
Factors
Planning
Horizon
Estimating Guidelines for Times,
Costs, and Resources
Copyright © 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5–6
1. Responsibility.
2. Use several people to estimate.
3. Normal conditions.
4. Time units.
5. Independence.
6. Contingencies.
7. Adding a risk assessment helps avoid
surprises to stakeholders.
Top-Down versus Bottom-Up Estimating
• Top-Down Estimates(Macro) are usually
derived from a resource or group of
resources who use prior experience and
information to determine the project
duration and total cost.
• Bottom-Up Estimates (Micro) can serve
as a check on cost elements in the WBS by
rolling up the work package associated
cost accounts to major deliverables at the
work package level.
Macro versus Micro Estimating
Copyright © 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5–8
TABLE 5.1
Conditions for Preferring Top-Down or Bottom-up
Time and Cost Estimates
Condition
Strategic decision making
Macro Estimates
X
Micro Estimates
Cost and time important X
High uncertainty X
Internal, small project X
Fixed-price contract X
Customer wants details X
Unstable scope X
Estimating Projects: Preferred Approach
Copyright © 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5–9
•Make rough top-down estimates.
•Develop the WBS/OBS.
•Make bottom-up estimates.
•Develop schedules and budgets.
•Reconcile differences between
top-down and bottom-up
estimates
Methods for Estimating Project
Times and Costs
• Top-down
Approaches
(Macro)
–Consensus methods
–Ratio methods
–Apportion method
–Function point methods for
software and system projects
–Learning curves
Project Estimate
Times
Costs
Copyright © 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5–
10
Apportion Method of Allocating Project Costs Using a
(High Level) Work Breakdown Structure
FIGURE 5.1
Copyright © 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5–
11
Simplified Basic Function Point Count Process for a
Prospective Project or Deliverable: Example
In this approach we are looking at durations, not costs
TABLE 5.2
Copyright © 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5–10
Example:
Function Point Count Method
TABLE 5.3
Copyright © 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5–11
Methods for Estimating Project
Times and Costs (cont’d)
• Bottom-up
Approaches (Micro)
–Template method
–Parametric Procedures
Applied to Specific Tasks
–Range Estimating
–A Hybrid: Phase Estimating
Copyright © 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5–14
Phase Estimating over
Copyright © 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5–15
Product Life Cycle
FIGURE 5.3
Level of Detail
Copyright © 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5–16
• Level of detail is different for different levels of
management.
• Level of detail in the WBS varies with the
complexity of the project.
• Excessive detail is costly.
–Fosters a focus on departmental outcomes
–Creates unproductive paperwork
• Insufficient detail is costly.
–Lack of focus on goals
–Wasted effort on nonessential activities
Types of Costs
Copyright © 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5–17
• Direct Costs
–Costs that are clearly chargeable to a specific
work package.
•Labor, materials, equipment, and other
• Direct Project Overhead Costs
–Costs incurred that are directly tied to an
identifiable project deliverable or work
package.
•Salary, rents, supplies, specialized machinery
• General and Administrative Overhead Costs
–Organization costs that are not directly
linked to a specific project
Example: Contract Bid Summary Costs
FIGURE 5.6
Direct costs $80,000
Direct overhead
Total direct costs
$20,000
$100,000
G&A overhead (20%)
Total costs
$20,000
$120,000
Profit (20%) $24,000
Total bid $144,000
Copyright © 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5–18
Three Views of Cost Accrual
FIGURE 5.5
Copyright © 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5–19
Refining Estimates
Copyright © 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5–20
• Reasons for Adjusting Estimates
–Interaction costs are hidden in estimates.
–Normal conditions do not apply.
–Things go wrong on projects.
–Changes in project scope and plans.
–Overly optimistic
–Strategic misrepresentation
• Adjusting Estimates
–Time and cost estimates of specific activities are
adjusted as the risks, resources, and situation
particulars become more clearly defined.
Creating a Database for Estimating
• The best way to improve the accuracy of
estimates is to collect and archive data from
previous projects, both estimates and
actuals.
• Historical data provides a knowledge base for
improving project time and cost estimates.
Creating an estimating database is a “best
practice” among leading project management
organizations.
Creating a Database for Estimating
Copyright © 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5–22
FIGURE 5.7
Estimating
Database
Templates

