‗Drill Questions to Pass the PMP Certification Exam‘




         Gifts of training worth over $2,000 USD
                     will be given away during this session:

             PMP Application Overview 90 minutes
     4 week PMP Accelerated Exam Prep Program – 2x weekly


      See slides #17 and #64 for Winner information
                              WARNING
An additional training will be awarded next week on a follow-up
call. READ through this presentation for the details.
       Free Drawing sponsored by PMP Interactive Consulting : # 978-290-8834 www.pmpicon.com
FREE MATERIAL



 List of Best Studying Techniques
- sample of what is shared with classes (hardcopy at
  conference)


 Copy of our white paper ―How to Pass the
  PMP Certification Exam with Confidence‖
        (electronic pdf file upon request)




                2010 National BDPA Technology Conference   3
                 PMPICON.COM All Rights Protected 2010
2010 National BDPA Technology Conference


    Drilling Questions to Pass the PMP
             Certification Exam


           Elaine Jackson, PMP
            PMP Interactive Consulting


                July 28th – July 31st
                  Philadelphia, PA
WHO ARE YOU ?

                Please share :

                 Name
                  State
               Career Path
Amount of PMP Training/Work Experience
     What made you pick this session
 1 thing you hope to learn in this session


           2010 National BDPA Technology Conference   5
            PMPICON.COM All Rights Protected 2010
WE ARE

              PMP Interactive Consulting

•5 years PMP coaching experience internationally
•we have a 95% closing rate getting you to pass the exam
•students pass exam on 1st attempt
•dedicated virtual training programs to keep students relaxed
•specializing in students that are busy and need PMP – NOW!
•virtual training any time /any place –be comfortable while studying
•corporate training for project management
•over 5 years of data collected to identify a different teaching method
       one stop source to get PMP knowledge into your head !
   Knowledge that stays with you after the exam!
                      2010 National BDPA Technology Conference   6
                       PMPICON.COM All Rights Protected 2010
Objectives


 Requirements
 PMI Audit
 PMP Test Environment
 Exam Prep
 Sample Test Material (read
   disclaimer to set realistic expectations)

 Questions

 Drawing for                  gifts
2010 National BDPA Technology Conference       7
 PMPICON.COM All Rights Protected 2010
WHAT DO YOU VALUE




              ?

 2010 National BDPA Technology Conference   8
  PMPICON.COM All Rights Protected 2010
PROJECT MANAGEMENT




HOW IS PM conducted at your company?

 HOW CAN you be a MORE EFFECTIVE
       PROJECT MANAGER?




            2010 National BDPA Technology Conference   9
             PMPICON.COM All Rights Protected 2010
USP of PMP Interactive Consulting

       PMPICON
   You pass test on 1st attempt
                                         OTHER Training Programs
   Ensures FULL understanding
                                         Limited time for each student per class
   Caring training environment
                                         You travel to their locations
   Virtual classes                      You pay for their rental locations
   ** Group and 1:1 training **         You need more study time before test
   On-site training                     You are not focused for test process
   Flexibility in scheduling            You end up paying again for same class
   Tough Love program                   X Promise to return your money if you fail
                                         (who wants money –you want your PMP)
•   Holistic Program
                                         X Guarantee you will pass the exam (are
•   Nurturing relationship
                                         they going to sit in the test with you and
•   *30 minutes free career              hold your hand?)
    assessment with my career
    coach Dargin Consulting
                        2010 National BDPA Technology Conference           10
                         PMPICON.COM All Rights Protected 2010
Requirements

 35 contact hrs of formal PMP Training

 4500 hours of documented project work
 College degree (BS or higher)
                or
 7500 hours of documents project work
 + College degree (from a junior college)

Application must be complete  tips …
            2010 National BDPA Technology Conference   11
             PMPICON.COM All Rights Protected 2010
Application Tips




• Be truthful - dedicated
• Be patient
• Research project work
   (coach can help you do it right) / SAVE TIME TOO.
 Manager Information                 (not all managers are the same)

 Use a PMP coach



                  2010 National BDPA Technology Conference        12
                   PMPICON.COM All Rights Protected 2010
Your College Training

Secure a copy of your degree




          2010 National BDPA Technology Conference   13
           PMPICON.COM All Rights Protected 2010
HOURS of PMP Work

• Work experience can be from many areas
• MUST fit in the following process groups:

Initiating
Planning
Executing
Monitoring & Controlling
Closing


             2010 National BDPA Technology Conference   14
              PMPICON.COM All Rights Protected 2010
THE AUDIT !




• 10% of applications submitted get audited
• Don‘t be AFRAID …
• BE Ready to take the exam




              2010 National BDPA Technology Conference   15
               PMPICON.COM All Rights Protected 2010
Contact HOURS




PMI may audit you
     … even after you pass the exam !

             2010 National BDPA Technology Conference   16
              PMPICON.COM All Rights Protected 2010
PRIZE DRAWING




    Free Assistance with your PMI PMP Application
Overview to help you avoid an audit due to errors on your
           PMP Certification PMI application
                    90-minute session

                    Winner:                                Not many things
                Jeannette Wiggins                         are free in life …
               CONGRATULATIONS!                            call to activate
             Award Valid until 12/31/2010                  your award.
                2010 National BDPA Technology Conference              17
                 PMPICON.COM All Rights Protected 2010
Preparing for the Exam


STUDY ----

• STUDY toward deadline
• Use current materials
 Join study groups
• Study 5+ hours daily




               2010 National BDPA Technology Conference   18
                PMPICON.COM All Rights Protected 2010
If You Have Concerns:




• contact your PMP Coach
 contact your local PMI Chapter President
• contact PMI



            2010 National BDPA Technology Conference   19
             PMPICON.COM All Rights Protected 2010
PMP Test Environment tips



• BRING CURRENT VALID ID
   leave jewelry home
•   wear loose clothing
•   bring food that gives you energy
•   bring sweater for comfort




