SlideShare a Scribd company logo
In plumbing, a pipe installed to drain water
from the roof gutters or roof catchment to the
storm drain or other means of disposal. Also
called a conductor, downspout, or roof drain.
8.4 Roof Leader
Roof gutter
Downspout
Roof Drain
Roof leader is either Exposed or Concealed Type
Pit
Drain Pipe
Illustration
Area of Roof A
10m x 20m = 200 m 𝟐
Solution
A
B
Area of Roof B
8m x 20m = 160 m 𝟐
Comments
 For 20 meters length of the gutter the rains has to
travel a long way, It might be overloaded and overflow.
The terminal maybe clogged with dirty such as leaves,
etc. Thus, We need two or more terminals for roof
leader.
D = 100mm & D = 90mm
( expensive or oversized ):
Find the number of terminals
𝐃 = 𝟏𝟎𝟎𝐦𝐦
 Cross section: A1 = πD2
/4 = 3.14 × 1002
/4 = 7850𝑚m2
Divide into two terminals: 3925𝑚𝑚2
Chooses D = 75mm ; A2 = π ×
752
4
= 4416𝑚m2
> 3925mm2
D = 75mm OK ! 
D = 50mm, A = 1963𝑚m2
< 3925𝑚𝑚2

D = 90mm, A = 6359mm2
> 3925𝑚𝑚2
(Not economic)
𝐃 = 𝟗𝟎𝐦𝐦
 Cross section: A1 = πD2
/4 = 3.14 × 902
/4 = 6359𝑚m2
Divide into two terminals: 3179𝑚𝑚2
Chooses D = 75mm ; A2 = π × 752
/4 = 4415𝑚m2
> 3179𝑚𝑚2
D = 75mm OK ! 
Second Solution
Roof A
𝐴 = 200𝑚2
2 terminals = 100𝑚2
Roof B
𝐴 = 160𝑚2
2 terminals = 80𝑚2
Choose 𝐷 = 75𝑚𝑚
Thank You !!!

More Related Content

What's hot

MAX FAJARDO ESTIMATE.pdf
MAX FAJARDO ESTIMATE.pdfMAX FAJARDO ESTIMATE.pdf
MAX FAJARDO ESTIMATE.pdf
EdnaMarieObtinalla
 
Presentation plumbing
Presentation plumbingPresentation plumbing
Presentation plumbingLiguidliguid
 
Design of column according ACI codes
Design of column according ACI codesDesign of column according ACI codes
Design of column according ACI codes
Engr. Majid Seraj Baloch
 
reinforced concrete arki.ppt
reinforced concrete arki.pptreinforced concrete arki.ppt
reinforced concrete arki.ppt
ChristopherArce4
 
Flexural design of beam...PRC-I
Flexural design of beam...PRC-IFlexural design of beam...PRC-I
Flexural design of beam...PRC-I
Irfan Malik
 
NSCP 2010 , Volume 1
NSCP 2010 , Volume 1NSCP 2010 , Volume 1
NSCP 2010 , Volume 1
PUP Lopez College of Civil Engg.
 
Chapter 5-cables and arches
Chapter 5-cables and archesChapter 5-cables and arches
Chapter 5-cables and arches
ISET NABEUL
 
Sasoli1
Sasoli1Sasoli1
Sasoli1
buetk khuzdar
 
Problems Associated with Bituminous Binders and Macadam Asphalt Mat
Problems Associated with Bituminous Binders and Macadam Asphalt MatProblems Associated with Bituminous Binders and Macadam Asphalt Mat
Problems Associated with Bituminous Binders and Macadam Asphalt Mat
Christine Salazar
 
Analysis of T-Beam
Analysis of T-BeamAnalysis of T-Beam
Analysis of T-Beam
01008828934
 
Solution of Chapter- 04 - shear & moment in beams - Strength of Materials by ...
Solution of Chapter- 04 - shear & moment in beams - Strength of Materials by ...Solution of Chapter- 04 - shear & moment in beams - Strength of Materials by ...
Solution of Chapter- 04 - shear & moment in beams - Strength of Materials by ...
Ashiqur Rahman Ziad
 
Friction full
Friction fullFriction full
Friction full
Kosygin Leishangthem
 
Ge 105 lecture 2 (TAPING CORRECTION) by: Broddett B. Abatayo
Ge 105 lecture 2 (TAPING CORRECTION) by: Broddett B. AbatayoGe 105 lecture 2 (TAPING CORRECTION) by: Broddett B. Abatayo
Ge 105 lecture 2 (TAPING CORRECTION) by: Broddett B. Abatayo
BPA ABATAYO Land Surveying Services
 
Beam Design and Drawing of RCC Structures
Beam Design and Drawing of RCC StructuresBeam Design and Drawing of RCC Structures
Beam Design and Drawing of RCC Structures
Shubham .
 
