SlideShare a Scribd company logo
Part1
Initial
State
Hour
1 0 0
Demand
(MW)
A B C Pmin (MW) Pmax (MW)
1 1 1 170 475 1 1 1 0 1 1
1 1 0 150 400 1 1 0 1 1 1
1 0 1 120 325 1 0 1 1 1 1
1 0 0 100 250 1 0 0 1 0 1
0 1 1 70 225 0 1 1 1 0 1
0 1 0 50 150 0 1 0 1 0 0
0 0 1 20 75 0 0 1 0 0 0
0 0 0 0 0 0 0 0 0 0 0
Unit
Pmin
(MW)
Pmax
(MW)
Min Up
(TD)
(h)
Min Down
(TU)
(h)
No Load
Cost
($)
Marginal
Cost
($MWh)
A 100 250 4 3 300 8
B 50 150 2 1 200 15
C 20 75 1 1 0 18
Unit
Status
00
01
10
11
All Cheapest
A B C
1 0 1 1 0 500 Green 150 100 0 0 2,550 2,550 1 1 0
2 0 1 0 1 200 Green 150 130 20 0 1,900 1,900 1 0 1
3 0 1 0 0 0 Green 150 150 0 0 1,500 1,500 1 0 0
1 200 Green 1 6,200 5,850
2 500 Green 2 5,850 5,650
3 700 Orang 3 5,650
1 0 Green 1 5,800 5,800
2 500 Orang 2 5,650
3 500 Orang 3 5,250 5,250
2 0 Green 2 5,100
3 200 Green 3 4,900 4900
4 0 Green 4 8,300
5 200 Green 5 8,100
6 500 Green 6 8,050 8,050
4 0 Green 4 8,100
5 0 Green 5 7,700
6 500 Green 6 7,850
4 0 Orang 4 7,950
5 200 Orang 5 8,100
6 0 Green 6 7,000
4 0 Orang 4 7,750
5 0 Orang 5 7,700
6 0 Green 6 6,800
4 0 Green 4 9,000
5 200 Green 5 8,800
6 500 Green 6 8,750
The cheapest path from analysing above table is to arrive at State 10 in Hour 3, with total cost of $ 6,800. Tracing back the path, below is the UC plan
Cost with Predecessor statesLowest
Transition
plus State
Cost
2,550
1,900
1,500
First Three Hours No Ramp Rate Nor Spinning Reserve were considered
1,000 11
500 01
200
Unit Data
Start Up Cost
($)
Initial Status
Units Possible Operating Scenarios
System
State 1 2 3
150 300
Colour Coding: at most one Orange can be in the UC plan
Hourly Demand
Unit has been OFF for time ˂ TD
Unit has been OFF for time ≥ TD
Unit has been ON for time ˂ TU
200 01
Description Action
Can NOT start unit
Can start unit
Can NOT Shut Down Unit
11 0 1 1
1 0 1
1 1 1
1 1 0
1 0 19
8
7
6
Can Shut Down Unit
Unit Status Description
Unit has been ON for time ≥ TU
To
State
From
State
250 50
250
5
4
1 1 0
Operating Cost
Start-up
Shutdown
Cost
Colour Code
Demand PA PC
1 1 1
System
State
Transition Costs
0300
300
10
State CostPB
300
2050
1700
1500
0
0
50
3450
3250
1 0 0
230 50 20
200
200
200
150
0
130
3,650
3,950
50 3200
2,100
2,300
2,100
50 0 2450
3,200
3,400
50 20 2650200
0 1 10 150 50 3350
1
1 0 0200 0 0 1900
180 0 20 2100
200 3,550
3,850
3,350
1,900
Unit Status
1 1
1
4,150
3,250
3,750
3,750
From State
1 1 0
1
1 1
01
1
1
2,650
2,850
3,150
1 0
2,450
2,450
2,950
1 0
1,900
1,900
7
8
9
1
2
3
4
5
6
11
100
6
100 3$ 0
$ 1500
$ 3,200
$ 1,900
TOTAL { 0, 3, 6, 10}
is $ 6,800
$ 6,800
$ 4,900
$ 1,500
Part 2
Initial
State
Hour
1 0 0
Demand
(MW)
A B C Pmin (MW) Pmax (MW)
1 1 1 170 475 1 1 1 0 1 1
## # 0
1 1 0 150 400 1 1 0 1 1 1
## # #
1 0 1 120 325 1 0 1 1 1 1
## #
1 0 0 100 250 1 0 0 1 0 1
## #
0 1 1 70 225 0 1 1 1 0 1
## #
0 1 0 50 150 0 1 0 0 0 0
## #
0 0 1 20 75 0 0 1 0 0 0
## #
0 0 0 0 0 0 0 0 0 0 0
Unit
Pmin
(MW)
Pmax
(MW)
Min Up
(TD)
(h)
Min Down
(TU)
(h)
No Load
Cost
($)
Marginal
Cost
($MWh)
A 100 250 4 3 300 8
B 50 150 2 1 200 15
C 20 75 1 1 0 18
Unit
Status
00
01
10
11
all
Cheapest
A B C
1 0 1 1 0 500 Green 150 100 0 0 2,550 2,550 1 1 0
2 0 1 0 1 200 Green 150 130 20 0 1,900 1,900 1 0 1
3 0 1 0 0 0 Green 150 150 0 0 1,500 1,500 1 0 0
1 200 Green 1 5,700 5650
2 500 Green 2 5,650 5650
3 700 Orang 3 5,650
1 0 Green 1 5,300 5300
2 500 Orang 2 5,450
3 500 Orang 3 5,250 5250
2 0 Green 2 5,100
3 200 Green 3 4,900 4900
4 0 Green 4 8,300 8,300
5 200 Green 5 8,100 8,150
6 500 Green 6 8,050 8,050
4 0 Green 4 8,100 8,100
5 0 Green 5 7,700 7,750
6 500 Green 6 7,850
4 0 Orang 4 7,750
5 200 Orang 5 7,600
6 0 Green 6 7,000
4 0 Orang 4 7,550
5 0 Orang 5 7,200
6 0 Green 6 6,800
4 0 Green 4 9,000 9,000
5 200 Green 5 8,800
6 500 Green 6 8,950
The cheapest path from analysing above table is to arrive at State 10, with total cost of $ 6,800. Tracing back the path, below is the UC plan
Observations:
> Operating Scenario 0 1 0 could not supply the 7% Reserve Demand since Pmax is 150MW which is the