                 2010 National BDPA Technology Conference   20
                  PMPICON.COM All Rights Protected 2010
Testing Period


• Plan for breaks         5…
• Mark questions for review
                          4…
    DON‘T CHANGE ANSWERS
                           3…
                            2…
                             1…
            2010 National BDPA Technology Conference
                                                       End of test
                                                                 21
             PMPICON.COM All Rights Protected 2010
Questions


      CALL OUT ANSWERS
YOUR FULL PARTICIPATION IS NEEDED

        DISCUSSION TIME

        **** TAKE NOTES!


         2010 National BDPA Technology Conference   22
          PMPICON.COM All Rights Protected 2010
SOURCE OF QUESTIONS

    With the permission of Oliver Lehmann the
    following PMP questions are available to anyone
    wanting extra practice questions.

                   http://www.oliverlehmann.com/contents/free-
                     downloads/175_PMP_Sample_Questions.pdf

           Feel free to use these questions to be ready for your exam.
       Contact Oliver Lehmann if you have questions related to his material.

Disclaimer: Under no circumstances will studying only these questions prepare you to pass the whole
PMP Exam. This 90 minute presentation will enhance your ability to grasp the complexity and
importance of taking time to study thoroughly!
Quality PM Instructor + great training materials + dedicated student=PMP Certification

                                 2010 National BDPA Technology Conference                  23
                                  PMPICON.COM All Rights Protected 2010
QUESTION 1
    Being assigned as a project manager, you noticed during
    executing that conflicts arise in the team on both,
    technical and interpersonal level. What is an appropriate
    way of handling conflicts?

•   1- Conflicts distract the team and disrupt the work rhythm.
    You should always smooth them when they surface.

•   2- A conflict should be handled in a meeting so that the
    entire team can participate in solution finding.

•   3- Conflict should be addressed early and usually in
    private, using a direct, collaborative approach.

•   4- You should use your coercive power to quickly resolve
    conflicts and then focus on goal achievement.               24
ANSWER 1

3- Conflict should be addressed early and
  usually in private, using a direct,
  collaborative approach.



•   PMBOK
•   RITA‘S
•   HEAD FIRST
•   ANDY CROWE

             2010 National BDPA Technology Conference   25
              PMPICON.COM All Rights Protected 2010
QUESTION 2

What is the purpose of a Project charter?
1- To formally authorize a project or a phase and document
   initial requirements that satisfy the stakeholder‘s needs
   and expectations.

•   2- To document how the project will be planned, executed,
    monitored/controlled, and closed.

•   3- To link the project, which is going to be planned,
    executed, and monitored/controlled to the ongoing work of
    the organization.

•   4- To describe the process of performing the work defined
    in the project management plan in order to achieve the
    project‘s objectives.
                   2010 National BDPA Technology Conference    26
                    PMPICON.COM All Rights Protected 2010
ANSWER 2

1- To formally authorize a project or a phase
  and document initial requirements that
  satisfy the stakeholder‘s needs and
  expectations.

•   PMBOK
•   RITA‘S
•   HEAD FIRST
•   ANDY CROWE

             2010 National BDPA Technology Conference   27
              PMPICON.COM All Rights Protected 2010
QUESTION 3

  The concept of the _________ states that changes
  related to one requirement—scope, time or
  cost—will at least influence one other element.


• 1 - Three-point estimation

• 2 - Triple constraint

• 3 - Three wise men

• 4 - Three needs theory
                2010 National BDPA Technology Conference   28
                 PMPICON.COM All Rights Protected 2010
ANSWER 3

2 - Triple constraint



PMBOK
RITA‘S
HEADFIRST
ANDY CROWE



              2010 National BDPA Technology Conference   29
               PMPICON.COM All Rights Protected 2010
QUESTION 4
What does the term Best practice often refer to?

1- A standardized set of deliverables, like plans,
   reports, and checklists.

2- A set of Tools and techniques that a project
  manager should master.

3- The concept of State of the art applied to project
  management.

4- A specific sequence of work, described in terms
   of Soft logic. 2010 National BDPA Technology Conference
                                                          30
                  PMPICON.COM All Rights Protected 2010
ANSWER 4

4- A specific sequence of work, described
  in terms of Soft logic.

PMBOK
RITA‘S
HEADFIRST
ANDY CROWE



             2010 National BDPA Technology Conference   31
              PMPICON.COM All Rights Protected 2010
QUESTION 5

 The Communications management plan is a
  document, which includes descriptions of

1- Project level performance reports

2- Activity level status reports

3- Stakeholder communication requirements

4- Responsibility assignments

                 2010 National BDPA Technology Conference   32
                  PMPICON.COM All Rights Protected 2010
ANSWER 5

3- Stakeholder communication requirements



PMBOK
RITA‘S
HEADFIRST
ANDY CROWE



             2010 National BDPA Technology Conference   33
              PMPICON.COM All Rights Protected 2010
QUESTION 6

  Which of the following is generally not regarded as
  an element of active listening:

• 1- Making eye contact

• 2- Paraphrasing

• 3- Interpreting the information

• 4- Interrupting when appropriate

                2010 National BDPA Technology Conference   34
                 PMPICON.COM All Rights Protected 2010
ANSWER 6

4- Interrupting when appropriate



PMBOK
RITA‘S
HEADFIRST
ANDY CROWE



            2010 National BDPA Technology Conference   35
             PMPICON.COM All Rights Protected 2010
QUESTION 7

When should Lessons learned be organized?

• 1- During the project lifecycle and at the end.

• 2- At the end of the project during closing.

• 3- After the end of the project at a project post-
  mortem meeting.

• 4- Lessons learned can be organized when there is
  time available.
                  2010 National BDPA Technology Conference   36
                   PMPICON.COM All Rights Protected 2010
ANSWER 7

1- During the project lifecycle and at the
  end.

