Lecture 1 – Togethar work or Simultaneous work
And Alternate day working
Time and work
1
5
• If ‘A’ can do a work in ‘x’ days then ‘A’s one day work is
1
𝑥
1
5
1
1
5
Sachin complete a work in 5 days then his one day work is
1
5
1
5
1
5
1
5
Time and work
• If A’s 1 day work =
1
𝑥
then A can finish the work in ‘x’ days
8
7
6
5
4
3
2
1
Sohan complete a wall in 8 days
after 3 days remaining work
Time and work
• Relation between time and work
Time and work
A
complete
work in
10 days
B
complete
work in
15 days
If they working together how many days
will they take to complete the work
• Concept of together working and simultaneous working
Time and work
• A can complete a work in 20 days and B can do the
same work in 30 days , then time taken to complete
the work
Ans- 12 days
Time and work
• A and B working together can finish a piece of work
in 12 days while B alone can finish it in 30 days . In
how many days can A alone finish the work
Ans- 20
Time and work
• A completes 1/3 part of the work in 5 days while B complete 2/5
part of the same work in 10 days . In how many days will they
complete doing the work together?
(a) 7
3
4
(b) 9
3
8
(c) 8
4
5
(d) 10 days
1
2
3
Ans- 9
3
days
Time and work
• A can do a piece of work in 4 days and B can complete the
same work in 12 days. What is the number of days
required to do the same work together?
(a) 2 (b) 3 (c) 4 (d) 5
Ans- 3 days
Time and work
• Ayesha can complete a piece of work in 16 days. Amita can
complete the same piece of work in 8 days. If both of them
work together in how many days can they complete the same
piece of work?
(a) 4 2/5 (b) 5 1/3 days (c) 6 days (d) 12 days (e) None of these
Ans- 5 1/3 days
Time and work
• A and B together can complete a particular task in 8 days. If
B alone can complete the same task in 10 days, how many
days will A take to complete the task if he works alone?
• (a) 28 (b) 36 (c) 40 (d) 32 (e) None of these
Ans- 40 days
Time and work
• A can finish a work in 18 days and B can do the same
work in half of time taken by A then working together
what part of the same work they can finish in a day
(a) 1/6 (b) 1/9 (c) 2/5 (d) 2/7
Ans- 1/6 days
Time and work
Time and work
• A and B together can do a piece of work in 6 days. If A
can alone do the work in 18 days, then the number of days
required for B to finish the work is
(a) 12 (b) 9 (c) 15 (d) 10 (e) None of these
Ans- 9 days
• If A and B together can complete a piece of work in 15 days
and B alone in 20 days, in how many days can A alone
complete the work?
(a) 60 (b) 45 (c) 40 (d) 30 (e) None of these
Time and work
Ans- 60 days
• A, B and C can do a job working alone in 12, 16 and
24 days respectively. In how many days they can do
the job, if they worked together?
(a) 16/3 (b) 15/4 (c) 17/3 (d) 19/4
Time and work
Ans- 16/3 days
Time and work
• A, B and C can complete a work in 2 h. If A does the
job alone in 6 h and B in 5 h, then how long will it
take for C to finish the job alone?
(a) 5 1/2 h (b) 7 ½ h (c) 9 h (d) h 4 1/2
Ans- 7 1/2 days
Time and work
• Reena, Aastha and Shloka can independently complete a
piece of work in 6 hours, 4 hours and 12 hours
respectively. If they work together, how much time will
they take to complete that piece of work?
(a) 4 (b) 3 (c) 2 (d) 1 (e) None of these
Ans- 2 days
• A, B and C together can do a work in 6 days. A alone can
do it in 12 days while B alone can do it in 18 days, then
time taken by C is
(a) 9 days (b) 18 days (C) 27 days (d) 36 days
Time and work
Ans- 36 days
• A, B and C can complete a work in 2 h. If A does the job
alone in 6 h and B in 5 h, then how long will it take for C to
finish the job alone?
(a) 5 1/2 h (b) 7 1/2 h (c) 9 h (d)4 1/2 h
Time and work
Ans- 7 1/2 days
Time and work
• Alternate working concept
• A and B working separately can do a piece of work in 9 and
15 days, respectively. If they work for a day alternately, with
B beginning, then the work will be completed in
(a) 10 days (b) 11 2/5 days (c) 12 days(d) 13
Time and work
Ans- 11 2/5 days
• A and B can complete a piece of work in 12 and 18 days
respectively. A begins to do the work and they work
alternatively one at a time for one day each. The whole
work will be completed in
(a) 14 1/3days (b)15 2/3 days (c) 16 1/3days (d) 18 2/3 days
Time and work
Ans- 14 1/3 days
• A, B and C can do a piece of work in 20, 30 and 60 days
respectively. In how many days can A do the work if he is
assisted by B and C on every third day?
(a) 12 days (b) 15 days (c) 16 days (d) 18 days
Time and work
Ans-
Time and work
• A can do a work in 20 days and B can do in 10 days. A starts the
work and works alone for 5 days. Then, B joins A and they finish
the work. In how many days the work gets finished?
(a) 10 (b) 12 (c) 9 (d) 8
Ans- 10 days
Time and work
• A can do a piece of work in 10 days, while B can do it in 6 days. B
worked at it for 4 days. How long will A take to finish the
remaining work?
(a) 3 1/3days (b) 3 2/3 days (c) 3 2/5 days (d) 3 5/7 days (e) NoT
Ans- 3 1/3 days
Time and work
• A and B can do a work in 18 and 24 days, respectively. They
