SlideShare a Scribd company logo
1 of 51
FINAL DESIGN PRESENTATION
            TEAM 2-6
CHRIS SCHULTZ     STRUCTURAL
   DAVID LANE     SCHEDULING/ COST ESTIMATION
MARLA WATSON      SITE & TRANSPORTATION
 JAMIE FULLER     HYDROLOGY & HYDRAULICS
Objective


• To provide Capstone Developers with a final design of The
  Hangout

• To provide Clemson with an entertainment facility

• To provide Clemson’s campus with a late night dining option

• To further draw potential students to Clemson
Project Summary


•   The Hangout is a movie
    theater, restaurant, and
    meeting facility

•   Located on undeveloped land
    on Perimeter Road

•   Two story, 25,943 sq. ft.

•   Steel Frame Structure
Architecture & Structural Design

        Design Expert: Chris Schultz
Design Procedure
1. Architectural      4. Lateral Bracing

2. Framing            5. Computer Design and Check

3. Foundation
Architecture

•       Multi-use building under 3 assembly groups:

    •     Movie Theater, Restaurant, and Educational

•       Two 80-seat theaters with stadium seating

    •     Concession/Lobby/Arcade

•       Restaurant

•       2 Meeting Rooms and 2 Conference Rooms
Architecture
Ground Floor
Second Floor
Architecture
Structural Design
•       Roof
    •     1.5F22 steel deck

    •     Steel joists system

    •     ¼”/ft. slope with interior drainage

•       Floor
    •     1.5C22 steel deck with 4.5” concrete
          slab

    •     Steel W-flange beam system

•       CMU Wall
Roof Framing Plan



 Dead:
28 PSF

               Minimum Roof
                   Live:
                  20 PSF
Floor Framing Plan


              EDUCATIONAL
                 40 PSF
 Dead
Load: 70
  PSF

             ASSEMBLY:
              100 PSF
Columns and Foundation Design

•       Columns
    •     W-Flange beams

    •     Span both floors (30 ft.)

•       Footings
    •     Steel reinforced square footings

    •     CMU wall footing

•       5” Concrete Slab on Grade
Foundation Design

        W8x24


        W8x31
CMU Wall System


•   8” CMU Wall

•   2” Air Space

•   4” Brick Veneer



•   #4@24” Rebar
Hydrology & Hydraulics

   Design Expert: Jamie Fuller
Hydrology & Hydraulics Overview
  Pre & Post Development
         Conditions

       • Site Description
   • Sub-Basin Delineation
      • Flow Description
  • Hydrograph Generation

    Storm water Design
       Methodology

  • Storm water Management
• Computer Model Description

Storm water Design Analysis
Pre & Post Development Site Conditions

*Post-development flow must be less than or equal to the Pre-development flow.*


   Pre-Development                             Post-Development
   • Residual Grass Cover                    • Grass cover & Asphalt cover
   • 3 Pervious Sub-Basins                   • 11 Pervious Sub-Basins
   • 0 Impervious Sub-Basins                 • 19 Impervious Sub-Basins
   • 1 Catch Basin                           • 1 Catch Basin
                                             • 1 Storm water Pond (Detention)
                                             • 19 Inlet Structures
                                             • 24 Pipe Structures
                                             • Internal Roof Drainage
Pre-Developed Site




                                    EXISTING
                                   CATCHBASIN




               EXISTING DITCH
            ALONG PERIMETER ROAD
Pre-Development Sub-Basin Delineation




                     Sub-Basin    Area      Time of
                                 [acres]   Conc. [hr]

                        A        0.282       0.070
                        B        3.065       0.191
                        C        1.137       0.104
Pre-Development Water Flow
Post-Development Sub-Basin Delineation
                                   Table HT2: Post-Development Sub-Basin Summary
                                                                  Time of      Time of
                     Sub-                                 Slope Concentratio Concentratio Curve
                     Basin     Area      Area    Length          n (2-Year)  n (10-Year) Number

                                [ft2]    [acre]     [ft]    [ft/ft]    [hr]    [hr]
                      1      9,953.36    0.228    110.37   0.0181     0.082   0.068       71
                      2      6,581.43    0.151    121.42   0.1070     0.043   0.036       71
                      3      8,427.00    0.193    121.70   0.0821     0.048   0.040       71
                      4      14,041.94   0.322    149.83   0.0800     0.057   0.047       71
                      5       5,000.27   0.114    119.45   0.0200     0.021   0.017       98
                      6      11,468.20   0.263    152.65   0.0459     0.152   0.126       71