PMBOK
RITA‘S
HEADFIRST
ANDY CROWE



             2010 National BDPA Technology Conference   37
              PMPICON.COM All Rights Protected 2010
STUDY TIPS




       BUILD A CHEAT SHEET
     KNOW YOUR CALCULATOR
   SECURE A QUIET ENVIRONMENT
BECOME DEDICATED TO YOUR TRAINING




          2010 National BDPA Technology Conference   38
           PMPICON.COM All Rights Protected 2010
QUESTION 8
How should change management be planned?
• 1- Changes are generally not predictable, therefore
  planning for change management cannot be sensible.

• 2- Planning for change management should be done
  while the various change control processes are being
  applied.

• 3- Change management can be planned in a set of
  management plans or a specific change management
  plan.
• 4- Changes are a sign of bad planning. One should
  avoid changes during a project thus eliminating the
  need to manage them.                              39
ANSWER 8

3- Change management can be planned in a
  set of management plans or a specific
  change management plan.

PMBOK
RITA‘S
HEADFIRST
ANDY CROWE


            2010 National BDPA Technology Conference   40
             PMPICON.COM All Rights Protected 2010
QUESTION 9

According to Bruce Tuckmann, which are the stages
  of team development?

• 1- Honeymoon, rejection, regression, acceptance,
  re-entry

• 2- Forming, storming, norming, performing

• 3- Tell, sell, consult, join

• 4- Direct, support, coach, delegate
                 2010 National BDPA Technology Conference   41
                  PMPICON.COM All Rights Protected 2010
ANSWER 9

2- Forming, storming, norming, performing



PMBOK
RITA‘S
HEADFIRST
ANDY CROWE



            2010 National BDPA Technology Conference   42
             PMPICON.COM All Rights Protected 2010
QUESTION 10

    What is not a reason for companies to
    organize Lessons learned?
•   1- Lessons learned databases are an essential element of
    the organizational process assets.

•   2- Lessons learned should focus on identifying those
    accountable for errors and failures.

•   3- Lessons learned sessions should bring about
    recommendations to improve future performance on
    projects.

•   4- Phase-end lessons learned sessions provide a good
    team building exercise for project staff members.
                   2010 National BDPA Technology Conference    43
                    PMPICON.COM All Rights Protected 2010
ANSWER 10

2- Lessons learned should focus on
  identifying those accountable for errors
  and failures.

PMBOK
RITA‘S
HEADFIRST
ANDY CROWE


             2010 National BDPA Technology Conference   44
              PMPICON.COM All Rights Protected 2010
QUESTION 11

  A facilitator should

• 1- …be in full control of the discussion and its
  outcomes.

• 2- …always take notes by herself.

• 3- …avoid a flip chart Parking lot.

• 4- …give guidance as required without interfering.


                 2010 National BDPA Technology Conference   45
                  PMPICON.COM All Rights Protected 2010
ANSWER 11

4- …give guidance as required without
  interfering.

PMBOK
RITA‘S
HEADFIRST
ANDY CROWE



            2010 National BDPA Technology Conference   46
             PMPICON.COM All Rights Protected 2010
QUESTION 12

 How does a project management team stay in touch
 with the work and the attitudes of project team
 members?

• 1- By observation and communication

• 2- Using closed questions during team meetings

• 3- Through third-party assessments

• 4- Through the team members‘ functional managers
                2010 National BDPA Technology Conference   47
                 PMPICON.COM All Rights Protected 2010
ANSWER 12

1- By observation and communication



PMBOK
RITA‘S
HEADFIRST
ANDY CROWE



            2010 National BDPA Technology Conference   48
             PMPICON.COM All Rights Protected 2010
QUESTION 13

  Which document is developed along the risk
  management processes from Identify Risks through
  Plan risk responses to Monitor and control risks?

• 1- List of risk triggers

• 2- Risk register

• 3- Risk mitigation

• 4- Decision tree
                  2010 National BDPA Technology Conference   49
                   PMPICON.COM All Rights Protected 2010
ANSWER 13

2- Risk register

PMBOK
RITA‘S
HEADFIRST
ANDY CROWE




             2010 National BDPA Technology Conference   50
              PMPICON.COM All Rights Protected 2010
QUESTION 14
  A WBS dictionary is a document which…

• 1 …describes technical terms used for scope
  management.

• 2 …describes the details for each component in
  the WBS.

• 3 …translates essential WBS terms for global
  project teams.

• 4 …helps translating functional into technical
  requirements. 2010 National BDPA Technology Conference
                                                              51
                      PMPICON.COM All Rights Protected 2010
ANSWER 14

2 …describes the details for each
  component in the WBS.

PMBOK
RITA‘S
HEADFIRST
ANDY CROWE



             2010 National BDPA Technology Conference   52
              PMPICON.COM All Rights Protected 2010
QUESTION 15
  What should managers consider before
  conducting a performance-evaluation
  interview with a project team member?

• 1-Which management fallacies can most easily be
  delegated to the worker?
• 2- How can discussion of the manager‘s leadership
  style be avoided?
• 3- Has the employee been provided with sufficient
  instructions and work tools?
• 4- How can dispute related to unsatisfactory
  performance be avoided?
                2010 National BDPA Technology Conference   53
                 PMPICON.COM All Rights Protected 2010
ANSWER 15

3- Has the employee been provided with
  sufficient instructions and work tools?

PMBOK
RITA‘S
HEADFIRST
ANDY CROWE



             2010 National BDPA Technology Conference   54
              PMPICON.COM All Rights Protected 2010
QUESTION 16
              – what formula is needed

  A project has the following Earned value data
  assessed: AC: $ 4,000,000 CV: $ -500,000 SPI:
  1.12 BaC: $ 9,650,000 What is the Earned value
  of the project?