worked together for 8 days and then A left. The remaining work
was finished by B in
(a) 5 days (b) 5 1/3 days (c) 8 days (d) 10 days.
Ans- 5 1/3 days
Time and work
• A can complete a piece of work in 18 days, B in 20 days and C
in 30 days. B and C together start the work and are forced. to
leave after 2 days. The time taken by A alone to complete the
remaining work is
(a) 10 days (b) 12 days (c) 15 days (d) 16 days
Ans- 15 days
Time and work
• A can do a piece of work in 15 days, which B can do in 10 days. B
worked at it for 8 days. A can finish the remaining work in
(a) 2 days (b) 3 days (c) 5 days (d) 10 days
Ans- 3 days
Time and work
• A can do a work in 15 days and B in 20 days. If they work on it
together for 4 days, then the fraction of the work that is left is:
(a) ¼ (b) 1/10 (c) 7/15 (d) 8/15
Ans- 8/15 days
Time and work
• A and B can complete a work in 18 days and 15 days respectively.
They started doing the work together but after 3 days A had to
leave and B alone completed the remaining work. The whole
work was completed in
(a) 9 3/4 (b) 10 1/4 (c) 12 ¾ days (d) 12 1/2
Ans- 12 1/2 days
Time and work
• A, B and C can separately do a work in 12, 15 and 20 days
respectively. They started to work together but C left after 2 days.
The remaining work will be finished in (R.R.B., 2006)
(a) 4 days (b) 5 days (c) 6 days (d) 15 days
Ans- 4 days
Time and work
• A and B can do a piece of work in 30 days, while B and C can do the same
work in 24 days and C and A in 20 days. They all work together for 10 days
when B and C leave. How many days more will A take to finish the work?
(a) 18 days (b) 24 days (c) 30 days (d) 36 days
Ans- 18 days
Time and work
• A, B and C together can complete a piece of work in 10 days. All the three
started working at it together and after 4 days A left. Then B and C together
completed the work in 10 more days. A alone could complete the work in:
(a) 15 days (b) 16 days (c) 25 days (d) 50 days
Ans- 25 days
Time and work
• A can complete a work in 20 days and B in 30 days. A worked alone for 4
days and then B completed the remaining work along with C in 18 days. In
how many days can C working alone complete the work?
(a) 12 (b) 68 (c) 72 (d) 90
Ans- 90 days
Time and work
• A and B can complete a work in 8 days, working together. B alone
can do it in 12 days. After working for 4 days, B left the work.
How many days will A take to complete the remaining work?
(a) 16 (b) 18 (c) 20 (d) 22
Ans- 16 days
Time and work
• A mason can build a tank in 12 h. After working for 6 h, he took
the help of a boy and finished the work in another 5 h. The time
that the boy will take alone to complete the work is
(a) 30 h (b) 45 h (c) 60 h (d) 64 h
Ans- 60h
• A and B can do a piece of work in 24 and 30 days respectively. Both started
the work and worked for 6 days. Then B leaves the work and C joins and the
remaining work is completed by A and C together in 11 days. Find the days
in which C alone can do the work
(a) 80 (b) 100 (c) 120 (d) 130 (e) None of these
Time and work
Ans- 120 days
• A, B and C can alone complete a work in 10, 12 and 15 days
respectively. A and C started the work and after working for 4 days, A
left and B joined. In how many days the total work was completed
(a) 6 5/9 (b) 6 2/9 days (c) 6 days(d) 5 4/9 days (e)NoT
Time and work
Ans- 6 2/9 days
• Two persons A and B can do a work in 60 days and 40 days respectively. They
started the work together but A left after some time and B finished the
remaining work in 10 days. After how many days A leave?
• [IBPS RRBS Office Asst. (Pre) 2021]
(a) 12 days (b) 15 days (c) 8 days (d) 18 days (e) None of these
Time and work
Ans- 18 days
• A, B and C can complete a work in 12, 20 and 15 days respectively. A and B
started the work and worked for 5 days. Find the time taken by C to complete
the remaining work. [IBPS RRBS Officer Scale-1 (Pre) 2021]
(a) 4 days (b) 5 days (c) 6 days (d) 3 days (e) None of these
Time and work
Ans- 5 days
• A can finish a work in 20 days and B can finish the same work in 25 days.
They began together, but B left the work after 5 days. How many more days
will A take to finish the remaining work? [SSC CGL (Pre) 2020]
(a) 11 days (b) 8 days (c) 16 days (d) 21 days
Time and work
Ans- 11 days
• A and B can do a work in 12 days, B and C can do the same work
in 15 days, C and A can do the same work in 20 days. The time
taken by A, B and C to do the same work, is
(a) 5 days (b) 10 days (c) 15 days (d) 20 days
Time and work
Ans- 5 days
• A and B can do a work in 8 days, B and C can do the same work in
12 days. A, B and C together can finish it in 6 days. A and C
together will do it in
(a) 4 days (b) 6 days (c) 8 days (d) 12 days
Time and work
Ans- 8 days
• A and B can do a piece of work in 10 days. B and C can do it in 12
days and C and A in 15 days. In how many days will C finish it
alone?
(a) 24 (b) 30 (c) 40 (d) 60
Time and work
Ans- 40 days
• A and B can do a piece of work in 12 days, B and C in 8 days and C