                       7     10,844.39   0.248    146.75   0.0272     0.087   0.072       71
                       8      7,942.03   0.182    181.25   0.0496     0.082   0.067       71
                       9      5,775.20   0.132    178.20   0.0200     0.029   0.024       98
                      10      8,015.37   0.184    131.73   0.0455     0.065   0.054       71
                      11      2,393.74   0.054    152.90   0.0200     0.026   0.021       98
                      12      4,338.39   0.099    135.40   0.0200     0.023   0.019       98
                      13      3,144.82   0.072     76.91   0.0200     0.015   0.012       98
                      14      3,102.54   0.071     77.15   0.0200     0.015   0.012       98
                      15      3,015.38   0.069     77.63   0.0200     0.015   0.012       98
                      16      4,448.02   0.102     21.42   0.0200     0.005   0.004       98
                      17      9,533.99   0.218    155.65   0.0200     0.026   0.022       98
                      18      6,087.15   0.139    154.64   0.0200     0.026   0.022       98
                      19      8,338.67   0.191     63.93   0.0200     0.013   0.010       98
                      20     11,914.80   0.273    219.47   0.0318     0.113   0.094       71
                      21      3,879.63   0.089     80.63   0.0200     0.015   0.013       98
                      22      3,562.09   0.081     93.52   0.0320     0.057   0.047       71
                      23      5,681.28   0.130    187.90   0.0319     0.100   0.082       71
                      24      4,285.15   0.098     30.66   0.0200     0.007   0.006       98
                      25      5,294.88   0.121     42.31   0.0200     0.009   0.007       98
                      26     16,978.62   0.389    102.00   0.0200     0.019   0.015       98
                      27      2,754.89   0.063     76.48   0.0200     0.015   0.012       98
                      28      3,296.30   0.075     82.05   0.0200     0.016   0.013       98
                      29      3,845.59   0.088     88.30   0.0200     0.017   0.014       98
                      30      3,725.40   0.085    178.30   0.0200     0.029   0.024       98
Post-Development Water Flow
Post-Development Pipe Layout
      (Drainage System)

        INLET




                            DETENTION
                              POND




                  CULVERT
Stormwater Management – Pipe Structures

                         Table HT4: Pipe Properties Summary Table
                  Name     Diameter   Length   Slope        Invert     Invert  Material
                                                          Elevation   Elevatio
                                                             OUT        n IN
                             [in]       [ft]    [ft/ft]       [ft]       [ft]
                    1          9       266      0.011       802.0      799.0    PVC
                    2        12        210      0.009       793.0      791.0    PVC
                    3         11       257      0.015       790.0      786.0    PVC
                    4          8        22      0.022       791.0      790.5    PVC
                    5        10         62      0.064       786.0      782.0    PVC
                    6        10         60      0.029      783.75      782.0    PVC
                    7        10         55      0.031      787.75      784.0    PVC
                    8        12         55      0.027       787.5      786.0    PVC
                    9        12         54      0.018       789.0      788.0    PVC
                   10        12         55      0.054       785.0      782.0 Concrete
                   11        12         87      0.040       793.5      790.0    PVC
                   12        15        212      0.021       798.5      794.0    PVC
                   13        15        167      0.050       802.5      794.0    PVC
                   14        10         58      0.043       796.5      794.0    PVC
                   15          8        54      0.037       793.0      791.0    PVC
                   16        12         54      0.018       790.0      789.0    PVC
                   17        10         23      0.086       789.0      787.0    PVC
                   18         11       150      0.013       785.0      783.0 Concrete
                   19          8        20      0.075       782.0      780.5    PVC
                   20          4        27     Vertical    Vertical   Vertical  PVC
                   21          6        27     Vertical    Vertical   Vertical  PVC
                   22          8        27     Vertical    Vertical   Vertical  PVC
                   23          8        27     Vertical    Vertical   Vertical  PVC
                   24          8        27     Vertical    Vertical   Vertical  PVC
Stormwater Management – Inlet Structures
                                                     Table HT3: Drainage Inlet and Gutter Summary Table
                                             Inlets                                                                     Gutters
 Name         Type       Location   Length     Throat      Grate Width Grate Length      RIM       Curb     Slope     Width     Pavement    Longitudinal
                                                                                      Elevation    Height                         Slope        Slope
                                     [ft]       [ft]           [ft]         [ft]         [ft]       [in]    [ft/ft]    [ft]       [ft/ft]      [ft/ft]
   1       Combination   On Grade     3          4              3            3          804.5         6     0.02        3         0.02         0.01
   2       Combination   On Grade     3          4              3            3          800.0         6     0.02        3         0.02         0.01
   3       Combination   On Grade     3          4              3            3          793.0         6     0.02        3         0.02         0.01
   4         Slotted     On Grade     3          4              3            3          787.0         6     0.02        3         0.02         0.01
   5       Combination   On Grade     3          4              3            3          793.0         6     0.02        3         0.02         0.01
   6       Combination   On Grade     3          4              3            3          798.0         6     0.02        3         0.02         0.01
   7       Combination   On Grade     3          4              3            3          795.0         6     0.02        3         0.02         0.01
   8       Combination   On Grade     3          4              3            3          792.0         6     0.02        3         0.02         0.01
   9       Combination   On Grade     3          4              3            3          791.0         6     0.02        3         0.02         0.01
  10       Combination   On Grade     3          4              3            3          788.0         6     0.02        3         0.02         0.01
  11       Combination   On Grade     3          4              3            3          783.0         6     0.02        3         0.02         0.01
  12       Combination   On Grade     3          4              3            3          785.0         6     0.02        3         0.02         0.01
  13       Combination   On Grade     3          4              3            3          787.5         6     0.02        3         0.02         0.01
  14       Combination   On Grade     3          4              3            3          789.7         6     0.02        3         0.02         0.01
  15       Combination   On Grade     3          4              3            3          791.4         6     0.02        3         0.02         0.01
  16       Combination   On Grade     3          4              3            3          805.0         6     0.02        3         0.02         0.01
  17       Combination   On Grade     3          4              3            3          800.0         6     0.02        3         0.02         0.01
  18       Combination   On Grade     3          4              3            3          796.0         6     0.02        3         0.02         0.01
  19         Slotted     On Grade     3          4              3            3          787.0         6     0.02        3         0.02         0.01
                                    Width     Length       Grate Width Grate Length      RIM                          Width     Pavement    Longitudinal
 Name         Type       Location                                                     Elevation                                   Slope        Slope
                                     [in]       [in]           [ft]         [ft]         [ft]                          [ft]        [ft]         [ft]
Existing
 Catch        Grate       On sag      1          6              3            5         775.73                           3         0.02         0.02
 Basin
Computer Model
  I-INLET
O-OUTFALL                              UNITS ARE   CONNECTED BY NON-ROUTED
                                       CONNECTORS, CIRCULAR CONDUIT, AND
                                                   PIPE STRUCTURES.