• 1- $3,000,000

• 2- $3,500,000

• 3- $4,480,000

• 4- $5,650,000
              2010 National BDPA Technology Conference   55
               PMPICON.COM All Rights Protected 2010
Answer 16

2-   $3,500,000

PMBOK
RITA‘S
HEADFIRST
ANDY CROWE




            2010 National BDPA Technology Conference   56
             PMPICON.COM All Rights Protected 2010
NETWORK DIAGRAM

`
         FORWARD PASS

    ES               EF



          DURATION



    LS                  LF



          BACKWARD PASS      57
SCHEDULE NETWORK DIAGRAM

A = 4 (no predecessor)
B = 6 (no predecessor)
                                      Answers can be
C = 9 (predecessor : A & D)           discussed on webinar
D = 1 (predecessor: B)                next week if there is an
E = 2 (predecessor: B)                interest
F= 0 (predecessor: C &B)
- draw network diagram
- what are the paths
- what is the critical path
- draw forward and backward passes
- how much float is on activity C
- duration of activity B        2010 National BDPA Technology Conference
                                          PMPICON.COM All Rights Protected 2010
Using what you know of FS
                relationships to solve k
1       FS + 4 relationship CALCULATE MISSING VALUES
        k = missing values
                                            Think of what
        There is lag in this example!       this question is
                                                                       asking.
                                                                       We can work on this
    7                  k                  k                        k   next week if there is
                                                                       an interest.
         Duration =9                          Duration = 4
             C                                    G
         predecessor                           successor


        k              k                   k                      20

                       2010 National BDPA Technology Conference                     59
                        PMPICON.COM All Rights Protected 2010
Suggestions


• Do not be intimidated by math
• Do not daydream while in test mode
• Use the web to access more knowledge
• Get your PMP then volunteer at PMI meetings
 Enhance your profession




               2010 National BDPA Technology Conference   60
                PMPICON.COM All Rights Protected 2010
BOOKS FOR STUDYING

• PMBOK Guide 4th Edition

• PMP Exam Prep – 6th Edition (Rita Mulcahy)

• Head First PMP – 2nd Edition (Green, Stellman)

• The PMP Exam How to Pass on Your First Try
        4th Edition (Andy Crowe)


               2010 National BDPA Technology Conference   61
                PMPICON.COM All Rights Protected 2010
BOOKS TO ENHANCE

• Results Without Authority - Controlling a
  Project When The Team Does Not Belong to
  You (Kendrick)

• The One Page Project Manager (Campbell)




              2010 National BDPA Technology Conference   62
               PMPICON.COM All Rights Protected 2010
READING FOR FUN AND
                  KNOWLEDGE

• 100 Things Project Managers Should Do
  Before They Die (Rita Mulcahy)

• The Lazy Project Manager (Peter Taylor)
(www.thelazyprojectmanager.net
With this project management training course you can learn more
   about productive laziness and how you can apply a number of
   simple techniques and approaches in your own projects to make
   your life a whole lot less stressful.
Learn how to be twice as productive and still leave the office early!




                    2010 National BDPA Technology Conference       63
                     PMPICON.COM All Rights Protected 2010
FINAL DRAWING

         4-WEEK Accelerated PMP Training
                       Program
             Virtual Class Environment
       Meeting 2x weekly for 90 minute classes
                                                        This award was only
                                                        for individuals NOT YET
                                                        certified. I will award
                                                        Another free training class
        Winner:                                         at a webinar next
 Valerie Johnson, PMP                                   week - look for my mail.
 CONGRATULATIONS!                                       The 1st one to join the
Award Valid until 12/31/2010                            call gets the training.
                      2010 National BDPA Technology Conference              64
                       PMPICON.COM All Rights Protected 2010
ONE PIECE OF ADVICE




GET MENTORED



    2010 National BDPA Technology Conference   65
     PMPICON.COM All Rights Protected 2010
KEY TAKE-AWAY



WHAT ARE YOU GOING TO DO
        DIFFERENT
  TO PREPARE FOR YOUR
 PMP CERTIFICATION EXAM?



       2010 National BDPA Technology Conference   66
        PMPICON.COM All Rights Protected 2010
WHAT HAPPENS AFTER PMP?

              YOU NEED A PLAN

-   PROMOTE YOUR PMP
-   WORK YOUR POSITION FOR A RAISE
-   GET CERTIFICATION FOR PROMOTIONS
-   WRITE A BOOK

     Make your plan work for your life goals !


                 2010 National BDPA Technology Conference   67
                  PMPICON.COM All Rights Protected 2010
REFERENCES

                  CALL – TO – ACTION

• Refer your company (PMP Corporate Training Program)
• Refer your co-workers (PMP 1:1 and group training classes)
             We PAY finder fees for referrals $!$
                 Contact us for benefits …



                           $$$
                    2010 National BDPA Technology Conference   68
                     PMPICON.COM All Rights Protected 2010
… AND …



•   Join our listing for training notices
•   Gain access to monthly PMP chats/webinars
•   Network with those that can help your career
•   Form teaming agreements for future projects
•   International chats
•   Focus ahead of where you are now !

