SlideShare a Scribd company logo
Resume of
SABER AL MUALLEM
Construction Project Engineer/
Electrical & Instrument Engineer
P.O Box 599 Safwa 31921 Kingdom of Saudi Arabia
Mobile: +966 54 332 3755 / Home: +966 13 664 0825 or +966 13 664 7271
E-mail saber.muallem@gmail.com
Education & Training
• BS of Applied Electrical Engineering – Year 1992 to 1997
King Fahad University of Petroleum & Minerals, Dhahran Saudi Arabia
 Power & control course were my favorite elective courses.
• Complete three courses in I/A series system – June-July 2000
Foxboro Training Institute, Jubail Saudi Arabia
 They are Introduction to Configuration, Integrated Process Control and Foxbatch Application.
• Completed two courses on the technical training in Quality & Process of epoxy resin November-
December 1998
Ciba Specialty Chemicals Performance Polymers, USA
 They are Introduction to Configuration, Integrated Process Control and Foxbatch Application.
• Aramco, E-learning – Year 2002 to present
Saudi Aramco Corporate E-Learning, Kingdom Saudi Arabia
 Enrolled on different online courses as a self-development
Experience Starting from January 1998 up to December 2015
Aramco Projects June 2002 to December 2015
Starting from June 2002 up to now, I have been working in different projects at Saudi Aramco. My main
duty/assignments is Instruments & Control construction up to commissioning. Also I was one of the MCC &
PAC Champion. In addition to that at the beginning of each project and in the early work usually I was assigned
to manage the construction of different buildings especially those accommodates the process control system,
electrical early work and follow up structure steel material as well as erection.
Below are the projects that I have been working on starting from the latest: (Note for any personal reference
refer to the end of this CV for each BI)
1. BI 10-00302 Wasit program, NGL package.
2. BI 10-00302 914 Wasit Program, Permanent communication project
3. BI 10-00041 Hawiyah Gas Plant Expansion
4. BI 10-00038 Hawiyah Gas Plant PCS Replacement Project
5. BI 10-00096 Upgrade RO plant at Barri Gas Plant
6. BI 10-03218 Cogeneration Interconnection Facility JGP & RTR
7. BI 10-03182 Cogeneration at Barri Gas Plant
8. BI 10-03150 Barri NGL
9. BI 10-03022 Qatif Facility- Pipe line
1of 3
10. BI 10-0 Haradh Manifold Facility
Project Engineer
SNC LAVALIN Arabia, Al-Khobar Saudi Arabia - February 2011 to December 2015
• Working on WASIT project for NGL & Permanent communication projects
• Participate on the detail design of the permanent communication, especially the design of the DC
System.
• Supervise the construction of process & substation building up to the equipment installation & testing.
• Manage the activity on filed like the transformer installation, cable tray installation, and cable pulling
and instrumentation activity.
• Structure Steel erection supervision was one of the activities added to my knowledge as PE.
Project Engineer
JACOBS Delta Catalytic Arabia LTD, Al-Khobar Saudi Arabia – August 2007 to February 2011
• Lead the replacement contract project to replace HGP PCS through construction, commissioning and
closing the MCC
• Mange the construction activity of the instrument and the PCS of the HGP expansion project
• Champion of the all of the PCS MCC’s of the expansion project.
• Supervise and lead the MCC of process interface building construction.
• Close out the project and get the PAC certificate signed by proponent.
Site Superintendent
Al Hugayet Contracting Est., Dammam Saudi Arabia – March 2004 to July 2007
Worked as Engineer Ш at Saudi Aramco project management team CTS (Contracting Technical Support) in the
BGP, JGP, RTR, UGP & SGP Cogeneration Projects. Reverse Osmosis project at BGP. Through the life of
the projects my responsibility includes:
• Reviewing the detailed design package.
• Expedite & insure the material delivery within time.
• Supervise the site construction activities to confirm it is compliance with Aramco standard &
international standards as well.
• Manage the electrical, instrument & control activities
• Arrange the vendors visit to the site from the construction up to commissioning period.
Instrument Engineer
SAUDI ARABIA COPRA, Al-Khobar Saudi Arabia – March – October 2003
Assigned at Saudi Aramco Berri Gas Plant under Project Management Team (PMT) as a Project Management
Consultant (PMC) senior instrument which includes the following tasks:
• Supervise the Pre- commissioning of the instrumentation, which is done by S.A.Kent ‘contract of
electrical & instrumentation
• Clear the items of the Master Punch Items.
• Get through the fallowing control systems:
1. Tristation 1131, which is an integrated tool for developing, testing & documenting & critical
process control application for Tricon programmable logic controllers ( PLC ) used in the
