PROGRESS OF CIVIL & MECHANICAL PROJECTS OF C &ESS

Published in: Engineering, Business
  • Be the first to comment

  • Be the first to like this

Presentation 1

  1. 1. C&ESS DEPARTMENT CONTRACT WORKS EFP-I S No Name of Work Estimated Cost Press Advertisem ent date Date of Opening Work Done by Parties Target Completion Date Present StatusAFE Cost Lowest Cost 1 CONSTRUCTION OF FOUNDATION FOR REBOILER, CONDENSATE POTS & SOFTENING UNITS AT UCH#II, Distt: DheraBugti. 1.773 Million 22.08.2013 At 1130 hrs 30 days Work executed departmentally. Tender cancelled. 2 Construction of Pre- Drilling Engineering Works for Zin PAB-2 (Zin#06), Distt. Dera Bughti, Balochistan 51.738 Millions 27.10.201 3 11.11.2013 90 Days work is in progress. 3 CONSTRUCTION OF PRE DRILLING CIVIL WORK AT LOTI DEEP # 01. DISTRICT DERA BUGHTI, BALUCHISTAN. 59.624 Millions 04.02.201 4 21.02.2014 90 days LOI issued. Contract agreement execution stage 4 CONSTRUCTIONS OF PRE DRILLING CIVIL WORK AT WELL LOCATION ZIN SML #04. DISTRICT DERA BUGTI BALOCHISTAN 54.031 millions 31.05.201 4 16.06.2014 60 days After retender. Bid advertised & opened on 16.06.2014.
  2. 2. S No Name of Work Estimate d Cost Press Advertise ment date Date of Opening Work Done by Parties Target Completion Date Present StatusAFE Cost Lowest Cost 5 CONSTRUCTIONS OF PRE DRILLING CIVIL WORK AT LOTI WELL #19. DISTRICT DERA BUGHTI, BALUCHISTAN. 41.798 millions 04.04.201421.04.2014 60 days LOI issued on 03.06.2014 and contract agreement to be executed. 6 CONSTRUCTIONS OF PRE DRILLING CIVIL WORK AT WELL LOCATION PIRKO DEEP #01. DISTRICT DERA BUGTI BALOCHISTAN. 54.406 millions 28.04.14 60 days LOI issued on 03.06.2014 and contract agreement to be executed. 7 CONSTRUCTIONS OF PRE DRILLING CIVIL WORK AT LOTI#20. DISTRICT DERA BUGT BALOCHISTAN 41.798 millions 31.05.201420.06.2014 60 days After retender. Bid advertised & opened on 20.06.2014. CONSTRUCTIONS OF PRE DRILLING CIVIL WORK AT WELL LOCATION PIRKO #54. DISTRICT DERA BUGTI 44.762 millions Press advertised on 23.04.2014.open ed on 7.5.14 and is under management
  3. 3. C&ESS DEPARTMENT CONTRACT WORKS EFP-II S No Name of Work Estimate d Cost Press Advertise ment date Date of Opening Work Done by Parties Target Completio n Date Present StatusAFE Cost Lowest Cost 1 Engineering works for Sohniwala Well # 1 at Tehsil Ahmedpur Distt. Jhang Rs.16 million 23.03.201 3 07.04.20 13 30 day Completed 2 Construction of Metalled Road, Boundary Wall & cement Concrete Stone Paving- additional works for Annxe at Regional Office Multan, District:Muzzafar Gahr. 2.64 M 03.09.201 3 2/10/20 13 30 days Work Completed. 3 CONSTRUCTION OF PRE DRILLING CIVIL WORK AT KUP-I (KULCHAS E.L).DISTT: DERA BUGTI BALOCHISTAN 55 Million 31.08.201 3 16.09.20 13 45 days Work is in Progress. Watch Towers, culverts and cause under progress.
  4. 4. C&ESS DEPARTMENT CONTRACT WORKS EFP-III S No Name of Work Estimated Cost Press Advertisem ent date Date of Opening Work Done by Parties Target Completion Date Present StatusAFE Cost Lowest Cost 1 Engineering works for Jand well # 1 Distt. Attock Rs.20 millions 24.03.2013 09.04.2013 28.05.2013 Completed 2 Construction Of One R.C.C Underground Water Reservior At Water Source Near Mela #1 Water Point.Distt:Kohat 3.742 M 21.08.2013 06-09-2013 At 1130 hrs 90 days Completed. 3 Construction of Pre Drilling Engineering Works At Rajian-8 District Chakwal Punjab 27 M 15.07.2013 15.08.2013 45 days Completed. 4 Supply of Utility Water (170,000 liters per day) to Nashpa Oil Plant and Camps including Rig N-2 at Nashpa Field 14.10 M 27.07.2013 22.08.2013 365 days Work in progress 5 Construction of Pre Drilling Engineering Works AT NASHPA-5 District Karak KPK Rs:116.65 millions 04.02.14 45 days Work in progress
  5. 5. S No Name of Work Estimat ed Cost Press Advertis ement date Date of Opening Work Done by Parties Target Completion Date Present StatusAFE Cost Lowest Cost 6 Construction of internal road at chanda plant, Distt: Kohat KPK. 3.364 Millions 01.11.20 13 18.11.201 3 45 Days Work in progress 7 Modification in new store shed at Dakhni Plant Well. 1.948 Millions 02.09.20 13 26-09- 2013 60 days Completed 8 Construction of Engineering Works Required For Workover Job At Rajian#2 District. 20.193 Millions 03.09.20 13 16.09.13 30 Days Completed. 9 CONSTRUCTION OF FOUNDATION FOR INSTALLATION OF WEIGH BRIDGE NASHPA OIL FIELD 0.931 M 30.08.20 13 19.09.201 3 45 days Completed. REPAIR OF (0.8KMS) ROAD AT RATTA MOHRA RAJIAN OIL FIELD, DISTRICT 2.232 14.12.20 30.12.201
  6. 6. S No Name of Work Estimated Cost Press Advertisem ent date Date of Opening Work Done by Parties Target Completion Date Present StatusAFE Cost Lowest Cost 11 CONSTRACTION OF RCC WALL (LENGTH 816.RM) AT NASHPA PLANT. DISTT:KARAK 14.387 Million 23.11.2013 10.12.201 3 60 days 60 % Completed. Suspended due to land problem 12 CONSTRACTION OF FOUNDATION FOR INSTALLATION OF WEIGH BRIDGE AT RAJIAN OIL FIELD. DISTRICT ATTOCK. 1.5 MILLION 09.01.2014 27.01.201 4 45 days 80 % Completed. 13 CONSTRUCTION OF DYKE WALL AND P. C.C HARD STANDING FOR MELA CRUDE STORAGE TANK DISST:KOHAT, KPK. 1.854 Million 13.11.2013 28.11.201 3 45 days Work completed. Final bill payment is under process. 14 Construction of Engineering Works Required For Workover Job At Mela#1 District.Kohat KPK 25 Million 05.12.2013 21.12.201 3 30 days Well started flowing and tender was annulled after approval for award of work. Construction of Permanent Wire Woven Mesh Fencing at Nashpa#1 2.18 07.04.201 Work order issued on 15.05.14. work in
  7. 7. S No Name of Work Estimated Cost Press Advertise ment date Date of Opening Work Done by Parties Target Completio n Date Present StatusAFE Cost Lowest Cost 16 Construction of Permanent Wire Woven Mesh Fencing at Nashpa #4 Well.Distt:Karak 2.62 Million 22.03.20 14 07.04.2 014 30 days Work order issued on 15.05.14. work in progress. 17 CONSTRUCTION OF ENGINEERING WORKS REQUIRED FOR WORKOVER JOB AT CHAK NAURANG SOUTH # 1.DISTRICT CHAKWAL 12.23 Million 11.01.20 14 23.01.2 013 30 days Completed. 18 CONSTRUCTION OF UNDER GROUND WATER STORAGE TANK AT CHANDA PLANT DISST:KOHAT, KPK. 6.988 Million 09.01.20 14 28.01.2 014 45 days Tender will be opened on 25-05- 2014 at EFP-III. Under management approval. 19 Construction of Pre Drilling Engineering Works at Nashpa -6 District: karak, KPK Rs:30.12 millions 30 DAYS Case for contractor scope of work is being initiated for press advertisement from management.
