Nadeem Kureshi
Project Selection Models
Project Selection
 Project selection is the process of evaluating
individual projects or groups of projects,
 and then choosing to implement some set of
them so that the objectives of the parent
organization will be achieved.
 The proper choice of investment projects is
crucial to the long-run survival of every firm.
 Daily we witness the results of both good and
bad investment choices.
Decision Models
 Models abstract the relevant issues about a problem
from the plethora of detail in which the problem is
embedded.
 Reality is far too complex to deal with in its entirety.
 This process of carving away the unwanted reality
from the bones of a problem is called modeling the
problem.
 The idealized version of the problem that results is
called a model.
 Models may be quite simple to understand, or
they may be extremely complex. In general,
introducing more reality into a model tends to
make the model more difficult to manipulate.
Criteria for Project Selection Model
1. Realism
2. Capability
3. Flexibility
4. Ease of use
5. Cost
6. Easy computerization
Numeric and Non-Numeric Models
 Both widely used, Many organizations use both at the
same time, or they use models that are combinations of
the two.
 Nonnumeric models, as the name implies, do not use
numbers as inputs. Numeric models do, but the criteria
being measured may be either objective or subjective.
 It is important to remember that:
 the qualities of a project may be represented by numbers, and
 that subjective measures are not necessarily less useful or
reliable than objective measures.
Nonnumeric Models
 Nonnumeric models are older and simpler and
have only a few subtypes to consider.
The Sacred Cow
 Suggested by a senior and powerful official in the
organization. Often initiated with a simple comment
such as, “If you have a chance, why don’t you look into
. . .,” and there follows an undeveloped idea for a new
product, for the development of a new market, for the
design and adoption of a global data base and
information system, or for some other project requiring
an investment of the firm’s resources. “Sacred” in the
sense that it will be maintained until successfully
concluded, or until the boss, personally, recognizes the
idea as a failure and terminates it.
The Operating Necessity
 If a flood is threatening the plant, a project to
build a protective dike does not require much
formal evaluation, which is an example of this
scenario. If the project is required in order to
keep the system operating, the primary question
becomes: Is the system worth saving at the
estimated cost of the project?
The Competitive Necessity
 The decision to undertake the project based on a
desire to maintain the company’s competitive
position in that market.
 Investment in an operating necessity project takes
precedence over a competitive necessity project
 Both types of projects may bypass the more careful
numeric analysis used for projects deemed to be less
urgent or less important to the survival of the firm.
The Product Line Extension
 A project to develop and distribute new products
judged on the degree to which it fits the firm’s existing
product line, fills a gap, strengthens a weak link, or
extends the line in a new, desirable direction.
 Sometimes careful calculations of profitability are not
required. Decision makers can act on their beliefs about
what will be the likely impact on the total system
performance if the new product is added to the line.
Comparative Benefit Model
 Organization has many projects to consider but the
projects do not seem to be easily comparable. For
example, some projects concern potential new
products, some concern changes in production
methods, others concern computerization of certain
records, and still others cover a variety of subjects not
easily categorized (e.g., a proposal to create a daycare
center for employees with small children).
 No precise way to define or measure “benefit.”
Q-Sort Method
 Of the several techniques for ordering projects, the Q-
Sort is one of the most straightforward.
 First, the projects are divided into three groups—good,
fair, and poor—according to their relative merits. If any
group has more than eight members, it is subdivided
into two categories, such as fair-plus and fair-minus.
When all categories have eight or fewer members, the
projects within each category are ordered from best to
worst. Again, the order is determined on the basis of
relative merit. The rater may use specific criteria to rank
each project, or may simply use general overall
judgment.
The Q-Sort Method
Numeric Models: Profit/Profitability
 A large majority of all firms using project
evaluation and selection models use profitability
as the sole measure of acceptability.
Models
 Present & Future Value
 Benefit / Cost Ratio
 Payback period
 Internal Rate of Return
 Annual Value
 Variations of IRR
Present Value
The Present value or present worth method of evaluating projects
is a widely used technique. The Present Value represents an
amount of money at time zero representing the discounted cash
flows for the project.
T = 0 +/- Cash Flows
PV
Net Present Value (NPV)
The Net Present Value of an investment it is simply the difference
between cash outflows and cash inflows on a present value basis.
In this context, the discount rate equals the minimum rate of return
for the investment
Where:
NPV = ∑ Present Value (Cash Benefits) - ∑ Present Value (Cash Costs)
 Initial Investment: $100,000
 Project Life: 10 years
 Salvage Value: $ 20,000
 Annual Receipts: $ 40,000
 Annual Disbursements: $ 22,000
 Annual Discount Rate: 12%, 18%
What is the net present value for this project?
Is the project an acceptable investment?
Present Value Example
Present Value Example Solution
 Annual Receipts
 $40,000(P/A, 12%, 10) $ 226,000
 Salvage Value
 $20,000(P/F, 12%, 10) $ 6,440
 Annual Disbursements
 $22,000(P/A, 12%, 10) -$124,000
 Initial Investment (t=0) -$100,000
 Net Present Value $ 8,140
 Greater than zero, therefore acceptable project
Future Value
The future value method evaluates a project based upon
the basis of how much money will be accumulated at
some future point in time. This is just the reverse of the
present value concept.
T = 0 +/- Cash Flows
FV
 Initial Investment: $100,000
 Project Life: 10 years
 Salvage Value: $ 20,000
 Annual Receipts: $ 40,000
 Annual Disbursements: $ 22,000
 Annual Discount Rate: 12%, 18%
What is the net future value for this project?
Is the project an acceptable investment?
Future Value Example
Future Value Example Solution
 Annual Receipts
 $40,000(F/A, 12%, 10) $ 701,960
 Salvage Value
 $20,000(year 10) $ 20,000
 Annual Disbursements
 $22,000(F/A, 12%, 10) -$386,078
 Initial Investment
 $100,000(F/P, 12%, 10) -$310,600
 Net Future Value $ 25,280
 Positive value, therefore acceptable project
 Can be used to compare with future value of other projects
PV/FV
No theoretical difference if project is
evaluated in present or future value
PV of $ 25,282
$25,282(P/F, 12%, 10) $ 8,140
FV of $ 8,140
$8,140(F/P, 12%, 10) $ 25,280
Annual Value
 Sometimes it is more convenient to evaluate a
project in terms of its annual value or cost. For
example it may be easier to evaluate specific
components of an investment or individual
pieces of equipment based upon their annual
costs as the data may be more readily available
for analysis.
Annual Analysis Example
 A new piece of equipment is being evaluated for
purchase which will generate annual benefits in the
amount of $10,000 for a 10 year period, with annual
costs of $5,000. The initial cost of the machine is
$40,000 and the expected salvage is $2,000 at the end of
10 years. What is the net annual worth if interest on
invested capital is 10%?
Annual Example Solution
 Benefits:
 $10,000 per year $10,000
 Salvage
 $2,000(P/F, 10%, 10)(A/P, 10%,10) $ 125
 Costs:
 $5,000 per year -$ 5,000
 Investment:
 $40,000(A/P, 10%, 10) -$ 6,508
 Net Annual Value -$1,383
Since this is less than zero, the project is expected to earn less than the acceptable rate of 10%,
therefore the project should be rejected.
Benefit/Cost Ratio
 The benefit/cost ratio is also called the
profitability index and is defined as the ratio of
the sum of the present value of future benefits to the
sum of the present value of the future capital
expenditures and costs.
B/C Ratio Example
Project A Project B
 Present value cash inflows
$500,000 $100,000
 Present value cash outflows
$300,000 $ 50,000
 Net Present Value
$200,000 $ 50,000
 Benefit/Cost Ratio
1.67 2.0
Payback Period
One of the most common evaluation criteria used.
Simply the number of years required for the cash income
from a project to return the initial cash investment.
The investment decision criteria for this technique
suggests that if the calculated payback period is less than
some maximum value acceptable to the company, the
proposal is accepted.
Example illustrates five investment proposals having
identical capital investment requirements but differing
expected annual cash flows and lives.
Payback Period
Example
Calculation of the payback period for a given investment proposal.
a) Prepare End of Year Cumulative Net Cash Flows
