SlideShare a Scribd company logo
Available online at www.sciencedirect.com
www.elsevier.com/locate/ijproman
International Journal of Project Management 26 (2008) 149–163
Project risk management practice: The case of a South African
utility company
Riaan van Wyk a, Paul Bowen b,*, Akintola Akintoye c
a
Electricity Supply Commission of South Africa (ESKOM),
South Africa
b
Department of Construction Economics and Management,
University of Cape Town, Private Bag, Rondebosch 7700, South
Africa
c
School of the Built and Natural Environment, Glasgow
Caledonian University, Cowcaddens Road, Glasgow, Scotland,
UK
Received 26 October 2006; received in revised form 26
February 2007; accepted 20 March 2007
Abstract
This paper documents the risk management practice of a utility
company for its Recovery Plan project to address the risks of
power
interruptions due to a shortfall of supply and increasing
electricity demand. The company’s corporate risk management
process and its
practice at divisional and project levels are discussed. The key
role of stakeholders in risk identification, analysis, mitigation,
monitoring
and reporting is emphasised by the company and this drives its
risk management practice. Despite the level of resources
available within
the company to use more sophisticated risk management tools,
the company adopts simple risk management methods
suggesting that a
large size company does not necessarily use ‘state of the art’
risk management techniques. Recommendations for improved
practice are
made.
� 2007 Elsevier Ltd and IPMA. All rights reserved.
Keywords: Risk management; Utility; Case study; Stakeholder;
Electricity; South Africa
1. Introduction
Risk management continues to be a major feature of the
project management of large construction, engineering and
technological projects in an attempt to reduce uncertainties
and to achieve project success. Miller and Lessard [1] have
argued why large engineering projects should be carefully
managed given that they are ‘‘high stakes games’’ charac-
terised by substantial irreversible commitments, skewed
reward structures in case of success, and high probabilities
of failure. In addition, they categorised the risk associated
with different types of projects ranging from oil platform
projects, nuclear-power projects, hydro-electric-power pro-
jects, urban transport projects, road and tunnel systems,
and research and development projects. They are of the
opinion that power projects possess moderate risks in so
far as engineering is concerned, but are very difficult in
0263-7863/$30.00 � 2007 Elsevier Ltd and IPMA. All rights
reserved.
doi:10.1016/j.ijproman.2007.03.011
* Corresponding author. Tel.: +27 21 650 3445; fax: +27 21 689
7564.
E-mail address: [email protected] (P. Bowen).
terms of social acceptability. Elkingston and Smallman
[2] examined project risk management practices of British
utility companies given that the utilities sector (comprising
water, power, telecommunications) is associated with less
predictable projects which are perceived to be riskier than
day-to-day business activities. They argued that risk man-
agement is an integral part of project management in this
sector; hence, most large companies put substantial
resources into the management of their business risk.
The current paper presents the risk management of a
Recovery Plan project of the Eskom Holdings Ltd. power
company in South Africa. Eskom Holdings Ltd. is wholly
owned by the South African government. The company
is a vertically-integrated operation that generates, trans-
mits, and distributes electricity to industrial, mining, com-
mercial, agricultural, re-distributors and residential users.
It is also involved in the purchase and sale of electricity
to and from South African Development Community
(SADC) countries, comprising Botswana, Mozambique,
Namibia, Zimbabwe, Lesotho, Swaziland and Zambia.
mailto:[email protected]
Shantelle Hildred
150 R. van Wyk et al. / International Journal of Project
Management 26 (2008) 149–163
The company’s business is divided into a number of divi-
sions: Generation, Transmission and Distribution;
Resource and Strategy; Finance, Key Sales and Customers
Services; Enterprises; Human Resources; and Corporate
and External Relations. The group has many main subsidi-
aries, with the core businesses including non-regulated elec-
tricity supply industry activities, the provision of electricity
supply and related services outside South Africa, the grant-
ing of home loans to employees, the management and
insurance of perceived risks to Eskom, and social invest-
ment initiatives. The company’s revenue in the 12 months
of the 2005/2006 financial year was R36,607m
(US$4947m or £2662m)1 and employed some 29,697 per-
sons (excluding contract and temporary workers). This
paper does not add to the theory of risk management.
Rather, the purpose is to document rich case study material
indicating the practice of risk management and the extent
to which practice and theory converge/diverge. One of
the authors is currently employed by Eskom in a project
management capacity, thus facilitating access to the case
material presented here.
The case study has been structured into four parts: Part
1 describes the corporate risk management process of the
holding company. Part 2 presents the risk management
process of a division of the company; the distributive divi-
sion being used for this purpose. Part 3 presents the case
study of a Recovery Plan project of the division to address
the risks of power interruptions due to a shortfall of supply
and increasing electricity demand. Part 4 documents the
conclusions emanating from the study. The lesson from
the case study is that a (very) large company with an appro-
priate level of resources may not necessarily use sophisti-
cated risk management tools; rather, simple methods that
enable the company to mitigate the risks faced by the busi-
ness are adopted.
2. Corporate risk management within Eskom Holdings Ltd.
Risk management within Eskom is an important and
integral element of the business. Given the importance of
risk management, the company has a dedicated Risk Man-
agement Committee (RMC) as one of its seven primary
committees (the other committees are the Board commit-
tee, audit committee, tender committee, human resources
committee, remuneration and ethics committee, sustain-
ability committee, and executive management committee).
The RMC comprises three non-executive directors, the
finance director and the managing director (Generation
division). The RMC is chaired by an independent, non-
executive director. The committee is tasked with ensuring
that the company’s risk management strategies and pro-
cesses are aligned with best practice. It also deals with
1 Exchange rates as at 7th September 2006: R7.40 SA Rands =
US$1;
R13.75 SA Rands = £1.
the company’s integrated risk management strategy and
processes, these embracing risk tolerance and appetite, risk
accountably, major risk exposures, and emerging risk
issues.
Eskom practices an integrated risk management strategy
and process by identifying risks and opportunities against
business objectives during risk assessments throughout
the organisation, from both a line and functional perspec-
tive. Risk integration between divisions and subsidiaries is
reviewed by the RMC to ensure a coordinated approach to
risk mitigation measures. Key risk management ‘‘buzz
words’’ feature prominently in the company’s risk manage-
ment process, as depicted in the company’s 186 page 2006
annual report (http://www.eskom.co.za/annreport06/).
The risk prefixes that are contained in the annual report
include: exposure, assessment, accountability, internal con-
trol, matrix, categories, mitigation measures, tolerance lev-
els, categories, identification, evaluation, appetite, profile,
audit, financing, issues, process, ownership, etc. A content
analysis of the annual report shows that the word ‘risk’ is
mentioned 206 times whilst the term ‘risk management’ is
mentioned 56 times; these being explicit indicators of the
importance that the company attaches to the risks to which
it is exposed. Risk categories that the company faces are
defined in the company’s risk matrix, and include: finance,
technical, environmental, legal, human resources, informa-
tion, stakeholders, regulatory and strategic.
The remit of the company’s Risk Management Commit-
tee (RMC) is to ensure that Integrated Risk Management
(IRM) is applied throughout the Eskom business. It
reviews the risk processes and all major risks within the
business and reports back to the Board. Integration
between the various Eskom divisions and subsidiaries is
ensured via the interaction of the different risk (or risk-
related) committees. Each division within the company
handles its own Risk Management System and may have
slightly different risk approaches within each of the six
regions: Western; Eastern; Northern; North-West; South-
ern; and Central. This diversity is allowed as long as it sup-
ports the strategy and milestones set by the RMC which
encourages a coordinated and common approach for the
business as a whole.
Eskom has adopted the Code of Practice published by
the Institute of Risk Management of South Africa. In
addition, it has developed its own methodology for deter-
mining the ‘value’ or weighting for specific risks faced by
the company. These weightings are used to assist the
organisation to better identify which risks should receive
priority and also show the value of risk mitigation mea-
sures. Aligned to this valuation methodology there are
risk tolerance levels for each division and main subsidiar-
ies, together with risk appetite parameters for each func-
tional risk area. Being a South African utility company
with a wider remit for the sale and purchase of electricity
from neighbouring countries, the company has identified
some risks that it considers it faces. These are depicted
in Table 1.
http://www.eskom.co.za/annreport06
Table 1
A list of key risks faced by the company
Key risks
1. Regulatory risk that encompasses the need for clear
regulatory
framework and adequate price increases to ensure long-term
sustainability
2. Future capacity, where the following needs to be addressed:
a. The availability of capacity in the long-term
b. The impact of new capital projects on the overall business
c. The ongoing ability to maintain consistent supply
d. Aging plant and increasing plant performance indicators
3. Debt management of small power users
4. Non-technical energy losses where the theft of conductors
results in
the lack of supply of power and the potential for injuries to the
public
5. The ability to respond to changes in the industry arising from
the
proposed new Electricity Supply Industry in South Africa while
meeting the shareholder’s objective for the company
6. Shareholder relationships with the focus on the ability to
manage
the different expectations of the shareholder and government
departments in terms of Eskom’s business objectives
7. Information security, management of the outsourced
information
technology service contract, lack of skills and resources, and
infor-
mation technology business continuity management
8. Availability of the skills required for the future business
needs
including skills retention, training and succession planning. The
impact of HIV/AIDS is also addressed as a component of this
key risk area
2 The King Reports on Corporate Governance (King I and King
II),
published by the King Committee on Corporate Governance,
aimed at
promoting the highest standards of corporate governance in
South Africa.
More specifically, the King I Report dealt with financial and
regulatory
aspects of corporate governance and, in addition, advocated an
integrated
approach to good governance in the interests of a wide range of
stakeholders. With the publication of the King II Report, in
terms of
which risk management received official consideration for the
first time in
South Africa, companies are now required to audit risk exposure
on an
annual basis and disclose it to their shareholders. In addition,
King II
acknowledged that a company’s activities are more than profit
to
shareholders, embracing economic, environmental and social
aspects.
R. van Wyk et al. / International Journal of Project Management
26 (2008) 149–163 151
3. Risk Management System within the Distribution Division
Given that each Division and each region within the
company handles its own Risk Management System, risk
management within the Distribution (Western Region)
Division forms part of the responsibilities of the Business
Planning and Integrated Risk (BPIR) Committee which is
led by the BPIR Manager. BPIR is therefore a subcom-
mittee of the Regional (Western) Executive Committee
(REC). BPIR duties focus on a holistic business planning
and integration function, which includes all associated
risks. The REC appoints the members and chairperson
of the BPIR committee, who, in return, report back
and advise on all Region’s business risk-related matters.
Membership of BPIR consists of REC members, subject
matter experts and other Eskom officials. They manage
the entire Risk Management Process at regional level
and include issues around process deadlocks and emer-
gency preparedness.
The BPIR committee meets once a month and has iden-
tified the following attributes of its approach to the overall
Eskom Integrated Risk Management (IRM):
� assists with business decision-making as more informa-
tion becomes available from the risk process being
executed;
� facilitates learning from and incorporating lessons from
the past;
� allows for an external view on matters which could lead
to more issues being identified;
� provides for integration between the different functional
departments leading to the optimal addressing of risk
issues;
� allows identification of any opportunities arising from
the matters at hand;
� ensures focus on objectives, keeping in line with the
regional objectives and those set by the Risk Manage-
ment Committee at Board level;
� ensures a proper audit trail for all risk-related matters:
the origin, owner, actions decided upon and taken,
and progress;
� assists with decision making, by providing input into the
continuous business planning which is also a function of
this committee;
� very importantly, it strives to protect against any impact
to the region’s financial results and image; and
� meets the requirements of the King II2 report.
4. Case study of the Western Cape Recovery Plan project
One of the projects of the Western Region Distribution
Division is Eskom’s Recovery Plan for the Western Cape.
The project was developed to address the current risk of
power interruptions due to a shortfall of supply and increas-
ing electricity demand during the winter period. To under-
stand the reasons for the shortfall in supply, it is necessary
to understand how the Western Cape is supplied with elec-
tricity and the existing constraints surrounding this.
The Western Cape requires up to 4250 MegaWatt (MW)
of power supply daily over peak periods during the winter
months. This is supplied from four power stations that pro-
vide a combined total of 4780 MW as follows:
2 · Nuclear reactors at the Koeberg Nuclear
Station (900 MW · 2)
1800 MW
Coal power stations in Mpumalanga
2400 MW
Palmiet hydro-electric pump station
400 MW
Steenbras hydro-electric pump station
180 MW
Total
4780 MW
However, there are peak periods in this region when
there is a surge in power consumption and these usually
occur between 5am and 8am, and 6pm and 8pm during
week days as shown in Fig. 1.
During routine maintenance on Unit 1 at the Koeberg
Nuclear Station in late 2005 serious damage was done to
the generator and its cooling system for this Unit. How-
Fig. 1. Demand for electricity as shown in the peak periods.
152 R. van Wyk et al. / International Journal of Project
Management 26 (2008) 149–163
ever, the nuclear reactor was not affected. The time for
repairing the generator and cooling system was set for at
least three months from January 2006. The repair pro-
gramme was focused on minimizing the period for Unit 1
to be out of service. This meant that various options had
to be considered which included obtaining replacement
parts (i.e. stator and rotor), acquiring spare parts, and
repairing the damaged parts. The dismantling of the Unit
1 generator is considered a slow process due to the cool
down period required (5 days) and separation of the rotor
and stator (10 days). After the assessment of the extent of
the damage, it was decided to start repairs to the stator and
rotor and obtain a spare rotor from a company in France.
This particular company had been the original advisors to
the Koeberg plant some 20 years ago.
During this time, Koeberg Unit 2 continued to provide
the required electricity to the Western Cape. However, a
number of power interruptions were experienced during
the month of February 2006 due to a variety of reasons,
including:
1. Unit 6 of the Kendal Power Station in Mpumalanga
tripped causing a large fluctuation on the National Net-
work. As a safety precaution, Koeberg’s Unit 2 was
removed from the grid and placed in a controlled shut
down. After the stabilisation of the network, it took
Unit 2 about a week to start up and increase generation
to full capacity. Due to the shortage of supply during
this period, load shedding (controlled black-outs) were
required and implemented. Public opinion was vocifer-
ous in its condemnation of Eskom.
2. Flash-overs between transmission lines due to high pol-
lution from veld fires and unexpected fog caused various
power lines to trip; interrupting the power flow from the
north and forcing Koeberg’s Unit 2 to remove itself
from the grid once again. This led to more load shedding
to manage the power shortage. This served only to
increase public condemnation.
Another risk was identified from the scheduled refuel-
ling of Unit 2 which was scheduled for March 2006. How-
ever, the repairs to Unit 1 had to be completed in time so
that Unit 2 could be shut down for approximately two
months to complete the refuelling and routine maintenance
procedures. In normal circumstances both units would then
have been ready to provide power for the winter months.
The rotor from France was only expected (and delivered)
during April 2006 and the repairs to the local rotor and sta-
tor were still underway at that time. It was impossible to
remove Unit 2 before Unit 1 was repaired as there was
no means to provide for the shortfall in electricity supply.
The economic impact of the February power outages was
estimated to be in excess of R500 million (about US$68m
or £36m) and was subject of discussion at provincial and
national governmental levels. To remove Unit 2 from the
grid would immediately mean a shortfall of another
900 MW and would force further load shedding to occur
with its associated economic impact.
The Western Cape Recovery Plan was an effort to do
the following: (1) explain the electricity supply problem;
(2) forecast the power demand and expected shortfall for
the winter months; (3) provide the timelines for Koeberg
R. van Wyk et al. / International Journal of Project Management
26 (2008) 149–163 153
Unit 1 to be repaired and Unit 2 to be refuelled; (4) iden-
tify all risks that could impact on the project plan; (5)
develop mitigating actions for the identified risks; (6) iden-
tify other energy saving options to minimize the impact of
the shortfall; (7) provide load shedding principles and
guidelines; and (8) provide stakeholder and communica-
tion guidelines.
This plan was a combined effort between Eskom, the
City of Cape Town (electricity department) and RED
ONE (the recently formed regional electricity distributor).
Load Shedding
Streamlead
KSACS Streamlead
DSM Streamlead Customer Services
Streamlead
Grid and National
Control Streamlead
Human Resources
Streamlead
Koeberg/Generation
Streamlead
Corporate Finance
Streamlead
Eskom Enterprises
Streamlead
Other Corporate
Functions
Key
PM
DSM
ERD
WR
Recovery Programme PMO
Recovery Programme Manager
National Recovery Sponsor
Transmission Managing Director
Western Region Risk Manager
Fig. 2. Team structure for the Weste
Eskom
Holdings
Eskom
Executive
Eskom
Recovery
Team
Dept of
Public
Enterprises
Dept of
Provincial
&Local
Government
Provincial
Government
Energy Risk
Management
Committee
ERMC
Recovery
Team
Integrated
Recovery Team
M
Fig. 3. Stakeholder structure for risk man
An Eskom Recovery Team was established which was
headed by the Managing Director of the Transmission
Division. The team structure is shown in Fig. 2. The team
reported into a bigger operating model made up of various
stakeholders headed by the Energy Risk Management
Committee (ERMC) as shown in Fig. 3. The Eskom
Recovery Team (ERT) met at least once every two weeks
where progress on the Recovery Plan was given. The feed-
back was consolidated and forwarded to the Integrated
Recovery Team and finally to ERMC. A weekly status
Corporate Communications/ERD Streamlead
WR Communications & Stakeholders Streamlead
Corporate Spokesperson
SO – Programme Management Office
– Demand Side Management
– External Relations Dept.
– Western Region
Corporate Communications & Stakeholder Manager
Regional Recovery Sponsor
Western Region General Manager
rn Cape Recovery Plan project.
unicipal
Municipal
Recovery
Team
RED1 Other
Stakeholders
Dept of
Minerals
& Energy
agement of the Recovery Plan project.
154 R. van Wyk et al. / International Journal of Project
Management 26 (2008) 149–163
report was also compiled by ERT and published internally
within Eskom and externally to the general public.
5. Risk management of the Recovery Plan project
There are typically five stages associated with risk man-
agement, namely: (1) risk management planning, (2) risk
identification, (3) qualitative and quantitative risk analysis,
(4) risk response planning, and (5) risk monitoring and con-
trol [3]. However, Edwards and Bowen [4] state that the pro-
cess of risk management should include evaluation and
reporting and they have as a result categorised the process
of risk management into nine stages: Identification; Classifi-
cation; Allocation; Analysis; Response; Recording; Moni-
toring; Control; and Evaluation. Chapman [5] identified
nine phases of the generic risk management process
(RMP), comprising: define; focus; identify; structure, owner-
ship; eliminate; evaluate; plan and manage. Practically, how-
ever, it is possible to classify all these stages into a four-stage
risk management cycle: risk identification; risk analysis; risk
response; and risk reporting. The risk identification stage
includes classification and allocation, while risk reporting
includes monitoring, control and evaluation. The risk man-
agement practice of the Recovery Plan project within the
Eskom integrated risk management protocol is presented
below along the lines of this four-stage framework.