                  FREE PDU’s
                  2010 National BDPA Technology Conference   69
                   PMPICON.COM All Rights Protected 2010
CLIENT REFERENCES
Aimee L. Strang, PMP
(client)

 “I highly recommend Elaine's PMP certification study group course for anyone
planning to take the PMP in order to advance their careers. The course is particularly
helpful for those who need to retake the exam or whose jobs require that they be
certified. The study group meets virtually via web meeting which is a hugely
beneficial for working professionals! In addition, Elaine is extremely flexible and
accommodating with participants. In addition, Elaine knows her stuff! The PMP isn't
just about learning the material but also knowing HOW to take approach and tackle
the test. The course is excellent for those who need a refreshers course in test taking
skills. Elaine knows what study materials to recommend and will tailor sessions to fit
YOUR needs. She's not going to sugar coat it. Elaine tells it like it is—which is both
hard to find and welcomed. Elaine does everything in her ethical power to
thoroughly prepare participants for the exam.” January 30, 2010

                             2010 National BDPA Technology Conference          70
                              PMPICON.COM All Rights Protected 2010
CLIENT REFERENCES
Carla Rambo -
(client)

“As I read all of Elaine's recommendations, it is clear that the value
that Elaine brought to me was exactly what she provided others. She
committed to my professional growth as much as she would commit to
a large corporate enterprise. She was creative, worked diligently to
remove any of my roadblocks and was a huge support. I thoroughly
enjoyed all of my interactions with her and one day, I hope to meet
her personally, to thank her. Everyone needs to have Elaine on their
team! Make sure she's in your court, too... you'll be so very glad you
did. Thank you Elaine. --Carla” March 25, 2010


                       2010 National BDPA Technology Conference   71
                        PMPICON.COM All Rights Protected 2010
???




2010 National BDPA Technology Conference   72
 PMPICON.COM All Rights Protected 2010
CONTACT

    Elaine Jackson, PMP
       President, CEO
 PMP Interactive Consulting
     www.pmpicon.com
 elainetjackson@gmail.com
       # 978-290-8834

  connections accepted on:
LinkedIN & Twitter & Facebook
     2010 National BDPA Technology Conference   73
      PMPICON.COM All Rights Protected 2010