Emergency shutdown system ESD.
2of 3
2. Honeywell DCS, TDC 3000 Data acquisition & control device for industrial process applications.
3. Compressor control system (CCS) using series 4 controller, manufactured by the Compressor
controls corporation (CCC).
4. Bently Nevada 3500 Monitoring & protection of the rotating machines.
Electrical/ Instrument Engineer
Suderohbau Saudi Ltd. (SRB), Dammam Saudi Arabia – June 2002 to March 2003
• SRB is a contract company working for almost twenty years in KSA in the electrical & oil projects.
• Supervise the engineering design and the construction of the Qatif Downstream project for The Saudi
Oil Co. ARAMCO.
• Supervise the construction in the site of Harad project for ARAMCO.
• Well known about ARAMCO standards as well as other like SECECO.
Electrical/ Instrument & DCS Engineer
Arabian Chemical Industrials Co. (JANA), Dammam Saudi Arabia – September 1998 to June 2002
• JANA producing the epoxy resin Liquid, Solution & Solid grades.
• Take care of all electrical equipment in the plant including switchgear, motors, transformers etc.
• Do the instrument jobs for the almost kind of smart technology instrument in the plant such as the level,
pressure, and temperature transmitters as well as the control valves.
• Develop & modify the programs in the DCS (operation control system by FOXBORO). Create new
batch process for new grade of product. Was in call duty for any trouble in the DCS.
• Trained by FOBBORO on I/A Series System.
• Supervise the commissioning of the plant and during the construction stage.
• Trainee the new operators during the commissioning of the plant.
• Get the experience of the chemical & mechanical engineering sense through the meeting & negotiating
with the engineers within or out of the company.
Electrical/ Instrument & DCS Engineer
Al-Hujailan Consultants Office, Al-Khobar Saudi Arabia – January to August 1998
• The office designs projects from the first level up to the end for government and privets projects.
• Do lot of jobs -according to the standard- to Saudi Oil Company ARAMCO.
• Learn the basic of the design and implement the Microstation software in the design.
Trainee, Electrical Engineer
Saudi Iron & Steel Co. (HADEED), Jubail Industrial City, Saudi Arabia February to August 1998
• Cooperative Training Program for Applied Electrical Engineer, for seven month.
• Have trained in the Central Maintenance Department CSD & on the Maine Electrical Control Room.
• Do the maintenance of the circuit breakers, induction & DC motors.
• In the control said get to know the PLC with the ladder program, relays, limit switch. .etc application in
the control system.
• Weekly reporting to the Coop advisor for any cared activity & at the end of the program I have being
evaluated by the company supervisors and wrote the coop report at the end of the program.
3of 3
Background
1. Grew up in Safwa
2. Honest and hard worker
3. Good in communication skills (English)
4. Group leader
5. Enjoy fishing, diving, car mechanics, and outdoor camping.
Personal references
1. BI 10-0914 & 302 Wasit Gas Program (Permanent Communication)
• Abdulaziz A Ghamdi Sr. Project Manager abdulaziz.ghamdi.9@aramco.com
• Said A. Garwan, Sr. Project Manager (said.garwan@aramco.com)
• Turky J. Yami, Sr. Project Engineer (turki.yami@aramco.com)
• Fahad Abdulhafeez, Project Manager (fahad.abdulhafeez@aramco.com)
2. BI 10-00041 Hawiyah Gas Plant Expansion
• Said A. Garwan, Sr. Project Manager (said.garwan@aramco.com)
• Nezar Khalifah, Sr. Project Engineer, (nezar.khalifah@aramco.com)
• Ahmed A. Awaji, Sr. Project Engineer, (ahmed.awaji@aramco.com)
• Abdallah Utaibi, Lead Project Engineer, (abdallah.utaibi.1@aramco.com)
3. BI 10-00038 Hawiyah Gas Plant PCS Replacement Project
• Said A. Garwan, Sr. Project Manager (said.garwan@aramco.com)
• Abdallah Utaibi, Lead Project Engineer, (abdallah.utaibi.1@aramco.com)
4. BI 10-00096 Upgrade RO plant at Barri Gas Plant
• Faisal Hajjar, Project Manager, (faisal.hajjar@aramco.com)
• Abd Ghani Rumaih, Lead Engineer (RTR), (abdghani.rumaih@aramco.com)
5. BI 10-03218 Cogeneration Interconnection Facility JGP & RTR
• Abdulrauf Rassol, Lead Project Engineer.(abdulrauf.abdrabrasool@aramco.com)
• Mohammed Ajaji, Lead Project Engineer, (mohmmed.ajaji@aramco.com)
6. BI 10-03182 Cogeneration at Barri Gas Plant
• Majed Harthi, Project Manager, (majed.harthi@aramco.com)
7. BI 10-03150 Barri NGL
• Ali Sadeg, Sr. Project Manager, (ali.sadeg@aramcoservices.com)
• Hassan Mansour, Project Manager, (hassan.mansour.1@aramco.com)
• Hassan Mubarak, Project Manager, (hasan.mubarak@aramco.com)
• Ahmed Ghamdi, Lead Engineer (BGP), (ahmed.ghamdi.77@aramco.com)
8. BI 10-03022 Qatif Facility- Pipe line
• Hayef Khaldi, (hayef.khaldi@aramcoservices.com)
9. BI 10-0 Haradh Manifold Facility
• Ali Sadge, Sr. Project Manager, (ali.sadeg@aramcoservices.com)
4of 3

