ARBA MINCH INSTITUTE OF
TECHNOLOGY
FACULTY OF CIVIL ENGINEERIN
Internship Report on Building Construction
Project
BRHANU TOPIYAW CONSTRUCTION PLC
BY ABEL SISAY
ABEL SISAY (NSR/078/13, SEC. B)
Phone No: +251943348947
+251912247486
Email: abelsisay121619@gmail.com
September
Arba Minch, Ethiopia
2024
Introduction
1 Introduction and Background
This presentation introduces my internship program and the hosting
company, Birhan Tobiyaw Building Contractor.
2 Internship Experience
I will discuss my overall internship experience, including site work and office activities.
3 Benefits Gained
I will highlight the benefits I derived from this internship experience, such
as skill development and practical knowledge.
4 Conclusion and Recommendations
The presentation concludes with my overall reflections and
recommendations based on my internship experience. 1
Background of the Hosting
Company
Birhan Tobiyaw Building Contractor
Birhan Tobiyaw is a grade one engineering consultant
specializing in building construction.
Company History
The company has a rich history and a strong track record
in the construction industry.
Main Office
The company's main office is located
in Addis Ababa, Ethiopia.
2
Organizational structure
The building is 1B+G+8 office and mixed use building
Project: Devlopment Bank of Ethiopia
Location : Adama Near to Posta Office
Owner : Devlopment Bank of Ethiopia
Contractor: Birhan Tobiyaw Building Contractor
Consultant : Ultimate Plan P.L.C
Project information
4
Sections of the Company I
Worked In
1 Site Work
My responsibilities included observing and
participating in various site activities.
2 Office Work
I had the opportunity to gain insights into the
administrative and documentation aspects of
construction.
5
Materials
Concrete
Concrete is a key material used in reinforced concrete structures.
Cement
Cement serves as the binding agent in concrete,
providing strength and durability.
Aggregate
Aggregates, such as sand and gravel,
provide volume and strength to concrete.
Water
Water is essential for hydration of cement, facilitating
the chemical reactions that lead to concrete hardening.
Batching, mixing and placing of concrete
spacer
6
Concrete Work
Batching
Precise measurement of concrete ingredients is crucial
for consistent quality.
Mixing
Thorough mixing ensures a homogeneous concrete
mix with uniform properties.
Placing
Concrete is carefully placed in the formwork,
ensuring proper compaction and density.
Compacting
Vibrating the concrete removes air pockets and
improves workability.
Curing
Curing involves maintaining moisture and temperature
to allow for proper hydration and hardening.
7
Reinforcement Work
1 Cutting and Bending
Reinforcement bars are cut and bent to
the required shapes and sizes.
2 Placement
Reinforcement bars are placed in the
formwork according to the design
drawings.
3 Stirrups
Stirrups are used to reinforce the shear
strength of concrete structures.
4 Lapping
Lapping involves overlapping
reinforcement bars to provide a
continuous reinforcing element.
8
Formwork
Temporary Mold
Formwork serves as a temporary mold for
concrete structures.
Requirements
Formwork must be strong, rigid, and capable of
resisting the pressure of fresh concrete.
9
Scaffolding
Temporary structure erected separately from
structural support scaffolds.
Provides easy circulation and working environment.
Required for all types of structures constructed above ground level.
Various stages of construction should be erected at convenient heights.
Only limited loads should be put on the scaffolding.
10
Equipment Used
Mobile Truck Mixer
Used to transport and mix concrete.
Concrete Pumper Truck
Delivers concrete from the
mixer to the desired location.
Vibrator
Used to remove air bubbles
and consolidate concrete.
11
Man Power
1 Project Manager
Overall project planning and execution.
2 Site Engineer
Supervises construction activities on site.
3 Office Engineer
Assists with drawings, calculations, and
documentation.
4 Foreman
Manages and supervises the labor crew.
12
Major site works (superstructure)
Are activities performed above the ground level.
Work task I have been executed
13
Elevation Column
1
Provide Cretcher
A device to hold concrete while pouring.
2 Tie Spacer
Ensures proper spacing
and alignment of
reinforcement bars.
3
Keep Formwork
The mold for the concrete to set in.
4 Check Alignment
Ensure the column is plumb
and straight.
5
Cast Concrete
Pouring concrete into the formwork.
6 Keep Stirrups
Reinforcement bars that
provide shear strength.
7
Tie Bars
Connecting the column
reinforcement to the foundation.
8 Remove Formwork
Removing the formwork
after the concrete has cured.
14
Shear Wall
Tie Starter Bars
Reinforcement bars that connect to
the foundation.
Provide Stirrups
Reinforcement bars that provide
shear strength.
Put Spacers
Maintain the correct distance between
reinforcement bars.
Keep Formwork
The mold for the concrete to set in.
Cast Concrete
Pouring concrete into the formwork.
15
Beam
Primary Beam
Runs from column to column.
Secondary Beam
Runs from beam to beam
through the slab.
Distributes loads from the slab
to the primary beams.