                                                           PERVIOUS AREA




  IMPERVIOUS AREA




                      DETENTION POND
2-YR 24-HR Hydrology & Hydraulics Analysis

            Pre-Development                      Post-Development
                                                     w/o Pond




                              Post-Development
                                   w/Pond
10-YR 24-HR Hydrology & Hydraulics Analysis
             Pre-Development
                                                  Post-Development
                                                      w/o Pond




                               Post-Development
                                    w/Pond
100-YR Rainfall Event Hydrograph
Peak Runoff Discharges

                   Table HT5: Hydrograph Essential Data

                    Storm Event         Peak Discharge    Runoff Volume
                          [YR]               [cfs]           [acre-ft]
Pre-Development          2-Year             1.953             0.2531
                         10-Year            6.606             0.6585
Post-Development         2-Year             9.691             0.8414
  Without Pond           10-Year            12.50             1.3333
                         2-Year             2.574             0.1869
Post-Development         10-Year            5.601             0.3649
    With Pond           100-Year            11.81             0.8008
Storm water Pond Elevation View




      Maximum stage during 100-YR storm:
         7.90 feet (freeboard not used)

             Top Elevation: 787 feet
            Bottom Elevation: 777 feet
Site and Transportation

   Design Expert: Marla Watson
Site & Transportation Overview

• Site Layout & Setbacks
• Site Grading Plan
• Site Traffic Plan
• Access Road Cross Section
• Site Lighting Plan
Site Layout and Setbacks


                                       TYPICAL
                                      SETBACKS




                       ACCESS ROADS




15’X15’ DUMPSTER PAD
Site Grading Plan

                     PERMANENT SLOPE
                           4:1




                                       DETENTION POND
                                        787’ SURFACE
                                         777’ FLOOR
                                       1680 CY VOLUME



805’ BUILDING
Site Traffic Plan

1-WAY DELIVERY TRUCK       PARKING LOT
    ACCESS ROAD        2-WAY ACCESS AISLES




                                  CAT BUS STOP

                                                            75 REGULAR SPACES




                                             BICYCLE RACK
Access Road Cross Section
Site Lighting Plan




                          DOUBLE ARM PARKING LOT
                           30’ HIGH WITH 14” ARMS
                               1.0 FOOTCANDLE




                     SITE LIGHTING
Construction Scheduling and Cost
           Estimation


         Design Expert: David Lane
Schedule



                          Define
                          workdays
             Sequencing


Durations
Schedule



TASK COST    TASK CODE ACCOUNT NAME                     UNIT OF   QTY        NO. OF CREW      DURATION WEATHER     Total
ACCOUNT CODE                                            MEASURE              CREWS PROD.               ADJ.        Duration

03 - CONCRETE
                   REGULAR CONCRETE, 4000 PSI, 4"
03 30 53.40 3150
(P.68 IN BCCD)                                          SF          2100          1    C-8         2613      0.1              1
                   EQUIPMENT PAD 8'X8'X 10"
03 30 53.40 3580
(P. 68 IN BCCD)                                         EACH            1         1    C-8           8       0.1              1
03 30 53.40 3940   FOOTING, STRIP 3000 PSI 24" X 12",
(P. 69 IN BCCD)    REINFORCED                           CY              38        1   C-14L         48       0.1              1
Schedule
Schedule




Mobilization                 Completion
                154 eight-
  Date:                        Date:
                  hour
January 9,                   August 13,
                workdays
  2012                         2012
Cost Estimate



                              Adjustment
                              Factors
                  Division
                  Breakdown
      Line Item


WBS
Cost Estimate

TASK COST                 TASK CODE    UNIT OF   QTY        UNIT          CREW         TOTAL COST
ACCOUNT CODE              ACCOUNT      MEASURE              COST         INCREASE
                          NAME                                           COST

04- MASONRY
                          STANDARD
04 21 13.13 2000 (P. 89   BRICK
IN BCCD)                  VANEER       SF              15820 $   14.35   $   218,316   $     445,333
                          REINFORCED
                          CONCRETE
04 22 10.24 0200 (P.96    BLOCK EXT.
IN BCCD)                  8"X8"X16"    SF              15820 $   10.25   $   139,849   $     302,004
Cost Estimate


                             Cost of Site Features

Design Feature                          Estimated Total Cost   Percent of Total Project Cost


Hydrology and Hydraulic Features               $      92,000                             2%

Site and Transportation Features               $     900,000                           21%

Structural and Architectural Features          $   1,100,000                           25%
Cost Estimate
DIVISION                       COST           COST PER
                                              SF
DIVISION TOTAL                 $    4,838,253 $     186
LOCATION MODIFICATION [.76]    $    3,677,072
GENERAL CONDITIONS [+10%]      $      367,707
CONTINGENCY [+5%]              $      183,854
TOTAL PROJECT COST             $    4,228,633 $     163
Conclusion


•   25,943 sq. ft. multiuse facility

•   2 stadium seating theaters

•   81 parking spaces + CAT access


•   154 eight-hour workdays, August 13,
    2012.

•   $4.2 Million, $163/SF
QUESTIONS?

