K.S. “Buck” Collier
 NICET Level III Fire Protection
Engineering Technology/Water
Based Systems Layout.
 Have worked in industry 28 years.
 January 1986 to December 1999
employed by Commonwealth
Sprinkler Company
 February 2000 to present
employed by K & E Fire Sprinkler
 Water Supply
 Occupancy
 Building Construction
 Basic Definition- The water that is available to
the building/job site. The design of the
sprinkler system is based on this available
water
 Varies from project to project
 Can be public or private
 Public- Locality provides water flow data
◦ Some perform hydrant flow test
◦ Some provide calculated information
 Private- designs will include tank and pump
 The three elements of the water
supply are:
 Static Pressure
 Residual Pressure
 Water Flow
 Static Pressure: The pressure
available with no water flow
 Residual Pressure: The pressure
available with a water flow
 Flow: The amount of gallons per
minute of the water flow
These three make up the Water Supply Curve
Occupancy Determines Hazard Classification
Light Hazard
(Schools, Office Buildings, Restaurant Seating Areas, Hospitals)
Ordinary Hazard
Group I (Parking deck, restaurant service area, beverage
manufacturing)
Group 2 (Repair garages, mercantile, barns, chemical plants,
piers, wood shop)
Extra Hazard
Group 1 (Aircraft hangers, printing, saw mills,)
Group 2 (Flammable liquid spraying, Manufactured home
assemblies, plastic processing)
The Fire Hazards are based on fuel load
Each Fire Hazard has its own design criteria
Design Criteria are the requirements to which
the sprinkler system design is based
 Water Density
 Coverage per Sprinkler
 Spacing per Sprinkler
 Remote Area
Water Density= Gallons per minute (GPM) per
sq. ft. covered by the sprinkler
Light hazard= .10 gpm per sq. ft.
Ordinary hazard
Group 1= .15 gpm per sq. ft.
Group 2 =.20 gpm per sq. ft.
Extra Hazard
Group 1 = .30 gpm per sq. ft.
Group 2 = .40 gpm per sq. ft
Coverage per Sprinkler (max. square footage)
Light hazard= 225 sq. ft.
Ordinary hazard= 130 sq. ft.
Extra Hazard= 100 sq. ft.
Spacing for a Standard Sprinkler (max.)
Light hazard= 15’-0”
Ordinary hazard= 15’-0”
Extra Hazard= 12’-0”
Remote Area- The area that must be proven,
by hydraulic calculations, that if all sprinklers
activate, the piping and supply can provide
the required pressure and gpm
Light Hazard- minimum of 1500 sq. ft
Ordinary Hazard- minimum of 1500 sq. ft
Extra Hazard- minimum of 2500 sq. ft.
 Construction of Building Effects Design of
Sprinkler System
◦ Sloped Ceilings
 Impact reaction time of sprinklers thus requiring an
increase in remote area size by 30%.
 1500 sq ft. +30% (450 sq. ft.) = 1950 sq. ft.
◦ Unconditioned Spaces
 Dry System required for unconditioned spaces
 Dry Systems impact reaction time of sprinklers thus
requiring and increase in remote area size by 30%.
 1500 sq ft. +30% (450 sq. ft.) = 1950 sq. ft.
 Example: seasonal restaurant seating area
◦ Heated flat ceiling
 1500 sq ft remote area
◦ Unheated flat ceiling
 1500 sq ft. +30% (450 sq. ft.) = 1950 sq. ft. remote
area
◦ Unheated sloped ceiling
 1500 sq ft. +30% (450 sq. ft.) = 1950 sq. ft. +30%
(585 sq. ft.) = 2535 sq. ft. remote area
Thank you for allowing me to give this brief
presentation on Basics of Fire Sprinkler Design
Sincerely,
K.S. “Buck” Collier
February 5, 2014

More Related Content

Similar to Basics of fire sprinkler design ascet meeting 2 5

New Solutions for NPP Robustness Improvement
New Solutions for NPP Robustness ImprovementNew Solutions for NPP Robustness Improvement
New Solutions for NPP Robustness ImprovementAlexander Wolski
 
Ai Ch E Facility Siting Presentation
Ai Ch E Facility Siting PresentationAi Ch E Facility Siting Presentation
Ai Ch E Facility Siting Presentationernestvictor
 
