Presented by:
Gibson Ali Holemba
Provincial Works Manager
New Ireland Province
General Information
Major Works Contract is Value of Works worth above
K5 million
Minor Works Contract is Value of Works worth
between K500 Thousand & K5 Million
Proforma Contract is Value of Works worth below
K500 Thousand
Community Based Contracts is value of works worth
K50 Thousand and below
2
Qualification Information
1. Relevant Experience
The bidder must posses some relevant experience in similar projects. Qualification
Information must include similar projects, monetary value of the past project, duration
of the past project and company registration with IPA (Current) and have valid
Certificate of Compliance (CoC) with IRC and GST Registered.
2. Past Performance
The bidder will be assessed basing on the past projects. The main areas of assessment
will be on Quality of Works undertook, Final Cost, Contract Duration Completion Date
and Safety Record in the past projects. The bidder must provide such information
during the time of bid.
3. Management & Technical Skills
The bidder must also provide in the bid document the Technical Expertise
(Organizational Chart) and Project Management Tools (How to manage the project)
and Quality Systems that will make the project “Value for Money”. The bidder must
NOT have any Affiliation to DoW nor its staff or any officer that is employed by
Department of Works. Any Affiliation with DoW will deem the bid null and void and will
be forfeited outright.
3
Qualification Information
4. Recourses
The bidder must posses required Plant and Equipment to bid for the project. If the
bidder will hire equipment from other party, it must be stated in the bid. The
resources may include Trade Skills of Technical Personnel (Manpower), Company's
established Facilities (Site office) and most of all Financial Capacity. The bidder
must guarantee in its bid that it has enough financial recourses that is required to
start and finish the project.
5. Methodology
The bidder must also provide in its bid information the method of construction it
will undertake in line to the provided scope of works. It must also state clear during
the bid the use of Subcontractors in any works included in the bid. Reporting of
works is very important and must be stated in the bid document the mode and
method of reporting. Submitted bid document must be able to demonstrate the
Current Workload the company has on hand and the progress of each project. In
addition, the bidder must provide the Tentative Works Program to show how the
bidder intents to plan and execute the works according to the contract period
stated. The program is tentative only and Microsoft Excel or Project Software are
most preferred.
4
Technical Requirements
Bid Conformance
Submitted Time Conformance Was bid submitted prior to close
Sealed Bid Was bid sealed when opened
Signed BoQ Is the BoQ form properly signed by Bidder
Relevant Experience
Past Projects Has completed projects of similar type of works
Project Costs Has completed projects of similar value
Duration of Project Has completed projects of similar project duration
Company Registered Is company registered
Past Performance
Quality Has completed quality / acceptable works
Final Cost Has completed within project costs
Completion Date Has completed within the completion date of the contract
Safety Record Has a good safety record and safety plan
Management & Technical Skills
Technical Expertise Has technical expertise to complete the works
Project Management Tools Has proven project management capacity
Quality Systems Has QA systems in place
5
Technical Requirements
Resources
Plant Has access to good plant, either owned or hired
Trade Skills Has suitable skilled personnel and labour
Facilities Has suitable support facilities
Financial Capacity Able to finance projects without cash flow issues
Insurances Evidence Evidence that insurance can be provided under the contract
Methodology
Use of Subcontractors Able to use and manage subcontractors
Reporting Able to provide acceptable reporting documents
Current Workload Current workload and workload capacity provided
Programme Submitted Was a suitable programme submitted
Other Overriding Issues (Extended capacity, other, etc)
Issues may include
Success on multiple bids currently being evaluated that may over extend current capacity
Price well below other bidders posing cost risk
6
Bid Assessment Range
Assessment Range
Passes Fail %
20 0 100.00% Assessment pass range to vary between 65 to 95%
19 1 95.00%
18 2 90.00% Recommended determination of Pass Percentage
17 3 85.00% 85-95 Good contractor competition / capacity
16 4 80.00% 75-85
Average contractor competition /
capacity
15 5 75.00% 65-75 Poor contractor competition / capacity
14 6 70.00%
13 7 65.00% Adjustment may also be subject to No. of Bids submitted
12 8 60.00%
11 9 55.00%
10 10 50.00%
7
8
9