  8. 8. S No Name of Work Estimate d Cost Press Advertisemen t date Date of Opening Work Done by Parties Target Completion Date Present StatusAFE Cost Lowest Cost 20 HIRING OF DOZERS (D-8K/D- 8N/KOMATTSU 155, MODEL 2000 & ABOVE) FOR NASHPA-6 WELL, DISTRICT KARAK, KPK. Rs: 2.00 million 3 months Case approved by management and LOI to be issued. 21 CONSTRUCTIONS OF PRE DRILLING CIVIL WORK AT DAKHNI DEEP WELL NO. 5 DISTRICT ATTOCK. 40.00 millions 03.04.2014 18.04.2014 45 days Work order issued on 25.05.2014. problem in land acquisition. 22 CONSTRUCTION OF R.C.C HARD STANDING FOR INSTALLATION OF 20000 BPD CAPACITY NEW SEPARATION BATTERY AT NASHPA District: Karak, KPK Rs:2.855 millions 05.04.2014 24.04.2014 45 days Work order issued on _______ and work is under progress.
  9. 9. C&ESS DEPARTMENT CONTRACT WORKS EFP-IV S No Name of Work Estimated Cost Press Advertise ment date Date of Opening Work Done by Parties Target Completion Date Present StatusAFE Cost Lowest Cost 1 Engineering works for Qadirpur HRL well # 7 Distt. Ghotki Sindh Rs.18.00 millions 02.04.201 3 18.04.20 13 240 days after award Completed 2 Engineering works for Maru East Well # 1 at Distt. Ghotki Sindh Rs.36.31 millions 30.04.201 3 15.05.20 13 45 days after award Completed. 3 Engineering works for Qadirpur Well # 50 at Distt. Ghotki Sindh Rs.34.66 millions 05.06.201 3 20.06.20 13 30 days Completed 4 Construction of Pre- Drilling Engineering Works at QP-51 District Ghotki, Sindh. 30 Millions 07.09.201 3 30.09.20 13 30 days Completed 5 Construction of Pre- Drilling Engineering Works at HRL #08 District Ghotki, Sindh. 25 Millions 27.10.201 3 12.11.20 13 30 days Completed
  10. 10. S No Name of Work Estimated Cost Press Advertisem ent date Work Done by Parties Date of Opening Target Completio n Date Present StatusAFE Cost Lowest Cost 6 Construction of Pre-Drilling Engineering Works at QP-52 District Ghotki, Sindh. 35.693 Millions 07.09.2013 07.10.2013 30 days Completed. 7 CONSTRUCTION OF CIVIL SYSTEM AT ERW PLATFORM (QP-42,43,44) FOR SCADA SYSTEM. DISTRICT GHOTKI, SINDH. 1.645 Million 17.11.2013 04.12.2013 30 days Completed 8 Construction of Pre Drilling Engineering Works at Well Location Sara West Well # 05.District Ghotk Rs.63.153 millions 60 days bids will be opened on 13.06.2014 agaist retendering. 9 Construction of Pre Drilling Engineering Works at Well Location, Reti # 02. District Ghotki. Rs.42.44 millions 08.03.2014 26.03.2014 45 days LOI issued on 30.05.14. 10 Construction of Pre Drilling Engineering Works at Qdir Pur Well # 53. . District Ghotki. Rs.25.727 millions 03.04.2014 21.04.2014 30 days Work order issued on 30.05.2014 and work in progress. 11 REPAIR / MAINTENANCE OF QADIRPUR INTERNAL ROAD.DISTRICT : GHOTKI, SINDH Rs 14.231 millions 24.05.2014 09.06.2014 90 DAYS case sent on 10.06.2014 for management approval by EFP- IV.
