SlideShare a Scribd company logo
Build a Model
Solution
8/13/15Note: when creating student version, be sure to delete
Scenario Summary worksheet. Also delete the Best and Worse
case scenarios from the Scenario Manager. Also delete this
message in the student version.Chapter:11Estimating Cash
Flows and Analyzing RiskProblem:18Webmasters.com has
developed a powerful new server that would be used for
corporations’ Internet activities. It would cost $10 million at
Year 0 to buy the equipment necessary to manufacture the
server. The project would require net working capital at the
beginning of each year in an amount equal to 10% of the year's
projected sales; for example, NWC0 = 10%(Sales1). The
servers would sell for $24,000 per unit, and Webmasters
believes that variable costs would amount to $17,500 per unit.
After Year 1, the sales price and variable costs will increase at
the inflation rate of 3%. The company’s nonvariable costs
would be $1 million at Year 1 and would increase with
inflation. The server project would have a life of 4 years. If
the project is undertaken, it must be continued for the entire 4
years. Also, the project's returns are expected to be highly
correlated with returns on the firm's other assets. The firm
believes it could sell 1,000 units per year. The equipment
would be depreciated over a 5-year period, using MACRS rates.
The estimated market value of the equipment at the end of the
project’s 4-year life is $500,000. Webmasters’ federal-plus-
state tax rate is 40%. Its cost of capital is 10% for average-risk
projects, defined as projects with a coefficient of variation of
NPV between 0.8 and 1.2. Low-risk projects are evaluated with
a WACC of 8%, and high-risk projects at 13%.a. Develop a
spreadsheet model, and use it to find the project’s NPV, IRR,
and payback. Input Data (in thousands of dollars)Equipment
cost$10,000Key Results:Net operating working
capital/Sales10% NPV =$3,463First year sales (in units)1,000
IRR =21.1%Sales price per unit$24.00 Payback
=2.90Variable cost per unit (excl. depr.)$17.50Nonvariable
costs (excl. depr.)$1,000Market value of equipment at Year
4$500Tax rate40%WACC10%Inflation in prices and
costs3.0%Estimated salvage value at year 4$500Intermediate
Calculations01234Units sold1,0001,0001,0001,000Sales price
per unit (excl. depr.)$24.00$24.72$25.46$26.23Variable costs
per unit (excl. depr.)$17.50$18.03$18.57$19.12Nonvariable
costs (excl. depr.)1,0001,0301,0611,093Sales
revenue$24,000$24,720$25,462$26,225Required level of net
operating working capital$2,400$2,472$2,546$2,623$0Basis for
depreciation$10,000Annual equipment depr.
rate20.00%32.00%19.20%11.52%Annual depreciation
expense$2,000$3,200$1,920$1,152Ending Bk Val: Cost –
Accum Dep'rn$10,000$8,000$4,800$2,880$1,728Salvage
value$500Profit (or loss) on salvage-$1,228Tax on profit (or
loss)-$491Net cash flow due to salvage$991YearsCash Flow
Forecast01234Sales
revenue$24,000$24,720$25,462$26,225Variable
costs17,50018,02518,56619,123Nonvariable operating
costs1,0001,0301,0611,093Depreciation
(equipment)2,0003,2001,9201,152Oper. income before taxes
(EBIT)$3,500$2,465$3,915$4,858Taxes on operating income
(40%)1,4009861,5661,943Net operating profit after
taxes$2,100$1,479$2,349$2,915Add back
depreciation2,0003,2001,9201,152Equipment purchases-
$10,000Cash flow due to change in NOWC-$2,400-$72-$74-
$76$2,623Net cash flow due to salvage$991Net Cash Flow
(Time line of cash flows)-
$12,400$4,028$4,605$4,193$7,681Key Results: Appraisal of
the Proposed ProjectNet Present Value (at 10%) =$3,463IRR
=21.09%MIRR =16.99%Payback = 2.90Discounted Payback =
3.23Data for Payback YearsYears01234Net cash flow-
$12,400$4,028$4,605$4,193$7,681Cumulative CF -$12,400-
$8,372-$3,767$425$8,106Part of year required for
payback1.001.000.900.00Data for Discounted Payback
YearsYears01234Net cash flow-
$12,400$4,028$4,605$4,193$7,681Discounted cash flow-
$12,400$3,662$3,806$3,150$5,246Cumulative CF -$12,400-
$8,738-$4,933-$1,783$3,463Part of year required for discounted
payback1.001.001.000.23b. Now conduct a sensitivity analysis
to determine the sensitivity of NPV to changes in the sales
price, variable costs per unit, and number of units sold. Set
these variables’ values at 10% and 20% above and below their
base-case values. Include a graph in your analysis.%
DeviationSALES PRICENote about data tables. The data in the