lowest hour demand during the three hour period, however this did not affect at all since it was not
viable scenario in the original case
> The Base case scenarios are capable of supporting 7% load reserve, hint, the overall UC plan and
cost did not change
0 01,900
1,900
11 0 1 1 200 0 150 50 3350
3,350
0 1 13,550
3,850
10 1 0 0 200 200 0 0 1900
1,900
1
02,450
2,950
9 1 0 1 200 180 0 20 2100
2,100
1 0 12,300
2,100
8 1 1 0 200 150 50 0 2450
2,450
1
0250 0 50 3200
3,200
1
1
1
3,400
7 1 1 1 200 130 50 20 2650
2,650
1 1 12,850
3,150
6 1 0 1 300
1 1 13,950
4,150
5 1 1 0 300 250 50 0 3250
3,250
1 1 03,750
3,750
0 1700 1,900
0 1500 1,500
4 1 1 1 300 230 50 20 3450
3,650
State Cost
Lowest
Transition
plus State
Cost
From State
Cost with Predecessor states
Unit Status
50 2050 2,550
To
State
From
State
System
State
Start-up
Shutdown
Cost
Colour Code
Demand PA PB PC
Unit has been OFF for time ≥ TD Can start unit
Unit has been ON for time ˂ TU Can NOT Shut Down Unit
Unit has been ON for time ≥ TU Can Shut Down Unit
Transition Costs Operating Cost
200 01
Unit Status Description
Description Action
Unit has been OFF for time ˂ TD Can NOT start unit
Colour Coding: at most one Orange can be in the UC plan
Unit Data
Start Up Cost
($)
Initial Status
1,000 11
500 01
First Three Hours UC considering 7% Reserve of the hour demand and ignoring Ramp Rate
Units Possible Operating Scenarios
System
State
Hourly Demand
1 2 3
150 300 200
7
8
9
1
2
3
4
5
6
11
100
6
100 3
$ 200
$ 0
$ 1500
$ 3,200 $ 0
TOTAL { 0, 3, 6, 10}
is $ 6,800
$ 1,900
$ 6,800
$ 4,900
$ 1,500
Part 3
Initial
State
Hour
1 0 0
Demand
(MW)
A B C Pmin (MW) Pmax (MW)
1 1 1 170 475 1 1 1 0 1 1
## # 0
1 1 0 150 400 1 1 0 1 1 1
## # #
1 0 1 120 325 1 0 1 1 0 1
## #
1 0 0 100 250 1 0 0 1 0 1
## #
0 1 1 70 225 0 1 1 1 0 1
## #
0 1 0 50 150 0 1 0 1 0 0
## #
0 0 1 20 75 0 0 1 0 0 0
## #
0 0 0 0 0 0 0 0 0 0 0
Colour Coding:
Unit
Pmin
(MW)
Pmax
(MW)
Min Up
(TD)
(h)
Min Down
(TU)
(h)
No Load
Cost
($)
Marginal
Cost
($MWh)
A 100 250 4 3 300 8
B 50 150 2 1 200 15
C 20 75 1 1 0 18
Unit
Status
00
01
10
11
all Cheapest
A B C
1 0 1 1 0 500 Green 150 100 0 0 2,550 2,550 1 1 0
2 0 1 0 1 200 Green 150 130 20 0 1,900 1,900 1 0 1
3 0 1 0 0 0 Green 150 150 0 0 1,500 1,500 1 0 0
1 200 Green 155 40 1 6,785 6,165
2 500 Green 185 20 2 6,165 5,825
3 700 Orang 205 20 3 5,825
1 0 Green 1
2 500 Orang 185 0 2 6,105
3 500 Orang 205 0 3 5,565 5,565
2 0 Green 2
3 200 Green 3
4 0 Green 130 20 4 8,475
5 200 Green 5
4 0 Green 150 0 4 8,275
5 0 Green 150 0 5 8,015
9 4 1 0 1 0 Orang 200 180 20 4 8,265 1 0 1
10 4 1 0 0 0 Orang 200 200 0 4 8,065 1 0 0
4 0 Green 0 50 4 9,175
5 200 Green 0 50 5 9,115
The cheapest path from analysing above table is to arrive at State 8 with total cost of $ 8,015. Tracing back the path, below is the UC plan
Observations:
> Considering the Ramp rate of 5 MW/hr did affect the UC. Many transitions were not possible and
state 6 from the base case is not visible anymore.
> The cost of UC increase by $ 1,215 from the Base case UC
0 1 1
150 3350 3,550
0 2100 2,100
0 1900 1,900
11 0 1 1 200
150 3350 3,350
Ramp Constraints
8 1 1 0 200
50 2450 2,450
1 1 0
50 2450 2,450
7 1 1 1 200
50 2650 2,650
1 1 1
6 1 0 1 300
Ramp Constraints
1 0 1
Ramp Constraints
5 1 1 0 300
Ramp Constraints
1 1 0115 3705 4,205
95 3565 4,065
1 1 195 3765 4,265
75 3625 4,325
0 1500 1,500
4 1 1 1 300
105 4035 4,235
State + Start
up cost
From State
Cost with Predecessor states
Unit Status
50 2050 2,550
0 1700 1,900
Transition Costs Operating Cost
To
State
From
State
System
State
Start-up
Shutdown
Cost
Colour Code
Demand PA PB PC
State Cost
( Marginal +
No load)
Unit has been OFF for time ˂ TD Can NOT start unit
Unit has been OFF for time ≥ TD Can start unit
Unit has been ON for time ˂ TU Can NOT Shut Down Unit
Unit has been ON for time ≥ TU Can Shut Down Unit
500 01
200 01
Unit Status Description
Description Action