More Related Content

Viewers also liked

NWHM_[Nwsltr-Vol25]
NWHM_[Nwsltr-Vol25]NWHM_[Nwsltr-Vol25]
NWHM_[Nwsltr-Vol25]ICSCAHM
 
Pelileo un rincon para conocer
Pelileo un rincon para conocerPelileo un rincon para conocer
Pelileo un rincon para conocerlilianavillena
 
4 en ls_cuidados de en
4 en ls_cuidados de en4 en ls_cuidados de en
4 en ls_cuidados de enCECY50
 
Metodos anticonceptivos y planificación familiar
Metodos anticonceptivos y planificación familiarMetodos anticonceptivos y planificación familiar
Metodos anticonceptivos y planificación familiarSandra Liliana
 
Inteligencia artificial 1
Inteligencia artificial 1Inteligencia artificial 1
Inteligencia artificial 1Nauber Gois
 
Calendario 2017 1 (1)
Calendario 2017 1 (1)Calendario 2017 1 (1)
Calendario 2017 1 (1)CECY50
 
Unidad iv
Unidad ivUnidad iv
Unidad ivCECY50
 
закон всемирного тяготения
закон всемирного тяготениязакон всемирного тяготения
закон всемирного тяготенияKate Gulyaeva
 

Viewers also liked (13)

HYH-resume
HYH-resume HYH-resume
HYH-resume
 
NWHM_[Nwsltr-Vol25]
NWHM_[Nwsltr-Vol25]NWHM_[Nwsltr-Vol25]
NWHM_[Nwsltr-Vol25]
 
Pelileo un rincon para conocer
Pelileo un rincon para conocerPelileo un rincon para conocer
Pelileo un rincon para conocer
 
Tugas tik 1912017
Tugas tik 1912017Tugas tik 1912017
Tugas tik 1912017
 
CEPA Presentation
CEPA PresentationCEPA Presentation
CEPA Presentation
 
4 en ls_cuidados de en
4 en ls_cuidados de en4 en ls_cuidados de en
4 en ls_cuidados de en
 
Metodos anticonceptivos y planificación familiar
Metodos anticonceptivos y planificación familiarMetodos anticonceptivos y planificación familiar
Metodos anticonceptivos y planificación familiar
 
Inteligencia artificial 1
Inteligencia artificial 1Inteligencia artificial 1
Inteligencia artificial 1
 
Calendario 2017 1 (1)
Calendario 2017 1 (1)Calendario 2017 1 (1)
Calendario 2017 1 (1)
 
Unidad iv
Unidad ivUnidad iv
Unidad iv
 
Black Tea and Rosewater Perfume
Black Tea and Rosewater PerfumeBlack Tea and Rosewater Perfume
Black Tea and Rosewater Perfume
 
Reforestation
ReforestationReforestation
Reforestation
 
закон всемирного тяготения
закон всемирного тяготениязакон всемирного тяготения
закон всемирного тяготения
 

Similar to Proforma Contract Bid Requirements

RFP1. Project Initiation Phase The purpose of the RFP document.docx
RFP1. Project Initiation Phase The purpose of the RFP document.docxRFP1. Project Initiation Phase The purpose of the RFP document.docx
RFP1. Project Initiation Phase The purpose of the RFP document.docxhealdkathaleen
 
Running head CONTRACT CLOSEOUT 1CONTRACT CLOSEOUT 16.docx
Running head CONTRACT CLOSEOUT 1CONTRACT CLOSEOUT 16.docxRunning head CONTRACT CLOSEOUT 1CONTRACT CLOSEOUT 16.docx
Running head CONTRACT CLOSEOUT 1CONTRACT CLOSEOUT 16.docxjoellemurphey
 
ProTech training presentation
ProTech training presentationProTech training presentation
ProTech training presentationGiselle Duran
 
Final presentation from shahida
Final presentation from shahidaFinal presentation from shahida
Final presentation from shahidashahida quraishi
 
Tendering process, Bid Evaluation & Award Process
Tendering process, Bid Evaluation & Award ProcessTendering process, Bid Evaluation & Award Process
Tendering process, Bid Evaluation & Award ProcessPrateek Kashyap
 
Procurement management-plan template
Procurement management-plan templateProcurement management-plan template
Procurement management-plan templateVivek Srivastava
 
Pre qualification stages and tender selection
Pre qualification stages and tender selectionPre qualification stages and tender selection
Pre qualification stages and tender selectionanojan kanagarathnam
 