column input should NOT be input using a cell reference to the
column input cell. For example, the base case Sales Price in
Cell B95 should be the number $24.00 you should NOT have the
formula =D28 in that cell. This is because you'll use D28 as the
column input cell in the data table and if Excel tries to
iteratively replace Cell D28 with the formula =D28 rather than a
series of numbers, Excel will calculate the wrong answer.
Unfortunately, Excel won't tell you that there is a problem, so
you'll just get the wrong values for the data
table!fromBaseNPVBase Case$24.00$3,463-20%$19.20-$5,893-
10%$21.60-
$1,2150%$24.00$3,46310%$26.40$8,14120%$28.80$12,820%
DeviationVARIABLE COST% Deviation1st YEAR UNIT
SALESfromBaseNPVfromBaseNPVBase Case$17.50$3,463Base
Case1,000$3,463-20%$14.00$10,401-20%800$1,045-
10%$15.75$6,932-
10%900$2,2540%$17.50$3,4630%1,000$3,46310%$19.25-
$610%1,100$4,67320%$21.00-
$3,47520%1,200$5,882DeviationNPV at Different Deviations
from BasefromSalesVariableBase CasePriceCost/UnitUnits
Sold-20%-$5,893$10,401$1,045-10%-
$1,215$6,932$2,2540%$3,463$3,463$3,46310%$8,141-
$6$4,67320%$12,820-
$3,475$5,882Range$18,712$13,876$4,837c. Now conduct a
scenario analysis. Assume that there is a 25% probability that
best-case conditions, with each of the variables discussed in
Part b being 20% better than its base-case value, will occur.
There is a 25% probability of worst-case conditions, with the
variables 20% worse than base, and a 50% probability of base-
case
conditions.SalesUnitVariableScenarioProbabilityPriceSalesCost
sNPVBest Case25%$28.801,200$14.00$25,435Base
Case50%$24.001,000$17.50$3,463 Worst Case
25%$19.20800$21.00($11,990)Expected NPV =$5,093Standard
Deviation = $13,332Coefficient of Variation = Std Dev /
Expected NPV =2.62d. If the project appears to be more or less
risky than an average project, find its risk-adjusted NPV, IRR,
and payback.CV range of firm's average-risk
project:0.8to1.2Low-risk WACC =8%WACC =10%High-risk
WACC =13%Risk-adjusted WACC =13%Risk adjusted NPV
=$2,387IRR =21.09%
Kenneth D. Jackson: IRR does not change.
Payback =2.90
Kenneth D. Jackson: Paypack does not change.
e. On the basis of information in the problem, would you
recommend that the project be accepted?At this point, the
project looks risky but acceptable. There is a good chance that
it will produce a positive NPV, but there is also a chance that
the NPV could be quite low.The problem gave no information
about the size of the project relative to the total corporation. If
the company were quite large, and this were but one of many
projects, and if the projects were independent of one another,
then it should be accepted. However, if the firm were relatively
small, and this project under bad conditions could bankrupt the
company, then the decision is not clear. If management is
highly risk averse, they might turn it down. However, well-
diversified investors would probably prefer to see it accepted.
So, to maximize the stock price, it should be accepted.We
indicate in the problem that this project's returns will tend to be
highly correlated with the firm's other projects' returns. Thus,
its stand-alone risk (which is what we have been analyzing) also
reflects its within-firm risk. If this were not true, then we
would need to make further risk adjustments.
Sensitivity Analysis
Sales price-0.2-0.100.10.2-5892.876254354208-
1214.76951847552123463.33721740317748141.4439532818797
12819.550689160566VC-0.2-
0.100.10.210401.2073765453136932.27229697424633463.3372
174031774-5.5978621678877971-3474.5329417389548Units-
0.2-
0.100.10.21044.99390478791972254.16556109554953463.3372
1740317744672.50887371080535881.6805300184315
Percentage Deviation from Base
NPV ($)
Scenario SummaryScenario SummaryCurrent
Values:BaseBestWorstCreated by Michael C. Ehrhardt on
11/13/2001Created by Michael C. Ehrhardt on 11/13/2001
Modified by Michael C. Ehrhardt on 11/13/2001Created by
Michael C. Ehrhardt on 11/13/2001Changing
Cells:$D$291,0001,0001,200800$D$30$24.00$24.00$28.80$19.
20$D$31$17.50$17.50$14.00$21.00Result
Cells:$D$79$3,463$3,463$25,435($11,990)$D$8021.09%21.09
%76.96%ERROR:#NUM!$D$8116.99%16.99%43.42%-
41.46%Notes: Current Values column represents values of
changing cells attime Scenario Summary Report was created.
Changing cells for eachscenario are highlighted in gray.
Build a ModelSolution81315Note when creating student version, b.docx