at most one Orange can be in the UC plan
Dashed Gray transitions are not possible due to TD Constraints
Red Transitions are not possible due to Ramp Rate constraints
Unit Data
Start Up Cost
($)
Initial Status
1,000 11
Units Possible Operating Scenarios
System
State
Hourly Demand
1 2 3
150 300 200
First Three Hours UC considering Ramp Rate and ignoring Reserve Requirement
7
8
9
1
2
3
4
5
11
100
5
8
0 3$ 0
$ 1500
$ 5,565
$ 0
TOTAL { 0, 3, 5, 8} is
$ 8,015
$ 8,015
6
$ 3,565
$ 2,450
$ 1,500
Part4
Initial
State
Hour
1 0 0
Demand
(MW)
A B C Pmin (MW) Pmax (MW)
1 1 1 170 475 1 1 1 0 1 1 1 1
1 1 0 150 400 1 1 0 1 1 1 1 1
1 0 1 120 325 1 0 1 1 1 1 1 0
1 0 0 100 250 1 0 0 1 0 1 0 0
0 1 1 70 225 0 1 1 1 0 1 0 0
0 1 0 50 150 0 1 0 1 0 0 0 0
0 0 1 20 75 0 0 1 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0
Unit
Pmin
(MW)
Pmax
(MW)
Min Up
(TD)
(h)
Min Down
(TU)
(h)
No Load
Cost
($)
Marginal
Cost
($MWh)
A 100 250 4 3 300 8
B 50 150 2 1 200 15
C 20 75 1 1 0 18
Unit
Status
00
01
10
11
All Cheapest
A B C
1 0 1 1 0 500 Green 150 100 0 0 2,550 2,550 1 1 0
2 0 1 0 1 200 Green 150 130 20 0 1,900 1,900 1 0 1
3 0 1 0 0 0 Green 150 150 0 0 1,500 1,500 1 0 0
1 200 Green 1 6,200 5,850
2 500 Green 2 5,850 5650
3 700 Orang 3 5,650
1 0 Green 1 5,800 5,800
2 500 Orang 2 5,650
3 500 Orang 3 5,250 5,250
2 0 Green 2 5,100
3 200 Green 3 4,900 4,900
4 0 Green 4 8,300 8,500 8,500
5 200 Green 5 8,100 8,650
6 500 Orang 6 8,050 8,050
4 0 Green 4 8,100 8,300
5 0 Green 5 7,700 8,250
6 500 Orang 6 7,850
4 0 Orang 4 7,950
5 200 Orang 5 8,100
6 0 Green 6 7,000
4 0 Orang 4 7,750 6,800
5 0 Orang 5 7,700
6 0 Green 6 6,800
4 0 Gray 4 9,000 9,200
5 200 Gray 5 8,800 9,350
6 500 Gray 6 8,750
7 0 Green 7 11,500
8 200 Green 8 11,350
9 500 Green 9 10,950
10 700 Green 10 10,950
7 0 Green 7 11,300
8 0 Green 8 10,950
9 500 Green 9 10,750
10 500 Green 10 10,550
7 0 Green 7 11,700
8 200 Green 8 11,250
9 0 Green 9 10,200
10 200 Green 10 10,200
12 0 Green 12 15,760
13 200 Green 13 15,560
14 500 Green 14 15,510
12 0 Green 12 13,700
13 0 Green 13 13,300
14 500 Green 14 13,450
The cheapest path from analysing above table is to arrive at State 16 with total cost of $ 13,300. Tracing back the path, below is the UC plan
1 15,010
5,310
16 1 1 0 400 0 150 50 2750
2,750
1 1 02,750
3,250
15 1 1 1 400 250 130 20 4810
4,810
1
1 0 1
3,400
3,200
3,400
3,750
14 1 0 1 300 250 0 50 3200
3,200
1 1
3,650
3,950
4,150
13 1 1 0 300 250 50 0 3250
3,250
1 1 0
3,250
3,750
12 1 1 1 300 230 50 20 3450
3,450
1
01,900
1,900
11 0 1 1 200 0 150 50 3350
3,350
0 1 13,550
3,850
10 1 0 0 200 200 0 0 1900
1,900
1
1200 150 50 0 2450
2,450
1
0
02,450
2,950
9 1 0 1 200 180 0 20 2100
2,100
1 0 12,300
2,100
8 1 1 0
1
3,400
7 1 1 1 200 130 50 20 2650
2,650
1 1 12,850
3,150
6 1 0 1 300 250 0 50 3200
3,200
1
1 1
0
13,950
4,150
5 1 1 0 300 250 50 0 3250
3,250
1 1 03,750
3,750
0 1500 1,500
4 1 1 1 300 230 50 20 3450
3,650
State + Start
up cost
From State
Cost with Predecessor states
Unit Status
50 2050 2,550
0 1700 1,900
Transition Costs Operating Cost
To
State
From
State
System
State
Start-up
Shutdown
Cost
Colour Code
Demand PA PB PC
State Cost
( Marginal +
No load)
Unit has been OFF for time ˂ TD Can NOT start unit
Unit has been OFF for time ≥ TD Can start unit
Unit has been ON for time ˂ TU Can NOT Shut Down Unit
Unit has been ON for time ≥ TU Can Shut Down Unit
500 01
200 01
Unit Status Description
Description Action
Colour Coding: at most one Orange can be in the UC plan
Dashed Gray transitions are not possible due to TD Constraints
Unit Data
Start Up Cost
($)
Initial Status
1,000 11
First Five Hours No Ramp Rate Nor Spinning Reserve were considered
Units Possible Operating Scenarios
System
State
Hourly Demand
1 2 3 4 5
150 300 200 300 400
7
8
9
1
2
3
4
5
6
11
100
6
100 3$ 0
$ 1500
$ 3,200 $ 6,800
TOTAL { 0, 3, 6, 10, 13, 16}
is $ 13,300
12
13
14
15
16
$ 1,500
$ 4,900
$ 1,900
13
$ 10,550
$ 3,250
16
$ 13,300
$ 2,750
$ 0