5.1. Risk identification (and classification and allocation) of
the Recovery Plan project
The role of stakeholders in the RMP is emphasised by
Loosemore et al. [6]. According to them, effective and fre-
quent involvement of stakeholders at all stages of the RMP
will ensure that more risks are identified and commitment
obtained in managing them. Stakeholder management
becomes very critical in the risk identification process given
that they can have conflicting interests and the risks identi-
fied could be biased towards those interests or limited to their
own experiences. The possibility that the stakeholder mix
could change over time also has an impact on project objec-
tives and its associated risks. Furthermore, stakeholders
might be unable to express their objectives clearly or limit
the sharing of valid information due to confidentiality or
inter-stakeholder politics. Hence, they have suggested that
the risk manager or risk management service provider should
encourage stakeholders to balance their objectives with one
another, be flexible where possible, and understand the pres-
sures and background under which objectives are created.
It is generally accepted that companies with organic
structures allow for more creative and imaginary
approaches to identify risks, though it is still easier for
mechanistic structured companies to implement those
approaches [4]. This is because the latter could provide
backing in the form of authority sources, addressing possi-
ble resistance. Hence, companies’ management should be
committed to the risk management process, identifying
leaders with a strong personal passion for the subject.
The classification of risks creates a common framework
for grouping risks, although different cultures could classify
the same risk differently. Edwards and Bowen [4] suggest
two primary categories for classifying risks: Natural and
Human Risks. Natural risks are those from systems ‘‘beyond
human agency’’ which include risks from weather, geologi-
cal, biological and extraterrestrial systems. Risks from
human systems are more difficult to categorise due to their
overlapping nature. These include risks from social, political,
cultural, health, legal, economic, financial, technical and
managerial systems. Baber [7] refers to internally and exter-
nally generated risks. The Project Management Institute [8]
classifies risk into internal and external. Examples of internal
risk in project development are issues relating to labour,
materials, site conditions, cash flow, etc., while external risks
include governmental regulations, vandalism, sabotage,
environmental factors, market forces, inflation, etc.
It is generally accepted as a good risk management prac-
tice that a risk should be allocated to the party who can best
manage it that risk. To avoid duplication it is suggested that
continuous investigations are undertaken during the pro-
cess of risk management to ensure that another stakeholder
has not already taken up the control of a risk [6].
Eskom, in general, is very risk aware and has invested
considerable resources into this project management prac-
tice within the company. Many processes are in place to
identify and manage potential risks in its various functional
areas. Within its Distribution Division the foci of opera-
tions are customer services, engineering (safety standards
– occupational safety and health requirements); finance;
human resources; information management; and commer-
cial. All of these functional departments are represented
on the BPIR Committee where risks are raised and man-
aged. At this level risks are categorized as follows: finance;
technical operation and performance; legal audit and com-
pliance; people; strategic acquisitions, divestitures and pro-
jects; strategy; transformation; pricing; regulatory (NER);
stakeholders; information; subsidiaries, associates and joint
ventures.
In this particular case, the main reason for the inade-
quate supply capacity to meet the needs of the Western
Cape within the normally envisaged risk possibility of a
loss of generation at Koeberg was aggravated by decisions
by central government that limited the capacity of Eskom
to build new power stations or transmission lines. Arising
from the White Paper on Energy Policy [9], government
decided it was necessary to proceed with ‘the unbundling
of Eskom’s generation and transmission groups’ and ‘sep-
arate the power stations into a number of companies’ to
‘create the opportunity for private sector and Black Eco-
nomic Empowerment investment opportunities in the gen-
eration sector’. Later, the Intergovernmental Fiscal Review
[10] stated ‘The ESI restructuring involves three key
aspects: the sale of 30 per cent of Eskom’s generating
capacity to private investors, with a black empowerment
equity stake of at least 10 per cent of capacity; the separa-
tion of Eskom into several generation clusters and a sepa-
3 Eskom initiated a schemed whereby the public were
encouraged to
exchange their conventional light bulbs for less electricity-
consuming
CFLs – at no cost to the consumer.
R. van Wyk et al. / International Journal of Project Management
26 (2008) 149–163 155
rate transmission company; and the introduction of an
electricity market, which will ensure competition between
the different electricity generators. These reforms will begin
during the course of 2003.’ The central government had
taken responsibility to manage the investment decisions
of the supply industry, and it was only in late 2004, with
looming insufficient capacity, that the decision was made
to return the responsibility for electricity sufficiency to
Eskom [11]. Thus, Eskom was constrained by external
forces in its ability to respond to identified risk. Most sub-
sequent risk was a consequence of this external risk.
The identified risks are usually assigned to the BPIR
Committee members for mitigation. Although the commit-
tee members remain accountable, they could subsequently
delegate the risk mitigation actions and management to rel-
evant staff within the establishment.
The Eskom Recovery Team panel of experts responsible
for addressing the Western Cape Recovery Plan project
comprised senior managers drawn from the following
departments and/or divisions: National Recovery Sponsor
(this is …
Assignment 4: HR Training Class
Due Week 8 and worth 200 points
Imagine that you are a member of the HR department of a small
retail company and upper management has asked you to create a
new employee customer service training class for all new
employees.
Write a six to seven (6-7) pages paper in which you:
1. Justify the use of a needs assessment of your company’s
proposed employee customer service training, stressing five (5)
ways in which such an assessment would expose any existing
performance deficiencies.
2. Develop a customer service training implementation plan and
determine the method of training (i.e., presentation, discussion,
case study, discovery, role play, simulation, modeling, or on-
the-job training).
3. Justify why you selected the training method that you did.
4. Propose two (2) ways to motivate an employee who has no
interest in attending a training class.
5. Develop a survey to collect feedback from the employees
who attend the training.
6. Use at least three (3) quality academic resources in this
assignment. Note: Wikipedia and other Websites do not qualify
as academic resources.
Your assignment must follow these formatting requirements:
· Be typed, double spaced, using Times New Roman font (size
12), with one-inch margins on all sides; citations and references
must follow APA or school-specific format. Check with your
professor for any additional instructions.
· Include a cover page containing the title of the assignment, the
student’s name, the professor’s name, the course title, and the
date. The cover page and the reference page are not included in
the required assignment page length.
The specific course learning outcomes associated with this
assignment are:
· Design job and task analyses that align with the overall HRM
strategy.
· Design training and development systems to improve
employee performance.
· Use technology and information resources to research issues in
strategic human resource development.
· Write clearly and concisely about strategic human resource
development using proper writing mechanics.
Rubric
Points: 200
Assignment 4:HR Training Class
Criteria
Unacceptable
Below 70% F
Fair
70-79% C
Proficient
80-89% B
Exemplary
90-100% A
1. Justify the use of a needs assessment of your company’s
proposed employee customer service training, stressing five (5)
ways in which such an assessment would expose any existing
performance deficiencies.
Weight: 20%
Did not submit or incompletely justified the use of a needs
assessment of your company’s proposed employee customer
service training, stressing five (5) ways in which such an
assessment would expose any existing performance deficiencies.
Partially justified the use of a needs assessment of your
company’s proposed employee customer service training,
stressing five (5) ways in which such an assessment would
expose any existing performance deficiencies.
Satisfactorily justified the use of a needs assessment of your
company’s proposed employee customer service training,
stressing five (5) ways in which such an assessment would
expose any existing performance deficiencies.
Thoroughly justified the use of a needs assessment of your
company’s proposed employee customer service training,
stressing five (5) ways in which such an assessment would
expose any existing performance deficiencies.
2. Develop a customer service training implementation plan and
determine the method of training (i.e., presentation, discussion,
case study, discovery, role play, simulation, modeling, or on-
the-job training).
Weight: 20%
Did not submit or incompletely developed a customer service
training implementation plan and did not submit or incompletely
determined the method of training (i.e., presentation,
discussion, case study, discovery, role play, simulation,
modeling, or on-the-job training).
Partially developed a customer service training implementation
plan and partially determined the method of training (i.e.,
presentation, discussion, case study, discovery, role play,
simulation, modeling, or on-the-job training).
Satisfactorily developed a customer service training
implementation plan and satisfactorily determined the method
of training (i.e., presentation, discussion, case study, discovery,
role play, simulation, modeling, or on-the-job training).
Thoroughly developed a customer service training
implementation plan and thoroughly determined the method of
training (i.e., presentation, discussion, case study, discovery,
role play, simulation, modeling, or on-the-job training).
3. Justify why you selected the training method that you did.
Weight: 10%
Did not submit or incompletely justified why you selected the
training method that you did.
Partially justified why you selected the training method that you
did.
Satisfactorily justified why you selected the training method
that you did.
Thoroughly justified why you selected the training method that
you did.
4. Propose two (2) ways to motivate an employee who has no
interest in attending a training class.
Weight: 15%
Did not submit or incompletely proposed two (2) ways to
motivate an employee who has no interest in attending a
training class.
Partially proposed two (2) ways to motivate an employee who
has no interest in attending a training class.
Satisfactorily proposed two (2) ways to motivate an employee
who has no interest in attending a training class.
Thoroughly proposed two (2) ways to motivate an employee
who has no interest in attending a training class.
5. Develop a survey to collect feedback from the employees
who attend the training.
Weight: 20%
Did not submit or incompletely developed a survey to collect
feedback from the employees who attend the training.
Partially developed a survey to collect feedback from the
employees who attend the training.
Satisfactorily developed a survey to collect feedback from the
employees who attend the training.
Thoroughly developed a survey to collect feedback from the
employees who attend the training.
6. 3 references
Weight: 5%
No references provided
Does not meet the required number of references; some or all
references poor quality choices.
Meets number of required references; all references high quality
choices.
Exceeds number of required references; all references high
quality choices.
7. Clarity, writing mechanics, and formatting requirements
Weight: 10%
More than 6 errors present
5-6 errors present
3-4 errors present
0-2 errors present
Running head: HR TRAINING CLASS 1
HR TRAINING CLASS 2
HR Training Class
xxxxx xxxxx
Dr. XXXXXX
HRM 530
August 24, 2014
Introduction
The paper will justify the use of a needs assessment of a
company’s proposed employee customer service training, and
the practices of HRM such as performance management. HRM
empowering employees can also extend to innovation and less
stress. This paper will elaborate on stressing the five (5) ways
in which such an assessment would expose any existing
performance deficiencies. From my perspective, successful
organizations treat all their workers as knowledge workers and
provide proper training informing them about company
expectations during the new hired employee’s orientation. Let
employees know how well the company is performing, and they
invite ideas about how the organization can do better working
as a team. Thus, upper management creates new employee
customer orientation for all new employees and training
development for the purpose of customer service training and an
implementation plan to determine the method of training (i.e.,
presentation, discussion, case study, discovery, role play,
simulation, modeling, or on-the-job training). Lastly, this paper
elaborates on the selection of the training method, the way to
encourage or motivate an employee that have no interest in
training, and setting up a meeting to collect feedback from an
employee who has attended training.
Needs Assessment
Every company needs an assessment to help address any gaps or
needs between present conditions and preferred ones. By
creating an assessment, it identifies where employees and
companies need to improve by listening to what the employees
have to say and give their opinion. It’s also very important in a
training session to listen to what employees say or ideas,
because it helps improve their performances as well as
relationships with management. By having a needs assessment
with employee customer service training, employee’s
performance deficiencies will be exposed. There are many ways
in which an assessment would expose any existing performance
deficiencies, such as observation, interviews, questionnaires,
studying job descriptions and difficulty analysis (Stewart G.L.
& Brown, K.G., 2012). First, with observation, this gives the
trainer first hand data on employee’s strengths and weaknesses
without affecting their productivity. Secondly, with
interviewing, the trainer will be able to gauge the employee’s
options and perceptions but allowing them to address their own
performances while asking in depth questions about
performances. Third, with the questionnaires, this option will
help give a bigger picture of the environment as respondents
will be asked identical questions; data collected will help
identify challenges in performances after being analyzed in a
quantitative way. Fourth, studying job descriptions, this will
help enacting a thorough training and supervision on the
trainers as the employees will be aware of their responsibilities
and what is expected of them. Lastly, the difficulty analysis
will help managers identify what job duties are causing the
employees problems and determine what training is needed in
the particular area in order to better boost performance.
Customer Service Training Implementation Plan
To train customer service employees, there has to be a well laid
out plan. The plan will need to cover such aspects as the goal of
the training, the trainers, the duration of training, the method of
training, the budget for the training process and the technology
that subsequently needed for a successful training session. Per
the HR training class title, the customer service employees will
be trained on how to improve their job duties. The training
implementation will consist of goal training, trainers, methods
used to train and the time of duration of the training. First, the
goal of training is to educate all training customer service
representatives on ways to better serve the customer, secondly,
the training will be conducted by seasonal experience trainers
who will be either from the company or hired from outside.
Once the training is completed, a thorough report will be
conveyed to the management team, either by voice or report on
how well the session was accepted. Third, the method of
training will consist of on job training and case studies. This is
the most effective way because it has been proved that
employees listen to what is practically justifiable. For example,
customers are reminded that failure is a part of success;
however, for employees to believe this, trainers will need to
incorporate case studies and examples on famous individuals
who have failed and then bounced back with a successful story.
Lastly, the trainers will need to determine how long the duration
of the training will be, therefore, during the implementation
training process, an estimated time and budget will need to be
proposed. The company’s management team, Human Resource
Department and trainers will need to propose a cost effective
training budget and once agreed, the finance department will
approve and incorporate into the budget.
Selected Training Method
I selected on the job training and case studies as my two
training methods and the primary training method would be on
the job training. I selected this as my primary training method
because it has advantages over the other methods. This method
gives an employee a chance to ask workplace specific questions
and get pioneering guidance (Rothwell and Kazanas, 2004). It
also raises employee’s skills as new standards and practices
emerge as changes occur as job duties change. However, I
included the case study training method because it internalizes
the concepts passed on during job training. According to Wilson
(2005), company psychologists have proved that employees tend
to listen and believe to what is practically justifiable. When
training, employees need to hear what others have done in order
for them to accept the concepts of training, for example, as
mentioned earlier, employees may be reminded that failure is a
big part of success. Therefore, the training method of case
studies will give the employees an idea of, in order to be
successful; you will have setbacks in the process.
Employee Motivation
There are numerous ways to motivate employees to attend a
training class but my two motivational ways I chose are;
offering incentives and cross training opportunities after the
training is completed. For me, I find that attending training
class is boring because, the sessions are based on information
that’s already been relayed to us, therefore, I choose not to go
but I will explain why the two motivators I chose is beneficial
to the employee and employer. First, offering incentives such
as monetary increases, extra vacation days or additional hours
of personal time would attract more employees to attend the
training class and motivate them to perform to the best of their
ability, therefore, when incentives for employees are facilitated,
an instant level of enthusiastic peaks from employees to
attending training class. Secondly, allowing employees to cross
training on duties within the company that they are unfamiliar
with, would spark them to attend the training class as well.
Allowing employees the opportunity to advance their knowledge
within the company will motivate them to attend the training,
which consecutively makes them more valuable to the company.
Therefore, managers should encourage cross training after a
class because it breaks the monotony and employees are able to
switch up at any given time and do another job when needed.
Also, with cross training, employees will have the opportunity
to trade jobs periodically which makes a good business strategy
because it a proactive way to keep the company running
smoothing. The motivators I chose are just two out of the many
ways that helps generate fulfilling work attitudes from
employees.
Survey Development
The survey below will be used to collect feedback from
employees attending the training. This survey will seek the
interest how to collect feedback from employees on whether the
training was beneficial, how the training once learned will be
put into practice, whether more training is needed in customer
service and the challenges they expect face while serving the
customers on a day to day basis (Montana and Charnov, 2002).
Also, this survey will focus on the aspects s age, job position
and employee opinions regarding the training class. Lastly, the
survey will consist of two sections; the first section pertains to
collecting information regarding the data of participants and the
second section pertains to collecting information about the
participant’s feedback towards training.
Survey
Section One
1. Indicate your sex
⃝ Male
⃝ Female
2. Indicate your position in the company
⃝ Employee
⃝ Senior Employee
⃝ Manager
⃝ Senior Manager
3. Marital Status
⃝ Single
⃝ Married
Section Two
Please indicate your view by checking the column of the items
listed below:
Strongly Agree
Agree
Neutral
Disagree
Strongly Disagree
1. The training fulfilled by expectations.
2. Will you be able to utilize the training?
3. Topics were identified and adhered to.
4. Content thought out and easily followed.
5. Materials relevant and handy.
6. The trainer was well informed.
7. The value of instructions was good.
8. Trainer achieved the training objectives.
9. Discussion and interaction encouraged.
10. Ample time for questions/discussion.
Section Three
Good Average Poor Very Poor
11. What is your overall rating? ⃝
⃝ ⃝ ⃝
12. Suggestion on what needs to be improved.
13. Additional Comments.
References
Montana, P. J. & Charnov, B. H. (2002). Training and
Development Management. Barron’s
Educational Series, pg. 225. ISBN 0-7641-1276-7
Rothwell, W.J. & Kazanas, H.C. (2004). The Strategic
Development of Talent. Human Resource
Development Press, pg. 4. ISBN 0-87425-752-2.
Stewart G.L. & Brown, K.G. (2012). Human Resource
Management. Linking Strategy to
Practice. (2nd ed.).
Wilson, J. P. (2005). Human Resource Management: Learning
and Training for Individuals and
Organizations.
Available online at www.sciencedirect.comwww.elsevier.comlo.docx