More Related Content

What's hot

Project Plan Presentation Example
Project Plan Presentation ExampleProject Plan Presentation Example
Project Plan Presentation ExampleMartin Sillaots
 
Project Management Concepts (from PMBOK 5th Ed)
Project Management Concepts (from PMBOK 5th Ed)Project Management Concepts (from PMBOK 5th Ed)
Project Management Concepts (from PMBOK 5th Ed)Jeremy Jay Lim
 
Understanding p6 dates
Understanding p6 datesUnderstanding p6 dates
Understanding p6 dateskrunalplanning
 
Project Scope Management -
Project Scope Management - Project Scope Management -
Project Scope Management - dyaksa hanindito
 
Introduction to project management
Introduction to project managementIntroduction to project management
Introduction to project managementBarun_agnihotri
 
Estimating Cost & Time.ppt
Estimating Cost & Time.pptEstimating Cost & Time.ppt
Estimating Cost & Time.ppt341741357
 
Introduction to MS project
Introduction to MS projectIntroduction to MS project
Introduction to MS projectSamir Paralikar
 
Project Management Office Vol. 1 - One Page Gold Vol. 1
Project Management Office Vol. 1  - One Page Gold Vol. 1Project Management Office Vol. 1  - One Page Gold Vol. 1
Project Management Office Vol. 1 - One Page Gold Vol. 1ken martin
 
Agile Project Management
Agile Project ManagementAgile Project Management
Agile Project ManagementAbdullah Khan
 
PMO Presentation
PMO PresentationPMO Presentation
PMO PresentationTURKI , PMP
 
Making the Case for a PMO to Help Defense ROI
Making the Case for a PMO to Help Defense ROIMaking the Case for a PMO to Help Defense ROI
Making the Case for a PMO to Help Defense ROIGigi Steele McAlwee
 
Chap 6 Developing A Project Plan
Chap 6 Developing A Project PlanChap 6 Developing A Project Plan
Chap 6 Developing A Project Planproject management
 
PMP Lecture 3: Project Management Processes
PMP Lecture 3: Project Management ProcessesPMP Lecture 3: Project Management Processes
PMP Lecture 3: Project Management ProcessesMohamed Loey
 
Lect-6&7: Network Diagrams, PERT and CPM
Lect-6&7: Network Diagrams, PERT and CPMLect-6&7: Network Diagrams, PERT and CPM
Lect-6&7: Network Diagrams, PERT and CPMMubashir Ali
 
Practical Project Management - full course
Practical Project Management - full coursePractical Project Management - full course
Practical Project Management - full courseMarten Schoonman
 

What's hot (20)

080613 Mega-Project Schedule Integration & Management RCF Method-1
080613 Mega-Project Schedule Integration & Management RCF Method-1 080613 Mega-Project Schedule Integration & Management RCF Method-1
080613 Mega-Project Schedule Integration & Management RCF Method-1
 
Project Plan Presentation Example
Project Plan Presentation ExampleProject Plan Presentation Example
Project Plan Presentation Example
 
Chapter 3
Chapter 3Chapter 3
Chapter 3
 
Project Management Concepts (from PMBOK 5th Ed)
Project Management Concepts (from PMBOK 5th Ed)Project Management Concepts (from PMBOK 5th Ed)
Project Management Concepts (from PMBOK 5th Ed)
 
Understanding p6 dates
Understanding p6 datesUnderstanding p6 dates
Understanding p6 dates
 
Project Planning Scheduling
Project Planning SchedulingProject Planning Scheduling
Project Planning Scheduling
 
Project Scope Management -
Project Scope Management - Project Scope Management -
Project Scope Management -
 
Introduction to project management
Introduction to project managementIntroduction to project management
Introduction to project management
 
Estimating Cost & Time.ppt
Estimating Cost & Time.pptEstimating Cost & Time.ppt
Estimating Cost & Time.ppt
 
Introduction to MS project
Introduction to MS projectIntroduction to MS project
Introduction to MS project
 
Project Management Office Vol. 1 - One Page Gold Vol. 1
Project Management Office Vol. 1  - One Page Gold Vol. 1Project Management Office Vol. 1  - One Page Gold Vol. 1
Project Management Office Vol. 1 - One Page Gold Vol. 1
 
Agile Project Management
Agile Project ManagementAgile Project Management
Agile Project Management
 
