SlideShare a Scribd company logo
AC Interference and Mitigation




Florida Energy Pipeline Association
Pipelines & HVAC Lines Collocated
•   Collocated Utilities
     Pipelines and HVAC Power
      Lines often share the same
      right of way

     There are problems that
      must be addressed when
      HVAC and buried pipelines
      share the same right of way
Enhanced Regulatory Scrutiny

•   Regulators are focusing more on this issue given recent risk
    findings by operators and enhanced pipeline safety regulations
•   NACE Standard RP0177 (Latest Revision) - Recommended Practice
    on Mitigation of Alternating Current & Lightning Effects on
    Metallic Structure and Corrosion Control Systems. Also, ANSI/IEEE
    Standard 80 specifies safety design criteria for determining
    maximum acceptable touch and step voltages during fault
    conditions.
Three Distinct Issues

•   Health and Safety of Personnel/Public/Livestock
     Well known and easily fixed
•   AC Fault Currents
     Short duration occurring at a particular tower location
•   AC Induced Corrosion
     Not well understood but affects well coated pipe
     Steady state condition
     Can be quite damaging and intense
How do Pipelines and AC Interact

•   Electrostatic Coupling
     Capacitive nuisance effect
•   Conductive Coupling
     Fault Currents at tower footings
•   Inductive Coupling
     Steady State Induced AC voltage buildup
Electrostatic Coupling

                         Pipe and Power line create a circuit
                         of two capacitors in series. A
                         capacitor is a passive electronic
                         component consisting of a pair of
                         conductors separated by an
                         insulator (air)
Electrostatic Coupling

                         Can generate very high AC voltage
                         levels – but there is not enough
                         power to do much more than
                         create a minor electrostatic shock.
                         Generally a nuisance, however can
                         be an issue and grounding may be
                         required.
How do Pipelines and AC Interact

•   Electrostatic Coupling
     Capacitive nuisance effect
•   Conductive Coupling
     Fault Currents at tower footings
•   Inductive Coupling
     Steady State Induced AC voltage buildup
Conductive Coupling
                      AC Fault Conditions
                      •Relatively rare
                      •Short duration
                      •Generally due to weather
                      (lightning and high winds)
                      •Can be structural failure

                      Causes intense stressing of pipeline
                      coating and possibly the pipeline
                      wall
Conductive Couplings
•   Rare occurrences that can result in significant current
    discharging through the ground
•   Separation distance of the pipeline from the fault is critical
•   Soil resistivity is critical – note soil layering can affect current
    path
•   Requires arcing through the soil for a current path – not easy
How do Pipelines and AC Interact

•   Electrostatic Coupling
     Capacitive nuisance effect
•   Conductive Coupling
     Fault Currents at tower footings
•   Inductive Coupling
     Steady State Induced AC voltage buildup
Electromagnetic Induction
                                •A function of Line Current not
                                Voltage
                                •Power transferred is
               I1                    •Proportional to line
                                     current
                                     •Proportional to
                                     parallelism
                            φ
                                     •Inversely proportional to
                                     separation distance
                                •Can result in high voltages on
                       I2       long sections of pipeline even
                                if the pipeline is grounded
Electromagnetic Induction
                     • Current through the HVAC lines generate a
                     Longitudinal Electric Field (LEF)
A   B    C           • The separation between the phase conductors
                     has a significant effect on the LEF and increases
                     with separation
                     • Bundled buried conductors have no separation
                     and provide only a minimal effect on pipelines
Electromagnetic Induction
•   The arrangement of       A
                             B
                                      A
                                      B
    phases on multiple       C        C

    circuit HVAC lines can
                                 Center Line Symmetric
    have a large impact on
    the LEF                  A        C
                             B        B
                             C        A



                                 Center Point Symmetric
Electromagnetic Induction
•     If all characteristics are
      perfectly uniform along
      the pipeline/HVAC then
      there will be a zero
      voltage at the mid point      0         L

      and peaks where the               L/2

      HVAC and pipeline
      separate if the pipeline is
      electrically “short”
Electromagnetic Induction

•   If the length is electrically
    “long” it would look more
    like this…

                                    0         L
                                        L/2
What are the effects of Coupling
•   Electrostatic Coupling
     Capacitive nuisance effect
•   Conductive Coupling
     Fault Currents at tower footings
          Safety Concern
          Stress Voltage
•   Inductive Coupling
     Steady State Induced AC voltage buildup
         Safety Concern
         AC Induced Corrosion
Stress Voltage
                 AC Fault Conditions
                 •Relatively rare
                 •Short duration
                 •Rapid localized increase in voltage
                 •Can cause significant coating
                 damage
                 •Could result in a direct arc from
                 tower footing to pipeline heating
                 the metal quickly (burning a hole)
Steady State AC Corrosion

•   Until recently not a concern for pipeline operators
•   Published studies pre-1990s discounted AC corrosion as
    a possibility
•   Regulators not focused on this as a risk until quite
    recently
German Experiments

•   Pipeline failures in Germany in the early 90s on well
    protected new pipelines puzzled investigators
•   Previously, AC corrosion rates were not considered a
    threat
•   Testing on coupons with 1 cm2 holidays in low resistivity
    soils found corrosion rates of 210 mpy on steel polarized
    to 1800-2000 mV cse
Morphology of AC Corrosion

Round crater like corrosion with
deep pits typical of very active
corrosion

May have some false indications of
Microbiologically Induced Corrosion

Occurs in the presence of AC
Transmission and in some cases
Distribution lines

Likely in lower soil resistivities
Optimum Coating Holiday
•   Testing has found that the optimum coating holiday size
    for high AC Corrosion rates is between 1-3 cm2 coating
    holiday.
•   AC Current density is the key consideration
     0-20 A/m2        no corrosion
     20-100 A/m2      corrosion risk unpredictable
     Above 100 A/m2   corrosion can be expected
Sample Calculation
 Sample calculation for a
 1 cm2 holiday in 10 ohm-
 m soil
 Even at very low AC
 voltage levels this could
 yield corrosion rates in
 excess of 20 mpy even
 with good CP applied
AC Voltage vs. Soil Resistivity

This graph shows the
holiday size and AC
Voltage required to
exceed the 100 A/m2
“corrosion can be
expected” threshold at
varying soil resistivities.
AC Induced Corrosion

•   The higher the quality of the coating the greater the risk of
    AC induced corrosion
•   AC Induced corrosion with well coated pipelines can create
    significant and rapid corrosion even at low levels of induced
    AC Voltage even with good CP levels on pipeline
•   Corrosion mechanism still being researched but evidence is
    clear that it occurs
Safety Concerns

•   High voltage levels either from induction (steady state)
    or from fault conditions (rare and short duration)
    present a danger to personnel
     15 VAC threshold is well established by NACE
        Based on release threshold calculations

     Gradient Mats are well established for a long time in the
      industry
Step and Touch Potential

During a fault condition or even steady
state AC Voltage presence on the           10 kV
pipeline can create a safety condition
at above ground structures (test
stations, valves, etc…)