More Related Content

Similar to Build a ModelSolution81315Note when creating student version, b.docx

Compute IRR and NPV in Microsoft Excel 1.IRR Function .docx
Compute IRR and NPV in Microsoft Excel 1.IRR Function .docxCompute IRR and NPV in Microsoft Excel 1.IRR Function .docx
Compute IRR and NPV in Microsoft Excel 1.IRR Function .docx
patricke8
 
CASE17CASE 19 Instructor VersionCopyright 2014 Health .docx
CASE17CASE 19             Instructor VersionCopyright 2014 Health .docxCASE17CASE 19             Instructor VersionCopyright 2014 Health .docx
CASE17CASE 19 Instructor VersionCopyright 2014 Health .docx
wendolynhalbert
 
Project Profitability Analysis and Evaluation
Project Profitability Analysis and EvaluationProject Profitability Analysis and Evaluation
Project Profitability Analysis and EvaluationArpit Amar
 
Ch05 P24 Build a Model Spring 1, 201372212Chapter 5. Ch 05 P24 B.docx
Ch05 P24 Build a Model Spring 1, 201372212Chapter 5. Ch 05 P24 B.docxCh05 P24 Build a Model Spring 1, 201372212Chapter 5. Ch 05 P24 B.docx
Ch05 P24 Build a Model Spring 1, 201372212Chapter 5. Ch 05 P24 B.docx
tidwellveronique
 
Benchmarking using replacement asset value
Benchmarking using replacement asset valueBenchmarking using replacement asset value
Benchmarking using replacement asset value
Business Industrial Network
 
Cbproblems solutions
Cbproblems solutionsCbproblems solutions
Cbproblems solutionsmely3178
 
1. Payback Period and Net Present Value[LO1, 2] If a project with .docx
1. Payback Period and Net Present Value[LO1, 2] If a project with .docx1. Payback Period and Net Present Value[LO1, 2] If a project with .docx
1. Payback Period and Net Present Value[LO1, 2] If a project with .docx
paynetawnya
 
Management consultancy-chapter-26-and-35
Management consultancy-chapter-26-and-35Management consultancy-chapter-26-and-35
Management consultancy-chapter-26-and-35
Holy Cross College
 
Schneider, Arnold, (2012) Managerial Accounting, United States, .docx
Schneider, Arnold, (2012) Managerial Accounting, United States, .docxSchneider, Arnold, (2012) Managerial Accounting, United States, .docx
Schneider, Arnold, (2012) Managerial Accounting, United States, .docx
anhlodge
 
AgendaComprehending risk when modeling investment (project) de.docx
AgendaComprehending risk when modeling investment (project) de.docxAgendaComprehending risk when modeling investment (project) de.docx
AgendaComprehending risk when modeling investment (project) de.docx
galerussel59292
 
Project_selectionProject_selectionnn.ppt
Project_selectionProject_selectionnn.pptProject_selectionProject_selectionnn.ppt
Project_selectionProject_selectionnn.ppt
ssdongre1
 
Lecture cash flow evaluation new
Lecture cash flow evaluation newLecture cash flow evaluation new
Lecture cash flow evaluation newBsgr Planmin
 
Lecture cash flow evaluation new
Lecture cash flow evaluation newLecture cash flow evaluation new
Lecture cash flow evaluation newBsgr Planmin
 
Ch14sol cash flow estimation
Ch14sol cash flow estimationCh14sol cash flow estimation
Ch14sol cash flow estimation
Hassan Zada
 
7.12Chapter 7 Problem 12a). Complete the spreadsheet below by esti.docx
7.12Chapter 7 Problem 12a). Complete the spreadsheet below by esti.docx7.12Chapter 7 Problem 12a). Complete the spreadsheet below by esti.docx
7.12Chapter 7 Problem 12a). Complete the spreadsheet below by esti.docx
alinainglis
 

Similar to Build a ModelSolution81315Note when creating student version, b.docx (17)

Compute IRR and NPV in Microsoft Excel 1.IRR Function .docx
Compute IRR and NPV in Microsoft Excel 1.IRR Function .docxCompute IRR and NPV in Microsoft Excel 1.IRR Function .docx
Compute IRR and NPV in Microsoft Excel 1.IRR Function .docx
 
CASE17CASE 19 Instructor VersionCopyright 2014 Health .docx
CASE17CASE 19             Instructor VersionCopyright 2014 Health .docxCASE17CASE 19             Instructor VersionCopyright 2014 Health .docx
CASE17CASE 19 Instructor VersionCopyright 2014 Health .docx
 
Project Profitability Analysis and Evaluation
Project Profitability Analysis and EvaluationProject Profitability Analysis and Evaluation
Project Profitability Analysis and Evaluation
 
Ch05 P24 Build a Model Spring 1, 201372212Chapter 5. Ch 05 P24 B.docx
Ch05 P24 Build a Model Spring 1, 201372212Chapter 5. Ch 05 P24 B.docxCh05 P24 Build a Model Spring 1, 201372212Chapter 5. Ch 05 P24 B.docx
Ch05 P24 Build a Model Spring 1, 201372212Chapter 5. Ch 05 P24 B.docx
 
Benchmarking using replacement asset value
Benchmarking using replacement asset valueBenchmarking using replacement asset value
Benchmarking using replacement asset value
 
Cbproblems solutions
Cbproblems solutionsCbproblems solutions
Cbproblems solutions
 
Cbproblems solutions
Cbproblems solutionsCbproblems solutions
Cbproblems solutions
 
1. Payback Period and Net Present Value[LO1, 2] If a project with .docx
1. Payback Period and Net Present Value[LO1, 2] If a project with .docx1. Payback Period and Net Present Value[LO1, 2] If a project with .docx
1. Payback Period and Net Present Value[LO1, 2] If a project with .docx
 