More Related Content

Similar to Available online at www.sciencedirect.comwww.elsevier.comlo.docx

ERM LCPL overview
ERM LCPL overviewERM LCPL overview
ERM LCPL overview
karld
 
THE INTEGRATED REPORTING - Case study Arcelormittal
THE INTEGRATED REPORTING   - Case study ArcelormittalTHE INTEGRATED REPORTING   - Case study Arcelormittal
THE INTEGRATED REPORTING - Case study Arcelormittal
SIMIONSORINGABRIEL
 
Sydney Water Critical Water Mains Strategy and Implementation LESAM2013
Sydney Water Critical Water Mains Strategy and Implementation LESAM2013Sydney Water Critical Water Mains Strategy and Implementation LESAM2013
Sydney Water Critical Water Mains Strategy and Implementation LESAM2013
david zhang
 
Effect or Risk Management Methods on project performance in Rwandan Construct...
Effect or Risk Management Methods on project performance in Rwandan Construct...Effect or Risk Management Methods on project performance in Rwandan Construct...
Effect or Risk Management Methods on project performance in Rwandan Construct...
Sibo Kanyambari Aimable
 
Enterprise risk management
Enterprise risk managementEnterprise risk management
Enterprise risk management
Anu Damodaran
 
Unit 7 Assignment Group Assignment – Risk Analysis and Ident
Unit 7 Assignment Group Assignment – Risk Analysis and IdentUnit 7 Assignment Group Assignment – Risk Analysis and Ident
Unit 7 Assignment Group Assignment – Risk Analysis and Ident
corbing9ttj
 
CHAPTER 35 ERM at Malaysias Media Company Astro Quickly Imple.docx
CHAPTER 35 ERM at Malaysias Media Company Astro Quickly Imple.docxCHAPTER 35 ERM at Malaysias Media Company Astro Quickly Imple.docx
CHAPTER 35 ERM at Malaysias Media Company Astro Quickly Imple.docx
walterl4
 
Hazard Identification, Risk Assessment And Risk Control In a 250 MW Solar Pow...
Hazard Identification, Risk Assessment And Risk Control In a 250 MW Solar Pow...Hazard Identification, Risk Assessment And Risk Control In a 250 MW Solar Pow...
Hazard Identification, Risk Assessment And Risk Control In a 250 MW Solar Pow...
IRJET Journal
 
Enterprise Risk Management
Enterprise Risk ManagementEnterprise Risk Management
Enterprise Risk Management
Anu Damodaran
 
System shock analysis and complex network effects
System shock analysis and complex network effectsSystem shock analysis and complex network effects
System shock analysis and complex network effects
Kimmo Soramaki
 
PAM Case Study 1 - Predictive Maintenance V1
PAM Case Study 1 - Predictive Maintenance V1PAM Case Study 1 - Predictive Maintenance V1
PAM Case Study 1 - Predictive Maintenance V1
Ralph Overbeck
 