More Related Content

Viewers also liked

Net2NO goes to SXSW - Case Study
Net2NO goes to SXSW - Case StudyNet2NO goes to SXSW - Case Study
Net2NO goes to SXSW - Case StudyChris Schultz
 
Introduction to Smiths Detection
Introduction to Smiths DetectionIntroduction to Smiths Detection
Introduction to Smiths DetectionSmiths Detection
 
Niko Niko Product Intro
Niko Niko Product IntroNiko Niko Product Intro
Niko Niko Product IntroChris Schultz
 
Concept to deployment: The Lifecycle of Explosives Detection
Concept to deployment: The Lifecycle of Explosives DetectionConcept to deployment: The Lifecycle of Explosives Detection
Concept to deployment: The Lifecycle of Explosives DetectionSmiths Detection
 
Brooke McMillian- How To Build A Great Online Community
Brooke McMillian- How To Build A Great Online CommunityBrooke McMillian- How To Build A Great Online Community
Brooke McMillian- How To Build A Great Online CommunityChris Schultz
 
Ryan Delk - More than #hustle: breaking into new markets
Ryan Delk -  More than #hustle: breaking into new marketsRyan Delk -  More than #hustle: breaking into new markets
Ryan Delk - More than #hustle: breaking into new marketsChris Schultz
 
NIU Blackboard Portfolio Pilot Information
NIU Blackboard Portfolio Pilot InformationNIU Blackboard Portfolio Pilot Information
NIU Blackboard Portfolio Pilot InformationJason Rhode
 
Digby presentation
Digby presentationDigby presentation
Digby presentationshkirsop
 
Capsim Presentation (MBA)
Capsim Presentation (MBA)Capsim Presentation (MBA)
Capsim Presentation (MBA)Joshua D. Lee
 
Strategy Digby Mgt667 001
Strategy Digby Mgt667 001Strategy Digby Mgt667 001
Strategy Digby Mgt667 001hutbay
 
Patrick Comer – Get over yourself – How to hire, train, and develop a high pe...
Patrick Comer – Get over yourself – How to hire, train, and develop a high pe...Patrick Comer – Get over yourself – How to hire, train, and develop a high pe...
Patrick Comer – Get over yourself – How to hire, train, and develop a high pe...Chris Schultz
 
Capstone simulation presentation
Capstone simulation presentationCapstone simulation presentation
Capstone simulation presentationDev Anumolu
 
Capsim Andrews Results Presentation
Capsim Andrews Results PresentationCapsim Andrews Results Presentation
Capsim Andrews Results PresentationEvgenii Gvozdev
 

Viewers also liked (17)

Net2NO goes to SXSW - Case Study
Net2NO goes to SXSW - Case StudyNet2NO goes to SXSW - Case Study
Net2NO goes to SXSW - Case Study
 
HTT May 2015 Issue
HTT May 2015 IssueHTT May 2015 Issue
HTT May 2015 Issue
 
Diapositivas infor 3
Diapositivas infor 3Diapositivas infor 3
Diapositivas infor 3
 
Introduction to Smiths Detection
Introduction to Smiths DetectionIntroduction to Smiths Detection
Introduction to Smiths Detection
 
Niko Niko Product Intro
Niko Niko Product IntroNiko Niko Product Intro
Niko Niko Product Intro
 
Concept to deployment: The Lifecycle of Explosives Detection
Concept to deployment: The Lifecycle of Explosives DetectionConcept to deployment: The Lifecycle of Explosives Detection
Concept to deployment: The Lifecycle of Explosives Detection
 
HFN Media Kit
HFN Media KitHFN Media Kit
HFN Media Kit
 
Brooke McMillian- How To Build A Great Online Community
Brooke McMillian- How To Build A Great Online CommunityBrooke McMillian- How To Build A Great Online Community
Brooke McMillian- How To Build A Great Online Community
 
Ryan Delk - More than #hustle: breaking into new markets
Ryan Delk -  More than #hustle: breaking into new marketsRyan Delk -  More than #hustle: breaking into new markets
Ryan Delk - More than #hustle: breaking into new markets
 
NIU Blackboard Portfolio Pilot Information
NIU Blackboard Portfolio Pilot InformationNIU Blackboard Portfolio Pilot Information
NIU Blackboard Portfolio Pilot Information
 
Digby presentation
Digby presentationDigby presentation
Digby presentation
 
Capsim Presentation (MBA)
Capsim Presentation (MBA)Capsim Presentation (MBA)
Capsim Presentation (MBA)
 
Strategy Digby Mgt667 001
Strategy Digby Mgt667 001Strategy Digby Mgt667 001
Strategy Digby Mgt667 001
 
Patrick Comer – Get over yourself – How to hire, train, and develop a high pe...
Patrick Comer – Get over yourself – How to hire, train, and develop a high pe...Patrick Comer – Get over yourself – How to hire, train, and develop a high pe...
Patrick Comer – Get over yourself – How to hire, train, and develop a high pe...
 