More Related Content

What's hot

Mc cormick xtx tier 3 (2007 2013) - xtx3 - 145 tractor service repair manual
Mc cormick xtx tier 3 (2007 2013) - xtx3 - 145 tractor service repair manualMc cormick xtx tier 3 (2007 2013) - xtx3 - 145 tractor service repair manual
Mc cormick xtx tier 3 (2007 2013) - xtx3 - 145 tractor service repair manual
ufjjsekkdmmd
 
TC74ACT244FT PSpice Model (Free SPICE Model)
TC74ACT244FT PSpice Model (Free SPICE Model)TC74ACT244FT PSpice Model (Free SPICE Model)
TC74ACT244FT PSpice Model (Free SPICE Model)Tsuyoshi Horigome
 
TC74ACT244FW PSpice Model (Free SPICE Model)
TC74ACT244FW PSpice Model (Free SPICE Model)TC74ACT244FW PSpice Model (Free SPICE Model)
TC74ACT244FW PSpice Model (Free SPICE Model)Tsuyoshi Horigome
 
Mc cormick x7.6 tier 4i (2013 ) - rpe2 - x7.680 tractor service repair manual
Mc cormick x7.6 tier 4i (2013  ) - rpe2 - x7.680 tractor service repair manualMc cormick x7.6 tier 4i (2013  ) - rpe2 - x7.680 tractor service repair manual
Mc cormick x7.6 tier 4i (2013 ) - rpe2 - x7.680 tractor service repair manual
ufjjsjefkkeskmd
 
Hoyer IE3 Electric Motors
Hoyer IE3 Electric MotorsHoyer IE3 Electric Motors
Hoyer IE3 Electric Motors
Arve
 
Electronically operated crimping machines - H50 46
Electronically operated crimping machines - H50 46Electronically operated crimping machines - H50 46
Electronically operated crimping machines - H50 46
Joe Pereira
 
Mc cormick xtx tier 3 (2007 2013) - xtx3 - 165 tractor service repair manual
Mc cormick xtx tier 3 (2007 2013) - xtx3 - 165 tractor service repair manualMc cormick xtx tier 3 (2007 2013) - xtx3 - 165 tractor service repair manual
Mc cormick xtx tier 3 (2007 2013) - xtx3 - 165 tractor service repair manual
fisejfjksekmm
 

What's hot (7)

Mc cormick xtx tier 3 (2007 2013) - xtx3 - 145 tractor service repair manual
Mc cormick xtx tier 3 (2007 2013) - xtx3 - 145 tractor service repair manualMc cormick xtx tier 3 (2007 2013) - xtx3 - 145 tractor service repair manual
Mc cormick xtx tier 3 (2007 2013) - xtx3 - 145 tractor service repair manual
 
TC74ACT244FT PSpice Model (Free SPICE Model)
TC74ACT244FT PSpice Model (Free SPICE Model)TC74ACT244FT PSpice Model (Free SPICE Model)
TC74ACT244FT PSpice Model (Free SPICE Model)
 
TC74ACT244FW PSpice Model (Free SPICE Model)
TC74ACT244FW PSpice Model (Free SPICE Model)TC74ACT244FW PSpice Model (Free SPICE Model)
TC74ACT244FW PSpice Model (Free SPICE Model)
 
Mc cormick x7.6 tier 4i (2013 ) - rpe2 - x7.680 tractor service repair manual
Mc cormick x7.6 tier 4i (2013  ) - rpe2 - x7.680 tractor service repair manualMc cormick x7.6 tier 4i (2013  ) - rpe2 - x7.680 tractor service repair manual
Mc cormick x7.6 tier 4i (2013 ) - rpe2 - x7.680 tractor service repair manual
 
Hoyer IE3 Electric Motors
Hoyer IE3 Electric MotorsHoyer IE3 Electric Motors
Hoyer IE3 Electric Motors
 
Electronically operated crimping machines - H50 46
Electronically operated crimping machines - H50 46Electronically operated crimping machines - H50 46
Electronically operated crimping machines - H50 46
 
Mc cormick xtx tier 3 (2007 2013) - xtx3 - 165 tractor service repair manual
Mc cormick xtx tier 3 (2007 2013) - xtx3 - 165 tractor service repair manualMc cormick xtx tier 3 (2007 2013) - xtx3 - 165 tractor service repair manual
Mc cormick xtx tier 3 (2007 2013) - xtx3 - 165 tractor service repair manual
 

Similar to 3 units commitment

APC in thermal power plant
APC in thermal power plant APC in thermal power plant
APC in thermal power plant
Molla Morshad
 
Catalog cs contactor d range
Catalog cs contactor d rangeCatalog cs contactor d range
Catalog cs contactor d range
Thuan Kieu
 
Catalog cs contactor d range-dienhathe.vn
Catalog cs contactor d range-dienhathe.vnCatalog cs contactor d range-dienhathe.vn
Catalog cs contactor d range-dienhathe.vn
Dien Ha The
 
Catalog cs contactor d range
Catalog cs contactor d rangeCatalog cs contactor d range
Catalog cs contactor d range
Dien Ha The
 
Nodal Insights for Generation Owners and Modeling with AURORAxmp
Nodal Insights for Generation Owners and Modeling with AURORAxmpNodal Insights for Generation Owners and Modeling with AURORAxmp
Nodal Insights for Generation Owners and Modeling with AURORAxmp
EPIS Inc
 
0244 Panorama I UPS Testing
0244 Panorama I UPS Testing0244 Panorama I UPS Testing
0244 Panorama I UPS TestingJoe Tate
 
JVL Intergrated Servo Motor in Stainless Steel
JVL Intergrated Servo Motor in Stainless Steel JVL Intergrated Servo Motor in Stainless Steel
JVL Intergrated Servo Motor in Stainless Steel
Electromate
 
Bảng giá mitsubishi 2020
Bảng giá mitsubishi 2020Bảng giá mitsubishi 2020
Bảng giá mitsubishi 2020
PhmAnhHuy
 
Original PNP Transistor 2SA2098 SA2098 2098 TO-220 New Sanyo
Original PNP Transistor 2SA2098 SA2098 2098 TO-220 New SanyoOriginal PNP Transistor 2SA2098 SA2098 2098 TO-220 New Sanyo
Original PNP Transistor 2SA2098 SA2098 2098 TO-220 New Sanyo
AUTHELECTRONIC
 