Risk management practices among commercial banks in ghana
Risk management practices among commercial banks in ghanaRisk management practices among commercial banks in ghana
Risk management practices among commercial banks in ghana
Alexander Decker
 
PAM Case Study 3 - Flooding Risk V1
 PAM Case Study 3 - Flooding Risk V1 PAM Case Study 3 - Flooding Risk V1
PAM Case Study 3 - Flooding Risk V1
Ralph Overbeck
 
MBA Research Project
MBA Research ProjectMBA Research Project
MBA Research Project
Vineet Chauhan
 
future internetArticleERMOCTAVE A Risk Management Fra
future internetArticleERMOCTAVE A Risk Management Frafuture internetArticleERMOCTAVE A Risk Management Fra
future internetArticleERMOCTAVE A Risk Management Fra
DustiBuckner14
 
Future internet articleermoctave a risk management fra
Future internet articleermoctave a risk management fraFuture internet articleermoctave a risk management fra
Future internet articleermoctave a risk management fra
arnit1
 
future internetArticleERMOCTAVE A Risk Management Fra.docx
future internetArticleERMOCTAVE A Risk Management Fra.docxfuture internetArticleERMOCTAVE A Risk Management Fra.docx
future internetArticleERMOCTAVE A Risk Management Fra.docx
gilbertkpeters11344
 
Ace emerging-risks-barometer-2013
Ace emerging-risks-barometer-2013Ace emerging-risks-barometer-2013
Ace emerging-risks-barometer-2013
Factor-X
 
52 a risk-management_approach_to_a_successful_infrastructure_project
52 a risk-management_approach_to_a_successful_infrastructure_project52 a risk-management_approach_to_a_successful_infrastructure_project
52 a risk-management_approach_to_a_successful_infrastructure_project
Eng. Mohamed Muhumed
 
Guide to empower banks to assess natural capital risk
Guide to empower banks to assess natural capital riskGuide to empower banks to assess natural capital risk
Guide to empower banks to assess natural capital risk
WE-SECO
 

Similar to Available online at www.sciencedirect.comwww.elsevier.comlo.docx (20)

ERM LCPL overview
ERM LCPL overviewERM LCPL overview
ERM LCPL overview
 
THE INTEGRATED REPORTING - Case study Arcelormittal
THE INTEGRATED REPORTING   - Case study ArcelormittalTHE INTEGRATED REPORTING   - Case study Arcelormittal
THE INTEGRATED REPORTING - Case study Arcelormittal
 
Sydney Water Critical Water Mains Strategy and Implementation LESAM2013
Sydney Water Critical Water Mains Strategy and Implementation LESAM2013Sydney Water Critical Water Mains Strategy and Implementation LESAM2013
Sydney Water Critical Water Mains Strategy and Implementation LESAM2013
 
Effect or Risk Management Methods on project performance in Rwandan Construct...
Effect or Risk Management Methods on project performance in Rwandan Construct...Effect or Risk Management Methods on project performance in Rwandan Construct...
Effect or Risk Management Methods on project performance in Rwandan Construct...
 
Enterprise risk management
Enterprise risk managementEnterprise risk management
Enterprise risk management
 
Unit 7 Assignment Group Assignment – Risk Analysis and Ident
Unit 7 Assignment Group Assignment – Risk Analysis and IdentUnit 7 Assignment Group Assignment – Risk Analysis and Ident
Unit 7 Assignment Group Assignment – Risk Analysis and Ident
 
CHAPTER 35 ERM at Malaysias Media Company Astro Quickly Imple.docx
CHAPTER 35 ERM at Malaysias Media Company Astro Quickly Imple.docxCHAPTER 35 ERM at Malaysias Media Company Astro Quickly Imple.docx
CHAPTER 35 ERM at Malaysias Media Company Astro Quickly Imple.docx
 
Hazard Identification, Risk Assessment And Risk Control In a 250 MW Solar Pow...
Hazard Identification, Risk Assessment And Risk Control In a 250 MW Solar Pow...Hazard Identification, Risk Assessment And Risk Control In a 250 MW Solar Pow...
Hazard Identification, Risk Assessment And Risk Control In a 250 MW Solar Pow...
 
Enterprise Risk Management
Enterprise Risk ManagementEnterprise Risk Management
Enterprise Risk Management
 
System shock analysis and complex network effects
System shock analysis and complex network effectsSystem shock analysis and complex network effects
System shock analysis and complex network effects
 
PAM Case Study 1 - Predictive Maintenance V1
PAM Case Study 1 - Predictive Maintenance V1PAM Case Study 1 - Predictive Maintenance V1
PAM Case Study 1 - Predictive Maintenance V1
 
Risk management practices among commercial banks in ghana
Risk management practices among commercial banks in ghanaRisk management practices among commercial banks in ghana
Risk management practices among commercial banks in ghana
 
PAM Case Study 3 - Flooding Risk V1
 PAM Case Study 3 - Flooding Risk V1 PAM Case Study 3 - Flooding Risk V1
PAM Case Study 3 - Flooding Risk V1
 
MBA Research Project
MBA Research ProjectMBA Research Project
MBA Research Project
 
future internetArticleERMOCTAVE A Risk Management Fra
future internetArticleERMOCTAVE A Risk Management Frafuture internetArticleERMOCTAVE A Risk Management Fra
future internetArticleERMOCTAVE A Risk Management Fra
 
Future internet articleermoctave a risk management fra
Future internet articleermoctave a risk management fraFuture internet articleermoctave a risk management fra
Future internet articleermoctave a risk management fra
 
future internetArticleERMOCTAVE A Risk Management Fra.docx
future internetArticleERMOCTAVE A Risk Management Fra.docxfuture internetArticleERMOCTAVE A Risk Management Fra.docx
future internetArticleERMOCTAVE A Risk Management Fra.docx
 
Ace emerging-risks-barometer-2013
Ace emerging-risks-barometer-2013Ace emerging-risks-barometer-2013
Ace emerging-risks-barometer-2013
 
52 a risk-management_approach_to_a_successful_infrastructure_project
52 a risk-management_approach_to_a_successful_infrastructure_project52 a risk-management_approach_to_a_successful_infrastructure_project
52 a risk-management_approach_to_a_successful_infrastructure_project
 
Guide to empower banks to assess natural capital risk
Guide to empower banks to assess natural capital riskGuide to empower banks to assess natural capital risk
Guide to empower banks to assess natural capital risk
 

More from celenarouzie

Attaining ExpertiseYou are tr.docx
Attaining ExpertiseYou are tr.docxAttaining ExpertiseYou are tr.docx
Attaining ExpertiseYou are tr.docx
celenarouzie
 
attachment Chloe” is a example of the whole packet. Please follow t.docx
attachment Chloe” is a example of the whole packet. Please follow t.docxattachment Chloe” is a example of the whole packet. Please follow t.docx
attachment Chloe” is a example of the whole packet. Please follow t.docx
celenarouzie
 
AttachmentFor this discussionUse Ericksons theoretic.docx
AttachmentFor this discussionUse Ericksons theoretic.docxAttachmentFor this discussionUse Ericksons theoretic.docx
AttachmentFor this discussionUse Ericksons theoretic.docx
celenarouzie
 
Attachment Programs and Families Working Together Learn.docx
Attachment Programs and Families Working Together Learn.docxAttachment Programs and Families Working Together Learn.docx
Attachment Programs and Families Working Together Learn.docx
celenarouzie
 
Attachment and Emotional Development in InfancyThe purpose o.docx
Attachment and Emotional Development in InfancyThe purpose o.docxAttachment and Emotional Development in InfancyThe purpose o.docx
Attachment and Emotional Development in InfancyThe purpose o.docx
celenarouzie
 
ATTACHEMENT from 7.1 and 7.2 Go back to the Powerpoint for thi.docx
ATTACHEMENT from 7.1 and 7.2 Go back to the Powerpoint for thi.docxATTACHEMENT from 7.1 and 7.2 Go back to the Powerpoint for thi.docx
ATTACHEMENT from 7.1 and 7.2 Go back to the Powerpoint for thi.docx
celenarouzie
 
Attached the dataset Kaggle has hosted a data science competitio.docx
Attached the dataset Kaggle has hosted a data science competitio.docxAttached the dataset Kaggle has hosted a data science competitio.docx
Attached the dataset Kaggle has hosted a data science competitio.docx
celenarouzie
 
Attached you will find all of the questions.These are just like th.docx
Attached you will find all of the questions.These are just like th.docxAttached you will find all of the questions.These are just like th.docx
Attached you will find all of the questions.These are just like th.docx
celenarouzie
 
Attached the dataset Kaggle has hosted a data science compet.docx
Attached the dataset Kaggle has hosted a data science compet.docxAttached the dataset Kaggle has hosted a data science compet.docx
Attached the dataset Kaggle has hosted a data science compet.docx
celenarouzie
 
B. Answer Learning Exercises  Matching words parts 1, 2, 3,.docx
B. Answer Learning Exercises  Matching words parts 1, 2, 3,.docxB. Answer Learning Exercises  Matching words parts 1, 2, 3,.docx
B. Answer Learning Exercises  Matching words parts 1, 2, 3,.docx
celenarouzie
 
B)What is Joe waiting for in order to forgive Missy May in The Gild.docx
B)What is Joe waiting for in order to forgive Missy May in The Gild.docxB)What is Joe waiting for in order to forgive Missy May in The Gild.docx
B)What is Joe waiting for in order to forgive Missy May in The Gild.docx
celenarouzie
 
B)Blanche and Stella both view Stanley very differently – how do the.docx
B)Blanche and Stella both view Stanley very differently – how do the.docxB)Blanche and Stella both view Stanley very differently – how do the.docx
B)Blanche and Stella both view Stanley very differently – how do the.docx
celenarouzie
 
b) What is the largest value that can be represented by 3 digits usi.docx
b) What is the largest value that can be represented by 3 digits usi.docxb) What is the largest value that can be represented by 3 digits usi.docx
b) What is the largest value that can be represented by 3 digits usi.docx
celenarouzie
 
b$ E=EE#s{gEgE lEgEHEFs ig=ii 5i= l; i € 3 r i.Er1 b €€.docx
b$ E=EE#s{gEgE lEgEHEFs ig=ii 5i= l; i € 3 r  i.Er1 b €€.docxb$ E=EE#s{gEgE lEgEHEFs ig=ii 5i= l; i € 3 r  i.Er1 b €€.docx
b$ E=EE#s{gEgE lEgEHEFs ig=ii 5i= l; i € 3 r i.Er1 b €€.docx
celenarouzie
 
B A S I C L O G I C M O D E L D E V E L O P M E N T Pr.docx
B A S I C  L O G I C  M O D E L  D E V E L O P M E N T  Pr.docxB A S I C  L O G I C  M O D E L  D E V E L O P M E N T  Pr.docx
B A S I C L O G I C M O D E L D E V E L O P M E N T Pr.docx
celenarouzie
 
B H1. The first issue that jumped out to me is that the presiden.docx
B H1. The first issue that jumped out to me is that the presiden.docxB H1. The first issue that jumped out to me is that the presiden.docx
B H1. The first issue that jumped out to me is that the presiden.docx
celenarouzie
 
b l u e p r i n t i CONSUMER PERCEPTIONSHQW DQPerception.docx
b l u e p r i n t i CONSUMER PERCEPTIONSHQW DQPerception.docxb l u e p r i n t i CONSUMER PERCEPTIONSHQW DQPerception.docx
b l u e p r i n t i CONSUMER PERCEPTIONSHQW DQPerception.docx
celenarouzie
 
B R O O K I N G SM E T R O P O L I TA N P O L I CY .docx
B R O O K I N G SM E T R O P O L I TA N P O L I CY .docxB R O O K I N G SM E T R O P O L I TA N P O L I CY .docx
B R O O K I N G SM E T R O P O L I TA N P O L I CY .docx
celenarouzie
 
B L O C K C H A I N & S U P P LY C H A I N SS U N I L.docx
B L O C K C H A I N  &  S U P P LY  C H A I N SS U N I L.docxB L O C K C H A I N  &  S U P P LY  C H A I N SS U N I L.docx
B L O C K C H A I N & S U P P LY C H A I N SS U N I L.docx
celenarouzie
 
Año 15, núm. 43 enero – abril de 2012. Análisis 97 Orien.docx
Año 15, núm. 43  enero – abril de 2012. Análisis 97 Orien.docxAño 15, núm. 43  enero – abril de 2012. Análisis 97 Orien.docx
Año 15, núm. 43 enero – abril de 2012. Análisis 97 Orien.docx
celenarouzie
 

More from celenarouzie (20)

Attaining ExpertiseYou are tr.docx
Attaining ExpertiseYou are tr.docxAttaining ExpertiseYou are tr.docx
Attaining ExpertiseYou are tr.docx
 
attachment Chloe” is a example of the whole packet. Please follow t.docx
attachment Chloe” is a example of the whole packet. Please follow t.docxattachment Chloe” is a example of the whole packet. Please follow t.docx
attachment Chloe” is a example of the whole packet. Please follow t.docx
 
AttachmentFor this discussionUse Ericksons theoretic.docx
AttachmentFor this discussionUse Ericksons theoretic.docxAttachmentFor this discussionUse Ericksons theoretic.docx
AttachmentFor this discussionUse Ericksons theoretic.docx
 