Management consultancy-chapter-26-and-35
Management consultancy-chapter-26-and-35Management consultancy-chapter-26-and-35
Management consultancy-chapter-26-and-35
 
Schneider, Arnold, (2012) Managerial Accounting, United States, .docx
Schneider, Arnold, (2012) Managerial Accounting, United States, .docxSchneider, Arnold, (2012) Managerial Accounting, United States, .docx
Schneider, Arnold, (2012) Managerial Accounting, United States, .docx
 
AgendaComprehending risk when modeling investment (project) de.docx
AgendaComprehending risk when modeling investment (project) de.docxAgendaComprehending risk when modeling investment (project) de.docx
AgendaComprehending risk when modeling investment (project) de.docx
 
Project_selectionProject_selectionnn.ppt
Project_selectionProject_selectionnn.pptProject_selectionProject_selectionnn.ppt
Project_selectionProject_selectionnn.ppt
 
Lecture cash flow evaluation new
Lecture cash flow evaluation newLecture cash flow evaluation new
Lecture cash flow evaluation new
 
Lecture cash flow evaluation new
Lecture cash flow evaluation newLecture cash flow evaluation new
Lecture cash flow evaluation new
 
Ch14sol cash flow estimation
Ch14sol cash flow estimationCh14sol cash flow estimation
Ch14sol cash flow estimation
 
7.12Chapter 7 Problem 12a). Complete the spreadsheet below by esti.docx
7.12Chapter 7 Problem 12a). Complete the spreadsheet below by esti.docx7.12Chapter 7 Problem 12a). Complete the spreadsheet below by esti.docx
7.12Chapter 7 Problem 12a). Complete the spreadsheet below by esti.docx
 
Ch12ppt
Ch12pptCh12ppt
Ch12ppt
 

More from jasoninnes20

1-2paragraphsapa formatWelcome to Module 6. Divers.docx
1-2paragraphsapa formatWelcome to Module 6. Divers.docx1-2paragraphsapa formatWelcome to Module 6. Divers.docx
1-2paragraphsapa formatWelcome to Module 6. Divers.docx
jasoninnes20
 
1-Post a two-paragraph summary of the lecture;  2- Review the li.docx
1-Post a two-paragraph summary of the lecture;  2- Review the li.docx1-Post a two-paragraph summary of the lecture;  2- Review the li.docx
1-Post a two-paragraph summary of the lecture;  2- Review the li.docx
jasoninnes20
 
1-What are the pros and cons of parole. Discuss!2-Discuss ways t.docx
1-What are the pros and cons of parole. Discuss!2-Discuss ways t.docx1-What are the pros and cons of parole. Discuss!2-Discuss ways t.docx
1-What are the pros and cons of parole. Discuss!2-Discuss ways t.docx
jasoninnes20
 
1-page (max) proposal including a Title, Executive Summary, Outline,.docx
1-page (max) proposal including a Title, Executive Summary, Outline,.docx1-page (max) proposal including a Title, Executive Summary, Outline,.docx
1-page (max) proposal including a Title, Executive Summary, Outline,.docx
jasoninnes20
 
1-Identify the benefits of sharing your action research with oth.docx
1-Identify the benefits of sharing your action research with oth.docx1-Identify the benefits of sharing your action research with oth.docx
1-Identify the benefits of sharing your action research with oth.docx
jasoninnes20
 
1-page APA 7 the edition No referenceDescription of Personal a.docx
1-page APA 7 the edition  No referenceDescription of Personal a.docx1-page APA 7 the edition  No referenceDescription of Personal a.docx
1-page APA 7 the edition No referenceDescription of Personal a.docx
jasoninnes20
 
1-Pretend that you are a new teacher.  You see that one of your st.docx
1-Pretend that you are a new teacher.  You see that one of your st.docx1-Pretend that you are a new teacher.  You see that one of your st.docx
1-Pretend that you are a new teacher.  You see that one of your st.docx
jasoninnes20
 
1- What is the difference between a multi-valued attribute and a.docx
1- What is the difference between a multi-valued attribute and a.docx1- What is the difference between a multi-valued attribute and a.docx
1- What is the difference between a multi-valued attribute and a.docx
jasoninnes20
 
1- What is a Relational Algebra What are the operators. Explain.docx
1- What is a Relational Algebra What are the operators. Explain.docx1- What is a Relational Algebra What are the operators. Explain.docx
1- What is a Relational Algebra What are the operators. Explain.docx
jasoninnes20
 
1- Watch the movie Don Quixote, which is an adaptation of Cerv.docx
1- Watch the movie Don Quixote, which is an adaptation of Cerv.docx1- Watch the movie Don Quixote, which is an adaptation of Cerv.docx
1- Watch the movie Don Quixote, which is an adaptation of Cerv.docx
jasoninnes20
 
1- reply to both below, no more than 75 words per each.  PSY 771.docx
1- reply to both below, no more than 75 words per each.  PSY 771.docx1- reply to both below, no more than 75 words per each.  PSY 771.docx
1- reply to both below, no more than 75 words per each.  PSY 771.docx
jasoninnes20
 