b) Find the First Non-Negative Year
c) Calculate How Much of that year is required to cover the
previous period negative balance
d) Add up Previous Negative Cash Flow Years
Initial Annual Net Cash Flows
Investment 1 2 3 4 5 6 7 8 9 10
Alternative A
(45,000) 10,500 11,500 12,500 13,500 13,500 13,500 13,500 13,500 13,500 13,500
End of Year Cummulative Net Cash Flow
(45,000) (34,500) (23,000) (10,500) 3,000 16,500 30,000 43,500 57,000 70,500 84,000
Pay Back Period
Fraction of First Positive Year 0.78
Pay Back Period 3.78
a
b
c) 0.78 = 10,500/13,500
d) 3 + 0.78
Example:
Calculate the payback period for the following
investment proposal
Initial Annual Net Cash Flows
Investment 1 2 3 4 5 6 7 8 9 10
Alternative A
(120) 10 10 50 50 50 50 50 50 50 50
End of Year Cummulative Net Cash Flow
(120) (110) (100) (50) 0 50 100 150 200 250 300
Pay Back Period
Fraction of First Positive Year 1.00
Pay Back Period 4.00
Example:
Calculate the payback period for the following
investment proposal
Initial Annual Net Cash Flows
Investment 1 2 3 4 5 6 7 8 9 10
Alternative A
(120) 10 10 50 50 50 50 50 50 50 50
End of Year Cummulative Net Cash Flow
(120) (110) (100) (50) 0 50 100 150 200 250 300
Pay Back Period
Fraction of First Positive Year 1.00
Pay Back Period 4.00
Example:
Calculate the payback period for the following
investment proposal
Initial Annual Net Cash Flows
Investment 1 2 3 4 5 6 7 8 9 10
Alternative A
(120) 10 10 50 50 50 50 50 50 50 50
End of Year Cummulative Net Cash Flow
(120) (110) (100) (50) 0 50 100 150 200 250 300
Pay Back Period
Fraction of First Positive Year 1.00
Pay Back Period 4.00
Example:
Calculate the payback period for the following
investment proposal
Initial Annual Net Cash Flows
Investment 1 2 3 4 5 6 7 8 9 10
Alternative A
(250) 86 50 77 52 41 70 127 24 6 40
End of Year Cummulative Net Cash Flow
(250) (164) (115) (38) 14 55 124 252 276 282 322
Pay Back Period
Fraction of First Positive Year 0.73
Pay Back Period 3.73
Example:
Calculate the payback period for the following
investment proposal
Initial Annual Net Cash Flows
Investment 1 2 3 4 5 6 7 8 9 10
Alternative A
(250) 86 50 77 52 41 70 127 24 6 40
End of Year Cummulative Net Cash Flow
(250) (164) (115) (38) 14 55 124 252 276 282 322
Pay Back Period
Fraction of First Positive Year 0.73
Pay Back Period 3.73
Example:
Calculate the payback period for the following
investment proposal
Initial Annual Net Cash Flows
Investment 1 2 3 4 5 6 7 8 9 10
Alternative A
(250) 86 50 77 52 41 70 127 24 6 40
End of Year Cummulative Net Cash Flow
(250) (164) (115) (38) 14 55 124 252 276 282 322
Pay Back Period
Fraction of First Positive Year 0.73
Pay Back Period 3.73
IRR & Discount Rates
Internal Rate of Return
 Internal Rate of Return refers to the interest rate that the investor
will receive on the investment principal
 IRR is defined as that interest rate (r) which equates the sum of the
present value of cash inflows with the sum of the present value of
cash outflows for a project. This is the same as defining the IRR as
that rate which satisfies each of the following expressions:
∑ PV cash inflows - ∑ PV cash outflows = 0
NPV = 0 for r
∑ PV cash inflows = ∑ PV cash outflows
In general, the calculation procedure involves a trial-and-error solution. The following
examples illustrate the calculation procedures for determining the internal rate of return.
Example
Given an investment project having the following annual cash flows; find the IRR.
Solution:
Step 1. Pick an interest rate and solve for the NPV. Try r =15%
NPV = -30(1.0) -1(P/F,1,15%) + 5(P/F,2,15) + 5.5(P/F,3,15) + 4(P/F,4,15)
+ 17(P/F,5,15) + 20(P/F,6,15) + 20(P/F,7,15) - 2(P/F,8,15) + 10(P/F,9,15)
= + $5.62
Since the NPV>0, 15% is not the IRR. It now becomes necessary to select a higher interest
rate in order to reduce the NPV value.
Step 2. If r =20% is used, the NPV = - $ 1.66 and therefore this rate is too high.
Step 3. By interpolation the correct value for the IRR is determined to be r =18.7%
Year 0 1 2 3 4 5 6 7 8 9
Cash Flow (30.0) (1.0) 5.0 5.5 4.0 17.0 20.0 20.0 (2.0) 10.0
IRR using Excel
Using Excel you should insert the following function in the
targeted cell C6:
Analysis
The acceptance or rejection of a project based on the
IRR criterion is made by comparing the calculated
rate with the required rate of return, or cutoff rate
established by the firm. If the IRR exceeds the
required rate the project should be accepted; if not, it
should be rejected.
If the required rate of return is the return investors
expect the organization to earn on new projects,
then accepting a project with an IRR greater than the
required rate should result in an increase of the firms
value.
Analysis
There are several reasons for the widespread popularity of
the IRR as an evaluation criterion:
 Perhaps the primary advantage offered by the
technique is that it provides a single figure which
can be used as a measure of project value.
 Furthermore, IRR is expressed as a percentage
value. Most managers and engineers prefer to think
of economic decisions in terms of percentages as
compared with absolute values provided by
present, future, and annual value calculations.
Analysis
Another advantage offered by the IRR method is related
to the calculation procedure itself:
As its name suggests, the IRR is determined internally
for each project and is a function of the magnitude and
timing of the cash flows.
Some evaluators find this superior to selecting a rate prior
to calculation of the criterion, such as in the profitability
index and the present, future, and annual value
determinations. In other words, the IRR eliminates the
need to have an external interest rate supplied for
calculation purposes.
Selecting a Discount Rate
“There is nothing so disastrous as a rational investment policy in an irrational
world” John Maynard Keynes
We have discussed the time value of money and illustrated several
examples of its use. In all cases an interest rate or “discount rate” is
used to bring the future cash flows to the present (NPV - Net
Present Value)
The selection of the appropriate discount rate has been the source
of considerable debate and much disagreement. In most companies,
the selection of the discount rate is determined by the accounting
department or the board of directors and the engineer just uses the
number provided to him, but short of just being provided with a
rate, what is the correct or appropriate rate to use?
Example
What is the impact of the discount rate on the investment?
Cash
Flow Yr 0
Cash
Flow Yr 1
Cash
Flow Yr 2
Cash
Flow Yr 3
Cash Flow
Yr 4
Cash
Flow Yr 5
-500 -500 +750 +600 +800 +1000
ROR NPV
2% 1,941
6% 1,581
10% 1,283
15% 981
20% 739
IRR 47.82% 0
Real Option Model
 Recently, a project selection model was developed based on a
notion well known in financial markets. When one invests, one
foregoes the value of alternative future investments. Economists
refer to the value of an opportunity foregone as the “opportunity
cost” of the investment made.
 The argument is that a project may have greater net present
value if delayed to the future. If the investment can be delayed,
its cost is discounted compared to a present investment of the
same amount. Further, if the investment in a project is delayed,
its value may increase (or decrease) with the passage of time
because some of the uncertainties will be reduced.
 If the value of the project drops, it may fail the selection process.
 If the value increases, the investor gets a higher payoff.
 The real options approach acts to reduce both technological and
commercial risk.
Numeric Models: Scoring
 In an attempt to overcome some of the
disadvantages of profitability models,
particularly their focus on a single decision
criterion, a number of evaluation/selection
models hat use multiple criteria to evaluate a
project have been developed. Such models vary
widely in their complexity and information
requirements. The examples discussed illustrate
some of the different types of numeric scoring
models.
Some factors to consider
Unweighted 0–1 Factor Model
 A set of relevant factors is selected by management and then
usually listed in a preprinted form. One or more raters score the
project on each factor, depending on whether or not it qualifies
for an individual criterion.
 The raters are chosen by senior managers, for the most part
from the rolls of senior management.
 The criteria for choice are:
 (1) a clear understanding of organizational goals
 (2) a good knowledge of the firm’s potential project portfolio.
 Next slide: The columns are summed, projects with a sufficient
number of qualifying factors may be selected.
 Advantage: It uses several criteria in the decision process.
 Disadvantage: It assumes all criteria are of equal importance and
it allows for no gradation of the degree to which a specific
project meets the various criteria.
Unweighted Factor Scoring Model
 X marks in 0-1
scoring model are
replaced by numbers,
from a 5 point scale.
Weighted Factor Scoring Model
 When numeric weights reflecting the relative importance of each
individual factor are added, we have a weighted factor scoring
model. In general, it takes the form
1
n
i ij j
j
S S W