Attachment Programs and Families Working Together Learn.docx
Attachment Programs and Families Working Together Learn.docxAttachment Programs and Families Working Together Learn.docx
Attachment Programs and Families Working Together Learn.docx
 
Attachment and Emotional Development in InfancyThe purpose o.docx
Attachment and Emotional Development in InfancyThe purpose o.docxAttachment and Emotional Development in InfancyThe purpose o.docx
Attachment and Emotional Development in InfancyThe purpose o.docx
 
ATTACHEMENT from 7.1 and 7.2 Go back to the Powerpoint for thi.docx
ATTACHEMENT from 7.1 and 7.2 Go back to the Powerpoint for thi.docxATTACHEMENT from 7.1 and 7.2 Go back to the Powerpoint for thi.docx
ATTACHEMENT from 7.1 and 7.2 Go back to the Powerpoint for thi.docx
 
Attached the dataset Kaggle has hosted a data science competitio.docx
Attached the dataset Kaggle has hosted a data science competitio.docxAttached the dataset Kaggle has hosted a data science competitio.docx
Attached the dataset Kaggle has hosted a data science competitio.docx
 
Attached you will find all of the questions.These are just like th.docx
Attached you will find all of the questions.These are just like th.docxAttached you will find all of the questions.These are just like th.docx
Attached you will find all of the questions.These are just like th.docx
 
Attached the dataset Kaggle has hosted a data science compet.docx
Attached the dataset Kaggle has hosted a data science compet.docxAttached the dataset Kaggle has hosted a data science compet.docx
Attached the dataset Kaggle has hosted a data science compet.docx
 
B. Answer Learning Exercises  Matching words parts 1, 2, 3,.docx
B. Answer Learning Exercises  Matching words parts 1, 2, 3,.docxB. Answer Learning Exercises  Matching words parts 1, 2, 3,.docx
B. Answer Learning Exercises  Matching words parts 1, 2, 3,.docx
 
B)What is Joe waiting for in order to forgive Missy May in The Gild.docx
B)What is Joe waiting for in order to forgive Missy May in The Gild.docxB)What is Joe waiting for in order to forgive Missy May in The Gild.docx
B)What is Joe waiting for in order to forgive Missy May in The Gild.docx
 
B)Blanche and Stella both view Stanley very differently – how do the.docx
B)Blanche and Stella both view Stanley very differently – how do the.docxB)Blanche and Stella both view Stanley very differently – how do the.docx
B)Blanche and Stella both view Stanley very differently – how do the.docx
 
b) What is the largest value that can be represented by 3 digits usi.docx
b) What is the largest value that can be represented by 3 digits usi.docxb) What is the largest value that can be represented by 3 digits usi.docx
b) What is the largest value that can be represented by 3 digits usi.docx
 
b$ E=EE#s{gEgE lEgEHEFs ig=ii 5i= l; i € 3 r i.Er1 b €€.docx
b$ E=EE#s{gEgE lEgEHEFs ig=ii 5i= l; i € 3 r  i.Er1 b €€.docxb$ E=EE#s{gEgE lEgEHEFs ig=ii 5i= l; i € 3 r  i.Er1 b €€.docx
b$ E=EE#s{gEgE lEgEHEFs ig=ii 5i= l; i € 3 r i.Er1 b €€.docx
 
B A S I C L O G I C M O D E L D E V E L O P M E N T Pr.docx
B A S I C  L O G I C  M O D E L  D E V E L O P M E N T  Pr.docxB A S I C  L O G I C  M O D E L  D E V E L O P M E N T  Pr.docx
B A S I C L O G I C M O D E L D E V E L O P M E N T Pr.docx
 
B H1. The first issue that jumped out to me is that the presiden.docx
B H1. The first issue that jumped out to me is that the presiden.docxB H1. The first issue that jumped out to me is that the presiden.docx
B H1. The first issue that jumped out to me is that the presiden.docx
 
b l u e p r i n t i CONSUMER PERCEPTIONSHQW DQPerception.docx
b l u e p r i n t i CONSUMER PERCEPTIONSHQW DQPerception.docxb l u e p r i n t i CONSUMER PERCEPTIONSHQW DQPerception.docx
b l u e p r i n t i CONSUMER PERCEPTIONSHQW DQPerception.docx
 
B R O O K I N G SM E T R O P O L I TA N P O L I CY .docx
B R O O K I N G SM E T R O P O L I TA N P O L I CY .docxB R O O K I N G SM E T R O P O L I TA N P O L I CY .docx
B R O O K I N G SM E T R O P O L I TA N P O L I CY .docx
 
B L O C K C H A I N & S U P P LY C H A I N SS U N I L.docx
B L O C K C H A I N  &  S U P P LY  C H A I N SS U N I L.docxB L O C K C H A I N  &  S U P P LY  C H A I N SS U N I L.docx
B L O C K C H A I N & S U P P LY C H A I N SS U N I L.docx
 
Año 15, núm. 43 enero – abril de 2012. Análisis 97 Orien.docx
Año 15, núm. 43  enero – abril de 2012. Análisis 97 Orien.docxAño 15, núm. 43  enero – abril de 2012. Análisis 97 Orien.docx
Año 15, núm. 43 enero – abril de 2012. Análisis 97 Orien.docx
 

Recently uploaded

Oliver Asks for More by Charles Dickens (9)
Oliver Asks for More by Charles Dickens (9)Oliver Asks for More by Charles Dickens (9)
Oliver Asks for More by Charles Dickens (9)
nitinpv4ai
 
INTRODUCTION TO HOSPITALS & AND ITS ORGANIZATION
INTRODUCTION TO HOSPITALS & AND ITS ORGANIZATION INTRODUCTION TO HOSPITALS & AND ITS ORGANIZATION
INTRODUCTION TO HOSPITALS & AND ITS ORGANIZATION
ShwetaGawande8
 
220711130100 udita Chakraborty Aims and objectives of national policy on inf...
220711130100 udita Chakraborty  Aims and objectives of national policy on inf...220711130100 udita Chakraborty  Aims and objectives of national policy on inf...
220711130100 udita Chakraborty Aims and objectives of national policy on inf...
Kalna College
 
The basics of sentences session 7pptx.pptx
The basics of sentences session 7pptx.pptxThe basics of sentences session 7pptx.pptx
The basics of sentences session 7pptx.pptx
heathfieldcps1
 
BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 8 - CẢ NĂM - FRIENDS PLUS - NĂM HỌC 2023-2024 (B...
BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 8 - CẢ NĂM - FRIENDS PLUS - NĂM HỌC 2023-2024 (B...BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 8 - CẢ NĂM - FRIENDS PLUS - NĂM HỌC 2023-2024 (B...
BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 8 - CẢ NĂM - FRIENDS PLUS - NĂM HỌC 2023-2024 (B...
Nguyen Thanh Tu Collection
 
Brand Guideline of Bashundhara A4 Paper - 2024
Brand Guideline of Bashundhara A4 Paper - 2024Brand Guideline of Bashundhara A4 Paper - 2024
Brand Guideline of Bashundhara A4 Paper - 2024
khabri85
 
欧洲杯下注-欧洲杯下注押注官网-欧洲杯下注押注网站|【​网址​🎉ac44.net🎉​】
欧洲杯下注-欧洲杯下注押注官网-欧洲杯下注押注网站|【​网址​🎉ac44.net🎉​】欧洲杯下注-欧洲杯下注押注官网-欧洲杯下注押注网站|【​网址​🎉ac44.net🎉​】
欧洲杯下注-欧洲杯下注押注官网-欧洲杯下注押注网站|【​网址​🎉ac44.net🎉​】
andagarcia212
 
Accounting for Restricted Grants When and How To Record Properly
Accounting for Restricted Grants  When and How To Record ProperlyAccounting for Restricted Grants  When and How To Record Properly
Accounting for Restricted Grants When and How To Record Properly
TechSoup
 
Educational Technology in the Health Sciences
Educational Technology in the Health SciencesEducational Technology in the Health Sciences
Educational Technology in the Health Sciences
Iris Thiele Isip-Tan
 
KHUSWANT SINGH.pptx ALL YOU NEED TO KNOW ABOUT KHUSHWANT SINGH
KHUSWANT SINGH.pptx ALL YOU NEED TO KNOW ABOUT KHUSHWANT SINGHKHUSWANT SINGH.pptx ALL YOU NEED TO KNOW ABOUT KHUSHWANT SINGH
KHUSWANT SINGH.pptx ALL YOU NEED TO KNOW ABOUT KHUSHWANT SINGH
shreyassri1208
 
Level 3 NCEA - NZ: A Nation In the Making 1872 - 1900 SML.ppt
Level 3 NCEA - NZ: A  Nation In the Making 1872 - 1900 SML.pptLevel 3 NCEA - NZ: A  Nation In the Making 1872 - 1900 SML.ppt
Level 3 NCEA - NZ: A Nation In the Making 1872 - 1900 SML.ppt
Henry Hollis
 
How to Manage Reception Report in Odoo 17
How to Manage Reception Report in Odoo 17How to Manage Reception Report in Odoo 17
How to Manage Reception Report in Odoo 17
Celine George
 
مصحف القراءات العشر أعد أحرف الخلاف سمير بسيوني.pdf
مصحف القراءات العشر   أعد أحرف الخلاف سمير بسيوني.pdfمصحف القراءات العشر   أعد أحرف الخلاف سمير بسيوني.pdf
مصحف القراءات العشر أعد أحرف الخلاف سمير بسيوني.pdf
سمير بسيوني
 
Ch-4 Forest Society and colonialism 2.pdf
Ch-4 Forest Society and colonialism 2.pdfCh-4 Forest Society and colonialism 2.pdf
Ch-4 Forest Society and colonialism 2.pdf
lakshayrojroj
 
SWOT analysis in the project Keeping the Memory @live.pptx
SWOT analysis in the project Keeping the Memory @live.pptxSWOT analysis in the project Keeping the Memory @live.pptx
SWOT analysis in the project Keeping the Memory @live.pptx
zuzanka
 
CIS 4200-02 Group 1 Final Project Report (1).pdf
CIS 4200-02 Group 1 Final Project Report (1).pdfCIS 4200-02 Group 1 Final Project Report (1).pdf
CIS 4200-02 Group 1 Final Project Report (1).pdf
blueshagoo1
 
THE SACRIFICE HOW PRO-PALESTINE PROTESTS STUDENTS ARE SACRIFICING TO CHANGE T...
THE SACRIFICE HOW PRO-PALESTINE PROTESTS STUDENTS ARE SACRIFICING TO CHANGE T...THE SACRIFICE HOW PRO-PALESTINE PROTESTS STUDENTS ARE SACRIFICING TO CHANGE T...
THE SACRIFICE HOW PRO-PALESTINE PROTESTS STUDENTS ARE SACRIFICING TO CHANGE T...
indexPub
 
Observational Learning
Observational Learning Observational Learning
Observational Learning
sanamushtaq922
 
Andreas Schleicher presents PISA 2022 Volume III - Creative Thinking - 18 Jun...
Andreas Schleicher presents PISA 2022 Volume III - Creative Thinking - 18 Jun...Andreas Schleicher presents PISA 2022 Volume III - Creative Thinking - 18 Jun...
Andreas Schleicher presents PISA 2022 Volume III - Creative Thinking - 18 Jun...
EduSkills OECD
 
220711130097 Tulip Samanta Concept of Information and Communication Technology
220711130097 Tulip Samanta Concept of Information and Communication Technology220711130097 Tulip Samanta Concept of Information and Communication Technology
220711130097 Tulip Samanta Concept of Information and Communication Technology
Kalna College
 

Recently uploaded (20)

Oliver Asks for More by Charles Dickens (9)
Oliver Asks for More by Charles Dickens (9)Oliver Asks for More by Charles Dickens (9)
Oliver Asks for More by Charles Dickens (9)
 
INTRODUCTION TO HOSPITALS & AND ITS ORGANIZATION
INTRODUCTION TO HOSPITALS & AND ITS ORGANIZATION INTRODUCTION TO HOSPITALS & AND ITS ORGANIZATION
INTRODUCTION TO HOSPITALS & AND ITS ORGANIZATION
 
220711130100 udita Chakraborty Aims and objectives of national policy on inf...
220711130100 udita Chakraborty  Aims and objectives of national policy on inf...220711130100 udita Chakraborty  Aims and objectives of national policy on inf...
220711130100 udita Chakraborty Aims and objectives of national policy on inf...
 
The basics of sentences session 7pptx.pptx
The basics of sentences session 7pptx.pptxThe basics of sentences session 7pptx.pptx
The basics of sentences session 7pptx.pptx
 
BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 8 - CẢ NĂM - FRIENDS PLUS - NĂM HỌC 2023-2024 (B...
BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 8 - CẢ NĂM - FRIENDS PLUS - NĂM HỌC 2023-2024 (B...BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 8 - CẢ NĂM - FRIENDS PLUS - NĂM HỌC 2023-2024 (B...
BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 8 - CẢ NĂM - FRIENDS PLUS - NĂM HỌC 2023-2024 (B...
 