1- Pathogenesis 2- Organs affected in the body 3- Chain of i.docx
1- Pathogenesis 2- Organs affected in the body 3- Chain of i.docx1- Pathogenesis 2- Organs affected in the body 3- Chain of i.docx
1- Pathogenesis 2- Organs affected in the body 3- Chain of i.docx
jasoninnes20
 
1-  I can totally see where there would be tension between.docx
1-  I can totally see where there would be tension between.docx1-  I can totally see where there would be tension between.docx
1-  I can totally see where there would be tension between.docx
jasoninnes20
 
1- One of the most difficult challenges leaders face is to integrate.docx
1- One of the most difficult challenges leaders face is to integrate.docx1- One of the most difficult challenges leaders face is to integrate.docx
1- One of the most difficult challenges leaders face is to integrate.docx
jasoninnes20
 
1- Design one assignment of the Word Find (education word) and the o.docx
1- Design one assignment of the Word Find (education word) and the o.docx1- Design one assignment of the Word Find (education word) and the o.docx
1- Design one assignment of the Word Find (education word) and the o.docx
jasoninnes20
 
1- This chapter suggests that emotional intelligence is an interpers.docx
1- This chapter suggests that emotional intelligence is an interpers.docx1- This chapter suggests that emotional intelligence is an interpers.docx
1- This chapter suggests that emotional intelligence is an interpers.docx
jasoninnes20
 
1-2 pages APA format1. overall purpose of site 2. resources .docx
1-2 pages APA format1. overall purpose of site 2. resources .docx1-2 pages APA format1. overall purpose of site 2. resources .docx
1-2 pages APA format1. overall purpose of site 2. resources .docx
jasoninnes20
 
1-Define Energy.2- What is Potential energy3- What is K.docx
1-Define Energy.2- What is Potential energy3- What is K.docx1-Define Energy.2- What is Potential energy3- What is K.docx
1-Define Energy.2- What is Potential energy3- What is K.docx
jasoninnes20
 
1- Find one quote from chapter 7-9. Explain why this quote stood.docx
1- Find one quote from chapter 7-9. Explain why this quote stood.docx1- Find one quote from chapter 7-9. Explain why this quote stood.docx
1- Find one quote from chapter 7-9. Explain why this quote stood.docx
jasoninnes20
 
1-Confucianism2-ShintoChoose one of the religious system.docx
1-Confucianism2-ShintoChoose one of the religious system.docx1-Confucianism2-ShintoChoose one of the religious system.docx
1-Confucianism2-ShintoChoose one of the religious system.docx
jasoninnes20
 

More from jasoninnes20 (20)

1-2paragraphsapa formatWelcome to Module 6. Divers.docx
1-2paragraphsapa formatWelcome to Module 6. Divers.docx1-2paragraphsapa formatWelcome to Module 6. Divers.docx
1-2paragraphsapa formatWelcome to Module 6. Divers.docx
 
1-Post a two-paragraph summary of the lecture;  2- Review the li.docx
1-Post a two-paragraph summary of the lecture;  2- Review the li.docx1-Post a two-paragraph summary of the lecture;  2- Review the li.docx
1-Post a two-paragraph summary of the lecture;  2- Review the li.docx
 
1-What are the pros and cons of parole. Discuss!2-Discuss ways t.docx
1-What are the pros and cons of parole. Discuss!2-Discuss ways t.docx1-What are the pros and cons of parole. Discuss!2-Discuss ways t.docx
1-What are the pros and cons of parole. Discuss!2-Discuss ways t.docx
 
1-page (max) proposal including a Title, Executive Summary, Outline,.docx
1-page (max) proposal including a Title, Executive Summary, Outline,.docx1-page (max) proposal including a Title, Executive Summary, Outline,.docx
1-page (max) proposal including a Title, Executive Summary, Outline,.docx
 
1-Identify the benefits of sharing your action research with oth.docx
1-Identify the benefits of sharing your action research with oth.docx1-Identify the benefits of sharing your action research with oth.docx
1-Identify the benefits of sharing your action research with oth.docx
 
1-page APA 7 the edition No referenceDescription of Personal a.docx
1-page APA 7 the edition  No referenceDescription of Personal a.docx1-page APA 7 the edition  No referenceDescription of Personal a.docx
1-page APA 7 the edition No referenceDescription of Personal a.docx
 
1-Pretend that you are a new teacher.  You see that one of your st.docx
1-Pretend that you are a new teacher.  You see that one of your st.docx1-Pretend that you are a new teacher.  You see that one of your st.docx
1-Pretend that you are a new teacher.  You see that one of your st.docx
 
1- What is the difference between a multi-valued attribute and a.docx
1- What is the difference between a multi-valued attribute and a.docx1- What is the difference between a multi-valued attribute and a.docx
1- What is the difference between a multi-valued attribute and a.docx
 
1- What is a Relational Algebra What are the operators. Explain.docx
1- What is a Relational Algebra What are the operators. Explain.docx1- What is a Relational Algebra What are the operators. Explain.docx
1- What is a Relational Algebra What are the operators. Explain.docx
 
1- Watch the movie Don Quixote, which is an adaptation of Cerv.docx
1- Watch the movie Don Quixote, which is an adaptation of Cerv.docx1- Watch the movie Don Quixote, which is an adaptation of Cerv.docx
1- Watch the movie Don Quixote, which is an adaptation of Cerv.docx
 