Solution Manual for Structural Analysis 6th SI by Aslam Kassimali
Solution Manual for Structural Analysis 6th SI by Aslam KassimaliSolution Manual for Structural Analysis 6th SI by Aslam Kassimali
Solution Manual for Structural Analysis 6th SI by Aslam Kassimali
physicsbook
 
Design of RCC Column footing
Design of RCC Column footingDesign of RCC Column footing
Design of RCC Column footing
Arun Kurali
 
Earthquake Load Calculation (base shear method)
Earthquake Load Calculation (base shear method)Earthquake Load Calculation (base shear method)
Earthquake Load Calculation (base shear method)
Shekh Muhsen Uddin Ahmed
 
Material Testing Lab Equipments
Material Testing Lab EquipmentsMaterial Testing Lab Equipments
Material Testing Lab Equipments
Naveed Hussain
 
Cast Iron and Galvanized Iron Pipes
Cast Iron and Galvanized Iron PipesCast Iron and Galvanized Iron Pipes
Cast Iron and Galvanized Iron Pipes
Akshay Dhimate
 

What's hot (20)

MAX FAJARDO ESTIMATE.pdf
MAX FAJARDO ESTIMATE.pdfMAX FAJARDO ESTIMATE.pdf
MAX FAJARDO ESTIMATE.pdf
 
Presentation plumbing
Presentation plumbingPresentation plumbing
Presentation plumbing
 
Design of column according ACI codes
Design of column according ACI codesDesign of column according ACI codes
Design of column according ACI codes
 
reinforced concrete arki.ppt
reinforced concrete arki.pptreinforced concrete arki.ppt
reinforced concrete arki.ppt
 
Flexural design of beam...PRC-I
Flexural design of beam...PRC-IFlexural design of beam...PRC-I
Flexural design of beam...PRC-I
 
NSCP 2010 , Volume 1
NSCP 2010 , Volume 1NSCP 2010 , Volume 1
NSCP 2010 , Volume 1
 
Chapter 5-cables and arches
Chapter 5-cables and archesChapter 5-cables and arches
Chapter 5-cables and arches
 
Sasoli1
Sasoli1Sasoli1
Sasoli1
 
Problems Associated with Bituminous Binders and Macadam Asphalt Mat
Problems Associated with Bituminous Binders and Macadam Asphalt MatProblems Associated with Bituminous Binders and Macadam Asphalt Mat
Problems Associated with Bituminous Binders and Macadam Asphalt Mat
 
Analysis of T-Beam
Analysis of T-BeamAnalysis of T-Beam
Analysis of T-Beam
 
Solution of Chapter- 04 - shear & moment in beams - Strength of Materials by ...
Solution of Chapter- 04 - shear & moment in beams - Strength of Materials by ...Solution of Chapter- 04 - shear & moment in beams - Strength of Materials by ...
Solution of Chapter- 04 - shear & moment in beams - Strength of Materials by ...
 
Friction full
Friction fullFriction full
Friction full
 
Ge 105 lecture 2 (TAPING CORRECTION) by: Broddett B. Abatayo
Ge 105 lecture 2 (TAPING CORRECTION) by: Broddett B. AbatayoGe 105 lecture 2 (TAPING CORRECTION) by: Broddett B. Abatayo
Ge 105 lecture 2 (TAPING CORRECTION) by: Broddett B. Abatayo
 
Beam Design and Drawing of RCC Structures
Beam Design and Drawing of RCC StructuresBeam Design and Drawing of RCC Structures
Beam Design and Drawing of RCC Structures
 
Solution Manual for Structural Analysis 6th SI by Aslam Kassimali
Solution Manual for Structural Analysis 6th SI by Aslam KassimaliSolution Manual for Structural Analysis 6th SI by Aslam Kassimali
Solution Manual for Structural Analysis 6th SI by Aslam Kassimali
 
Design of RCC Column footing
Design of RCC Column footingDesign of RCC Column footing
Design of RCC Column footing
 
Earthquake Load Calculation (base shear method)
Earthquake Load Calculation (base shear method)Earthquake Load Calculation (base shear method)
Earthquake Load Calculation (base shear method)
 