  11. 11. C&ESS DEPARTMENT CONTRACT WORKS EFP-V S No Name of Work Estimated Cost Press Advertisem ent date Date of Opening Work Done by Parties Target Completio n Date Present StatusAFE Cost Lowest Cost 1 Engineering works for Jakhro West Well # 1 at Distt. Sanghar Sindh Rs.25.00 millions 20.04.2013 06.05.201 3 120 days Completed 2 CONSTRUCTION OF PRE DRILLING CIVIL WORKS AT WELL KUNNAR DEEP#09.Distt: Hyderabad. 23.00 M 24.07.2013 13.08.201 3 45 days Complted. 3 CONSTRUCTION OF PRE DRILLING CIVIL WORK AT WELL CHAK DIM5#3. 32.00 M 24.07.2013 13.08.201 3 30 days Completed 4 Construction of Pre Drilling Engineering Works AT CHAK 25C- 1, District Sanghar, Sindh. 32 Millions 13.08.2013 30.08.201 3 30 Days Completed 5 Construction of Pre- Drilling Engineering works at Manna-1 (Tay X-2), Distt. Hyderabad, Sindh. 24 Millions 29.08.2013 13.09.201 3 45 Days Completed
  12. 12. S No Name of Work Estimated Cost Press Advertisem ent date Date of Opening Work Done By Parties Target Completio n Date Present StatusAFE Cost Lowest Cost 6 CONSTRUTION OF 550RFT LONG RCC SLUB CULVERT OVER BOBI & SINJORO PLANTS PIPE LINES DISTRICT SANGHAR SINDH. 3.645 Million 45 Days Tender cancelled before Press Advertisement 7 CONSTRUCTION OF WORK OVER JOB CIVI WORKS AT CHAK 66 NORTH EAST # 01, DISTRICT SHANGHER. 12.124 million 07.12.203 23.12.201 3 30 days Work order issued ______. 90 % Completed. Waiting for rig. 8 Construction of Pre Drilling Engineering Works at Goth Patafi Well # 01 (Hanif Siddiqui # 1 District Hyderabad Rs.22.270 millions 21.12.2013 07.01.201 4 30 days Completed 9 Construction of Pre Drilling Engineering Works at Pasaki Deep Well # 04 District Hyderabad Rs.23.050 millions 21.12.2013 09.01.201 4 30 days Completed
  13. 13. S No Name of Work Estimate d Cost Press Advertise ment date Date of Opening Work Done By Parties Target Completi on Date Present StatusAFE Cost Lowest Cost 10 CONSTRUCTIONS OF PRE DRILLING CIVIL WORK AT WELL LOCATION SOUTH EAST X -01. (Pali Deep # 1) DISTRICT TANDO ALAHYAR, SINDH. 42.913 millions 27.03.201 4 11.04.20 14 45 days LOI issued on 02.06.2014. 11 CONSTRUCTION OF PRE DRILLING CIVIL WORK AT WELL LOCATION, SAAND #02 DISTT: TANDO ALLAH YAR. 39.446 12.03.201 4 26.03.14 45 days. Work order issued on _______ work in progress. 12 CONSTRUCTION OF PRE DRILLING CIVIL WORK AT WELL LOCATION,KUNNER #09 DISTRICT : HYDERABAD., SINDH RS.31.205 15.05.201 4 30.05.20 14 30 days Bids opened on 30.05.2014 and is under management approval.
  14. 14. C&ESS DEPARTMENT CONTRACT WORKS FGCP-I S No Name of Work Estimated Cost Press Advertise ment date Date of Opening Work Done By Parties Target Completion Date Present StatusAFE Cost Lowest Cost 1 Hiring Services for Pipeline Construction work for Uch-II Development Project Rs.68.826 millions 15.03.201 3 30.03.20 13 17.06.2013 (60 days) Completed 2 Civil & Mechanical Works for Installation of Well Head Assembilies and Flow Line for 09 wells at Uch Gas Field, Near Dera Murad Jamali, Distt. Bughti, Balochistan. 160 Millions 19.08.201 3 04.09.20 13 180 Days 55% work copmleted. 3 Electrical and Instrumentation Works for Well Head Facilities for 15 wells at Uch Gas Field, Near Dera Murad Jamali, Distt. Bughti, Balochistan. 80 Millions 19.08.201 3 04.09.20 13 90 Days Work order is to be used.
  15. 15. C&ESS DEPARTMENT CONTRACT WORKS FGCP-I S No Name of Work Estimate d Cost Press Advertis ement date Date of Opening Work Done By Parties Target Completion Date Present StatusAFE Cost Lowest Cost 1 Hiring Services for Pipeline Construction work for Uch-II Development Project Rs.68.82 6 millions 15.03.20 13 30.03.2013 17.06.2013 (60 days) Completed 2 Civil & Mechanical Works for Installation of Well Head Assembilies and Flow Line for 09 wells at Uch Gas Field, Near Dera Murad Jamali, Distt. Bughti, Balochistan. 160 Millions 19.08.20 13 04.09.2013 180 Days 55% work copmleted. 3 Electrical and Instrumentation Works for Well Head Facilities for 15 wells at Uch Gas Field, Near Dera Murad Jamali, Distt. Bughti, Balochistan. 80 Millions 19.08.20 13 04.09.2013 90 Days Work order is to be used.
  16. 16. C&ESS DEPARTMENT CONTRACT WORKS HEAD OFFICE S No Name of Work Estimate d Cost Press Advertise ment date Date of Opening Work Done By Parties Target Completio n Date Present Status AFE Cost Lowest Cost 1 Construction of Admin building, warehouses & security office building (Contract C- 1), near Kunnar Oil Field Distt. Hyderabad Sindh Rs.66.70 millions 08.09.201 3 08.10.2013 240 days Management approval accorded and LOI issued by SCM department on 28.05.2014 . 2 Construction of workshop offices, MPE&I workshop, safety & Firefighting Building (Contract C- 2), Laboratory near Kunnar Oil Field Distt. Hyderabad Sindh Rs.48.40 millions 08.09.201 3 08.10.2013 240 days Contract Agreement Execution Stage. 3 Construction of Officer's Houses (C-1) at Sinjhoro Plant Distt. Sanghar Sindh Rs.89.61 9 millions 22.3.2014 26.03.2014 240 days Case deferred by Procurement Committee. Caravan as alternate option suggested by PC. 4 Construction of Assistant's Houses (C- II) at Sinjhoro Plant Distt. Sanghar Sindh Rs.63.00 millions 11.05.201 3 27.06.2013 240 days Case deferred by Procurement Committee. Caravan as alternate option suggested by PC.