 
where
Si the total score of the ith project,
Sij the score of the ith project on the jth criterion, and
Wj the weight of the jth criterion.
Constrained Weighted Factor Scoring
Model
 Additional criteria enter the model as constraints rather than weighted
factors. These constraints represent project characteristics that must be
present or absent in order for the project to be acceptable.
 We might have specified that we would not undertake any project that
would significantly lower the quality of the final product (visible to the
buyer or not).
 We would amend the weighted scoring model to take the form:
1 1
v
n
i ij j ik
j k
S S W C
 
  
where Cik 1 if the i th project satisfies the Kth constraint, and 0 if it does not.
Example: P & G practice
 Would not consider a project to add a new consumer
product or product line:
 that cannot be marketed nationally;
 that cannot be distributed through mass outlets (grocery
stores, drugstores);
 that will not generate gross revenues in excess of $—million;
for which Procter & Gamble’s potential market share is not
at least 50 percent;
 and that does not utilize Procter & Gamble’s scientific
expertise, manufacturing expertise, advertising expertise, or
packaging and distribution expertise.
Final Thought
 Selecting the type of model to aid the
evaluation/selection process depends on the
philosophy and wishes of management.
 Weighted scoring models preferred for three
fundamental reasons.
 they allow the multiple objectives of all organizations to be
reflected in the important decision about which projects will
be supported and which will be rejected.
 scoring models are easily adapted to changes in managerial
philosophy or changes in the environment.
 they do not suffer from the bias toward the short run that is
inherent in profitability models that discount future cash
flows.
ACTIVITY
 Exercise – Project Selection
 Approximate Time: 30 minutes
Project selection models (Numeric /Scoring
Models and Non-numeric models)

