By Hui Qin Teoh
07th October 2016
LIMELIGHT PROJECT
Project Description
76% of project/program managers' time in the Huawei team space in MRD is spent
generating reports instead of managing vendors.
To improve efficiency of the PMO space in MRD, this project:
• Developed various reports that can be generated automatically.
• Distributed workload within the team to run different reports.
• Established a governance process to maintain the quality of the vendor’s data that is
uploaded into the MRD centralised database system.
With the success of this project, it is planned that the process improvements can be
expanded to external teams in the future.
.
Project Completed:
07/10/2016
Hard Financial Benefits
Cost savings (Type 1)
• Reduced total time spent on producing report by 49% (Approx. 156 hours per month)
• Prevented additional cost spend on purchasing additional space to store data in share
folder.
• Decreased printing cost by removing tasks that required printing.
Revenue enhancement (Type 3)
• Enhanced speed of mobile sites delivery which allow the sites to generate revenue once
the sites are taking traffic.
Soft Benefits
Productivity improvement (Type 2)
• Enlarged job scope of each individual which assist with their career development.
• Enriched team’s motivation created by sense of achievement.
• Generated positive energy in working environment as a result of reduced frustration
caused by to over processing .
• Increased delivery numbers as a result of spending more time managing vendors.
• Empowered team members to identify process problem and improve process.
• Introduced stronger team spirit by introducing tasks to be done as a team.
• Enhanced productivity in our team.
Customer Experience Benefits
• Decreased waiting time for financial team & material forecast team to received
forecast report.
• Removed waiting time by providing easy access to trackers for senior management.
• Shorten delivery times for critical sites that was requested by sales/Optus Business
teams .
• Improved mobile network coverage in specify regions to accommodate special events’
capacity requirements.
• Enabled marketing team to extract forecast data out of our database to assist them to
plan SA3 marketing strategy.
Personnel
Limelight: Hui Qin Teoh
Blackbelt: Libby Heydon
Process Owner: David William
MRD Process improvement
Project Started:
26/08/2016
Process Improvement Process
Learn to See
Type of Waste Issues Solutions Tools
Waiting Time • 80% of project manager’s time are spent
generating reports instead of managing
vendor.
• Automate reports by using Excel
macro and Excel formula.
• Dedicate one resources to generate
automation reports instead of each
project managers generate their
own for their project only.
• Additional milestone added into
database.
Standardisation
Movement • Forecast generated by program manager
was not shared.
• This prevents project managers
completing their month end delivery
report.
• Proposed program manager to
stored forecast on share folder upon
due date.
Standardisation
Motion • Running out of space in share folder
• Folder name outdated due to project
name changes as the result of
restructure.
• Folders are not stored in a centralised
location.
• Team members not aware of where
documents are located
• Spring clean for share folder
• Folder needs to be renamed
• Create tracker to track locations for
important documents
5S
Process Errors • Vendor needs to reflect their actual &
forecast milestone into Optus database.
• Optus database is not accurate, and
should act as single source of truth.
• Find the root cause & implement
changes to the current work
process.
Cause & Effect Diagram
Generate Reports Process
1. Print Full
Dashboard
Report
Once a week - Full Dashboard Report
2. Request
report from
database
3. Download
report
4. Reflect
report data
into tracker
5. Retrieve
vendor report
from email
6. Reflect
report data
into tracker
7. Combine data
and prepare Full
Dashboard Report
8. Print new Full
Dashboard Report
9. Compare current
and previous
dashboard report
Daily - Engineering order pending raised & sites not fully ready for services
10. Print Full
Dashboard
Report
11. Request
report from
database
12. Download
report
13. Produce list of engineering
order pending raised
14. Produce list of sites not
fully ready for services.
To Be
Continued
Generate Reports Process
15. Prepare Deep Dive
breakdown report
Once a week – Deep Dive Breakdown Report & SA3 Greening Report
16. Prepare SA3
Greening report
Once a month – Month End Delivery Report
17. Prepare Month End
Delivery Report
Waste of waiting time
Problem:
• 76% of project manager’s time are spent generating reports instead of managing vendor:
• Multiple reports required by senior management and external teams:
1. Full Dashboard Report weekly.
2. Month End Delivery Report.
3. Deep Dive Breakdown Report.
4. SA3 Greening report.
• Current report that is generated from system contains too much data, need to spend time to filter:
1. Engineering order pending raised.
2. Sites not fully ready for services. (Some technologies still not ready but can’t be easily
spotted in the report)
• Some data is not captured into database and required to be tracked manually into a separate
tracker.
Solutions:
• Automate reports by using Excel macro and Excel formula.
• Dedicate one resource to generate automation reports instead of each project manager generating their
own for their project only.
• Additional milestone added into database.
Tools:
• Standardisation
Standard Work Combination Sheet
Date 05/10/2016 Zoom in/out
Monthly Requirement 1 Walking
Takt Time 85.92 Hr Computer Interaction
Process Name: MRD PM monthly reporting task Queue Time (waiting)
Task/ Activity Wlk Cl QT
No. time
per month
No.
Resou
rcers
1 Print Full Dashboard report 0.08 4 2
2 Request report from database 0.08 4 2
3 Download report 0.17 4 2
4 Reflect report data into tracker 0.08 4 2
5
Retrieve vendor report from
email
0.08 4 2
6 Reflect report data into tracker 0.08 4 2
7
Combine data and prepare Full
Dashboard report
2 4 2
8
Print new Full Dashboard
report
0.08 4 2
9
Compare current and previous
dashboard report
0.5 4 2
10 Print Full Dashboard report 0.08 20 2
11 Request report from database 0.08 20 2
12 Download report 0.17 20 2
13
Produce list of engineering
order pending raised
0.5 20 2
14
Produce list of site not fully
ready for services.
2 20 2
15
Prepare Deep dive break down
report
8 4 2
16 Prepare SA3 greening report 4 4 2
17
Prepare month end delivery
report
4 1 2
Totals : (0.08+0.08+0.17+0.08+0.08+0.08+2+0.08+0.5)*4*2 +
(0.08+0.08+0.17+0.5+2)*20*2 + (8+4)*4*2 + 4*2 = 242.4 hr
Total working hr per month = 20*8*2 = 320
Total time spend on reporting = 242.2/320 = 76%
Processing Times (hours)
Zio - Zoom in/out Wlk – Walking CI – Computer Interaction QT - Queue Time
5 10 15 20 25 30 35 40 45 50
Page 1 of 2
Standard Work Combination Sheet
Date 05/10/2016 Zoom in/out
Monthly Requirement 1 Walking
Takt Time 85.92 Hr Computer Interaction
Process Name: MRD PM monthly reporting task Queue Time (waiting)Page 2 of 2
Task/ Activity Wlk Cl QT
No. time
per month
No.
Resou
rcers
1 Print Full Dashboard report 0.08 4 2
2 Request report from database 0.08 4 2
3 Download report 0.17 4 2
4 Reflect report data into tracker 0.08 4 2
5
Retrieve vendor report from
email
0.08 4 2
6 Reflect report data into tracker 0.08 4 2
7
Combine data and prepare Full
Dashboard report
2 4 2
8
Print new Full Dashboard
report
0.08 4 2
9
Compare current and previous
dashboard report
0.5 4 2
10 Print Full Dashboard report 0.08 20 2
11 Request report from database 0.08 20 2
12 Download report 0.17 20 2
13
Produce list of engineering
order pending raised
0.5 20 2
