SlideShare a Scribd company logo
A.4.1.1.- DISEÑO DE ACERO POR FLEXIÓN FRANJA INTERIOR TRAMO 1, 2, 3 Y 4:

1

3

2

Mu =

53.82 Ton.m

Vu =
0.55

20.37 Ton

A.4.2.1.- DISEÑO DE ACERO POR FLEXIÓN FRANJA DE BORDE IZQUIERDO TRAMO 1, 2, 3 Y 4:

4

1

Mu =

3

2

70.98 Ton.m

d = h-3-(5/8")/2
d=
51.206

Vu =
0.55

1

28.28 Ton

d = h-3-(5/8")/2
d=
51.206

1

a = As*fy/(0.85*f¨c*b)
a=
0.176 As
As = Mu/(o*fy*(d-a/2)
As =
0.00
31.109
5%
32.664
-5%
29.553
cantidad de fierros =

As *d-0.17647*As^2/2-Mu/(o*fy)
cm2
Paralelo al trafico se diseña este acero
16 fierros
5/8
@
0.10 cm

a = As*fy/(0.85*f¨c*b)
a=
0.176 As
As *d-0.17647*As^2/2-Mu/(o*fy)
As = Mu/(o*fy*(d-a/2)
As =
0.00
41.845
cm2
5%
43.9375
-5%
39.753
Paralelo al trafico se diseña este acero
cantidad de fierros =
21 fierros
5/8
@
0.10 cm

Cheque de cuantia maxima:

Cheque de cuantia maxima:

Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy]
Pmax = 0.0214

Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy]
Pmax = 0.0214

p=

0.00608

VERDADERO

7.- DI S EÑO DE ACERO TRANS VERS AL
SI h<= 600 mm

VERDADERO

AST < 1750/(L^0.5) <= 50% > As
AST =
27.67 As
Ast =
8.608
Fierros =

8.-ACERO TRAS VERS AL S UPERI OR

0.4464

Fierros =

1

cm2
3/8"

9.- CHEQUEO POR CORTE:
Vs + Vc >= Vu
0.53*(f´c^0.5)*bw*d>= Vu
45.4128

VERDADERO

VERDADERO

SI h<= 600 mm

VERDADERO

Fierros =

16
3/8"
@ 0.125 cm
acero perpendicuar al trafico

8.-ACERO TRAS VERS AL S UPERI OR

Analisis para un metro

As =

0.00817

AST < 1750/(L^0.5) <= 50% > As
AST =
27.67 As
Ast =
11.58

12
3/8"
@ 0.125 cm
acero perpendicuar al trafico

As >= 0.75*Ag/fy

p=

7.- DI S EÑO DE ACERO TRANS VERS AL

@

As >= 0.75*Ag/fy

Analisis para un metro

As =
0.33 cm ambos sentidos

0.4464

Fierros =

1

cm2
3/8"

9.- CHEQUEO POR CORTE:
Vs + Vc >= Vu
0.53*(f´c^0.5)*bw*d>= Vu
45.4128

VERDADERO

@

0.33 cm ambos sentidos

4
A.4.3.1.- DISEÑO DE ACERO POR FLEXIÓN FRANJA DE BORDE DERECHO TRAMO 1, 2, 3 Y 4:

1

Mu =

3

2

81.03 Ton.m

Vu =
0.55

31.76 Ton

d = h-3-(5/8")/2
d=
51.206

1
a = As*fy/(0.85*f¨c*b)
a=
0.176 As
As *d-0.17647*As^2/2-Mu/(o*fy)
As = Mu/(o*fy*(d-a/2)
As =
0.00
48.355
cm2
5%
50.7723
-5%
45.937
Paralelo al trafico se diseña este acero
cantidad de fierros =
24 fierros
5/8
@
0.10 cm
Cheque de cuantia maxima:
Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy]
Pmax = 0.0214
p=

0.00944

VERDADERO

7.- DI S EÑO DE ACERO TRANS VERS AL
SI h<= 600 mm

VERDADERO

AST < 1750/(L^0.5) <= 50% > As
AST =
27.67 As
Ast =
13.38
Fierros =

19
3/8"
@ 0.125 cm
acero perpendicuar al trafico

8.-ACERO TRAS VERS AL S UPERI OR
As >= 0.75*Ag/fy

Analisis para un metro

As =

0.4464

Fierros =

1

cm2
3/8"

9.- CHEQUEO POR CORTE:
Vs + Vc >= Vu
0.53*(f´c^0.5)*bw*d>= Vu
45.4128

VERDADERO

@

0.33 cm ambos sentidos

4
B.3.1.1.- DISEÑO DE ACERO POR FLEXIÓN FRANJA INTERIOR TRAMO 1 Y 3 M (+):

1

Mu =

3

2

37.44 Ton.m

Vu =
0.45

27.03 Ton

B.3.1.2.- DISEÑO DE ACERO POR FLEXIÓN FRANJA INTERIOR TRAMO 2 Y 4 M (-):

4

1

3

2

Mu =

37.44 Ton.m

d = h-3-(5/8")/2
d=
41.206

Vu =
0.45

1

20.06 Ton

d = h-3-(5/8")/2
d=
41.206

1

a = As*fy/(0.85*f¨c*b)
a=
0.176 As
As *d-0.17647*As^2/2-Mu/(o*fy)
As = Mu/(o*fy*(d-a/2)
As =
0.00
27.0136 cm2
5%
28.3642
-5%
25.6629
Paralelo al trafico se diseña este acero
cantidad de fierros =
14 fierros
5/8
@
0.10 cm

a = As*fy/(0.85*f¨c*b)
a=
0.176 As
As *d-0.17647*As^2/2-Mu/(o*fy)
As = Mu/(o*fy*(d-a/2)
As =
0.00
27.0136 cm2
5%
28.3642
-5%
25.6629
Paralelo al trafico se diseña este acero
cantidad de fierros =
14 fierros
5/8
@
0.10 cm

Cheque de cuantia maxima:

Cheque de cuantia maxima:

Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy]
Pmax = 0.0214

Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy]
Pmax = 0.0214

p=

0.00656

VERDADERO

7.- DI S EÑO DE ACERO TRANS VERS AL
SI h<= 600 mm

8.-ACERO TRAS VERS AL S UPERI OR

0.4464

Fierros =

1

cm2
3/8"

9.- CHEQUEO POR CORTE:
Vs + Vc >= Vu
0.53*(f´c^0.5)*bw*d>= Vu
36.5442

VERDADERO

SI h<= 600 mm

VERDADERO

Fierros =

11
3/8"
@ 0.125 cm
acero perpendicuar al trafico

8.-ACERO TRAS VERS AL S UPERI OR

Analisis para un metro

As =

VERDADERO

AST < 1750/(L^0.5) <= 50% > As
AST =
27.67 As
Ast =
7.475

11
3/8"
@ 0.125 cm
acero perpendicuar al trafico

As >= 0.75*Ag/fy

0.00656

7.- DI S EÑO DE ACERO TRANS VERS AL

VERDADERO

AST < 1750/(L^0.5) <= 50% > As
AST =
27.67 As
Ast =
7.475
Fierros =

p=

@

As >= 0.75*Ag/fy

Analisis para un metro

As =
0.33 cm ambos sentidos

0.4464

Fierros =

1

cm2
3/8"

9.- CHEQUEO POR CORTE:
Vs + Vc >= Vu
0.53*(f´c^0.5)*bw*d>= Vu
36.5442

VERDADERO

@

0.33 cm ambos sentidos

4
B.3.1.3.- DISEÑO DE ACERO POR FLEXIÓN FRANJA INTERIOR TRAMO 1 Y 3 M (-):

1

3

2

Mu =

43.53 Ton.m

Vu =
0.45

30.82 Ton

B.3.1.4.- DISEÑO DE ACERO POR FLEXIÓN FRANJA INTERIOR TRAMO 2 Y 4 M (-):

4

1

3

2

Mu =

43.53 Ton.m

d = h-3-(5/8")/2
d=
41.206

Vu =
0.45

1

23.32 Ton

d = h-3-(5/8")/2
d=
41.206

1

a = As*fy/(0.85*f¨c*b)
a=
0.176 As
As *d-0.17647*As^2/2-Mu/(o*fy)
As = Mu/(o*fy*(d-a/2)
As =
0.00
31.7493 cm2
5%
33.3368
-5%
30.1619
Paralelo al trafico se diseña este acero
cantidad de fierros =
16 fierros
5/8
@
0.10 cm

a = As*fy/(0.85*f¨c*b)
a=
0.176 As
As *d-0.17647*As^2/2-Mu/(o*fy)
As = Mu/(o*fy*(d-a/2)
As =
0.00
31.7493 cm2
5%
33.3368
-5%
30.1619
Paralelo al trafico se diseña este acero
cantidad de fierros =
16 fierros
5/8
@
0.10 cm

Cheque de cuantia maxima:

Cheque de cuantia maxima:

Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy]
Pmax = 0.0214

Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy]
Pmax = 0.0214

p=

0.00770

VERDADERO

7.- DI S EÑO DE ACERO TRANS VERS AL
SI h<= 600 mm

p=

0.00770

VERDADERO

7.- DI S EÑO DE ACERO TRANS VERS AL

VERDADERO

SI h<= 600 mm

VERDADERO

AST < 1750/(L^0.5) <= 50% > As
AST =
27.67 As
Ast =
8.785

AST < 1750/(L^0.5) <= 50% > As
AST =
27.67 As
Ast =
8.785

Fierros =

Fierros =

12
3/8"
@ 0.125 cm
acero perpendicuar al trafico

8.-ACERO TRAS VERS AL S UPERI OR
As >= 0.75*Ag/fy

8.-ACERO TRAS VERS AL S UPERI OR

Analisis para un metro

As =

0.4464

Fierros =

1

cm2
3/8"

12
3/8"
@ 0.125 cm
acero perpendicuar al trafico

@

As >= 0.75*Ag/fy

Analisis para un metro

As =
0.33 cm ambos sentidos

0.4464

Fierros =

1

9.- CHEQUEO POR CORTE:

9.- CHEQUEO POR CORTE:

Vs + Vc >= Vu

cm2
3/8"