Capsim presentation
Capsim presentationCapsim presentation
Capsim presentation
 
Capstone simulation presentation
Capstone simulation presentationCapstone simulation presentation
Capstone simulation presentation
 
Capsim Andrews Results Presentation
Capsim Andrews Results PresentationCapsim Andrews Results Presentation
Capsim Andrews Results Presentation
 

Similar to Final Design Presentation for The Hangout Entertainment Facility

. Narmada Canal ExPresentation for Extradose Bridge for Gandhi Nagar Metro....
.   Narmada Canal ExPresentation for Extradose Bridge for Gandhi Nagar Metro.....   Narmada Canal ExPresentation for Extradose Bridge for Gandhi Nagar Metro....
. Narmada Canal ExPresentation for Extradose Bridge for Gandhi Nagar Metro....IndraNathMishra2
 
Ready rackner for qs
Ready rackner for qsReady rackner for qs
Ready rackner for qsHiren Thakkar
 
232365141 1-qs-techinical-data
232365141 1-qs-techinical-data232365141 1-qs-techinical-data
232365141 1-qs-techinical-datahlksd
 
cost appraisal
cost appraisalcost appraisal
cost appraisalahmong4
 
Chittagong City Outer Ring Road Project
Chittagong City Outer Ring Road ProjectChittagong City Outer Ring Road Project
Chittagong City Outer Ring Road ProjectRakibul Haque
 
[Name Sponged] Consulting Project
[Name Sponged] Consulting Project[Name Sponged] Consulting Project
[Name Sponged] Consulting ProjectRyan Elder
 
Dewatering project pit alam 1 3
Dewatering project pit alam 1   3Dewatering project pit alam 1   3
Dewatering project pit alam 1 3Muhammad Ichsan
 
Deep groove ball bearing 6000 series
Deep groove ball bearing 6000 seriesDeep groove ball bearing 6000 series
Deep groove ball bearing 6000 seriesCathy Zhang
 
Thermitrex Sks Crane Rail Process
Thermitrex Sks Crane Rail ProcessThermitrex Sks Crane Rail Process
Thermitrex Sks Crane Rail ProcessThermitrex
 
Ship design project Final presentation
Ship design project Final presentationShip design project Final presentation
Ship design project Final presentationKifayath Chowdhury
 
FIELD DEVELOPMENT REPORT PROJECT OF DRILLING DEPT
FIELD DEVELOPMENT REPORT PROJECT OF DRILLING DEPTFIELD DEVELOPMENT REPORT PROJECT OF DRILLING DEPT
FIELD DEVELOPMENT REPORT PROJECT OF DRILLING DEPTMUHAMMAD NOMAN KHAN
 
Term Project Paper on Design of Shallow and Deep Foundation for a cement plan...
Term Project Paper on Design of Shallow and Deep Foundation for a cement plan...Term Project Paper on Design of Shallow and Deep Foundation for a cement plan...
Term Project Paper on Design of Shallow and Deep Foundation for a cement plan...Rakibul Hasan,MEng,EIT
 
Saint Francis & Purple Vision NAHF Presentation 24/3/12
Saint Francis & Purple Vision NAHF Presentation 24/3/12Saint Francis & Purple Vision NAHF Presentation 24/3/12
Saint Francis & Purple Vision NAHF Presentation 24/3/12Purple Vision
 
Saint Francis & Purple Vision NAHF Presentation 24/3/12
Saint Francis & Purple Vision NAHF Presentation 24/3/12Saint Francis & Purple Vision NAHF Presentation 24/3/12
Saint Francis & Purple Vision NAHF Presentation 24/3/12Purple Vision
 

Similar to Final Design Presentation for The Hangout Entertainment Facility (20)

. Narmada Canal ExPresentation for Extradose Bridge for Gandhi Nagar Metro....
.   Narmada Canal ExPresentation for Extradose Bridge for Gandhi Nagar Metro.....   Narmada Canal ExPresentation for Extradose Bridge for Gandhi Nagar Metro....
. Narmada Canal ExPresentation for Extradose Bridge for Gandhi Nagar Metro....
 
Ready rackner for qs
Ready rackner for qsReady rackner for qs
Ready rackner for qs
 
QS.pdf
QS.pdfQS.pdf
QS.pdf
 
232365141 1-qs-techinical-data
232365141 1-qs-techinical-data232365141 1-qs-techinical-data
232365141 1-qs-techinical-data
 
cost appraisal
cost appraisalcost appraisal
cost appraisal
 
Chittagong City Outer Ring Road Project
Chittagong City Outer Ring Road ProjectChittagong City Outer Ring Road Project
Chittagong City Outer Ring Road Project
 
[Name Sponged] Consulting Project
[Name Sponged] Consulting Project[Name Sponged] Consulting Project
[Name Sponged] Consulting Project
 
Jaw Crusher
Jaw CrusherJaw Crusher
Jaw Crusher
 
Dewatering project pit alam 1 3
Dewatering project pit alam 1   3Dewatering project pit alam 1   3
Dewatering project pit alam 1 3
 
Engineering Simulation
Engineering SimulationEngineering Simulation
Engineering Simulation
 
Deep groove ball bearing 6000 series
Deep groove ball bearing 6000 seriesDeep groove ball bearing 6000 series
Deep groove ball bearing 6000 series
 
Thermitrex Sks Crane Rail Process
Thermitrex Sks Crane Rail ProcessThermitrex Sks Crane Rail Process
Thermitrex Sks Crane Rail Process
 
Group 3 Presentation
Group 3 PresentationGroup 3 Presentation
Group 3 Presentation
 
Ship design project Final presentation
Ship design project Final presentationShip design project Final presentation
Ship design project Final presentation
 
LABORATORIO DE VERTEDEROS
LABORATORIO DE VERTEDEROS LABORATORIO DE VERTEDEROS
LABORATORIO DE VERTEDEROS
 
FIELD DEVELOPMENT REPORT PROJECT OF DRILLING DEPT
FIELD DEVELOPMENT REPORT PROJECT OF DRILLING DEPTFIELD DEVELOPMENT REPORT PROJECT OF DRILLING DEPT
FIELD DEVELOPMENT REPORT PROJECT OF DRILLING DEPT
 
Rab
RabRab
Rab
 
Term Project Paper on Design of Shallow and Deep Foundation for a cement plan...
Term Project Paper on Design of Shallow and Deep Foundation for a cement plan...Term Project Paper on Design of Shallow and Deep Foundation for a cement plan...
Term Project Paper on Design of Shallow and Deep Foundation for a cement plan...
 