14
Produce list of site not fully
ready for services.
2 20 2
15
Prepare Deep dive break down
report
8 4 2
16 Prepare SA3 greening report 4 4 2
17
Prepare month end delivery
report
4 1 2
Totals : (0.08+0.08+0.17+0.08+0.08+0.08+2+0.08+0.5)*4*2 +
(0.08+0.08+0.17+0.5+2)*20*2 + (8+4)*4*2 + 4*2 = 242.4 hr
Total working hr per month = 20*8*2 = 320
Total time spend on reporting = 242.2/320 = 76%
Processing Times (hours)
Zio - Zoom in/out Wlk – Walking CI – Computer Interaction QT - Queue Time
40 60 80 100 120 140 160 180 200 220 240
Generate Reports Process
1. Print Full
Dashboard
Report
Once a week - Full Dashboard Report weekly
2. Request
report from
database
3. Download
report
4. Reflect
report data
into tracker
5. Retrieve
vendor report
from email
6. Reflect
report data
into tracker
7. Combine data
and prepare Full
Dashboard Report
8. Print new Full
Dashboard Report
9. Compare current
and previous
dashboard report
Daily - Engineering order pending raised & Site not fully ready for services
10. Print Full
Dashboard
Report
11. Request
report from
database
12. Download
report
13. Produce list of engineering
order pending raised
14. Produce list of sites not
fully ready for services.
To Be
Continued
Task 5, 6 & 7 removed by
introducing vendor to
upload data into our
database & develop
tracker with Excel
formulas
Task 10, 13 & 14
removed by developing
tracker with Excel
Marco to filter lists
Generate Reports Process
15. Prepare Deep Dive
Breakdown report
Once a week – Deep Dive Breakdown Report & SA3 Greening Report
16. Prepare SA3
greening report
Once a month – Month End Delivery Report
17. Prepare Month End
Delivery Report
Task 16 removed by
developing tracker with
Excel Marco & Excel
formulas
Halve work time by
dedicating one resource to
perform this task
Generate Month End Delivery Reports Process
1. Request report
from database
2. Download
report
3. Request report
from program
manager
4. Received
response from
program manager
5. Print both
reports
6. Analysis and
consolidate
report
7. Upload Manual
forecast and actual
in database
Waste of Movement
Problem:
• Forecast report generated by program manager was not shared. This required a
request to be sent to program manager.
• This prevented project managers to complete their month end delivery report.
Solutions:
• Proposed program manager to store forecast report on share folder upon due
date.
Tools:
• Standardisation
Standard Work Combination Sheet
Date 29/09/2016 Work (physical)
Monthly Requirement 1 Walking
Takt Time 60 mins Computer Interaction
Process Name: Month End Delivery Report Queue Time (waiting)
Work Instruction No. 1
Task/ Activity Wrk Wlk Cl QT
1
Request report from
database
5
2 Download report 10
3
Request report from
program manager
5
4
Received response from
program manager
30
5 Print both reports 5
6
Analysis and
consolidate report
30
7
Upload Manual forecast
and actual in database
10
Totals : 5+10+5+30+5+30+10 = 95 mins
* With assumption: queue time is 30 mins for
Program manager to response.
Processing Times (minutes)
Wrk – Work Physical Wlk – Walking CI – Computer Interaction QT - Queue Time
10 20 30 40 50 60 70 80 90 100 110
Generate Month End Delivery Reports Process
1. Request report
from database
2. Download
report
3. Request report
from program
manager
4. Received
response from
program manager
5. Print both
reports
6. Analysis and
consolidate
report
7. Upload Manual
forecast and actual
in database
Task 3 & 4 removed by
proposed program
manager to store
forecast report on share
folder upon due date.
Standard Work Combination Sheet
Date 29/09/2016 Work (physical)
Monthly Requirement 1 Walking
Takt Time 60 mins Computer Interaction
Process Name: Month End Delivery Report Queue Time (waiting)
Work Instruction No. 1
Task/ Activity Wrk Wlk Cl QT
1
Request report from
database
5
2 Download report 10
3
Request report from
program manager
5
4
Received response from
program manager
30
5 Print both reports 5
6
Analysis and
consolidate report
30
7
Upload Manual forecast
and actual in database
10
Totals : 5+10+5+30+10 = 60 mins
* Task 3 & 4 remove as program manager is storing
forecast on share folder upon due date.
Processing Times (minutes)
Wrk – Work Physical Wlk – Walking CI – Computer Interaction QT - Queue Time
10 20 30 40 50 60 70 80 90 100 110
Waste of Motion
Problem:
• Running out of space in share folder.
• Folders are not stored in a centralised location which makes it
challenging for program manager to find data.
• Folder name is outdated due to project name changes as the result of
restructure.
• Memory reaching capacity which slows down driver and increases wait
time.
• Team members are not aware where documents are located.
Solutions:
• Spring clean the share folder.
• Folder need to be renamed
• Create tracker to log locations for important documents.
Tools:
• 5S.
5S
S0: Starting
• Meeting with team members.
• Agree on new folders structures.
• Create new folders.
S1: Sort
• Move files into new locations.
• Unwanted files goes into “unwanted” folder. (Just in case
other team members might still want the files)
• Agreement from team members before remove files in
Unwanted” folder.
S2: Set in Order:
• Update “File Location”
S3: Shine:
• Set reminder in Outlook to clean up twice a year.
S4: Standardise:
• Agree with stakeholders to maintain the current format.
• Agree with stakeholders the auditing timeline.
• Provide quick training to new members to follow the
standard.
S5: Sustain:
• Schedule audit quarterly.
• Setup quick session before clean up day to reinforce
expectations.
Attendees:
1. Program Manager
2. Project Manager 1
3. Project Manager 2
4. Project Manager 3
5. Project Coordinator
Data Upload Process
Data updated
in vendor’s
database
Optus project
manager use
data to generate
report and
manage vendor
Vendor
compiles FTP
Files and set it
to Optus
File
uploaded
Data reflected
into Optus
database
Waste of Process Errors
Problem:
• Vendor needs to reflect their actual & forecast milestone into Optus database.
• Optus database which should act as single source of truth is not accurate.
• Multiple reports have been scattered around via email.
• Request additional reports from vendor to understand which milestones have
been completed.
• Additional effort required to micro manage milestone to be signed off in
database.
Solutions:
• Find the root cause & implement changes to the current work process.
Tools:
• Cause & Effect Diagram.
Cause & Effect Diagram
Data is not accurate
in Optus database
ManpowerMachinesMeasurement
Mother Nature Materials Methods
1
No Handover document
No work manual
Change of Resources
Milestone not actualised in
vendor’s database
1
1
1
New Database implemented
in vendor space
1
1
No check list
Full Milestone
report was not shared
1
Attendees:
1. Vendor Program Manager
2. Optus Program Manager
3. Vendor Project Manager
4. Optus Project Manager
5. Vendor Database
administrator
6. Optus Database
administrator 1
7. Optus Database
administrator 2
Optus firewall
prevents data upload
Action
Issues Action
Milestone not actualised due to
human error.
1) Setup governance meeting.
2) Block actualisation of successor milestone if
depended milestone is not actualised.
Milestone not actualised due to
owner of milestone not definite
1) Define milestone’s owner.
2) Setup responsible matrix.
3) Automation actualising some milestone.
Full Milestone report was not shared 1) Instructed internal team to share the report.
New Database implemented in
vendor space
1) Vendor to work on transferring data from new
database to Optus database.
Optus firewall prevents data upload 1) Ensure specific resource have the required access to
upload file.
201601007 Limelight - Hui Qin Teoh