Buoyancy2 q
Buoyancy2 qBuoyancy2 q
Buoyancy2 q
 
Material Testing Lab Equipments
Material Testing Lab EquipmentsMaterial Testing Lab Equipments
Material Testing Lab Equipments
 
Cast Iron and Galvanized Iron Pipes
Cast Iron and Galvanized Iron PipesCast Iron and Galvanized Iron Pipes
Cast Iron and Galvanized Iron Pipes
 

Similar to 8.4 roof leader

EasyHeat ADKS Heat Tracing Cable Kits - Brochure
EasyHeat ADKS Heat Tracing Cable Kits - BrochureEasyHeat ADKS Heat Tracing Cable Kits - Brochure
EasyHeat ADKS Heat Tracing Cable Kits - Brochure
Thorne & Derrick UK
 
EasyHeat ADKS 1000 Heat Tracing Cable Kit - Brochure
EasyHeat ADKS 1000 Heat Tracing Cable Kit - BrochureEasyHeat ADKS 1000 Heat Tracing Cable Kit - Brochure
EasyHeat ADKS 1000 Heat Tracing Cable Kit - Brochure
Thorne & Derrick UK
 
EasyHeat ADKS-100 Heat Tracing Cable Kit - Brochure
EasyHeat ADKS-100 Heat Tracing Cable Kit - BrochureEasyHeat ADKS-100 Heat Tracing Cable Kit - Brochure
EasyHeat ADKS-100 Heat Tracing Cable Kit - Brochure
Thorne & Derrick UK
 
EasyHeat AKDS 400 Heat Tracing Cable Kit - Brochure
EasyHeat AKDS 400 Heat Tracing Cable Kit - BrochureEasyHeat AKDS 400 Heat Tracing Cable Kit - Brochure
EasyHeat AKDS 400 Heat Tracing Cable Kit - Brochure
Thorne & Derrick UK
 
EasyHeat ADKS 1200 Heat Tracing Cable Kit - Brochure
EasyHeat ADKS 1200 Heat Tracing Cable Kit - BrochureEasyHeat ADKS 1200 Heat Tracing Cable Kit - Brochure
EasyHeat ADKS 1200 Heat Tracing Cable Kit - Brochure
Thorne & Derrick UK
 
EasyHeat ADKS 150 Heat Tracing Cable Kit - Brochure
EasyHeat ADKS 150 Heat Tracing Cable Kit - BrochureEasyHeat ADKS 150 Heat Tracing Cable Kit - Brochure
EasyHeat ADKS 150 Heat Tracing Cable Kit - Brochure
Thorne & Derrick UK
 
EasyHeat ADKS 600 Heat Tracing Cable Kit - Brochure
EasyHeat ADKS 600 Heat Tracing Cable Kit - BrochureEasyHeat ADKS 600 Heat Tracing Cable Kit - Brochure
EasyHeat ADKS 600 Heat Tracing Cable Kit - Brochure
Thorne & Derrick UK
 
EasyHeat ADKS 300 Heat Tracing Cable Kit - Brochure
EasyHeat ADKS 300 Heat Tracing Cable Kit - BrochureEasyHeat ADKS 300 Heat Tracing Cable Kit - Brochure
EasyHeat ADKS 300 Heat Tracing Cable Kit - Brochure
Thorne & Derrick UK
 
EasyHeat ADKS 500 Heat Tracing Cable Kit - Brochure
EasyHeat ADKS 500 Heat Tracing Cable Kit  - BrochureEasyHeat ADKS 500 Heat Tracing Cable Kit  - Brochure
EasyHeat ADKS 500 Heat Tracing Cable Kit - Brochure
Thorne & Derrick UK
 
Lecture16.pdf
Lecture16.pdfLecture16.pdf
Lecture16.pdf
Adel Naser Daoud
 
Tugas 3 Contoh Perhitungan Pompa.pptx
Tugas 3 Contoh Perhitungan Pompa.pptxTugas 3 Contoh Perhitungan Pompa.pptx
Tugas 3 Contoh Perhitungan Pompa.pptx
Rihfa
 
Gaviotas Hyidraulic Ram Pump: Installation, Operation and Maintenance Manual
Gaviotas Hyidraulic Ram Pump: Installation, Operation and Maintenance ManualGaviotas Hyidraulic Ram Pump: Installation, Operation and Maintenance Manual
Gaviotas Hyidraulic Ram Pump: Installation, Operation and Maintenance Manual
Fatin62c
 