1- reply to both below, no more than 75 words per each.  PSY 771.docx
1- reply to both below, no more than 75 words per each.  PSY 771.docx1- reply to both below, no more than 75 words per each.  PSY 771.docx
1- reply to both below, no more than 75 words per each.  PSY 771.docx
 
1- Pathogenesis 2- Organs affected in the body 3- Chain of i.docx
1- Pathogenesis 2- Organs affected in the body 3- Chain of i.docx1- Pathogenesis 2- Organs affected in the body 3- Chain of i.docx
1- Pathogenesis 2- Organs affected in the body 3- Chain of i.docx
 
1-  I can totally see where there would be tension between.docx
1-  I can totally see where there would be tension between.docx1-  I can totally see where there would be tension between.docx
1-  I can totally see where there would be tension between.docx
 
1- One of the most difficult challenges leaders face is to integrate.docx
1- One of the most difficult challenges leaders face is to integrate.docx1- One of the most difficult challenges leaders face is to integrate.docx
1- One of the most difficult challenges leaders face is to integrate.docx
 
1- Design one assignment of the Word Find (education word) and the o.docx
1- Design one assignment of the Word Find (education word) and the o.docx1- Design one assignment of the Word Find (education word) and the o.docx
1- Design one assignment of the Word Find (education word) and the o.docx
 
1- This chapter suggests that emotional intelligence is an interpers.docx
1- This chapter suggests that emotional intelligence is an interpers.docx1- This chapter suggests that emotional intelligence is an interpers.docx
1- This chapter suggests that emotional intelligence is an interpers.docx
 
1-2 pages APA format1. overall purpose of site 2. resources .docx
1-2 pages APA format1. overall purpose of site 2. resources .docx1-2 pages APA format1. overall purpose of site 2. resources .docx
1-2 pages APA format1. overall purpose of site 2. resources .docx
 
1-Define Energy.2- What is Potential energy3- What is K.docx
1-Define Energy.2- What is Potential energy3- What is K.docx1-Define Energy.2- What is Potential energy3- What is K.docx
1-Define Energy.2- What is Potential energy3- What is K.docx
 
1- Find one quote from chapter 7-9. Explain why this quote stood.docx
1- Find one quote from chapter 7-9. Explain why this quote stood.docx1- Find one quote from chapter 7-9. Explain why this quote stood.docx
1- Find one quote from chapter 7-9. Explain why this quote stood.docx
 
1-Confucianism2-ShintoChoose one of the religious system.docx
1-Confucianism2-ShintoChoose one of the religious system.docx1-Confucianism2-ShintoChoose one of the religious system.docx
1-Confucianism2-ShintoChoose one of the religious system.docx
 

Recently uploaded

Thesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.pptThesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.ppt
EverAndrsGuerraGuerr
 
Synthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptxSynthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptx
Pavel ( NSTU)
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
siemaillard
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
siemaillard
 
Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345
beazzy04
 
Home assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdfHome assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdf
Tamralipta Mahavidyalaya
 
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
EugeneSaldivar
 
How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...
Jisc
 
Sectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdfSectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdf
Vivekanand Anglo Vedic Academy
 
Overview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with MechanismOverview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with Mechanism
DeeptiGupta154
 
2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...
Sandy Millin
 
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCECLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
BhavyaRajput3
 
Fish and Chips - have they had their chips
Fish and Chips - have they had their chipsFish and Chips - have they had their chips
Fish and Chips - have they had their chips
GeoBlogs
 
Additional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdfAdditional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdf
joachimlavalley1
 
Cambridge International AS A Level Biology Coursebook - EBook (MaryFosbery J...
Cambridge International AS  A Level Biology Coursebook - EBook (MaryFosbery J...Cambridge International AS  A Level Biology Coursebook - EBook (MaryFosbery J...
Cambridge International AS A Level Biology Coursebook - EBook (MaryFosbery J...
AzmatAli747758
 
MARUTI SUZUKI- A Successful Joint Venture in India.pptx
MARUTI SUZUKI- A Successful Joint Venture in India.pptxMARUTI SUZUKI- A Successful Joint Venture in India.pptx
MARUTI SUZUKI- A Successful Joint Venture in India.pptx
bennyroshan06
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
Celine George
 
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptxStudents, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
EduSkills OECD
 
How to Split Bills in the Odoo 17 POS Module
How to Split Bills in the Odoo 17 POS ModuleHow to Split Bills in the Odoo 17 POS Module
How to Split Bills in the Odoo 17 POS Module
Celine George
 
Supporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptxSupporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptx
Jisc
 

Recently uploaded (20)

Thesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.pptThesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.ppt
 
Synthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptxSynthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptx
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
 
Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345
 
Home assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdfHome assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdf
 
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
 
How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...
 
Sectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdfSectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdf
 
Overview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with MechanismOverview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with Mechanism
 
2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...
 