Procedure Followed
• Erect Cristy
• Tie Formwork
• Keep +ve and -ve Bars
• Insert Spacer
• Check C/C of Stirrups
• Cast Concrete
Carries the major load.
16
Slab
Erect H-Frame Arrangement of Formwork Cleaning and Painting
Arrangement Reinforcement Provide Spacer Concrete Casting
17
Staircase
Formwork
The mold for the concrete to set in.
Reinforcement
Steel bars that provide structural strength.
18
Office Work
Takeoff Sheet
A table format used to compute different
amounts of materials.
Material Ordering
Ordering materials based on takeoff calculations.
Cost Estimation
Estimating construction costs based on material
quantities and labor.
Project Scheduling
Planning and managing the project timeline. 19
Bar Schedule Explained
A bar schedule is a table format used to calculate the total amount of reinforcement bar
required for a certain structure.
20
Overall Internship Benefits
1 Practical Skill Improvement
My internship provided me with practical experience in various
construction tasks, enhancing my hands-on skills.
2
Theoretical Knowledge Upgrade
I gained a deeper understanding of construction theory, applying
classroom knowledge to real-world scenarios.
3
Communication Skills Enhancement
I learned effective communication techniques, collaborating
with team members and stakeholders.
4
Teamwork and Leadership Development
I worked effectively as part of a team and had opportunities to lead and
inspire others. 21
Key Internship Takeaways
Task Execution
I learned to execute given tasks efficiently and effectively,
following industry best practices.
Task Performance
I gained the ability to perform tasks effectively, meeting
project requirements and deadlines.
Problem Solving
I developed critical thinking skills and problem-solving
abilities, finding solutions to challenges on-site.
Time and Task Management
I learned to manage my time and prioritize tasks effectively,
22
Recommendations for Improvement
Company Recommendations
1. Improve site worker safety by providing
essential equipment like safety shoes.
2. Ensure timely provision of necessary raw
materials to avoid project delays.
3. Invest in concrete vibrators to achieve
optimal concrete compaction, preventing
over-vibration or under-vibration.
University Recommendations
1. Extend the internship period to provide
students with adequate time to acquire
practical skills and knowledge.
2. Establish a dedicated practice area within
the university to supplement theoretical
learning with hands-on experience.
23
Conclusion
My internship at Birhan Tobiyaw Building Contractor
provided me with valuable experience and skills. I am
confident in my ability to contribute effectively to the
construction industry.
24
The End
Thank you for your time and consideration.

Abel_Sisay_Internship_Report_on_Building_Construction_Project.pptx

  • 1.
    ARBA MINCH INSTITUTEOF TECHNOLOGY FACULTY OF CIVIL ENGINEERIN Internship Report on Building Construction Project BRHANU TOPIYAW CONSTRUCTION PLC BY ABEL SISAY ABEL SISAY (NSR/078/13, SEC. B) Phone No: +251943348947 +251912247486 Email: abelsisay121619@gmail.com September Arba Minch, Ethiopia 2024
  • 2.
    Introduction 1 Introduction andBackground This presentation introduces my internship program and the hosting company, Birhan Tobiyaw Building Contractor. 2 Internship Experience I will discuss my overall internship experience, including site work and office activities. 3 Benefits Gained I will highlight the benefits I derived from this internship experience, such as skill development and practical knowledge. 4 Conclusion and Recommendations The presentation concludes with my overall reflections and recommendations based on my internship experience. 1
  • 3.
    Background of theHosting Company Birhan Tobiyaw Building Contractor Birhan Tobiyaw is a grade one engineering consultant specializing in building construction. Company History The company has a rich history and a strong track record in the construction industry. Main Office The company's main office is located in Addis Ababa, Ethiopia. 2
  • 4.
  • 5.
    The building is1B+G+8 office and mixed use building Project: Devlopment Bank of Ethiopia Location : Adama Near to Posta Office Owner : Devlopment Bank of Ethiopia Contractor: Birhan Tobiyaw Building Contractor Consultant : Ultimate Plan P.L.C Project information 4
  • 6.
    Sections of theCompany I Worked In 1 Site Work My responsibilities included observing and participating in various site activities. 2 Office Work I had the opportunity to gain insights into the administrative and documentation aspects of construction. 5
  • 7.
    Materials Concrete Concrete is akey material used in reinforced concrete structures. Cement Cement serves as the binding agent in concrete, providing strength and durability. Aggregate Aggregates, such as sand and gravel, provide volume and strength to concrete. Water Water is essential for hydration of cement, facilitating the chemical reactions that lead to concrete hardening. Batching, mixing and placing of concrete spacer 6
  • 8.
    Concrete Work Batching Precise measurementof concrete ingredients is crucial for consistent quality. Mixing Thorough mixing ensures a homogeneous concrete mix with uniform properties. Placing Concrete is carefully placed in the formwork, ensuring proper compaction and density. Compacting Vibrating the concrete removes air pockets and improves workability. Curing Curing involves maintaining moisture and temperature to allow for proper hydration and hardening. 7
  • 9.