More Related Content

What's hot

Final pla presentation
Final pla presentationFinal pla presentation
Final pla presentationdanish143
 
ELECTRICAL SUPERVISOR CURRICULUM VITAE
ELECTRICAL SUPERVISOR CURRICULUM VITAEELECTRICAL SUPERVISOR CURRICULUM VITAE
ELECTRICAL SUPERVISOR CURRICULUM VITAEsekar palani
 
CV - MEP Inspector Engineer Froilan Ramos Balanao
CV -  MEP Inspector Engineer  Froilan Ramos BalanaoCV -  MEP Inspector Engineer  Froilan Ramos Balanao
CV - MEP Inspector Engineer Froilan Ramos BalanaoFroilan Balanao
 
MEP Supervisor
MEP SupervisorMEP Supervisor
MEP SupervisorArun Arun
 
SULTAN CV 2016 MAY
SULTAN CV 2016 MAYSULTAN CV 2016 MAY
SULTAN CV 2016 MAYsultan said
 
Rama nand yadav cv
Rama nand yadav   cvRama nand yadav   cv
Rama nand yadav cv
Rama Nand Yadav
 
Electrical QA QC Engineer
Electrical QA QC EngineerElectrical QA QC Engineer
Electrical QA QC EngineerSalman Faris
 
mubashir Electrical engineer
mubashir Electrical engineermubashir Electrical engineer
mubashir Electrical engineerMubashir ahmee
 
design electrical engineer cv
design electrical engineer cvdesign electrical engineer cv
design electrical engineer cv
saryhasabadly
 
QA/AC SUPERVISOR ELECTRICAL & INSTRUMENT
QA/AC SUPERVISOR ELECTRICAL & INSTRUMENTQA/AC SUPERVISOR ELECTRICAL & INSTRUMENT
QA/AC SUPERVISOR ELECTRICAL & INSTRUMENT
muhammad jamil
 
aslam Doc. controller cv.doc
aslam Doc. controller cv.docaslam Doc. controller cv.doc
aslam Doc. controller cv.docMohd. Aslam
 
CV of Ronnel T. Domingo - Electrical Engineer
CV of Ronnel T. Domingo - Electrical EngineerCV of Ronnel T. Domingo - Electrical Engineer
CV of Ronnel T. Domingo - Electrical EngineerRONNEL DOMINGO
 
CV Muhammed Salahuddeen, Fire Protection Engineer
CV Muhammed Salahuddeen, Fire Protection EngineerCV Muhammed Salahuddeen, Fire Protection Engineer
CV Muhammed Salahuddeen, Fire Protection EngineerMuhammed Salahuddeen
 
CV-Engineering Manager-Lead Electrical Eng_RFSIASAT
CV-Engineering Manager-Lead Electrical Eng_RFSIASATCV-Engineering Manager-Lead Electrical Eng_RFSIASAT
CV-Engineering Manager-Lead Electrical Eng_RFSIASATRommel Siasat
 
CV NGUYEN HUU THUC - ELECTRICAL & INSTRUMENT ENGINEER
CV NGUYEN HUU THUC - ELECTRICAL & INSTRUMENT ENGINEERCV NGUYEN HUU THUC - ELECTRICAL & INSTRUMENT ENGINEER
CV NGUYEN HUU THUC - ELECTRICAL & INSTRUMENT ENGINEERNguyen Thuc
 