More Related Content

What's hot

Tab ware maintenance scheduling software & equipment maintenance software
Tab ware maintenance scheduling software & equipment maintenance softwareTab ware maintenance scheduling software & equipment maintenance software
Tab ware maintenance scheduling software & equipment maintenance software
AsanHerio
 
Ga 09 G2 Charles Tatum Portfolio
Ga 09 G2 Charles Tatum PortfolioGa 09 G2 Charles Tatum Portfolio
Ga 09 G2 Charles Tatum Portfolio
Ctatum
 
Project management system-recource management
Project management system-recource managementProject management system-recource management
Project management system-recource management
Adapt Software India Private Limited
 
Primavera - Tutorial
Primavera - TutorialPrimavera - Tutorial
Primavera - Tutorial
Rajeev Sharma
 
[WEBINAR] Understanding the 2014 Coverage Gap Discount Program (CGDP) Invoice...
[WEBINAR] Understanding the 2014 Coverage Gap Discount Program (CGDP) Invoice...[WEBINAR] Understanding the 2014 Coverage Gap Discount Program (CGDP) Invoice...
[WEBINAR] Understanding the 2014 Coverage Gap Discount Program (CGDP) Invoice...
Paragon Solutions
 
Growth Management and Development Dashboard
Growth Management and Development DashboardGrowth Management and Development Dashboard
Growth Management and Development Dashboard
Safe Software
 
EBS Plan Viewer - An excel based Planning workbench
EBS Plan Viewer - An excel based Planning workbenchEBS Plan Viewer - An excel based Planning workbench
EBS Plan Viewer - An excel based Planning workbench
Amit Sharma
 
Project resource planning
Project resource planningProject resource planning
Project resource planning
New Haven Technologies
 
9b Case Study BP Final Process Maps 2007
9b Case Study BP Final Process Maps 20079b Case Study BP Final Process Maps 2007
9b Case Study BP Final Process Maps 2007
Ralph W Peters
 
DataCenter-PackagedServices
DataCenter-PackagedServicesDataCenter-PackagedServices
DataCenter-PackagedServicesTyler Carlson
 
DataCenter-PackagedServices
DataCenter-PackagedServicesDataCenter-PackagedServices
DataCenter-PackagedServicesPrahlad Reddy
 

What's hot (12)

Tab ware maintenance scheduling software & equipment maintenance software
Tab ware maintenance scheduling software & equipment maintenance softwareTab ware maintenance scheduling software & equipment maintenance software
Tab ware maintenance scheduling software & equipment maintenance software
 
Ga 09 G2 Charles Tatum Portfolio
Ga 09 G2 Charles Tatum PortfolioGa 09 G2 Charles Tatum Portfolio
Ga 09 G2 Charles Tatum Portfolio
 
Project management system-recource management
Project management system-recource managementProject management system-recource management
Project management system-recource management
 
Primavera - Tutorial
Primavera - TutorialPrimavera - Tutorial
Primavera - Tutorial
 
[WEBINAR] Understanding the 2014 Coverage Gap Discount Program (CGDP) Invoice...
[WEBINAR] Understanding the 2014 Coverage Gap Discount Program (CGDP) Invoice...[WEBINAR] Understanding the 2014 Coverage Gap Discount Program (CGDP) Invoice...
[WEBINAR] Understanding the 2014 Coverage Gap Discount Program (CGDP) Invoice...
 