PMO Presentation
PMO PresentationPMO Presentation
PMO Presentation
 
Work Breakdown Structure
Work Breakdown StructureWork Breakdown Structure
Work Breakdown Structure
 
Making the Case for a PMO to Help Defense ROI
Making the Case for a PMO to Help Defense ROIMaking the Case for a PMO to Help Defense ROI
Making the Case for a PMO to Help Defense ROI
 
Chap 6 Developing A Project Plan
Chap 6 Developing A Project PlanChap 6 Developing A Project Plan
Chap 6 Developing A Project Plan
 
PMP Lecture 3: Project Management Processes
PMP Lecture 3: Project Management ProcessesPMP Lecture 3: Project Management Processes
PMP Lecture 3: Project Management Processes
 
Lect-6&7: Network Diagrams, PERT and CPM
Lect-6&7: Network Diagrams, PERT and CPMLect-6&7: Network Diagrams, PERT and CPM
Lect-6&7: Network Diagrams, PERT and CPM
 
Practical Project Management - full course
Practical Project Management - full coursePractical Project Management - full course
Practical Project Management - full course
 
Chap008
Chap008Chap008
Chap008
 

Similar to CHAPTER 5.pptx

Larson8e_CH05_PowerPoint.pptx
Larson8e_CH05_PowerPoint.pptxLarson8e_CH05_PowerPoint.pptx
Larson8e_CH05_PowerPoint.pptxfilizmizrak1
 
Chapter FiveEstimating Project Times and Costs5–1Copyrig
Chapter FiveEstimating Project Times and Costs5–1CopyrigChapter FiveEstimating Project Times and Costs5–1Copyrig
Chapter FiveEstimating Project Times and Costs5–1CopyrigJinElias52
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management FrameworkRahul Sudame
 
Chapter 2 -project evaluation
Chapter 2 -project evaluationChapter 2 -project evaluation
Chapter 2 -project evaluationRohanMistry15
 
4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt
4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt
4. PAE AcFn621Ch-4a Project Alaysis and Selection.pptProfDrAnbalaganChinn
 
Chapter 09 Monitoring and control
Chapter 09 Monitoring and controlChapter 09 Monitoring and control
Chapter 09 Monitoring and controlRohanMistry15
 
Best Practices: Implement Massive SCM Projects
Best Practices: Implement Massive SCM ProjectsBest Practices: Implement Massive SCM Projects
Best Practices: Implement Massive SCM ProjectsARC Advisory Group
 
Chapter 05 Software effort estimation PartII_final
Chapter 05 Software effort estimation PartII_finalChapter 05 Software effort estimation PartII_final
Chapter 05 Software effort estimation PartII_finalRohanMistry15
 
09. Project Cost Management
09. Project Cost Management09. Project Cost Management
09. Project Cost ManagementBhuWan Khadka
 
Machine intelligence methodology for large IT projects
Machine intelligence methodology for large IT projectsMachine intelligence methodology for large IT projects
Machine intelligence methodology for large IT projectsJeremy Lehman
 
Why Do Projects Fail? Getting Ready for EIA 748 – Earned Value Management (EVM)
Why Do Projects Fail? Getting Ready for EIA 748 – Earned Value Management (EVM)Why Do Projects Fail? Getting Ready for EIA 748 – Earned Value Management (EVM)
Why Do Projects Fail? Getting Ready for EIA 748 – Earned Value Management (EVM)Unanet
 

Similar to CHAPTER 5.pptx (20)

Larson8e_CH05_PowerPoint.pptx
Larson8e_CH05_PowerPoint.pptxLarson8e_CH05_PowerPoint.pptx
Larson8e_CH05_PowerPoint.pptx
 
Chapter FiveEstimating Project Times and Costs5–1Copyrig
Chapter FiveEstimating Project Times and Costs5–1CopyrigChapter FiveEstimating Project Times and Costs5–1Copyrig
Chapter FiveEstimating Project Times and Costs5–1Copyrig
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management Framework
 
Chapter 2 -project evaluation
Chapter 2 -project evaluationChapter 2 -project evaluation
Chapter 2 -project evaluation
 
Project Cost Management for IEM talk on 13 January 2018.
Project Cost Management  for IEM talk on 13 January 2018.Project Cost Management  for IEM talk on 13 January 2018.
Project Cost Management for IEM talk on 13 January 2018.
 