and A in 6 days. How long would B take to do the same work alone?
(a) 24 days (b) 32 days (c) 40 (d) 48 days
Time and work
Ans- 48 days
• A and B together can do a work in 12 days. B and C together do it
in 15 days. If A's efficiency is twice that of C, then the days
required for B alone to finish the work, is
(a) 60 (b) 30 (c) 20 (d) 15
Time and work
Ans- 20 days
• A and B can do a work in 12 days, B and C in 15 days and C and A in
20 days. If A, B and C work together, they will complete the work in
[RRB (ASM) 2012] (a) 5 days (b) 15 2/3 days (c) 10 days (d) 7 5/6days
Time and work
Ans- 5 days
• A and B together can complete a piece of work in 40 days, B and C
can do it in 60 days and C and A can do it in 30 days. A, B and C
together can complete half of the actual work in [SBI PO (Pre) 2021]
(a) 49/3 days (b) 10/3 days(c) 40/3 days (d) 20/3 days (e) 70/3 days
Time and work
Ans- 40/3
Time and work
• Efficiency and Time Relation concept
• A is thrice as good a workman as B and is, therefore able to
finish a piece of work in 60 days less than B. The time (in days)
in which they can do it working together, is
(a) 22 (b) 23 1/4 (c) 23 (d) 22 1/2
Time and work
Ans-22 1/2
• A can complete a piece of work in 12 days. E is 60% more
efficient than A. The number days, that B will take to complete the
same work, is
(a) 6 (b) 7 ½ (c) 8 (d)8 1/2
Ans- 7 1/2
Time and work
• Kamal can do a work in 15 days. Bimal is 50% more efficient
than Kamal. The number of days, Bimal will take to do the same
piece of work, is
(a)7 ½ (b) 10 (c) 12 (d) 14
Time and work
Ans- 10 days
• A does 20% less work than B. If A can complete a 7 1/2 hours, then
B can piece of work in hours, then B can do it in (S.S.C.2006)
(a) 5 hours (b) 5 1/2hours (c) 6 hours (d) 6 1/2hours
Ans- 6 hours
• A is 50% as efficient as B. C does half of the work done by A and
B together. If C alone does the work in 40 days, then A, B and C
together can do the work in:
(a) 13 1/3days (b) 15 days (c) 20 days (d) 30 days
Time and work
Ans- 13 1/3
• A is twice as good a workman as B. If they work together, they
can complete a job in 18 days. If A alone does the job, in how
many days he will complete the job?
(a) 27 days (b) 36 days (c) 40 days (d) 54 days
Time and work
Ans- 27 days
• A works twice as fast as B. If B can complete a work in 24 days
independently, the number of days in which A and B can together
finish the work is
(a) 12 days (b) 9 days (c) 8 days (d) 6 days (e) None of these
Time and work
Ans- 8 days
• X is 3 times as fast as Y and is able to complete the work in 40
days less than Y. Then, thetime in which they can complete the
work together, is
(a) 15 days (b) 10 days (c) 7 1/2 days (d) 5 days
Time and work
Ans- 15 days
𝑀1 × 𝐷1 × 𝑇1 × 𝑊2 = 𝑀2 × 𝐷2 × 𝑇2 × 𝑊1
• 20 workers working for 5 h per day complete a work in 10 days. If
25 workers are employed to work 10 h per day, what is the time
required to complete the work?
(a) 4 days (b) 5 days (c) 6 days (d) 8 days
Time and work
Ans- 4 days
• 12 men can do a piece of work in 24 days. How many days are
needed to complete the work, if 8 men do this work?
[IDBI PO 2010](a) 28 (b) 36 (c) 48 (d) 52 (e) None of these
Time and work
Ans- 36 days
• 15 men complete a work in 16 days. If 24 men are employed, then
the time required to complete that work will be [CDS 2014]
(a) 7 days (b) 8 days (c) 10 days (d) 12 days (e) Not
Time and work
Ans- 10 days
• 36 men can do a work in 32 days working 7 h per day, then the
number of men required to complete the same work in 24 days
working 6 h per day, is [SSC (FC) 2012)
(a) 64 (b) 56 (c) 49 (d) 27
Ans- 56
Time and work
• 90 men are engaged to do a piece of work in 40 days but it is found
that in 25 days, 2/3 work is completed. How many men should be
allowed to go off, so that the work may be finished in time?
[SSC (10+2) 2008] (a) 10 (b) 15 (c) 20 (d) 25 (e) Not
Time and work
Ans- 15
• A contract is to be completed in 92 days and 234 men were set to
work, each working 16 h per day. After 66 days, 4/7 of the work is
completed. How many additional men may be employed, so that the
work may be completed in time, each man now working 18 h per day?
(a) 162 (b) 234 (c) 262 (d) 81 (e) None of these
Time and work
Ans- 162
• A contract is to be completed in 50 days and 105 men were set to
work, each working 8 h per day. After 25 days, 2/5 th of the work is
finished. How many additional men be employed, so that the work
may be completed on time, each man now working 9 h per day?
[SNAP 2012] (a) 34 (b)36 (c) 35 (d) 37 (e) NOT.
Time and work
Ans- 35
• A contractor undertook to finish a certain work in 124 days and
employed 120 men. After 64 days, he found that he had already
done 2/3 of the work. How many men can be discharged now, so
that the work may finish in time ?
(a) 40 (b) 50 (c) 48 (d) 56 (e) NOT
Time and work
Ans- 56
• Seven men can complete a work, in 12 days. They started the
work and after 5 days, two men left. In how many days will the
work be completed by the remaining men?
(a) 5 (b) 6 (c) 7 (d) 8 (e) None of these
Ans- 10
Time and work
Thank U