Growth Management and Development Dashboard
Growth Management and Development DashboardGrowth Management and Development Dashboard
Growth Management and Development Dashboard
 
EBS Plan Viewer - An excel based Planning workbench
EBS Plan Viewer - An excel based Planning workbenchEBS Plan Viewer - An excel based Planning workbench
EBS Plan Viewer - An excel based Planning workbench
 
Project resource planning
Project resource planningProject resource planning
Project resource planning
 
9b Case Study BP Final Process Maps 2007
9b Case Study BP Final Process Maps 20079b Case Study BP Final Process Maps 2007
9b Case Study BP Final Process Maps 2007
 
DataCenter-PackagedServices
DataCenter-PackagedServicesDataCenter-PackagedServices
DataCenter-PackagedServices
 
DataCenter-PackagedServices
DataCenter-PackagedServicesDataCenter-PackagedServices
DataCenter-PackagedServices
 
tcc primavera
tcc primaveratcc primavera
tcc primavera
 

Viewers also liked

Tarea 2
Tarea 2Tarea 2
Trabajo finalinformatica
Trabajo finalinformaticaTrabajo finalinformatica
Trabajo finalinformatica
Magali Aimara Diaz
 
Historia de la odontologia busqueda en dialnet
Historia de la odontologia busqueda en dialnetHistoria de la odontologia busqueda en dialnet
Historia de la odontologia busqueda en dialnet
FRAN LERATE DIAZ
 
Power Point_Intro to Distributors-compressed
Power Point_Intro to Distributors-compressedPower Point_Intro to Distributors-compressed
Power Point_Intro to Distributors-compressedJo-Ann Chui
 
Signing up in sound of space
Signing up in sound of spaceSigning up in sound of space
Signing up in sound of space
Sound Of Space
 
Evo binary - Is Planı
Evo binary - Is PlanıEvo binary - Is Planı
Evo binary - Is Planı
Kazandiran Firsat
 
Tecnología celular (2)
Tecnología celular (2)Tecnología celular (2)
Tecnología celular (2)
xiomara borja aponte
 
A combizmok kvantitatív MR vizsgálata excentrikus és nyújtásos-rövidüléses ko...
A combizmok kvantitatív MR vizsgálata excentrikus és nyújtásos-rövidüléses ko...A combizmok kvantitatív MR vizsgálata excentrikus és nyújtásos-rövidüléses ko...
A combizmok kvantitatív MR vizsgálata excentrikus és nyújtásos-rövidüléses ko...Katalin Tóth
 
Tarea 3
Tarea 3Tarea 3
TS & QS Summer 2016 Lunch and Learn - QS Only
TS & QS Summer 2016 Lunch and Learn  - QS OnlyTS & QS Summer 2016 Lunch and Learn  - QS Only
TS & QS Summer 2016 Lunch and Learn - QS OnlyDaniel Chang
 
Csökkentett csőfeszültséggel végzett CT vizsgálatok, technika, lehetséges alk...
Csökkentett csőfeszültséggel végzett CT vizsgálatok, technika, lehetséges alk...Csökkentett csőfeszültséggel végzett CT vizsgálatok, technika, lehetséges alk...
Csökkentett csőfeszültséggel végzett CT vizsgálatok, technika, lehetséges alk...Katalin Tóth
 
Riesgos fisicos
Riesgos fisicosRiesgos fisicos
Læringsteori
LæringsteoriLæringsteori
Læringsteori
Thorbjørn Skjævestad
 
Presentation on Road Network
 Presentation on Road Network Presentation on Road Network
Presentation on Road Network
Sulaiman Aliyu Umar
 
науково практична конференція
науково практична  конференціянауково практична  конференція
науково практична конференція
Ирина Шершавец
 
jls CV-Portfolio 2016 Bil
jls CV-Portfolio 2016 Biljls CV-Portfolio 2016 Bil
jls CV-Portfolio 2016 BilJoyce Scharf
 
Sistema operativo de windows y linux
Sistema operativo de windows y linuxSistema operativo de windows y linux
Sistema operativo de windows y linux
Paula Vallades
 
Supper moto october 2016
Supper moto   october 2016Supper moto   october 2016
Supper moto october 2016
Quang Lê
 

Viewers also liked (19)

Tarea 2
Tarea 2Tarea 2
Tarea 2
 
Trabajo finalinformatica
Trabajo finalinformaticaTrabajo finalinformatica
Trabajo finalinformatica
 
Historia de la odontologia busqueda en dialnet
Historia de la odontologia busqueda en dialnetHistoria de la odontologia busqueda en dialnet
Historia de la odontologia busqueda en dialnet
 
Power Point_Intro to Distributors-compressed
Power Point_Intro to Distributors-compressedPower Point_Intro to Distributors-compressed
Power Point_Intro to Distributors-compressed
 
Signing up in sound of space
Signing up in sound of spaceSigning up in sound of space
Signing up in sound of space
 
Evo binary - Is Planı
Evo binary - Is PlanıEvo binary - Is Planı
Evo binary - Is Planı
 
Tecnología celular (2)
Tecnología celular (2)Tecnología celular (2)
Tecnología celular (2)
 
A combizmok kvantitatív MR vizsgálata excentrikus és nyújtásos-rövidüléses ko...
A combizmok kvantitatív MR vizsgálata excentrikus és nyújtásos-rövidüléses ko...A combizmok kvantitatív MR vizsgálata excentrikus és nyújtásos-rövidüléses ko...
A combizmok kvantitatív MR vizsgálata excentrikus és nyújtásos-rövidüléses ko...
 