More Related Content

Similar to Project_selectionProject_selectionnn.ppt

The capital budgeting process
The capital budgeting processThe capital budgeting process
The capital budgeting processAileen Mae Doroja
 
Introduction to cost management & control in construction projects
Introduction to cost management & control in construction projectsIntroduction to cost management & control in construction projects
Introduction to cost management & control in construction projectsEssam Lotffy, PMP®, CCP®
 
Capitalbudgeting
CapitalbudgetingCapitalbudgeting
Capitalbudgetingtootimothy
 
The theory and practice of corporate
The theory and practice of corporate The theory and practice of corporate
The theory and practice of corporate Babasab Patil
 
FN6033-CORP FIN-LECTURE 5A.ppt
FN6033-CORP FIN-LECTURE 5A.pptFN6033-CORP FIN-LECTURE 5A.ppt
FN6033-CORP FIN-LECTURE 5A.ppthass6
 
LECTURE 2 310723 (1)_organized (1).pptx
LECTURE 2 310723 (1)_organized (1).pptxLECTURE 2 310723 (1)_organized (1).pptx
LECTURE 2 310723 (1)_organized (1).pptxMhlonishwaKhumalo
 
Project management
Project managementProject management
Project managementAnish Jojan
 
Project appraisal part 2
Project appraisal part  2Project appraisal part  2
Project appraisal part 2danappadharwad
 
Making Investment Decisions (introduction)
Making Investment Decisions (introduction)Making Investment Decisions (introduction)
Making Investment Decisions (introduction)tutor2u
 
Project Selection Methods
Project Selection MethodsProject Selection Methods
Project Selection MethodsManikandan M
 
Publication_ Six Questions on the Path to Financially Justified Projects
Publication_ Six Questions on the Path to Financially Justified ProjectsPublication_ Six Questions on the Path to Financially Justified Projects
Publication_ Six Questions on the Path to Financially Justified ProjectsBill Kay, MSOL, PMP
 
237367257 question-case-study-3
237367257 question-case-study-3237367257 question-case-study-3
237367257 question-case-study-3homeworkping3
 
Training on Financial and Economic Project Evaluation
Training on Financial and Economic Project Evaluation Training on Financial and Economic Project Evaluation
Training on Financial and Economic Project Evaluation tobiassommer2013
 
project selection.pptx
project selection.pptxproject selection.pptx
project selection.pptxNimra zaman
 

Similar to Project_selectionProject_selectionnn.ppt (20)

Capital budgeting
Capital budgetingCapital budgeting
Capital budgeting
 
The capital budgeting process
The capital budgeting processThe capital budgeting process
The capital budgeting process
 