Saint Francis & Purple Vision NAHF Presentation 24/3/12
Saint Francis & Purple Vision NAHF Presentation 24/3/12Saint Francis & Purple Vision NAHF Presentation 24/3/12
Saint Francis & Purple Vision NAHF Presentation 24/3/12
 
Saint Francis & Purple Vision NAHF Presentation 24/3/12
Saint Francis & Purple Vision NAHF Presentation 24/3/12Saint Francis & Purple Vision NAHF Presentation 24/3/12
Saint Francis & Purple Vision NAHF Presentation 24/3/12
 

Recently uploaded

Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesFatimaKhan178732
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Celine George
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionSafetyChain Software
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxOH TEIK BIN
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsKarinaGenton
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application ) Sakshi Ghasle
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introductionMaksud Ahmed
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 

Recently uploaded (20)

Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and Actinides
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
 
Staff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSDStaff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSD
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory Inspection
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptx
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its Characteristics
 
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application )
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 

Final Design Presentation for The Hangout Entertainment Facility

  • 1. FINAL DESIGN PRESENTATION TEAM 2-6 CHRIS SCHULTZ STRUCTURAL DAVID LANE SCHEDULING/ COST ESTIMATION MARLA WATSON SITE & TRANSPORTATION JAMIE FULLER HYDROLOGY & HYDRAULICS
  • 2. Objective • To provide Capstone Developers with a final design of The Hangout • To provide Clemson with an entertainment facility • To provide Clemson’s campus with a late night dining option • To further draw potential students to Clemson
  • 3. Project Summary • The Hangout is a movie theater, restaurant, and meeting facility • Located on undeveloped land on Perimeter Road • Two story, 25,943 sq. ft. • Steel Frame Structure
  • 4. Architecture & Structural Design Design Expert: Chris Schultz
  • 5. Design Procedure 1. Architectural 4. Lateral Bracing 2. Framing 5. Computer Design and Check 3. Foundation
  • 6. Architecture • Multi-use building under 3 assembly groups: • Movie Theater, Restaurant, and Educational • Two 80-seat theaters with stadium seating • Concession/Lobby/Arcade • Restaurant • 2 Meeting Rooms and 2 Conference Rooms
  • 11. Structural Design • Roof • 1.5F22 steel deck • Steel joists system • ¼”/ft. slope with interior drainage • Floor • 1.5C22 steel deck with 4.5” concrete slab • Steel W-flange beam system • CMU Wall
  • 12. Roof Framing Plan Dead: 28 PSF Minimum Roof Live: 20 PSF
  • 13. Floor Framing Plan EDUCATIONAL 40 PSF Dead Load: 70 PSF ASSEMBLY: 100 PSF
  • 14. Columns and Foundation Design • Columns • W-Flange beams • Span both floors (30 ft.) • Footings • Steel reinforced square footings • CMU wall footing • 5” Concrete Slab on Grade
  • 15. Foundation Design W8x24 W8x31
  • 16. CMU Wall System • 8” CMU Wall • 2” Air Space • 4” Brick Veneer • #4@24” Rebar
  • 17. Hydrology & Hydraulics Design Expert: Jamie Fuller
  • 18. Hydrology & Hydraulics Overview Pre & Post Development Conditions • Site Description • Sub-Basin Delineation • Flow Description • Hydrograph Generation Storm water Design Methodology • Storm water Management • Computer Model Description Storm water Design Analysis
  • 19. Pre & Post Development Site Conditions *Post-development flow must be less than or equal to the Pre-development flow.* Pre-Development Post-Development • Residual Grass Cover • Grass cover & Asphalt cover • 3 Pervious Sub-Basins • 11 Pervious Sub-Basins • 0 Impervious Sub-Basins • 19 Impervious Sub-Basins • 1 Catch Basin • 1 Catch Basin • 1 Storm water Pond (Detention) • 19 Inlet Structures • 24 Pipe Structures • Internal Roof Drainage