ABB POLIM-C..N High Voltage Surge Arresters AC up to 7.5 kV - AC Surge Arrest...
ABB POLIM-C..N High Voltage Surge Arresters AC up to 7.5 kV - AC Surge Arrest...ABB POLIM-C..N High Voltage Surge Arresters AC up to 7.5 kV - AC Surge Arrest...
ABB POLIM-C..N High Voltage Surge Arresters AC up to 7.5 kV - AC Surge Arrest...
Thorne & Derrick International
 
Cataloge ge 2.industrial components_dienhathe.com-1_record_plus
Cataloge ge 2.industrial components_dienhathe.com-1_record_plusCataloge ge 2.industrial components_dienhathe.com-1_record_plus
Cataloge ge 2.industrial components_dienhathe.com-1_record_plus
Dien Ha The
 
Cataloge ge 2.industrial components-1_record_plus
Cataloge ge 2.industrial components-1_record_plusCataloge ge 2.industrial components-1_record_plus
Cataloge ge 2.industrial components-1_record_plus
Thuan Kieu
 
Cataloge ge 2.industrial components-1_record_plus
Cataloge ge 2.industrial components-1_record_plusCataloge ge 2.industrial components-1_record_plus
Cataloge ge 2.industrial components-1_record_plus
Dien Ha The
 
Presentation (group)
Presentation (group)Presentation (group)
Presentation (group)Ankit Grover
 
Harmonic rh dc_servo_specsheet
Harmonic rh dc_servo_specsheetHarmonic rh dc_servo_specsheet
Harmonic rh dc_servo_specsheet
Electromate
 
Nir_pres_Hagana_v1
Nir_pres_Hagana_v1Nir_pres_Hagana_v1
Nir_pres_Hagana_v1Nir Morgulis
 
At500 catalog v.17
At500 catalog v.17At500 catalog v.17
At500 catalog v.17
Tiffany -Mao
 
Review Week_12_Customer_PulauPanggung (PT.BAS).pptx
Review Week_12_Customer_PulauPanggung (PT.BAS).pptxReview Week_12_Customer_PulauPanggung (PT.BAS).pptx
Review Week_12_Customer_PulauPanggung (PT.BAS).pptx
noelmanroe1
 
Haydon kerk ac_hybrid_actuators_specsheet
Haydon kerk ac_hybrid_actuators_specsheetHaydon kerk ac_hybrid_actuators_specsheet
Haydon kerk ac_hybrid_actuators_specsheet
Electromate
 
WEG Contactors Oveload Relays
WEG Contactors Oveload RelaysWEG Contactors Oveload Relays
WEG Contactors Oveload Relays
Allan Bernardino
 

Similar to 3 units commitment (20)

APC in thermal power plant
APC in thermal power plant APC in thermal power plant
APC in thermal power plant
 
Catalog cs contactor d range
Catalog cs contactor d rangeCatalog cs contactor d range
Catalog cs contactor d range
 
Catalog cs contactor d range-dienhathe.vn
Catalog cs contactor d range-dienhathe.vnCatalog cs contactor d range-dienhathe.vn
Catalog cs contactor d range-dienhathe.vn
 
Catalog cs contactor d range
Catalog cs contactor d rangeCatalog cs contactor d range
Catalog cs contactor d range
 
Nodal Insights for Generation Owners and Modeling with AURORAxmp
Nodal Insights for Generation Owners and Modeling with AURORAxmpNodal Insights for Generation Owners and Modeling with AURORAxmp
Nodal Insights for Generation Owners and Modeling with AURORAxmp
 
0244 Panorama I UPS Testing
0244 Panorama I UPS Testing0244 Panorama I UPS Testing
0244 Panorama I UPS Testing
 
JVL Intergrated Servo Motor in Stainless Steel
JVL Intergrated Servo Motor in Stainless Steel JVL Intergrated Servo Motor in Stainless Steel
JVL Intergrated Servo Motor in Stainless Steel
 
Bảng giá mitsubishi 2020
Bảng giá mitsubishi 2020Bảng giá mitsubishi 2020
Bảng giá mitsubishi 2020
 
Original PNP Transistor 2SA2098 SA2098 2098 TO-220 New Sanyo
Original PNP Transistor 2SA2098 SA2098 2098 TO-220 New SanyoOriginal PNP Transistor 2SA2098 SA2098 2098 TO-220 New Sanyo
Original PNP Transistor 2SA2098 SA2098 2098 TO-220 New Sanyo
 
ABB POLIM-C..N High Voltage Surge Arresters AC up to 7.5 kV - AC Surge Arrest...
ABB POLIM-C..N High Voltage Surge Arresters AC up to 7.5 kV - AC Surge Arrest...ABB POLIM-C..N High Voltage Surge Arresters AC up to 7.5 kV - AC Surge Arrest...
ABB POLIM-C..N High Voltage Surge Arresters AC up to 7.5 kV - AC Surge Arrest...
 
Cataloge ge 2.industrial components_dienhathe.com-1_record_plus
Cataloge ge 2.industrial components_dienhathe.com-1_record_plusCataloge ge 2.industrial components_dienhathe.com-1_record_plus
Cataloge ge 2.industrial components_dienhathe.com-1_record_plus
 
Cataloge ge 2.industrial components-1_record_plus
Cataloge ge 2.industrial components-1_record_plusCataloge ge 2.industrial components-1_record_plus
Cataloge ge 2.industrial components-1_record_plus
 
Cataloge ge 2.industrial components-1_record_plus
Cataloge ge 2.industrial components-1_record_plusCataloge ge 2.industrial components-1_record_plus
Cataloge ge 2.industrial components-1_record_plus
 
Presentation (group)
Presentation (group)Presentation (group)
Presentation (group)
 
Harmonic rh dc_servo_specsheet
Harmonic rh dc_servo_specsheetHarmonic rh dc_servo_specsheet
Harmonic rh dc_servo_specsheet
 