Tarea 3
Tarea 3Tarea 3
Tarea 3
 
TS & QS Summer 2016 Lunch and Learn - QS Only
TS & QS Summer 2016 Lunch and Learn  - QS OnlyTS & QS Summer 2016 Lunch and Learn  - QS Only
TS & QS Summer 2016 Lunch and Learn - QS Only
 
WarwoodFinalReport
WarwoodFinalReportWarwoodFinalReport
WarwoodFinalReport
 
Csökkentett csőfeszültséggel végzett CT vizsgálatok, technika, lehetséges alk...
Csökkentett csőfeszültséggel végzett CT vizsgálatok, technika, lehetséges alk...Csökkentett csőfeszültséggel végzett CT vizsgálatok, technika, lehetséges alk...
Csökkentett csőfeszültséggel végzett CT vizsgálatok, technika, lehetséges alk...
 
Riesgos fisicos
Riesgos fisicosRiesgos fisicos
Riesgos fisicos
 
Læringsteori
LæringsteoriLæringsteori
Læringsteori
 
Presentation on Road Network
 Presentation on Road Network Presentation on Road Network
Presentation on Road Network
 
науково практична конференція
науково практична  конференціянауково практична  конференція
науково практична конференція
 
jls CV-Portfolio 2016 Bil
jls CV-Portfolio 2016 Biljls CV-Portfolio 2016 Bil
jls CV-Portfolio 2016 Bil
 
Sistema operativo de windows y linux
Sistema operativo de windows y linuxSistema operativo de windows y linux
Sistema operativo de windows y linux
 
Supper moto october 2016
Supper moto   october 2016Supper moto   october 2016
Supper moto october 2016
 

Similar to 201601007 Limelight - Hui Qin Teoh

Automating and Scheduling Data Usage and Reporting
Automating and Scheduling Data Usage and Reporting Automating and Scheduling Data Usage and Reporting
Automating and Scheduling Data Usage and Reporting
Safe Software
 
British American Tobacco GP Upgrade
British American Tobacco GP UpgradeBritish American Tobacco GP Upgrade
British American Tobacco GP Upgrade
Cedar Consulting
 
Cfp guidance template_kpc_hr_cockpit
Cfp guidance template_kpc_hr_cockpitCfp guidance template_kpc_hr_cockpit
Cfp guidance template_kpc_hr_cockpit
Loic Rakotoarivony
 
PWA Dashboards Presentation
PWA Dashboards PresentationPWA Dashboards Presentation
PWA Dashboards PresentationRyan Werge
 
rough-work.pptx
rough-work.pptxrough-work.pptx
rough-work.pptx
sharpan
 
Innovate 2014 - Customizing Your Rational Insight Deployment (workshop)
Innovate 2014 - Customizing Your Rational Insight Deployment (workshop)Innovate 2014 - Customizing Your Rational Insight Deployment (workshop)
Innovate 2014 - Customizing Your Rational Insight Deployment (workshop)
Marc Nehme
 
Tableau @ Spil Games
Tableau @ Spil GamesTableau @ Spil Games
Tableau @ Spil GamesRob Winters
 
2024.02.14 Monthly Operational Review_Jan'24.pptx
2024.02.14 Monthly Operational Review_Jan'24.pptx2024.02.14 Monthly Operational Review_Jan'24.pptx
2024.02.14 Monthly Operational Review_Jan'24.pptx
ismailsheriff14
 
07_Extending Workforce Management_Verizon (3)dp
07_Extending Workforce Management_Verizon (3)dp07_Extending Workforce Management_Verizon (3)dp
07_Extending Workforce Management_Verizon (3)dpDebra L Phillips
 
Mid-term Review Meeting - WP6
Mid-term Review Meeting - WP6Mid-term Review Meeting - WP6
Mid-term Review Meeting - WP6
SLOPE Project
 
205560 jeppesen’s upgrade to primavera p6 release 8.2 agile approach
205560 jeppesen’s upgrade to primavera p6 release 8.2 agile approach205560 jeppesen’s upgrade to primavera p6 release 8.2 agile approach
205560 jeppesen’s upgrade to primavera p6 release 8.2 agile approach
p6academy
 
204720 unifier at xcel energy
204720 unifier at xcel energy204720 unifier at xcel energy
204720 unifier at xcel energy
p6academy
 
rough-work.pptx
rough-work.pptxrough-work.pptx
rough-work.pptx
sharpan
 
MPUG Webinar - Creating a Portfolio KPI Report in Project Online
MPUG Webinar - Creating a Portfolio KPI Report in Project OnlineMPUG Webinar - Creating a Portfolio KPI Report in Project Online
MPUG Webinar - Creating a Portfolio KPI Report in Project Online
Raphael Santos
 
1 of my Data Migration Projects at ABB
1 of my Data Migration Projects at ABB1 of my Data Migration Projects at ABB
1 of my Data Migration Projects at ABBTommy Lombard
 
Performance tracking
Performance tracking Performance tracking
Performance tracking Reza Fahlevi
 
FEWS Data Analysis with ARR2016
FEWS Data Analysis with ARR2016 FEWS Data Analysis with ARR2016
FEWS Data Analysis with ARR2016
Lindsay Millard
 
Building the BI system and analytics capabilities at the company based on Rea...
Building the BI system and analytics capabilities at the company based on Rea...Building the BI system and analytics capabilities at the company based on Rea...
Building the BI system and analytics capabilities at the company based on Rea...
GameCamp
 

Similar to 201601007 Limelight - Hui Qin Teoh (20)

Automating and Scheduling Data Usage and Reporting
Automating and Scheduling Data Usage and Reporting Automating and Scheduling Data Usage and Reporting
Automating and Scheduling Data Usage and Reporting
 