  • 20. Pre-Developed Site EXISTING CATCHBASIN EXISTING DITCH ALONG PERIMETER ROAD
  • 21. Pre-Development Sub-Basin Delineation Sub-Basin Area Time of [acres] Conc. [hr] A 0.282 0.070 B 3.065 0.191 C 1.137 0.104
  • 23. Post-Development Sub-Basin Delineation Table HT2: Post-Development Sub-Basin Summary Time of Time of Sub- Slope Concentratio Concentratio Curve Basin Area Area Length n (2-Year) n (10-Year) Number [ft2] [acre] [ft] [ft/ft] [hr] [hr] 1 9,953.36 0.228 110.37 0.0181 0.082 0.068 71 2 6,581.43 0.151 121.42 0.1070 0.043 0.036 71 3 8,427.00 0.193 121.70 0.0821 0.048 0.040 71 4 14,041.94 0.322 149.83 0.0800 0.057 0.047 71 5 5,000.27 0.114 119.45 0.0200 0.021 0.017 98 6 11,468.20 0.263 152.65 0.0459 0.152 0.126 71 7 10,844.39 0.248 146.75 0.0272 0.087 0.072 71 8 7,942.03 0.182 181.25 0.0496 0.082 0.067 71 9 5,775.20 0.132 178.20 0.0200 0.029 0.024 98 10 8,015.37 0.184 131.73 0.0455 0.065 0.054 71 11 2,393.74 0.054 152.90 0.0200 0.026 0.021 98 12 4,338.39 0.099 135.40 0.0200 0.023 0.019 98 13 3,144.82 0.072 76.91 0.0200 0.015 0.012 98 14 3,102.54 0.071 77.15 0.0200 0.015 0.012 98 15 3,015.38 0.069 77.63 0.0200 0.015 0.012 98 16 4,448.02 0.102 21.42 0.0200 0.005 0.004 98 17 9,533.99 0.218 155.65 0.0200 0.026 0.022 98 18 6,087.15 0.139 154.64 0.0200 0.026 0.022 98 19 8,338.67 0.191 63.93 0.0200 0.013 0.010 98 20 11,914.80 0.273 219.47 0.0318 0.113 0.094 71 21 3,879.63 0.089 80.63 0.0200 0.015 0.013 98 22 3,562.09 0.081 93.52 0.0320 0.057 0.047 71 23 5,681.28 0.130 187.90 0.0319 0.100 0.082 71 24 4,285.15 0.098 30.66 0.0200 0.007 0.006 98 25 5,294.88 0.121 42.31 0.0200 0.009 0.007 98 26 16,978.62 0.389 102.00 0.0200 0.019 0.015 98 27 2,754.89 0.063 76.48 0.0200 0.015 0.012 98 28 3,296.30 0.075 82.05 0.0200 0.016 0.013 98 29 3,845.59 0.088 88.30 0.0200 0.017 0.014 98 30 3,725.40 0.085 178.30 0.0200 0.029 0.024 98
  • 25. Post-Development Pipe Layout (Drainage System) INLET DETENTION POND CULVERT
  • 26. Stormwater Management – Pipe Structures Table HT4: Pipe Properties Summary Table Name Diameter Length Slope Invert Invert Material Elevation Elevatio OUT n IN [in] [ft] [ft/ft] [ft] [ft] 1 9 266 0.011 802.0 799.0 PVC 2 12 210 0.009 793.0 791.0 PVC 3 11 257 0.015 790.0 786.0 PVC 4 8 22 0.022 791.0 790.5 PVC 5 10 62 0.064 786.0 782.0 PVC 6 10 60 0.029 783.75 782.0 PVC 7 10 55 0.031 787.75 784.0 PVC 8 12 55 0.027 787.5 786.0 PVC 9 12 54 0.018 789.0 788.0 PVC 10 12 55 0.054 785.0 782.0 Concrete 11 12 87 0.040 793.5 790.0 PVC 12 15 212 0.021 798.5 794.0 PVC 13 15 167 0.050 802.5 794.0 PVC 14 10 58 0.043 796.5 794.0 PVC 15 8 54 0.037 793.0 791.0 PVC 16 12 54 0.018 790.0 789.0 PVC 17 10 23 0.086 789.0 787.0 PVC 18 11 150 0.013 785.0 783.0 Concrete 19 8 20 0.075 782.0 780.5 PVC 20 4 27 Vertical Vertical Vertical PVC 21 6 27 Vertical Vertical Vertical PVC 22 8 27 Vertical Vertical Vertical PVC 23 8 27 Vertical Vertical Vertical PVC 24 8 27 Vertical Vertical Vertical PVC
  • 27. Stormwater Management – Inlet Structures Table HT3: Drainage Inlet and Gutter Summary Table Inlets Gutters Name Type Location Length Throat Grate Width Grate Length RIM Curb Slope Width Pavement Longitudinal Elevation Height Slope Slope [ft] [ft] [ft] [ft] [ft] [in] [ft/ft] [ft] [ft/ft] [ft/ft] 1 Combination On Grade 3 4 3 3 804.5 6 0.02 3 0.02 0.01 2 Combination On Grade 3 4 3 3 800.0 6 0.02 3 0.02 0.01 3 Combination On Grade 3 4 3 3 793.0 6 0.02 3 0.02 0.01 4 Slotted On Grade 3 4 3 3 787.0 6 0.02 3 0.02 0.01 5 Combination On Grade 3 4 3 3 793.0 6 0.02 3 0.02 0.01 6 Combination On Grade 3 4 3 3 798.0 6 0.02 3 0.02 0.01 7 Combination On Grade 3 4 3 3 795.0 6 0.02 3 0.02 0.01 8 Combination On Grade 3 4 3 3 792.0 6 0.02 3 0.02 0.01 9 Combination On Grade 3 4 3 3 791.0 6 0.02 3 0.02 0.01 10 Combination On Grade 3 4 3 3 788.0 6 0.02 3 0.02 0.01 11 Combination On Grade 3 4 3 3 783.0 6 0.02 3 0.02 0.01 12 Combination On Grade 3 4 3 3 785.0 6 0.02 3 0.02 0.01 13 Combination On Grade 3 4 3 3 787.5 6 0.02 3 0.02 0.01 14 Combination On Grade 3 4 3 3 789.7 6 0.02 3 0.02 0.01 15 Combination On Grade 3 4 3 3 791.4 6 0.02 3 0.02 0.01 16 Combination On Grade 3 4 3 3 805.0 6 0.02 3 0.02 0.01 17 Combination On Grade 3 4 3 3 800.0 6 0.02 3 0.02 0.01 18 Combination On Grade 3 4 3 3 796.0 6 0.02 3 0.02 0.01 19 Slotted On Grade 3 4 3 3 787.0 6 0.02 3 0.02 0.01 Width Length Grate Width Grate Length RIM Width Pavement Longitudinal Name Type Location Elevation Slope Slope [in] [in] [ft] [ft] [ft] [ft] [ft] [ft] Existing Catch Grate On sag 1 6 3 5 775.73 3 0.02 0.02 Basin
