BE HEALTHY WEBSITE
Customer
reports
fault via
email
1 min
NVA
Time
Non-Value Add
(including waste time)
1 hour 58 mins to
3 hours 20 mins
Value Add 2 hours 2 mins to
5 hours 3 mins
Customer
reports
fault via
phone
4 mins
NVA
Engineer
fixes fault
2 hours
VA
Engineer
escalates
fault to
manager
5 mins
NVA
Support rep
opens fault
file and
assigns
engineer
5 mins
NVA
Support rep
updates
customer
on fault
status
1 min
VA
Support rep
updates
customer
on fault
status
1 min
VA
Manager
fixes fault
5 hours
VA
Support rep
closes the
customer’s
fault file
1 min
NVA
Support rep
informs
customers
that the
fault is fixed
1 min
VA
30
mins
2
mins
5
mins
1
hour
30
mins
20
mins
2
hours
5
mins
5
mins
2
mins
JUN’S SERVICE BOOKING PROCESS
Time
Non-Value Add
(including waste time)
1 hour 21 minsValue Add
15 days, 4 hours,
15 mins +
Customer
calls for
printer
service
3 mins
NVA
Call center
rep explains
service
options
available
20 mins
VA
Booking
team
allocate an
appointment
10 mins
NVA
Customer
informed by
email
1 min
VA
Logistics
team
schedules a
visit
30 mins
NVA
Technician
performs the
service
1 hour
VA
Customer
confirms the
appointment
X
If not suitable,
the booking
team is
notified by
email
1 min
NVA
If suitable,
the logistics
team is
notified by
email
1 min
NVA
5
mins
20
mins
5
mins
2
weeks
1
day
3
hours
3
hours
NO YES
MARTA’S BASIC PRODUCTION PROCESS
Time
Non-Value Add
(including waste time)
3 hours 14 min
Value Add 2 hours 5 mins
Assistant
makes
basic cake
batter
15 mins
VA
Assistant
checks
daily recipe
10 mins
NVA
Owner
checks
batter
5 mins
NVA
Assistant
bakes cake
1 hour
VA
Owner
checks
cake
5 mins
NVA
Assistant
decorates
cake
20 mins
VA
Owner
checks
decoration
quality
5 mins
NVA
Assistant
displays
cake in
bakery
20 mins
VA
Assistant checks daily recipe
Assistant
walks from
kitchen to
stockroom
with batter
4 mins
NVA
Assistant
collects
ingredients
from
stockroom
5 mins
NVA
Assistant
weighs
ingredients
5 mins
VA
Assistant
adds
ingredients
to batter
5 mins
VA
Assistant
returns to
the kitchen
with batter
4 mins
NVA
2
mins
30
mins
2
mins
30
mins
20
mins
30
mins
20
mins
1
min
1
min
1
min
1
min
PROCESS MAP TEMPLATE
Time
Non-Value Add
(including waste time)
1 hour 58 mins to
3 hours 20 mins
Value Add 2 hour 2 mins to5
hr 1 min
Customer
reports
technical
fault via
email(30mi
s for
process1 min
NVA
Customer
reports
technical
fault via
phone (2
min for
process)4 min
NVA
Support rep opens fault file and
assigns engineer(5 mins NVA)
5 mins
Support rep updates customer
on fault status(1 min VA)
Engin
eer
fixes
faults
2hour
s( VA)
Engin
eer to
mana
ger
5min
NVA
Informed
customer
fault
status
1 min
VA
Man
ager
fixes
fault
s
5 hr
VA
Infor
med
cust
ome
rs
1min
VA
File closed
1min
NVA
Informed
customers
fault fixed1 min
VA
Inform
customer
fault
status
1 min
VA
Use this template to create process maps for the main operational processes within your business. You can do the following:
• Copy, resize and move each map component.
• Adapt any of the example maps within this document to reflect your own business process.
• Print the map, or share it digitally.
Remember to calculate the Value Add and Non-Value Add time for your process. This will enable you to review its efficiency, and identify
areas for improvement as you progress through the module.

Case study process_maps

  • 1.
    BE HEALTHY WEBSITE Customer reports faultvia email 1 min NVA Time Non-Value Add (including waste time) 1 hour 58 mins to 3 hours 20 mins Value Add 2 hours 2 mins to 5 hours 3 mins Customer reports fault via phone 4 mins NVA Engineer fixes fault 2 hours VA Engineer escalates fault to manager 5 mins NVA Support rep opens fault file and assigns engineer 5 mins NVA Support rep updates customer on fault status 1 min VA Support rep updates customer on fault status 1 min VA Manager fixes fault 5 hours VA Support rep closes the customer’s fault file 1 min NVA Support rep informs customers that the fault is fixed 1 min VA 30 mins 2 mins 5 mins 1 hour 30 mins 20 mins 2 hours 5 mins 5 mins 2 mins
  • 2.
    JUN’S SERVICE BOOKINGPROCESS Time Non-Value Add (including waste time) 1 hour 21 minsValue Add 15 days, 4 hours, 15 mins + Customer calls for printer service 3 mins NVA Call center rep explains service options available 20 mins VA Booking team allocate an appointment 10 mins NVA Customer informed by email 1 min VA Logistics team schedules a visit 30 mins NVA Technician performs the service 1 hour VA Customer confirms the appointment X If not suitable, the booking team is notified by email 1 min NVA If suitable, the logistics team is notified by email 1 min NVA 5 mins 20 mins 5 mins 2 weeks 1 day 3 hours 3 hours NO YES
  • 3.
    MARTA’S BASIC PRODUCTIONPROCESS Time Non-Value Add (including waste time) 3 hours 14 min Value Add 2 hours 5 mins Assistant makes basic cake batter 15 mins VA Assistant checks daily recipe 10 mins NVA Owner checks batter 5 mins NVA Assistant bakes cake 1 hour VA Owner checks cake 5 mins NVA Assistant decorates cake 20 mins VA Owner checks decoration quality 5 mins NVA Assistant displays cake in bakery 20 mins VA Assistant checks daily recipe Assistant walks from kitchen to stockroom with batter 4 mins NVA Assistant collects ingredients from stockroom 5 mins NVA Assistant weighs ingredients 5 mins VA Assistant adds ingredients to batter 5 mins VA Assistant returns to the kitchen with batter 4 mins NVA 2 mins 30 mins 2 mins 30 mins 20 mins 30 mins 20 mins 1 min 1 min 1 min 1 min
  • 4.
    PROCESS MAP TEMPLATE Time Non-ValueAdd (including waste time) 1 hour 58 mins to 3 hours 20 mins Value Add 2 hour 2 mins to5 hr 1 min Customer reports technical fault via email(30mi s for process1 min NVA Customer reports technical fault via phone (2 min for process)4 min NVA Support rep opens fault file and assigns engineer(5 mins NVA) 5 mins Support rep updates customer on fault status(1 min VA) Engin eer fixes faults 2hour s( VA) Engin eer to mana ger 5min NVA Informed customer fault status 1 min VA Man ager fixes fault s 5 hr VA Infor med cust ome rs 1min VA File closed 1min NVA Informed customers fault fixed1 min VA Inform customer fault status 1 min VA Use this template to create process maps for the main operational processes within your business. You can do the following: • Copy, resize and move each map component. • Adapt any of the example maps within this document to reflect your own business process. • Print the map, or share it digitally. Remember to calculate the Value Add and Non-Value Add time for your process. This will enable you to review its efficiency, and identify areas for improvement as you progress through the module.