Similar to 8.4 roof leader (12)

EasyHeat ADKS Heat Tracing Cable Kits - Brochure
EasyHeat ADKS Heat Tracing Cable Kits - BrochureEasyHeat ADKS Heat Tracing Cable Kits - Brochure
EasyHeat ADKS Heat Tracing Cable Kits - Brochure
 
EasyHeat ADKS 1000 Heat Tracing Cable Kit - Brochure
EasyHeat ADKS 1000 Heat Tracing Cable Kit - BrochureEasyHeat ADKS 1000 Heat Tracing Cable Kit - Brochure
EasyHeat ADKS 1000 Heat Tracing Cable Kit - Brochure
 
EasyHeat ADKS-100 Heat Tracing Cable Kit - Brochure
EasyHeat ADKS-100 Heat Tracing Cable Kit - BrochureEasyHeat ADKS-100 Heat Tracing Cable Kit - Brochure
EasyHeat ADKS-100 Heat Tracing Cable Kit - Brochure
 
EasyHeat AKDS 400 Heat Tracing Cable Kit - Brochure
EasyHeat AKDS 400 Heat Tracing Cable Kit - BrochureEasyHeat AKDS 400 Heat Tracing Cable Kit - Brochure
EasyHeat AKDS 400 Heat Tracing Cable Kit - Brochure
 
EasyHeat ADKS 1200 Heat Tracing Cable Kit - Brochure
EasyHeat ADKS 1200 Heat Tracing Cable Kit - BrochureEasyHeat ADKS 1200 Heat Tracing Cable Kit - Brochure
EasyHeat ADKS 1200 Heat Tracing Cable Kit - Brochure
 
EasyHeat ADKS 150 Heat Tracing Cable Kit - Brochure
EasyHeat ADKS 150 Heat Tracing Cable Kit - BrochureEasyHeat ADKS 150 Heat Tracing Cable Kit - Brochure
EasyHeat ADKS 150 Heat Tracing Cable Kit - Brochure
 
EasyHeat ADKS 600 Heat Tracing Cable Kit - Brochure
EasyHeat ADKS 600 Heat Tracing Cable Kit - BrochureEasyHeat ADKS 600 Heat Tracing Cable Kit - Brochure
EasyHeat ADKS 600 Heat Tracing Cable Kit - Brochure
 
EasyHeat ADKS 300 Heat Tracing Cable Kit - Brochure
EasyHeat ADKS 300 Heat Tracing Cable Kit - BrochureEasyHeat ADKS 300 Heat Tracing Cable Kit - Brochure
EasyHeat ADKS 300 Heat Tracing Cable Kit - Brochure
 
EasyHeat ADKS 500 Heat Tracing Cable Kit - Brochure
EasyHeat ADKS 500 Heat Tracing Cable Kit  - BrochureEasyHeat ADKS 500 Heat Tracing Cable Kit  - Brochure
EasyHeat ADKS 500 Heat Tracing Cable Kit - Brochure
 
Lecture16.pdf
Lecture16.pdfLecture16.pdf
Lecture16.pdf
 
Tugas 3 Contoh Perhitungan Pompa.pptx
Tugas 3 Contoh Perhitungan Pompa.pptxTugas 3 Contoh Perhitungan Pompa.pptx
Tugas 3 Contoh Perhitungan Pompa.pptx
 
Gaviotas Hyidraulic Ram Pump: Installation, Operation and Maintenance Manual
Gaviotas Hyidraulic Ram Pump: Installation, Operation and Maintenance ManualGaviotas Hyidraulic Ram Pump: Installation, Operation and Maintenance Manual
Gaviotas Hyidraulic Ram Pump: Installation, Operation and Maintenance Manual
 

More from Smee Kaem Chann

stress-and-strain
stress-and-strainstress-and-strain
stress-and-strain
Smee Kaem Chann
 
Robot khmer engineer
Robot khmer engineerRobot khmer engineer
Robot khmer engineer
Smee Kaem Chann
 
15 poteau-2
15 poteau-215 poteau-2
15 poteau-2
Smee Kaem Chann
 
14 poteau-1
14 poteau-114 poteau-1
14 poteau-1
Smee Kaem Chann
 
12 plancher-Eurocode 2
12 plancher-Eurocode 212 plancher-Eurocode 2
12 plancher-Eurocode 2
Smee Kaem Chann
 