Drill Questions to Pass the PMP Exam

  • 1.
    POST CONFERENCE THANKYOU NOTE Thanks for allowing me to share great information related to the PMP Certification Exam Preparation. Here is the slide deck shared at the conference with some additional changes and a huge surprise. Reading important material can be quite rewarding at times! See you at next year’s conference in Chicago. Elaine Jackson, PMP 2010 National BDPA Technology Conference 1 PMPICON.COM All Rights Protected 2010
  • 2.
    ‗Drill Questions toPass the PMP Certification Exam‘ Gifts of training worth over $2,000 USD will be given away during this session: PMP Application Overview 90 minutes 4 week PMP Accelerated Exam Prep Program – 2x weekly See slides #17 and #64 for Winner information WARNING An additional training will be awarded next week on a follow-up call. READ through this presentation for the details. Free Drawing sponsored by PMP Interactive Consulting : # 978-290-8834 www.pmpicon.com
  • 3.
    FREE MATERIAL  Listof Best Studying Techniques - sample of what is shared with classes (hardcopy at conference)  Copy of our white paper ―How to Pass the PMP Certification Exam with Confidence‖ (electronic pdf file upon request) 2010 National BDPA Technology Conference 3 PMPICON.COM All Rights Protected 2010
  • 4.
    2010 National BDPATechnology Conference Drilling Questions to Pass the PMP Certification Exam Elaine Jackson, PMP PMP Interactive Consulting July 28th – July 31st Philadelphia, PA
  • 5.
    WHO ARE YOU? Please share : Name State Career Path Amount of PMP Training/Work Experience What made you pick this session 1 thing you hope to learn in this session 2010 National BDPA Technology Conference 5 PMPICON.COM All Rights Protected 2010
  • 6.
    WE ARE PMP Interactive Consulting •5 years PMP coaching experience internationally •we have a 95% closing rate getting you to pass the exam •students pass exam on 1st attempt •dedicated virtual training programs to keep students relaxed •specializing in students that are busy and need PMP – NOW! •virtual training any time /any place –be comfortable while studying •corporate training for project management •over 5 years of data collected to identify a different teaching method one stop source to get PMP knowledge into your head ! Knowledge that stays with you after the exam! 2010 National BDPA Technology Conference 6 PMPICON.COM All Rights Protected 2010
  • 7.
    Objectives  Requirements  PMIAudit  PMP Test Environment  Exam Prep  Sample Test Material (read disclaimer to set realistic expectations)  Questions  Drawing for gifts 2010 National BDPA Technology Conference 7 PMPICON.COM All Rights Protected 2010
  • 8.
    WHAT DO YOUVALUE ? 2010 National BDPA Technology Conference 8 PMPICON.COM All Rights Protected 2010
  • 9.
    PROJECT MANAGEMENT HOW ISPM conducted at your company? HOW CAN you be a MORE EFFECTIVE PROJECT MANAGER? 2010 National BDPA Technology Conference 9 PMPICON.COM All Rights Protected 2010
  • 10.
    USP of PMPInteractive Consulting PMPICON  You pass test on 1st attempt OTHER Training Programs  Ensures FULL understanding Limited time for each student per class  Caring training environment You travel to their locations  Virtual classes You pay for their rental locations  ** Group and 1:1 training ** You need more study time before test  On-site training You are not focused for test process  Flexibility in scheduling You end up paying again for same class  Tough Love program X Promise to return your money if you fail (who wants money –you want your PMP) • Holistic Program X Guarantee you will pass the exam (are • Nurturing relationship they going to sit in the test with you and • *30 minutes free career hold your hand?) assessment with my career coach Dargin Consulting 2010 National BDPA Technology Conference 10 PMPICON.COM All Rights Protected 2010
  • 11.
    Requirements  35 contacthrs of formal PMP Training  4500 hours of documented project work  College degree (BS or higher) or  7500 hours of documents project work  + College degree (from a junior college) Application must be complete  tips … 2010 National BDPA Technology Conference 11 PMPICON.COM All Rights Protected 2010
  • 12.
    Application Tips • Betruthful - dedicated • Be patient • Research project work (coach can help you do it right) / SAVE TIME TOO.  Manager Information (not all managers are the same)  Use a PMP coach 2010 National BDPA Technology Conference 12 PMPICON.COM All Rights Protected 2010
  • 13.
    Your College Training Securea copy of your degree 2010 National BDPA Technology Conference 13 PMPICON.COM All Rights Protected 2010
  • 14.
    HOURS of PMPWork • Work experience can be from many areas • MUST fit in the following process groups: Initiating Planning Executing Monitoring & Controlling Closing 2010 National BDPA Technology Conference 14 PMPICON.COM All Rights Protected 2010
  • 15.
    THE AUDIT ! •10% of applications submitted get audited • Don‘t be AFRAID … • BE Ready to take the exam 2010 National BDPA Technology Conference 15 PMPICON.COM All Rights Protected 2010
  • 16.
    Contact HOURS PMI mayaudit you … even after you pass the exam ! 2010 National BDPA Technology Conference 16 PMPICON.COM All Rights Protected 2010
  • 17.
    PRIZE DRAWING Free Assistance with your PMI PMP Application Overview to help you avoid an audit due to errors on your PMP Certification PMI application 90-minute session Winner: Not many things Jeannette Wiggins are free in life … CONGRATULATIONS! call to activate Award Valid until 12/31/2010 your award. 2010 National BDPA Technology Conference 17 PMPICON.COM All Rights Protected 2010
  • 18.
    Preparing for theExam STUDY ---- • STUDY toward deadline • Use current materials  Join study groups • Study 5+ hours daily 2010 National BDPA Technology Conference 18 PMPICON.COM All Rights Protected 2010
  • 19.
    If You HaveConcerns: • contact your PMP Coach  contact your local PMI Chapter President • contact PMI 2010 National BDPA Technology Conference 19 PMPICON.COM All Rights Protected 2010
  • 20.
    PMP Test Environmenttips • BRING CURRENT VALID ID  leave jewelry home • wear loose clothing • bring food that gives you energy • bring sweater for comfort 2010 National BDPA Technology Conference 20 PMPICON.COM All Rights Protected 2010
  • 21.
    Testing Period • Planfor breaks 5… • Mark questions for review 4…  DON‘T CHANGE ANSWERS 3… 2… 1… 2010 National BDPA Technology Conference End of test 21 PMPICON.COM All Rights Protected 2010
  • 22.
    Questions  CALL OUT ANSWERS YOUR FULL PARTICIPATION IS NEEDED DISCUSSION TIME **** TAKE NOTES! 2010 National BDPA Technology Conference 22 PMPICON.COM All Rights Protected 2010
  • 23.
    SOURCE OF QUESTIONS With the permission of Oliver Lehmann the following PMP questions are available to anyone wanting extra practice questions. http://www.oliverlehmann.com/contents/free- downloads/175_PMP_Sample_Questions.pdf Feel free to use these questions to be ready for your exam. Contact Oliver Lehmann if you have questions related to his material. Disclaimer: Under no circumstances will studying only these questions prepare you to pass the whole PMP Exam. This 90 minute presentation will enhance your ability to grasp the complexity and importance of taking time to study thoroughly! Quality PM Instructor + great training materials + dedicated student=PMP Certification 2010 National BDPA Technology Conference 23 PMPICON.COM All Rights Protected 2010