Brand Guideline of Bashundhara A4 Paper - 2024
Brand Guideline of Bashundhara A4 Paper - 2024Brand Guideline of Bashundhara A4 Paper - 2024
Brand Guideline of Bashundhara A4 Paper - 2024
 
欧洲杯下注-欧洲杯下注押注官网-欧洲杯下注押注网站|【​网址​🎉ac44.net🎉​】
欧洲杯下注-欧洲杯下注押注官网-欧洲杯下注押注网站|【​网址​🎉ac44.net🎉​】欧洲杯下注-欧洲杯下注押注官网-欧洲杯下注押注网站|【​网址​🎉ac44.net🎉​】
欧洲杯下注-欧洲杯下注押注官网-欧洲杯下注押注网站|【​网址​🎉ac44.net🎉​】
 
Accounting for Restricted Grants When and How To Record Properly
Accounting for Restricted Grants  When and How To Record ProperlyAccounting for Restricted Grants  When and How To Record Properly
Accounting for Restricted Grants When and How To Record Properly
 
Educational Technology in the Health Sciences
Educational Technology in the Health SciencesEducational Technology in the Health Sciences
Educational Technology in the Health Sciences
 
KHUSWANT SINGH.pptx ALL YOU NEED TO KNOW ABOUT KHUSHWANT SINGH
KHUSWANT SINGH.pptx ALL YOU NEED TO KNOW ABOUT KHUSHWANT SINGHKHUSWANT SINGH.pptx ALL YOU NEED TO KNOW ABOUT KHUSHWANT SINGH
KHUSWANT SINGH.pptx ALL YOU NEED TO KNOW ABOUT KHUSHWANT SINGH
 
Level 3 NCEA - NZ: A Nation In the Making 1872 - 1900 SML.ppt
Level 3 NCEA - NZ: A  Nation In the Making 1872 - 1900 SML.pptLevel 3 NCEA - NZ: A  Nation In the Making 1872 - 1900 SML.ppt
Level 3 NCEA - NZ: A Nation In the Making 1872 - 1900 SML.ppt
 
How to Manage Reception Report in Odoo 17
How to Manage Reception Report in Odoo 17How to Manage Reception Report in Odoo 17
How to Manage Reception Report in Odoo 17
 
مصحف القراءات العشر أعد أحرف الخلاف سمير بسيوني.pdf
مصحف القراءات العشر   أعد أحرف الخلاف سمير بسيوني.pdfمصحف القراءات العشر   أعد أحرف الخلاف سمير بسيوني.pdf
مصحف القراءات العشر أعد أحرف الخلاف سمير بسيوني.pdf
 
Ch-4 Forest Society and colonialism 2.pdf
Ch-4 Forest Society and colonialism 2.pdfCh-4 Forest Society and colonialism 2.pdf
Ch-4 Forest Society and colonialism 2.pdf
 
SWOT analysis in the project Keeping the Memory @live.pptx
SWOT analysis in the project Keeping the Memory @live.pptxSWOT analysis in the project Keeping the Memory @live.pptx
SWOT analysis in the project Keeping the Memory @live.pptx
 
CIS 4200-02 Group 1 Final Project Report (1).pdf
CIS 4200-02 Group 1 Final Project Report (1).pdfCIS 4200-02 Group 1 Final Project Report (1).pdf
CIS 4200-02 Group 1 Final Project Report (1).pdf
 
THE SACRIFICE HOW PRO-PALESTINE PROTESTS STUDENTS ARE SACRIFICING TO CHANGE T...
THE SACRIFICE HOW PRO-PALESTINE PROTESTS STUDENTS ARE SACRIFICING TO CHANGE T...THE SACRIFICE HOW PRO-PALESTINE PROTESTS STUDENTS ARE SACRIFICING TO CHANGE T...
THE SACRIFICE HOW PRO-PALESTINE PROTESTS STUDENTS ARE SACRIFICING TO CHANGE T...
 
Observational Learning
Observational Learning Observational Learning
Observational Learning
 
Andreas Schleicher presents PISA 2022 Volume III - Creative Thinking - 18 Jun...
Andreas Schleicher presents PISA 2022 Volume III - Creative Thinking - 18 Jun...Andreas Schleicher presents PISA 2022 Volume III - Creative Thinking - 18 Jun...
Andreas Schleicher presents PISA 2022 Volume III - Creative Thinking - 18 Jun...
 
220711130097 Tulip Samanta Concept of Information and Communication Technology
220711130097 Tulip Samanta Concept of Information and Communication Technology220711130097 Tulip Samanta Concept of Information and Communication Technology
220711130097 Tulip Samanta Concept of Information and Communication Technology
 