The person touching the structure is
exposed to 2 kV touch potential while     9 kV
                                          8 kV
the man standing is exposed to 1 kV in    7 kV
this diagram
Gradient Mats

Creates
equipotential
environment for
personnel
AC Mitigation

                AC Mitigation typically involves installation of
                one or more grounding devices to allow AC
                current to readily discharge off of the pipeline
                thus minimizing coating stress during fault
                conditions and reducing the inductive voltage
                levels to well below any threshold for
                personnel safety or AC induced corrosion.
Key Issues
             1. Step and Touch potentials at above ground
                appurtances (15 VAC NACE criteria)

             2. Conductive coupling dumping excessive Fault
                Current onto pipeline causing damage

             3. Induced Voltage discharging through smaller
                holidays on well coated pipelines causing AC
                induced corrosion
AC Modeling

•   Very complex mathematically to model
       Numerous variables
       Some very difficult to quantify
       Requires input from utility on the operating conditions
       Requires field data gathering
       Different modeling software
           PRCI, SES/CDEGS, ARC Engineering, Dabkowski, others…
Goals for AC Modeling

•   Calculating Fault Condition Stress Values
•   Calculating Induced Voltage at various points along the
    model
•   Evaluating Impact of Mitigation Measures
     Where
     How much
     How effective
Shortcomings of Modeling

•   Modeling is only as good as the data being used
•   Modeling is only as good as the assumptions being
    made
•   Modeling has to focus on worst case conditions
What is being modeled
•   The power line
     Peak loads, winter and summer
     Max fault current (line to ground)
     Shield wire data – type and geometry (mostly for fault analysis –
      only minor impact on steady state)
     Phase wire data
     Phase imbalance data
     Tower data
What is being modeled

•   The pipeline
     Pipe diameter
     Wall thickness
     Depth of cover
     Coating resistance and thickness (generally a guess since it is
      not practical to measure this)
     Centerline distance from towers
What is being modeled

•   The environment
     Soil resistivity along the colocation
     Soil resistivity at various depths (used in some of the more
      sophisticated modeling)
     Foreign structures of note (multiple pipelines and multiple
      HVAC lines)
Typical Modeling
Stress Currents

•   The concern is elevated short duration coating stress.
    Different coatings have different coating stress limits
•   Computer modeling is very complex and requires
    numerous assumptions
     Geometry
     Soil Resistivity and layering
     Transmission Fault data
Modeling of Mitigation
Modeling Results
Conductive Coupling Modeling

•   Dabkowski – Corrosion 2003 presented the following:
Risk Assessment w/o Modeling
•   Look for changes that will cause voltage spikes
     Changes in the pipeline to HVAC distance from each other
     Changes in the HVAC line (phase transpositions)
     Changes in soil resistivity
•   Identify what your concerns might be
     Stress voltages during fault conditions
     Steady state AC induced corrosion
Risk Assessment w/o Modeling

•   Corrosion risk - Zero in on areas where voltage spikes
    can be anticipated and there is low soil resistivity.
•   Fault current risk – Zero in on areas with the least
    separation between tower footings and pipeline
•   Modeling may not be required
Field testing of LEF

•   It is possible to take AC voltage readings and to measure the
    induced longitudinal electrical field (LEF) by placing a
    calibrated insulated cable on the ground parallel to the
    pipeline, grounding it, and using an high impedance
    voltmeter to measure the open circuit potential
•   The value received reflects the operating conditions at the
    time
AC Mitigation Project
AC Test Coupons
•    Designed to replicate a
     1 cm2 holiday
•    Can be used to
     determine the actual
     current density being
     picked up at the
     pipeline before
     applying mitigation and
     after installing
     mitigation
•    Uses the same coating
     and geometry as the
     pipe
PCR Installation
Copper Ground Wire Detail
Optimum AC Mitigation

•   Modeling is only as good as the model, the assumptions and
    the data being input
•   Gradient control line(s) parallel to the pipeline for new well
    coated pipelines are recommended to minimize AC Corrosion
    risk
•   Short lines at the tower footings are best for fault condition
    mitigation and can be used in conjunction with long gradient
    control lines
MATCOR’s MITIGATOR™
What is the MITIGATOR™?
Looks like the SPL™ Linear
Anode.
Not an anode but a copper
grounding cable
Special backfill
Installation
Installation of the MITIGATOR™ along a
Williams (Transco) Gas pipeline in Northern
New Jersey.
The pipeline is actually to the left of the
MITIGATOR™ trench.
The MITGATOR™ provides for easy installation,
a much larger surface area for discharging
copper, and the copper conductor is housed in
a special backfill with corrosion inhibitors.
From the Plattline™ Website




                   Life expectancy of Plattline in this application would be quite
                   long and would generally be determined by Plattline as a
                   projected cathodic protection system. The most common
                   sizes of Plattline for AC mitigation are plus and standard.
Zinc Ribbon



              SIZE         SURFACE AREA   COST

              Standard     54.0 mm2       $2.50/ft.

              Plus         76.2 mm2       $5.00/ft.

              Super        114.3 mm2      $9.50/ft.

              MITIGATOR™   119.6 mm2      $5.25/ft.
Concerns with Zinc
•   Zinc can passivate and should have a special backfill when
    used for AC Mitigation
•   Zinc is much more difficult to handle and install relative to
    the Mitigator™
•   Must use a torch to make connections
•   Requires more frequent use of decouplers
•   Will consume over time – not as long a life as copper
Areas for more investigation

•   Sophisticated modeling of Mitigator™ vs. Zinc

•   Investigation of “propagation constant” and the spacing
    of decouplers for zinc vs. Mitigator™
Summary of AC Interference

•   There are three key threats
     Safety (15 V AC Threshold)
     Fault Conditions (rare but potentially damaging)
     AC Corrosion – for new well coated pipelines this can easily be
      the most challenging and difficult threat to control and can
      cause damage even at lower levels of AC
Summary of AC Interference

•   Modeling may not be fully effective – especially for AC
    Corrosion
•   AC Coupons give information based on current operating
    conditions – changes in electrical flow affect the AC Induced
    Voltage
•   Risk Assessment can often be performed without expensive
    modeling
Questions


            Questions?