Harish_QA_QC_Engineer_resume
Harish_QA_QC_Engineer_resumeHarish_QA_QC_Engineer_resume
Harish_QA_QC_Engineer_resumeHarish G
 

What's hot (20)

Final pla presentation
Final pla presentationFinal pla presentation
Final pla presentation
 
Rabeesh CV 2014
Rabeesh CV  2014Rabeesh CV  2014
Rabeesh CV 2014
 
Instrumentation Engineer
Instrumentation EngineerInstrumentation Engineer
Instrumentation Engineer
 
ELECTRICAL SUPERVISOR CURRICULUM VITAE
ELECTRICAL SUPERVISOR CURRICULUM VITAEELECTRICAL SUPERVISOR CURRICULUM VITAE
ELECTRICAL SUPERVISOR CURRICULUM VITAE
 
CV - MEP Inspector Engineer Froilan Ramos Balanao
CV -  MEP Inspector Engineer  Froilan Ramos BalanaoCV -  MEP Inspector Engineer  Froilan Ramos Balanao
CV - MEP Inspector Engineer Froilan Ramos Balanao
 
MEP Supervisor
MEP SupervisorMEP Supervisor
MEP Supervisor
 
SULTAN CV 2016 MAY
SULTAN CV 2016 MAYSULTAN CV 2016 MAY
SULTAN CV 2016 MAY
 
Rama nand yadav cv
Rama nand yadav   cvRama nand yadav   cv
Rama nand yadav cv
 
Electrical QA QC Engineer
Electrical QA QC EngineerElectrical QA QC Engineer
Electrical QA QC Engineer
 
mubashir Electrical engineer
mubashir Electrical engineermubashir Electrical engineer
mubashir Electrical engineer
 
design electrical engineer cv
design electrical engineer cvdesign electrical engineer cv
design electrical engineer cv
 
QA/AC SUPERVISOR ELECTRICAL & INSTRUMENT
QA/AC SUPERVISOR ELECTRICAL & INSTRUMENTQA/AC SUPERVISOR ELECTRICAL & INSTRUMENT
QA/AC SUPERVISOR ELECTRICAL & INSTRUMENT
 
aslam Doc. controller cv.doc
aslam Doc. controller cv.docaslam Doc. controller cv.doc
aslam Doc. controller cv.doc
 
CV of Ronnel T. Domingo - Electrical Engineer
CV of Ronnel T. Domingo - Electrical EngineerCV of Ronnel T. Domingo - Electrical Engineer
CV of Ronnel T. Domingo - Electrical Engineer
 
CV Muhammed Salahuddeen, Fire Protection Engineer
CV Muhammed Salahuddeen, Fire Protection EngineerCV Muhammed Salahuddeen, Fire Protection Engineer
CV Muhammed Salahuddeen, Fire Protection Engineer
 
CV-Engineering Manager-Lead Electrical Eng_RFSIASAT
CV-Engineering Manager-Lead Electrical Eng_RFSIASATCV-Engineering Manager-Lead Electrical Eng_RFSIASAT
CV-Engineering Manager-Lead Electrical Eng_RFSIASAT
 
Asif CV
Asif CVAsif CV
Asif CV
 
DOCUMENT CONTROLLER CV
DOCUMENT CONTROLLER  CVDOCUMENT CONTROLLER  CV
DOCUMENT CONTROLLER CV
 
CV NGUYEN HUU THUC - ELECTRICAL & INSTRUMENT ENGINEER
CV NGUYEN HUU THUC - ELECTRICAL & INSTRUMENT ENGINEERCV NGUYEN HUU THUC - ELECTRICAL & INSTRUMENT ENGINEER
CV NGUYEN HUU THUC - ELECTRICAL & INSTRUMENT ENGINEER
 
Harish_QA_QC_Engineer_resume
Harish_QA_QC_Engineer_resumeHarish_QA_QC_Engineer_resume
Harish_QA_QC_Engineer_resume
 

Viewers also liked

Mohammed Aziz Megahed FINAL -1
Mohammed Aziz Megahed FINAL -1Mohammed Aziz Megahed FINAL -1
Mohammed Aziz Megahed FINAL -1Mohammed Aziz
 