Procurement ManagementImportance of Project Procurem
Procurement ManagementImportance of Project ProcuremProcurement ManagementImportance of Project Procurem
Procurement ManagementImportance of Project ProcuremDaliaCulbertson719
 
Plan procurement management
Plan procurement management Plan procurement management
Plan procurement management Shereef Sabri
 
Network Rail & Innovate UK: Applicant Briefing "SBRI Innovation in Rail Secur...
Network Rail & Innovate UK: Applicant Briefing "SBRI Innovation in Rail Secur...Network Rail & Innovate UK: Applicant Briefing "SBRI Innovation in Rail Secur...
Network Rail & Innovate UK: Applicant Briefing "SBRI Innovation in Rail Secur...KTN
 
Procurement ops450
Procurement ops450Procurement ops450
Procurement ops450kahogan62
 
project implimentation.-Three.Procurement.ppt
project implimentation.-Three.Procurement.pptproject implimentation.-Three.Procurement.ppt
project implimentation.-Three.Procurement.pptselam49
 
Faid daoud updated cv 19 july 2016
Faid daoud updated cv 19 july 2016Faid daoud updated cv 19 july 2016
Faid daoud updated cv 19 july 2016Faid Daoud
 
Application sourcing focused on value, not cost alone
Application sourcing focused on value, not cost aloneApplication sourcing focused on value, not cost alone
Application sourcing focused on value, not cost aloneWGroup
 
Competition scope, competition eligibility conditions and application process...
Competition scope, competition eligibility conditions and application process...Competition scope, competition eligibility conditions and application process...
Competition scope, competition eligibility conditions and application process...KTN
 
How to Perfectly Construct an RFP in 8 StepsThe RFP (request for.docx
How to Perfectly Construct an RFP in 8 StepsThe RFP (request for.docxHow to Perfectly Construct an RFP in 8 StepsThe RFP (request for.docx
How to Perfectly Construct an RFP in 8 StepsThe RFP (request for.docxpooleavelina
 
Conduct procurements
Conduct procurements Conduct procurements
Conduct procurements Shereef Sabri
 

Similar to Proforma Contract Bid Requirements (20)

RFP1. Project Initiation Phase The purpose of the RFP document.docx
RFP1. Project Initiation Phase The purpose of the RFP document.docxRFP1. Project Initiation Phase The purpose of the RFP document.docx
RFP1. Project Initiation Phase The purpose of the RFP document.docx
 
Running head CONTRACT CLOSEOUT 1CONTRACT CLOSEOUT 16.docx
Running head CONTRACT CLOSEOUT 1CONTRACT CLOSEOUT 16.docxRunning head CONTRACT CLOSEOUT 1CONTRACT CLOSEOUT 16.docx
Running head CONTRACT CLOSEOUT 1CONTRACT CLOSEOUT 16.docx
 
PPRA.ppt
PPRA.pptPPRA.ppt
PPRA.ppt
 
ProTech training presentation
ProTech training presentationProTech training presentation
ProTech training presentation
 
Final presentation from shahida
Final presentation from shahidaFinal presentation from shahida
Final presentation from shahida
 
Tendering process, Bid Evaluation & Award Process
Tendering process, Bid Evaluation & Award ProcessTendering process, Bid Evaluation & Award Process
Tendering process, Bid Evaluation & Award Process
 
Procurement management-plan template
Procurement management-plan templateProcurement management-plan template
Procurement management-plan template
 
Pre qualification stages and tender selection
Pre qualification stages and tender selectionPre qualification stages and tender selection
Pre qualification stages and tender selection
 
Procurement ManagementImportance of Project Procurem
Procurement ManagementImportance of Project ProcuremProcurement ManagementImportance of Project Procurem
Procurement ManagementImportance of Project Procurem
 
Plan procurement management
Plan procurement management Plan procurement management
Plan procurement management
 
Network Rail & Innovate UK: Applicant Briefing "SBRI Innovation in Rail Secur...
Network Rail & Innovate UK: Applicant Briefing "SBRI Innovation in Rail Secur...Network Rail & Innovate UK: Applicant Briefing "SBRI Innovation in Rail Secur...
Network Rail & Innovate UK: Applicant Briefing "SBRI Innovation in Rail Secur...
 