British American Tobacco GP Upgrade
British American Tobacco GP UpgradeBritish American Tobacco GP Upgrade
British American Tobacco GP Upgrade
 
Cfp guidance template_kpc_hr_cockpit
Cfp guidance template_kpc_hr_cockpitCfp guidance template_kpc_hr_cockpit
Cfp guidance template_kpc_hr_cockpit
 
PWA Dashboards Presentation
PWA Dashboards PresentationPWA Dashboards Presentation
PWA Dashboards Presentation
 
rough-work.pptx
rough-work.pptxrough-work.pptx
rough-work.pptx
 
Innovate 2014 - Customizing Your Rational Insight Deployment (workshop)
Innovate 2014 - Customizing Your Rational Insight Deployment (workshop)Innovate 2014 - Customizing Your Rational Insight Deployment (workshop)
Innovate 2014 - Customizing Your Rational Insight Deployment (workshop)
 
Tableau @ Spil Games
Tableau @ Spil GamesTableau @ Spil Games
Tableau @ Spil Games
 
2024.02.14 Monthly Operational Review_Jan'24.pptx
2024.02.14 Monthly Operational Review_Jan'24.pptx2024.02.14 Monthly Operational Review_Jan'24.pptx
2024.02.14 Monthly Operational Review_Jan'24.pptx
 
07_Extending Workforce Management_Verizon (3)dp
07_Extending Workforce Management_Verizon (3)dp07_Extending Workforce Management_Verizon (3)dp
07_Extending Workforce Management_Verizon (3)dp
 
Mid-term Review Meeting - WP6
Mid-term Review Meeting - WP6Mid-term Review Meeting - WP6
Mid-term Review Meeting - WP6
 
IQA_Project
IQA_ProjectIQA_Project
IQA_Project
 
205560 jeppesen’s upgrade to primavera p6 release 8.2 agile approach
205560 jeppesen’s upgrade to primavera p6 release 8.2 agile approach205560 jeppesen’s upgrade to primavera p6 release 8.2 agile approach
205560 jeppesen’s upgrade to primavera p6 release 8.2 agile approach
 
CV Khader Dec'16
CV Khader Dec'16CV Khader Dec'16
CV Khader Dec'16
 
204720 unifier at xcel energy
204720 unifier at xcel energy204720 unifier at xcel energy
204720 unifier at xcel energy
 
rough-work.pptx
rough-work.pptxrough-work.pptx
rough-work.pptx
 
MPUG Webinar - Creating a Portfolio KPI Report in Project Online
MPUG Webinar - Creating a Portfolio KPI Report in Project OnlineMPUG Webinar - Creating a Portfolio KPI Report in Project Online
MPUG Webinar - Creating a Portfolio KPI Report in Project Online
 
1 of my Data Migration Projects at ABB
1 of my Data Migration Projects at ABB1 of my Data Migration Projects at ABB
1 of my Data Migration Projects at ABB
 
Performance tracking
Performance tracking Performance tracking
Performance tracking
 
FEWS Data Analysis with ARR2016
FEWS Data Analysis with ARR2016 FEWS Data Analysis with ARR2016
FEWS Data Analysis with ARR2016
 
Building the BI system and analytics capabilities at the company based on Rea...
Building the BI system and analytics capabilities at the company based on Rea...Building the BI system and analytics capabilities at the company based on Rea...
Building the BI system and analytics capabilities at the company based on Rea...
 