Vs + Vc >= Vu

0.53*(f´c^0.5)*bw*d>= Vu
36.5442

VERDADERO

0.53*(f´c^0.5)*bw*d>= Vu
36.5442

VERDADERO

@

0.33 cm ambos sentidos

4
B.3.2.1.- DISEÑO DE ACERO POR FLEXIÓN FRANJA DE BORDE IZQUIERDO TRAMO 1 Y 3 M (+):

1

Mu =

3

2

84.90 Ton.m

Vu =
0.45

20.80 Ton

B.3.2.2.- DISEÑO DE ACERO POR FLEXIÓN FRANJA DE BORDE IZQUIERDO TRAMO 2 Y 4 M (+):

4

1

Mu =

3

2

84.90 Ton.m

d = h-3-(5/8")/2
d=
41.206

Vu =
0.45

18.10 Ton

d = h-3-(5/8")/2
d=
41.206

1

1
a = As*fy/(0.85*f¨c*b)
a=
0.176 As
As *d-0.17647*As^2/2-Mu/(o*fy)
As = Mu/(o*fy*(d-a/2)
As =
0.00
67.457
cm2
5%
70.8303
-5%
64.085
Paralelo al trafico se diseña este acero
cantidad de fierros =
34 fierros
5/8
@
0.10 cm

a = As*fy/(0.85*f¨c*b)
a=
0.176 As
As *d-0.17647*As^2/2-Mu/(o*fy)
As = Mu/(o*fy*(d-a/2)
As =
0.00
67.457
cm2
5%
70.8303
-5%
64.085
Paralelo al trafico se diseña este acero
cantidad de fierros =
34 fierros
5/8
@
0.10 cm

Cheque de cuantia maxima:

Cheque de cuantia maxima:

Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy]
Pmax = 0.0214

Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy]
Pmax = 0.0214

p=

0.01637

VERDADERO

7.- DI S EÑO DE ACERO TRANS VERS AL
SI h<= 600 mm

VERDADERO

26
3/8"
@ 0.125 cm
acero perpendicuar al trafico

As =

Analisis para un metro

0.4464

Fierros =

1

9.- CHEQUEO POR CORTE:
Vs + Vc >= Vu
0.53*(f´c^0.5)*bw*d>= Vu
36.5442

VERDADERO

SI h<= 600 mm

Fierros =

VERDADERO

26
3/8"
@ 0.125 cm
acero perpendicuar al trafico

@

As >= 0.75*Ag/fy

Analisis para un metro

As =

cm2
3/8"

VERDADERO

8.-ACERO TRAS VERS AL S UPERI OR

8.-ACERO TRAS VERS AL S UPERI OR
As >= 0.75*Ag/fy

0.01637

AST < 1750/(L^0.5) <= 50% > As
AST =
27.67 As
Ast =
18.67

AST < 1750/(L^0.5) <= 50% > As
AST =
27.67 As
Ast =
18.67
Fierros =

p=

7.- DI S EÑO DE ACERO TRANS VERS AL

0.33 cm ambos sentidos

0.4464

Fierros =

1

cm2
3/8"

9.- CHEQUEO POR CORTE:
Vs + Vc >= Vu
0.53*(f´c^0.5)*bw*d>= Vu
36.5442

VERDADERO

@

0.33 cm ambos sentidos

4
B.3.2.3.- DISEÑO DE ACERO POR FLEXIÓN FRANJA DE BORDE DERECHO TRAMO 1 Y 3 M (+):

1

3

2

Mu =

54.54 Ton.m

Vu =

B.3.2.4.- DISEÑO DE ACERO POR FLEXIÓN FRANJA DE BORDE DERECHO TRAMO 2 Y 4 M (+):

4

34.98 Ton

1

Mu =

3

2

54.54 Ton.m

d = h-3-(5/8")/2
0.45
d=
41.206

Vu =

26.95 Ton

d = h-3-(5/8")/2
0.45
d=
41.206

1

1

a = As*fy/(0.85*f¨c*b)
a=
0.176 As
As *d-0.17647*As^2/2-Mu/(o*fy)
As = Mu/(o*fy*(d-a/2)
As =
0.00
40.606
cm2
5%
42.6362
-5%
38.576
Paralelo al trafico se diseña este acero
cantidad de fierros =
20 fierros
5/8
@
0.10 cm

a = As*fy/(0.85*f¨c*b)
a=
0.176 As
As *d-0.17647*As^2/2-Mu/(o*fy)
As = Mu/(o*fy*(d-a/2)
As =
0.00
40.606
cm2
5%
42.6362
-5%
38.576
Paralelo al trafico se diseña este acero
cantidad de fierros =
20 fierros
5/8
@
0.10 cm

Cheque de cuantia maxima:

Cheque de cuantia maxima:

Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy]
Pmax = 0.0214

Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy]
Pmax = 0.0214

p=

0.00985

VERDADERO

7.- DI S EÑO DE ACERO TRANS VERS AL
SI h<= 600 mm

8.-ACERO TRAS VERS AL S UPERI OR

0.4464

Fierros =

1

cm2
3/8"

9.- CHEQUEO POR CORTE:
Vs + Vc >= Vu
0.53*(f´c^0.5)*bw*d>= Vu
36.5442

VERDADERO

SI h<= 600 mm

VERDADERO

Fierros =

16
3/8"
@ 0.125 cm
acero perpendicuar al trafico

8.-ACERO TRAS VERS AL S UPERI OR

Analisis para un metro

As =

VERDADERO

AST < 1750/(L^0.5) <= 50% > As
AST = 27.67 As
Ast =
11.24

16
3/8"
@ 0.125 cm
acero perpendicuar al trafico

As >= 0.75*Ag/fy

0.00985

7.- DI S EÑO DE ACERO TRANS VERS AL

VERDADERO

AST < 1750/(L^0.5) <= 50% > As
AST =
27.67 As
Ast =
11.24
Fierros =

p=

@

As >= 0.75*Ag/fy

Analisis para un metro

As =
0.33 cm ambos sentidos

0.4464

Fierros =

1

cm2
3/8"

9.- CHEQUEO POR CORTE:
Vs + Vc >= Vu
0.53*(f´c^0.5)*bw*d>= Vu
36.5442

VERDADERO

@

0.33 cm ambos sentidos

4
C.3.1.1.- DISEÑO DE ACERO POR FLEXIÓN FRANJA INTERIOR TRAMO 1 Y 4 M (+):

1

3

2

Mu =

38.69 Ton.m

Vu =
0.45

26.72 Ton

d = h-3-(5/8")/2
d=
41.206

1
a = As*fy/(0.85*f¨c*b)
a=
0.176 As
As *d-0.17647*As^2/2-Mu/(o*fy)
As = Mu/(o*fy*(d-a/2)
As =
0.00
27.9767 cm2
5%
29.3755
-5%
26.5779
Paralelo al trafico se diseña este acero
cantidad de fierros =
14 fierros
5/8
@
0.10 cm
Cheque de cuantia maxima:
Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy]
Pmax = 0.0214
p=

0.00679

VERDADERO

7.- DI S EÑO DE ACERO TRANS VERS AL
SI h<= 600 mm

VERDADERO

AST < 1750/(L^0.5) <= 50% > As
AST =
27.67 As
Ast =
7.741
Fierros =

11
3/8"
@ 0.125 cm
acero perpendicuar al trafico

8.-ACERO TRAS VERS AL S UPERI OR
As >= 0.75*Ag/fy

Analisis para un metro

As =

0.4464

Fierros =

1

cm2
3/8"

9.- CHEQUEO POR CORTE:
Vs + Vc >= Vu
0.53*(f´c^0.5)*bw*d>= Vu
36.5442

VERDADERO

@

0.33 cm ambos sentidos

4
C.3.1.2.- DISEÑO DE ACERO POR FLEXIÓN FRANJA INTERIOR TRAMO 2 Y 3 M (+):

1

3

2

Mu =

26.36 Ton.m

Vu =
0.45

23.13 Ton

C.3.1.3.- DISEÑO DE ACERO POR FLEXIÓN FRANJA INTERIOR TRAMO 1 Y 4 M (-):

4

1

Mu =

44.38 Ton.m

d = h-3-(5/8")/2
d=
41.206

Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy]
Pmax = 0.0214
0.00453

VERDADERO

7.- DI S EÑO DE ACERO TRANS VERS AL
SI h<= 600 mm

d = h-3-(5/8")/2
d=
41.206

8.-ACERO TRAS VERS AL S UPERI OR

Fierros =

1

9.- CHEQUEO POR CORTE:
Vs + Vc >= Vu
0.53*(f´c^0.5)*bw*d>= Vu
VERDADERO

0.00787

@

VERDADERO

0.33 cm ambos sentidos

VERDADERO

AST < 1750/(L^0.5) <= 50% > As
AST =
27.67 As
Ast =
8.97
13
3/8"
@ 0.125 cm
acero perpendicuar al trafico

8.-ACERO TRAS VERS AL S UPERI OR
Analisis para un metro

As =

0.4464

Fierros =

cm2
3/8"

p=

7.- DI S EÑO DE ACERO TRANS VERS AL

As >= 0.75*Ag/fy

Analisis para un metro

0.4464

Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy]
Pmax = 0.0214

Fierros =

7
3/8"
@ 0.125 cm
acero perpendicuar al trafico

As =

a = As*fy/(0.85*f¨c*b)
a=
0.176 As
As *d-0.17647*As^2/2-Mu/(o*fy)
As = Mu/(o*fy*(d-a/2)
As =
0.00
32.4192 cm2
5%
34.0401
-5%
30.7982
Paralelo al trafico se diseña este acero
cantidad de fierros =
16 fierros
5/8
@
0.10 cm

SI h<= 600 mm

VERDADERO

AST < 1750/(L^0.5) <= 50% > As
AST =
27.67 As
Ast =
5.165

36.5442

Ton

Cheque de cuantia maxima:

Cheque de cuantia maxima:

As >= 0.75*Ag/fy

30.52

1

a = As*fy/(0.85*f¨c*b)
a=
0.176 As
As *d-0.17647*As^2/2-Mu/(o*fy)
As = Mu/(o*fy*(d-a/2)
As =
0.00
18.665
cm2
5%
19.5983
-5%
17.7318
Paralelo al trafico se diseña este acero
cantidad de fierros =
9
fierros
5/8
@
0.10 cm

Fierros =

Vu =
0.45

1

p=

3

2

1

cm2
3/8"

