ASCE OC - EWRI: OCWD Mid-Basin Injection: Centennial Park Project

390 views

Published on

American Society of Civil Engineering Orange County Branch (ASCE OC) - Environmental And Water Resources Institute (EWRI) - February Luncheon Presentation: Mid-Basin Injection at Centennial Park Project. Ground Water Replenishment System (GWRS) Presentation by OCWD and Tetra Tech

Published in: Engineering
  • Be the first to comment

  • Be the first to like this

ASCE OC - EWRI: OCWD Mid-Basin Injection: Centennial Park Project

  1. 1. Mid‐Basin Injection: Centennial Park OCWD: Ben Smith Tetra Tech: Mike Tsoi & Erin Cabanero
  2. 2. Orange County Water District • CA special district, manage groundwater in central &  north Orange County • Water supply to 19 agencies, serving >2.4 million • Groundwater Replenishment System (GWRS): wastewater to drinking water • Seawater intrusion barrier in Fountain Valley & Huntington Beach • Santa Ana River and lakes to capture & recharge water • 2,150± acres land above Prado Dam: water conservation,  storage, & quality • Green Acres Project: disinfected tertiary for non‐potable uses
  3. 3. Overview of GWRS Projects • GWRS Original Project (Completed 2008) – 70 MGD treatment facility with future expansion  capacities, injection wells, and 13.8 mile pipeline • GWRS Initial Expansion (Completed 2015) – Expansion to 100 MGD, flow equalization • GWRS Final Expansion (Completion ~2023) – Expansion to 130 MGD, pump station, water supply  pipeline, & treatment process reconfiguration at OC  Sanitation District Plant 2
  4. 4. Recharge of GWRS Water Total GWRS Final Expansion capacity = 130 MGD MBI 8 MGD Burris Basin Outlet & Pump Station 20 MGD GWRS Final Expansion 130 MGD Talbert Seawater Barrier > 15 MGD Recharge Facility Recharge Capacity Talbert Seawater Barrier > 15 MGD Mid‐Basin Injection 1.5 + 6.5 MGD Burris Basin Outlet 20 MGD Anaheim Recharge Basins 87 MGD TOTAL 130 MGD Recharge Basins 87 MGD
  5. 5. Project Location June 2017 Principal Aquifer Contours CENTENNIAL  PARK Why Centennial Park? – Raise local water levels – Next to MBI Demonstration project – Next to existing GWRS pipeline – Recharge GWRS water with 4 wells – Reduce nearby well pumping energy – Reduce amount of GWRS water that  must be recharged in Anaheim
  6. 6. Travel Time & Level Change
  7. 7. Site Stakeholders • City • Park Users • Nearby Residents • Santa Ana College • Godinez High School • Mitchell School • Heritage Museum
  8. 8. Santa Ana MOU & License • Federal & State approvals required • MOU and License outline: – Site Use Restrictions • Max. 6 month impact to single location – General Project Concept • No permanent loss of park use • Wells below grade in parking lots • Not interrupt park uses during construction – Site Improvements • Asphalt Paving • Shared Structures • Lake Replenishment
  9. 9. MBI‐1 Components - Connect to GWRS & Cross Edinger Bridge - 1.9 Miles Supply & Backflush Pipes  (night‐time) - 2 Air‐Gap Structures - 4 Injection Wells in Vaults (24‐hour drilling, ~1,100 ft) - 2 CMU Shared Structures - 2 Monitoring Wells (~1,200 ft) - Grind & Cap Paving (9.6 ac) - Skate Park Camera/Fence - Process Control System
  10. 10. Demonstration MBI Well Above Ground Pipes, Motor, & Building Centennial wells will be below ground & electrical in Shared Structures Completed Construction April 2015
  11. 11. Drilling Development & Staging
  12. 12. Edinger Bridge Crossing 30” pipe, aesthetic cover OC Encroachment & ACOE 408
  13. 13. Project Timeline Event Dates Execute MOU with City of Santa Ana July 2014 Certify EIR/EA April 2016 Execute City Agreement and SAUSD Easement June 2016 Design Jul 2015 – Feb 2017 Financing Application Apr 2016 – Jul 2017 Execute Second SAUSD Easement (SAR-13) April – June 2017 Award MBI-2017-1 Construction July 2017 Construct MBI-2017-2 (SAR-13) Aug – Dec 2017 Submit Title 22 MBI Eng. Report Supplement February 2018 Hold Required DDW Public Hearing July 2018 Obtain Regional Board Permit Amendment December 2019 Begin Operation of MBI Centennial Park Wells Spring 2019 Complete MBI-2017-1 Construction January 2020