Nir_pres_Hagana_v1
Nir_pres_Hagana_v1Nir_pres_Hagana_v1
Nir_pres_Hagana_v1
 
At500 catalog v.17
At500 catalog v.17At500 catalog v.17
At500 catalog v.17
 
Review Week_12_Customer_PulauPanggung (PT.BAS).pptx
Review Week_12_Customer_PulauPanggung (PT.BAS).pptxReview Week_12_Customer_PulauPanggung (PT.BAS).pptx
Review Week_12_Customer_PulauPanggung (PT.BAS).pptx
 
Haydon kerk ac_hybrid_actuators_specsheet
Haydon kerk ac_hybrid_actuators_specsheetHaydon kerk ac_hybrid_actuators_specsheet
Haydon kerk ac_hybrid_actuators_specsheet
 
WEG Contactors Oveload Relays
WEG Contactors Oveload RelaysWEG Contactors Oveload Relays
WEG Contactors Oveload Relays
 

Recently uploaded

The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
SupreethSP4
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
ongomchris
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 

Recently uploaded (20)

The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 

3 units commitment

  • 1. Part1 Initial State Hour 1 0 0 Demand (MW) A B C Pmin (MW) Pmax (MW) 1 1 1 170 475 1 1 1 0 1 1 1 1 0 150 400 1 1 0 1 1 1 1 0 1 120 325 1 0 1 1 1 1 1 0 0 100 250 1 0 0 1 0 1 0 1 1 70 225 0 1 1 1 0 1 0 1 0 50 150 0 1 0 1 0 0 0 0 1 20 75 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Unit Pmin (MW) Pmax (MW) Min Up (TD) (h) Min Down (TU) (h) No Load Cost ($) Marginal Cost ($MWh) A 100 250 4 3 300 8 B 50 150 2 1 200 15 C 20 75 1 1 0 18 Unit Status 00 01 10 11 All Cheapest A B C 1 0 1 1 0 500 Green 150 100 0 0 2,550 2,550 1 1 0 2 0 1 0 1 200 Green 150 130 20 0 1,900 1,900 1 0 1 3 0 1 0 0 0 Green 150 150 0 0 1,500 1,500 1 0 0 1 200 Green 1 6,200 5,850 2 500 Green 2 5,850 5,650 3 700 Orang 3 5,650 1 0 Green 1 5,800 5,800 2 500 Orang 2 5,650 3 500 Orang 3 5,250 5,250 2 0 Green 2 5,100 3 200 Green 3 4,900 4900 4 0 Green 4 8,300 5 200 Green 5 8,100 6 500 Green 6 8,050 8,050 4 0 Green 4 8,100 5 0 Green 5 7,700 6 500 Green 6 7,850 4 0 Orang 4 7,950 5 200 Orang 5 8,100 6 0 Green 6 7,000 4 0 Orang 4 7,750 5 0 Orang 5 7,700 6 0 Green 6 6,800 4 0 Green 4 9,000 5 200 Green 5 8,800 6 500 Green 6 8,750 The cheapest path from analysing above table is to arrive at State 10 in Hour 3, with total cost of $ 6,800. Tracing back the path, below is the UC plan Cost with Predecessor statesLowest Transition plus State Cost 2,550 1,900 1,500 First Three Hours No Ramp Rate Nor Spinning Reserve were considered 1,000 11 500 01 200 Unit Data Start Up Cost ($) Initial Status Units Possible Operating Scenarios System State 1 2 3 150 300 Colour Coding: at most one Orange can be in the UC plan Hourly Demand Unit has been OFF for time ˂ TD Unit has been OFF for time ≥ TD Unit has been ON for time ˂ TU 200 01 Description Action Can NOT start unit Can start unit Can NOT Shut Down Unit 11 0 1 1 1 0 1 1 1 1 1 1 0 1 0 19 8 7 6 Can Shut Down Unit Unit Status Description Unit has been ON for time ≥ TU To State From State 250 50 250 5 4 1 1 0 Operating Cost Start-up Shutdown Cost Colour Code Demand PA PC 1 1 1 System State Transition Costs 0300 300 10 State CostPB 300 2050 1700 1500 0 0 50 3450 3250 1 0 0 230 50 20 200 200 200 150 0 130 3,650 3,950 50 3200 2,100 2,300 2,100 50 0 2450 3,200 3,400 50 20 2650200 0 1 10 150 50 3350 1 1 0 0200 0 0 1900 180 0 20 2100 200 3,550 3,850 3,350 1,900 Unit Status 1 1 1 4,150 3,250 3,750 3,750 From State 1 1 0 1 1 1 01 1 1 2,650 2,850 3,150 1 0 2,450 2,450 2,950 1 0 1,900 1,900 7 8 9 1 2 3 4 5 6 11 100 6 100 3$ 0 $ 1500 $ 3,200 $ 1,900 TOTAL { 0, 3, 6, 10} is $ 6,800 $ 6,800 $ 4,900 $ 1,500
  • 2. Part 2 Initial State Hour 1 0 0 Demand (MW) A B C Pmin (MW) Pmax (MW) 1 1 1 170 475 1 1 1 0 1 1 ## # 0 1 1 0 150 400 1 1 0 1 1 1 ## # # 1 0 1 120 325 1 0 1 1 1 1 ## # 1 0 0 100 250 1 0 0 1 0 1 ## # 0 1 1 70 225 0 1 1 1 0 1 ## # 0 1 0 50 150 0 1 0 0 0 0 ## # 0 0 1 20 75 0 0 1 0 0 0 ## # 0 0 0 0 0 0 0 0 0 0 0 Unit Pmin (MW) Pmax (MW) Min Up (TD) (h) Min Down (TU) (h) No Load Cost ($) Marginal Cost ($MWh) A 100 250 4 3 300 8 B 50 150 2 1 200 15 C 20 75 1 1 0 18 Unit Status 00 01 10 11 all Cheapest A B C 1 0 1 1 0 500 Green 150 100 0 0 2,550 2,550 1 1 0 2 0 1 0 1 200 Green 150 130 20 0 1,900 1,900 1 0 1 3 0 1 0 0 0 Green 150 150 0 0 1,500 1,500 1 0 0 1 200 Green 1 5,700 5650 2 500 Green 2 5,650 5650 3 700 Orang 3 