9.- CHEQUEO POR CORTE:
Vs + Vc >= Vu
0.53*(f´c^0.5)*bw*d>= Vu
36.5442

VERDADERO

@

0.33 cm ambos sentidos

4
C.3.1.4.- DISEÑO DE ACERO POR FLEXIÓN FRANJA INTERIOR TRAMO 2 Y 3 M (-):

1

3

2

Mu =

35.66 Ton.m

Vu =
0.45

26.73 Ton

C.3.2.1.- DISEÑO DE ACERO POR FLEXIÓN FRANJA DE BORDE IZQUIERDO TRAMO 1 Y 4 M (-):

4

1

Mu =

3

2

49.90 Ton.m

d = h-3-(5/8")/2
d=
41.206

Vu =
0.45

1

30.35 Ton

d = h-3-(5/8")/2
d=
41.206

1

a = As*fy/(0.85*f¨c*b)
a=
0.176 As
As *d-0.17647*As^2/2-Mu/(o*fy)
As = Mu/(o*fy*(d-a/2)
As =
0.00
25.6498 cm2
5%
26.9322
-5%
24.3673
Paralelo al trafico se diseña este acero
cantidad de fierros =
13 fierros
5/8
@
0.10 cm

a = As*fy/(0.85*f¨c*b)
a=
0.176 As
As = Mu/(o*fy*(d-a/2)
As =
0.00
36.825
5%
38.666
-5%
34.984
cantidad de fierros =

As *d-0.17647*As^2/2-Mu/(o*fy)
cm2
Paralelo al trafico se diseña este acero
18 fierros
5/8
@
0.10 cm

Cheque de cuantia maxima:

Cheque de cuantia maxima:

Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy]
Pmax = 0.0214

Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy]
Pmax = 0.0214

p=

0.00622

VERDADERO

7.- DI S EÑO DE ACERO TRANS VERS AL
SI h<= 600 mm

p=

0.00894

VERDADERO

7.- DI S EÑO DE ACERO TRANS VERS AL

VERDADERO

SI h<= 600 mm

VERDADERO

AST < 1750/(L^0.5) <= 50% > As
AST =
27.67 As
Ast =
7.097

AST < 1750/(L^0.5) <= 50% > As
AST =
27.67 As
Ast =
10.19

Fierros =

Fierros =

10
3/8"
@ 0.125 cm
acero perpendicuar al trafico

8.-ACERO TRAS VERS AL S UPERI OR
As >= 0.75*Ag/fy

8.-ACERO TRAS VERS AL S UPERI OR

Analisis para un metro

As =

0.4464

Fierros =

1

cm2
3/8"

14
3/8"
@ 0.125 cm
acero perpendicuar al trafico

@

As >= 0.75*Ag/fy

Analisis para un metro

As =
0.33 cm ambos sentidos

0.4464

Fierros =

1

9.- CHEQUEO POR CORTE:

9.- CHEQUEO POR CORTE:

Vs + Vc >= Vu

cm2
3/8"

Vs + Vc >= Vu

0.53*(f´c^0.5)*bw*d>= Vu
36.5442

VERDADERO

0.53*(f´c^0.5)*bw*d>= Vu
36.5442

VERDADERO

@

0.33 cm ambos sentidos

4
C.3.2.2.- DISEÑO DE ACERO POR FLEXIÓN FRANJA DE BORDE IZQUIERDO TRAMO 2 Y 3 M (-):

1

Mu =

3

2

36.17 Ton.m

Vu =

24.17 Ton

C.3.3.1.- DISEÑO DE ACERO POR FLEXIÓN FRANJA DE BORDE DERECHO TRAMO 1 Y 4 M (-):

4

1

Mu =

3

2

56.11 Ton.m

d = h-3-(5/8")/2
0.45
d=
41.206

Vu =

34.69 Ton

d = h-3-(5/8")/2
0.45
d=
41.206

1

1

a = As*fy/(0.85*f¨c*b)
a=
0.176 As
As *d-0.17647*As^2/2-Mu/(o*fy)
As = Mu/(o*fy*(d-a/2)
As =
0.00
26.040
cm2
5%
27.3416
-5%
24.738
Paralelo al trafico se diseña este acero
cantidad de fierros =
13 fierros
5/8
@
0.10 cm

a = As*fy/(0.85*f¨c*b)
a=
0.176 As
As *d-0.17647*As^2/2-Mu/(o*fy)
As = Mu/(o*fy*(d-a/2)
As =
0.00
41.902
cm2
5%
43.9973
-5%
39.807
Paralelo al trafico se diseña este acero
cantidad de fierros =
21 fierros
5/8
@
0.10 cm

Cheque de cuantia maxima:

Cheque de cuantia maxima:

Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy]
Pmax = 0.0214

Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy]
Pmax = 0.0214

p=

0.00632

VERDADERO

7.- DI S EÑO DE ACERO TRANS VERS AL
SI h<= 600 mm

VERDADERO

AST < 1750/(L^0.5) <= 50% > As
AST =
27.67 As
Ast =
7.205
Fierros =

8.-ACERO TRAS VERS AL S UPERI OR

0.4464

Fierros =

1

cm2
3/8"

9.- CHEQUEO POR CORTE:
Vs + Vc >= Vu
0.53*(f´c^0.5)*bw*d>= Vu
36.5442

VERDADERO

VERDADERO

SI h<= 600 mm

VERDADERO

Fierros =

16
3/8"
@ 0.125 cm
acero perpendicuar al trafico

8.-ACERO TRAS VERS AL S UPERI OR

Analisis para un metro

As =

0.01017

AST < 1750/(L^0.5) <= 50% > As
AST = 27.67 As
Ast =
11.59

10
3/8"
@ 0.125 cm
acero perpendicuar al trafico

As >= 0.75*Ag/fy

p=

7.- DI S EÑO DE ACERO TRANS VERS AL

@

As >= 0.75*Ag/fy

Analisis para un metro

As =
0.33 cm ambos sentidos

0.4464

Fierros =

1

cm2
3/8"

9.- CHEQUEO POR CORTE:
Vs + Vc >= Vu
0.53*(f´c^0.5)*bw*d>= Vu
36.5442

VERDADERO

@

0.33 cm ambos sentidos

4
C.3.3.2.- DISEÑO DE ACERO POR FLEXIÓN FRANJA DE BORDE DERECHO TRAMO 2 Y 3 M (-):

1

Mu =

3

2

39.08 Ton.m

Vu =

30.72 Ton

d = h-3-(5/8")/2
0.45
d=
41.206
1
a = As*fy/(0.85*f¨c*b)
a=
0.176 As
As *d-0.17647*As^2/2-Mu/(o*fy)
As = Mu/(o*fy*(d-a/2)
As =
0.00
28.278
cm2
5%
29.6921
-5%
26.864
Paralelo al trafico se diseña este acero
cantidad de fierros =
14 fierros
5/8
@
0.10 cm
Cheque de cuantia maxima:
Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy]
Pmax = 0.0214
p=

0.00686

VERDADERO

7.- DI S EÑO DE ACERO TRANS VERS AL
SI h<= 600 mm

VERDADERO

AST < 1750/(L^0.5) <= 50% > As
AST = 27.67 As
Ast =
7.825
Fierros =

11
3/8"
@ 0.125 cm
acero perpendicuar al trafico

8.-ACERO TRAS VERS AL S UPERI OR
As >= 0.75*Ag/fy

Analisis para un metro

As =

0.4464

Fierros =

1

cm2
3/8"

9.- CHEQUEO POR CORTE:
Vs + Vc >= Vu
0.53*(f´c^0.5)*bw*d>= Vu
36.5442

VERDADERO

@

0.33 cm ambos sentidos

4

More Related Content

What's hot

22-Design of Four Bolt Extended Endplate Connection (Steel Structural Design ...
22-Design of Four Bolt Extended Endplate Connection (Steel Structural Design ...22-Design of Four Bolt Extended Endplate Connection (Steel Structural Design ...
22-Design of Four Bolt Extended Endplate Connection (Steel Structural Design ...
Hossam Shafiq II
 
Kites team l5
Kites team l5Kites team l5
Kites team l5
aero103
 
INDUSTRIAL BUILDING GANTRY GIRDER
INDUSTRIAL BUILDING  GANTRY GIRDERINDUSTRIAL BUILDING  GANTRY GIRDER
INDUSTRIAL BUILDING GANTRY GIRDER
Harsh Shani
 
Design of isolated footing by ACI code
Design of isolated footing by ACI codeDesign of isolated footing by ACI code
Design of isolated footing by ACI code
Mahmoud Al-Sharawi
 
09-Strength of Gusset Plate (Steel Structural Design & Prof. Shehab Mourad)
09-Strength of Gusset Plate (Steel Structural Design & Prof. Shehab Mourad)09-Strength of Gusset Plate (Steel Structural Design & Prof. Shehab Mourad)
09-Strength of Gusset Plate (Steel Structural Design & Prof. Shehab Mourad)
Hossam Shafiq II
 
Form 1: Measurements
Form 1: MeasurementsForm 1: Measurements
Form 1: Measurements
Julius Osanjo
 
Structural building by engineer abdikani farah ahmed(enggalaydh)
Structural building by engineer abdikani farah ahmed(enggalaydh)Structural building by engineer abdikani farah ahmed(enggalaydh)
Structural building by engineer abdikani farah ahmed(enggalaydh)
EngGalaydh Farah Axmed
 
12-Examples on Compression Members (Steel Structural Design & Prof. Shehab Mo...
12-Examples on Compression Members (Steel Structural Design & Prof. Shehab Mo...12-Examples on Compression Members (Steel Structural Design & Prof. Shehab Mo...
12-Examples on Compression Members (Steel Structural Design & Prof. Shehab Mo...
Hossam Shafiq II
 
Subok pang defense
Subok pang defenseSubok pang defense
Subok pang defense
Lester Kun
 
Engineering example calculation
Engineering example calculationEngineering example calculation
Engineering example calculation
MOSTAFA DAIF
 
Undeterminate problems
Undeterminate problemsUndeterminate problems
Undeterminate problems
Mahmoud Youssef Abido
 