  17. 17. S No Name of Work Estimated Cost Press Advertis ement date Date of Opening Work Done By Parties Target Completion Date Present Status AFE Cost Lowest Cost 5 Construction of Officer's Houses (C- 1) at Uch Gas Field for Uch-II Rs.87.00 millions 08.09.2 013 09.10.20 13 365 days Annulled and Case for Caravans to be processed by Admin Deptt. 6 Construction of Boundary wall at Jhal Magsi Distt. Mera Murad Jamali Rs.28.00 millions 08.08.2 013 10.09.20 13 120 days Word order issued on 08.04.2014 and contractor is to mobilize yet. 7 Construction of Officer's House & Infrastructure Works at Tando Alam Sindh Rs.75.00 millions 28.07.2 013 28.08.20 12 21.07.2013 (365 days) Annulled and Case for Caravans to be processed by Admin Deptt. 8 Construction of Govt. Rural Dispensary (Social Welfare Scheme), Village Dhayala, Teh. Dina, Distt. Jhelum, Punjab. Rs.4.765 M 06.06.2 0113 10.07.20 13 240 days Work under construction. 9 Construction of Waste Pit & Skimmer Tank at Kal Oil Field Distt. Chakwal Rs.3.898 millions 06.06.2 013 08.07.20 13 60 days Work order issued on 14.03.2014. Work under construction.
  18. 18. S No Name of Work Estimat ed Cost Press Adverti sement date Date of Opening Work Done By Parties Target Compl etion Date Present Status AFE Cost Lowest Cost 10 Construction of Assistant's Houses (C-2) at Uch Gas Field Uch-II Rs.87.00 millions 06.06.2 013 09.07.201 3 365 days Annulled and Case for Caravans to be processed by Admin Deptt. 11 Construction of Worker's Houses (C- 3) at Uch Gas Field Uch-II Rs.87.00 millions 06.06.2 013 09.07.201 3 365 days Annulled and Case for Caravans to be processed by Admin Deptt. 12 Up-gradation of Pasaki Facility Road from Hyderabad to Mirpur Khas main Road to new constructed Kunnar Plant Road Rs.59.00 millions 06.06.2 013 04.07.201 3 180 days Work order issued on 03.06.2014 Work is under construction. 13 Construction of Foundation for Dehydration Plant at Bobi Rs.4.22 millions 06.06.2 013 04.07.201 3 30 days Work order issued on 10.03.2014 and work is under construction. 14 Renovation of OGTI Hostel I-9 Islamabad Rs.1.986 millions 27.07.2 013 30-08- 2013 60 days After obtaining expenditure approval from ED(Petroserv) case submitted to SCM deptt on 28.01.2014 for further processing.
  19. 19. S No Name of Work Estimate d Cost Press Advertis ement date Date of Opening Work Done By Parties Target Completio n Date Present Status AFE Cost Lowest Cost 15 Construction of PCC courtyard & fixing of Fiber Glass shed at Masjid Chanda Plant Rs.1.26 millions 28.07.20 13 27.08.2013 60 days Sent for annullment on 14.03.14 due to expiry of bid validity. 16 Construction of Prefabricated worker houses at Sinjhoro (C- 3) using SCIP Rs.84.00 millions 28.07.20 13 27.082013 240 days Case deferred by Procurement Committee. Caravan as alternate option suggested by PC. 17 Construction of Offices & other allied building at Bahu Well-2 Rs.10.03 millions 15.10.20 13 21.11.2013 240 days Deffered by Procurement Committee due low production life of Bahu. 18 Construction of new workshop shed at Dakhni Plant Rs.15.51 millions 15.10.20 13 25.11.2013 240 days Financial Evaluation done and uploaded on 02.06.2014. 19 Construction of Hard standing bath/wash room & canteen for ATA at Qadirpur Rs.7.943 millions 15.10.20 13 28.11.2013 90 days annulled on 15.04.14 due to no participation by bidders. Fresh case is being prepared.
  20. 20. S No Name of Work Estimat ed Cost Press Advertise ment date Date of Openin g Work Done By Parties Target Completio n Date Present Status AFE Cost Lowest Cost 20 Repair of Road from Sohbatpur to Uch Plant Rs.16.3 66 millions 28.07.2013 28.08.2 013 At 1130 hrs 90 days Work order issued on _______. Work is under construction. 21 Extension of Police Check Post (changla wall Maue Dariya) Near well No 3 at Dakhni field 1.663 M 15.10.2013 18.11.2 013 60 days Contract Agreement prepared and submitted to SCM on 13.04.2014. 22 CONSTRUCTION OF REGIONAL COORDINATOR PRE FAB STRUCTURE OFFIC I/C SEWRAGE SYSTEM.DISTT: HYDERABAD. 8.103 M 240 days Pended. 23 Costruction of 12 rooms & 27 bathrooms at Qadir Pur Gas Field. Distt:Ghotki Sindh. 10.86 M 08.08.2013 09.09.2 013 240 days Annulled on 28.04.14 and fresh case to be intiated for re-tendering. 24 Construction of Permanent Wire Woven Mesh Fencing at Nashpa #3 Well.Distt:Karak 1.532 M 08.09.2013 07.10.2 013 At 1130 hrs 30 days Annulled due to expiry of bid validity and case for approval through Field Tender is in process.
  21. 21. S No Name of Work Estimate d Cost Press Advertis ement date Date of Opening Work Done By Parties Target Comple tion Date Present Status AFE Cost Lowest Cost 25 Engineering Works for Bahu Wells #5,6,7 & 8 platform High Rising at Bahu Gas Field, Tehsil ahmad pur sial, Distt: Jhang. 209.713 M 08.09.20 13 07.10.2013 365 days Annulled on 11.04.14 due to expiry of bid validity and case is sent to user deptt to confirm if the requirement still exists. 26 Hiring of vehicles for Field Units of C&ESS department OGDCL, Islamabad 25.68 M 180 days Case file lost at SCM deptt and sent again on 12.05.14 to SCM deptt for press advertisement. 27 CONSTRUCTION OF FOUNDATION FOR REBOILER, CONDENSATE POTS & SOFTENING UNITS AT UCH#II, Distt: DheraBugti. 1.773 Million 22.08.2013 At 1130 hrs 30 days Work executed departmentally. Tender cancelled 28 CONSTRUCTION OF UNDER GROUND ROOM FOR HSD STORAGE TANK AT OGDCL HEAD OFFICE ISLAMABAD. 1.13 Millions 02.08.20 13 20.08.2013 30 Days Work order issued on 14.05.14 and contractor mobilized but change in site is under consideration. 29 Construction of RCC water pond at Nashpa 3.861 millions 15.10.20 13 27.11.2013 90 Days Contract Agreement prepared and submitted to SCM on
  22. 22. S No Name of Work Estimate d Cost Press Advertis ement date Date of Opening Work Done By Parties Target Comple tion Date Present Status AFE Cost Lowest Cost 30 Supply and fixing of geo membrane sheet 0.50 mm thick at effuluent water pits at Dakhni, Distt. Attock 10.856 Millions 15.10.2 013 22.11.2013 30 days Resubmitted to SCM Departement on 21.o5.2014for Retendering. 31 Construction of Civil Works for 09 Wells for Sinjhoro Gas field, Distt. Sanghar, Sindh. 12.542 Millions 15.10.2 013 20.11.2013 90 Days After obtaining expenditure approval from ED(Petroserv) case submitted to M(S & FA) for AFE No. 32 Construction of Internal Road at Nashpa Plant, Distt. Karak, KPK 4.138 millions 04.01.2 014 06.02.2014 45 Days Contract Agreement prepared and submitted to SCM on 13.04.2014. 33 Construction of Soldier Room, Toilet, Bath Kitchen For FC Post at Uch Dera Bugti Balochistan. 1.011 Millions 60 days Case returned to SCM on 22.05.2014 for retendering. 34 Hiring of Consultancy Services for Residential Camp at Nashpa Nil 30.09.2013 75 days.Case returned to SCM on 30.09.2013. with soft copy of TOR 35 Pre-qualification / enlistment of contractors for PDEWs Nil Nil Sent to GM (SCM) for on 25.11.2013.