More Related Content

Similar to Time and Work Concepts Explained

3rd time & work new_
3rd time & work new_3rd time & work new_
3rd time & work new_priya mega
 
Ethiopian Banking Questions with Answers.pdf
Ethiopian Banking Questions with Answers.pdfEthiopian Banking Questions with Answers.pdf
Ethiopian Banking Questions with Answers.pdfAsfawosen Dingama
 
Time and work questins FOR COMPETATIVE EXAMS
Time and work questins FOR COMPETATIVE EXAMS Time and work questins FOR COMPETATIVE EXAMS
Time and work questins FOR COMPETATIVE EXAMS Aradhana Kumari
 
Indiabix all math solution - learninghomebd
Indiabix all math solution - learninghomebdIndiabix all math solution - learninghomebd
Indiabix all math solution - learninghomebdLearningHomeBD.com
 
Aptitude_Day06.pptx
Aptitude_Day06.pptxAptitude_Day06.pptx
Aptitude_Day06.pptxvikiawsac
 
Aptitude time and work
Aptitude time and workAptitude time and work
Aptitude time and workMaria Yesudass
 
TIME AND WORK , TIME SPEED AND DISTANCE FOR CAT , MAT , MBA , BANKING EXAM , ...
TIME AND WORK , TIME SPEED AND DISTANCE FOR CAT , MAT , MBA , BANKING EXAM , ...TIME AND WORK , TIME SPEED AND DISTANCE FOR CAT , MAT , MBA , BANKING EXAM , ...
TIME AND WORK , TIME SPEED AND DISTANCE FOR CAT , MAT , MBA , BANKING EXAM , ...SOURAV DAS
 
Time and work session 1
Time and work session 1Time and work session 1
Time and work session 1George Prep
 
Banks and SSC Time and Work
Banks and SSC Time and WorkBanks and SSC Time and Work
Banks and SSC Time and WorkGeorge Prep
 

Similar to Time and Work Concepts Explained (20)

Time and work
Time and workTime and work
Time and work
 
3rd time & work new_
3rd time & work new_3rd time & work new_
3rd time & work new_
 
Time and work rbi
Time and work rbiTime and work rbi
Time and work rbi
 
Ethiopian Banking Questions with Answers.pdf
Ethiopian Banking Questions with Answers.pdfEthiopian Banking Questions with Answers.pdf
Ethiopian Banking Questions with Answers.pdf
 
Time and work questins FOR COMPETATIVE EXAMS
Time and work questins FOR COMPETATIVE EXAMS Time and work questins FOR COMPETATIVE EXAMS
Time and work questins FOR COMPETATIVE EXAMS
 
TRW
TRWTRW
TRW
 
Qa01 time and work
Qa01 time and workQa01 time and work
Qa01 time and work
 
maths set-01.pptx
maths set-01.pptxmaths set-01.pptx
maths set-01.pptx
 
Indiabix all math solution - learninghomebd
Indiabix all math solution - learninghomebdIndiabix all math solution - learninghomebd
Indiabix all math solution - learninghomebd
 
Doc
DocDoc
Doc
 
3. Workbook.pdf
3. Workbook.pdf3. Workbook.pdf
3. Workbook.pdf
 
Aptitude_Day06.pptx
Aptitude_Day06.pptxAptitude_Day06.pptx
Aptitude_Day06.pptx
 
Aptitude time and work
Aptitude time and workAptitude time and work
Aptitude time and work
 
Time and work ea #2
Time and work  ea #2Time and work  ea #2
Time and work ea #2
 
Time and work standard level
Time and work standard levelTime and work standard level
Time and work standard level
 
TIME AND WORK , TIME SPEED AND DISTANCE FOR CAT , MAT , MBA , BANKING EXAM , ...
TIME AND WORK , TIME SPEED AND DISTANCE FOR CAT , MAT , MBA , BANKING EXAM , ...TIME AND WORK , TIME SPEED AND DISTANCE FOR CAT , MAT , MBA , BANKING EXAM , ...
TIME AND WORK , TIME SPEED AND DISTANCE FOR CAT , MAT , MBA , BANKING EXAM , ...
 