201601007 Limelight - Hui Qin Teoh

  • 1. By Hui Qin Teoh 07th October 2016 LIMELIGHT PROJECT
  • 2. Project Description 76% of project/program managers' time in the Huawei team space in MRD is spent generating reports instead of managing vendors. To improve efficiency of the PMO space in MRD, this project: • Developed various reports that can be generated automatically. • Distributed workload within the team to run different reports. • Established a governance process to maintain the quality of the vendor’s data that is uploaded into the MRD centralised database system. With the success of this project, it is planned that the process improvements can be expanded to external teams in the future. . Project Completed: 07/10/2016 Hard Financial Benefits Cost savings (Type 1) • Reduced total time spent on producing report by 49% (Approx. 156 hours per month) • Prevented additional cost spend on purchasing additional space to store data in share folder. • Decreased printing cost by removing tasks that required printing. Revenue enhancement (Type 3) • Enhanced speed of mobile sites delivery which allow the sites to generate revenue once the sites are taking traffic. Soft Benefits Productivity improvement (Type 2) • Enlarged job scope of each individual which assist with their career development. • Enriched team’s motivation created by sense of achievement. • Generated positive energy in working environment as a result of reduced frustration caused by to over processing . • Increased delivery numbers as a result of spending more time managing vendors. • Empowered team members to identify process problem and improve process. • Introduced stronger team spirit by introducing tasks to be done as a team. • Enhanced productivity in our team. Customer Experience Benefits • Decreased waiting time for financial team & material forecast team to received forecast report. • Removed waiting time by providing easy access to trackers for senior management. • Shorten delivery times for critical sites that was requested by sales/Optus Business teams . • Improved mobile network coverage in specify regions to accommodate special events’ capacity requirements. • Enabled marketing team to extract forecast data out of our database to assist them to plan SA3 marketing strategy. Personnel Limelight: Hui Qin Teoh Blackbelt: Libby Heydon Process Owner: David William MRD Process improvement Project Started: 26/08/2016
  • 4. Learn to See Type of Waste Issues Solutions Tools Waiting Time • 80% of project manager’s time are spent generating reports instead of managing vendor. • Automate reports by using Excel macro and Excel formula. • Dedicate one resources to generate automation reports instead of each project managers generate their own for their project only. • Additional milestone added into database. Standardisation Movement • Forecast generated by program manager was not shared. • This prevents project managers completing their month end delivery report. • Proposed program manager to stored forecast on share folder upon due date. Standardisation Motion • Running out of space in share folder • Folder name outdated due to project name changes as the result of restructure. • Folders are not stored in a centralised location. • Team members not aware of where documents are located • Spring clean for share folder • Folder needs to be renamed • Create tracker to track locations for important documents 5S Process Errors • Vendor needs to reflect their actual & forecast milestone into Optus database. • Optus database is not accurate, and should act as single source of truth. • Find the root cause & implement changes to the current work process. Cause & Effect Diagram
  • 5.
  • 6. Generate Reports Process 1. Print Full Dashboard Report Once a week - Full Dashboard Report 2. Request report from database 3. Download report 4. Reflect report data into tracker 5. Retrieve vendor report from email 6. Reflect report data into tracker 7. Combine data and prepare Full Dashboard Report 8. Print new Full Dashboard Report 9. Compare current and previous dashboard report Daily - Engineering order pending raised & sites not fully ready for services 10. Print Full Dashboard Report 11. Request report from database 12. Download report 13. Produce list of engineering order pending raised 14. Produce list of sites not fully ready for services. To Be Continued
  • 7. Generate Reports Process 15. Prepare Deep Dive breakdown report Once a week – Deep Dive Breakdown Report & SA3 Greening Report 16. Prepare SA3 Greening report Once a month – Month End Delivery Report 17. Prepare Month End Delivery Report
  • 8. Waste of waiting time Problem: • 76% of project manager’s time are spent generating reports instead of managing vendor: • Multiple reports required by senior management and external teams: 1. Full Dashboard Report weekly. 2. Month End Delivery Report. 3. Deep Dive Breakdown Report. 4. SA3 Greening report. • Current report that is generated from system contains too much data, need to spend time to filter: 1. Engineering order pending raised. 2. Sites not fully ready for services. (Some technologies still not ready but can’t be easily spotted in the report) • Some data is not captured into database and required to be tracked manually into a separate tracker. Solutions: • Automate reports by using Excel macro and Excel formula. • Dedicate one resource to generate automation reports instead of each project manager generating their own for their project only. • Additional milestone added into database. Tools: • Standardisation
  • 9. Standard Work Combination Sheet Date 05/10/2016 Zoom in/out Monthly Requirement 1 Walking Takt Time 85.92 Hr Computer Interaction Process Name: MRD PM monthly reporting task Queue Time (waiting) Task/ Activity Wlk Cl QT No. time per month No. Resou rcers 1 Print Full Dashboard report 0.08 4 2 2 Request report from database 0.08 4 2 3 Download report 0.17 4 2 4 Reflect report data into tracker 0.08 4 2 5 Retrieve vendor report from email 0.08 4 2 6 Reflect report data into tracker 0.08 4 2 7 Combine data and prepare Full Dashboard report 2 4 2 8 Print new Full Dashboard report 0.08 4 2 9 Compare current and previous dashboard report 0.5 4 2 10 Print Full Dashboard report 0.08 20 2 11 Request report from database 0.08 20 2 12 Download report 0.17 20 2 13 Produce list of engineering order pending raised 0.5 20 2 14 Produce list of site not fully ready for services. 2 20 2 15 Prepare Deep dive break down report 8 4 2 16 Prepare SA3 greening report 4 4 2 17 Prepare month end delivery report 4 1 2 Totals : (0.08+0.08+0.17+0.08+0.08+0.08+2+0.08+0.5)*4*2 + (0.08+0.08+0.17+0.5+2)*20*2 + (8+4)*4*2 + 4*2 = 242.4 hr Total working hr per month = 20*8*2 = 320 Total time spend on reporting = 242.2/320 = 76% Processing Times (hours) Zio - Zoom in/out Wlk – Walking CI – Computer Interaction QT - Queue Time 5 10 15 20 25 30 35 40 45 50 Page 1 of 2
  • 10. Standard Work Combination Sheet Date 05/10/2016 Zoom in/out Monthly Requirement 1 Walking Takt Time 85.92 Hr Computer Interaction Process Name: MRD PM monthly reporting task Queue Time (waiting)Page 2 of 2 Task/ Activity Wlk Cl QT No. time per month No. Resou rcers 1 Print Full Dashboard report 0.08 4 2 2 Request report from database 0.08 4 2 3 Download report 0.17 4 2 4 Reflect report data into tracker 0.08 4 2 5 Retrieve vendor report from email 0.08 4 2 6 Reflect report data into tracker 0.08 4 2 7 Combine data and prepare Full Dashboard report 2 4 2 8 Print new Full Dashboard report 0.08 4 2 9 Compare current and previous dashboard report 0.5 4 2 10 Print Full Dashboard report 0.08 20 2 11 Request report from database 0.08 20 2 12 Download report 0.17 20 2 13 Produce list of engineering order pending raised 0.5 20 2 14 Produce list of site not fully ready for services. 2 20 2 15 Prepare Deep dive break down report 8 4 2 16 Prepare SA3 greening report 4 4 2 17 Prepare month end delivery report 4 1 2 Totals : (0.08+0.08+0.17+0.08+0.08+0.08+2+0.08+0.5)*4*2 + (0.08+0.08+0.17+0.5+2)*20*2 + (8+4)*4*2 + 4*2 = 242.4 hr Total working hr per month = 20*8*2 = 320 Total time spend on reporting = 242.2/320 = 76% Processing Times (hours) Zio - Zoom in/out Wlk – Walking CI – Computer Interaction QT - Queue Time 40 60 80 100 120 140 160 180 200 220 240