More Related Content

What's hot

underground cable in transmission grid
underground cable in transmission gridunderground cable in transmission grid
underground cable in transmission grid
Engr. naeem
 
Your electrical safety specilist for all equipments Powered AC and DC
Your electrical safety specilist for all equipments   Powered AC and DCYour electrical safety specilist for all equipments   Powered AC and DC
Your electrical safety specilist for all equipments Powered AC and DC
Mahesh Chandra Manav
 
Overhead line work ppt
Overhead line work pptOverhead line work ppt
Overhead line work ppt
Demsew Mitiku
 
Cable installation book
Cable installation bookCable installation book
Cable installation book
BHAGWAN PRASAD
 
Factors considered for High Voltage Cable Joint design
Factors considered for High Voltage Cable Joint design Factors considered for High Voltage Cable Joint design
Factors considered for High Voltage Cable Joint design
Shahab Khan
 
E2 earthing manual earth guidance notes
E2 earthing manual earth guidance notesE2 earthing manual earth guidance notes
E2 earthing manual earth guidance notes
bsganwal
 
Gas insulated substation.
Gas insulated substation.Gas insulated substation.
Gas insulated substation.
Pêrsêûs Sâîf
 
Seminar on Gas Insulated Substation
Seminar on Gas Insulated SubstationSeminar on Gas Insulated Substation
Seminar on Gas Insulated Substation
Soumya Raj Poddar
 
underground presentation
underground presentation underground presentation
underground presentation
abhinav singh baghel
 
High Voltage Gas Insulted Switchgear (GIS) Field Testing According to IEEE C3...
High Voltage Gas Insulted Switchgear (GIS) Field Testing According to IEEE C3...High Voltage Gas Insulted Switchgear (GIS) Field Testing According to IEEE C3...
High Voltage Gas Insulted Switchgear (GIS) Field Testing According to IEEE C3...
Ali Sepehri
 
Follow India national building code(NBC2016) for electrical installation and ...
Follow India national building code(NBC2016) for electrical installation and ...Follow India national building code(NBC2016) for electrical installation and ...
Follow India national building code(NBC2016) for electrical installation and ...
Mahesh Chandra Manav
 
Copper and aluminum compared in a life-cycle cost perspective
Copper and aluminum compared in a life-cycle cost perspectiveCopper and aluminum compared in a life-cycle cost perspective
Copper and aluminum compared in a life-cycle cost perspective
Leonardo ENERGY
 
Starting First
Starting FirstStarting First
Starting First
Pana Mann
 
Gas insulated substation
Gas insulated substationGas insulated substation
Gas insulated substation
MOHDFAIZAN75
 
High Voltage Gas Insulated Substation (GIS) Routine Tests According to IEEE C...
High Voltage Gas Insulated Substation (GIS) Routine Tests According to IEEE C...High Voltage Gas Insulated Substation (GIS) Routine Tests According to IEEE C...
High Voltage Gas Insulated Substation (GIS) Routine Tests According to IEEE C...
Ali Sepehri
 
1.8 overhead vs underground system
1.8 overhead vs underground system1.8 overhead vs underground system
1.8 overhead vs underground system
W3Edify
 
EE2353 / High Voltage Engineering - Testing of Cables
EE2353 / High Voltage Engineering - Testing of CablesEE2353 / High Voltage Engineering - Testing of Cables
EE2353 / High Voltage Engineering - Testing of Cables
Rajesh Ramesh
 
Comparison of overhead and underground transmission lines
Comparison of overhead and underground transmission linesComparison of overhead and underground transmission lines
Comparison of overhead and underground transmission lines
ahmed usama
 
Performances of distribution transformer installed in metallic enclosures
Performances of  distribution transformer installed in metallic enclosuresPerformances of  distribution transformer installed in metallic enclosures
Performances of distribution transformer installed in metallic enclosures
nehakardam
 
Assuring Reliability of Critical Power Cable Systems
Assuring Reliability of Critical Power Cable SystemsAssuring Reliability of Critical Power Cable Systems
Assuring Reliability of Critical Power Cable Systems
michaeljmack
 

What's hot (20)

underground cable in transmission grid
underground cable in transmission gridunderground cable in transmission grid
underground cable in transmission grid
 
Your electrical safety specilist for all equipments Powered AC and DC
Your electrical safety specilist for all equipments   Powered AC and DCYour electrical safety specilist for all equipments   Powered AC and DC
Your electrical safety specilist for all equipments Powered AC and DC
 
Overhead line work ppt
Overhead line work pptOverhead line work ppt
Overhead line work ppt
 
Cable installation book
Cable installation bookCable installation book
Cable installation book
 
Factors considered for High Voltage Cable Joint design
Factors considered for High Voltage Cable Joint design Factors considered for High Voltage Cable Joint design
Factors considered for High Voltage Cable Joint design
 
E2 earthing manual earth guidance notes
E2 earthing manual earth guidance notesE2 earthing manual earth guidance notes
E2 earthing manual earth guidance notes
 
Gas insulated substation.
Gas insulated substation.Gas insulated substation.
Gas insulated substation.
 
Seminar on Gas Insulated Substation
Seminar on Gas Insulated SubstationSeminar on Gas Insulated Substation
Seminar on Gas Insulated Substation
 
underground presentation
underground presentation underground presentation
underground presentation
 
High Voltage Gas Insulted Switchgear (GIS) Field Testing According to IEEE C3...
High Voltage Gas Insulted Switchgear (GIS) Field Testing According to IEEE C3...High Voltage Gas Insulted Switchgear (GIS) Field Testing According to IEEE C3...
High Voltage Gas Insulted Switchgear (GIS) Field Testing According to IEEE C3...
 
Follow India national building code(NBC2016) for electrical installation and ...
Follow India national building code(NBC2016) for electrical installation and ...Follow India national building code(NBC2016) for electrical installation and ...
Follow India national building code(NBC2016) for electrical installation and ...
 
Copper and aluminum compared in a life-cycle cost perspective
Copper and aluminum compared in a life-cycle cost perspectiveCopper and aluminum compared in a life-cycle cost perspective
Copper and aluminum compared in a life-cycle cost perspective
 
Starting First
Starting FirstStarting First
Starting First
 
Gas insulated substation
Gas insulated substationGas insulated substation
Gas insulated substation
 
High Voltage Gas Insulated Substation (GIS) Routine Tests According to IEEE C...
High Voltage Gas Insulated Substation (GIS) Routine Tests According to IEEE C...High Voltage Gas Insulated Substation (GIS) Routine Tests According to IEEE C...
High Voltage Gas Insulated Substation (GIS) Routine Tests According to IEEE C...
 
1.8 overhead vs underground system
1.8 overhead vs underground system1.8 overhead vs underground system
1.8 overhead vs underground system
 
EE2353 / High Voltage Engineering - Testing of Cables
EE2353 / High Voltage Engineering - Testing of CablesEE2353 / High Voltage Engineering - Testing of Cables
EE2353 / High Voltage Engineering - Testing of Cables
 
Comparison of overhead and underground transmission lines
Comparison of overhead and underground transmission linesComparison of overhead and underground transmission lines
Comparison of overhead and underground transmission lines
 
Performances of distribution transformer installed in metallic enclosures
Performances of  distribution transformer installed in metallic enclosuresPerformances of  distribution transformer installed in metallic enclosures
Performances of distribution transformer installed in metallic enclosures
 
Assuring Reliability of Critical Power Cable Systems
Assuring Reliability of Critical Power Cable SystemsAssuring Reliability of Critical Power Cable Systems
Assuring Reliability of Critical Power Cable Systems
 

Similar to 2012 FEPA Presentation: Ted Huck

2012 FEPA Presentation: Jeff Didas
2012 FEPA Presentation: Jeff Didas2012 FEPA Presentation: Jeff Didas
2012 FEPA Presentation: Jeff Didas
FloridaPipeTalk
 