Time and work session 1
Time and work session 1Time and work session 1
Time and work session 1
 
Banks and SSC Time and Work
Banks and SSC Time and WorkBanks and SSC Time and Work
Banks and SSC Time and Work
 
Timeandwork
TimeandworkTimeandwork
Timeandwork
 
Time and work
Time and workTime and work
Time and work
 

More from MRUNALSHETHIYA1

Presentation Templates to work on Presentation
Presentation Templates to work on PresentationPresentation Templates to work on Presentation
Presentation Templates to work on PresentationMRUNALSHETHIYA1
 
Presentation on OUR ENVIRONMENT Lecture
Presentation on  OUR ENVIRONMENT LecturePresentation on  OUR ENVIRONMENT Lecture
Presentation on OUR ENVIRONMENT LectureMRUNALSHETHIYA1
 
HRM- unit 1 Bcom IT/BM shivaji university.docx
HRM- unit 1 Bcom IT/BM shivaji university.docxHRM- unit 1 Bcom IT/BM shivaji university.docx
HRM- unit 1 Bcom IT/BM shivaji university.docxMRUNALSHETHIYA1
 

More from MRUNALSHETHIYA1 (7)

Presentation Templates to work on Presentation
Presentation Templates to work on PresentationPresentation Templates to work on Presentation
Presentation Templates to work on Presentation
 
Presentation on OUR ENVIRONMENT Lecture
Presentation on  OUR ENVIRONMENT LecturePresentation on  OUR ENVIRONMENT Lecture
Presentation on OUR ENVIRONMENT Lecture
 
Presentation3.pptx
Presentation3.pptxPresentation3.pptx
Presentation3.pptx
 
HRM- unit 1 Bcom IT/BM shivaji university.docx
HRM- unit 1 Bcom IT/BM shivaji university.docxHRM- unit 1 Bcom IT/BM shivaji university.docx
HRM- unit 1 Bcom IT/BM shivaji university.docx
 
Adjectives notes
Adjectives notesAdjectives notes
Adjectives notes
 
Exercises on nouns
Exercises on nounsExercises on nouns
Exercises on nouns
 
Grammar Topic Nouns
Grammar Topic NounsGrammar Topic Nouns
Grammar Topic Nouns
 

Recently uploaded

_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting DataJhengPantaleon
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsKarinaGenton
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application ) Sakshi Ghasle
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfakmcokerachita
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationnomboosow
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introductionMaksud Ahmed
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17Celine George
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesFatimaKhan178732
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docxPoojaSen20
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsanshu789521
 

Recently uploaded (20)

_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its Characteristics
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application )
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdf
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communication
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and Actinides
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docx
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha elections
 