  23. 23. S No Name of Work Estimate d Cost Press Advertis ement date Date of Opening Work Done By Parties Target Comple tion Date Present Status AFE Cost Lowest Cost 36 Construction of BMP Posts in Tribal area Ranjanpur, Distt: Ranjanpur. 2.564 Million 45 days Completed departmental. 37 CONSTRUCTION OF REPAIR OF ROAD FROM JAND TO CHOWK SHAHEEDAN 4.3 KM AT DAKHNI FIELD 27.11.2 013 26.12.2013 90 DAYS Case approved by Procurement Committee on 10.06.2014. 87 Construction of BMP Posts in Trible area Ranjanpur, Distt: Ranjanpur. Rs.2.564 60 days Completed through party resources. 39 CONSTRACTION/EXTE NSION IN EXISTING SOCIAL WELFARE DISPENSERY AT RAJIAN OIL FIELD, Punjab 0.965 Million 26.01.2 014 26.02.2014 30 days Financial Evaluation done and uploaded on 06.06.2014. 40 INSTALLATION OF UNDER GROUND POWER SUPPLY SYSTEM AT KOT SARANG Distt: 3.12 million 60 days Original case file lost. Bid documents prepared and approval is being sought again for execution.
  24. 24. S No Name of Work Estimate d Cost Press Advertis ement date Date of Opening Work Done By Parties Target Comple tion Date Present Status AFE Cost Lowest Cost 41 CONSTRUCTION OF SOCIAL WELFARE PUBLIC DOSPENSARY LPG PLANT AT BOBI OIL FIELD, DISTRICT SANGHAR SINDH. 12.983 Million 180 days BOQ prepared and bid documents are under preparation. 42 EXTENSION OF EXISTING SOCIA WELFARE DISPENSARY AT KUUNAR OIL FEILD. 5.4 Million 26.01.20 14 04.03.2014 180 days Technical Evaluation done on 12.05.14 and sent to SCM for Financial opening / annullment. 43 CONSTRUCTION OF PRODUCED WATER PIT, BOUNDARY WALL AND ALLIED CIVIL WORKS OUTSIDE CHANDA PLANT PREMISES. 15.429 Million 26.01.20 14 03.03.2014 120 days Retendered on 07.05.2014 and will be opened on 29.06.14. 44 Raising & Strengthening of OGDC Bund at Qadirpur Gas Field District Ghotki Province Sindh. 171 million 04.01.20 14 04.01.2014 120 days To be presented in P & FC for approval of award on 11.06.2014 45 CONSTRACTION OF 10 NO. NEW ROOMS IN WORKER CAMP AT LOGISTIC CAP 8.422 million 180 days Sent to SCM Deptt for Press Advertisement
  25. 25. S No Name of Work Estimate d Cost Press Advertis ement date Date of Opening Work Done By Parties Target Comple tion Date Present Status AFE Cost Lowest Cost 46 IMPROVEMENT OF WATER SUPPLY SCHEME IN THE AREA OF KAL OIL FIELD. DISTRICT CHAKWAL, PUNJAB Rs 0.65 millions 15.02.20 14 21.03.2014 30 days To be done departmentally on quotation basis within PPRA limits. 47 CONSTRUCTION OF OH WATER TANK AND CAR PARKING AT CHANDA PLANT. 5.267 Million 75 days Bid opened on 28.05.2014. Case awaited from SCM for Technical Evaluation. 48 CONSTRUCTION OF 02 NO.CLASS ROOMS WITH VERANDAH FOR GOVT.PRIMARY SCHOOL ALWARGI BANDA AT NASHPA . 1.125 Million 90 days Technical Evaluation done on 09.04.14 and sent to SCM for Financial opening. 49 CONSTRUCTION OF METALLED ROAD (45.657 Kms) FROM UCH PLANT TO UPL DERA MURAD JAMALI DISTRICT DERA BUGHTI, PROVINCE BALUCHISTAN. 868.27 million 22.02.20 14 24.03.2014 18 months Annulled due to poor response and case is being sent for press advertisement for retendering.
  26. 26. S No Name of Work Estimated Cost Press Advertis ement date Date of Opening Work Done By Parties Target Complet ion Date Present Status AFE Cost Lowest Cost 509 CONSTRUCTION OF REPAIR OF ROAD FROM TANDO MURREE TO TANDO ALAM # 15 BASE CAMP Rs 2.45 millions 26.01.20 14 28.02.2014 30 days Technical Evaluation done on 12.05.14 and sent to SCM for Financial opening. 51 Repair Maintenance of 01 km Road, Mohri Rajgan to Chak Tareda Under Social Welfare. Tehsil Sohawa. 1.297 Million 04.01.20 14 10.02.2014 45 days Financial Evaluation done and uploaded on 06.06.2014. 52 SUPPLY & INSTALLATION & COMMISSIONING OF DOUBLE GATE SYSTEM, HYDRAULIC ROAD BLOCKER & HYDRAULIC BARRIER AT NASHPA DISTRICT KARAK KPK. Rs 4.10 millions 27.02.20 14 03.04.2014 60 days Technical Evaluation done on 11.04.2014. letter to sent to bidder for withdrawal of exceptions / deviations. Financial opening awaited. 53 CONSTRUCTION OF 03 NOS PICKETS WITH ATTACH BATH, KITCHEN & TOILETS FOR PHASE-II FC PICKETS AT UCH-II GAS FIELD. DISTRICT DERA BUGTI BALUCHISTAN Rs 2.518 millions 45 days Financial Evaluation done on 13.05.14 and case is with SCM for further processing.