Application of Solar Energy
Application of Solar EnergyApplication of Solar Energy
Application of Solar EnergyLisa Montero
 
Assessment of the natural air ventilation of buildings in urban area with the...
Assessment of the natural air ventilation of buildings in urban area with the...Assessment of the natural air ventilation of buildings in urban area with the...
Assessment of the natural air ventilation of buildings in urban area with the...Stephane Meteodyn
 
In the United States today, nearly all of our electricity isproduc.pdf
In the United States today, nearly all of our electricity isproduc.pdfIn the United States today, nearly all of our electricity isproduc.pdf
In the United States today, nearly all of our electricity isproduc.pdfarchgeetsenterprises
 
In the United States today, nearly all of our electricity isproduc.pdf
In the United States today, nearly all of our electricity isproduc.pdfIn the United States today, nearly all of our electricity isproduc.pdf
In the United States today, nearly all of our electricity isproduc.pdff3apparelsonline
 
FIRE SAFETY CONSIDERING NBC 2005
FIRE SAFETY CONSIDERING NBC 2005FIRE SAFETY CONSIDERING NBC 2005
FIRE SAFETY CONSIDERING NBC 2005Sajid Iqbal
 
General Water Permit - Ed Puchi
General Water Permit - Ed PuchiGeneral Water Permit - Ed Puchi
General Water Permit - Ed PuchiAGC of California
 
Engineering Final Year Project Report on "Electrical Safety and Protection of...
Engineering Final Year Project Report on "Electrical Safety and Protection of...Engineering Final Year Project Report on "Electrical Safety and Protection of...
Engineering Final Year Project Report on "Electrical Safety and Protection of...Pratap Bhunia
 
TUNNEL VENTILATION AND SAFETY - PAPAR PRESENTED AT IPWE SEMINAR 2014
TUNNEL VENTILATION AND SAFETY - PAPAR PRESENTED AT IPWE SEMINAR 2014TUNNEL VENTILATION AND SAFETY - PAPAR PRESENTED AT IPWE SEMINAR 2014
TUNNEL VENTILATION AND SAFETY - PAPAR PRESENTED AT IPWE SEMINAR 2014Hitesh Khanna
 
Estimation of design discharge for various sewer systems
Estimation of design discharge for various sewer systemsEstimation of design discharge for various sewer systems
Estimation of design discharge for various sewer systemssidrarashiddar
 
ventilación mecánica
ventilación mecánicaventilación mecánica
ventilación mecánicaUSCO
 
Serecon_Obstruction_Mapper_Examples
Serecon_Obstruction_Mapper_ExamplesSerecon_Obstruction_Mapper_Examples
Serecon_Obstruction_Mapper_ExamplesMykhailo Vorona
 
High-Rise Passive House Feasibility Study
High-Rise Passive House Feasibility StudyHigh-Rise Passive House Feasibility Study
High-Rise Passive House Feasibility StudyRDH Building Science
 
OISD-STD-117 Fire Protection Facilities for Petroleum Depots, Terminals, Pipe...
OISD-STD-117 Fire Protection Facilities for Petroleum Depots, Terminals, Pipe...OISD-STD-117 Fire Protection Facilities for Petroleum Depots, Terminals, Pipe...
OISD-STD-117 Fire Protection Facilities for Petroleum Depots, Terminals, Pipe...AnupamaPanoli
 
408255585-Project-Report.pptx.,.....................
408255585-Project-Report.pptx.,.....................408255585-Project-Report.pptx.,.....................
408255585-Project-Report.pptx.,.....................SarveshMusale
 
FIRE FIGHTING NOTES PART 01 BY ER. EZAZUL HAQUE SIDDIQUE pptx
FIRE FIGHTING NOTES PART 01 BY ER. EZAZUL HAQUE SIDDIQUE pptxFIRE FIGHTING NOTES PART 01 BY ER. EZAZUL HAQUE SIDDIQUE pptx
FIRE FIGHTING NOTES PART 01 BY ER. EZAZUL HAQUE SIDDIQUE pptxMEP ENGINEER'S SERVICES
 

Similar to Basics of fire sprinkler design ascet meeting 2 5 (20)