Time and Work Concepts Explained

  • 1. Time and work Presented by Assistant Professor Santosh Vishwnath Amande. MSc (Maths) SET Trainer of mathematics and reasoning DGCC, Satara Lecture 1 – Togethar work or Simultaneous work And Alternate day working
  • 2. Time and work 1 5 • If ‘A’ can do a work in ‘x’ days then ‘A’s one day work is 1 𝑥 1 5 1 1 5 Sachin complete a work in 5 days then his one day work is 1 5 1 5 1 5 1 5
  • 3. Time and work • If A’s 1 day work = 1 𝑥 then A can finish the work in ‘x’ days 8 7 6 5 4 3 2 1 Sohan complete a wall in 8 days after 3 days remaining work
  • 4. Time and work • Relation between time and work
  • 5. Time and work A complete work in 10 days B complete work in 15 days If they working together how many days will they take to complete the work • Concept of together working and simultaneous working
  • 6. Time and work • A can complete a work in 20 days and B can do the same work in 30 days , then time taken to complete the work Ans- 12 days
  • 7. Time and work • A and B working together can finish a piece of work in 12 days while B alone can finish it in 30 days . In how many days can A alone finish the work Ans- 20
  • 8. Time and work • A completes 1/3 part of the work in 5 days while B complete 2/5 part of the same work in 10 days . In how many days will they complete doing the work together? (a) 7 3 4 (b) 9 3 8 (c) 8 4 5 (d) 10 days 1 2 3 Ans- 9 3 days
  • 9. Time and work • A can do a piece of work in 4 days and B can complete the same work in 12 days. What is the number of days required to do the same work together? (a) 2 (b) 3 (c) 4 (d) 5 Ans- 3 days
  • 10. Time and work • Ayesha can complete a piece of work in 16 days. Amita can complete the same piece of work in 8 days. If both of them work together in how many days can they complete the same piece of work? (a) 4 2/5 (b) 5 1/3 days (c) 6 days (d) 12 days (e) None of these Ans- 5 1/3 days
  • 11. Time and work • A and B together can complete a particular task in 8 days. If B alone can complete the same task in 10 days, how many days will A take to complete the task if he works alone? • (a) 28 (b) 36 (c) 40 (d) 32 (e) None of these Ans- 40 days
  • 12. Time and work • A can finish a work in 18 days and B can do the same work in half of time taken by A then working together what part of the same work they can finish in a day (a) 1/6 (b) 1/9 (c) 2/5 (d) 2/7 Ans- 1/6 days
  • 13. Time and work Time and work • A and B together can do a piece of work in 6 days. If A can alone do the work in 18 days, then the number of days required for B to finish the work is (a) 12 (b) 9 (c) 15 (d) 10 (e) None of these Ans- 9 days
  • 14. • If A and B together can complete a piece of work in 15 days and B alone in 20 days, in how many days can A alone complete the work? (a) 60 (b) 45 (c) 40 (d) 30 (e) None of these Time and work Ans- 60 days
  • 15. • A, B and C can do a job working alone in 12, 16 and 24 days respectively. In how many days they can do the job, if they worked together? (a) 16/3 (b) 15/4 (c) 17/3 (d) 19/4 Time and work Ans- 16/3 days
  • 16. Time and work • A, B and C can complete a work in 2 h. If A does the job alone in 6 h and B in 5 h, then how long will it take for C to finish the job alone? (a) 5 1/2 h (b) 7 ½ h (c) 9 h (d) h 4 1/2 Ans- 7 1/2 days
  • 17. Time and work • Reena, Aastha and Shloka can independently complete a piece of work in 6 hours, 4 hours and 12 hours respectively. If they work together, how much time will they take to complete that piece of work? (a) 4 (b) 3 (c) 2 (d) 1 (e) None of these Ans- 2 days
  • 18. • A, B and C together can do a work in 6 days. A alone can do it in 12 days while B alone can do it in 18 days, then time taken by C is (a) 9 days (b) 18 days (C) 27 days (d) 36 days Time and work Ans- 36 days
  • 19. • A, B and C can complete a work in 2 h. If A does the job alone in 6 h and B in 5 h, then how long will it take for C to finish the job alone? (a) 5 1/2 h (b) 7 1/2 h (c) 9 h (d)4 1/2 h Time and work Ans- 7 1/2 days
  • 20. Time and work • Alternate working concept
  • 21. • A and B working separately can do a piece of work in 9 and 15 days, respectively. If they work for a day alternately, with B beginning, then the work will be completed in (a) 10 days (b) 11 2/5 days (c) 12 days(d) 13 Time and work Ans- 11 2/5 days
  • 22. • A and B can complete a piece of work in 12 and 18 days respectively. A begins to do the work and they work alternatively one at a time for one day each. The whole work will be completed in (a) 14 1/3days (b)15 2/3 days (c) 16 1/3days (d) 18 2/3 days Time and work Ans- 14 1/3 days
  • 23. • A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day? (a) 12 days (b) 15 days (c) 16 days (d) 18 days Time and work Ans-
  • 24. Time and work • A can do a work in 20 days and B can do in 10 days. A starts the work and works alone for 5 days. Then, B joins A and they finish the work. In how many days the work gets finished? (a) 10 (b) 12 (c) 9 (d) 8 Ans- 10 days
  • 25. Time and work • A can do a piece of work in 10 days, while B can do it in 6 days. B worked at it for 4 days. How long will A take to finish the remaining work? (a) 3 1/3days (b) 3 2/3 days (c) 3 2/5 days (d) 3 5/7 days (e) NoT Ans- 3 1/3 days