Mahmoud attallah resume update
Mahmoud attallah resume   updateMahmoud attallah resume   update
Mahmoud attallah resume update
Mahmoud Attallah
 
SNC Lavalin Middle East
SNC Lavalin Middle East SNC Lavalin Middle East
SNC Lavalin Middle East
John Jeffers
 
3856 basem azzouz cv june-2016
3856 basem azzouz cv june-20163856 basem azzouz cv june-2016
3856 basem azzouz cv june-2016
basem ali
 
Eng. Hassan Ossama CV. 2016 New
Eng. Hassan Ossama CV. 2016 NewEng. Hassan Ossama CV. 2016 New
Eng. Hassan Ossama CV. 2016 NewHassan Ossama
 

Viewers also liked (8)

Mohamed ElGazzar Egypt
Mohamed ElGazzar EgyptMohamed ElGazzar Egypt
Mohamed ElGazzar Egypt
 
Mohammed Aziz Megahed FINAL -1
Mohammed Aziz Megahed FINAL -1Mohammed Aziz Megahed FINAL -1
Mohammed Aziz Megahed FINAL -1
 
Mahmoud attallah resume update
Mahmoud attallah resume   updateMahmoud attallah resume   update
Mahmoud attallah resume update
 
eto cv
eto cveto cv
eto cv
 
SNC Lavalin Middle East
SNC Lavalin Middle East SNC Lavalin Middle East
SNC Lavalin Middle East
 
Ahmad Abuzaid CV 1 Feb 2017
Ahmad Abuzaid CV 1 Feb 2017Ahmad Abuzaid CV 1 Feb 2017
Ahmad Abuzaid CV 1 Feb 2017
 
3856 basem azzouz cv june-2016
3856 basem azzouz cv june-20163856 basem azzouz cv june-2016
3856 basem azzouz cv june-2016
 
Eng. Hassan Ossama CV. 2016 New
Eng. Hassan Ossama CV. 2016 NewEng. Hassan Ossama CV. 2016 New
Eng. Hassan Ossama CV. 2016 New
 

Similar to SABER CV

Curriculum Vitae of R M Rico
Curriculum Vitae of R M RicoCurriculum Vitae of R M Rico
Curriculum Vitae of R M RicoRene Rico
 
C.V.Haider-2015 Last Final Augest-15
C.V.Haider-2015 Last  Final Augest-15C.V.Haider-2015 Last  Final Augest-15
C.V.Haider-2015 Last Final Augest-15Haider Braich
 
Saeed Fadl CV
Saeed Fadl CVSaeed Fadl CV
Saeed Fadl CVsaeed981
 
Saeed Fadl CV
Saeed Fadl CVSaeed Fadl CV
Saeed Fadl CVsaeed981
 
Anas Khalifa's CV_JAN.-2017
Anas Khalifa's CV_JAN.-2017Anas Khalifa's CV_JAN.-2017
Anas Khalifa's CV_JAN.-2017Anas Khalifa
 
Anas Khalifa's CV_JAN.-2017
Anas Khalifa's CV_JAN.-2017Anas Khalifa's CV_JAN.-2017
Anas Khalifa's CV_JAN.-2017Anas Khalifa
 
Cv mechanical supervisor
Cv mechanical supervisorCv mechanical supervisor
Cv mechanical supervisor
James Ct
 
Jasim_CV_-_2016_W_MEP
Jasim_CV_-_2016_W_MEPJasim_CV_-_2016_W_MEP
Jasim_CV_-_2016_W_MEPJasim MK
 
Mohamed kamal cv2018
Mohamed kamal cv2018Mohamed kamal cv2018
Mohamed kamal cv2018
MOHAMED KAMAL
 
Wael El Ahmadi 2016 - Sr. Construction Engineer - Mechanical -Cv
Wael El Ahmadi 2016 - Sr. Construction Engineer - Mechanical -CvWael El Ahmadi 2016 - Sr. Construction Engineer - Mechanical -Cv
Wael El Ahmadi 2016 - Sr. Construction Engineer - Mechanical -CvWael El Ahmadi
 
YOGESH ELECTRICAL ENGG
YOGESH ELECTRICAL ENGG YOGESH ELECTRICAL ENGG
YOGESH ELECTRICAL ENGG yogesh kumar
 
CV Ahmad Ezz QC Supervisor - Mech.& Welding
CV Ahmad Ezz QC Supervisor - Mech.& WeldingCV Ahmad Ezz QC Supervisor - Mech.& Welding
CV Ahmad Ezz QC Supervisor - Mech.& WeldingAboEzz77
 