New Solutions for NPP Robustness Improvement
New Solutions for NPP Robustness ImprovementNew Solutions for NPP Robustness Improvement
New Solutions for NPP Robustness Improvement
 
Ai Ch E Facility Siting Presentation
Ai Ch E Facility Siting PresentationAi Ch E Facility Siting Presentation
Ai Ch E Facility Siting Presentation
 
Application of Solar Energy
Application of Solar EnergyApplication of Solar Energy
Application of Solar Energy
 
Novec 1230
Novec 1230Novec 1230
Novec 1230
 
Assessment of the natural air ventilation of buildings in urban area with the...
Assessment of the natural air ventilation of buildings in urban area with the...Assessment of the natural air ventilation of buildings in urban area with the...
Assessment of the natural air ventilation of buildings in urban area with the...
 
In the United States today, nearly all of our electricity isproduc.pdf
In the United States today, nearly all of our electricity isproduc.pdfIn the United States today, nearly all of our electricity isproduc.pdf
In the United States today, nearly all of our electricity isproduc.pdf
 
In the United States today, nearly all of our electricity isproduc.pdf
In the United States today, nearly all of our electricity isproduc.pdfIn the United States today, nearly all of our electricity isproduc.pdf
In the United States today, nearly all of our electricity isproduc.pdf
 
FIRE SAFETY CONSIDERING NBC 2005
FIRE SAFETY CONSIDERING NBC 2005FIRE SAFETY CONSIDERING NBC 2005
FIRE SAFETY CONSIDERING NBC 2005
 
General Water Permit - Ed Puchi
General Water Permit - Ed PuchiGeneral Water Permit - Ed Puchi
General Water Permit - Ed Puchi
 
Engineering Final Year Project Report on "Electrical Safety and Protection of...
Engineering Final Year Project Report on "Electrical Safety and Protection of...Engineering Final Year Project Report on "Electrical Safety and Protection of...
Engineering Final Year Project Report on "Electrical Safety and Protection of...
 
TUNNEL VENTILATION AND SAFETY - PAPAR PRESENTED AT IPWE SEMINAR 2014
TUNNEL VENTILATION AND SAFETY - PAPAR PRESENTED AT IPWE SEMINAR 2014TUNNEL VENTILATION AND SAFETY - PAPAR PRESENTED AT IPWE SEMINAR 2014
TUNNEL VENTILATION AND SAFETY - PAPAR PRESENTED AT IPWE SEMINAR 2014
 
Estimation of design discharge for various sewer systems
Estimation of design discharge for various sewer systemsEstimation of design discharge for various sewer systems
Estimation of design discharge for various sewer systems
 
ventilación mecánica
ventilación mecánicaventilación mecánica
ventilación mecánica
 
Serecon_Obstruction_Mapper_Examples
Serecon_Obstruction_Mapper_ExamplesSerecon_Obstruction_Mapper_Examples
Serecon_Obstruction_Mapper_Examples
 
57910334-5-MEP-Fire-Protection-rev.ppt
57910334-5-MEP-Fire-Protection-rev.ppt57910334-5-MEP-Fire-Protection-rev.ppt
57910334-5-MEP-Fire-Protection-rev.ppt
 
High-Rise Passive House Feasibility Study
High-Rise Passive House Feasibility StudyHigh-Rise Passive House Feasibility Study
High-Rise Passive House Feasibility Study
 
OISD-STD-117 Fire Protection Facilities for Petroleum Depots, Terminals, Pipe...
OISD-STD-117 Fire Protection Facilities for Petroleum Depots, Terminals, Pipe...OISD-STD-117 Fire Protection Facilities for Petroleum Depots, Terminals, Pipe...
OISD-STD-117 Fire Protection Facilities for Petroleum Depots, Terminals, Pipe...
 
408255585-Project-Report.pptx.,.....................
408255585-Project-Report.pptx.,.....................408255585-Project-Report.pptx.,.....................
408255585-Project-Report.pptx.,.....................
 
