2014 FINAL QUARTER BUDGET REVIEW, Morobe Province, Laguna Hotel, NCD
1. 2014 FINAL QUARTER
BUDGET REVIEW,
LAGUNA HOTEL,
NCD
Presented by:
Kingsford Kassen
PROVINCIAL WORKS MANAGER
MOROBE PROVINCE
DEPARTMENT OF
WORKS
Morobe Provincial Office
2. Morobe Province has a Total Land Area of 33, 525
km2
Total estimated Population in Morobe Province is
about 539, 404.
The population occupies a total area of 11, 708 km2
National Road in Morobe Province has a total length
of 328.607 km
Provincial /Minor Roads has a total length of 505 km &
146.439km captured in RAMS
BACKGROUND
3.
4. NOTABLE ACHIEVEMENTS
23.293km of Lae City Roads completed.
8.0km of Unitech Roads fully sealed.
10km of Bukawa Road Re-gravelled
12km of New Kumalu Bypass Road fully completed
60km of Menyama-Aseki Road maintained
7.5km of Wau Highway Road widening complete under TSSP
130.89km of Highlands Highway maintained under TSSP
32.5km of Ramu Highway maintained under TSSP
Construction of Mongi & Buming Bridge, Finschafen District
Maintenance of Mape Ring Road (30km), Finschafen District
Maintenance of Kasuka-Tinibi (13km), Nawaeb District
5. SUMMARY OF FUNDINGS
Development Budget:
Total CFC issued: K 188, 517, 130.00
Total Expenditure to-date: K186, 613, 841.37
Balance to-be Committed: K 1, 903, 288.63
Trust Accounts:
Total CFC issued: K 38, 740, 520.00
Total Expenditure to-date: K 30, 747, 656.00
Balance to-be Committed: K 7, 992, 898.00
Donor Funded Projects: (TSSP)
Total CFC issued: K 34, 402, 220.00
Total Expenditure to-date: K 19, 037, 503.00
Balance to-be Committed: K 11, 534, 064.53
6. PROGRESS SUMMARY
FUNDING AGENCY TOTAL FUNDING
ALLOCATED
(PGK)
ROAD
LENGTH
MAINTAINED
(KM)
CROSS DRAINAGE
STRUCTURES
MAINTATINED
(NO.)
GoPNG (DEVELOPMENT) 186, 613, 841.37 313.00 • 4 x Bridges
• 2 x Culverts (Multi-
plate)
GoPNG (TRUST ACCOUNTS) 30, 747, 656.00 161.00 • 2 x Bridges
TSSP (AUSAID) 19, 037, 503.00 230.00 • 538 x Culverts
• 3 x Bridges
Total 251, 763, 717.37 704.00 • 7 x Bridges
• 540 Culverts
Expenditure Rate for Morobe Province this Quarter (4th) K59.5
million/month
Progress Rate is at K357, 618.92/km
7. PROJECT STATUS REPORTS
National Road Maintenance
Works
National Bridge Maintenance
Works
AusAID Funded Projects – TSSP
Specific Maintenance Works
Emergency Maintenance Works
8. NEW PLANNED PROJECTS
Bukawa Road Pilot Project – (Capacity Building Project)
Lae City Roads Stage 4
Wau Highway Minor Works – TSSP
Ramu Highway Minor Works – TSSP
Highlands Highway Minor Works – TSSP
Highlands Highway Major Drainage Works – TSSP
Highlands Highway Rehabilitation Works – 10km (GoPNG)
Highlands Highway Pavement Investigation
Wau Highway Major Works – Patep Bridge to Mumeng Bridge
Erap – Boana Road – World Bank
9. NEW PLANNED PROJECTS
Wawin National High School Roads
Buimo CIS Roads
NARI Roads
Taraka Police Barracks Roads
Telikom College Roads
Bulolo Town Roads
Wau Town Roads
10. ISSUES AND CONSTRAINTS
No Supervision funds for TSSP Projects in 3rd & 4th Qtr
Wau Highway Section from Markham Bridge to Bulolo
EoS under NRA in bad state
Four (4) Lane Project needs proper advise
Delay in Procuring of Projects result in Variation & EoT
(Kuranga-Wau Project & Patep Bridge –Mumeng Bridge)
In-house/Country Training of new Graduate Engineers
Outstanding Payments for Specific Maintenance on Wau
Highway (NR008)
Insufficient budget allocation for Lae City Roads.
Casual Project Engineers need to be on Concept Payroll