Chapter 5 corona
Chapter 5  coronaChapter 5  corona
Chapter 5 corona
firaoltemesgen1
 
Chapter Five Corona and Overhead line Insulators.pptx
Chapter Five Corona and Overhead line Insulators.pptxChapter Five Corona and Overhead line Insulators.pptx
Chapter Five Corona and Overhead line Insulators.pptx
ssuserc8d444
 
Hvdc technology
Hvdc technologyHvdc technology
Hvdc technology
BhargavDNVK
 
Distribution systems
Distribution systemsDistribution systems
Distribution systems
Dr. Catherine T J
 
Effect of grounding
Effect of groundingEffect of grounding
Effect of grounding
Mohammad Zaid
 
Dc voltage
Dc voltageDc voltage
Dc voltage
sarunkutti
 
Protection & switchgear
Protection & switchgear   Protection & switchgear
Protection & switchgear
johny renoald
 
Comparative evaluation of hvdc
Comparative evaluation of hvdcComparative evaluation of hvdc
Comparative evaluation of hvdc
shivamverma394
 
Circuit Breaker : Types
Circuit Breaker : TypesCircuit Breaker : Types
Circuit Breaker : Types
Ridwanul Hoque
 
Transmission Line Constraints
Transmission Line ConstraintsTransmission Line Constraints
Transmission Line Constraints
Ridwanul Hoque
 
Circuit Breaker
Circuit BreakerCircuit Breaker
Circuit Breaker
gopalakrishnan385714
 
UNIT IV Circuit Breaker.pptx
UNIT IV Circuit Breaker.pptxUNIT IV Circuit Breaker.pptx
UNIT IV Circuit Breaker.pptx
gopalakrishnan385714
 
Lightning impulse test in precise
Lightning impulse test in  preciseLightning impulse test in  precise
Lightning impulse test in precise
Muthar Hussain
 
05-Breakdown in PN Diode.pptx
05-Breakdown in PN Diode.pptx05-Breakdown in PN Diode.pptx
05-Breakdown in PN Diode.pptx
SVNITHISHSELVAN
 
Measurement of hvac (High Voltage Engineering )
Measurement  of  hvac (High Voltage Engineering )Measurement  of  hvac (High Voltage Engineering )
Measurement of hvac (High Voltage Engineering )
Abhishek Choksi
 
Mod5part1
Mod5part1Mod5part1
Mod5part1
Asha Anu Kurian
 
1502957304lectrure_1 [Autosaved].pptx
1502957304lectrure_1 [Autosaved].pptx1502957304lectrure_1 [Autosaved].pptx
1502957304lectrure_1 [Autosaved].pptx
Tajmun1
 
1502957304lectrure_1.pptx
1502957304lectrure_1.pptx1502957304lectrure_1.pptx
1502957304lectrure_1.pptx
Tajmun1
 
00798333
0079833300798333
00798333
Warren Jin
 

Similar to 2012 FEPA Presentation: Ted Huck (20)

2012 FEPA Presentation: Jeff Didas
2012 FEPA Presentation: Jeff Didas2012 FEPA Presentation: Jeff Didas
2012 FEPA Presentation: Jeff Didas
 
Chapter 5 corona
Chapter 5  coronaChapter 5  corona
Chapter 5 corona
 
Chapter Five Corona and Overhead line Insulators.pptx
Chapter Five Corona and Overhead line Insulators.pptxChapter Five Corona and Overhead line Insulators.pptx
Chapter Five Corona and Overhead line Insulators.pptx
 
Hvdc technology
Hvdc technologyHvdc technology
Hvdc technology
 
Distribution systems
Distribution systemsDistribution systems
Distribution systems
 
Effect of grounding
Effect of groundingEffect of grounding
Effect of grounding
 
Dc voltage
Dc voltageDc voltage
Dc voltage
 
Protection & switchgear
Protection & switchgear   Protection & switchgear
Protection & switchgear
 
Comparative evaluation of hvdc
Comparative evaluation of hvdcComparative evaluation of hvdc
Comparative evaluation of hvdc
 
Circuit Breaker : Types
Circuit Breaker : TypesCircuit Breaker : Types
Circuit Breaker : Types
 
Transmission Line Constraints
Transmission Line ConstraintsTransmission Line Constraints
Transmission Line Constraints
 
Circuit Breaker
Circuit BreakerCircuit Breaker
Circuit Breaker
 
UNIT IV Circuit Breaker.pptx
UNIT IV Circuit Breaker.pptxUNIT IV Circuit Breaker.pptx
UNIT IV Circuit Breaker.pptx
 
Lightning impulse test in precise
Lightning impulse test in  preciseLightning impulse test in  precise
Lightning impulse test in precise
 
05-Breakdown in PN Diode.pptx
05-Breakdown in PN Diode.pptx05-Breakdown in PN Diode.pptx
05-Breakdown in PN Diode.pptx
 
Measurement of hvac (High Voltage Engineering )
Measurement  of  hvac (High Voltage Engineering )Measurement  of  hvac (High Voltage Engineering )
Measurement of hvac (High Voltage Engineering )
 
Mod5part1
Mod5part1Mod5part1
Mod5part1
 
1502957304lectrure_1 [Autosaved].pptx
1502957304lectrure_1 [Autosaved].pptx1502957304lectrure_1 [Autosaved].pptx
1502957304lectrure_1 [Autosaved].pptx
 
1502957304lectrure_1.pptx
1502957304lectrure_1.pptx1502957304lectrure_1.pptx
1502957304lectrure_1.pptx
 
00798333
0079833300798333
00798333
 

More from FloridaPipeTalk

2012 FEPA Presentation: Paul Smith
2012 FEPA Presentation: Paul Smith2012 FEPA Presentation: Paul Smith
2012 FEPA Presentation: Paul Smith
FloridaPipeTalk
 
2012 FEPA Presentation: Peter Lidiak
2012 FEPA Presentation: Peter Lidiak2012 FEPA Presentation: Peter Lidiak
2012 FEPA Presentation: Peter Lidiak
FloridaPipeTalk
 
2012 FEPA Presentation: Mark Weise
2012 FEPA Presentation: Mark Weise2012 FEPA Presentation: Mark Weise
2012 FEPA Presentation: Mark Weise
FloridaPipeTalk
 
2012 FEPA Presentation: Larry Hjalmarson
2012 FEPA Presentation: Larry Hjalmarson2012 FEPA Presentation: Larry Hjalmarson
2012 FEPA Presentation: Larry Hjalmarson
FloridaPipeTalk
 
2012 FEPA Presentation: Donald Morris
2012 FEPA Presentation: Donald Morris2012 FEPA Presentation: Donald Morris
2012 FEPA Presentation: Donald Morris
FloridaPipeTalk
 
2012 FEPA Presentation: Erik Kirkpatrick
2012 FEPA Presentation: Erik Kirkpatrick2012 FEPA Presentation: Erik Kirkpatrick
2012 FEPA Presentation: Erik Kirkpatrick
FloridaPipeTalk
 