  • 11. Generate Reports Process 1. Print Full Dashboard Report Once a week - Full Dashboard Report weekly 2. Request report from database 3. Download report 4. Reflect report data into tracker 5. Retrieve vendor report from email 6. Reflect report data into tracker 7. Combine data and prepare Full Dashboard Report 8. Print new Full Dashboard Report 9. Compare current and previous dashboard report Daily - Engineering order pending raised & Site not fully ready for services 10. Print Full Dashboard Report 11. Request report from database 12. Download report 13. Produce list of engineering order pending raised 14. Produce list of sites not fully ready for services. To Be Continued Task 5, 6 & 7 removed by introducing vendor to upload data into our database & develop tracker with Excel formulas Task 10, 13 & 14 removed by developing tracker with Excel Marco to filter lists
  • 12. Generate Reports Process 15. Prepare Deep Dive Breakdown report Once a week – Deep Dive Breakdown Report & SA3 Greening Report 16. Prepare SA3 greening report Once a month – Month End Delivery Report 17. Prepare Month End Delivery Report Task 16 removed by developing tracker with Excel Marco & Excel formulas Halve work time by dedicating one resource to perform this task
  • 13.
  • 14. Generate Month End Delivery Reports Process 1. Request report from database 2. Download report 3. Request report from program manager 4. Received response from program manager 5. Print both reports 6. Analysis and consolidate report 7. Upload Manual forecast and actual in database
  • 15. Waste of Movement Problem: • Forecast report generated by program manager was not shared. This required a request to be sent to program manager. • This prevented project managers to complete their month end delivery report. Solutions: • Proposed program manager to store forecast report on share folder upon due date. Tools: • Standardisation
  • 16. Standard Work Combination Sheet Date 29/09/2016 Work (physical) Monthly Requirement 1 Walking Takt Time 60 mins Computer Interaction Process Name: Month End Delivery Report Queue Time (waiting) Work Instruction No. 1 Task/ Activity Wrk Wlk Cl QT 1 Request report from database 5 2 Download report 10 3 Request report from program manager 5 4 Received response from program manager 30 5 Print both reports 5 6 Analysis and consolidate report 30 7 Upload Manual forecast and actual in database 10 Totals : 5+10+5+30+5+30+10 = 95 mins * With assumption: queue time is 30 mins for Program manager to response. Processing Times (minutes) Wrk – Work Physical Wlk – Walking CI – Computer Interaction QT - Queue Time 10 20 30 40 50 60 70 80 90 100 110
  • 17. Generate Month End Delivery Reports Process 1. Request report from database 2. Download report 3. Request report from program manager 4. Received response from program manager 5. Print both reports 6. Analysis and consolidate report 7. Upload Manual forecast and actual in database Task 3 & 4 removed by proposed program manager to store forecast report on share folder upon due date.
  • 18. Standard Work Combination Sheet Date 29/09/2016 Work (physical) Monthly Requirement 1 Walking Takt Time 60 mins Computer Interaction Process Name: Month End Delivery Report Queue Time (waiting) Work Instruction No. 1 Task/ Activity Wrk Wlk Cl QT 1 Request report from database 5 2 Download report 10 3 Request report from program manager 5 4 Received response from program manager 30 5 Print both reports 5 6 Analysis and consolidate report 30 7 Upload Manual forecast and actual in database 10 Totals : 5+10+5+30+10 = 60 mins * Task 3 & 4 remove as program manager is storing forecast on share folder upon due date. Processing Times (minutes) Wrk – Work Physical Wlk – Walking CI – Computer Interaction QT - Queue Time 10 20 30 40 50 60 70 80 90 100 110
  • 19.
  • 20. Waste of Motion Problem: • Running out of space in share folder. • Folders are not stored in a centralised location which makes it challenging for program manager to find data. • Folder name is outdated due to project name changes as the result of restructure. • Memory reaching capacity which slows down driver and increases wait time. • Team members are not aware where documents are located. Solutions: • Spring clean the share folder. • Folder need to be renamed • Create tracker to log locations for important documents. Tools: • 5S.
  • 21. 5S S0: Starting • Meeting with team members. • Agree on new folders structures. • Create new folders. S1: Sort • Move files into new locations. • Unwanted files goes into “unwanted” folder. (Just in case other team members might still want the files) • Agreement from team members before remove files in Unwanted” folder. S2: Set in Order: • Update “File Location” S3: Shine: • Set reminder in Outlook to clean up twice a year. S4: Standardise: • Agree with stakeholders to maintain the current format. • Agree with stakeholders the auditing timeline. • Provide quick training to new members to follow the standard. S5: Sustain: • Schedule audit quarterly. • Setup quick session before clean up day to reinforce expectations. Attendees: 1. Program Manager 2. Project Manager 1 3. Project Manager 2 4. Project Manager 3 5. Project Coordinator
  • 22.
  • 23. Data Upload Process Data updated in vendor’s database Optus project manager use data to generate report and manage vendor Vendor compiles FTP Files and set it to Optus File uploaded Data reflected into Optus database
  • 24. Waste of Process Errors Problem: • Vendor needs to reflect their actual & forecast milestone into Optus database. • Optus database which should act as single source of truth is not accurate. • Multiple reports have been scattered around via email. • Request additional reports from vendor to understand which milestones have been completed. • Additional effort required to micro manage milestone to be signed off in database. Solutions: • Find the root cause & implement changes to the current work process. Tools: • Cause & Effect Diagram.
  • 25. Cause & Effect Diagram Data is not accurate in Optus database ManpowerMachinesMeasurement Mother Nature Materials Methods 1 No Handover document No work manual Change of Resources Milestone not actualised in vendor’s database 1 1 1 New Database implemented in vendor space 1 1 No check list Full Milestone report was not shared 1 Attendees: 1. Vendor Program Manager 2. Optus Program Manager 3. Vendor Project Manager 4. Optus Project Manager 5. Vendor Database administrator 6. Optus Database administrator 1 7. Optus Database administrator 2 Optus firewall prevents data upload
  • 26. Action Issues Action Milestone not actualised due to human error. 1) Setup governance meeting. 2) Block actualisation of successor milestone if depended milestone is not actualised. Milestone not actualised due to owner of milestone not definite 1) Define milestone’s owner. 2) Setup responsible matrix. 3) Automation actualising some milestone. Full Milestone report was not shared 1) Instructed internal team to share the report. New Database implemented in vendor space 1) Vendor to work on transferring data from new database to Optus database. Optus firewall prevents data upload 1) Ensure specific resource have the required access to upload file.