4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt
4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt
4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt
 
Chap005
Chap005Chap005
Chap005
 
Chap005
Chap005Chap005
Chap005
 
Chapter 09 Monitoring and control
Chapter 09 Monitoring and controlChapter 09 Monitoring and control
Chapter 09 Monitoring and control
 
PMP-Cost Management area
PMP-Cost Management areaPMP-Cost Management area
PMP-Cost Management area
 
Best Practices: Implement Massive SCM Projects
Best Practices: Implement Massive SCM ProjectsBest Practices: Implement Massive SCM Projects
Best Practices: Implement Massive SCM Projects
 
Chapter 05 Software effort estimation PartII_final
Chapter 05 Software effort estimation PartII_finalChapter 05 Software effort estimation PartII_final
Chapter 05 Software effort estimation PartII_final
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
09. Project Cost Management
09. Project Cost Management09. Project Cost Management
09. Project Cost Management
 
Business case writing presentation
Business case writing presentationBusiness case writing presentation
Business case writing presentation
 
Managing Project Success
Managing Project SuccessManaging Project Success
Managing Project Success
 
ch07.ppt
ch07.pptch07.ppt
ch07.ppt
 
005810603.pdf
005810603.pdf005810603.pdf
005810603.pdf
 
Machine intelligence methodology for large IT projects
Machine intelligence methodology for large IT projectsMachine intelligence methodology for large IT projects
Machine intelligence methodology for large IT projects
 
Why Do Projects Fail? Getting Ready for EIA 748 – Earned Value Management (EVM)
Why Do Projects Fail? Getting Ready for EIA 748 – Earned Value Management (EVM)Why Do Projects Fail? Getting Ready for EIA 748 – Earned Value Management (EVM)
Why Do Projects Fail? Getting Ready for EIA 748 – Earned Value Management (EVM)
 

More from KristleJoyDimayuga

The-Global-Interstate-PPT.pptxxxxxxxxxxx
The-Global-Interstate-PPT.pptxxxxxxxxxxxThe-Global-Interstate-PPT.pptxxxxxxxxxxx
The-Global-Interstate-PPT.pptxxxxxxxxxxxKristleJoyDimayuga
 
spanish language in foreign language 1 .
spanish language in foreign language 1 .spanish language in foreign language 1 .
spanish language in foreign language 1 .KristleJoyDimayuga
 
Global-and-regional-cooperation-and-integration.pptx
Global-and-regional-cooperation-and-integration.pptxGlobal-and-regional-cooperation-and-integration.pptx
Global-and-regional-cooperation-and-integration.pptxKristleJoyDimayuga
 
SCIENCE_AND_TECHNOLOGY_GROUP_1_REPORT-Copy.pptx
SCIENCE_AND_TECHNOLOGY_GROUP_1_REPORT-Copy.pptxSCIENCE_AND_TECHNOLOGY_GROUP_1_REPORT-Copy.pptx
SCIENCE_AND_TECHNOLOGY_GROUP_1_REPORT-Copy.pptxKristleJoyDimayuga
 
CPAR-TAX-General-Principles-Batch-91-Handout.pdf
CPAR-TAX-General-Principles-Batch-91-Handout.pdfCPAR-TAX-General-Principles-Batch-91-Handout.pdf
CPAR-TAX-General-Principles-Batch-91-Handout.pdfKristleJoyDimayuga
 

More from KristleJoyDimayuga (11)

The-Global-Interstate-PPT.pptxxxxxxxxxxx
The-Global-Interstate-PPT.pptxxxxxxxxxxxThe-Global-Interstate-PPT.pptxxxxxxxxxxx
The-Global-Interstate-PPT.pptxxxxxxxxxxx
 
spanish language in foreign language 1 .
spanish language in foreign language 1 .spanish language in foreign language 1 .
spanish language in foreign language 1 .
 