Procurement ops450
Procurement ops450Procurement ops450
Procurement ops450
 
project implimentation.-Three.Procurement.ppt
project implimentation.-Three.Procurement.pptproject implimentation.-Three.Procurement.ppt
project implimentation.-Three.Procurement.ppt
 
Faid daoud updated cv 19 july 2016
Faid daoud updated cv 19 july 2016Faid daoud updated cv 19 july 2016
Faid daoud updated cv 19 july 2016
 
Application sourcing focused on value, not cost alone
Application sourcing focused on value, not cost aloneApplication sourcing focused on value, not cost alone
Application sourcing focused on value, not cost alone
 
Competition scope, competition eligibility conditions and application process...
Competition scope, competition eligibility conditions and application process...Competition scope, competition eligibility conditions and application process...
Competition scope, competition eligibility conditions and application process...
 
Credicon Introduction
Credicon  IntroductionCredicon  Introduction
Credicon Introduction
 
Tendering-professional practices-jamia millia islamia
Tendering-professional practices-jamia millia islamiaTendering-professional practices-jamia millia islamia
Tendering-professional practices-jamia millia islamia
 
How to Perfectly Construct an RFP in 8 StepsThe RFP (request for.docx
How to Perfectly Construct an RFP in 8 StepsThe RFP (request for.docxHow to Perfectly Construct an RFP in 8 StepsThe RFP (request for.docx
How to Perfectly Construct an RFP in 8 StepsThe RFP (request for.docx
 
Conduct procurements
Conduct procurements Conduct procurements
Conduct procurements
 

More from Gibson Ali Holemba

Flood Loads on Bridges over River Crossings
Flood Loads on Bridges over River Crossings Flood Loads on Bridges over River Crossings
Flood Loads on Bridges over River Crossings Gibson Ali Holemba
 
2014 FINAL QUARTER BUDGET REVIEW, Morobe Province, Laguna Hotel, NCD
2014 FINAL QUARTER BUDGET REVIEW, Morobe Province, Laguna Hotel, NCD2014 FINAL QUARTER BUDGET REVIEW, Morobe Province, Laguna Hotel, NCD
2014 FINAL QUARTER BUDGET REVIEW, Morobe Province, Laguna Hotel, NCDGibson Ali Holemba
 
2015 First Quarter Budget Review
2015 First Quarter Budget Review2015 First Quarter Budget Review
2015 First Quarter Budget ReviewGibson Ali Holemba
 
Flood Resistant Bridge Design in PNG rev0117 draft
Flood Resistant Bridge Design in PNG rev0117 draftFlood Resistant Bridge Design in PNG rev0117 draft
Flood Resistant Bridge Design in PNG rev0117 draftGibson Ali Holemba
 
General Flood Resistant Bridge Design Guidelines
General Flood Resistant Bridge Design GuidelinesGeneral Flood Resistant Bridge Design Guidelines
General Flood Resistant Bridge Design GuidelinesGibson Ali Holemba
 

More from Gibson Ali Holemba (7)

Sustainable Bridge Design
Sustainable Bridge DesignSustainable Bridge Design
Sustainable Bridge Design
 
Flood Loads on Bridges over River Crossings
Flood Loads on Bridges over River Crossings Flood Loads on Bridges over River Crossings
Flood Loads on Bridges over River Crossings
 
Decision Making
Decision MakingDecision Making
Decision Making
 
2014 FINAL QUARTER BUDGET REVIEW, Morobe Province, Laguna Hotel, NCD
2014 FINAL QUARTER BUDGET REVIEW, Morobe Province, Laguna Hotel, NCD2014 FINAL QUARTER BUDGET REVIEW, Morobe Province, Laguna Hotel, NCD
2014 FINAL QUARTER BUDGET REVIEW, Morobe Province, Laguna Hotel, NCD
 
2015 First Quarter Budget Review
2015 First Quarter Budget Review2015 First Quarter Budget Review
2015 First Quarter Budget Review
 
Flood Resistant Bridge Design in PNG rev0117 draft
Flood Resistant Bridge Design in PNG rev0117 draftFlood Resistant Bridge Design in PNG rev0117 draft
Flood Resistant Bridge Design in PNG rev0117 draft
 