  • 28. Computer Model I-INLET O-OUTFALL UNITS ARE CONNECTED BY NON-ROUTED CONNECTORS, CIRCULAR CONDUIT, AND PIPE STRUCTURES. PERVIOUS AREA IMPERVIOUS AREA DETENTION POND
  • 29. 2-YR 24-HR Hydrology & Hydraulics Analysis Pre-Development Post-Development w/o Pond Post-Development w/Pond
  • 30. 10-YR 24-HR Hydrology & Hydraulics Analysis Pre-Development Post-Development w/o Pond Post-Development w/Pond
  • 31. 100-YR Rainfall Event Hydrograph
  • 32. Peak Runoff Discharges Table HT5: Hydrograph Essential Data Storm Event Peak Discharge Runoff Volume [YR] [cfs] [acre-ft] Pre-Development 2-Year 1.953 0.2531 10-Year 6.606 0.6585 Post-Development 2-Year 9.691 0.8414 Without Pond 10-Year 12.50 1.3333 2-Year 2.574 0.1869 Post-Development 10-Year 5.601 0.3649 With Pond 100-Year 11.81 0.8008
  • 33. Storm water Pond Elevation View Maximum stage during 100-YR storm: 7.90 feet (freeboard not used) Top Elevation: 787 feet Bottom Elevation: 777 feet
  • 34. Site and Transportation Design Expert: Marla Watson
  • 35. Site & Transportation Overview • Site Layout & Setbacks • Site Grading Plan • Site Traffic Plan • Access Road Cross Section • Site Lighting Plan
  • 36. Site Layout and Setbacks TYPICAL SETBACKS ACCESS ROADS 15’X15’ DUMPSTER PAD
  • 37. Site Grading Plan PERMANENT SLOPE 4:1 DETENTION POND 787’ SURFACE 777’ FLOOR 1680 CY VOLUME 805’ BUILDING
  • 38. Site Traffic Plan 1-WAY DELIVERY TRUCK PARKING LOT ACCESS ROAD 2-WAY ACCESS AISLES CAT BUS STOP 75 REGULAR SPACES BICYCLE RACK
  • 39. Access Road Cross Section
  • 40. Site Lighting Plan DOUBLE ARM PARKING LOT 30’ HIGH WITH 14” ARMS 1.0 FOOTCANDLE SITE LIGHTING
  • 41. Construction Scheduling and Cost Estimation Design Expert: David Lane
  • 42. Schedule Define workdays Sequencing Durations
  • 43. Schedule TASK COST TASK CODE ACCOUNT NAME UNIT OF QTY NO. OF CREW DURATION WEATHER Total ACCOUNT CODE MEASURE CREWS PROD. ADJ. Duration 03 - CONCRETE REGULAR CONCRETE, 4000 PSI, 4" 03 30 53.40 3150 (P.68 IN BCCD) SF 2100 1 C-8 2613 0.1 1 EQUIPMENT PAD 8'X8'X 10" 03 30 53.40 3580 (P. 68 IN BCCD) EACH 1 1 C-8 8 0.1 1 03 30 53.40 3940 FOOTING, STRIP 3000 PSI 24" X 12", (P. 69 IN BCCD) REINFORCED CY 38 1 C-14L 48 0.1 1
  • 45. Schedule Mobilization Completion 154 eight- Date: Date: hour January 9, August 13, workdays 2012 2012
  • 46. Cost Estimate Adjustment Factors Division Breakdown Line Item WBS
  • 47. Cost Estimate TASK COST TASK CODE UNIT OF QTY UNIT CREW TOTAL COST ACCOUNT CODE ACCOUNT MEASURE COST INCREASE NAME COST 04- MASONRY STANDARD 04 21 13.13 2000 (P. 89 BRICK IN BCCD) VANEER SF 15820 $ 14.35 $ 218,316 $ 445,333 REINFORCED CONCRETE 04 22 10.24 0200 (P.96 BLOCK EXT. IN BCCD) 8"X8"X16" SF 15820 $ 10.25 $ 139,849 $ 302,004
  • 48. Cost Estimate Cost of Site Features Design Feature Estimated Total Cost Percent of Total Project Cost Hydrology and Hydraulic Features $ 92,000 2% Site and Transportation Features $ 900,000 21% Structural and Architectural Features $ 1,100,000 25%
  • 49. Cost Estimate DIVISION COST COST PER SF DIVISION TOTAL $ 4,838,253 $ 186 LOCATION MODIFICATION [.76] $ 3,677,072 GENERAL CONDITIONS [+10%] $ 367,707 CONTINGENCY [+5%] $ 183,854 TOTAL PROJECT COST $ 4,228,633 $ 163
  • 50. Conclusion • 25,943 sq. ft. multiuse facility • 2 stadium seating theaters • 81 parking spaces + CAT access • 154 eight-hour workdays, August 13, 2012. • $4.2 Million, $163/SF

Editor's Notes

  1. Large autocad drawing scale down and focus on typical bay.Insert textThen show autocad drawing of footing profile