Similar to SABER CV (20)

Abdelmagid Abdel Aziz
Abdelmagid Abdel AzizAbdelmagid Abdel Aziz
Abdelmagid Abdel Aziz
 
Curriculum Vitae of R M Rico
Curriculum Vitae of R M RicoCurriculum Vitae of R M Rico
Curriculum Vitae of R M Rico
 
C.V.Haider-2015 Last Final Augest-15
C.V.Haider-2015 Last  Final Augest-15C.V.Haider-2015 Last  Final Augest-15
C.V.Haider-2015 Last Final Augest-15
 
Saeed Fadl CV
Saeed Fadl CVSaeed Fadl CV
Saeed Fadl CV
 
Saeed Fadl CV
Saeed Fadl CVSaeed Fadl CV
Saeed Fadl CV
 
M SUBBA RAO CV latest
M SUBBA RAO CV latestM SUBBA RAO CV latest
M SUBBA RAO CV latest
 
Anas Khalifa's CV_JAN.-2017
Anas Khalifa's CV_JAN.-2017Anas Khalifa's CV_JAN.-2017
Anas Khalifa's CV_JAN.-2017
 
Anas Khalifa's CV_JAN.-2017
Anas Khalifa's CV_JAN.-2017Anas Khalifa's CV_JAN.-2017
Anas Khalifa's CV_JAN.-2017
 
Cv mechanical supervisor
Cv mechanical supervisorCv mechanical supervisor
Cv mechanical supervisor
 
MS CV May 2016
MS CV May 2016MS CV May 2016
MS CV May 2016
 
Jasim_CV_-_2016_W_MEP
Jasim_CV_-_2016_W_MEPJasim_CV_-_2016_W_MEP
Jasim_CV_-_2016_W_MEP
 
Ahmad Naser CV
Ahmad Naser CVAhmad Naser CV
Ahmad Naser CV
 
cv Rashid Tagelsir updated . -2016
cv Rashid Tagelsir   updated . -2016cv Rashid Tagelsir   updated . -2016
cv Rashid Tagelsir updated . -2016
 
RESUME-Sijin
RESUME-SijinRESUME-Sijin
RESUME-Sijin
 
Shakir CV
Shakir CV Shakir CV
Shakir CV
 
Mohamed kamal cv2018
Mohamed kamal cv2018Mohamed kamal cv2018
Mohamed kamal cv2018
 
Wael El Ahmadi 2016 - Sr. Construction Engineer - Mechanical -Cv
Wael El Ahmadi 2016 - Sr. Construction Engineer - Mechanical -CvWael El Ahmadi 2016 - Sr. Construction Engineer - Mechanical -Cv
Wael El Ahmadi 2016 - Sr. Construction Engineer - Mechanical -Cv
 
YOGESH ELECTRICAL ENGG
YOGESH ELECTRICAL ENGG YOGESH ELECTRICAL ENGG
YOGESH ELECTRICAL ENGG
 
Ahmed El- Kholy CV
Ahmed El- Kholy CVAhmed El- Kholy CV
Ahmed El- Kholy CV
 
CV Ahmad Ezz QC Supervisor - Mech.& Welding
CV Ahmad Ezz QC Supervisor - Mech.& WeldingCV Ahmad Ezz QC Supervisor - Mech.& Welding
CV Ahmad Ezz QC Supervisor - Mech.& Welding
 