PERHITUNGAN TULANGAN LONGITUDINAL BALOK BETON BERTULANG RANGKAP
PERHITUNGAN TULANGAN LONGITUDINAL BALOK BETON BERTULANG RANGKAPPERHITUNGAN TULANGAN LONGITUDINAL BALOK BETON BERTULANG RANGKAP
PERHITUNGAN TULANGAN LONGITUDINAL BALOK BETON BERTULANG RANGKAP
Sumarno Feriyal
 
21-Design of Simple Shear Connections (Steel Structural Design & Prof. Shehab...
21-Design of Simple Shear Connections (Steel Structural Design & Prof. Shehab...21-Design of Simple Shear Connections (Steel Structural Design & Prof. Shehab...
21-Design of Simple Shear Connections (Steel Structural Design & Prof. Shehab...
Hossam Shafiq II
 
Chapter 12
Chapter 12Chapter 12
Chapter 12
Afgaab Cumar
 
Doubly reinforced beam]
Doubly reinforced beam]Doubly reinforced beam]
Doubly reinforced beam]
raymondsabado2005
 
MasonryShearWall Design-1 Sheet1
MasonryShearWall Design-1 Sheet1MasonryShearWall Design-1 Sheet1
MasonryShearWall Design-1 Sheet1
Yongsheng (Jack) Jiao
 
Column sections Classification
Column sections ClassificationColumn sections Classification
Column sections Classification
Kingsley Aboagye
 
Design of Cantilever retaining wall
Design of Cantilever retaining wallDesign of Cantilever retaining wall
Design of Cantilever retaining wall
Achuthan Karnnan
 
Masonry Shear Wall Design-Excel Sheet 2
Masonry Shear Wall Design-Excel Sheet 2Masonry Shear Wall Design-Excel Sheet 2
Masonry Shear Wall Design-Excel Sheet 2
Yongsheng (Jack) Jiao
 
6. diseño de puente compuesto2
6. diseño de puente compuesto26. diseño de puente compuesto2
6. diseño de puente compuesto2
ing_eliali4748
 

What's hot (20)

22-Design of Four Bolt Extended Endplate Connection (Steel Structural Design ...
22-Design of Four Bolt Extended Endplate Connection (Steel Structural Design ...22-Design of Four Bolt Extended Endplate Connection (Steel Structural Design ...
22-Design of Four Bolt Extended Endplate Connection (Steel Structural Design ...
 
Kites team l5
Kites team l5Kites team l5
Kites team l5
 
INDUSTRIAL BUILDING GANTRY GIRDER
INDUSTRIAL BUILDING  GANTRY GIRDERINDUSTRIAL BUILDING  GANTRY GIRDER
INDUSTRIAL BUILDING GANTRY GIRDER
 
Design of isolated footing by ACI code
Design of isolated footing by ACI codeDesign of isolated footing by ACI code
Design of isolated footing by ACI code
 
09-Strength of Gusset Plate (Steel Structural Design & Prof. Shehab Mourad)
09-Strength of Gusset Plate (Steel Structural Design & Prof. Shehab Mourad)09-Strength of Gusset Plate (Steel Structural Design & Prof. Shehab Mourad)
09-Strength of Gusset Plate (Steel Structural Design & Prof. Shehab Mourad)
 
Form 1: Measurements
Form 1: MeasurementsForm 1: Measurements
Form 1: Measurements
 
Structural building by engineer abdikani farah ahmed(enggalaydh)
Structural building by engineer abdikani farah ahmed(enggalaydh)Structural building by engineer abdikani farah ahmed(enggalaydh)
Structural building by engineer abdikani farah ahmed(enggalaydh)
 
12-Examples on Compression Members (Steel Structural Design & Prof. Shehab Mo...
12-Examples on Compression Members (Steel Structural Design & Prof. Shehab Mo...12-Examples on Compression Members (Steel Structural Design & Prof. Shehab Mo...
12-Examples on Compression Members (Steel Structural Design & Prof. Shehab Mo...
 
Subok pang defense
Subok pang defenseSubok pang defense
Subok pang defense
 
Engineering example calculation
Engineering example calculationEngineering example calculation
Engineering example calculation
 
Undeterminate problems
Undeterminate problemsUndeterminate problems
Undeterminate problems
 
PERHITUNGAN TULANGAN LONGITUDINAL BALOK BETON BERTULANG RANGKAP
PERHITUNGAN TULANGAN LONGITUDINAL BALOK BETON BERTULANG RANGKAPPERHITUNGAN TULANGAN LONGITUDINAL BALOK BETON BERTULANG RANGKAP
PERHITUNGAN TULANGAN LONGITUDINAL BALOK BETON BERTULANG RANGKAP
 
21-Design of Simple Shear Connections (Steel Structural Design & Prof. Shehab...
21-Design of Simple Shear Connections (Steel Structural Design & Prof. Shehab...21-Design of Simple Shear Connections (Steel Structural Design & Prof. Shehab...
21-Design of Simple Shear Connections (Steel Structural Design & Prof. Shehab...
 
Chapter 12
Chapter 12Chapter 12
Chapter 12
 
Doubly reinforced beam]
Doubly reinforced beam]Doubly reinforced beam]
Doubly reinforced beam]
 
MasonryShearWall Design-1 Sheet1
MasonryShearWall Design-1 Sheet1MasonryShearWall Design-1 Sheet1
MasonryShearWall Design-1 Sheet1
 
Column sections Classification
Column sections ClassificationColumn sections Classification
Column sections Classification
 
Design of Cantilever retaining wall
Design of Cantilever retaining wallDesign of Cantilever retaining wall
Design of Cantilever retaining wall
 
Masonry Shear Wall Design-Excel Sheet 2
Masonry Shear Wall Design-Excel Sheet 2Masonry Shear Wall Design-Excel Sheet 2
Masonry Shear Wall Design-Excel Sheet 2
 
6. diseño de puente compuesto2
6. diseño de puente compuesto26. diseño de puente compuesto2
6. diseño de puente compuesto2
 

Viewers also liked

4 soal ukk tkj xi istalasi os dasar 2013
4 soal ukk tkj xi istalasi os dasar 20134 soal ukk tkj xi istalasi os dasar 2013
4 soal ukk tkj xi istalasi os dasar 2013
Ovik's Kipo
 
Remote detection of illegal usage of electricity
Remote detection of illegal usage of electricityRemote detection of illegal usage of electricity
Remote detection of illegal usage of electricity
ATHUL RAJ.R
 
motoFANkowy tutorial odc. 1
motoFANkowy tutorial odc. 1motoFANkowy tutorial odc. 1
motoFANkowy tutorial odc. 1
Rajdy w Pobiedziskach / motoFANki
 
Common Online Terminologies
Common Online TerminologiesCommon Online Terminologies
Common Online Terminologies
bajeapolonia
 
motoFANki_2014
motoFANki_2014motoFANki_2014
Sarah colina principle 2
Sarah colina principle 2Sarah colina principle 2
Sarah colina principle 2
Anne Acosta
 
Wena ganda chos!
Wena ganda chos!Wena ganda chos!
Wena ganda chos!
Anne Acosta
 
motoFANki_2014_coś więcej
motoFANki_2014_coś więcejmotoFANki_2014_coś więcej
motoFANki_2014_coś więcej
Rajdy w Pobiedziskach / motoFANki
 
Presentation1 1
Presentation1 1Presentation1 1
Presentation1 1
Anne Acosta
 
Costs associated with production
Costs associated with productionCosts associated with production
Costs associated with production
Anne Acosta
 
Production and costs concepts
Production and costs  conceptsProduction and costs  concepts
Production and costs concepts
Anne Acosta
 
Step by Step - Reusing old features to build new ones
Step by Step - Reusing old features to build new onesStep by Step - Reusing old features to build new ones
Step by Step - Reusing old features to build new ones
Allon Mureinik
 
E-Mode LNA
E-Mode LNAE-Mode LNA
E-Mode LNA
Sushil Kumar
 
Chop - Shop Barbers, Crane Lane
Chop - Shop Barbers, Crane LaneChop - Shop Barbers, Crane Lane
Chop - Shop Barbers, Crane Lane
Marie-Clare Byard
 
Edu carex core_module
Edu carex core_moduleEdu carex core_module
Edu carex core_module
akhileshdel
 
Nuclear power plant
Nuclear power plantNuclear power plant
Nuclear power plant
ATHUL RAJ.R
 

Viewers also liked (20)

το κουτι της πανδωρας A
το κουτι της πανδωρας    Aτο κουτι της πανδωρας    A
το κουτι της πανδωρας A
 
4 soal ukk tkj xi istalasi os dasar 2013
4 soal ukk tkj xi istalasi os dasar 20134 soal ukk tkj xi istalasi os dasar 2013
4 soal ukk tkj xi istalasi os dasar 2013
 
Remote detection of illegal usage of electricity
Remote detection of illegal usage of electricityRemote detection of illegal usage of electricity
Remote detection of illegal usage of electricity
 
motoFANkowy tutorial odc. 1
motoFANkowy tutorial odc. 1motoFANkowy tutorial odc. 1
motoFANkowy tutorial odc. 1
 
Common Online Terminologies
Common Online TerminologiesCommon Online Terminologies
Common Online Terminologies
 
motoFANki_2014
motoFANki_2014motoFANki_2014
motoFANki_2014
 
Sarah colina principle 2
Sarah colina principle 2Sarah colina principle 2
Sarah colina principle 2
 
Jamaica accidents
Jamaica   accidentsJamaica   accidents
Jamaica accidents
 
Wena ganda chos!
Wena ganda chos!Wena ganda chos!
Wena ganda chos!
 
motoFANki_2014_coś więcej
motoFANki_2014_coś więcejmotoFANki_2014_coś więcej
motoFANki_2014_coś więcej
 
Presentation1 1
Presentation1 1Presentation1 1
Presentation1 1
 
Costs associated with production
Costs associated with productionCosts associated with production
Costs associated with production
 
Production and costs concepts
Production and costs  conceptsProduction and costs  concepts
Production and costs concepts
 
Step by Step - Reusing old features to build new ones
Step by Step - Reusing old features to build new onesStep by Step - Reusing old features to build new ones
Step by Step - Reusing old features to build new ones
 
E-Mode LNA
E-Mode LNAE-Mode LNA
E-Mode LNA
 
Chop - Shop Barbers, Crane Lane
Chop - Shop Barbers, Crane LaneChop - Shop Barbers, Crane Lane
Chop - Shop Barbers, Crane Lane
 