  • 24.
    QUESTION 1 Being assigned as a project manager, you noticed during executing that conflicts arise in the team on both, technical and interpersonal level. What is an appropriate way of handling conflicts? • 1- Conflicts distract the team and disrupt the work rhythm. You should always smooth them when they surface. • 2- A conflict should be handled in a meeting so that the entire team can participate in solution finding. • 3- Conflict should be addressed early and usually in private, using a direct, collaborative approach. • 4- You should use your coercive power to quickly resolve conflicts and then focus on goal achievement. 24
  • 25.
    ANSWER 1 3- Conflictshould be addressed early and usually in private, using a direct, collaborative approach. • PMBOK • RITA‘S • HEAD FIRST • ANDY CROWE 2010 National BDPA Technology Conference 25 PMPICON.COM All Rights Protected 2010
  • 26.
    QUESTION 2 What isthe purpose of a Project charter? 1- To formally authorize a project or a phase and document initial requirements that satisfy the stakeholder‘s needs and expectations. • 2- To document how the project will be planned, executed, monitored/controlled, and closed. • 3- To link the project, which is going to be planned, executed, and monitored/controlled to the ongoing work of the organization. • 4- To describe the process of performing the work defined in the project management plan in order to achieve the project‘s objectives. 2010 National BDPA Technology Conference 26 PMPICON.COM All Rights Protected 2010
  • 27.
    ANSWER 2 1- Toformally authorize a project or a phase and document initial requirements that satisfy the stakeholder‘s needs and expectations. • PMBOK • RITA‘S • HEAD FIRST • ANDY CROWE 2010 National BDPA Technology Conference 27 PMPICON.COM All Rights Protected 2010
  • 28.
    QUESTION 3 The concept of the _________ states that changes related to one requirement—scope, time or cost—will at least influence one other element. • 1 - Three-point estimation • 2 - Triple constraint • 3 - Three wise men • 4 - Three needs theory 2010 National BDPA Technology Conference 28 PMPICON.COM All Rights Protected 2010
  • 29.
    ANSWER 3 2 -Triple constraint PMBOK RITA‘S HEADFIRST ANDY CROWE 2010 National BDPA Technology Conference 29 PMPICON.COM All Rights Protected 2010
  • 30.
    QUESTION 4 What doesthe term Best practice often refer to? 1- A standardized set of deliverables, like plans, reports, and checklists. 2- A set of Tools and techniques that a project manager should master. 3- The concept of State of the art applied to project management. 4- A specific sequence of work, described in terms of Soft logic. 2010 National BDPA Technology Conference 30 PMPICON.COM All Rights Protected 2010
  • 31.
    ANSWER 4 4- Aspecific sequence of work, described in terms of Soft logic. PMBOK RITA‘S HEADFIRST ANDY CROWE 2010 National BDPA Technology Conference 31 PMPICON.COM All Rights Protected 2010
  • 32.
    QUESTION 5 TheCommunications management plan is a document, which includes descriptions of 1- Project level performance reports 2- Activity level status reports 3- Stakeholder communication requirements 4- Responsibility assignments 2010 National BDPA Technology Conference 32 PMPICON.COM All Rights Protected 2010
  • 33.
    ANSWER 5 3- Stakeholdercommunication requirements PMBOK RITA‘S HEADFIRST ANDY CROWE 2010 National BDPA Technology Conference 33 PMPICON.COM All Rights Protected 2010
  • 34.
    QUESTION 6 Which of the following is generally not regarded as an element of active listening: • 1- Making eye contact • 2- Paraphrasing • 3- Interpreting the information • 4- Interrupting when appropriate 2010 National BDPA Technology Conference 34 PMPICON.COM All Rights Protected 2010
  • 35.
    ANSWER 6 4- Interruptingwhen appropriate PMBOK RITA‘S HEADFIRST ANDY CROWE 2010 National BDPA Technology Conference 35 PMPICON.COM All Rights Protected 2010
  • 36.
    QUESTION 7 When shouldLessons learned be organized? • 1- During the project lifecycle and at the end. • 2- At the end of the project during closing. • 3- After the end of the project at a project post- mortem meeting. • 4- Lessons learned can be organized when there is time available. 2010 National BDPA Technology Conference 36 PMPICON.COM All Rights Protected 2010
  • 37.
    ANSWER 7 1- Duringthe project lifecycle and at the end. PMBOK RITA‘S HEADFIRST ANDY CROWE 2010 National BDPA Technology Conference 37 PMPICON.COM All Rights Protected 2010
  • 38.
    STUDY TIPS BUILD A CHEAT SHEET KNOW YOUR CALCULATOR SECURE A QUIET ENVIRONMENT BECOME DEDICATED TO YOUR TRAINING 2010 National BDPA Technology Conference 38 PMPICON.COM All Rights Protected 2010
  • 39.
    QUESTION 8 How shouldchange management be planned? • 1- Changes are generally not predictable, therefore planning for change management cannot be sensible. • 2- Planning for change management should be done while the various change control processes are being applied. • 3- Change management can be planned in a set of management plans or a specific change management plan. • 4- Changes are a sign of bad planning. One should avoid changes during a project thus eliminating the need to manage them. 39
  • 40.
    ANSWER 8 3- Changemanagement can be planned in a set of management plans or a specific change management plan. PMBOK RITA‘S HEADFIRST ANDY CROWE 2010 National BDPA Technology Conference 40 PMPICON.COM All Rights Protected 2010
  • 41.
    QUESTION 9 According toBruce Tuckmann, which are the stages of team development? • 1- Honeymoon, rejection, regression, acceptance, re-entry • 2- Forming, storming, norming, performing • 3- Tell, sell, consult, join • 4- Direct, support, coach, delegate 2010 National BDPA Technology Conference 41 PMPICON.COM All Rights Protected 2010
  • 42.
    ANSWER 9 2- Forming,storming, norming, performing PMBOK RITA‘S HEADFIRST ANDY CROWE 2010 National BDPA Technology Conference 42 PMPICON.COM All Rights Protected 2010
  • 43.
    QUESTION 10 What is not a reason for companies to organize Lessons learned? • 1- Lessons learned databases are an essential element of the organizational process assets. • 2- Lessons learned should focus on identifying those accountable for errors and failures. • 3- Lessons learned sessions should bring about recommendations to improve future performance on projects. • 4- Phase-end lessons learned sessions provide a good team building exercise for project staff members. 2010 National BDPA Technology Conference 43 PMPICON.COM All Rights Protected 2010
  • 44.
    ANSWER 10 2- Lessonslearned should focus on identifying those accountable for errors and failures. PMBOK RITA‘S HEADFIRST ANDY CROWE 2010 National BDPA Technology Conference 44 PMPICON.COM All Rights Protected 2010
  • 45.
    QUESTION 11 A facilitator should • 1- …be in full control of the discussion and its outcomes. • 2- …always take notes by herself. • 3- …avoid a flip chart Parking lot. • 4- …give guidance as required without interfering. 2010 National BDPA Technology Conference 45 PMPICON.COM All Rights Protected 2010