Thesis-Format-Chap-1-3.pdf
Thesis-Format-Chap-1-3.pdfThesis-Format-Chap-1-3.pdf
Thesis-Format-Chap-1-3.pdf
 
Ambrosia-ppt.pptx
Ambrosia-ppt.pptxAmbrosia-ppt.pptx
Ambrosia-ppt.pptx
 
Global-and-regional-cooperation-and-integration.pptx
Global-and-regional-cooperation-and-integration.pptxGlobal-and-regional-cooperation-and-integration.pptx
Global-and-regional-cooperation-and-integration.pptx
 
SCIENCE_AND_TECHNOLOGY_GROUP_1_REPORT-Copy.pptx
SCIENCE_AND_TECHNOLOGY_GROUP_1_REPORT-Copy.pptxSCIENCE_AND_TECHNOLOGY_GROUP_1_REPORT-Copy.pptx
SCIENCE_AND_TECHNOLOGY_GROUP_1_REPORT-Copy.pptx
 
Environmental-Science.pptx
Environmental-Science.pptxEnvironmental-Science.pptx
Environmental-Science.pptx
 
CHAPTER 6.pptx
CHAPTER 6.pptxCHAPTER 6.pptx
CHAPTER 6.pptx
 
CPAR-TAX-General-Principles-Batch-91-Handout.pdf
CPAR-TAX-General-Principles-Batch-91-Handout.pdfCPAR-TAX-General-Principles-Batch-91-Handout.pdf
CPAR-TAX-General-Principles-Batch-91-Handout.pdf
 
TROJAN HORSE.pptx
TROJAN HORSE.pptxTROJAN HORSE.pptx
TROJAN HORSE.pptx
 
Real-Number-System.pptx
Real-Number-System.pptxReal-Number-System.pptx
Real-Number-System.pptx
 

Recently uploaded

Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdf
Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdfCatalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdf
Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdfOrient Homes
 
2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis UsageNeil Kimberley
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurSuhani Kapoor
 
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / NcrCall Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncrdollysharma2066
 
Call Girls In ⇛⇛Chhatarpur⇚⇚. Brings Offer Delhi Contact Us 8377877756
Call Girls In ⇛⇛Chhatarpur⇚⇚. Brings Offer Delhi Contact Us 8377877756Call Girls In ⇛⇛Chhatarpur⇚⇚. Brings Offer Delhi Contact Us 8377877756
Call Girls In ⇛⇛Chhatarpur⇚⇚. Brings Offer Delhi Contact Us 8377877756dollysharma2066
 
Non Text Magic Studio Magic Design for Presentations L&P.pptx
Non Text Magic Studio Magic Design for Presentations L&P.pptxNon Text Magic Studio Magic Design for Presentations L&P.pptx
Non Text Magic Studio Magic Design for Presentations L&P.pptxAbhayThakur200703
 
(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCRsoniya singh
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessAggregage
 
Investment analysis and portfolio management
Investment analysis and portfolio managementInvestment analysis and portfolio management
Investment analysis and portfolio managementJunaidKhan750825
 
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...lizamodels9
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Roomdivyansh0kumar0
 
BEST Call Girls In BELLMONT HOTEL ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In BELLMONT HOTEL ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In BELLMONT HOTEL ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In BELLMONT HOTEL ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,noida100girls
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfpollardmorgan
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation SlidesKeppelCorporation
 
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...lizamodels9
 
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service DewasVip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewasmakika9823
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst SummitHolger Mueller
 

Recently uploaded (20)

Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdf
Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdfCatalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdf
Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdf
 
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCREnjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
 
2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
 
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / NcrCall Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
 
Call Girls In ⇛⇛Chhatarpur⇚⇚. Brings Offer Delhi Contact Us 8377877756
Call Girls In ⇛⇛Chhatarpur⇚⇚. Brings Offer Delhi Contact Us 8377877756Call Girls In ⇛⇛Chhatarpur⇚⇚. Brings Offer Delhi Contact Us 8377877756
Call Girls In ⇛⇛Chhatarpur⇚⇚. Brings Offer Delhi Contact Us 8377877756
 
KestrelPro Flyer Japan IT Week 2024 (English)
KestrelPro Flyer Japan IT Week 2024 (English)KestrelPro Flyer Japan IT Week 2024 (English)
KestrelPro Flyer Japan IT Week 2024 (English)
 
Non Text Magic Studio Magic Design for Presentations L&P.pptx
Non Text Magic Studio Magic Design for Presentations L&P.pptxNon Text Magic Studio Magic Design for Presentations L&P.pptx
Non Text Magic Studio Magic Design for Presentations L&P.pptx
 