Edu carex core_module
Edu carex core_moduleEdu carex core_module
Edu carex core_module
 
Nuclear power plant
Nuclear power plantNuclear power plant
Nuclear power plant
 
áóôåéá óïâáñá
áóôåéá óïâáñááóôåéá óïâáñá
áóôåéá óïâáñá
 
Ex.arithmoi
Ex.arithmoiEx.arithmoi
Ex.arithmoi
 

Similar to Calculo 1

Ch 8.pdf
Ch 8.pdfCh 8.pdf
Roof Truss Design (By Hamza Waheed UET Lahore )
Roof Truss Design (By Hamza Waheed UET Lahore )Roof Truss Design (By Hamza Waheed UET Lahore )
Roof Truss Design (By Hamza Waheed UET Lahore )
Hamza Waheed
 
Rcc Design Sheets
Rcc Design SheetsRcc Design Sheets
Rcc Design Sheets
klecivil
 
Rcc member design steps
Rcc member design stepsRcc member design steps
Rcc member design steps
DYPCET
 
Calculo de acero en vigas ok
Calculo de acero en vigas okCalculo de acero en vigas ok
Calculo de acero en vigas ok
AngelMendozaChinchay
 
Singly R.C. beam
Singly R.C. beam  Singly R.C. beam
Singly R.C. beam
Yash Patel
 
Harshal
HarshalHarshal
طه
طهطه
Design calculations of raft foundation
Design calculations of raft foundationDesign calculations of raft foundation
Design calculations of raft foundation
Shahzad Ali
 
onw way slab design
onw way slab designonw way slab design
onw way slab design
Palak Patel
 
Design of stairs
Design of stairsDesign of stairs
Design of stairs
Bahzad5
 
Baseplate
BaseplateBaseplate
Baseplate
peerfn88
 
DESIGN OF CIRCULAR OVERHEAD WATER TANK.pptx
DESIGN OF CIRCULAR OVERHEAD WATER TANK.pptxDESIGN OF CIRCULAR OVERHEAD WATER TANK.pptx
DESIGN OF CIRCULAR OVERHEAD WATER TANK.pptx
subhashini214160
 
Design and analysis of school building
Design and analysis of school buildingDesign and analysis of school building
Design and analysis of school building
Raghav Sankar
 
Doubly reinforced beam design
Doubly reinforced beam   designDoubly reinforced beam   design
Doubly reinforced beam design
Selvakumar Palanisamy
 
Perancangan Alat Proses Styrene Production
Perancangan Alat Proses Styrene ProductionPerancangan Alat Proses Styrene Production
Perancangan Alat Proses Styrene Production
Ricco Riyan Kurniawan
 
Design of footing
Design of footingDesign of footing
Design of footing
NripeshJha
 
Power screw application
Power screw applicationPower screw application
Power screw application
alsaid fathy
 
Puentes
PuentesPuentes
Foundation Reinforcement Calcs & Connection Calcs
Foundation Reinforcement Calcs & Connection CalcsFoundation Reinforcement Calcs & Connection Calcs
Foundation Reinforcement Calcs & Connection Calcs
Magdel Kotze
 

Similar to Calculo 1 (20)

Ch 8.pdf
Ch 8.pdfCh 8.pdf
Ch 8.pdf
 
Roof Truss Design (By Hamza Waheed UET Lahore )
Roof Truss Design (By Hamza Waheed UET Lahore )Roof Truss Design (By Hamza Waheed UET Lahore )
Roof Truss Design (By Hamza Waheed UET Lahore )
 
Rcc Design Sheets
Rcc Design SheetsRcc Design Sheets
Rcc Design Sheets
 
Rcc member design steps
Rcc member design stepsRcc member design steps
Rcc member design steps
 
Calculo de acero en vigas ok
Calculo de acero en vigas okCalculo de acero en vigas ok
Calculo de acero en vigas ok
 
Singly R.C. beam
Singly R.C. beam  Singly R.C. beam
Singly R.C. beam
 
Harshal
HarshalHarshal
Harshal
 
طه
طهطه
طه
 
Design calculations of raft foundation
Design calculations of raft foundationDesign calculations of raft foundation
Design calculations of raft foundation
 
onw way slab design
onw way slab designonw way slab design
onw way slab design
 
Design of stairs
Design of stairsDesign of stairs
Design of stairs
 
Baseplate
BaseplateBaseplate
Baseplate
 
DESIGN OF CIRCULAR OVERHEAD WATER TANK.pptx
DESIGN OF CIRCULAR OVERHEAD WATER TANK.pptxDESIGN OF CIRCULAR OVERHEAD WATER TANK.pptx
DESIGN OF CIRCULAR OVERHEAD WATER TANK.pptx
 
Design and analysis of school building
Design and analysis of school buildingDesign and analysis of school building
Design and analysis of school building
 
Doubly reinforced beam design
Doubly reinforced beam   designDoubly reinforced beam   design
Doubly reinforced beam design
 
Perancangan Alat Proses Styrene Production
Perancangan Alat Proses Styrene ProductionPerancangan Alat Proses Styrene Production
Perancangan Alat Proses Styrene Production
 
Design of footing
Design of footingDesign of footing
Design of footing
 
Power screw application
Power screw applicationPower screw application
Power screw application
 
Puentes
PuentesPuentes
Puentes
 
Foundation Reinforcement Calcs & Connection Calcs
Foundation Reinforcement Calcs & Connection CalcsFoundation Reinforcement Calcs & Connection Calcs
Foundation Reinforcement Calcs & Connection Calcs
 

Recently uploaded

MARY JANE WILSON, A “BOA MÃE” .
MARY JANE WILSON, A “BOA MÃE”           .MARY JANE WILSON, A “BOA MÃE”           .
MARY JANE WILSON, A “BOA MÃE” .
Colégio Santa Teresinha
 
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
PECB
 
writing about opinions about Australia the movie
writing about opinions about Australia the moviewriting about opinions about Australia the movie
writing about opinions about Australia the movie
Nicholas Montgomery
 
Azure Interview Questions and Answers PDF By ScholarHat
Azure Interview Questions and Answers PDF By ScholarHatAzure Interview Questions and Answers PDF By ScholarHat
Azure Interview Questions and Answers PDF By ScholarHat
Scholarhat
 
A Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdfA Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdf
Jean Carlos Nunes Paixão
 
The simplified electron and muon model, Oscillating Spacetime: The Foundation...
The simplified electron and muon model, Oscillating Spacetime: The Foundation...The simplified electron and muon model, Oscillating Spacetime: The Foundation...
The simplified electron and muon model, Oscillating Spacetime: The Foundation...
RitikBhardwaj56
 
Smart-Money for SMC traders good time and ICT
Smart-Money for SMC traders good time and ICTSmart-Money for SMC traders good time and ICT
Smart-Money for SMC traders good time and ICT
simonomuemu
 
PCOS corelations and management through Ayurveda.
PCOS corelations and management through Ayurveda.PCOS corelations and management through Ayurveda.
PCOS corelations and management through Ayurveda.
Dr. Shivangi Singh Parihar
 
S1-Introduction-Biopesticides in ICM.pptx
S1-Introduction-Biopesticides in ICM.pptxS1-Introduction-Biopesticides in ICM.pptx
S1-Introduction-Biopesticides in ICM.pptx
tarandeep35
 
A Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in EducationA Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in Education
Peter Windle
 
Advanced Java[Extra Concepts, Not Difficult].docx
Advanced Java[Extra Concepts, Not Difficult].docxAdvanced Java[Extra Concepts, Not Difficult].docx
Advanced Java[Extra Concepts, Not Difficult].docx
adhitya5119
 
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdfANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
Priyankaranawat4
 
Digital Artifact 1 - 10VCD Environments Unit
Digital Artifact 1 - 10VCD Environments UnitDigital Artifact 1 - 10VCD Environments Unit
Digital Artifact 1 - 10VCD Environments Unit
chanes7
 
Chapter 4 - Islamic Financial Institutions in Malaysia.pptx
Chapter 4 - Islamic Financial Institutions in Malaysia.pptxChapter 4 - Islamic Financial Institutions in Malaysia.pptx
Chapter 4 - Islamic Financial Institutions in Malaysia.pptx
Mohd Adib Abd Muin, Senior Lecturer at Universiti Utara Malaysia
 
The Diamonds of 2023-2024 in the IGRA collection
The Diamonds of 2023-2024 in the IGRA collectionThe Diamonds of 2023-2024 in the IGRA collection
The Diamonds of 2023-2024 in the IGRA collection
Israel Genealogy Research Association
 
PIMS Job Advertisement 2024.pdf Islamabad
PIMS Job Advertisement 2024.pdf IslamabadPIMS Job Advertisement 2024.pdf Islamabad
PIMS Job Advertisement 2024.pdf Islamabad
AyyanKhan40
 
South African Journal of Science: Writing with integrity workshop (2024)
South African Journal of Science: Writing with integrity workshop (2024)South African Journal of Science: Writing with integrity workshop (2024)
South African Journal of Science: Writing with integrity workshop (2024)
Academy of Science of South Africa
 
Your Skill Boost Masterclass: Strategies for Effective Upskilling
Your Skill Boost Masterclass: Strategies for Effective UpskillingYour Skill Boost Masterclass: Strategies for Effective Upskilling
Your Skill Boost Masterclass: Strategies for Effective Upskilling
Excellence Foundation for South Sudan
 
The History of Stoke Newington Street Names
The History of Stoke Newington Street NamesThe History of Stoke Newington Street Names
The History of Stoke Newington Street Names
History of Stoke Newington
 
How to Build a Module in Odoo 17 Using the Scaffold Method
How to Build a Module in Odoo 17 Using the Scaffold MethodHow to Build a Module in Odoo 17 Using the Scaffold Method
How to Build a Module in Odoo 17 Using the Scaffold Method
Celine George
 

Recently uploaded (20)

MARY JANE WILSON, A “BOA MÃE” .
MARY JANE WILSON, A “BOA MÃE”           .MARY JANE WILSON, A “BOA MÃE”           .
MARY JANE WILSON, A “BOA MÃE” .
 