  • 26. Time and work • A and B can do a work in 18 and 24 days, respectively. They worked together for 8 days and then A left. The remaining work was finished by B in (a) 5 days (b) 5 1/3 days (c) 8 days (d) 10 days. Ans- 5 1/3 days
  • 27. Time and work • A can complete a piece of work in 18 days, B in 20 days and C in 30 days. B and C together start the work and are forced. to leave after 2 days. The time taken by A alone to complete the remaining work is (a) 10 days (b) 12 days (c) 15 days (d) 16 days Ans- 15 days
  • 28. Time and work • A can do a piece of work in 15 days, which B can do in 10 days. B worked at it for 8 days. A can finish the remaining work in (a) 2 days (b) 3 days (c) 5 days (d) 10 days Ans- 3 days
  • 29. Time and work • A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is: (a) ¼ (b) 1/10 (c) 7/15 (d) 8/15 Ans- 8/15 days
  • 30. Time and work • A and B can complete a work in 18 days and 15 days respectively. They started doing the work together but after 3 days A had to leave and B alone completed the remaining work. The whole work was completed in (a) 9 3/4 (b) 10 1/4 (c) 12 ¾ days (d) 12 1/2 Ans- 12 1/2 days
  • 31. Time and work • A, B and C can separately do a work in 12, 15 and 20 days respectively. They started to work together but C left after 2 days. The remaining work will be finished in (R.R.B., 2006) (a) 4 days (b) 5 days (c) 6 days (d) 15 days Ans- 4 days
  • 32. Time and work • A and B can do a piece of work in 30 days, while B and C can do the same work in 24 days and C and A in 20 days. They all work together for 10 days when B and C leave. How many days more will A take to finish the work? (a) 18 days (b) 24 days (c) 30 days (d) 36 days Ans- 18 days
  • 33. Time and work • A, B and C together can complete a piece of work in 10 days. All the three started working at it together and after 4 days A left. Then B and C together completed the work in 10 more days. A alone could complete the work in: (a) 15 days (b) 16 days (c) 25 days (d) 50 days Ans- 25 days
  • 34. Time and work • A can complete a work in 20 days and B in 30 days. A worked alone for 4 days and then B completed the remaining work along with C in 18 days. In how many days can C working alone complete the work? (a) 12 (b) 68 (c) 72 (d) 90 Ans- 90 days
  • 35. Time and work • A and B can complete a work in 8 days, working together. B alone can do it in 12 days. After working for 4 days, B left the work. How many days will A take to complete the remaining work? (a) 16 (b) 18 (c) 20 (d) 22 Ans- 16 days
  • 36. Time and work • A mason can build a tank in 12 h. After working for 6 h, he took the help of a boy and finished the work in another 5 h. The time that the boy will take alone to complete the work is (a) 30 h (b) 45 h (c) 60 h (d) 64 h Ans- 60h
  • 37. • A and B can do a piece of work in 24 and 30 days respectively. Both started the work and worked for 6 days. Then B leaves the work and C joins and the remaining work is completed by A and C together in 11 days. Find the days in which C alone can do the work (a) 80 (b) 100 (c) 120 (d) 130 (e) None of these Time and work Ans- 120 days
  • 38. • A, B and C can alone complete a work in 10, 12 and 15 days respectively. A and C started the work and after working for 4 days, A left and B joined. In how many days the total work was completed (a) 6 5/9 (b) 6 2/9 days (c) 6 days(d) 5 4/9 days (e)NoT Time and work Ans- 6 2/9 days
  • 39. • Two persons A and B can do a work in 60 days and 40 days respectively. They started the work together but A left after some time and B finished the remaining work in 10 days. After how many days A leave? • [IBPS RRBS Office Asst. (Pre) 2021] (a) 12 days (b) 15 days (c) 8 days (d) 18 days (e) None of these Time and work Ans- 18 days
  • 40. • A, B and C can complete a work in 12, 20 and 15 days respectively. A and B started the work and worked for 5 days. Find the time taken by C to complete the remaining work. [IBPS RRBS Officer Scale-1 (Pre) 2021] (a) 4 days (b) 5 days (c) 6 days (d) 3 days (e) None of these Time and work Ans- 5 days
  • 41. • A can finish a work in 20 days and B can finish the same work in 25 days. They began together, but B left the work after 5 days. How many more days will A take to finish the remaining work? [SSC CGL (Pre) 2020] (a) 11 days (b) 8 days (c) 16 days (d) 21 days Time and work Ans- 11 days
  • 42. • A and B can do a work in 12 days, B and C can do the same work in 15 days, C and A can do the same work in 20 days. The time taken by A, B and C to do the same work, is (a) 5 days (b) 10 days (c) 15 days (d) 20 days Time and work Ans- 5 days
  • 43. • A and B can do a work in 8 days, B and C can do the same work in 12 days. A, B and C together can finish it in 6 days. A and C together will do it in (a) 4 days (b) 6 days (c) 8 days (d) 12 days Time and work Ans- 8 days
  • 44. • A and B can do a piece of work in 10 days. B and C can do it in 12 days and C and A in 15 days. In how many days will C finish it alone? (a) 24 (b) 30 (c) 40 (d) 60 Time and work Ans- 40 days
