Case: Commercial Building using
Elematic Precast Technology
IT building with MLCP project
2017
Project :
IT Building- G+6(2 basement)
9mt Grid – 5Lac sq.ft BUA
MLCP G+8( 16Mtr span)-4Lac sq.ft BUA
Technology used: Elematic Finland
Office Structure: Column+ Beam Frame with Prestressed Hollow core slab
Parking structure – Wall Frame structure with Prestressed Hollow core slabs
ARCHITECTS Perspective- Office building
6/13/2017 Presented by Shridhar Rao 2
ARCHITECTS Perspective- MLCP building
6/13/2017 Presented by Shridhar Rao 3
Layout of the Buildings
6/13/2017 Presented by Shridhar Rao 4
MLCP & IT building
6/13/2017 Presented by Shridhar Rao 5
MLCP Building
completed
IT Building in
progress
400 Ton Hydraulic Mobile Luffing crane used on
MLCP construction to lift walls and slabs
6/13/2017 Presented by Shridhar Rao 6
IT building-9mtr span – in progress
6/13/2017 Presented by Shridhar Rao 7
Pre stressed
Hollow core slabs
Prestressed BeamPrecast column
IT building – In progress
6/13/2017 Presented by Shridhar Rao 8
Double wall for
basement retaining
wall and shear wall
IT Building
6/13/2017 Presented by Shridhar Rao 9
Waterproofing
Membrane
Reinforcement
bars to be bent
on HCS
MLCP Entrance
6/13/2017 Presented by Shridhar Rao 10
Column Corbel
MLCP Entrance Ramp
6/13/2017 Presented by Shridhar Rao 11
Intermediate
Beam
supporting
HCS
MLCP with Hollow core slab spanning 16MT –
Column free space
6/13/2017 Presented by Shridhar Rao 12
Load bearing
Wall
Load Bearing walls with openings
6/13/2017 Presented by Shridhar Rao 13
MLCP Building- 16Mtr span
6/13/2017 Presented by Shridhar Rao 14
Façade Panels(Non
load bearing)
MLCP Building- 16Mtr column free space
www.elematic.com6/13/2017 Presented by Shridhar Rao 15
Completed Building!
www.elematic.com6/13/2017 Presented by Shridhar Rao 16
MLCP Building IT Building
Completed Building- Thank you
www.elematic.com6/13/2017 Presented by Shridhar Rao 17

Case: IT building project using Precast Technology