(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR
 
Best Practices for Implementing an External Recruiting Partnership
Best Practices for Implementing an External Recruiting PartnershipBest Practices for Implementing an External Recruiting Partnership
Best Practices for Implementing an External Recruiting Partnership
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for Success
 
Investment analysis and portfolio management
Investment analysis and portfolio managementInvestment analysis and portfolio management
Investment analysis and portfolio management
 
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
 
BEST Call Girls In BELLMONT HOTEL ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In BELLMONT HOTEL ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In BELLMONT HOTEL ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In BELLMONT HOTEL ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
 
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
 
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service DewasVip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst Summit
 

CHAPTER 5.pptx

  • 1. Copyright © 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5–1 Estimating Project Times and Costs CHAPTER FIVE
  • 3. Estimating Projects Copyright © 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5–3 • Estimating –The process of forecasting or approximating the time and cost of completing project deliverables. –The task of balancing the expectations of stakeholders and the need for control while the project is implemented • Types of Estimates –Top-down (macro) estimates: analogy, group consensus, or mathematical relationships –Bottom-up (micro) estimates: estimates of elements of the work breakdown structure
  • 4. Why Estimating Time and Cost Are Important EXHIBIT 5.1 • Estimates are needed to support good decisions. • Estimates are needed to schedule work. • Estimates are needed to determine how long the project should take and its cost. • Estimates are needed to determine whether the project is worth doing. • Estimates are needed to develop cash flow needs. • Estimates are needed to determine how well the project is progressing. • Estimates are needed to develop time-phased budgets and establish the project baseline. Copyright © 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5–4
  • 5. Factors Influencing the Quality of Estimates Quality of Estimates Copyright © 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5–5 Project complexity People Project Structure and Organization Padding Estimates Organization Culture Other (Nonproject) Factors Planning Horizon
  • 6. Estimating Guidelines for Times, Costs, and Resources Copyright © 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5–6 1. Responsibility. 2. Use several people to estimate. 3. Normal conditions. 4. Time units. 5. Independence. 6. Contingencies. 7. Adding a risk assessment helps avoid surprises to stakeholders.
  • 7. Top-Down versus Bottom-Up Estimating • Top-Down Estimates(Macro) are usually derived from a resource or group of resources who use prior experience and information to determine the project duration and total cost. • Bottom-Up Estimates (Micro) can serve as a check on cost elements in the WBS by rolling up the work package associated cost accounts to major deliverables at the work package level.
  • 8. Macro versus Micro Estimating Copyright © 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5–8 TABLE 5.1 Conditions for Preferring Top-Down or Bottom-up Time and Cost Estimates Condition Strategic decision making Macro Estimates X Micro Estimates Cost and time important X High uncertainty X Internal, small project X Fixed-price contract X Customer wants details X Unstable scope X
  • 9. Estimating Projects: Preferred Approach Copyright © 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5–9 •Make rough top-down estimates. •Develop the WBS/OBS. •Make bottom-up estimates. •Develop schedules and budgets. •Reconcile differences between top-down and bottom-up estimates
  • 10. Methods for Estimating Project Times and Costs • Top-down Approaches (Macro) –Consensus methods –Ratio methods –Apportion method –Function point methods for software and system projects –Learning curves Project Estimate Times Costs Copyright © 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5– 10
  • 11. Apportion Method of Allocating Project Costs Using a (High Level) Work Breakdown Structure FIGURE 5.1 Copyright © 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5– 11
  • 12. Simplified Basic Function Point Count Process for a Prospective Project or Deliverable: Example In this approach we are looking at durations, not costs TABLE 5.2 Copyright © 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5–10
  • 13. Example: Function Point Count Method TABLE 5.3 Copyright © 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5–11
  • 14. Methods for Estimating Project Times and Costs (cont’d) • Bottom-up Approaches (Micro) –Template method –Parametric Procedures Applied to Specific Tasks –Range Estimating –A Hybrid: Phase Estimating Copyright © 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5–14
  • 15. Phase Estimating over Copyright © 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5–15 Product Life Cycle FIGURE 5.3
  • 16. Level of Detail Copyright © 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5–16 • Level of detail is different for different levels of management. • Level of detail in the WBS varies with the complexity of the project. • Excessive detail is costly. –Fosters a focus on departmental outcomes –Creates unproductive paperwork • Insufficient detail is costly. –Lack of focus on goals –Wasted effort on nonessential activities
  • 17. Types of Costs Copyright © 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5–17 • Direct Costs –Costs that are clearly chargeable to a specific work package. •Labor, materials, equipment, and other • Direct Project Overhead Costs –Costs incurred that are directly tied to an identifiable project deliverable or work package. •Salary, rents, supplies, specialized machinery • General and Administrative Overhead Costs –Organization costs that are not directly linked to a specific project
  • 18. Example: Contract Bid Summary Costs FIGURE 5.6 Direct costs $80,000 Direct overhead Total direct costs $20,000 $100,000 G&A overhead (20%) Total costs $20,000 $120,000 Profit (20%) $24,000 Total bid $144,000 Copyright © 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5–18
  • 19. Three Views of Cost Accrual FIGURE 5.5 Copyright © 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5–19
  • 20. Refining Estimates Copyright © 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5–20 • Reasons for Adjusting Estimates –Interaction costs are hidden in estimates. –Normal conditions do not apply. –Things go wrong on projects. –Changes in project scope and plans. –Overly optimistic –Strategic misrepresentation • Adjusting Estimates –Time and cost estimates of specific activities are adjusted as the risks, resources, and situation particulars become more clearly defined.
  • 21. Creating a Database for Estimating • The best way to improve the accuracy of estimates is to collect and archive data from previous projects, both estimates and actuals. • Historical data provides a knowledge base for improving project time and cost estimates. Creating an estimating database is a “best practice” among leading project management organizations.
  • 22. Creating a Database for Estimating Copyright © 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5–22 FIGURE 5.7 Estimating Database Templates