  • 45. • A and B can do a piece of work in 12 days, B and C in 8 days and C and A in 6 days. How long would B take to do the same work alone? (a) 24 days (b) 32 days (c) 40 (d) 48 days Time and work Ans- 48 days
  • 46. • A and B together can do a work in 12 days. B and C together do it in 15 days. If A's efficiency is twice that of C, then the days required for B alone to finish the work, is (a) 60 (b) 30 (c) 20 (d) 15 Time and work Ans- 20 days
  • 47. • A and B can do a work in 12 days, B and C in 15 days and C and A in 20 days. If A, B and C work together, they will complete the work in [RRB (ASM) 2012] (a) 5 days (b) 15 2/3 days (c) 10 days (d) 7 5/6days Time and work Ans- 5 days
  • 48. • A and B together can complete a piece of work in 40 days, B and C can do it in 60 days and C and A can do it in 30 days. A, B and C together can complete half of the actual work in [SBI PO (Pre) 2021] (a) 49/3 days (b) 10/3 days(c) 40/3 days (d) 20/3 days (e) 70/3 days Time and work Ans- 40/3
  • 49. Time and work • Efficiency and Time Relation concept
  • 50. • A is thrice as good a workman as B and is, therefore able to finish a piece of work in 60 days less than B. The time (in days) in which they can do it working together, is (a) 22 (b) 23 1/4 (c) 23 (d) 22 1/2 Time and work Ans-22 1/2
  • 51. • A can complete a piece of work in 12 days. E is 60% more efficient than A. The number days, that B will take to complete the same work, is (a) 6 (b) 7 ½ (c) 8 (d)8 1/2 Ans- 7 1/2 Time and work
  • 52. • Kamal can do a work in 15 days. Bimal is 50% more efficient than Kamal. The number of days, Bimal will take to do the same piece of work, is (a)7 ½ (b) 10 (c) 12 (d) 14 Time and work Ans- 10 days
  • 53. • A does 20% less work than B. If A can complete a 7 1/2 hours, then B can piece of work in hours, then B can do it in (S.S.C.2006) (a) 5 hours (b) 5 1/2hours (c) 6 hours (d) 6 1/2hours Ans- 6 hours
  • 54. • A is 50% as efficient as B. C does half of the work done by A and B together. If C alone does the work in 40 days, then A, B and C together can do the work in: (a) 13 1/3days (b) 15 days (c) 20 days (d) 30 days Time and work Ans- 13 1/3
  • 55. • A is twice as good a workman as B. If they work together, they can complete a job in 18 days. If A alone does the job, in how many days he will complete the job? (a) 27 days (b) 36 days (c) 40 days (d) 54 days Time and work Ans- 27 days
  • 56. • A works twice as fast as B. If B can complete a work in 24 days independently, the number of days in which A and B can together finish the work is (a) 12 days (b) 9 days (c) 8 days (d) 6 days (e) None of these Time and work Ans- 8 days
  • 57. • X is 3 times as fast as Y and is able to complete the work in 40 days less than Y. Then, thetime in which they can complete the work together, is (a) 15 days (b) 10 days (c) 7 1/2 days (d) 5 days Time and work Ans- 15 days
  • 58. 𝑀1 × 𝐷1 × 𝑇1 × 𝑊2 = 𝑀2 × 𝐷2 × 𝑇2 × 𝑊1
  • 59. • 20 workers working for 5 h per day complete a work in 10 days. If 25 workers are employed to work 10 h per day, what is the time required to complete the work? (a) 4 days (b) 5 days (c) 6 days (d) 8 days Time and work Ans- 4 days
  • 60. • 12 men can do a piece of work in 24 days. How many days are needed to complete the work, if 8 men do this work? [IDBI PO 2010](a) 28 (b) 36 (c) 48 (d) 52 (e) None of these Time and work Ans- 36 days
  • 61. • 15 men complete a work in 16 days. If 24 men are employed, then the time required to complete that work will be [CDS 2014] (a) 7 days (b) 8 days (c) 10 days (d) 12 days (e) Not Time and work Ans- 10 days
  • 62. • 36 men can do a work in 32 days working 7 h per day, then the number of men required to complete the same work in 24 days working 6 h per day, is [SSC (FC) 2012) (a) 64 (b) 56 (c) 49 (d) 27 Ans- 56 Time and work
  • 63. • 90 men are engaged to do a piece of work in 40 days but it is found that in 25 days, 2/3 work is completed. How many men should be allowed to go off, so that the work may be finished in time? [SSC (10+2) 2008] (a) 10 (b) 15 (c) 20 (d) 25 (e) Not Time and work Ans- 15
  • 64. • A contract is to be completed in 92 days and 234 men were set to work, each working 16 h per day. After 66 days, 4/7 of the work is completed. How many additional men may be employed, so that the work may be completed in time, each man now working 18 h per day? (a) 162 (b) 234 (c) 262 (d) 81 (e) None of these Time and work Ans- 162
  • 65. • A contract is to be completed in 50 days and 105 men were set to work, each working 8 h per day. After 25 days, 2/5 th of the work is finished. How many additional men be employed, so that the work may be completed on time, each man now working 9 h per day? [SNAP 2012] (a) 34 (b)36 (c) 35 (d) 37 (e) NOT. Time and work Ans- 35
  • 66. • A contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 2/3 of the work. How many men can be discharged now, so that the work may finish in time ? (a) 40 (b) 50 (c) 48 (d) 56 (e) NOT Time and work Ans- 56
  • 67. • Seven men can complete a work, in 12 days. They started the work and after 5 days, two men left. In how many days will the work be completed by the remaining men? (a) 5 (b) 6 (c) 7 (d) 8 (e) None of these Ans- 10