5,650 1 0 Green 1 5,300 5300 2 500 Orang 2 5,450 3 500 Orang 3 5,250 5250 2 0 Green 2 5,100 3 200 Green 3 4,900 4900 4 0 Green 4 8,300 8,300 5 200 Green 5 8,100 8,150 6 500 Green 6 8,050 8,050 4 0 Green 4 8,100 8,100 5 0 Green 5 7,700 7,750 6 500 Green 6 7,850 4 0 Orang 4 7,750 5 200 Orang 5 7,600 6 0 Green 6 7,000 4 0 Orang 4 7,550 5 0 Orang 5 7,200 6 0 Green 6 6,800 4 0 Green 4 9,000 9,000 5 200 Green 5 8,800 6 500 Green 6 8,950 The cheapest path from analysing above table is to arrive at State 10, with total cost of $ 6,800. Tracing back the path, below is the UC plan Observations: > Operating Scenario 0 1 0 could not supply the 7% Reserve Demand since Pmax is 150MW which is the lowest hour demand during the three hour period, however this did not affect at all since it was not viable scenario in the original case > The Base case scenarios are capable of supporting 7% load reserve, hint, the overall UC plan and cost did not change 0 01,900 1,900 11 0 1 1 200 0 150 50 3350 3,350 0 1 13,550 3,850 10 1 0 0 200 200 0 0 1900 1,900 1 02,450 2,950 9 1 0 1 200 180 0 20 2100 2,100 1 0 12,300 2,100 8 1 1 0 200 150 50 0 2450 2,450 1 0250 0 50 3200 3,200 1 1 1 3,400 7 1 1 1 200 130 50 20 2650 2,650 1 1 12,850 3,150 6 1 0 1 300 1 1 13,950 4,150 5 1 1 0 300 250 50 0 3250 3,250 1 1 03,750 3,750 0 1700 1,900 0 1500 1,500 4 1 1 1 300 230 50 20 3450 3,650 State Cost Lowest Transition plus State Cost From State Cost with Predecessor states Unit Status 50 2050 2,550 To State From State System State Start-up Shutdown Cost Colour Code Demand PA PB PC Unit has been OFF for time ≥ TD Can start unit Unit has been ON for time ˂ TU Can NOT Shut Down Unit Unit has been ON for time ≥ TU Can Shut Down Unit Transition Costs Operating Cost 200 01 Unit Status Description Description Action Unit has been OFF for time ˂ TD Can NOT start unit Colour Coding: at most one Orange can be in the UC plan Unit Data Start Up Cost ($) Initial Status 1,000 11 500 01 First Three Hours UC considering 7% Reserve of the hour demand and ignoring Ramp Rate Units Possible Operating Scenarios System State Hourly Demand 1 2 3 150 300 200 7 8 9 1 2 3 4 5 6 11 100 6 100 3 $ 200 $ 0 $ 1500 $ 3,200 $ 0 TOTAL { 0, 3, 6, 10} is $ 6,800 $ 1,900 $ 6,800 $ 4,900 $ 1,500
  • 3. Part 3 Initial State Hour 1 0 0 Demand (MW) A B C Pmin (MW) Pmax (MW) 1 1 1 170 475 1 1 1 0 1 1 ## # 0 1 1 0 150 400 1 1 0 1 1 1 ## # # 1 0 1 120 325 1 0 1 1 0 1 ## # 1 0 0 100 250 1 0 0 1 0 1 ## # 0 1 1 70 225 0 1 1 1 0 1 ## # 0 1 0 50 150 0 1 0 1 0 0 ## # 0 0 1 20 75 0 0 1 0 0 0 ## # 0 0 0 0 0 0 0 0 0 0 0 Colour Coding: Unit Pmin (MW) Pmax (MW) Min Up (TD) (h) Min Down (TU) (h) No Load Cost ($) Marginal Cost ($MWh) A 100 250 4 3 300 8 B 50 150 2 1 200 15 C 20 75 1 1 0 18 Unit Status 00 01 10 11 all Cheapest A B C 1 0 1 1 0 500 Green 150 100 0 0 2,550 2,550 1 1 0 2 0 1 0 1 200 Green 150 130 20 0 1,900 1,900 1 0 1 3 0 1 0 0 0 Green 150 150 0 0 1,500 1,500 1 0 0 1 200 Green 155 40 1 6,785 6,165 2 500 Green 185 20 2 6,165 5,825 3 700 Orang 205 20 3 5,825 1 0 Green 1 2 500 Orang 185 0 2 6,105 3 500 Orang 205 0 3 5,565 5,565 2 0 Green 2 3 200 Green 3 4 0 Green 130 20 4 8,475 5 200 Green 5 4 0 Green 150 0 4 8,275 5 0 Green 150 0 5 8,015 9 4 1 0 1 0 Orang 200 180 20 4 8,265 1 0 1 10 4 1 0 0 0 Orang 200 200 0 4 8,065 1 0 0 4 0 Green 0 50 4 9,175 5 200 Green 0 50 5 9,115 The cheapest path from analysing above table is to arrive at State 8 with total cost of $ 8,015. Tracing back the path, below is the UC plan Observations: > Considering the Ramp rate of 5 MW/hr did affect the UC. Many transitions were not possible and state 6 from the base case is not visible anymore. > The cost of UC increase by $ 1,215 from the Base case UC 0 1 1 150 3350 3,550 0 2100 2,100 0 1900 1,900 11 0 1 1 200 150 3350 3,350 Ramp Constraints 8 1 1 0 200 50 2450 2,450 1 1 0 50 2450 2,450 7 1 1 1 200 50 2650 2,650 1 1 1 6 1 0 1 300 Ramp Constraints 1 0 1 Ramp Constraints 5 1 1 0 300 Ramp Constraints 1 1 0115 3705 4,205 95 3565 4,065 1 1 195 3765 4,265 75 3625 4,325 0 1500 1,500 4 1 1 1 300 105 4035 4,235 State + Start up cost From State Cost with Predecessor states Unit Status 50 2050 2,550 0 1700 1,900 Transition Costs Operating Cost To State From State System State Start-up