Introduction to cost management & control in construction projects
Introduction to cost management & control in construction projectsIntroduction to cost management & control in construction projects
Introduction to cost management & control in construction projects
 
Course03
Course03Course03
Course03
 
Pmp inititating process group
Pmp inititating process groupPmp inititating process group
Pmp inititating process group
 
Capital budgetingtraining
Capital budgetingtrainingCapital budgetingtraining
Capital budgetingtraining
 
Capitalbudgeting
CapitalbudgetingCapitalbudgeting
Capitalbudgeting
 
Capital budgeting
Capital budgetingCapital budgeting
Capital budgeting
 
The theory and practice of corporate
The theory and practice of corporate The theory and practice of corporate
The theory and practice of corporate
 
FN6033-CORP FIN-LECTURE 5A.ppt
FN6033-CORP FIN-LECTURE 5A.pptFN6033-CORP FIN-LECTURE 5A.ppt
FN6033-CORP FIN-LECTURE 5A.ppt
 
LECTURE 2 310723 (1)_organized (1).pptx
LECTURE 2 310723 (1)_organized (1).pptxLECTURE 2 310723 (1)_organized (1).pptx
LECTURE 2 310723 (1)_organized (1).pptx
 
Project management
Project managementProject management
Project management
 
Project appraisal part 2
Project appraisal part  2Project appraisal part  2
Project appraisal part 2
 
Making Investment Decisions (introduction)
Making Investment Decisions (introduction)Making Investment Decisions (introduction)
Making Investment Decisions (introduction)
 
Project Selection Methods
Project Selection MethodsProject Selection Methods
Project Selection Methods
 
Publication_ Six Questions on the Path to Financially Justified Projects
Publication_ Six Questions on the Path to Financially Justified ProjectsPublication_ Six Questions on the Path to Financially Justified Projects
Publication_ Six Questions on the Path to Financially Justified Projects
 
Ba7202 financial management (unit2) notes
Ba7202 financial management (unit2) notesBa7202 financial management (unit2) notes
Ba7202 financial management (unit2) notes
 
237367257 question-case-study-3
237367257 question-case-study-3237367257 question-case-study-3
237367257 question-case-study-3
 
Training on Financial and Economic Project Evaluation
Training on Financial and Economic Project Evaluation Training on Financial and Economic Project Evaluation
Training on Financial and Economic Project Evaluation
 
project selection.pptx
project selection.pptxproject selection.pptx
project selection.pptx
 

Recently uploaded

S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxSCMS School of Architecture
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfJiananWang21
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsvanyagupta248
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdfKamal Acharya
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesMayuraD1
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Call Girls Mumbai
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdfAldoGarca30
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaOmar Fathy
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapRishantSharmaFr
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdfKamal Acharya
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayEpec Engineered Technologies
 
Digital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxDigital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxpritamlangde
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Arindam Chakraborty, Ph.D., P.E. (CA, TX)
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxSCMS School of Architecture
 
Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Ramkumar k
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...jabtakhaidam7
 
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxmaisarahman1
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdfKamal Acharya
 

Recently uploaded (20)

S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech students
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
Digital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxDigital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptx
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
 
Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
 
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 

Project_selectionProject_selectionnn.ppt

  • 2. Project Selection  Project selection is the process of evaluating individual projects or groups of projects,  and then choosing to implement some set of them so that the objectives of the parent organization will be achieved.  The proper choice of investment projects is crucial to the long-run survival of every firm.  Daily we witness the results of both good and bad investment choices.
  • 3. Decision Models  Models abstract the relevant issues about a problem from the plethora of detail in which the problem is embedded.  Reality is far too complex to deal with in its entirety.  This process of carving away the unwanted reality from the bones of a problem is called modeling the problem.  The idealized version of the problem that results is called a model.
  • 4.  Models may be quite simple to understand, or they may be extremely complex. In general, introducing more reality into a model tends to make the model more difficult to manipulate.
  • 5. Criteria for Project Selection Model 1. Realism 2. Capability 3. Flexibility 4. Ease of use 5. Cost 6. Easy computerization
  • 6. Numeric and Non-Numeric Models  Both widely used, Many organizations use both at the same time, or they use models that are combinations of the two.  Nonnumeric models, as the name implies, do not use numbers as inputs. Numeric models do, but the criteria being measured may be either objective or subjective.  It is important to remember that:  the qualities of a project may be represented by numbers, and  that subjective measures are not necessarily less useful or reliable than objective measures.
  • 7. Nonnumeric Models  Nonnumeric models are older and simpler and have only a few subtypes to consider.
  • 8. The Sacred Cow  Suggested by a senior and powerful official in the organization. Often initiated with a simple comment such as, “If you have a chance, why don’t you look into . . .,” and there follows an undeveloped idea for a new product, for the development of a new market, for the design and adoption of a global data base and information system, or for some other project requiring an investment of the firm’s resources. “Sacred” in the sense that it will be maintained until successfully concluded, or until the boss, personally, recognizes the idea as a failure and terminates it.
  • 9. The Operating Necessity  If a flood is threatening the plant, a project to build a protective dike does not require much formal evaluation, which is an example of this scenario. If the project is required in order to keep the system operating, the primary question becomes: Is the system worth saving at the estimated cost of the project?
  • 10. The Competitive Necessity  The decision to undertake the project based on a desire to maintain the company’s competitive position in that market.  Investment in an operating necessity project takes precedence over a competitive necessity project  Both types of projects may bypass the more careful numeric analysis used for projects deemed to be less urgent or less important to the survival of the firm.
  • 11. The Product Line Extension  A project to develop and distribute new products judged on the degree to which it fits the firm’s existing product line, fills a gap, strengthens a weak link, or extends the line in a new, desirable direction.  Sometimes careful calculations of profitability are not required. Decision makers can act on their beliefs about what will be the likely impact on the total system performance if the new product is added to the line.
  • 12. Comparative Benefit Model  Organization has many projects to consider but the projects do not seem to be easily comparable. For example, some projects concern potential new products, some concern changes in production methods, others concern computerization of certain records, and still others cover a variety of subjects not easily categorized (e.g., a proposal to create a daycare center for employees with small children).  No precise way to define or measure “benefit.”
  • 13. Q-Sort Method  Of the several techniques for ordering projects, the Q- Sort is one of the most straightforward.  First, the projects are divided into three groups—good, fair, and poor—according to their relative merits. If any group has more than eight members, it is subdivided into two categories, such as fair-plus and fair-minus. When all categories have eight or fewer members, the projects within each category are ordered from best to worst. Again, the order is determined on the basis of relative merit. The rater may use specific criteria to rank each project, or may simply use general overall judgment.
  • 15. Numeric Models: Profit/Profitability  A large majority of all firms using project evaluation and selection models use profitability as the sole measure of acceptability.
  • 16. Models  Present & Future Value  Benefit / Cost Ratio  Payback period  Internal Rate of Return  Annual Value  Variations of IRR
  • 17. Present Value The Present value or present worth method of evaluating projects is a widely used technique. The Present Value represents an amount of money at time zero representing the discounted cash flows for the project. T = 0 +/- Cash Flows PV
  • 18. Net Present Value (NPV) The Net Present Value of an investment it is simply the difference between cash outflows and cash inflows on a present value basis. In this context, the discount rate equals the minimum rate of return for the investment Where: NPV = ∑ Present Value (Cash Benefits) - ∑ Present Value (Cash Costs)
  • 19.  Initial Investment: $100,000  Project Life: 10 years  Salvage Value: $ 20,000  Annual Receipts: $ 40,000  Annual Disbursements: $ 22,000  Annual Discount Rate: 12%, 18% What is the net present value for this project? Is the project an acceptable investment? Present Value Example
  • 20. Present Value Example Solution  Annual Receipts  $40,000(P/A, 12%, 10) $ 226,000  Salvage Value  $20,000(P/F, 12%, 10) $ 6,440  Annual Disbursements  $22,000(P/A, 12%, 10) -$124,000  Initial Investment (t=0) -$100,000  Net Present Value $ 8,140  Greater than zero, therefore acceptable project
  • 21. Future Value The future value method evaluates a project based upon the basis of how much money will be accumulated at some future point in time. This is just the reverse of the present value concept. T = 0 +/- Cash Flows FV
  • 22.  Initial Investment: $100,000  Project Life: 10 years  Salvage Value: $ 20,000  Annual Receipts: $ 40,000  Annual Disbursements: $ 22,000  Annual Discount Rate: 12%, 18% What is the net future value for this project? Is the project an acceptable investment? Future Value Example