SABER CV

  • 1. Resume of SABER AL MUALLEM Construction Project Engineer/ Electrical & Instrument Engineer P.O Box 599 Safwa 31921 Kingdom of Saudi Arabia Mobile: +966 54 332 3755 / Home: +966 13 664 0825 or +966 13 664 7271 E-mail saber.muallem@gmail.com Education & Training • BS of Applied Electrical Engineering – Year 1992 to 1997 King Fahad University of Petroleum & Minerals, Dhahran Saudi Arabia  Power & control course were my favorite elective courses. • Complete three courses in I/A series system – June-July 2000 Foxboro Training Institute, Jubail Saudi Arabia  They are Introduction to Configuration, Integrated Process Control and Foxbatch Application. • Completed two courses on the technical training in Quality & Process of epoxy resin November- December 1998 Ciba Specialty Chemicals Performance Polymers, USA  They are Introduction to Configuration, Integrated Process Control and Foxbatch Application. • Aramco, E-learning – Year 2002 to present Saudi Aramco Corporate E-Learning, Kingdom Saudi Arabia  Enrolled on different online courses as a self-development Experience Starting from January 1998 up to December 2015 Aramco Projects June 2002 to December 2015 Starting from June 2002 up to now, I have been working in different projects at Saudi Aramco. My main duty/assignments is Instruments & Control construction up to commissioning. Also I was one of the MCC & PAC Champion. In addition to that at the beginning of each project and in the early work usually I was assigned to manage the construction of different buildings especially those accommodates the process control system, electrical early work and follow up structure steel material as well as erection. Below are the projects that I have been working on starting from the latest: (Note for any personal reference refer to the end of this CV for each BI) 1. BI 10-00302 Wasit program, NGL package. 2. BI 10-00302 914 Wasit Program, Permanent communication project 3. BI 10-00041 Hawiyah Gas Plant Expansion 4. BI 10-00038 Hawiyah Gas Plant PCS Replacement Project 5. BI 10-00096 Upgrade RO plant at Barri Gas Plant 6. BI 10-03218 Cogeneration Interconnection Facility JGP & RTR 7. BI 10-03182 Cogeneration at Barri Gas Plant 8. BI 10-03150 Barri NGL 9. BI 10-03022 Qatif Facility- Pipe line 1of 3
  • 2. 10. BI 10-0 Haradh Manifold Facility Project Engineer SNC LAVALIN Arabia, Al-Khobar Saudi Arabia - February 2011 to December 2015 • Working on WASIT project for NGL & Permanent communication projects • Participate on the detail design of the permanent communication, especially the design of the DC System. • Supervise the construction of process & substation building up to the equipment installation & testing. • Manage the activity on filed like the transformer installation, cable tray installation, and cable pulling and instrumentation activity. • Structure Steel erection supervision was one of the activities added to my knowledge as PE. Project Engineer JACOBS Delta Catalytic Arabia LTD, Al-Khobar Saudi Arabia – August 2007 to February 2011 • Lead the replacement contract project to replace HGP PCS through construction, commissioning and closing the MCC • Mange the construction activity of the instrument and the PCS of the HGP expansion project • Champion of the all of the PCS MCC’s of the expansion project. • Supervise and lead the MCC of process interface building construction. • Close out the project and get the PAC certificate signed by proponent. Site Superintendent Al Hugayet Contracting Est., Dammam Saudi Arabia – March 2004 to July 2007 Worked as Engineer Ш at Saudi Aramco project management team CTS (Contracting Technical Support) in the BGP, JGP, RTR, UGP & SGP Cogeneration Projects. Reverse Osmosis project at BGP. Through the life of the projects my responsibility includes: • Reviewing the detailed design package. • Expedite & insure the material delivery within time. • Supervise the site construction activities to confirm it is compliance with Aramco standard & international standards as well. • Manage the electrical, instrument & control activities • Arrange the vendors visit to the site from the construction up to commissioning period. Instrument Engineer SAUDI ARABIA COPRA, Al-Khobar Saudi Arabia – March – October 2003 Assigned at Saudi Aramco Berri Gas Plant under Project Management Team (PMT) as a Project Management Consultant (PMC) senior instrument which includes the following tasks: • Supervise the Pre- commissioning of the instrumentation, which is done by S.A.Kent ‘contract of electrical & instrumentation • Clear the items of the Master Punch Items. • Get through the fallowing control systems: 1. Tristation 1131, which is an integrated tool for developing, testing & documenting & critical process control application for Tricon programmable logic controllers ( PLC ) used in the Emergency shutdown system ESD. 2of 3