Shutdown Cost Colour Code Demand PA PB PC State Cost ( Marginal + No load) Unit has been OFF for time ˂ TD Can NOT start unit Unit has been OFF for time ≥ TD Can start unit Unit has been ON for time ˂ TU Can NOT Shut Down Unit Unit has been ON for time ≥ TU Can Shut Down Unit 500 01 200 01 Unit Status Description Description Action at most one Orange can be in the UC plan Dashed Gray transitions are not possible due to TD Constraints Red Transitions are not possible due to Ramp Rate constraints Unit Data Start Up Cost ($) Initial Status 1,000 11 Units Possible Operating Scenarios System State Hourly Demand 1 2 3 150 300 200 First Three Hours UC considering Ramp Rate and ignoring Reserve Requirement 7 8 9 1 2 3 4 5 11 100 5 8 0 3$ 0 $ 1500 $ 5,565 $ 0 TOTAL { 0, 3, 5, 8} is $ 8,015 $ 8,015 6 $ 3,565 $ 2,450 $ 1,500
  • 4. Part4 Initial State Hour 1 0 0 Demand (MW) A B C Pmin (MW) Pmax (MW) 1 1 1 170 475 1 1 1 0 1 1 1 1 1 1 0 150 400 1 1 0 1 1 1 1 1 1 0 1 120 325 1 0 1 1 1 1 1 0 1 0 0 100 250 1 0 0 1 0 1 0 0 0 1 1 70 225 0 1 1 1 0 1 0 0 0 1 0 50 150 0 1 0 1 0 0 0 0 0 0 1 20 75 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Unit Pmin (MW) Pmax (MW) Min Up (TD) (h) Min Down (TU) (h) No Load Cost ($) Marginal Cost ($MWh) A 100 250 4 3 300 8 B 50 150 2 1 200 15 C 20 75 1 1 0 18 Unit Status 00 01 10 11 All Cheapest A B C 1 0 1 1 0 500 Green 150 100 0 0 2,550 2,550 1 1 0 2 0 1 0 1 200 Green 150 130 20 0 1,900 1,900 1 0 1 3 0 1 0 0 0 Green 150 150 0 0 1,500 1,500 1 0 0 1 200 Green 1 6,200 5,850 2 500 Green 2 5,850 5650 3 700 Orang 3 5,650 1 0 Green 1 5,800 5,800 2 500 Orang 2 5,650 3 500 Orang 3 5,250 5,250 2 0 Green 2 5,100 3 200 Green 3 4,900 4,900 4 0 Green 4 8,300 8,500 8,500 5 200 Green 5 8,100 8,650 6 500 Orang 6 8,050 8,050 4 0 Green 4 8,100 8,300 5 0 Green 5 7,700 8,250 6 500 Orang 6 7,850 4 0 Orang 4 7,950 5 200 Orang 5 8,100 6 0 Green 6 7,000 4 0 Orang 4 7,750 6,800 5 0 Orang 5 7,700 6 0 Green 6 6,800 4 0 Gray 4 9,000 9,200 5 200 Gray 5 8,800 9,350 6 500 Gray 6 8,750 7 0 Green 7 11,500 8 200 Green 8 11,350 9 500 Green 9 10,950 10 700 Green 10 10,950 7 0 Green 7 11,300 8 0 Green 8 10,950 9 500 Green 9 10,750 10 500 Green 10 10,550 7 0 Green 7 11,700 8 200 Green 8 11,250 9 0 Green 9 10,200 10 200 Green 10 10,200 12 0 Green 12 15,760 13 200 Green 13 15,560 14 500 Green 14 15,510 12 0 Green 12 13,700 13 0 Green 13 13,300 14 500 Green 14 13,450 The cheapest path from analysing above table is to arrive at State 16 with total cost of $ 13,300. Tracing back the path, below is the UC plan 1 15,010 5,310 16 1 1 0 400 0 150 50 2750 2,750 1 1 02,750 3,250 15 1 1 1 400 250 130 20 4810 4,810 1 1 0 1 3,400 3,200 3,400 3,750 14 1 0 1 300 250 0 50 3200 3,200 1 1 3,650 3,950 4,150 13 1 1 0 300 250 50 0 3250 3,250 1 1 0 3,250 3,750 12 1 1 1 300 230 50 20 3450 3,450 1 01,900 1,900 11 0 1 1 200 0 150 50 3350 3,350 0 1 13,550 3,850 10 1 0 0 200 200 0 0 1900 1,900 1 1200 150 50 0 2450 2,450 1 0 02,450 2,950 9 1 0 1 200 180 0 20 2100 2,100 1 0 12,300 2,100 8 1 1 0 1 3,400 7 1 1 1 200 130 50 20 2650 2,650 1 1 12,850 3,150 6 1 0 1 300 250 0 50 3200 3,200 1 1 1 0 13,950 4,150 5 1 1 0 300 250 50 0 3250 3,250 1 1 03,750 3,750 0 1500 1,500 4 1 1 1 300 230 50 20 3450 3,650 State + Start up cost From State Cost with Predecessor states Unit Status 50 2050 2,550 0 1700 1,900 Transition Costs Operating Cost To State From State System State Start-up Shutdown Cost Colour Code Demand PA PB PC State Cost ( Marginal + No load) Unit has been OFF for time ˂ TD Can NOT start unit Unit has been OFF for time ≥ TD Can start unit Unit has been ON for time ˂ TU Can NOT Shut Down Unit Unit has been ON for time ≥ TU Can Shut Down Unit 500 01 200 01 Unit Status Description Description Action Colour Coding: at most one Orange can be in the UC plan Dashed Gray transitions are not possible due to TD Constraints Unit Data Start Up Cost ($) Initial Status 1,000 11 First Five Hours No Ramp Rate Nor Spinning Reserve were considered Units Possible Operating Scenarios System State Hourly Demand 1 2 3 4 5 150 300 200 300 400 7 8 9 1 2 3 4 5 6 11 100 6 100 3$ 0 $ 1500 $ 3,200 $ 6,800 TOTAL { 0, 3, 6, 10, 13, 16} is $ 13,300 12 13 14 15 16 $ 1,500 $ 4,900 $ 1,900 13 $ 10,550 $ 3,250 16 $ 13,300 $ 2,750 $ 0