Editor's Notes

  1. Define the project Step 1: Defining the Project Scope Step 2: Establishing Project Priorities Step 3: Creating the Work Breakdown Structure Step 4: Integrating the WBS with the Organization Step 5: Coding the WBS for the Information System Responsibility matrices Project communication plan 1. Project objective 2. Deliverables 3. Milestones 4. Technical requirements 5. Limits and exclusions 6. Reviews with customer
  2. Estimating project time and cost is the foundation for project planning and control It is carried out at the early stage of the project Assumption kung gaano katagal at kung gaano kalaki yung magiging cost sa pag gawa ng project It balance the expectation kasi pag nag estimate tayo is palaging malapit dapat sa reality or dun sa inexpect natin That’s why Innacurate estimates lead to false expectations and consumer dissatisfaction Top down estimates are usually done by senior management. Management will often derive estimates from analogy, group consensus, or mathematical relationships. Bottom-up estimates are typically performed by the people who are doing the work. Their estimates are based on estimates of elements found in the work breakdown structure All project stakeholders prefer accurate cost and time estimates, but they also understand inherent uncertaintay in all projects
  3. Calculations Nagkakaron ng expectations Cost, time, and budget estimates are the lifeline for control; they serve as the standard for comparison of actual and plan throughout the life of the project.
  4. 1. The quality of the estimate depends on the planning horizon; mas accurate po yung estimates pag short lamang yung duration ng projects. 2. Project complexity - Time to implement new technology has a habit of expanding in an increasing, nonlinear fashion. Sometimes poorly written scope specifications for new technology result in errors in estimating times and costs. 3, The people factor can influence the quality of time and cost estimates. For example, accuracy of estimates depends on the skills of the people making the estimates. How familiar are they with the task they are estimating? A close match of skills to the task will influence productivity and learning time and, conversely, the opposite is also true. Staff turnover and whether people have worked on projects together in the past also influences accurate estimating. 4. Which project structure is chosen to manage the project will influence time and cost estimates. Project structure refers to matrix, functional, and projectized. The “speed” advantage of a focused dedicated team comes at a higher cost than a matrix team; however the matrix team will not deliver as quickly due to competing demands and divided focus. 5. When asked to estimate, most are inclined to “pad” estimates in order to increase the probability of being on budget and reducing the risk of being late. Padding, however, defeats the chance of truly arriving at realistic estimates, which is greatly needed in order to be competitive. 6. Organization culture can significantly influence project estimates. Some organizations tolerate padding, others encourage it, still others oppose it. in some organization t detailed estimating takes too much time and is not worth the effort or that it’s impossible to predict the future. Accurate estimates are the bedrock of effective project management. Dahil may ibat iba nga tayong organization culture nakakaapekto ito sa quality ng ating estimates. 7. Finally, nonproject factors can impact time and cost estimates. Equipment downtime, holidays, vacations, staff reduction, strikes, and legal limits influence project estimates.
  5. To do the estimates At the work package level, ang may responsibility dapat sa estimates should be made by the person(s) most familiar with the task, They will give an estimate based on experience and best judgment. Usually yung mga first-line supervisors or technicians ang responsible because they are experienced and familiar with the type of work involved. It is well known that a cost or time estimate usually has a better chance of being reasonable and realistic when several people with relevant experience and/or knowledge of the task are used (sometimes called “crowdsourcing”) they have differences pero kapag pinagsama sama yung mga differences ng kanialang estimates it will lead to concensus magkakaron sila ng maraming ideas at dun sa ideas na yun makikita nila yung magaganda at maiiwasan or maalis nila yung mga estimates na sa tingin nila ay maglelead lang into errors 3. When task time, cost, and resource estimates are determined, they are based on certain assumptions. Estimates should be based on normal conditions, efficient methods, and a normal level of resources. normal workday is eight hours, the time estimate should be based on an eight-hour day. Similarly, if the normal workday is two shifts, the time estimate should be based on a two-shift workday. time and cost estimates should be based on the normal levels of resources. 