Available online at www.sciencedirect.comwww.elsevier.comlo.docx

  • 1. Available online at www.sciencedirect.com www.elsevier.com/locate/ijproman International Journal of Project Management 26 (2008) 149–163 Project risk management practice: The case of a South African utility company Riaan van Wyk a, Paul Bowen b,*, Akintola Akintoye c a Electricity Supply Commission of South Africa (ESKOM), South Africa b Department of Construction Economics and Management, University of Cape Town, Private Bag, Rondebosch 7700, South Africa c School of the Built and Natural Environment, Glasgow Caledonian University, Cowcaddens Road, Glasgow, Scotland, UK Received 26 October 2006; received in revised form 26 February 2007; accepted 20 March 2007 Abstract This paper documents the risk management practice of a utility company for its Recovery Plan project to address the risks of power interruptions due to a shortfall of supply and increasing electricity demand. The company’s corporate risk management
  • 2. process and its practice at divisional and project levels are discussed. The key role of stakeholders in risk identification, analysis, mitigation, monitoring and reporting is emphasised by the company and this drives its risk management practice. Despite the level of resources available within the company to use more sophisticated risk management tools, the company adopts simple risk management methods suggesting that a large size company does not necessarily use ‘state of the art’ risk management techniques. Recommendations for improved practice are made. � 2007 Elsevier Ltd and IPMA. All rights reserved. Keywords: Risk management; Utility; Case study; Stakeholder; Electricity; South Africa 1. Introduction Risk management continues to be a major feature of the project management of large construction, engineering and technological projects in an attempt to reduce uncertainties and to achieve project success. Miller and Lessard [1] have argued why large engineering projects should be carefully managed given that they are ‘‘high stakes games’’ charac- terised by substantial irreversible commitments, skewed reward structures in case of success, and high probabilities of failure. In addition, they categorised the risk associated with different types of projects ranging from oil platform projects, nuclear-power projects, hydro-electric-power pro- jects, urban transport projects, road and tunnel systems, and research and development projects. They are of the opinion that power projects possess moderate risks in so far as engineering is concerned, but are very difficult in 0263-7863/$30.00 � 2007 Elsevier Ltd and IPMA. All rights
  • 3. reserved. doi:10.1016/j.ijproman.2007.03.011 * Corresponding author. Tel.: +27 21 650 3445; fax: +27 21 689 7564. E-mail address: [email protected] (P. Bowen). terms of social acceptability. Elkingston and Smallman [2] examined project risk management practices of British utility companies given that the utilities sector (comprising water, power, telecommunications) is associated with less predictable projects which are perceived to be riskier than day-to-day business activities. They argued that risk man- agement is an integral part of project management in this sector; hence, most large companies put substantial resources into the management of their business risk. The current paper presents the risk management of a Recovery Plan project of the Eskom Holdings Ltd. power company in South Africa. Eskom Holdings Ltd. is wholly owned by the South African government. The company is a vertically-integrated operation that generates, trans- mits, and distributes electricity to industrial, mining, com- mercial, agricultural, re-distributors and residential users. It is also involved in the purchase and sale of electricity to and from South African Development Community (SADC) countries, comprising Botswana, Mozambique, Namibia, Zimbabwe, Lesotho, Swaziland and Zambia. mailto:[email protected] Shantelle Hildred 150 R. van Wyk et al. / International Journal of Project Management 26 (2008) 149–163
  • 4. The company’s business is divided into a number of divi- sions: Generation, Transmission and Distribution; Resource and Strategy; Finance, Key Sales and Customers Services; Enterprises; Human Resources; and Corporate and External Relations. The group has many main subsidi- aries, with the core businesses including non-regulated elec- tricity supply industry activities, the provision of electricity supply and related services outside South Africa, the grant- ing of home loans to employees, the management and insurance of perceived risks to Eskom, and social invest- ment initiatives. The company’s revenue in the 12 months of the 2005/2006 financial year was R36,607m (US$4947m or £2662m)1 and employed some 29,697 per- sons (excluding contract and temporary workers). This paper does not add to the theory of risk management. Rather, the purpose is to document rich case study material indicating the practice of risk management and the extent to which practice and theory converge/diverge. One of the authors is currently employed by Eskom in a project management capacity, thus facilitating access to the case material presented here. The case study has been structured into four parts: Part 1 describes the corporate risk management process of the holding company. Part 2 presents the risk management process of a division of the company; the distributive divi- sion being used for this purpose. Part 3 presents the case study of a Recovery Plan project of the division to address the risks of power interruptions due to a shortfall of supply and increasing electricity demand. Part 4 documents the conclusions emanating from the study. The lesson from the case study is that a (very) large company with an appro- priate level of resources may not necessarily use sophisti- cated risk management tools; rather, simple methods that enable the company to mitigate the risks faced by the busi- ness are adopted.
  • 5. 2. Corporate risk management within Eskom Holdings Ltd. Risk management within Eskom is an important and integral element of the business. Given the importance of risk management, the company has a dedicated Risk Man- agement Committee (RMC) as one of its seven primary committees (the other committees are the Board commit- tee, audit committee, tender committee, human resources committee, remuneration and ethics committee, sustain- ability committee, and executive management committee). The RMC comprises three non-executive directors, the finance director and the managing director (Generation division). The RMC is chaired by an independent, non- executive director. The committee is tasked with ensuring that the company’s risk management strategies and pro- cesses are aligned with best practice. It also deals with 1 Exchange rates as at 7th September 2006: R7.40 SA Rands = US$1; R13.75 SA Rands = £1. the company’s integrated risk management strategy and processes, these embracing risk tolerance and appetite, risk accountably, major risk exposures, and emerging risk issues. Eskom practices an integrated risk management strategy and process by identifying risks and opportunities against business objectives during risk assessments throughout the organisation, from both a line and functional perspec- tive. Risk integration between divisions and subsidiaries is reviewed by the RMC to ensure a coordinated approach to risk mitigation measures. Key risk management ‘‘buzz words’’ feature prominently in the company’s risk manage- ment process, as depicted in the company’s 186 page 2006 annual report (http://www.eskom.co.za/annreport06/). The risk prefixes that are contained in the annual report include: exposure, assessment, accountability, internal con-
  • 6. trol, matrix, categories, mitigation measures, tolerance lev- els, categories, identification, evaluation, appetite, profile, audit, financing, issues, process, ownership, etc. A content analysis of the annual report shows that the word ‘risk’ is mentioned 206 times whilst the term ‘risk management’ is mentioned 56 times; these being explicit indicators of the importance that the company attaches to the risks to which it is exposed. Risk categories that the company faces are defined in the company’s risk matrix, and include: finance, technical, environmental, legal, human resources, informa- tion, stakeholders, regulatory and strategic. The remit of the company’s Risk Management Commit- tee (RMC) is to ensure that Integrated Risk Management (IRM) is applied throughout the Eskom business. It reviews the risk processes and all major risks within the business and reports back to the Board. Integration between the various Eskom divisions and subsidiaries is ensured via the interaction of the different risk (or risk- related) committees. Each division within the company handles its own Risk Management System and may have slightly different risk approaches within each of the six regions: Western; Eastern; Northern; North-West; South- ern; and Central. This diversity is allowed as long as it sup- ports the strategy and milestones set by the RMC which encourages a coordinated and common approach for the business as a whole. Eskom has adopted the Code of Practice published by the Institute of Risk Management of South Africa. In addition, it has developed its own methodology for deter- mining the ‘value’ or weighting for specific risks faced by the company. These weightings are used to assist the organisation to better identify which risks should receive priority and also show the value of risk mitigation mea- sures. Aligned to this valuation methodology there are
  • 7. risk tolerance levels for each division and main subsidiar- ies, together with risk appetite parameters for each func- tional risk area. Being a South African utility company with a wider remit for the sale and purchase of electricity from neighbouring countries, the company has identified some risks that it considers it faces. These are depicted in Table 1. http://www.eskom.co.za/annreport06 Table 1 A list of key risks faced by the company Key risks 1. Regulatory risk that encompasses the need for clear regulatory framework and adequate price increases to ensure long-term sustainability 2. Future capacity, where the following needs to be addressed: a. The availability of capacity in the long-term b. The impact of new capital projects on the overall business c. The ongoing ability to maintain consistent supply d. Aging plant and increasing plant performance indicators 3. Debt management of small power users 4. Non-technical energy losses where the theft of conductors results in the lack of supply of power and the potential for injuries to the public 5. The ability to respond to changes in the industry arising from the
  • 8. proposed new Electricity Supply Industry in South Africa while meeting the shareholder’s objective for the company 6. Shareholder relationships with the focus on the ability to manage the different expectations of the shareholder and government departments in terms of Eskom’s business objectives 7. Information security, management of the outsourced information technology service contract, lack of skills and resources, and infor- mation technology business continuity management 8. Availability of the skills required for the future business needs including skills retention, training and succession planning. The impact of HIV/AIDS is also addressed as a component of this key risk area 2 The King Reports on Corporate Governance (King I and King II), published by the King Committee on Corporate Governance, aimed at promoting the highest standards of corporate governance in South Africa. More specifically, the King I Report dealt with financial and regulatory aspects of corporate governance and, in addition, advocated an integrated approach to good governance in the interests of a wide range of stakeholders. With the publication of the King II Report, in terms of which risk management received official consideration for the first time in South Africa, companies are now required to audit risk exposure
  • 9. on an annual basis and disclose it to their shareholders. In addition, King II acknowledged that a company’s activities are more than profit to shareholders, embracing economic, environmental and social aspects. R. van Wyk et al. / International Journal of Project Management 26 (2008) 149–163 151 3. Risk Management System within the Distribution Division Given that each Division and each region within the company handles its own Risk Management System, risk management within the Distribution (Western Region) Division forms part of the responsibilities of the Business Planning and Integrated Risk (BPIR) Committee which is led by the BPIR Manager. BPIR is therefore a subcom- mittee of the Regional (Western) Executive Committee (REC). BPIR duties focus on a holistic business planning and integration function, which includes all associated risks. The REC appoints the members and chairperson of the BPIR committee, who, in return, report back and advise on all Region’s business risk-related matters. Membership of BPIR consists of REC members, subject matter experts and other Eskom officials. They manage the entire Risk Management Process at regional level and include issues around process deadlocks and emer- gency preparedness. The BPIR committee meets once a month and has iden- tified the following attributes of its approach to the overall Eskom Integrated Risk Management (IRM): � assists with business decision-making as more informa- tion becomes available from the risk process being
  • 10. executed; � facilitates learning from and incorporating lessons from the past; � allows for an external view on matters which could lead to more issues being identified; � provides for integration between the different functional departments leading to the optimal addressing of risk issues; � allows identification of any opportunities arising from the matters at hand; � ensures focus on objectives, keeping in line with the regional objectives and those set by the Risk Manage- ment Committee at Board level; � ensures a proper audit trail for all risk-related matters: the origin, owner, actions decided upon and taken, and progress; � assists with decision making, by providing input into the continuous business planning which is also a function of this committee; � very importantly, it strives to protect against any impact to the region’s financial results and image; and � meets the requirements of the King II2 report. 4. Case study of the Western Cape Recovery Plan project One of the projects of the Western Region Distribution Division is Eskom’s Recovery Plan for the Western Cape. The project was developed to address the current risk of power interruptions due to a shortfall of supply and increas-
  • 11. ing electricity demand during the winter period. To under- stand the reasons for the shortfall in supply, it is necessary to understand how the Western Cape is supplied with elec- tricity and the existing constraints surrounding this. The Western Cape requires up to 4250 MegaWatt (MW) of power supply daily over peak periods during the winter months. This is supplied from four power stations that pro- vide a combined total of 4780 MW as follows: 2 · Nuclear reactors at the Koeberg Nuclear Station (900 MW · 2) 1800 MW Coal power stations in Mpumalanga 2400 MW Palmiet hydro-electric pump station 400 MW Steenbras hydro-electric pump station 180 MW Total 4780 MW However, there are peak periods in this region when there is a surge in power consumption and these usually occur between 5am and 8am, and 6pm and 8pm during week days as shown in Fig. 1.
  • 12. During routine maintenance on Unit 1 at the Koeberg Nuclear Station in late 2005 serious damage was done to the generator and its cooling system for this Unit. How- Fig. 1. Demand for electricity as shown in the peak periods. 152 R. van Wyk et al. / International Journal of Project Management 26 (2008) 149–163 ever, the nuclear reactor was not affected. The time for repairing the generator and cooling system was set for at least three months from January 2006. The repair pro- gramme was focused on minimizing the period for Unit 1 to be out of service. This meant that various options had to be considered which included obtaining replacement parts (i.e. stator and rotor), acquiring spare parts, and repairing the damaged parts. The dismantling of the Unit 1 generator is considered a slow process due to the cool down period required (5 days) and separation of the rotor and stator (10 days). After the assessment of the extent of the damage, it was decided to start repairs to the stator and rotor and obtain a spare rotor from a company in France. This particular company had been the original advisors to the Koeberg plant some 20 years ago. During this time, Koeberg Unit 2 continued to provide the required electricity to the Western Cape. However, a number of power interruptions were experienced during the month of February 2006 due to a variety of reasons, including: 1. Unit 6 of the Kendal Power Station in Mpumalanga tripped causing a large fluctuation on the National Net- work. As a safety precaution, Koeberg’s Unit 2 was
  • 13. removed from the grid and placed in a controlled shut down. After the stabilisation of the network, it took Unit 2 about a week to start up and increase generation to full capacity. Due to the shortage of supply during this period, load shedding (controlled black-outs) were required and implemented. Public opinion was vocifer- ous in its condemnation of Eskom. 2. Flash-overs between transmission lines due to high pol- lution from veld fires and unexpected fog caused various power lines to trip; interrupting the power flow from the north and forcing Koeberg’s Unit 2 to remove itself from the grid once again. This led to more load shedding to manage the power shortage. This served only to increase public condemnation. Another risk was identified from the scheduled refuel- ling of Unit 2 which was scheduled for March 2006. How- ever, the repairs to Unit 1 had to be completed in time so that Unit 2 could be shut down for approximately two months to complete the refuelling and routine maintenance procedures. In normal circumstances both units would then have been ready to provide power for the winter months. The rotor from France was only expected (and delivered) during April 2006 and the repairs to the local rotor and sta- tor were still underway at that time. It was impossible to remove Unit 2 before Unit 1 was repaired as there was no means to provide for the shortfall in electricity supply. The economic impact of the February power outages was estimated to be in excess of R500 million (about US$68m or £36m) and was subject of discussion at provincial and national governmental levels. To remove Unit 2 from the grid would immediately mean a shortfall of another 900 MW and would force further load shedding to occur with its associated economic impact. The Western Cape Recovery Plan was an effort to do
  • 14. the following: (1) explain the electricity supply problem; (2) forecast the power demand and expected shortfall for the winter months; (3) provide the timelines for Koeberg R. van Wyk et al. / International Journal of Project Management 26 (2008) 149–163 153 Unit 1 to be repaired and Unit 2 to be refuelled; (4) iden- tify all risks that could impact on the project plan; (5) develop mitigating actions for the identified risks; (6) iden- tify other energy saving options to minimize the impact of the shortfall; (7) provide load shedding principles and guidelines; and (8) provide stakeholder and communica- tion guidelines. This plan was a combined effort between Eskom, the City of Cape Town (electricity department) and RED ONE (the recently formed regional electricity distributor). Load Shedding Streamlead KSACS Streamlead DSM Streamlead Customer Services Streamlead Grid and National Control Streamlead Human Resources Streamlead Koeberg/Generation Streamlead
  • 15. Corporate Finance Streamlead Eskom Enterprises Streamlead Other Corporate Functions Key PM DSM ERD WR Recovery Programme PMO Recovery Programme Manager National Recovery Sponsor Transmission Managing Director Western Region Risk Manager Fig. 2. Team structure for the Weste Eskom Holdings Eskom Executive Eskom Recovery
  • 16. Team Dept of Public Enterprises Dept of Provincial &Local Government Provincial Government Energy Risk Management Committee ERMC Recovery Team Integrated Recovery Team M Fig. 3. Stakeholder structure for risk man An Eskom Recovery Team was established which was headed by the Managing Director of the Transmission Division. The team structure is shown in Fig. 2. The team reported into a bigger operating model made up of various stakeholders headed by the Energy Risk Management
  • 17. Committee (ERMC) as shown in Fig. 3. The Eskom Recovery Team (ERT) met at least once every two weeks where progress on the Recovery Plan was given. The feed- back was consolidated and forwarded to the Integrated Recovery Team and finally to ERMC. A weekly status Corporate Communications/ERD Streamlead WR Communications & Stakeholders Streamlead Corporate Spokesperson SO – Programme Management Office – Demand Side Management – External Relations Dept. – Western Region Corporate Communications & Stakeholder Manager Regional Recovery Sponsor Western Region General Manager rn Cape Recovery Plan project. unicipal Municipal Recovery Team RED1 Other Stakeholders Dept of
  • 18. Minerals & Energy agement of the Recovery Plan project. 154 R. van Wyk et al. / International Journal of Project Management 26 (2008) 149–163 report was also compiled by ERT and published internally within Eskom and externally to the general public. 5. Risk management of the Recovery Plan project There are typically five stages associated with risk man- agement, namely: (1) risk management planning, (2) risk identification, (3) qualitative and quantitative risk analysis, (4) risk response planning, and (5) risk monitoring and con- trol [3]. However, Edwards and Bowen [4] state that the pro- cess of risk management should include evaluation and reporting and they have as a result categorised the process of risk management into nine stages: Identification; Classifi- cation; Allocation; Analysis; Response; Recording; Moni- toring; Control; and Evaluation. Chapman [5] identified nine phases of the generic risk management process (RMP), comprising: define; focus; identify; structure, owner- ship; eliminate; evaluate; plan and manage. Practically, how- ever, it is possible to classify all these stages into a four-stage risk management cycle: risk identification; risk analysis; risk response; and risk reporting. The risk identification stage includes classification and allocation, while risk reporting includes monitoring, control and evaluation. The risk man- agement practice of the Recovery Plan project within the Eskom integrated risk management protocol is presented below along the lines of this four-stage framework.