  27. 27. S No Name of Work Estimate d Cost Press Advertis ement date Date of Opening Work Done By Parties Target Completi on Date Present Status AFE Cost Lowest Cost 48 CONSTRACTION OF P.C.C HARD STANDING FOR STOCK MATERIALS AT NASHPA DISTRICT KARAK,KPK. Rs 0.716 millions 26.01.2 014 27.02.201 4 30 days Expenditure approval obtianed and AFE No alloted on 13.05.14. Financial evaluation done and uploaded on web 30.05.14. 56 Construction Of Police Picket At Sinjhoro Plant Gate District Sanghar. Rs 1.602 millions 09.04.2 014 09.05.201 4 45 days Technical Evaluation done and Financial opening is on 16.06.2014. 54 Raising of Sales Gas ROW at Nashpa (1.5 km) Distric karak, kpk. Rs 4.45 millions 45 days Technical Evaluation done and uploaded on 09.06.2014. 51 EARTH FILLING, CONSTRUCTION OF ONE WAY ROAD AND PARKING SHED AT NASHPA PLANT. DISTT: KARAK, KPK Rs 19.106 millions 15.02.2 014 20.03.201 4 120 days Received for endorsement of Executive Summary on 11.06.2014. 55 CONSTRUCTION OF COMPUTER ROOM FOR WEIGHING BRIDGE AT NASHPA PLANT. DISTT: Rs 0.934 millions 60 days work in progress as an additional work through the same contractor for weigh bridge.
  28. 28. S No Name of Work Estimate d Cost Press Advertis ement date Date of Opening Work Done By Parties Target Comple tion Date Present Status AFE Cost Lowest Cost 56 CONSTRUCTION OF HARD STANDING FOUNDATION AREA OF LOGISTIC WORKSHOP AT LOGISTIC CAMP KOTSARANG.DIST: CHAKWAL, PUNJAB Rs 16.06 millions 22.02.20 14 25.03.2014 30 days Technical Evaluation done on 07.04.2014 and case sent to SCM for Financial Opening. 57 CONSTRUCTION OF WATER TANK FOR DRINKING PURPOSE FOR LOCALS AT TANDO ALAM OIL COMPLEX Rs 0.816 millions 09.04.20 14 08.05.2014 60 days Technical Evaluation done on 21.05.2014 and sent to SCM deptt for Financial Evaluation. 58 Feasibility Study Of Existing Ogdcl Office Building Office Building Masood Mansion At F-8 Markaz For Addition Of New Floors For Gymnasium And Design/Consultancy Services For The Improvement Measures And Proposed Gymnasium Thereof millions 16.04.20 14 16.05.2014 90 days Received on 28.05.14 for Technical Evaluation.
  29. 29. S No Name of Work Estimated Cost Press Adverti sement date Date of Openin g Work Done By Parties Target Comple tion Date Present Status AFE Cost Lowest Cost 59 CONSTRUCTION OF ROW 31.05 KM FOR JAKHRO WELL-1 DISTRIC: KHAIRPUR ,SINDH 30.953 million 45 days Press advertised.Bid will be opened on 23.06.2014. 60 CONSTRUCTION OF 02 NOS. PRODUCTION STORAGE SHED & HARD STANDING AT NASHPA PLANT. DISTT: KARAK, KPK 45.68 million 240 days Sent to PTO (Mech) on 06.06.14 for Budget allocation. 61 CONSTRUCTION OF CIVIL WORKS FOR FIELD DEVELOPMENT AT WELL LOCATION DACHRA PUR # 02 .DISTT: HYDERABAD, SINDH. 2.41 million 30 days Technical Evaluation done on 02.06.2014 and sent for Financial Opening. 62 REPAIR/MAINTENANCE OF ROAD FROM REHMAT GAS FIELD TURN TO ANWAR ABAD. DISTT: GHOTKI Rs 25.327 millions 60 days Sent to SCM Deptt on 08.05.14 for Press Advertisement. 63 CONSTRUCTION OF GEO- MEMBRANE LINING FOR PRODUCED WATER PIT AT QADIR PUR PLANT.. 2.445 million 30 days Bid documents are being prepared.
  30. 30. S No Name of Work Estimated Cost Press Advertis ement date Date of Opening Work Done By Parties Target Complet ion Date Present Status AFE Cost Lowest Cost 64 RAISING OF APPROACH ROAD AT QADIRPUR#35. DISTRICT : GHOTKI, SINDH 2.969 45 days Bid documents prepared. Budget allocated by QP JV and file received in (E.O) South Section on 05.05.14. Case is to be sent to SCM for press advertisement. 65 CONSTRUCTION OF RAISED PLATFORM AT HRL-2. DISTRICT GHOTKI, SINDH 27.56 million 90 days Press advertised. Bids will be opened on 24.06.2014. 66 CONSTRUCTION OF RAISED PLATFORM AT HRL-7. DISTRICT GHOTKI, SINDH 27.55 million 90 days Bid opened on 10.06.2014 and case awiated from SCM deptt for Technical Evaluation. 67 RAISING OF APPROACH ROAD AT QADIRPUR#48. DISTRICT : GHOTKI, SINDH 5.11 million 45 days Bid documents prepared. Budget allocated by QP JV and file received in (E.O) South Section on 05.05.14. Case is to be sent to SCM for press advertisement. 68 CONSTRUCTION OF ROAD FROM DISPENSARY TO WELL NO.6 (ABOUT 7 KM) AT DAKHNI PLANT WELL. DISTRICT: ATTOCK. 35.088 150 days Press advertised on 16.05.2014 and bids will opened on 25.06.2014.