2012 FEPA Presentation: Richard Musgrove
2012 FEPA Presentation: Richard Musgrove2012 FEPA Presentation: Richard Musgrove
2012 FEPA Presentation: Richard Musgrove
FloridaPipeTalk
 
2012 FEPA Presentation: Stu Kogge
2012 FEPA Presentation: Stu Kogge2012 FEPA Presentation: Stu Kogge
2012 FEPA Presentation: Stu Kogge
FloridaPipeTalk
 
2012 FEPA Presentation: Don Thorn
2012 FEPA Presentation: Don Thorn2012 FEPA Presentation: Don Thorn
2012 FEPA Presentation: Don Thorn
FloridaPipeTalk
 
2012 FEPA Presentation: Danny Kilcollins
2012 FEPA Presentation: Danny Kilcollins2012 FEPA Presentation: Danny Kilcollins
2012 FEPA Presentation: Danny Kilcollins
FloridaPipeTalk
 
2012 FEPA Presentation: Charlie Hall
2012 FEPA Presentation: Charlie Hall2012 FEPA Presentation: Charlie Hall
2012 FEPA Presentation: Charlie Hall
FloridaPipeTalk
 
2012 FEPA Presentation: Berne Mosley
2012 FEPA Presentation: Berne Mosley2012 FEPA Presentation: Berne Mosley
2012 FEPA Presentation: Berne Mosley
FloridaPipeTalk
 

More from FloridaPipeTalk (12)

2012 FEPA Presentation: Paul Smith
2012 FEPA Presentation: Paul Smith2012 FEPA Presentation: Paul Smith
2012 FEPA Presentation: Paul Smith
 
2012 FEPA Presentation: Peter Lidiak
2012 FEPA Presentation: Peter Lidiak2012 FEPA Presentation: Peter Lidiak
2012 FEPA Presentation: Peter Lidiak
 
2012 FEPA Presentation: Mark Weise
2012 FEPA Presentation: Mark Weise2012 FEPA Presentation: Mark Weise
2012 FEPA Presentation: Mark Weise
 
2012 FEPA Presentation: Larry Hjalmarson
2012 FEPA Presentation: Larry Hjalmarson2012 FEPA Presentation: Larry Hjalmarson
2012 FEPA Presentation: Larry Hjalmarson
 
2012 FEPA Presentation: Donald Morris
2012 FEPA Presentation: Donald Morris2012 FEPA Presentation: Donald Morris
2012 FEPA Presentation: Donald Morris
 
2012 FEPA Presentation: Erik Kirkpatrick
2012 FEPA Presentation: Erik Kirkpatrick2012 FEPA Presentation: Erik Kirkpatrick
2012 FEPA Presentation: Erik Kirkpatrick
 
2012 FEPA Presentation: Richard Musgrove
2012 FEPA Presentation: Richard Musgrove2012 FEPA Presentation: Richard Musgrove
2012 FEPA Presentation: Richard Musgrove
 
2012 FEPA Presentation: Stu Kogge
2012 FEPA Presentation: Stu Kogge2012 FEPA Presentation: Stu Kogge
2012 FEPA Presentation: Stu Kogge
 
2012 FEPA Presentation: Don Thorn
2012 FEPA Presentation: Don Thorn2012 FEPA Presentation: Don Thorn
2012 FEPA Presentation: Don Thorn
 
2012 FEPA Presentation: Danny Kilcollins
2012 FEPA Presentation: Danny Kilcollins2012 FEPA Presentation: Danny Kilcollins
2012 FEPA Presentation: Danny Kilcollins
 
2012 FEPA Presentation: Charlie Hall
2012 FEPA Presentation: Charlie Hall2012 FEPA Presentation: Charlie Hall
2012 FEPA Presentation: Charlie Hall
 
2012 FEPA Presentation: Berne Mosley
2012 FEPA Presentation: Berne Mosley2012 FEPA Presentation: Berne Mosley
2012 FEPA Presentation: Berne Mosley
 

Recently uploaded

DearbornMusic-KatherineJasperFullSailUni
DearbornMusic-KatherineJasperFullSailUniDearbornMusic-KatherineJasperFullSailUni
DearbornMusic-KatherineJasperFullSailUni
katiejasper96
 
Satta Matka Dpboss Matka Guessing Kalyan Chart Indian Matka Kalyan panel Chart
Satta Matka Dpboss Matka Guessing Kalyan Chart Indian Matka Kalyan panel ChartSatta Matka Dpboss Matka Guessing Kalyan Chart Indian Matka Kalyan panel Chart
Satta Matka Dpboss Matka Guessing Kalyan Chart Indian Matka Kalyan panel Chart
➒➌➎➏➑➐➋➑➐➐Dpboss Matka Guessing Satta Matka Kalyan Chart Indian Matka
 
Zodiac Signs and Food Preferences_ What Your Sign Says About Your Taste
Zodiac Signs and Food Preferences_ What Your Sign Says About Your TasteZodiac Signs and Food Preferences_ What Your Sign Says About Your Taste
Zodiac Signs and Food Preferences_ What Your Sign Says About Your Taste
my Pandit
 
Lundin Gold Corporate Presentation - June 2024
Lundin Gold Corporate Presentation - June 2024Lundin Gold Corporate Presentation - June 2024
Lundin Gold Corporate Presentation - June 2024
Adnet Communications
 
Brian Fitzsimmons on the Business Strategy and Content Flywheel of Barstool S...
Brian Fitzsimmons on the Business Strategy and Content Flywheel of Barstool S...Brian Fitzsimmons on the Business Strategy and Content Flywheel of Barstool S...
Brian Fitzsimmons on the Business Strategy and Content Flywheel of Barstool S...
Neil Horowitz
 
Digital Transformation Frameworks: Driving Digital Excellence
Digital Transformation Frameworks: Driving Digital ExcellenceDigital Transformation Frameworks: Driving Digital Excellence
Digital Transformation Frameworks: Driving Digital Excellence
Operational Excellence Consulting
 
GKohler - Retail Scavenger Hunt Presentation
GKohler - Retail Scavenger Hunt PresentationGKohler - Retail Scavenger Hunt Presentation
GKohler - Retail Scavenger Hunt Presentation
GraceKohler1
 
list of states and organizations .pdf
list of  states  and  organizations .pdflist of  states  and  organizations .pdf
list of states and organizations .pdf
Rbc Rbcua
 
Innovation Management Frameworks: Your Guide to Creativity & Innovation
Innovation Management Frameworks: Your Guide to Creativity & InnovationInnovation Management Frameworks: Your Guide to Creativity & Innovation
Innovation Management Frameworks: Your Guide to Creativity & Innovation
Operational Excellence Consulting
 
The Steadfast and Reliable Bull: Taurus Zodiac Sign
The Steadfast and Reliable Bull: Taurus Zodiac SignThe Steadfast and Reliable Bull: Taurus Zodiac Sign
The Steadfast and Reliable Bull: Taurus Zodiac Sign
my Pandit
 