  • 19. 5.1. Risk identification (and classification and allocation) of the Recovery Plan project The role of stakeholders in the RMP is emphasised by Loosemore et al. [6]. According to them, effective and fre- quent involvement of stakeholders at all stages of the RMP will ensure that more risks are identified and commitment obtained in managing them. Stakeholder management becomes very critical in the risk identification process given that they can have conflicting interests and the risks identi- fied could be biased towards those interests or limited to their own experiences. The possibility that the stakeholder mix could change over time also has an impact on project objec- tives and its associated risks. Furthermore, stakeholders might be unable to express their objectives clearly or limit the sharing of valid information due to confidentiality or inter-stakeholder politics. Hence, they have suggested that the risk manager or risk management service provider should encourage stakeholders to balance their objectives with one another, be flexible where possible, and understand the pres- sures and background under which objectives are created. It is generally accepted that companies with organic structures allow for more creative and imaginary approaches to identify risks, though it is still easier for mechanistic structured companies to implement those approaches [4]. This is because the latter could provide backing in the form of authority sources, addressing possi- ble resistance. Hence, companies’ management should be committed to the risk management process, identifying leaders with a strong personal passion for the subject. The classification of risks creates a common framework for grouping risks, although different cultures could classify the same risk differently. Edwards and Bowen [4] suggest two primary categories for classifying risks: Natural and
  • 20. Human Risks. Natural risks are those from systems ‘‘beyond human agency’’ which include risks from weather, geologi- cal, biological and extraterrestrial systems. Risks from human systems are more difficult to categorise due to their overlapping nature. These include risks from social, political, cultural, health, legal, economic, financial, technical and managerial systems. Baber [7] refers to internally and exter- nally generated risks. The Project Management Institute [8] classifies risk into internal and external. Examples of internal risk in project development are issues relating to labour, materials, site conditions, cash flow, etc., while external risks include governmental regulations, vandalism, sabotage, environmental factors, market forces, inflation, etc. It is generally accepted as a good risk management prac- tice that a risk should be allocated to the party who can best manage it that risk. To avoid duplication it is suggested that continuous investigations are undertaken during the pro- cess of risk management to ensure that another stakeholder has not already taken up the control of a risk [6]. Eskom, in general, is very risk aware and has invested considerable resources into this project management prac- tice within the company. Many processes are in place to identify and manage potential risks in its various functional areas. Within its Distribution Division the foci of opera- tions are customer services, engineering (safety standards – occupational safety and health requirements); finance; human resources; information management; and commer- cial. All of these functional departments are represented on the BPIR Committee where risks are raised and man- aged. At this level risks are categorized as follows: finance; technical operation and performance; legal audit and com- pliance; people; strategic acquisitions, divestitures and pro- jects; strategy; transformation; pricing; regulatory (NER); stakeholders; information; subsidiaries, associates and joint
  • 21. ventures. In this particular case, the main reason for the inade- quate supply capacity to meet the needs of the Western Cape within the normally envisaged risk possibility of a loss of generation at Koeberg was aggravated by decisions by central government that limited the capacity of Eskom to build new power stations or transmission lines. Arising from the White Paper on Energy Policy [9], government decided it was necessary to proceed with ‘the unbundling of Eskom’s generation and transmission groups’ and ‘sep- arate the power stations into a number of companies’ to ‘create the opportunity for private sector and Black Eco- nomic Empowerment investment opportunities in the gen- eration sector’. Later, the Intergovernmental Fiscal Review [10] stated ‘The ESI restructuring involves three key aspects: the sale of 30 per cent of Eskom’s generating capacity to private investors, with a black empowerment equity stake of at least 10 per cent of capacity; the separa- tion of Eskom into several generation clusters and a sepa- 3 Eskom initiated a schemed whereby the public were encouraged to exchange their conventional light bulbs for less electricity- consuming CFLs – at no cost to the consumer. R. van Wyk et al. / International Journal of Project Management 26 (2008) 149–163 155 rate transmission company; and the introduction of an electricity market, which will ensure competition between the different electricity generators. These reforms will begin during the course of 2003.’ The central government had taken responsibility to manage the investment decisions
  • 22. of the supply industry, and it was only in late 2004, with looming insufficient capacity, that the decision was made to return the responsibility for electricity sufficiency to Eskom [11]. Thus, Eskom was constrained by external forces in its ability to respond to identified risk. Most sub- sequent risk was a consequence of this external risk. The identified risks are usually assigned to the BPIR Committee members for mitigation. Although the commit- tee members remain accountable, they could subsequently delegate the risk mitigation actions and management to rel- evant staff within the establishment. The Eskom Recovery Team panel of experts responsible for addressing the Western Cape Recovery Plan project comprised senior managers drawn from the following departments and/or divisions: National Recovery Sponsor (this is … Assignment 4: HR Training Class Due Week 8 and worth 200 points Imagine that you are a member of the HR department of a small retail company and upper management has asked you to create a new employee customer service training class for all new employees. Write a six to seven (6-7) pages paper in which you: 1. Justify the use of a needs assessment of your company’s proposed employee customer service training, stressing five (5) ways in which such an assessment would expose any existing performance deficiencies. 2. Develop a customer service training implementation plan and determine the method of training (i.e., presentation, discussion, case study, discovery, role play, simulation, modeling, or on-
  • 23. the-job training). 3. Justify why you selected the training method that you did. 4. Propose two (2) ways to motivate an employee who has no interest in attending a training class. 5. Develop a survey to collect feedback from the employees who attend the training. 6. Use at least three (3) quality academic resources in this assignment. Note: Wikipedia and other Websites do not qualify as academic resources. Your assignment must follow these formatting requirements: · Be typed, double spaced, using Times New Roman font (size 12), with one-inch margins on all sides; citations and references must follow APA or school-specific format. Check with your professor for any additional instructions. · Include a cover page containing the title of the assignment, the student’s name, the professor’s name, the course title, and the date. The cover page and the reference page are not included in the required assignment page length. The specific course learning outcomes associated with this assignment are: · Design job and task analyses that align with the overall HRM strategy. · Design training and development systems to improve employee performance. · Use technology and information resources to research issues in strategic human resource development. · Write clearly and concisely about strategic human resource development using proper writing mechanics. Rubric Points: 200 Assignment 4:HR Training Class Criteria
  • 24. Unacceptable Below 70% F Fair 70-79% C Proficient 80-89% B Exemplary 90-100% A 1. Justify the use of a needs assessment of your company’s proposed employee customer service training, stressing five (5) ways in which such an assessment would expose any existing performance deficiencies. Weight: 20% Did not submit or incompletely justified the use of a needs assessment of your company’s proposed employee customer service training, stressing five (5) ways in which such an assessment would expose any existing performance deficiencies. Partially justified the use of a needs assessment of your company’s proposed employee customer service training, stressing five (5) ways in which such an assessment would expose any existing performance deficiencies. Satisfactorily justified the use of a needs assessment of your company’s proposed employee customer service training, stressing five (5) ways in which such an assessment would expose any existing performance deficiencies. Thoroughly justified the use of a needs assessment of your company’s proposed employee customer service training, stressing five (5) ways in which such an assessment would expose any existing performance deficiencies. 2. Develop a customer service training implementation plan and determine the method of training (i.e., presentation, discussion, case study, discovery, role play, simulation, modeling, or on- the-job training). Weight: 20% Did not submit or incompletely developed a customer service training implementation plan and did not submit or incompletely
  • 25. determined the method of training (i.e., presentation, discussion, case study, discovery, role play, simulation, modeling, or on-the-job training). Partially developed a customer service training implementation plan and partially determined the method of training (i.e., presentation, discussion, case study, discovery, role play, simulation, modeling, or on-the-job training). Satisfactorily developed a customer service training implementation plan and satisfactorily determined the method of training (i.e., presentation, discussion, case study, discovery, role play, simulation, modeling, or on-the-job training). Thoroughly developed a customer service training implementation plan and thoroughly determined the method of training (i.e., presentation, discussion, case study, discovery, role play, simulation, modeling, or on-the-job training). 3. Justify why you selected the training method that you did. Weight: 10% Did not submit or incompletely justified why you selected the training method that you did. Partially justified why you selected the training method that you did. Satisfactorily justified why you selected the training method that you did. Thoroughly justified why you selected the training method that you did. 4. Propose two (2) ways to motivate an employee who has no interest in attending a training class. Weight: 15% Did not submit or incompletely proposed two (2) ways to motivate an employee who has no interest in attending a training class. Partially proposed two (2) ways to motivate an employee who has no interest in attending a training class. Satisfactorily proposed two (2) ways to motivate an employee who has no interest in attending a training class. Thoroughly proposed two (2) ways to motivate an employee
  • 26. who has no interest in attending a training class. 5. Develop a survey to collect feedback from the employees who attend the training. Weight: 20% Did not submit or incompletely developed a survey to collect feedback from the employees who attend the training. Partially developed a survey to collect feedback from the employees who attend the training. Satisfactorily developed a survey to collect feedback from the employees who attend the training. Thoroughly developed a survey to collect feedback from the employees who attend the training. 6. 3 references Weight: 5% No references provided Does not meet the required number of references; some or all references poor quality choices. Meets number of required references; all references high quality choices. Exceeds number of required references; all references high quality choices. 7. Clarity, writing mechanics, and formatting requirements Weight: 10% More than 6 errors present 5-6 errors present 3-4 errors present 0-2 errors present Running head: HR TRAINING CLASS 1 HR TRAINING CLASS 2
  • 27. HR Training Class xxxxx xxxxx Dr. XXXXXX HRM 530 August 24, 2014 Introduction The paper will justify the use of a needs assessment of a company’s proposed employee customer service training, and the practices of HRM such as performance management. HRM empowering employees can also extend to innovation and less stress. This paper will elaborate on stressing the five (5) ways in which such an assessment would expose any existing performance deficiencies. From my perspective, successful organizations treat all their workers as knowledge workers and provide proper training informing them about company expectations during the new hired employee’s orientation. Let employees know how well the company is performing, and they invite ideas about how the organization can do better working as a team. Thus, upper management creates new employee customer orientation for all new employees and training development for the purpose of customer service training and an implementation plan to determine the method of training (i.e., presentation, discussion, case study, discovery, role play, simulation, modeling, or on-the-job training). Lastly, this paper elaborates on the selection of the training method, the way to encourage or motivate an employee that have no interest in training, and setting up a meeting to collect feedback from an employee who has attended training.
  • 28. Needs Assessment Every company needs an assessment to help address any gaps or needs between present conditions and preferred ones. By creating an assessment, it identifies where employees and companies need to improve by listening to what the employees have to say and give their opinion. It’s also very important in a training session to listen to what employees say or ideas, because it helps improve their performances as well as relationships with management. By having a needs assessment with employee customer service training, employee’s performance deficiencies will be exposed. There are many ways in which an assessment would expose any existing performance deficiencies, such as observation, interviews, questionnaires, studying job descriptions and difficulty analysis (Stewart G.L. & Brown, K.G., 2012). First, with observation, this gives the trainer first hand data on employee’s strengths and weaknesses without affecting their productivity. Secondly, with interviewing, the trainer will be able to gauge the employee’s options and perceptions but allowing them to address their own performances while asking in depth questions about performances. Third, with the questionnaires, this option will help give a bigger picture of the environment as respondents will be asked identical questions; data collected will help identify challenges in performances after being analyzed in a quantitative way. Fourth, studying job descriptions, this will help enacting a thorough training and supervision on the trainers as the employees will be aware of their responsibilities and what is expected of them. Lastly, the difficulty analysis will help managers identify what job duties are causing the employees problems and determine what training is needed in the particular area in order to better boost performance. Customer Service Training Implementation Plan To train customer service employees, there has to be a well laid out plan. The plan will need to cover such aspects as the goal of the training, the trainers, the duration of training, the method of training, the budget for the training process and the technology
  • 29. that subsequently needed for a successful training session. Per the HR training class title, the customer service employees will be trained on how to improve their job duties. The training implementation will consist of goal training, trainers, methods used to train and the time of duration of the training. First, the goal of training is to educate all training customer service representatives on ways to better serve the customer, secondly, the training will be conducted by seasonal experience trainers who will be either from the company or hired from outside. Once the training is completed, a thorough report will be conveyed to the management team, either by voice or report on how well the session was accepted. Third, the method of training will consist of on job training and case studies. This is the most effective way because it has been proved that employees listen to what is practically justifiable. For example, customers are reminded that failure is a part of success; however, for employees to believe this, trainers will need to incorporate case studies and examples on famous individuals who have failed and then bounced back with a successful story. Lastly, the trainers will need to determine how long the duration of the training will be, therefore, during the implementation training process, an estimated time and budget will need to be proposed. The company’s management team, Human Resource Department and trainers will need to propose a cost effective training budget and once agreed, the finance department will approve and incorporate into the budget. Selected Training Method I selected on the job training and case studies as my two training methods and the primary training method would be on the job training. I selected this as my primary training method because it has advantages over the other methods. This method gives an employee a chance to ask workplace specific questions and get pioneering guidance (Rothwell and Kazanas, 2004). It also raises employee’s skills as new standards and practices emerge as changes occur as job duties change. However, I included the case study training method because it internalizes
  • 30. the concepts passed on during job training. According to Wilson (2005), company psychologists have proved that employees tend to listen and believe to what is practically justifiable. When training, employees need to hear what others have done in order for them to accept the concepts of training, for example, as mentioned earlier, employees may be reminded that failure is a big part of success. Therefore, the training method of case studies will give the employees an idea of, in order to be successful; you will have setbacks in the process. Employee Motivation There are numerous ways to motivate employees to attend a training class but my two motivational ways I chose are; offering incentives and cross training opportunities after the training is completed. For me, I find that attending training class is boring because, the sessions are based on information that’s already been relayed to us, therefore, I choose not to go but I will explain why the two motivators I chose is beneficial to the employee and employer. First, offering incentives such as monetary increases, extra vacation days or additional hours of personal time would attract more employees to attend the training class and motivate them to perform to the best of their ability, therefore, when incentives for employees are facilitated, an instant level of enthusiastic peaks from employees to attending training class. Secondly, allowing employees to cross training on duties within the company that they are unfamiliar with, would spark them to attend the training class as well. Allowing employees the opportunity to advance their knowledge within the company will motivate them to attend the training, which consecutively makes them more valuable to the company. Therefore, managers should encourage cross training after a class because it breaks the monotony and employees are able to switch up at any given time and do another job when needed. Also, with cross training, employees will have the opportunity to trade jobs periodically which makes a good business strategy because it a proactive way to keep the company running smoothing. The motivators I chose are just two out of the many
  • 31. ways that helps generate fulfilling work attitudes from employees. Survey Development The survey below will be used to collect feedback from employees attending the training. This survey will seek the interest how to collect feedback from employees on whether the training was beneficial, how the training once learned will be put into practice, whether more training is needed in customer service and the challenges they expect face while serving the customers on a day to day basis (Montana and Charnov, 2002). Also, this survey will focus on the aspects s age, job position and employee opinions regarding the training class. Lastly, the survey will consist of two sections; the first section pertains to collecting information regarding the data of participants and the second section pertains to collecting information about the participant’s feedback towards training. Survey Section One 1. Indicate your sex ⃝ Male ⃝ Female 2. Indicate your position in the company ⃝ Employee ⃝ Senior Employee ⃝ Manager ⃝ Senior Manager 3. Marital Status ⃝ Single ⃝ Married Section Two Please indicate your view by checking the column of the items listed below:
  • 32. Strongly Agree Agree Neutral Disagree Strongly Disagree 1. The training fulfilled by expectations. 2. Will you be able to utilize the training? 3. Topics were identified and adhered to. 4. Content thought out and easily followed. 5. Materials relevant and handy. 6. The trainer was well informed.
  • 33. 7. The value of instructions was good. 8. Trainer achieved the training objectives. 9. Discussion and interaction encouraged. 10. Ample time for questions/discussion. Section Three Good Average Poor Very Poor 11. What is your overall rating? ⃝ ⃝ ⃝ ⃝
  • 34. 12. Suggestion on what needs to be improved. 13. Additional Comments. References Montana, P. J. & Charnov, B. H. (2002). Training and Development Management. Barron’s Educational Series, pg. 225. ISBN 0-7641-1276-7 Rothwell, W.J. & Kazanas, H.C. (2004). The Strategic Development of Talent. Human Resource Development Press, pg. 4. ISBN 0-87425-752-2. Stewart G.L. & Brown, K.G. (2012). Human Resource Management. Linking Strategy to Practice. (2nd ed.). Wilson, J. P. (2005). Human Resource Management: Learning and Training for Individuals and Organizations.