  • 23. Future Value Example Solution  Annual Receipts  $40,000(F/A, 12%, 10) $ 701,960  Salvage Value  $20,000(year 10) $ 20,000  Annual Disbursements  $22,000(F/A, 12%, 10) -$386,078  Initial Investment  $100,000(F/P, 12%, 10) -$310,600  Net Future Value $ 25,280  Positive value, therefore acceptable project  Can be used to compare with future value of other projects
  • 24. PV/FV No theoretical difference if project is evaluated in present or future value PV of $ 25,282 $25,282(P/F, 12%, 10) $ 8,140 FV of $ 8,140 $8,140(F/P, 12%, 10) $ 25,280
  • 25. Annual Value  Sometimes it is more convenient to evaluate a project in terms of its annual value or cost. For example it may be easier to evaluate specific components of an investment or individual pieces of equipment based upon their annual costs as the data may be more readily available for analysis.
  • 26. Annual Analysis Example  A new piece of equipment is being evaluated for purchase which will generate annual benefits in the amount of $10,000 for a 10 year period, with annual costs of $5,000. The initial cost of the machine is $40,000 and the expected salvage is $2,000 at the end of 10 years. What is the net annual worth if interest on invested capital is 10%?
  • 27. Annual Example Solution  Benefits:  $10,000 per year $10,000  Salvage  $2,000(P/F, 10%, 10)(A/P, 10%,10) $ 125  Costs:  $5,000 per year -$ 5,000  Investment:  $40,000(A/P, 10%, 10) -$ 6,508  Net Annual Value -$1,383 Since this is less than zero, the project is expected to earn less than the acceptable rate of 10%, therefore the project should be rejected.
  • 28. Benefit/Cost Ratio  The benefit/cost ratio is also called the profitability index and is defined as the ratio of the sum of the present value of future benefits to the sum of the present value of the future capital expenditures and costs.
  • 29. B/C Ratio Example Project A Project B  Present value cash inflows $500,000 $100,000  Present value cash outflows $300,000 $ 50,000  Net Present Value $200,000 $ 50,000  Benefit/Cost Ratio 1.67 2.0
  • 30. Payback Period One of the most common evaluation criteria used. Simply the number of years required for the cash income from a project to return the initial cash investment. The investment decision criteria for this technique suggests that if the calculated payback period is less than some maximum value acceptable to the company, the proposal is accepted. Example illustrates five investment proposals having identical capital investment requirements but differing expected annual cash flows and lives.
  • 32. Example Calculation of the payback period for a given investment proposal. a) Prepare End of Year Cumulative Net Cash Flows b) Find the First Non-Negative Year c) Calculate How Much of that year is required to cover the previous period negative balance d) Add up Previous Negative Cash Flow Years Initial Annual Net Cash Flows Investment 1 2 3 4 5 6 7 8 9 10 Alternative A (45,000) 10,500 11,500 12,500 13,500 13,500 13,500 13,500 13,500 13,500 13,500 End of Year Cummulative Net Cash Flow (45,000) (34,500) (23,000) (10,500) 3,000 16,500 30,000 43,500 57,000 70,500 84,000 Pay Back Period Fraction of First Positive Year 0.78 Pay Back Period 3.78 a b c) 0.78 = 10,500/13,500 d) 3 + 0.78
  • 33. Example: Calculate the payback period for the following investment proposal Initial Annual Net Cash Flows Investment 1 2 3 4 5 6 7 8 9 10 Alternative A (120) 10 10 50 50 50 50 50 50 50 50 End of Year Cummulative Net Cash Flow (120) (110) (100) (50) 0 50 100 150 200 250 300 Pay Back Period Fraction of First Positive Year 1.00 Pay Back Period 4.00
  • 34. Example: Calculate the payback period for the following investment proposal Initial Annual Net Cash Flows Investment 1 2 3 4 5 6 7 8 9 10 Alternative A (120) 10 10 50 50 50 50 50 50 50 50 End of Year Cummulative Net Cash Flow (120) (110) (100) (50) 0 50 100 150 200 250 300 Pay Back Period Fraction of First Positive Year 1.00 Pay Back Period 4.00
  • 35. Example: Calculate the payback period for the following investment proposal Initial Annual Net Cash Flows Investment 1 2 3 4 5 6 7 8 9 10 Alternative A (120) 10 10 50 50 50 50 50 50 50 50 End of Year Cummulative Net Cash Flow (120) (110) (100) (50) 0 50 100 150 200 250 300 Pay Back Period Fraction of First Positive Year 1.00 Pay Back Period 4.00
  • 36. Example: Calculate the payback period for the following investment proposal Initial Annual Net Cash Flows Investment 1 2 3 4 5 6 7 8 9 10 Alternative A (250) 86 50 77 52 41 70 127 24 6 40 End of Year Cummulative Net Cash Flow (250) (164) (115) (38) 14 55 124 252 276 282 322 Pay Back Period Fraction of First Positive Year 0.73 Pay Back Period 3.73
  • 37. Example: Calculate the payback period for the following investment proposal Initial Annual Net Cash Flows Investment 1 2 3 4 5 6 7 8 9 10 Alternative A (250) 86 50 77 52 41 70 127 24 6 40 End of Year Cummulative Net Cash Flow (250) (164) (115) (38) 14 55 124 252 276 282 322 Pay Back Period Fraction of First Positive Year 0.73 Pay Back Period 3.73
  • 38. Example: Calculate the payback period for the following investment proposal Initial Annual Net Cash Flows Investment 1 2 3 4 5 6 7 8 9 10 Alternative A (250) 86 50 77 52 41 70 127 24 6 40 End of Year Cummulative Net Cash Flow (250) (164) (115) (38) 14 55 124 252 276 282 322 Pay Back Period Fraction of First Positive Year 0.73 Pay Back Period 3.73
  • 39. IRR & Discount Rates
  • 40. Internal Rate of Return  Internal Rate of Return refers to the interest rate that the investor will receive on the investment principal  IRR is defined as that interest rate (r) which equates the sum of the present value of cash inflows with the sum of the present value of cash outflows for a project. This is the same as defining the IRR as that rate which satisfies each of the following expressions: ∑ PV cash inflows - ∑ PV cash outflows = 0 NPV = 0 for r ∑ PV cash inflows = ∑ PV cash outflows In general, the calculation procedure involves a trial-and-error solution. The following examples illustrate the calculation procedures for determining the internal rate of return.
  • 41. Example Given an investment project having the following annual cash flows; find the IRR. Solution: Step 1. Pick an interest rate and solve for the NPV. Try r =15% NPV = -30(1.0) -1(P/F,1,15%) + 5(P/F,2,15) + 5.5(P/F,3,15) + 4(P/F,4,15) + 17(P/F,5,15) + 20(P/F,6,15) + 20(P/F,7,15) - 2(P/F,8,15) + 10(P/F,9,15) = + $5.62 Since the NPV>0, 15% is not the IRR. It now becomes necessary to select a higher interest rate in order to reduce the NPV value. Step 2. If r =20% is used, the NPV = - $ 1.66 and therefore this rate is too high. Step 3. By interpolation the correct value for the IRR is determined to be r =18.7% Year 0 1 2 3 4 5 6 7 8 9 Cash Flow (30.0) (1.0) 5.0 5.5 4.0 17.0 20.0 20.0 (2.0) 10.0
  • 42. IRR using Excel Using Excel you should insert the following function in the targeted cell C6:
  • 43. Analysis The acceptance or rejection of a project based on the IRR criterion is made by comparing the calculated rate with the required rate of return, or cutoff rate established by the firm. If the IRR exceeds the required rate the project should be accepted; if not, it should be rejected. If the required rate of return is the return investors expect the organization to earn on new projects, then accepting a project with an IRR greater than the required rate should result in an increase of the firms value.
  • 44. Analysis There are several reasons for the widespread popularity of the IRR as an evaluation criterion:  Perhaps the primary advantage offered by the technique is that it provides a single figure which can be used as a measure of project value.  Furthermore, IRR is expressed as a percentage value. Most managers and engineers prefer to think of economic decisions in terms of percentages as compared with absolute values provided by present, future, and annual value calculations.
  • 45. Analysis Another advantage offered by the IRR method is related to the calculation procedure itself: As its name suggests, the IRR is determined internally for each project and is a function of the magnitude and timing of the cash flows. Some evaluators find this superior to selecting a rate prior to calculation of the criterion, such as in the profitability index and the present, future, and annual value determinations. In other words, the IRR eliminates the need to have an external interest rate supplied for calculation purposes.
  • 46. Selecting a Discount Rate “There is nothing so disastrous as a rational investment policy in an irrational world” John Maynard Keynes We have discussed the time value of money and illustrated several examples of its use. In all cases an interest rate or “discount rate” is used to bring the future cash flows to the present (NPV - Net Present Value) The selection of the appropriate discount rate has been the source of considerable debate and much disagreement. In most companies, the selection of the discount rate is determined by the accounting department or the board of directors and the engineer just uses the number provided to him, but short of just being provided with a rate, what is the correct or appropriate rate to use?
  • 47. Example What is the impact of the discount rate on the investment? Cash Flow Yr 0 Cash Flow Yr 1 Cash Flow Yr 2 Cash Flow Yr 3 Cash Flow Yr 4 Cash Flow Yr 5 -500 -500 +750 +600 +800 +1000 ROR NPV 2% 1,941 6% 1,581 10% 1,283 15% 981 20% 739 IRR 47.82% 0
  • 48. Real Option Model  Recently, a project selection model was developed based on a notion well known in financial markets. When one invests, one foregoes the value of alternative future investments. Economists refer to the value of an opportunity foregone as the “opportunity cost” of the investment made.  The argument is that a project may have greater net present value if delayed to the future. If the investment can be delayed, its cost is discounted compared to a present investment of the same amount. Further, if the investment in a project is delayed, its value may increase (or decrease) with the passage of time because some of the uncertainties will be reduced.  If the value of the project drops, it may fail the selection process.  If the value increases, the investor gets a higher payoff.  The real options approach acts to reduce both technological and commercial risk.
  • 49. Numeric Models: Scoring  In an attempt to overcome some of the disadvantages of profitability models, particularly their focus on a single decision criterion, a number of evaluation/selection models hat use multiple criteria to evaluate a project have been developed. Such models vary widely in their complexity and information requirements. The examples discussed illustrate some of the different types of numeric scoring models.
  • 50. Some factors to consider
  • 51. Unweighted 0–1 Factor Model  A set of relevant factors is selected by management and then usually listed in a preprinted form. One or more raters score the project on each factor, depending on whether or not it qualifies for an individual criterion.  The raters are chosen by senior managers, for the most part from the rolls of senior management.  The criteria for choice are:  (1) a clear understanding of organizational goals  (2) a good knowledge of the firm’s potential project portfolio.  Next slide: The columns are summed, projects with a sufficient number of qualifying factors may be selected.  Advantage: It uses several criteria in the decision process.  Disadvantage: It assumes all criteria are of equal importance and it allows for no gradation of the degree to which a specific project meets the various criteria.
  • 52.
  • 53. Unweighted Factor Scoring Model  X marks in 0-1 scoring model are replaced by numbers, from a 5 point scale.
  • 54. Weighted Factor Scoring Model  When numeric weights reflecting the relative importance of each individual factor are added, we have a weighted factor scoring model. In general, it takes the form 1 n i ij j j S S W    where Si the total score of the ith project, Sij the score of the ith project on the jth criterion, and Wj the weight of the jth criterion.
  • 55. Constrained Weighted Factor Scoring Model  Additional criteria enter the model as constraints rather than weighted factors. These constraints represent project characteristics that must be present or absent in order for the project to be acceptable.  We might have specified that we would not undertake any project that would significantly lower the quality of the final product (visible to the buyer or not).  We would amend the weighted scoring model to take the form: 1 1 v n i ij j ik j k S S W C      where Cik 1 if the i th project satisfies the Kth constraint, and 0 if it does not.
  • 56. Example: P & G practice  Would not consider a project to add a new consumer product or product line:  that cannot be marketed nationally;  that cannot be distributed through mass outlets (grocery stores, drugstores);  that will not generate gross revenues in excess of $—million; for which Procter & Gamble’s potential market share is not at least 50 percent;  and that does not utilize Procter & Gamble’s scientific expertise, manufacturing expertise, advertising expertise, or packaging and distribution expertise.
  • 57. Final Thought  Selecting the type of model to aid the evaluation/selection process depends on the philosophy and wishes of management.  Weighted scoring models preferred for three fundamental reasons.  they allow the multiple objectives of all organizations to be reflected in the important decision about which projects will be supported and which will be rejected.  scoring models are easily adapted to changes in managerial philosophy or changes in the environment.  they do not suffer from the bias toward the short run that is inherent in profitability models that discount future cash flows.
  • 58. ACTIVITY  Exercise – Project Selection  Approximate Time: 30 minutes Project selection models (Numeric /Scoring Models and Non-numeric models)