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
 
writing about opinions about Australia the movie
writing about opinions about Australia the moviewriting about opinions about Australia the movie
writing about opinions about Australia the movie
 
Azure Interview Questions and Answers PDF By ScholarHat
Azure Interview Questions and Answers PDF By ScholarHatAzure Interview Questions and Answers PDF By ScholarHat
Azure Interview Questions and Answers PDF By ScholarHat
 
A Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdfA Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdf
 
The simplified electron and muon model, Oscillating Spacetime: The Foundation...
The simplified electron and muon model, Oscillating Spacetime: The Foundation...The simplified electron and muon model, Oscillating Spacetime: The Foundation...
The simplified electron and muon model, Oscillating Spacetime: The Foundation...
 
Smart-Money for SMC traders good time and ICT
Smart-Money for SMC traders good time and ICTSmart-Money for SMC traders good time and ICT
Smart-Money for SMC traders good time and ICT
 
PCOS corelations and management through Ayurveda.
PCOS corelations and management through Ayurveda.PCOS corelations and management through Ayurveda.
PCOS corelations and management through Ayurveda.
 
S1-Introduction-Biopesticides in ICM.pptx
S1-Introduction-Biopesticides in ICM.pptxS1-Introduction-Biopesticides in ICM.pptx
S1-Introduction-Biopesticides in ICM.pptx
 
A Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in EducationA Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in Education
 
Advanced Java[Extra Concepts, Not Difficult].docx
Advanced Java[Extra Concepts, Not Difficult].docxAdvanced Java[Extra Concepts, Not Difficult].docx
Advanced Java[Extra Concepts, Not Difficult].docx
 
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdfANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
 
Digital Artifact 1 - 10VCD Environments Unit
Digital Artifact 1 - 10VCD Environments UnitDigital Artifact 1 - 10VCD Environments Unit
Digital Artifact 1 - 10VCD Environments Unit
 
Chapter 4 - Islamic Financial Institutions in Malaysia.pptx
Chapter 4 - Islamic Financial Institutions in Malaysia.pptxChapter 4 - Islamic Financial Institutions in Malaysia.pptx
Chapter 4 - Islamic Financial Institutions in Malaysia.pptx
 
The Diamonds of 2023-2024 in the IGRA collection
The Diamonds of 2023-2024 in the IGRA collectionThe Diamonds of 2023-2024 in the IGRA collection
The Diamonds of 2023-2024 in the IGRA collection
 
PIMS Job Advertisement 2024.pdf Islamabad
PIMS Job Advertisement 2024.pdf IslamabadPIMS Job Advertisement 2024.pdf Islamabad
PIMS Job Advertisement 2024.pdf Islamabad
 
South African Journal of Science: Writing with integrity workshop (2024)
South African Journal of Science: Writing with integrity workshop (2024)South African Journal of Science: Writing with integrity workshop (2024)
South African Journal of Science: Writing with integrity workshop (2024)
 
Your Skill Boost Masterclass: Strategies for Effective Upskilling
Your Skill Boost Masterclass: Strategies for Effective UpskillingYour Skill Boost Masterclass: Strategies for Effective Upskilling
Your Skill Boost Masterclass: Strategies for Effective Upskilling
 
The History of Stoke Newington Street Names
The History of Stoke Newington Street NamesThe History of Stoke Newington Street Names
The History of Stoke Newington Street Names
 
How to Build a Module in Odoo 17 Using the Scaffold Method
How to Build a Module in Odoo 17 Using the Scaffold MethodHow to Build a Module in Odoo 17 Using the Scaffold Method
How to Build a Module in Odoo 17 Using the Scaffold Method
 