  31. 31. S No Name of Work Estimated Cost Press Advertis ement date Date of Opening Work Done By Parties Target Complet ion Date Present Status AFE Cost Lowest Cost 69 CONSTRUCTION OF RAISED PLATFORM AT QADIRPUR#50. DISTRICT : GHOTKI, SINDH 27.56 million 45 days Bid documents prepared. Budget allocated by QP JV and file received in (E.O) South Section on 05.05.14. Case is to be sent to SCM for press advertisement. 70 CONSTRUCTION OF RAISED PLATFORM AT QADIRPUR#45. DISTRICT : GHOTKI, SINDH 27.56 45 days Bid documents prepared. Budget allocated by QP JV and file received in C&ESS on 06.05.14. Case is to be sent to SCM for press advertisement. 71 CONSTRUCTION OF RAISING OF APPROCH ROAD AT QADIRPUR#50. DISTRICT : GHOTKI, SINDH 3.39 million 45 days Bid documents prepared. Case is with (E.O)South Section for budget arrangement. 72 CONSTRUCTION OF RAISING OF APPROACH ROAD AT QADIRPUR#31. DISTRICT : GHOTKI, SINDH 6.10 million 45 days Bid documents prepared. File is with (E.O)South section and is being sent to JV Accounts for budget allocation.
  32. 32. S No Name of Work Estimated Cost Press Advert iseme nt date Date of Opening Work Done By Parties Target Complet ion Date Present Status AFE Cost Lowest Cost 73 CONSTRUCTION OF STORE SHED FROM RETERIEVED MATERIAL OF TOOT AT DAKHNI PLANT DISTRICT ATTOCK, PUNJAB. 4.56 million 90 days Bids opened on 06.06.2014 and case awaited from SCM deptt for Technical Evaluation. 74 CONSTRUCTION OF METTALED ROAD FROM BASIC HEALTH UNIT TO AYUB LAKHAN TO GOVERNAMENT HIGH SCHOOL AYUB LAKHAN. 1.337 million 60 days Sent to SCM Deptt on 22.05.14 for Press Advertisement. 75 CONSTRACTION OF RAISING OF APPROCH ROAD AT QADIRPUR#41. DISTRICT : GHOTKI, SINDH 4.18 million 45 days Bid documents prepared. File is with (E.O)South section and is being sent to JV Accounts for budget allocation. 76 Construction of Foundation and Dyke Walls for Crude Storage Tanks at Rajian Well # 05 1.25 05.05. 2014 02.06.2014 Bids opened on 02.06.2014 and case awaited from SCM deptt for Technical Evaluation. 77 CONSTRACTION OF RAISED PLAT FORM AT QADIRPUR#38/39. DISTRICT : GHOTKI, SINDH 37.67 million 45 days Confirmation of Budget allocation is in Process
  33. 33. S No Name of Work Estimate d Cost Press Advertis ement date Date of Opening Work Done By Parties Target Comple tion Date Present Status AFE Cost Lowest Cost 78 RAISING OF APPROACH ROAD AT QADIRPUR# 11. DISTRICT : GHOTKI, SINDH 1.55 million 45 days Confirmation of Buget allocation is in Process 79 RAISING OF APPROACH ROAD AT QADIRPUR DEEP#1 . DISTRICT : GHOTKI, SINDH 14.87 million 45 days Sent to SCM deptt on 06.06.2014 for Press advertisement. 80 RAISING OF APPROACH ROAD AT QADIRPUR# 45. DISTRICT : GHOTKI, SINDH 6.19 million 45 days Sent to SCM deptt on 06.06.2014 for Press advertisement. 81 CONSTRACTION OF RAISED PLAT FORM AT QADIRPUR DEEP #01. DISTRICT : GHOTKI, SINDH 27.79 million 45 days Sent to SCM deptt on 06.06.2014 for Press advertisement.
  34. 34. S No Name of Work Estimat ed Cost Press Advertis ement date Date of Opening Work Done By Parties Target Comple tion Date Present Status AFE Cost Lowest Cost 86 CONSTRACTION OF RAISED PLAT FORM AT QADIRPUR#48. DISTRICT : GHOTKI, SINDH 27.56 million 45 days Bid documents prepared. Budget allocated by QP JV and file received in (E.O) South Section on 05.05.14. Case is to be sent to SCM for press advertisement. 87 CONSTRACTION OF RAISED PLAT FORM AT QADIRPUR#46. DISTRICT : GHOTKI, SINDH Rs 27.56 millions 45 days Budget allocated by QP JV department. Case is with (E.O)South Section.
  35. 35. PRE-DRILLING ENGINEERING WORKS AT EFP-3 DURING JUNE 2013 TO JUNE 2014 S.No Description Approv ed Cost EFP-3 input Remarks Earh Work Water Supply System Misc.Works Appro ach Road Preparati on of Well location Mud Pit Additional Mud Pit Establi shmen t Water required for drilling Operation Electric al Works Plumbing & Sanitary Works Total amount MRs MRs MRs MRs MRs MRs MRs MRs MRs MRs 1 PDCW at Jund-1 53.959 2.00 3.50 3.00 4.00 2.00 22.50 0 0 37.00 2 PDCW at Soghari-1 22.557 1.00 2.00 3.00 4.00 1.00 13.50 0.5 0.2 25.20 3 PDCW at Mela-4 39.856 4.00 5.00 4.00 3.00 1.00 22.50 0.5 0.2 40.20 4 PDCW at Rajian-7 23.505 1.50 3.00 4.00 3.00 1.00 13.50 0.5 0.2 26.70 5 PDCW at Rajian-8 60.100 2.00 4.00 4.00 5.00 0.00 18.00 33.00 6 Work over job at Rajian-2 20.193 3.00 0.00 0.00 7.00 10.00 7 PDCW at Nashpa-5 99.850 12.00 24.00 2.00 0.00 0.00 0.00 0 0 38.00 8 PDCW at Surqamar-1 25.00 25.00 9 PDCW at Kurrum-1 28.555 1.00 1.00 3.00 0.00 0.50 13.50 19.00
  36. 36. WATER SUPPLY SYSTEM FOR PLANT/ FIELD OPERATED BY EFP-3 DURING JUNE 2013 TO JUNE 2014 S.No Fields/ Plants Water Source Water required for Operational activities of Plants/ Fields Remarks Million Rupees 1 Chanda Plant/ Mela Plant Mela Water Point situated in hilly area ≈25 km away from Chanda Plant 28.640 2 Missa Kaswall Field from local near by Nallah 4.091 3 Rajian Oil Field from Chohan Nallah 12.274 4 Sadqal Oil Field Sadqal Water Point situated at Shah pur Dam 10.229 REPAIR/ MAINTANENCE OF APPROACH ROAD FROM PLANT TO WELL LOCATION DURING JUNE2013 TO JUNE 2014 S.No Approach Road Maintenance by EFP-3 Remarks MRs 1 From Well Nashpa-1,2,3,4 2.50 2 From Well Mela- 1,2,3,4 3.00 3 Road near Tharraly Bridge 0.50