Hamster Kombat' Telegram Game Surpasses 100 Million Players—Token Release Sch...
Hamster Kombat' Telegram Game Surpasses 100 Million Players—Token Release Sch...Hamster Kombat' Telegram Game Surpasses 100 Million Players—Token Release Sch...
Hamster Kombat' Telegram Game Surpasses 100 Million Players—Token Release Sch...
SOFTTECHHUB
 
Best Forex Brokers Comparison in INDIA 2024
Best Forex Brokers Comparison in INDIA 2024Best Forex Brokers Comparison in INDIA 2024
Best Forex Brokers Comparison in INDIA 2024
Top Forex Brokers Review
 
Business storytelling: key ingredients to a story
Business storytelling: key ingredients to a storyBusiness storytelling: key ingredients to a story
Business storytelling: key ingredients to a story
Alexandra Fulford
 
Best Competitive Marble Pricing in Dubai - ☎ 9928909666
Best Competitive Marble Pricing in Dubai - ☎ 9928909666Best Competitive Marble Pricing in Dubai - ☎ 9928909666
Best Competitive Marble Pricing in Dubai - ☎ 9928909666
Stone Art Hub
 
Pitch Deck Teardown: Kinnect's $250k Angel deck
Pitch Deck Teardown: Kinnect's $250k Angel deckPitch Deck Teardown: Kinnect's $250k Angel deck
Pitch Deck Teardown: Kinnect's $250k Angel deck
HajeJanKamps
 
2024-6-01-IMPACTSilver-Corp-Presentation.pdf
2024-6-01-IMPACTSilver-Corp-Presentation.pdf2024-6-01-IMPACTSilver-Corp-Presentation.pdf
2024-6-01-IMPACTSilver-Corp-Presentation.pdf
hartfordclub1
 
Best practices for project execution and delivery
Best practices for project execution and deliveryBest practices for project execution and delivery
Best practices for project execution and delivery
CLIVE MINCHIN
 
Top 10 Free Accounting and Bookkeeping Apps for Small Businesses
Top 10 Free Accounting and Bookkeeping Apps for Small BusinessesTop 10 Free Accounting and Bookkeeping Apps for Small Businesses
Top 10 Free Accounting and Bookkeeping Apps for Small Businesses
YourLegal Accounting
 
Taurus Zodiac Sign: Unveiling the Traits, Dates, and Horoscope Insights of th...
Taurus Zodiac Sign: Unveiling the Traits, Dates, and Horoscope Insights of th...Taurus Zodiac Sign: Unveiling the Traits, Dates, and Horoscope Insights of th...
Taurus Zodiac Sign: Unveiling the Traits, Dates, and Horoscope Insights of th...
my Pandit
 
❼❷⓿❺❻❷❽❷❼❽ Dpboss Matka Result Satta Matka Guessing Satta Fix jodi Kalyan Fin...
❼❷⓿❺❻❷❽❷❼❽ Dpboss Matka Result Satta Matka Guessing Satta Fix jodi Kalyan Fin...❼❷⓿❺❻❷❽❷❼❽ Dpboss Matka Result Satta Matka Guessing Satta Fix jodi Kalyan Fin...
❼❷⓿❺❻❷❽❷❼❽ Dpboss Matka Result Satta Matka Guessing Satta Fix jodi Kalyan Fin...
❼❷⓿❺❻❷❽❷❼❽ Dpboss Kalyan Satta Matka Guessing Matka Result Main Bazar chart
 

Recently uploaded (20)

DearbornMusic-KatherineJasperFullSailUni
DearbornMusic-KatherineJasperFullSailUniDearbornMusic-KatherineJasperFullSailUni
DearbornMusic-KatherineJasperFullSailUni
 
Satta Matka Dpboss Matka Guessing Kalyan Chart Indian Matka Kalyan panel Chart
Satta Matka Dpboss Matka Guessing Kalyan Chart Indian Matka Kalyan panel ChartSatta Matka Dpboss Matka Guessing Kalyan Chart Indian Matka Kalyan panel Chart
Satta Matka Dpboss Matka Guessing Kalyan Chart Indian Matka Kalyan panel Chart
 
Zodiac Signs and Food Preferences_ What Your Sign Says About Your Taste
Zodiac Signs and Food Preferences_ What Your Sign Says About Your TasteZodiac Signs and Food Preferences_ What Your Sign Says About Your Taste
Zodiac Signs and Food Preferences_ What Your Sign Says About Your Taste
 
Lundin Gold Corporate Presentation - June 2024
Lundin Gold Corporate Presentation - June 2024Lundin Gold Corporate Presentation - June 2024
Lundin Gold Corporate Presentation - June 2024
 
Brian Fitzsimmons on the Business Strategy and Content Flywheel of Barstool S...
Brian Fitzsimmons on the Business Strategy and Content Flywheel of Barstool S...Brian Fitzsimmons on the Business Strategy and Content Flywheel of Barstool S...
Brian Fitzsimmons on the Business Strategy and Content Flywheel of Barstool S...
 
Digital Transformation Frameworks: Driving Digital Excellence
Digital Transformation Frameworks: Driving Digital ExcellenceDigital Transformation Frameworks: Driving Digital Excellence
Digital Transformation Frameworks: Driving Digital Excellence
 
GKohler - Retail Scavenger Hunt Presentation
GKohler - Retail Scavenger Hunt PresentationGKohler - Retail Scavenger Hunt Presentation
GKohler - Retail Scavenger Hunt Presentation
 
list of states and organizations .pdf
list of  states  and  organizations .pdflist of  states  and  organizations .pdf
list of states and organizations .pdf
 
Innovation Management Frameworks: Your Guide to Creativity & Innovation
Innovation Management Frameworks: Your Guide to Creativity & InnovationInnovation Management Frameworks: Your Guide to Creativity & Innovation
Innovation Management Frameworks: Your Guide to Creativity & Innovation
 
The Steadfast and Reliable Bull: Taurus Zodiac Sign
The Steadfast and Reliable Bull: Taurus Zodiac SignThe Steadfast and Reliable Bull: Taurus Zodiac Sign
The Steadfast and Reliable Bull: Taurus Zodiac Sign
 
Hamster Kombat' Telegram Game Surpasses 100 Million Players—Token Release Sch...
Hamster Kombat' Telegram Game Surpasses 100 Million Players—Token Release Sch...Hamster Kombat' Telegram Game Surpasses 100 Million Players—Token Release Sch...
Hamster Kombat' Telegram Game Surpasses 100 Million Players—Token Release Sch...
 