Matlab_Prof Pouv Keangsé
Matlab_Prof Pouv KeangséMatlab_Prof Pouv Keangsé
Matlab_Prof Pouv Keangsé
Smee Kaem Chann
 
Vocabuary
VocabuaryVocabuary
Vocabuary
Smee Kaem Chann
 
Journal de bord
Journal de bordJournal de bord
Journal de bord
Smee Kaem Chann
 
Rapport de stage
Rapport de stage Rapport de stage
Rapport de stage
Smee Kaem Chann
 
Travaux Pratique Matlab + Corrige_Smee Kaem Chann
Travaux Pratique Matlab + Corrige_Smee Kaem ChannTravaux Pratique Matlab + Corrige_Smee Kaem Chann
Travaux Pratique Matlab + Corrige_Smee Kaem Chann
Smee Kaem Chann
 
Td triphasé
Td triphaséTd triphasé
Td triphasé
Smee Kaem Chann
 
Tp2 Matlab
Tp2 MatlabTp2 Matlab
Tp2 Matlab
Smee Kaem Chann
 
Cover matlab
Cover matlabCover matlab
Cover matlab
Smee Kaem Chann
 
New Interchange 3ed edition Vocabulary unit 8
New Interchange 3ed edition Vocabulary unit 8 New Interchange 3ed edition Vocabulary unit 8
New Interchange 3ed edition Vocabulary unit 8
Smee Kaem Chann
 
Matlab Travaux Pratique
Matlab Travaux Pratique Matlab Travaux Pratique
Matlab Travaux Pratique
Smee Kaem Chann
 
The technologies of building resists the wind load and earthquake
The technologies of building resists the wind load and earthquakeThe technologies of building resists the wind load and earthquake
The technologies of building resists the wind load and earthquake
Smee Kaem Chann
 
Devoir d'électricite des bêtiment
Devoir d'électricite des bêtimentDevoir d'électricite des bêtiment
Devoir d'électricite des bêtiment
Smee Kaem Chann
 
Rapport topographie 2016-2017
Rapport topographie 2016-2017  Rapport topographie 2016-2017
Rapport topographie 2016-2017
Smee Kaem Chann
 
Case study: Probability and Statistic
Case study: Probability and StatisticCase study: Probability and Statistic
Case study: Probability and Statistic
Smee Kaem Chann
 
Hydrologie générale
Hydrologie générale Hydrologie générale
Hydrologie générale
Smee Kaem Chann
 

More from Smee Kaem Chann (20)

stress-and-strain
stress-and-strainstress-and-strain
stress-and-strain
 
Robot khmer engineer
Robot khmer engineerRobot khmer engineer
Robot khmer engineer
 
15 poteau-2
15 poteau-215 poteau-2
15 poteau-2
 
14 poteau-1
14 poteau-114 poteau-1
14 poteau-1
 
12 plancher-Eurocode 2
12 plancher-Eurocode 212 plancher-Eurocode 2
12 plancher-Eurocode 2
 
Matlab_Prof Pouv Keangsé
Matlab_Prof Pouv KeangséMatlab_Prof Pouv Keangsé
Matlab_Prof Pouv Keangsé
 
Vocabuary
VocabuaryVocabuary
Vocabuary
 
Journal de bord
Journal de bordJournal de bord
Journal de bord
 
Rapport de stage
Rapport de stage Rapport de stage
Rapport de stage
 
Travaux Pratique Matlab + Corrige_Smee Kaem Chann
Travaux Pratique Matlab + Corrige_Smee Kaem ChannTravaux Pratique Matlab + Corrige_Smee Kaem Chann
Travaux Pratique Matlab + Corrige_Smee Kaem Chann
 
Td triphasé
Td triphaséTd triphasé
Td triphasé
 
Tp2 Matlab
Tp2 MatlabTp2 Matlab
Tp2 Matlab
 
Cover matlab
Cover matlabCover matlab
Cover matlab
 
New Interchange 3ed edition Vocabulary unit 8
New Interchange 3ed edition Vocabulary unit 8 New Interchange 3ed edition Vocabulary unit 8
New Interchange 3ed edition Vocabulary unit 8
 
Matlab Travaux Pratique
Matlab Travaux Pratique Matlab Travaux Pratique
Matlab Travaux Pratique
 
The technologies of building resists the wind load and earthquake
The technologies of building resists the wind load and earthquakeThe technologies of building resists the wind load and earthquake
The technologies of building resists the wind load and earthquake
 