  14. 14. Budget & Funding Description Budget Pre-Design Technical Studies $ 64,705 Design Services $ 1,145,099 Easements $ 50,400 Permitting $ 50,000 Construction Contract $ 23,107,567 Construction Contract (First Monitoring Well) $ 1,138,380 Construction Management Civil Construction Management $ 1,155,932 Well Construction Management $ 564,170 Project Contingency $ 2,323,747 Total Project Budget $ 29,800,000 SRF Loan (1.7% interest, 30 years) $27,300,000 Green Project Grant $ 2,500,000
  15. 15. Project Team Orange County Water District Tetra Tech Butier, Geotechnical Consultants Pacific Hydrotech Corporation Best Drilling and Pump OWNER: DESIGN: CONSTRUCTION MANAGEMENT:  PRIME CONTRACTOR:  WELL CONTRACTOR: 
  16. 16. Project Site Injection  Wells Demonstration  MBI Well Monitoring  Wells Shared  Structures Supply Pipes Backflush  Pipe
  17. 17. Santa Ana River Crossing OPTIONS Bore and jack option Existing knockouts within bridge
  18. 18. Santa Ana River Crossing OPTIONS Pipeline on Edinger bridge Downsize pipe from 36” to 30”
  19. 19. Santa Ana River Crossing PROTECTIVE CAGE AND AESTHETIC TREATMENT
  20. 20. County Review Army Corp of Engineers 408 permit Santa Ana River Crossing PERMITTING
  21. 21. • 16”/ 12” supply injection pipeline • 16” backflush pipeline • Instrumentation controls duct bank • Existing utilities Centennial Road CONSTRUCTION
  22. 22. Supply Pipe Material Epoxy lined & CMC steel pipe
  23. 23. Ductile Iron Pipe or CML&C steel pipe Backflush Pipe Material Contractor selected DIP
  24. 24. Instrumentation Controls ELECTRICAL AND INSTRUMENTATION CONDUITS
  25. 25. Injection Well LOCATED WITHIN BELOWGROUND VAULTS Supply / Injection Mode Backflush Mode
  26. 26. Downhole Control Valve Supply / Injection Mode Backflush Mode
  27. 27. • Air gap into lake through  abandoned irrigation  system • Lake evaporation • Backflush reduces  potable water refill • Backflush event raises  lake by ½‐inch Backflush Discharge to Lake
  28. 28. Backflush Discharge to Storm Drain Air gap into storm drain
  29. 29. Backflush Discharge to Storm Drain High school sign on structure Removing and replacing sign
  30. 30. Monitoring Well WELL DRILLING
  31. 31. Monitoring Well SOUND WALL INSTALLATION Placing sound panels Finished 24’ tall sound walls
  32. 32. Monitoring Well COMPLETED SITE Monitoring well in belowground vault
  33. 33. Well Drilling FIRE HYDRANT INSTALLATION Hot tap into existing pipeline Flushing the hydrant New hydrant
  34. 34. • OCWD electrical room • City locker rooms • City public bathrooms Shared Structure 1        
  35. 35. • Same location as existing  bathroom • OCWD electrical room • City office for skate park • City public bathrooms Shared Structure 2        
  36. 36. ADA Compliance Shared Structure 2 Shared Structure 1
  37. 37. • Improved irrigation system  for Gospel Swamp Farm • Garden beds • Improving educational  farming facility Heritage Museum Improvements
  38. 38. Maintaining access ACCESS TO SOCCER FIELDSACCESS TO SOCCER FIELDS
  39. 39. Critical Components CONSTRUCTION PHASINGCONSTRUCTION PHASING • Nighttime construction • Well construction at no more  than two locations at a time Godinez  High  School Santa Ana  College Athletic  Fields Parking Lots
  40. 40. Critical Components MULTIPLE DEPARTMENT PERMITTINGMULTIPLE DEPARTMENT PERMITTING • Public Works • Parks and Recreation • Planning/ Building • Police Department • Fire Authority • School District OCWDOCWD SANTA ANA Planning & Building SANTA ANA Planning & Building SANTA ANA Public Works SANTA ANA Public Works SANTA ANA Parks &  Recreation SANTA ANA Parks &  Recreation SANTA ANA Police  Department SANTA ANA Police  Department Orange  County Fire  Authority Orange  County Fire  Authority SANTA ANA Unified  School  District SANTA ANA Unified  School  District
  41. 41. Critical Components POTHOLING DURING DESIGN PHASEPOTHOLING DURING DESIGN PHASE • Open cut across entire width of street • Soil conditions: unconsolidated sand • Existing street alignment within curved street 410 ft radius 310 ft radius
  42. 42. Mid‐Basin Injection: Centennial Park OCWD: Ben Smith, Tetra Tech: Mike Tsoi & Erin Cabanero

×