Calculo 1

  • 1. A.4.1.1.- DISEÑO DE ACERO POR FLEXIÓN FRANJA INTERIOR TRAMO 1, 2, 3 Y 4: 1 3 2 Mu = 53.82 Ton.m Vu = 0.55 20.37 Ton A.4.2.1.- DISEÑO DE ACERO POR FLEXIÓN FRANJA DE BORDE IZQUIERDO TRAMO 1, 2, 3 Y 4: 4 1 Mu = 3 2 70.98 Ton.m d = h-3-(5/8")/2 d= 51.206 Vu = 0.55 1 28.28 Ton d = h-3-(5/8")/2 d= 51.206 1 a = As*fy/(0.85*f¨c*b) a= 0.176 As As = Mu/(o*fy*(d-a/2) As = 0.00 31.109 5% 32.664 -5% 29.553 cantidad de fierros = As *d-0.17647*As^2/2-Mu/(o*fy) cm2 Paralelo al trafico se diseña este acero 16 fierros 5/8 @ 0.10 cm a = As*fy/(0.85*f¨c*b) a= 0.176 As As *d-0.17647*As^2/2-Mu/(o*fy) As = Mu/(o*fy*(d-a/2) As = 0.00 41.845 cm2 5% 43.9375 -5% 39.753 Paralelo al trafico se diseña este acero cantidad de fierros = 21 fierros 5/8 @ 0.10 cm Cheque de cuantia maxima: Cheque de cuantia maxima: Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy] Pmax = 0.0214 Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy] Pmax = 0.0214 p= 0.00608 VERDADERO 7.- DI S EÑO DE ACERO TRANS VERS AL SI h<= 600 mm VERDADERO AST < 1750/(L^0.5) <= 50% > As AST = 27.67 As Ast = 8.608 Fierros = 8.-ACERO TRAS VERS AL S UPERI OR 0.4464 Fierros = 1 cm2 3/8" 9.- CHEQUEO POR CORTE: Vs + Vc >= Vu 0.53*(f´c^0.5)*bw*d>= Vu 45.4128 VERDADERO VERDADERO SI h<= 600 mm VERDADERO Fierros = 16 3/8" @ 0.125 cm acero perpendicuar al trafico 8.-ACERO TRAS VERS AL S UPERI OR Analisis para un metro As = 0.00817 AST < 1750/(L^0.5) <= 50% > As AST = 27.67 As Ast = 11.58 12 3/8" @ 0.125 cm acero perpendicuar al trafico As >= 0.75*Ag/fy p= 7.- DI S EÑO DE ACERO TRANS VERS AL @ As >= 0.75*Ag/fy Analisis para un metro As = 0.33 cm ambos sentidos 0.4464 Fierros = 1 cm2 3/8" 9.- CHEQUEO POR CORTE: Vs + Vc >= Vu 0.53*(f´c^0.5)*bw*d>= Vu 45.4128 VERDADERO @ 0.33 cm ambos sentidos 4
  • 2. A.4.3.1.- DISEÑO DE ACERO POR FLEXIÓN FRANJA DE BORDE DERECHO TRAMO 1, 2, 3 Y 4: 1 Mu = 3 2 81.03 Ton.m Vu = 0.55 31.76 Ton d = h-3-(5/8")/2 d= 51.206 1 a = As*fy/(0.85*f¨c*b) a= 0.176 As As *d-0.17647*As^2/2-Mu/(o*fy) As = Mu/(o*fy*(d-a/2) As = 0.00 48.355 cm2 5% 50.7723 -5% 45.937 Paralelo al trafico se diseña este acero cantidad de fierros = 24 fierros 5/8 @ 0.10 cm Cheque de cuantia maxima: Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy] Pmax = 0.0214 p= 0.00944 VERDADERO 7.- DI S EÑO DE ACERO TRANS VERS AL SI h<= 600 mm VERDADERO AST < 1750/(L^0.5) <= 50% > As AST = 27.67 As Ast = 13.38 Fierros = 19 3/8" @ 0.125 cm acero perpendicuar al trafico 8.-ACERO TRAS VERS AL S UPERI OR As >= 0.75*Ag/fy Analisis para un metro As = 0.4464 Fierros = 1 cm2 3/8" 9.- CHEQUEO POR CORTE: Vs + Vc >= Vu 0.53*(f´c^0.5)*bw*d>= Vu 45.4128 VERDADERO @ 0.33 cm ambos sentidos 4
  • 3. B.3.1.1.- DISEÑO DE ACERO POR FLEXIÓN FRANJA INTERIOR TRAMO 1 Y 3 M (+): 1 Mu = 3 2 37.44 Ton.m Vu = 0.45 27.03 Ton B.3.1.2.- DISEÑO DE ACERO POR FLEXIÓN FRANJA INTERIOR TRAMO 2 Y 4 M (-): 4 1 3 2 Mu = 37.44 Ton.m d = h-3-(5/8")/2 d= 41.206 Vu = 0.45 1 20.06 Ton d = h-3-(5/8")/2 d= 41.206 1 a = As*fy/(0.85*f¨c*b) a= 0.176 As As *d-0.17647*As^2/2-Mu/(o*fy) As = Mu/(o*fy*(d-a/2) As = 0.00 27.0136 cm2 5% 28.3642 -5% 25.6629 Paralelo al trafico se diseña este acero cantidad de fierros = 14 fierros 5/8 @ 0.10 cm a = As*fy/(0.85*f¨c*b) a= 0.176 As As *d-0.17647*As^2/2-Mu/(o*fy) As = Mu/(o*fy*(d-a/2) As = 0.00 27.0136 cm2 5% 28.3642 -5% 25.6629 Paralelo al trafico se diseña este acero cantidad de fierros = 14 fierros 5/8 @ 0.10 cm Cheque de cuantia maxima: Cheque de cuantia maxima: Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy] Pmax = 0.0214 Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy] Pmax = 0.0214 p= 0.00656 VERDADERO 7.- DI S EÑO DE ACERO TRANS VERS AL SI h<= 600 mm 8.-ACERO TRAS VERS AL S UPERI OR 0.4464 Fierros = 1 cm2 3/8" 9.- CHEQUEO POR CORTE: Vs + Vc >= Vu 0.53*(f´c^0.5)*bw*d>= Vu 36.5442 VERDADERO SI h<= 600 mm VERDADERO Fierros = 11 3/8" @ 0.125 cm acero perpendicuar al trafico 8.-ACERO TRAS VERS AL S UPERI OR Analisis para un metro As = VERDADERO AST < 1750/(L^0.5) <= 50% > As AST = 27.67 As Ast = 7.475 11 3/8" @ 0.125 cm acero perpendicuar al trafico As >= 0.75*Ag/fy 0.00656 7.- DI S EÑO DE ACERO TRANS VERS AL VERDADERO AST < 1750/(L^0.5) <= 50% > As AST = 27.67 As Ast = 7.475 Fierros = p= @ As >= 0.75*Ag/fy Analisis para un metro As = 0.33 cm ambos sentidos 0.4464 Fierros = 1 cm2 3/8" 9.- CHEQUEO POR CORTE: Vs + Vc >= Vu 0.53*(f´c^0.5)*bw*d>= Vu 36.5442 VERDADERO @ 0.33 cm ambos sentidos 4
  • 4. B.3.1.3.- DISEÑO DE ACERO POR FLEXIÓN FRANJA INTERIOR TRAMO 1 Y 3 M (-): 1 3 2 Mu = 43.53 Ton.m Vu = 0.45 30.82 Ton B.3.1.4.- DISEÑO DE ACERO POR FLEXIÓN FRANJA INTERIOR TRAMO 2 Y 4 M (-): 4 1 3 2 Mu = 43.53 Ton.m d = h-3-(5/8")/2 d= 41.206 Vu = 0.45 1 23.32 Ton d = h-3-(5/8")/2 d= 41.206 1 a = As*fy/(0.85*f¨c*b) a= 0.176 As As *d-0.17647*As^2/2-Mu/(o*fy) As = Mu/(o*fy*(d-a/2) As = 0.00 31.7493 cm2 5% 33.3368 -5% 30.1619 Paralelo al trafico se diseña este acero cantidad de fierros = 16 fierros 5/8 @ 0.10 cm a = As*fy/(0.85*f¨c*b) a= 0.176 As As *d-0.17647*As^2/2-Mu/(o*fy) As = Mu/(o*fy*(d-a/2) As = 0.00 31.7493 cm2 5% 33.3368 -5% 30.1619 Paralelo al trafico se diseña este acero cantidad de fierros = 16 fierros 5/8 @ 0.10 cm Cheque de cuantia maxima: Cheque de cuantia maxima: Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy] Pmax = 0.0214 Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy] Pmax = 0.0214 p= 0.00770 VERDADERO 7.- DI S EÑO DE ACERO TRANS VERS AL SI h<= 600 mm p= 0.00770 VERDADERO 7.- DI S EÑO DE ACERO TRANS VERS AL VERDADERO SI h<= 600 mm VERDADERO AST < 1750/(L^0.5) <= 50% > As AST = 27.67 As Ast = 8.785 AST < 1750/(L^0.5) <= 50% > As AST = 27.67 As Ast = 8.785 Fierros = Fierros = 12 3/8" @ 0.125 cm acero perpendicuar al trafico 8.-ACERO TRAS VERS AL S UPERI OR As >= 0.75*Ag/fy 8.-ACERO TRAS VERS AL S UPERI OR Analisis para un metro As = 0.4464 Fierros = 1 cm2 3/8" 12 3/8" @ 0.125 cm acero perpendicuar al trafico @ As >= 0.75*Ag/fy Analisis para un metro As = 0.33 cm ambos sentidos 0.4464 Fierros = 1 9.- CHEQUEO POR CORTE: 9.- CHEQUEO POR CORTE: Vs + Vc >= Vu cm2 3/8" Vs + Vc >= Vu 0.53*(f´c^0.5)*bw*d>= Vu 36.5442 VERDADERO 0.53*(f´c^0.5)*bw*d>= Vu 36.5442 VERDADERO @ 0.33 cm ambos sentidos 4
  • 5. B.3.2.1.- DISEÑO DE ACERO POR FLEXIÓN FRANJA DE BORDE IZQUIERDO TRAMO 1 Y 3 M (+): 1 Mu = 3 2 84.90 Ton.m Vu = 0.45 20.80 Ton B.3.2.2.- DISEÑO DE ACERO POR FLEXIÓN FRANJA DE BORDE IZQUIERDO TRAMO 2 Y 4 M (+): 4 1 Mu = 3 2 84.90 Ton.m d = h-3-(5/8")/2 d= 41.206 Vu = 0.45 18.10 Ton d = h-3-(5/8")/2 d= 41.206 1 1 a = As*fy/(0.85*f¨c*b) a= 0.176 As As *d-0.17647*As^2/2-Mu/(o*fy) As = Mu/(o*fy*(d-a/2) As = 0.00 67.457 cm2 5% 70.8303 -5% 64.085 Paralelo al trafico se diseña este acero cantidad de fierros = 34 fierros 5/8 @ 0.10 cm a = As*fy/(0.85*f¨c*b) a= 0.176 As As *d-0.17647*As^2/2-Mu/(o*fy) As = Mu/(o*fy*(d-a/2) As = 0.00 67.457 cm2 5% 70.8303 -5% 64.085 Paralelo al trafico se diseña este acero cantidad de fierros = 34 fierros 5/8 @ 0.10 cm Cheque de cuantia maxima: Cheque de cuantia maxima: Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy] Pmax = 0.0214 Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy] Pmax = 0.0214 p= 0.01637 VERDADERO 7.- DI S EÑO DE ACERO TRANS VERS AL SI h<= 600 mm VERDADERO 26 3/8" @ 0.125 cm acero perpendicuar al trafico As = Analisis para un metro 0.4464 Fierros = 1 9.- CHEQUEO POR CORTE: Vs + Vc >= Vu 0.53*(f´c^0.5)*bw*d>= Vu 36.5442 VERDADERO SI h<= 600 mm Fierros = VERDADERO 26 3/8" @ 0.125 cm acero perpendicuar al trafico @ As >= 0.75*Ag/fy Analisis para un metro As = cm2 3/8" VERDADERO 8.-ACERO TRAS VERS AL S UPERI OR 8.-ACERO TRAS VERS AL S UPERI OR As >= 0.75*Ag/fy 0.01637 AST < 1750/(L^0.5) <= 50% > As AST = 27.67 As Ast = 18.67 AST < 1750/(L^0.5) <= 50% > As AST = 27.67 As Ast = 18.67 Fierros = p= 7.- DI S EÑO DE ACERO TRANS VERS AL 0.33 cm ambos sentidos 0.4464 Fierros = 1 cm2 3/8" 9.- CHEQUEO POR CORTE: Vs + Vc >= Vu 0.53*(f´c^0.5)*bw*d>= Vu 36.5442 VERDADERO @ 0.33 cm ambos sentidos 4