  • 3. 2. Honeywell DCS, TDC 3000 Data acquisition & control device for industrial process applications. 3. Compressor control system (CCS) using series 4 controller, manufactured by the Compressor controls corporation (CCC). 4. Bently Nevada 3500 Monitoring & protection of the rotating machines. Electrical/ Instrument Engineer Suderohbau Saudi Ltd. (SRB), Dammam Saudi Arabia – June 2002 to March 2003 • SRB is a contract company working for almost twenty years in KSA in the electrical & oil projects. • Supervise the engineering design and the construction of the Qatif Downstream project for The Saudi Oil Co. ARAMCO. • Supervise the construction in the site of Harad project for ARAMCO. • Well known about ARAMCO standards as well as other like SECECO. Electrical/ Instrument & DCS Engineer Arabian Chemical Industrials Co. (JANA), Dammam Saudi Arabia – September 1998 to June 2002 • JANA producing the epoxy resin Liquid, Solution & Solid grades. • Take care of all electrical equipment in the plant including switchgear, motors, transformers etc. • Do the instrument jobs for the almost kind of smart technology instrument in the plant such as the level, pressure, and temperature transmitters as well as the control valves. • Develop & modify the programs in the DCS (operation control system by FOXBORO). Create new batch process for new grade of product. Was in call duty for any trouble in the DCS. • Trained by FOBBORO on I/A Series System. • Supervise the commissioning of the plant and during the construction stage. • Trainee the new operators during the commissioning of the plant. • Get the experience of the chemical & mechanical engineering sense through the meeting & negotiating with the engineers within or out of the company. Electrical/ Instrument & DCS Engineer Al-Hujailan Consultants Office, Al-Khobar Saudi Arabia – January to August 1998 • The office designs projects from the first level up to the end for government and privets projects. • Do lot of jobs -according to the standard- to Saudi Oil Company ARAMCO. • Learn the basic of the design and implement the Microstation software in the design. Trainee, Electrical Engineer Saudi Iron & Steel Co. (HADEED), Jubail Industrial City, Saudi Arabia February to August 1998 • Cooperative Training Program for Applied Electrical Engineer, for seven month. • Have trained in the Central Maintenance Department CSD & on the Maine Electrical Control Room. • Do the maintenance of the circuit breakers, induction & DC motors. • In the control said get to know the PLC with the ladder program, relays, limit switch. .etc application in the control system. • Weekly reporting to the Coop advisor for any cared activity & at the end of the program I have being evaluated by the company supervisors and wrote the coop report at the end of the program. 3of 3
  • 4. Background 1. Grew up in Safwa 2. Honest and hard worker 3. Good in communication skills (English) 4. Group leader 5. Enjoy fishing, diving, car mechanics, and outdoor camping. Personal references 1. BI 10-0914 & 302 Wasit Gas Program (Permanent Communication) • Abdulaziz A Ghamdi Sr. Project Manager abdulaziz.ghamdi.9@aramco.com • Said A. Garwan, Sr. Project Manager (said.garwan@aramco.com) • Turky J. Yami, Sr. Project Engineer (turki.yami@aramco.com) • Fahad Abdulhafeez, Project Manager (fahad.abdulhafeez@aramco.com) 2. BI 10-00041 Hawiyah Gas Plant Expansion • Said A. Garwan, Sr. Project Manager (said.garwan@aramco.com) • Nezar Khalifah, Sr. Project Engineer, (nezar.khalifah@aramco.com) • Ahmed A. Awaji, Sr. Project Engineer, (ahmed.awaji@aramco.com) • Abdallah Utaibi, Lead Project Engineer, (abdallah.utaibi.1@aramco.com) 3. BI 10-00038 Hawiyah Gas Plant PCS Replacement Project • Said A. Garwan, Sr. Project Manager (said.garwan@aramco.com) • Abdallah Utaibi, Lead Project Engineer, (abdallah.utaibi.1@aramco.com) 4. BI 10-00096 Upgrade RO plant at Barri Gas Plant • Faisal Hajjar, Project Manager, (faisal.hajjar@aramco.com) • Abd Ghani Rumaih, Lead Engineer (RTR), (abdghani.rumaih@aramco.com) 5. BI 10-03218 Cogeneration Interconnection Facility JGP & RTR • Abdulrauf Rassol, Lead Project Engineer.(abdulrauf.abdrabrasool@aramco.com) • Mohammed Ajaji, Lead Project Engineer, (mohmmed.ajaji@aramco.com) 6. BI 10-03182 Cogeneration at Barri Gas Plant • Majed Harthi, Project Manager, (majed.harthi@aramco.com) 7. BI 10-03150 Barri NGL • Ali Sadeg, Sr. Project Manager, (ali.sadeg@aramcoservices.com) • Hassan Mansour, Project Manager, (hassan.mansour.1@aramco.com) • Hassan Mubarak, Project Manager, (hasan.mubarak@aramco.com) • Ahmed Ghamdi, Lead Engineer (BGP), (ahmed.ghamdi.77@aramco.com) 8. BI 10-03022 Qatif Facility- Pipe line • Hayef Khaldi, (hayef.khaldi@aramcoservices.com) 9. BI 10-0 Haradh Manifold Facility • Ali Sadge, Sr. Project Manager, (ali.sadeg@aramcoservices.com) 4of 3