Devoir d'électricite des bêtiment
Devoir d'électricite des bêtimentDevoir d'électricite des bêtiment
Devoir d'électricite des bêtiment
 
Rapport topographie 2016-2017
Rapport topographie 2016-2017  Rapport topographie 2016-2017
Rapport topographie 2016-2017
 
Case study: Probability and Statistic
Case study: Probability and StatisticCase study: Probability and Statistic
Case study: Probability and Statistic
 
Hydrologie générale
Hydrologie générale Hydrologie générale
Hydrologie générale
 

Recently uploaded

14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
SyedAbiiAzazi1
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
NidhalKahouli2
 
AIR POLLUTION lecture EnE203 updated.pdf
AIR POLLUTION lecture EnE203 updated.pdfAIR POLLUTION lecture EnE203 updated.pdf
AIR POLLUTION lecture EnE203 updated.pdf
RicletoEspinosa1
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
drwaing
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
anoopmanoharan2
 
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
obonagu
 
Swimming pool mechanical components design.pptx
Swimming pool  mechanical components design.pptxSwimming pool  mechanical components design.pptx
Swimming pool mechanical components design.pptx
yokeleetan1
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
MIGUELANGEL966976
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
ClaraZara1
 
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
dxobcob
 
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
Mukeshwaran Balu
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
Rahul
 
TOP 10 B TECH COLLEGES IN JAIPUR 2024.pptx
TOP 10 B TECH COLLEGES IN JAIPUR 2024.pptxTOP 10 B TECH COLLEGES IN JAIPUR 2024.pptx
TOP 10 B TECH COLLEGES IN JAIPUR 2024.pptx
nikitacareer3
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
Madan Karki
 
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
awadeshbabu
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
heavyhaig
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Soumen Santra
 

Recently uploaded (20)

14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
 
AIR POLLUTION lecture EnE203 updated.pdf
AIR POLLUTION lecture EnE203 updated.pdfAIR POLLUTION lecture EnE203 updated.pdf
AIR POLLUTION lecture EnE203 updated.pdf
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
 
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
 
Swimming pool mechanical components design.pptx
Swimming pool  mechanical components design.pptxSwimming pool  mechanical components design.pptx
Swimming pool mechanical components design.pptx
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
 
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
 
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
 
TOP 10 B TECH COLLEGES IN JAIPUR 2024.pptx
TOP 10 B TECH COLLEGES IN JAIPUR 2024.pptxTOP 10 B TECH COLLEGES IN JAIPUR 2024.pptx
TOP 10 B TECH COLLEGES IN JAIPUR 2024.pptx
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
 
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
 

8.4 roof leader

  • 1. In plumbing, a pipe installed to drain water from the roof gutters or roof catchment to the storm drain or other means of disposal. Also called a conductor, downspout, or roof drain. 8.4 Roof Leader
  • 4. Roof leader is either Exposed or Concealed Type Pit Drain Pipe
  • 6. Area of Roof A 10m x 20m = 200 m 𝟐 Solution A B Area of Roof B 8m x 20m = 160 m 𝟐
  • 7. Comments  For 20 meters length of the gutter the rains has to travel a long way, It might be overloaded and overflow. The terminal maybe clogged with dirty such as leaves, etc. Thus, We need two or more terminals for roof leader. D = 100mm & D = 90mm ( expensive or oversized ):
  • 8. Find the number of terminals 𝐃 = 𝟏𝟎𝟎𝐦𝐦  Cross section: A1 = πD2 /4 = 3.14 × 1002 /4 = 7850𝑚m2 Divide into two terminals: 3925𝑚𝑚2 Chooses D = 75mm ; A2 = π × 752 4 = 4416𝑚m2 > 3925mm2 D = 75mm OK !  D = 50mm, A = 1963𝑚m2 < 3925𝑚𝑚2  D = 90mm, A = 6359mm2 > 3925𝑚𝑚2 (Not economic) 𝐃 = 𝟗𝟎𝐦𝐦  Cross section: A1 = πD2 /4 = 3.14 × 902 /4 = 6359𝑚m2 Divide into two terminals: 3179𝑚𝑚2 Chooses D = 75mm ; A2 = π × 752 /4 = 4415𝑚m2 > 3179𝑚𝑚2 D = 75mm OK ! 
  • 9. Second Solution Roof A 𝐴 = 200𝑚2 2 terminals = 100𝑚2 Roof B 𝐴 = 160𝑚2 2 terminals = 80𝑚2 Choose 𝐷 = 75𝑚𝑚 Thank You !!!