NZEB: Ventilation in dwellings
NZEB: Ventilation in dwellingsNZEB: Ventilation in dwellings
NZEB: Ventilation in dwellings
 
FIRE FIGHTING NOTES PART 01 BY ER. EZAZUL HAQUE SIDDIQUE pptx
FIRE FIGHTING NOTES PART 01 BY ER. EZAZUL HAQUE SIDDIQUE pptxFIRE FIGHTING NOTES PART 01 BY ER. EZAZUL HAQUE SIDDIQUE pptx
FIRE FIGHTING NOTES PART 01 BY ER. EZAZUL HAQUE SIDDIQUE pptx
 

Recently uploaded

247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 

Recently uploaded (20)

247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 

Basics of fire sprinkler design ascet meeting 2 5

  • 2.  NICET Level III Fire Protection Engineering Technology/Water Based Systems Layout.  Have worked in industry 28 years.  January 1986 to December 1999 employed by Commonwealth Sprinkler Company  February 2000 to present employed by K & E Fire Sprinkler
  • 3.  Water Supply  Occupancy  Building Construction
  • 4.  Basic Definition- The water that is available to the building/job site. The design of the sprinkler system is based on this available water  Varies from project to project  Can be public or private  Public- Locality provides water flow data ◦ Some perform hydrant flow test ◦ Some provide calculated information  Private- designs will include tank and pump
  • 5.  The three elements of the water supply are:  Static Pressure  Residual Pressure  Water Flow
  • 6.  Static Pressure: The pressure available with no water flow  Residual Pressure: The pressure available with a water flow  Flow: The amount of gallons per minute of the water flow These three make up the Water Supply Curve
  • 7.
  • 8.
  • 9. Occupancy Determines Hazard Classification Light Hazard (Schools, Office Buildings, Restaurant Seating Areas, Hospitals) Ordinary Hazard Group I (Parking deck, restaurant service area, beverage manufacturing) Group 2 (Repair garages, mercantile, barns, chemical plants, piers, wood shop) Extra Hazard Group 1 (Aircraft hangers, printing, saw mills,) Group 2 (Flammable liquid spraying, Manufactured home assemblies, plastic processing)
  • 10. The Fire Hazards are based on fuel load Each Fire Hazard has its own design criteria Design Criteria are the requirements to which the sprinkler system design is based
  • 11.  Water Density  Coverage per Sprinkler  Spacing per Sprinkler  Remote Area
  • 12. Water Density= Gallons per minute (GPM) per sq. ft. covered by the sprinkler Light hazard= .10 gpm per sq. ft. Ordinary hazard Group 1= .15 gpm per sq. ft. Group 2 =.20 gpm per sq. ft. Extra Hazard Group 1 = .30 gpm per sq. ft. Group 2 = .40 gpm per sq. ft
  • 13. Coverage per Sprinkler (max. square footage) Light hazard= 225 sq. ft. Ordinary hazard= 130 sq. ft. Extra Hazard= 100 sq. ft.
  • 14. Spacing for a Standard Sprinkler (max.) Light hazard= 15’-0” Ordinary hazard= 15’-0” Extra Hazard= 12’-0”
  • 15. Remote Area- The area that must be proven, by hydraulic calculations, that if all sprinklers activate, the piping and supply can provide the required pressure and gpm Light Hazard- minimum of 1500 sq. ft Ordinary Hazard- minimum of 1500 sq. ft Extra Hazard- minimum of 2500 sq. ft.
  • 16.
  • 17.
  • 18.  Construction of Building Effects Design of Sprinkler System ◦ Sloped Ceilings  Impact reaction time of sprinklers thus requiring an increase in remote area size by 30%.  1500 sq ft. +30% (450 sq. ft.) = 1950 sq. ft. ◦ Unconditioned Spaces  Dry System required for unconditioned spaces  Dry Systems impact reaction time of sprinklers thus requiring and increase in remote area size by 30%.  1500 sq ft. +30% (450 sq. ft.) = 1950 sq. ft.
  • 19.  Example: seasonal restaurant seating area ◦ Heated flat ceiling  1500 sq ft remote area ◦ Unheated flat ceiling  1500 sq ft. +30% (450 sq. ft.) = 1950 sq. ft. remote area ◦ Unheated sloped ceiling  1500 sq ft. +30% (450 sq. ft.) = 1950 sq. ft. +30% (585 sq. ft.) = 2535 sq. ft. remote area
  • 20.
  • 21. Thank you for allowing me to give this brief presentation on Basics of Fire Sprinkler Design Sincerely, K.S. “Buck” Collier February 5, 2014