    Reinforcement Work 1 Cuttingand Bending Reinforcement bars are cut and bent to the required shapes and sizes. 2 Placement Reinforcement bars are placed in the formwork according to the design drawings. 3 Stirrups Stirrups are used to reinforce the shear strength of concrete structures. 4 Lapping Lapping involves overlapping reinforcement bars to provide a continuous reinforcing element. 8
  • 10.
    Formwork Temporary Mold Formwork servesas a temporary mold for concrete structures. Requirements Formwork must be strong, rigid, and capable of resisting the pressure of fresh concrete. 9
  • 11.
    Scaffolding Temporary structure erectedseparately from structural support scaffolds. Provides easy circulation and working environment. Required for all types of structures constructed above ground level. Various stages of construction should be erected at convenient heights. Only limited loads should be put on the scaffolding. 10
  • 12.
    Equipment Used Mobile TruckMixer Used to transport and mix concrete. Concrete Pumper Truck Delivers concrete from the mixer to the desired location. Vibrator Used to remove air bubbles and consolidate concrete. 11
  • 13.
    Man Power 1 ProjectManager Overall project planning and execution. 2 Site Engineer Supervises construction activities on site. 3 Office Engineer Assists with drawings, calculations, and documentation. 4 Foreman Manages and supervises the labor crew. 12
  • 14.
    Major site works(superstructure) Are activities performed above the ground level. Work task I have been executed 13
  • 15.
    Elevation Column 1 Provide Cretcher Adevice to hold concrete while pouring. 2 Tie Spacer Ensures proper spacing and alignment of reinforcement bars. 3 Keep Formwork The mold for the concrete to set in. 4 Check Alignment Ensure the column is plumb and straight. 5 Cast Concrete Pouring concrete into the formwork. 6 Keep Stirrups Reinforcement bars that provide shear strength. 7 Tie Bars Connecting the column reinforcement to the foundation. 8 Remove Formwork Removing the formwork after the concrete has cured. 14
  • 16.
    Shear Wall Tie StarterBars Reinforcement bars that connect to the foundation. Provide Stirrups Reinforcement bars that provide shear strength. Put Spacers Maintain the correct distance between reinforcement bars. Keep Formwork The mold for the concrete to set in. Cast Concrete Pouring concrete into the formwork. 15
  • 17.
    Beam Primary Beam Runs fromcolumn to column. Secondary Beam Runs from beam to beam through the slab. Distributes loads from the slab to the primary beams. Procedure Followed • Erect Cristy • Tie Formwork • Keep +ve and -ve Bars • Insert Spacer • Check C/C of Stirrups • Cast Concrete Carries the major load. 16
  • 18.
    Slab Erect H-Frame Arrangementof Formwork Cleaning and Painting Arrangement Reinforcement Provide Spacer Concrete Casting 17
  • 19.
    Staircase Formwork The mold forthe concrete to set in. Reinforcement Steel bars that provide structural strength. 18
  • 20.
    Office Work Takeoff Sheet Atable format used to compute different amounts of materials. Material Ordering Ordering materials based on takeoff calculations. Cost Estimation Estimating construction costs based on material quantities and labor. Project Scheduling Planning and managing the project timeline. 19
  • 21.
    Bar Schedule Explained Abar schedule is a table format used to calculate the total amount of reinforcement bar required for a certain structure. 20
  • 22.
    Overall Internship Benefits 1Practical Skill Improvement My internship provided me with practical experience in various construction tasks, enhancing my hands-on skills. 2 Theoretical Knowledge Upgrade I gained a deeper understanding of construction theory, applying classroom knowledge to real-world scenarios. 3 Communication Skills Enhancement I learned effective communication techniques, collaborating with team members and stakeholders. 4 Teamwork and Leadership Development I worked effectively as part of a team and had opportunities to lead and inspire others. 21
  • 23.
    Key Internship Takeaways TaskExecution I learned to execute given tasks efficiently and effectively, following industry best practices. Task Performance I gained the ability to perform tasks effectively, meeting project requirements and deadlines. Problem Solving I developed critical thinking skills and problem-solving abilities, finding solutions to challenges on-site. Time and Task Management I learned to manage my time and prioritize tasks effectively, 22
  • 24.
    Recommendations for Improvement CompanyRecommendations 1. Improve site worker safety by providing essential equipment like safety shoes. 2. Ensure timely provision of necessary raw materials to avoid project delays. 3. Invest in concrete vibrators to achieve optimal concrete compaction, preventing over-vibration or under-vibration. University Recommendations 1. Extend the internship period to provide students with adequate time to acquire practical skills and knowledge. 2. Establish a dedicated practice area within the university to supplement theoretical learning with hands-on experience. 23
  • 25.
    Conclusion My internship atBirhan Tobiyaw Building Contractor provided me with valuable experience and skills. I am confident in my ability to contribute effectively to the construction industry. 24
  • 26.
    The End Thank youfor your time and consideration.