Best Forex Brokers Comparison in INDIA 2024
Best Forex Brokers Comparison in INDIA 2024Best Forex Brokers Comparison in INDIA 2024
Best Forex Brokers Comparison in INDIA 2024
 
Business storytelling: key ingredients to a story
Business storytelling: key ingredients to a storyBusiness storytelling: key ingredients to a story
Business storytelling: key ingredients to a story
 
Best Competitive Marble Pricing in Dubai - ☎ 9928909666
Best Competitive Marble Pricing in Dubai - ☎ 9928909666Best Competitive Marble Pricing in Dubai - ☎ 9928909666
Best Competitive Marble Pricing in Dubai - ☎ 9928909666
 
Pitch Deck Teardown: Kinnect's $250k Angel deck
Pitch Deck Teardown: Kinnect's $250k Angel deckPitch Deck Teardown: Kinnect's $250k Angel deck
Pitch Deck Teardown: Kinnect's $250k Angel deck
 
2024-6-01-IMPACTSilver-Corp-Presentation.pdf
2024-6-01-IMPACTSilver-Corp-Presentation.pdf2024-6-01-IMPACTSilver-Corp-Presentation.pdf
2024-6-01-IMPACTSilver-Corp-Presentation.pdf
 
Best practices for project execution and delivery
Best practices for project execution and deliveryBest practices for project execution and delivery
Best practices for project execution and delivery
 
Top 10 Free Accounting and Bookkeeping Apps for Small Businesses
Top 10 Free Accounting and Bookkeeping Apps for Small BusinessesTop 10 Free Accounting and Bookkeeping Apps for Small Businesses
Top 10 Free Accounting and Bookkeeping Apps for Small Businesses
 
Taurus Zodiac Sign: Unveiling the Traits, Dates, and Horoscope Insights of th...
Taurus Zodiac Sign: Unveiling the Traits, Dates, and Horoscope Insights of th...Taurus Zodiac Sign: Unveiling the Traits, Dates, and Horoscope Insights of th...
Taurus Zodiac Sign: Unveiling the Traits, Dates, and Horoscope Insights of th...
 
❼❷⓿❺❻❷❽❷❼❽ Dpboss Matka Result Satta Matka Guessing Satta Fix jodi Kalyan Fin...
❼❷⓿❺❻❷❽❷❼❽ Dpboss Matka Result Satta Matka Guessing Satta Fix jodi Kalyan Fin...❼❷⓿❺❻❷❽❷❼❽ Dpboss Matka Result Satta Matka Guessing Satta Fix jodi Kalyan Fin...
❼❷⓿❺❻❷❽❷❼❽ Dpboss Matka Result Satta Matka Guessing Satta Fix jodi Kalyan Fin...
 