  • 6. B.3.2.3.- DISEÑO DE ACERO POR FLEXIÓN FRANJA DE BORDE DERECHO TRAMO 1 Y 3 M (+): 1 3 2 Mu = 54.54 Ton.m Vu = B.3.2.4.- DISEÑO DE ACERO POR FLEXIÓN FRANJA DE BORDE DERECHO TRAMO 2 Y 4 M (+): 4 34.98 Ton 1 Mu = 3 2 54.54 Ton.m d = h-3-(5/8")/2 0.45 d= 41.206 Vu = 26.95 Ton d = h-3-(5/8")/2 0.45 d= 41.206 1 1 a = As*fy/(0.85*f¨c*b) a= 0.176 As As *d-0.17647*As^2/2-Mu/(o*fy) As = Mu/(o*fy*(d-a/2) As = 0.00 40.606 cm2 5% 42.6362 -5% 38.576 Paralelo al trafico se diseña este acero cantidad de fierros = 20 fierros 5/8 @ 0.10 cm a = As*fy/(0.85*f¨c*b) a= 0.176 As As *d-0.17647*As^2/2-Mu/(o*fy) As = Mu/(o*fy*(d-a/2) As = 0.00 40.606 cm2 5% 42.6362 -5% 38.576 Paralelo al trafico se diseña este acero cantidad de fierros = 20 fierros 5/8 @ 0.10 cm Cheque de cuantia maxima: Cheque de cuantia maxima: Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy] Pmax = 0.0214 Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy] Pmax = 0.0214 p= 0.00985 VERDADERO 7.- DI S EÑO DE ACERO TRANS VERS AL SI h<= 600 mm 8.-ACERO TRAS VERS AL S UPERI OR 0.4464 Fierros = 1 cm2 3/8" 9.- CHEQUEO POR CORTE: Vs + Vc >= Vu 0.53*(f´c^0.5)*bw*d>= Vu 36.5442 VERDADERO SI h<= 600 mm VERDADERO Fierros = 16 3/8" @ 0.125 cm acero perpendicuar al trafico 8.-ACERO TRAS VERS AL S UPERI OR Analisis para un metro As = VERDADERO AST < 1750/(L^0.5) <= 50% > As AST = 27.67 As Ast = 11.24 16 3/8" @ 0.125 cm acero perpendicuar al trafico As >= 0.75*Ag/fy 0.00985 7.- DI S EÑO DE ACERO TRANS VERS AL VERDADERO AST < 1750/(L^0.5) <= 50% > As AST = 27.67 As Ast = 11.24 Fierros = p= @ As >= 0.75*Ag/fy Analisis para un metro As = 0.33 cm ambos sentidos 0.4464 Fierros = 1 cm2 3/8" 9.- CHEQUEO POR CORTE: Vs + Vc >= Vu 0.53*(f´c^0.5)*bw*d>= Vu 36.5442 VERDADERO @ 0.33 cm ambos sentidos 4
  • 7. C.3.1.1.- DISEÑO DE ACERO POR FLEXIÓN FRANJA INTERIOR TRAMO 1 Y 4 M (+): 1 3 2 Mu = 38.69 Ton.m Vu = 0.45 26.72 Ton d = h-3-(5/8")/2 d= 41.206 1 a = As*fy/(0.85*f¨c*b) a= 0.176 As As *d-0.17647*As^2/2-Mu/(o*fy) As = Mu/(o*fy*(d-a/2) As = 0.00 27.9767 cm2 5% 29.3755 -5% 26.5779 Paralelo al trafico se diseña este acero cantidad de fierros = 14 fierros 5/8 @ 0.10 cm Cheque de cuantia maxima: Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy] Pmax = 0.0214 p= 0.00679 VERDADERO 7.- DI S EÑO DE ACERO TRANS VERS AL SI h<= 600 mm VERDADERO AST < 1750/(L^0.5) <= 50% > As AST = 27.67 As Ast = 7.741 Fierros = 11 3/8" @ 0.125 cm acero perpendicuar al trafico 8.-ACERO TRAS VERS AL S UPERI OR As >= 0.75*Ag/fy Analisis para un metro As = 0.4464 Fierros = 1 cm2 3/8" 9.- CHEQUEO POR CORTE: Vs + Vc >= Vu 0.53*(f´c^0.5)*bw*d>= Vu 36.5442 VERDADERO @ 0.33 cm ambos sentidos 4
  • 8. C.3.1.2.- DISEÑO DE ACERO POR FLEXIÓN FRANJA INTERIOR TRAMO 2 Y 3 M (+): 1 3 2 Mu = 26.36 Ton.m Vu = 0.45 23.13 Ton C.3.1.3.- DISEÑO DE ACERO POR FLEXIÓN FRANJA INTERIOR TRAMO 1 Y 4 M (-): 4 1 Mu = 44.38 Ton.m d = h-3-(5/8")/2 d= 41.206 Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy] Pmax = 0.0214 0.00453 VERDADERO 7.- DI S EÑO DE ACERO TRANS VERS AL SI h<= 600 mm d = h-3-(5/8")/2 d= 41.206 8.-ACERO TRAS VERS AL S UPERI OR Fierros = 1 9.- CHEQUEO POR CORTE: Vs + Vc >= Vu 0.53*(f´c^0.5)*bw*d>= Vu VERDADERO 0.00787 @ VERDADERO 0.33 cm ambos sentidos VERDADERO AST < 1750/(L^0.5) <= 50% > As AST = 27.67 As Ast = 8.97 13 3/8" @ 0.125 cm acero perpendicuar al trafico 8.-ACERO TRAS VERS AL S UPERI OR Analisis para un metro As = 0.4464 Fierros = cm2 3/8" p= 7.- DI S EÑO DE ACERO TRANS VERS AL As >= 0.75*Ag/fy Analisis para un metro 0.4464 Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy] Pmax = 0.0214 Fierros = 7 3/8" @ 0.125 cm acero perpendicuar al trafico As = a = As*fy/(0.85*f¨c*b) a= 0.176 As As *d-0.17647*As^2/2-Mu/(o*fy) As = Mu/(o*fy*(d-a/2) As = 0.00 32.4192 cm2 5% 34.0401 -5% 30.7982 Paralelo al trafico se diseña este acero cantidad de fierros = 16 fierros 5/8 @ 0.10 cm SI h<= 600 mm VERDADERO AST < 1750/(L^0.5) <= 50% > As AST = 27.67 As Ast = 5.165 36.5442 Ton Cheque de cuantia maxima: Cheque de cuantia maxima: As >= 0.75*Ag/fy 30.52 1 a = As*fy/(0.85*f¨c*b) a= 0.176 As As *d-0.17647*As^2/2-Mu/(o*fy) As = Mu/(o*fy*(d-a/2) As = 0.00 18.665 cm2 5% 19.5983 -5% 17.7318 Paralelo al trafico se diseña este acero cantidad de fierros = 9 fierros 5/8 @ 0.10 cm Fierros = Vu = 0.45 1 p= 3 2 1 cm2 3/8" 9.- CHEQUEO POR CORTE: Vs + Vc >= Vu 0.53*(f´c^0.5)*bw*d>= Vu 36.5442 VERDADERO @ 0.33 cm ambos sentidos 4
  • 9. C.3.1.4.- DISEÑO DE ACERO POR FLEXIÓN FRANJA INTERIOR TRAMO 2 Y 3 M (-): 1 3 2 Mu = 35.66 Ton.m Vu = 0.45 26.73 Ton C.3.2.1.- DISEÑO DE ACERO POR FLEXIÓN FRANJA DE BORDE IZQUIERDO TRAMO 1 Y 4 M (-): 4 1 Mu = 3 2 49.90 Ton.m d = h-3-(5/8")/2 d= 41.206 Vu = 0.45 1 30.35 Ton d = h-3-(5/8")/2 d= 41.206 1 a = As*fy/(0.85*f¨c*b) a= 0.176 As As *d-0.17647*As^2/2-Mu/(o*fy) As = Mu/(o*fy*(d-a/2) As = 0.00 25.6498 cm2 5% 26.9322 -5% 24.3673 Paralelo al trafico se diseña este acero cantidad de fierros = 13 fierros 5/8 @ 0.10 cm a = As*fy/(0.85*f¨c*b) a= 0.176 As As = Mu/(o*fy*(d-a/2) As = 0.00 36.825 5% 38.666 -5% 34.984 cantidad de fierros = As *d-0.17647*As^2/2-Mu/(o*fy) cm2 Paralelo al trafico se diseña este acero 18 fierros 5/8 @ 0.10 cm Cheque de cuantia maxima: Cheque de cuantia maxima: Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy] Pmax = 0.0214 Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy] Pmax = 0.0214 p= 0.00622 VERDADERO 7.- DI S EÑO DE ACERO TRANS VERS AL SI h<= 600 mm p= 0.00894 VERDADERO 7.- DI S EÑO DE ACERO TRANS VERS AL VERDADERO SI h<= 600 mm VERDADERO AST < 1750/(L^0.5) <= 50% > As AST = 27.67 As Ast = 7.097 AST < 1750/(L^0.5) <= 50% > As AST = 27.67 As Ast = 10.19 Fierros = Fierros = 10 3/8" @ 0.125 cm acero perpendicuar al trafico 8.-ACERO TRAS VERS AL S UPERI OR As >= 0.75*Ag/fy 8.-ACERO TRAS VERS AL S UPERI OR Analisis para un metro As = 0.4464 Fierros = 1 cm2 3/8" 14 3/8" @ 0.125 cm acero perpendicuar al trafico @ As >= 0.75*Ag/fy Analisis para un metro As = 0.33 cm ambos sentidos 0.4464 Fierros = 1 9.- CHEQUEO POR CORTE: 9.- CHEQUEO POR CORTE: Vs + Vc >= Vu cm2 3/8" Vs + Vc >= Vu 0.53*(f´c^0.5)*bw*d>= Vu 36.5442 VERDADERO 0.53*(f´c^0.5)*bw*d>= Vu 36.5442 VERDADERO @ 0.33 cm ambos sentidos 4
  • 10. C.3.2.2.- DISEÑO DE ACERO POR FLEXIÓN FRANJA DE BORDE IZQUIERDO TRAMO 2 Y 3 M (-): 1 Mu = 3 2 36.17 Ton.m Vu = 24.17 Ton C.3.3.1.- DISEÑO DE ACERO POR FLEXIÓN FRANJA DE BORDE DERECHO TRAMO 1 Y 4 M (-): 4 1 Mu = 3 2 56.11 Ton.m d = h-3-(5/8")/2 0.45 d= 41.206 Vu = 34.69 Ton d = h-3-(5/8")/2 0.45 d= 41.206 1 1 a = As*fy/(0.85*f¨c*b) a= 0.176 As As *d-0.17647*As^2/2-Mu/(o*fy) As = Mu/(o*fy*(d-a/2) As = 0.00 26.040 cm2 5% 27.3416 -5% 24.738 Paralelo al trafico se diseña este acero cantidad de fierros = 13 fierros 5/8 @ 0.10 cm a = As*fy/(0.85*f¨c*b) a= 0.176 As As *d-0.17647*As^2/2-Mu/(o*fy) As = Mu/(o*fy*(d-a/2) As = 0.00 41.902 cm2 5% 43.9973 -5% 39.807 Paralelo al trafico se diseña este acero cantidad de fierros = 21 fierros 5/8 @ 0.10 cm Cheque de cuantia maxima: Cheque de cuantia maxima: Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy] Pmax = 0.0214 Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy] Pmax = 0.0214 p= 0.00632 VERDADERO 7.- DI S EÑO DE ACERO TRANS VERS AL SI h<= 600 mm VERDADERO AST < 1750/(L^0.5) <= 50% > As AST = 27.67 As Ast = 7.205 Fierros = 8.-ACERO TRAS VERS AL S UPERI OR 0.4464 Fierros = 1 cm2 3/8" 9.- CHEQUEO POR CORTE: Vs + Vc >= Vu 0.53*(f´c^0.5)*bw*d>= Vu 36.5442 VERDADERO VERDADERO SI h<= 600 mm VERDADERO Fierros = 16 3/8" @ 0.125 cm acero perpendicuar al trafico 8.-ACERO TRAS VERS AL S UPERI OR Analisis para un metro As = 0.01017 AST < 1750/(L^0.5) <= 50% > As AST = 27.67 As Ast = 11.59 10 3/8" @ 0.125 cm acero perpendicuar al trafico As >= 0.75*Ag/fy p= 7.- DI S EÑO DE ACERO TRANS VERS AL @ As >= 0.75*Ag/fy Analisis para un metro As = 0.33 cm ambos sentidos 0.4464 Fierros = 1 cm2 3/8" 9.- CHEQUEO POR CORTE: Vs + Vc >= Vu 0.53*(f´c^0.5)*bw*d>= Vu 36.5442 VERDADERO @ 0.33 cm ambos sentidos 4
  • 11. C.3.3.2.- DISEÑO DE ACERO POR FLEXIÓN FRANJA DE BORDE DERECHO TRAMO 2 Y 3 M (-): 1 Mu = 3 2 39.08 Ton.m Vu = 30.72 Ton d = h-3-(5/8")/2 0.45 d= 41.206 1 a = As*fy/(0.85*f¨c*b) a= 0.176 As As *d-0.17647*As^2/2-Mu/(o*fy) As = Mu/(o*fy*(d-a/2) As = 0.00 28.278 cm2 5% 29.6921 -5% 26.864 Paralelo al trafico se diseña este acero cantidad de fierros = 14 fierros 5/8 @ 0.10 cm Cheque de cuantia maxima: Pmax =0.75*[0.85*B1*f¨c*(6117/(6117+fy))/fy] Pmax = 0.0214 p= 0.00686 VERDADERO 7.- DI S EÑO DE ACERO TRANS VERS AL SI h<= 600 mm VERDADERO AST < 1750/(L^0.5) <= 50% > As AST = 27.67 As Ast = 7.825 Fierros = 11 3/8" @ 0.125 cm acero perpendicuar al trafico 8.-ACERO TRAS VERS AL S UPERI OR As >= 0.75*Ag/fy Analisis para un metro As = 0.4464 Fierros = 1 cm2 3/8" 9.- CHEQUEO POR CORTE: Vs + Vc >= Vu 0.53*(f´c^0.5)*bw*d>= Vu 36.5442 VERDADERO @ 0.33 cm ambos sentidos 4