General Flood Resistant Bridge Design Guidelines
General Flood Resistant Bridge Design GuidelinesGeneral Flood Resistant Bridge Design Guidelines
General Flood Resistant Bridge Design Guidelines
 

Proforma Contract Bid Requirements

  • 1. Presented by: Gibson Ali Holemba Provincial Works Manager New Ireland Province
  • 2. General Information Major Works Contract is Value of Works worth above K5 million Minor Works Contract is Value of Works worth between K500 Thousand & K5 Million Proforma Contract is Value of Works worth below K500 Thousand Community Based Contracts is value of works worth K50 Thousand and below 2
  • 3. Qualification Information 1. Relevant Experience The bidder must posses some relevant experience in similar projects. Qualification Information must include similar projects, monetary value of the past project, duration of the past project and company registration with IPA (Current) and have valid Certificate of Compliance (CoC) with IRC and GST Registered. 2. Past Performance The bidder will be assessed basing on the past projects. The main areas of assessment will be on Quality of Works undertook, Final Cost, Contract Duration Completion Date and Safety Record in the past projects. The bidder must provide such information during the time of bid. 3. Management & Technical Skills The bidder must also provide in the bid document the Technical Expertise (Organizational Chart) and Project Management Tools (How to manage the project) and Quality Systems that will make the project “Value for Money”. The bidder must NOT have any Affiliation to DoW nor its staff or any officer that is employed by Department of Works. Any Affiliation with DoW will deem the bid null and void and will be forfeited outright. 3
  • 4. Qualification Information 4. Recourses The bidder must posses required Plant and Equipment to bid for the project. If the bidder will hire equipment from other party, it must be stated in the bid. The resources may include Trade Skills of Technical Personnel (Manpower), Company's established Facilities (Site office) and most of all Financial Capacity. The bidder must guarantee in its bid that it has enough financial recourses that is required to start and finish the project. 5. Methodology The bidder must also provide in its bid information the method of construction it will undertake in line to the provided scope of works. It must also state clear during the bid the use of Subcontractors in any works included in the bid. Reporting of works is very important and must be stated in the bid document the mode and method of reporting. Submitted bid document must be able to demonstrate the Current Workload the company has on hand and the progress of each project. In addition, the bidder must provide the Tentative Works Program to show how the bidder intents to plan and execute the works according to the contract period stated. The program is tentative only and Microsoft Excel or Project Software are most preferred. 4
  • 5. Technical Requirements Bid Conformance Submitted Time Conformance Was bid submitted prior to close Sealed Bid Was bid sealed when opened Signed BoQ Is the BoQ form properly signed by Bidder Relevant Experience Past Projects Has completed projects of similar type of works Project Costs Has completed projects of similar value Duration of Project Has completed projects of similar project duration Company Registered Is company registered Past Performance Quality Has completed quality / acceptable works Final Cost Has completed within project costs Completion Date Has completed within the completion date of the contract Safety Record Has a good safety record and safety plan Management & Technical Skills Technical Expertise Has technical expertise to complete the works Project Management Tools Has proven project management capacity Quality Systems Has QA systems in place 5
  • 6. Technical Requirements Resources Plant Has access to good plant, either owned or hired Trade Skills Has suitable skilled personnel and labour Facilities Has suitable support facilities Financial Capacity Able to finance projects without cash flow issues Insurances Evidence Evidence that insurance can be provided under the contract Methodology Use of Subcontractors Able to use and manage subcontractors Reporting Able to provide acceptable reporting documents Current Workload Current workload and workload capacity provided Programme Submitted Was a suitable programme submitted Other Overriding Issues (Extended capacity, other, etc) Issues may include Success on multiple bids currently being evaluated that may over extend current capacity Price well below other bidders posing cost risk 6
  • 7. Bid Assessment Range Assessment Range Passes Fail % 20 0 100.00% Assessment pass range to vary between 65 to 95% 19 1 95.00% 18 2 90.00% Recommended determination of Pass Percentage 17 3 85.00% 85-95 Good contractor competition / capacity 16 4 80.00% 75-85 Average contractor competition / capacity 15 5 75.00% 65-75 Poor contractor competition / capacity 14 6 70.00% 13 7 65.00% Adjustment may also be subject to No. of Bids submitted 12 8 60.00% 11 9 55.00% 10 10 50.00% 7
  • 8. 8
  • 9. 9