4. network analysis requires a standard unit of time. Specific time units to use should be selected early in the development phase of the project network. All task time estimates need consistent time units. Estimates of time must consider whether normal time is represented by calendar days, workdays, workweeks, person days, single shift, hours, minutes, etc. In practice the use of workdays is the dominant choice for expressing task duration. 5. each task time estimate should be considered independently of other activities. Estimators should treat each task as independent of other tasks that might be integrated by the WBS. Kasi magkakaiba naman ng task at may ttask na madali, matagal mahirap 6. Work package estimates should not include allowances for contingencies. The estimate should assume normal or average conditions even though every work package will not materialize as planned. For this reason top management needs to create an extra fund for contingencies that can be used to cover unforeseen events. 7. It is obvious some tasks carry more time and cost risks than others.
  6. these estimates are sometimes made by top managers who have very little knowledge of the component activities used to complete the project. The bottom-up approach also provides the customer with an opportunity to compare the low-cost, efficient method approach with any imposed restrictions. The main disadvantage of top-down approaches to estimating is simply that the time and cost for a specific task are not considered. Grouping many tasks into a common basket encourages errors of omission and the use of imposed times and costs. Micro estimating methods are usually more accurate than macro methods.
  7. This figure depicts conditions that suggest when one approach is preferred over another. Macro – top down Micro- bottom up
  8. these steps will be done before final negotiation with either an internal or external customer. In conclusion, the ideal approach is for the project manager to allow enough time for both the top-down and bottom-up estimates to be worked out so a complete plan based on reliable estimates can be offered to the customer. In this way false expectations are minimized for all stakeholders and negotiation is reduced
  9. This method simply uses the pooled experience of senior and/or middle managers to estimate the total project duration and cost. This typically involves a meeting where experts discuss, argue, and ultimately reach a decision as to their best guess estimate. Top-down methods (sometimes called parametric) usually use ratios, or surrogates, to estimate project times or costs. Top-down approaches are often used in the concept or “need” phase of a project to get an initial duration and cost estimate for the project. This method is an extension to the ratio method. Apportionment is used when projects closely follow past projects in features and costs. Given good historical data, estimates can be made quickly with little effort and reasonable accuracy. This method is very common in projects that are relatively standard but have some small variation or customization. In the software industry, software development projects are frequently estimated using weighted macro variables called “function points” or major parameters such as number of inputs, number of outputs, number of inquiries, number of data files, and number of interfaces. These weighted variables are adjusted for a complexity factor and added. The total adjusted count provides the basis for estimating the labor effort and cost for a project. learning curve (also known as improvement curve, experience curve, and industrial progress curve), which is described by the following relationship. Some projects require that the same task, group of tasks, or product be repeated several times. Managers know intuitively that the time to perform a task improves with repetition. This phenomenon is especially true of tasks that are labor intensive. In these circumstances the pattern of improvement phenomenon can be used to predict the reduction in time to perform the task.
  10. The database approach allows the project estimator to select a specific work package done in the past and glean information for estimating the current project. Over time, historical data and the degree of accuracy in the database should improve.