2012 FEPA Presentation: Ted Huck

  • 1. AC Interference and Mitigation Florida Energy Pipeline Association
  • 2. Pipelines & HVAC Lines Collocated • Collocated Utilities  Pipelines and HVAC Power Lines often share the same right of way  There are problems that must be addressed when HVAC and buried pipelines share the same right of way
  • 3. Enhanced Regulatory Scrutiny • Regulators are focusing more on this issue given recent risk findings by operators and enhanced pipeline safety regulations • NACE Standard RP0177 (Latest Revision) - Recommended Practice on Mitigation of Alternating Current & Lightning Effects on Metallic Structure and Corrosion Control Systems. Also, ANSI/IEEE Standard 80 specifies safety design criteria for determining maximum acceptable touch and step voltages during fault conditions.
  • 4. Three Distinct Issues • Health and Safety of Personnel/Public/Livestock  Well known and easily fixed • AC Fault Currents  Short duration occurring at a particular tower location • AC Induced Corrosion  Not well understood but affects well coated pipe  Steady state condition  Can be quite damaging and intense
  • 5. How do Pipelines and AC Interact • Electrostatic Coupling  Capacitive nuisance effect • Conductive Coupling  Fault Currents at tower footings • Inductive Coupling  Steady State Induced AC voltage buildup
  • 6. Electrostatic Coupling Pipe and Power line create a circuit of two capacitors in series. A capacitor is a passive electronic component consisting of a pair of conductors separated by an insulator (air)
  • 7. Electrostatic Coupling Can generate very high AC voltage levels – but there is not enough power to do much more than create a minor electrostatic shock. Generally a nuisance, however can be an issue and grounding may be required.
  • 8. How do Pipelines and AC Interact • Electrostatic Coupling  Capacitive nuisance effect • Conductive Coupling  Fault Currents at tower footings • Inductive Coupling  Steady State Induced AC voltage buildup
  • 9. Conductive Coupling AC Fault Conditions •Relatively rare •Short duration •Generally due to weather (lightning and high winds) •Can be structural failure Causes intense stressing of pipeline coating and possibly the pipeline wall
  • 10. Conductive Couplings • Rare occurrences that can result in significant current discharging through the ground • Separation distance of the pipeline from the fault is critical • Soil resistivity is critical – note soil layering can affect current path • Requires arcing through the soil for a current path – not easy
  • 11. How do Pipelines and AC Interact • Electrostatic Coupling  Capacitive nuisance effect • Conductive Coupling  Fault Currents at tower footings • Inductive Coupling  Steady State Induced AC voltage buildup
  • 12. Electromagnetic Induction •A function of Line Current not Voltage •Power transferred is I1 •Proportional to line current •Proportional to parallelism φ •Inversely proportional to separation distance •Can result in high voltages on I2 long sections of pipeline even if the pipeline is grounded
  • 13. Electromagnetic Induction • Current through the HVAC lines generate a Longitudinal Electric Field (LEF) A B C • The separation between the phase conductors has a significant effect on the LEF and increases with separation • Bundled buried conductors have no separation and provide only a minimal effect on pipelines
  • 14. Electromagnetic Induction • The arrangement of A B A B phases on multiple C C circuit HVAC lines can Center Line Symmetric have a large impact on the LEF A C B B C A Center Point Symmetric
  • 15. Electromagnetic Induction • If all characteristics are perfectly uniform along the pipeline/HVAC then there will be a zero voltage at the mid point 0 L and peaks where the L/2 HVAC and pipeline separate if the pipeline is electrically “short”
  • 16. Electromagnetic Induction • If the length is electrically “long” it would look more like this… 0 L L/2
  • 17. What are the effects of Coupling • Electrostatic Coupling  Capacitive nuisance effect • Conductive Coupling  Fault Currents at tower footings  Safety Concern  Stress Voltage • Inductive Coupling  Steady State Induced AC voltage buildup  Safety Concern  AC Induced Corrosion
  • 18. Stress Voltage AC Fault Conditions •Relatively rare •Short duration •Rapid localized increase in voltage •Can cause significant coating damage •Could result in a direct arc from tower footing to pipeline heating the metal quickly (burning a hole)
  • 19. Steady State AC Corrosion • Until recently not a concern for pipeline operators • Published studies pre-1990s discounted AC corrosion as a possibility • Regulators not focused on this as a risk until quite recently
  • 20. German Experiments • Pipeline failures in Germany in the early 90s on well protected new pipelines puzzled investigators • Previously, AC corrosion rates were not considered a threat • Testing on coupons with 1 cm2 holidays in low resistivity soils found corrosion rates of 210 mpy on steel polarized to 1800-2000 mV cse
  • 21. Morphology of AC Corrosion Round crater like corrosion with deep pits typical of very active corrosion May have some false indications of Microbiologically Induced Corrosion Occurs in the presence of AC Transmission and in some cases Distribution lines Likely in lower soil resistivities
  • 22. Optimum Coating Holiday • Testing has found that the optimum coating holiday size for high AC Corrosion rates is between 1-3 cm2 coating holiday. • AC Current density is the key consideration  0-20 A/m2 no corrosion  20-100 A/m2 corrosion risk unpredictable  Above 100 A/m2 corrosion can be expected
  • 23. Sample Calculation Sample calculation for a 1 cm2 holiday in 10 ohm- m soil Even at very low AC voltage levels this could yield corrosion rates in excess of 20 mpy even with good CP applied
  • 24. AC Voltage vs. Soil Resistivity This graph shows the holiday size and AC Voltage required to exceed the 100 A/m2 “corrosion can be expected” threshold at varying soil resistivities.
  • 25. AC Induced Corrosion • The higher the quality of the coating the greater the risk of AC induced corrosion • AC Induced corrosion with well coated pipelines can create significant and rapid corrosion even at low levels of induced AC Voltage even with good CP levels on pipeline • Corrosion mechanism still being researched but evidence is clear that it occurs
  • 26. Safety Concerns • High voltage levels either from induction (steady state) or from fault conditions (rare and short duration) present a danger to personnel  15 VAC threshold is well established by NACE  Based on release threshold calculations  Gradient Mats are well established for a long time in the industry
  • 27. Step and Touch Potential During a fault condition or even steady state AC Voltage presence on the 10 kV pipeline can create a safety condition at above ground structures (test stations, valves, etc…) The person touching the structure is exposed to 2 kV touch potential while 9 kV 8 kV the man standing is exposed to 1 kV in 7 kV this diagram
  • 29. AC Mitigation AC Mitigation typically involves installation of one or more grounding devices to allow AC current to readily discharge off of the pipeline thus minimizing coating stress during fault conditions and reducing the inductive voltage levels to well below any threshold for personnel safety or AC induced corrosion.
  • 30. Key Issues 1. Step and Touch potentials at above ground appurtances (15 VAC NACE criteria) 2. Conductive coupling dumping excessive Fault Current onto pipeline causing damage 3. Induced Voltage discharging through smaller holidays on well coated pipelines causing AC induced corrosion
  • 31. AC Modeling • Very complex mathematically to model  Numerous variables  Some very difficult to quantify  Requires input from utility on the operating conditions  Requires field data gathering  Different modeling software  PRCI, SES/CDEGS, ARC Engineering, Dabkowski, others…
  • 32. Goals for AC Modeling • Calculating Fault Condition Stress Values • Calculating Induced Voltage at various points along the model • Evaluating Impact of Mitigation Measures  Where  How much  How effective
  • 33. Shortcomings of Modeling • Modeling is only as good as the data being used • Modeling is only as good as the assumptions being made • Modeling has to focus on worst case conditions
  • 34. What is being modeled • The power line  Peak loads, winter and summer  Max fault current (line to ground)  Shield wire data – type and geometry (mostly for fault analysis – only minor impact on steady state)  Phase wire data  Phase imbalance data  Tower data
  • 35. What is being modeled • The pipeline  Pipe diameter  Wall thickness  Depth of cover  Coating resistance and thickness (generally a guess since it is not practical to measure this)  Centerline distance from towers
  • 36. What is being modeled • The environment  Soil resistivity along the colocation  Soil resistivity at various depths (used in some of the more sophisticated modeling)  Foreign structures of note (multiple pipelines and multiple HVAC lines)
  • 38. Stress Currents • The concern is elevated short duration coating stress. Different coatings have different coating stress limits • Computer modeling is very complex and requires numerous assumptions  Geometry  Soil Resistivity and layering  Transmission Fault data
  • 41. Conductive Coupling Modeling • Dabkowski – Corrosion 2003 presented the following:
  • 42. Risk Assessment w/o Modeling • Look for changes that will cause voltage spikes  Changes in the pipeline to HVAC distance from each other  Changes in the HVAC line (phase transpositions)  Changes in soil resistivity • Identify what your concerns might be  Stress voltages during fault conditions  Steady state AC induced corrosion
  • 43. Risk Assessment w/o Modeling • Corrosion risk - Zero in on areas where voltage spikes can be anticipated and there is low soil resistivity. • Fault current risk – Zero in on areas with the least separation between tower footings and pipeline • Modeling may not be required
  • 44. Field testing of LEF • It is possible to take AC voltage readings and to measure the induced longitudinal electrical field (LEF) by placing a calibrated insulated cable on the ground parallel to the pipeline, grounding it, and using an high impedance voltmeter to measure the open circuit potential • The value received reflects the operating conditions at the time
  • 46. AC Test Coupons • Designed to replicate a 1 cm2 holiday • Can be used to determine the actual current density being picked up at the pipeline before applying mitigation and after installing mitigation • Uses the same coating and geometry as the pipe
  • 49. Optimum AC Mitigation • Modeling is only as good as the model, the assumptions and the data being input • Gradient control line(s) parallel to the pipeline for new well coated pipelines are recommended to minimize AC Corrosion risk • Short lines at the tower footings are best for fault condition mitigation and can be used in conjunction with long gradient control lines
  • 50. MATCOR’s MITIGATOR™ What is the MITIGATOR™? Looks like the SPL™ Linear Anode. Not an anode but a copper grounding cable Special backfill
  • 51. Installation Installation of the MITIGATOR™ along a Williams (Transco) Gas pipeline in Northern New Jersey. The pipeline is actually to the left of the MITIGATOR™ trench. The MITGATOR™ provides for easy installation, a much larger surface area for discharging copper, and the copper conductor is housed in a special backfill with corrosion inhibitors.
  • 52. From the Plattline™ Website Life expectancy of Plattline in this application would be quite long and would generally be determined by Plattline as a projected cathodic protection system. The most common sizes of Plattline for AC mitigation are plus and standard.
  • 53. Zinc Ribbon SIZE SURFACE AREA COST Standard 54.0 mm2 $2.50/ft. Plus 76.2 mm2 $5.00/ft. Super 114.3 mm2 $9.50/ft. MITIGATOR™ 119.6 mm2 $5.25/ft.
  • 54. Concerns with Zinc • Zinc can passivate and should have a special backfill when used for AC Mitigation • Zinc is much more difficult to handle and install relative to the Mitigator™ • Must use a torch to make connections • Requires more frequent use of decouplers • Will consume over time – not as long a life as copper
  • 55. Areas for more investigation • Sophisticated modeling of Mitigator™ vs. Zinc • Investigation of “propagation constant” and the spacing of decouplers for zinc vs. Mitigator™
  • 56. Summary of AC Interference • There are three key threats  Safety (15 V AC Threshold)  Fault Conditions (rare but potentially damaging)  AC Corrosion – for new well coated pipelines this can easily be the most challenging and difficult threat to control and can cause damage even at lower levels of AC
  • 57. Summary of AC Interference • Modeling may not be fully effective – especially for AC Corrosion • AC Coupons give information based on current operating conditions – changes in electrical flow affect the AC Induced Voltage • Risk Assessment can often be performed without expensive modeling
  • 58. Questions Questions?