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCECLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
 
Fish and Chips - have they had their chips
Fish and Chips - have they had their chipsFish and Chips - have they had their chips
Fish and Chips - have they had their chips
 
Additional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdfAdditional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdf
 
Cambridge International AS A Level Biology Coursebook - EBook (MaryFosbery J...
Cambridge International AS  A Level Biology Coursebook - EBook (MaryFosbery J...Cambridge International AS  A Level Biology Coursebook - EBook (MaryFosbery J...
Cambridge International AS A Level Biology Coursebook - EBook (MaryFosbery J...
 
MARUTI SUZUKI- A Successful Joint Venture in India.pptx
MARUTI SUZUKI- A Successful Joint Venture in India.pptxMARUTI SUZUKI- A Successful Joint Venture in India.pptx
MARUTI SUZUKI- A Successful Joint Venture in India.pptx
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
 
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptxStudents, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
 
How to Split Bills in the Odoo 17 POS Module
How to Split Bills in the Odoo 17 POS ModuleHow to Split Bills in the Odoo 17 POS Module
How to Split Bills in the Odoo 17 POS Module
 
Supporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptxSupporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptx
 

Build a ModelSolution81315Note when creating student version, b.docx

  • 1. Build a Model Solution 8/13/15Note: when creating student version, be sure to delete Scenario Summary worksheet. Also delete the Best and Worse case scenarios from the Scenario Manager. Also delete this message in the student version.Chapter:11Estimating Cash Flows and Analyzing RiskProblem:18Webmasters.com has developed a powerful new server that would be used for corporations’ Internet activities. It would cost $10 million at Year 0 to buy the equipment necessary to manufacture the server. The project would require net working capital at the beginning of each year in an amount equal to 10% of the year's projected sales; for example, NWC0 = 10%(Sales1). The servers would sell for $24,000 per unit, and Webmasters believes that variable costs would amount to $17,500 per unit. After Year 1, the sales price and variable costs will increase at the inflation rate of 3%. The company’s nonvariable costs would be $1 million at Year 1 and would increase with inflation. The server project would have a life of 4 years. If the project is undertaken, it must be continued for the entire 4 years. Also, the project's returns are expected to be highly
  • 2. correlated with returns on the firm's other assets. The firm believes it could sell 1,000 units per year. The equipment would be depreciated over a 5-year period, using MACRS rates. The estimated market value of the equipment at the end of the project’s 4-year life is $500,000. Webmasters’ federal-plus- state tax rate is 40%. Its cost of capital is 10% for average-risk projects, defined as projects with a coefficient of variation of NPV between 0.8 and 1.2. Low-risk projects are evaluated with a WACC of 8%, and high-risk projects at 13%.a. Develop a spreadsheet model, and use it to find the project’s NPV, IRR, and payback. Input Data (in thousands of dollars)Equipment cost$10,000Key Results:Net operating working capital/Sales10% NPV =$3,463First year sales (in units)1,000 IRR =21.1%Sales price per unit$24.00 Payback =2.90Variable cost per unit (excl. depr.)$17.50Nonvariable costs (excl. depr.)$1,000Market value of equipment at Year 4$500Tax rate40%WACC10%Inflation in prices and costs3.0%Estimated salvage value at year 4$500Intermediate Calculations01234Units sold1,0001,0001,0001,000Sales price per unit (excl. depr.)$24.00$24.72$25.46$26.23Variable costs per unit (excl. depr.)$17.50$18.03$18.57$19.12Nonvariable costs (excl. depr.)1,0001,0301,0611,093Sales revenue$24,000$24,720$25,462$26,225Required level of net operating working capital$2,400$2,472$2,546$2,623$0Basis for depreciation$10,000Annual equipment depr.
  • 3. rate20.00%32.00%19.20%11.52%Annual depreciation expense$2,000$3,200$1,920$1,152Ending Bk Val: Cost – Accum Dep'rn$10,000$8,000$4,800$2,880$1,728Salvage value$500Profit (or loss) on salvage-$1,228Tax on profit (or loss)-$491Net cash flow due to salvage$991YearsCash Flow Forecast01234Sales revenue$24,000$24,720$25,462$26,225Variable costs17,50018,02518,56619,123Nonvariable operating costs1,0001,0301,0611,093Depreciation (equipment)2,0003,2001,9201,152Oper. income before taxes (EBIT)$3,500$2,465$3,915$4,858Taxes on operating income (40%)1,4009861,5661,943Net operating profit after taxes$2,100$1,479$2,349$2,915Add back depreciation2,0003,2001,9201,152Equipment purchases- $10,000Cash flow due to change in NOWC-$2,400-$72-$74- $76$2,623Net cash flow due to salvage$991Net Cash Flow (Time line of cash flows)- $12,400$4,028$4,605$4,193$7,681Key Results: Appraisal of the Proposed ProjectNet Present Value (at 10%) =$3,463IRR =21.09%MIRR =16.99%Payback = 2.90Discounted Payback = 3.23Data for Payback YearsYears01234Net cash flow- $12,400$4,028$4,605$4,193$7,681Cumulative CF -$12,400- $8,372-$3,767$425$8,106Part of year required for payback1.001.000.900.00Data for Discounted Payback YearsYears01234Net cash flow-