  37. 37. EARTH WORK REQUIRED FOR ROW,WASTE PITS AND LEVELING BY EFP-3 DURING JUNE2013 TO JUNE 2014 S.No DESCRIPTION Earth Work Remarks MRs 1 ROW for SNGPL Gas Pipe line from Nashpa Plant 1.500 2 Restoration of Mud Waste Pit at Nashpa-2 1.000 3 Restoration of Mud Waste Pit at Nashpa-3 1.000 4 Leveling of Hilly area at Plant for Loading Gantry and double Road 15.00 5 Effulent Water Pits (3No) at Dakhni Plant 0.900 6 Leveling of Store Area at Dakhni Plant 0.500
  38. 38. PRE-DRILLING ENGINEERING WORKS AT EFP-1 DURING JUNE 2013 TO JUNE 2014 S.No Description Approved Cost EFP-31input Remarks Earh Work Water Supply System Misc.Works Appro ach Road Preparati on of Well location Mud Pit Additional Mud Pit Establi shmen t Water required for drilling Operation Electric al Works Plumbing & Sanitary Works Total amount MRs MRs MRs MRs MRs MRs MRs MRs MRs MRs 1 2 3 4 5 6 7 8 9
  39. 39. WATER SUPPLY SYSTEM FOR PLANT/ FIELD OPERATED BY EFP-1 DURING JUNE 2013 TO JUNE 2014 S.No Fields/ Plants Water Source Water required for Operational activities of Plants/ Fields Remarks Million Rupees 1 2 3 4 REPAIR/ MAINTANENCE OF APPROACH ROAD FROM PLANT TO WELL LOCATION DURING JUNE2013 TO JUNE 2014 S.No Approach Road Maintenance by EFP-1 Remarks MRs 1 2 3
  40. 40. EARTH WORK REQUIRED FOR ROW,WASTE PITS AND LEVELING BY EFP-1 DURING JUNE2013 TO JUNE 2014 S.No DESCRIPTION Earth Work Remarks MRs 1 2 3 4 5 6
  41. 41. PRE-DRILLING ENGINEERING WORKS AT EFP-2 DURING JUNE 2013 TO JUNE 2014 S.No Description Approved Cost EFP-2 input Remarks Earh Work Water Supply System Misc.Works Appro ach Road Preparati on of Well location Mud Pit Additional Mud Pit Establi shmen t Water required for drilling Operation Electric al Works Plumbing & Sanitary Works Total amount     MRs MRs MRs MRs MRs MRs MRs MRs MRs   MRs   1 2 3 4 5 6 7 8 9
  42. 42. WATER SUPPLY SYSTEM FOR PLANT/ FIELD OPERATED BY EFP-2 DURING JUNE 2013 TO JUNE 2014 S.No Fields/ Plants Water Source Water required for Operational activities of Plants/ Fields Remarks       Million Rupees   1   2   3   4           REPAIR/ MAINTANENCE OF APPROACH ROAD FROM PLANT TO WELL LOCATION DURING JUNE2013 TO JUNE 2014 S.No Approach Road Maintenance by EFP-2 Remarks   MRs   1   2   3  
  43. 43. EARTH WORK REQUIRED FOR ROW,WASTE PITS AND LEVELING BY EFP-2 DURING JUNE2013 TO JUNE 2014 S.No DESCRIPTION Earth Work Remarks MRs 1 2 3 4 5 6
  44. 44. PRE-DRILLING ENGINEERING WORKS AT EFP-4 DURING JUNE 2013 TO JUNE 2014 S.No Description Approved Cost EFP-4 input Remarks Earh Work Water Supply System Misc.Works Appro ach Road Preparati on of Well location Mud Pit Additional Mud Pit Establi shmen t Water required for drilling Operation Electric al Works Plumbing & Sanitary Works Total amount     MRs MRs MRs MRs MRs MRs MRs MRs MRs   MRs   1 2 3 4 5 6 7 8 9
  45. 45. WATER SUPPLY SYSTEM FOR PLANT/ FIELD OPERATED BY EFP-4 DURING JUNE 2013 TO JUNE 2014 S.No Fields/ Plants Water Source Water required for Operational activities of Plants/ Fields Remarks       Million Rupees   1   2   3   4           REPAIR/ MAINTANENCE OF APPROACH ROAD FROM PLANT TO WELL LOCATION DURING JUNE2013 TO JUNE 2014 S.No Approach Road Maintenance by EFP-4 Remarks   MRs   1   2   3  
  46. 46. EARTH WORK REQUIRED FOR ROW,WASTE PITS AND LEVELING BY EFP-4 DURING JUNE2013 TO JUNE 2014 S.No DESCRIPTION Earth Work Remarks MRs 1 2 3 4 5 6
  47. 47. PRE-DRILLING ENGINEERING WORKS AT EFP-5 DURING JUNE 2013 TO JUNE 2014 S.No Description Approved Cost EFP-5 input Remarks Earh Work Water Supply System Misc.Works Appro ach Road Preparati on of Well location Mud Pit Additional Mud Pit Establi shmen t Water required for drilling Operation Electric al Works Plumbing & Sanitary Works Total amount     MRs MRs MRs MRs MRs MRs MRs MRs MRs   MRs   1 2 3 4 5 6 7 8 9
  48. 48. WATER SUPPLY SYSTEM FOR PLANT/ FIELD OPERATED BY EFP-5 DURING JUNE 2013 TO JUNE 2014 S.No Fields/ Plants Water Source Water required for Operational activities of Plants/ Fields Remarks       Million Rupees   1   2   3   4           REPAIR/ MAINTANENCE OF APPROACH ROAD FROM PLANT TO WELL LOCATION DURING JUNE2013 TO JUNE 2014 S.No Approach Road Maintenance by EFP-5 Remarks   MRs   1   2   3  
  49. 49. EARTH WORK REQUIRED FOR ROW,WASTE PITS AND LEVELING BY EFP-5 DURING JUNE2013 TO JUNE 2014 S.No DESCRIPTION Earth Work Remarks MRs 1 2 3 4 5 6
  50. 50. Financially Highlight of- Total Works Done, EFP’s FY 2013-14 1 EFP-I 2 EFP-II PAK Rs. 300.o1 Million 3 EFP-III  PAK Rs. 347.83 Million 4 EFP-IV 5 EFP-V 6 FGCP-I 7 FGCP-II

×