  • 4. $12,400$4,028$4,605$4,193$7,681Discounted cash flow- $12,400$3,662$3,806$3,150$5,246Cumulative CF -$12,400- $8,738-$4,933-$1,783$3,463Part of year required for discounted payback1.001.001.000.23b. Now conduct a sensitivity analysis to determine the sensitivity of NPV to changes in the sales price, variable costs per unit, and number of units sold. Set these variables’ values at 10% and 20% above and below their base-case values. Include a graph in your analysis.% DeviationSALES PRICENote about data tables. The data in the column input should NOT be input using a cell reference to the column input cell. For example, the base case Sales Price in Cell B95 should be the number $24.00 you should NOT have the formula =D28 in that cell. This is because you'll use D28 as the column input cell in the data table and if Excel tries to iteratively replace Cell D28 with the formula =D28 rather than a series of numbers, Excel will calculate the wrong answer. Unfortunately, Excel won't tell you that there is a problem, so you'll just get the wrong values for the data table!fromBaseNPVBase Case$24.00$3,463-20%$19.20-$5,893- 10%$21.60- $1,2150%$24.00$3,46310%$26.40$8,14120%$28.80$12,820% DeviationVARIABLE COST% Deviation1st YEAR UNIT SALESfromBaseNPVfromBaseNPVBase Case$17.50$3,463Base Case1,000$3,463-20%$14.00$10,401-20%800$1,045- 10%$15.75$6,932-
  • 5. 10%900$2,2540%$17.50$3,4630%1,000$3,46310%$19.25- $610%1,100$4,67320%$21.00- $3,47520%1,200$5,882DeviationNPV at Different Deviations from BasefromSalesVariableBase CasePriceCost/UnitUnits Sold-20%-$5,893$10,401$1,045-10%- $1,215$6,932$2,2540%$3,463$3,463$3,46310%$8,141- $6$4,67320%$12,820- $3,475$5,882Range$18,712$13,876$4,837c. Now conduct a scenario analysis. Assume that there is a 25% probability that best-case conditions, with each of the variables discussed in Part b being 20% better than its base-case value, will occur. There is a 25% probability of worst-case conditions, with the variables 20% worse than base, and a 50% probability of base- case conditions.SalesUnitVariableScenarioProbabilityPriceSalesCost sNPVBest Case25%$28.801,200$14.00$25,435Base Case50%$24.001,000$17.50$3,463 Worst Case 25%$19.20800$21.00($11,990)Expected NPV =$5,093Standard Deviation = $13,332Coefficient of Variation = Std Dev / Expected NPV =2.62d. If the project appears to be more or less risky than an average project, find its risk-adjusted NPV, IRR, and payback.CV range of firm's average-risk project:0.8to1.2Low-risk WACC =8%WACC =10%High-risk WACC =13%Risk-adjusted WACC =13%Risk adjusted NPV =$2,387IRR =21.09%
  • 6. Kenneth D. Jackson: IRR does not change. Payback =2.90 Kenneth D. Jackson: Paypack does not change. e. On the basis of information in the problem, would you recommend that the project be accepted?At this point, the project looks risky but acceptable. There is a good chance that it will produce a positive NPV, but there is also a chance that the NPV could be quite low.The problem gave no information about the size of the project relative to the total corporation. If the company were quite large, and this were but one of many projects, and if the projects were independent of one another, then it should be accepted. However, if the firm were relatively small, and this project under bad conditions could bankrupt the company, then the decision is not clear. If management is highly risk averse, they might turn it down. However, well- diversified investors would probably prefer to see it accepted. So, to maximize the stock price, it should be accepted.We indicate in the problem that this project's returns will tend to be highly correlated with the firm's other projects' returns. Thus, its stand-alone risk (which is what we have been analyzing) also reflects its within-firm risk. If this were not true, then we would need to make further risk adjustments. Sensitivity Analysis
  • 7. Sales price-0.2-0.100.10.2-5892.876254354208- 1214.76951847552123463.33721740317748141.4439532818797 12819.550689160566VC-0.2- 0.100.10.210401.2073765453136932.27229697424633463.3372 174031774-5.5978621678877971-3474.5329417389548Units- 0.2- 0.100.10.21044.99390478791972254.16556109554953463.3372 1740317744672.50887371080535881.6805300184315 Percentage Deviation from Base NPV ($) Scenario SummaryScenario SummaryCurrent Values:BaseBestWorstCreated by Michael C. Ehrhardt on 11/13/2001Created by Michael C. Ehrhardt on 11/13/2001 Modified by Michael C. Ehrhardt on 11/13/2001Created by Michael C. Ehrhardt on 11/13/2001Changing Cells:$D$291,0001,0001,200800$D$30$24.00$24.00$28.80$19. 20$D$31$17.50$17.50$14.00$21.00Result Cells:$D$79$3,463$3,463$25,435($11,990)$D$8021.09%21.09 %76.96%ERROR:#NUM!$D$8116.99%16.99%43.42%- 41.46%Notes: Current Values column represents values of changing cells attime Scenario Summary Report was created. Changing cells for eachscenario are highlighted in gray.