  • 46.
    ANSWER 11 4- …giveguidance as required without interfering. PMBOK RITA‘S HEADFIRST ANDY CROWE 2010 National BDPA Technology Conference 46 PMPICON.COM All Rights Protected 2010
  • 47.
    QUESTION 12 Howdoes a project management team stay in touch with the work and the attitudes of project team members? • 1- By observation and communication • 2- Using closed questions during team meetings • 3- Through third-party assessments • 4- Through the team members‘ functional managers 2010 National BDPA Technology Conference 47 PMPICON.COM All Rights Protected 2010
  • 48.
    ANSWER 12 1- Byobservation and communication PMBOK RITA‘S HEADFIRST ANDY CROWE 2010 National BDPA Technology Conference 48 PMPICON.COM All Rights Protected 2010
  • 49.
    QUESTION 13 Which document is developed along the risk management processes from Identify Risks through Plan risk responses to Monitor and control risks? • 1- List of risk triggers • 2- Risk register • 3- Risk mitigation • 4- Decision tree 2010 National BDPA Technology Conference 49 PMPICON.COM All Rights Protected 2010
  • 50.
    ANSWER 13 2- Riskregister PMBOK RITA‘S HEADFIRST ANDY CROWE 2010 National BDPA Technology Conference 50 PMPICON.COM All Rights Protected 2010
  • 51.
    QUESTION 14 A WBS dictionary is a document which… • 1 …describes technical terms used for scope management. • 2 …describes the details for each component in the WBS. • 3 …translates essential WBS terms for global project teams. • 4 …helps translating functional into technical requirements. 2010 National BDPA Technology Conference 51 PMPICON.COM All Rights Protected 2010
  • 52.
    ANSWER 14 2 …describesthe details for each component in the WBS. PMBOK RITA‘S HEADFIRST ANDY CROWE 2010 National BDPA Technology Conference 52 PMPICON.COM All Rights Protected 2010
  • 53.
    QUESTION 15 What should managers consider before conducting a performance-evaluation interview with a project team member? • 1-Which management fallacies can most easily be delegated to the worker? • 2- How can discussion of the manager‘s leadership style be avoided? • 3- Has the employee been provided with sufficient instructions and work tools? • 4- How can dispute related to unsatisfactory performance be avoided? 2010 National BDPA Technology Conference 53 PMPICON.COM All Rights Protected 2010
  • 54.
    ANSWER 15 3- Hasthe employee been provided with sufficient instructions and work tools? PMBOK RITA‘S HEADFIRST ANDY CROWE 2010 National BDPA Technology Conference 54 PMPICON.COM All Rights Protected 2010
  • 55.
    QUESTION 16 – what formula is needed A project has the following Earned value data assessed: AC: $ 4,000,000 CV: $ -500,000 SPI: 1.12 BaC: $ 9,650,000 What is the Earned value of the project? • 1- $3,000,000 • 2- $3,500,000 • 3- $4,480,000 • 4- $5,650,000 2010 National BDPA Technology Conference 55 PMPICON.COM All Rights Protected 2010
  • 56.
    Answer 16 2- $3,500,000 PMBOK RITA‘S HEADFIRST ANDY CROWE 2010 National BDPA Technology Conference 56 PMPICON.COM All Rights Protected 2010
  • 57.
    NETWORK DIAGRAM ` FORWARD PASS ES EF DURATION LS LF BACKWARD PASS 57
  • 58.
    SCHEDULE NETWORK DIAGRAM A= 4 (no predecessor) B = 6 (no predecessor) Answers can be C = 9 (predecessor : A & D) discussed on webinar D = 1 (predecessor: B) next week if there is an E = 2 (predecessor: B) interest F= 0 (predecessor: C &B) - draw network diagram - what are the paths - what is the critical path - draw forward and backward passes - how much float is on activity C - duration of activity B 2010 National BDPA Technology Conference PMPICON.COM All Rights Protected 2010
  • 59.
    Using what youknow of FS relationships to solve k 1 FS + 4 relationship CALCULATE MISSING VALUES k = missing values Think of what There is lag in this example! this question is asking. We can work on this 7 k k k next week if there is an interest. Duration =9 Duration = 4 C G predecessor successor k k k 20 2010 National BDPA Technology Conference 59 PMPICON.COM All Rights Protected 2010
  • 60.
    Suggestions • Do notbe intimidated by math • Do not daydream while in test mode • Use the web to access more knowledge • Get your PMP then volunteer at PMI meetings  Enhance your profession 2010 National BDPA Technology Conference 60 PMPICON.COM All Rights Protected 2010
  • 61.
    BOOKS FOR STUDYING •PMBOK Guide 4th Edition • PMP Exam Prep – 6th Edition (Rita Mulcahy) • Head First PMP – 2nd Edition (Green, Stellman) • The PMP Exam How to Pass on Your First Try 4th Edition (Andy Crowe) 2010 National BDPA Technology Conference 61 PMPICON.COM All Rights Protected 2010
  • 62.
    BOOKS TO ENHANCE •Results Without Authority - Controlling a Project When The Team Does Not Belong to You (Kendrick) • The One Page Project Manager (Campbell) 2010 National BDPA Technology Conference 62 PMPICON.COM All Rights Protected 2010
  • 63.
    READING FOR FUNAND KNOWLEDGE • 100 Things Project Managers Should Do Before They Die (Rita Mulcahy) • The Lazy Project Manager (Peter Taylor) (www.thelazyprojectmanager.net With this project management training course you can learn more about productive laziness and how you can apply a number of simple techniques and approaches in your own projects to make your life a whole lot less stressful. Learn how to be twice as productive and still leave the office early! 2010 National BDPA Technology Conference 63 PMPICON.COM All Rights Protected 2010
  • 64.
    FINAL DRAWING 4-WEEK Accelerated PMP Training Program Virtual Class Environment Meeting 2x weekly for 90 minute classes This award was only for individuals NOT YET certified. I will award Another free training class Winner: at a webinar next Valerie Johnson, PMP week - look for my mail. CONGRATULATIONS! The 1st one to join the Award Valid until 12/31/2010 call gets the training. 2010 National BDPA Technology Conference 64 PMPICON.COM All Rights Protected 2010
  • 65.
    ONE PIECE OFADVICE GET MENTORED 2010 National BDPA Technology Conference 65 PMPICON.COM All Rights Protected 2010
  • 66.
    KEY TAKE-AWAY WHAT AREYOU GOING TO DO DIFFERENT TO PREPARE FOR YOUR PMP CERTIFICATION EXAM? 2010 National BDPA Technology Conference 66 PMPICON.COM All Rights Protected 2010
  • 67.
    WHAT HAPPENS AFTERPMP? YOU NEED A PLAN - PROMOTE YOUR PMP - WORK YOUR POSITION FOR A RAISE - GET CERTIFICATION FOR PROMOTIONS - WRITE A BOOK Make your plan work for your life goals ! 2010 National BDPA Technology Conference 67 PMPICON.COM All Rights Protected 2010
  • 68.
    REFERENCES CALL – TO – ACTION • Refer your company (PMP Corporate Training Program) • Refer your co-workers (PMP 1:1 and group training classes) We PAY finder fees for referrals $!$ Contact us for benefits … $$$ 2010 National BDPA Technology Conference 68 PMPICON.COM All Rights Protected 2010
  • 69.
    … AND … • Join our listing for training notices • Gain access to monthly PMP chats/webinars • Network with those that can help your career • Form teaming agreements for future projects • International chats • Focus ahead of where you are now ! FREE PDU’s 2010 National BDPA Technology Conference 69 PMPICON.COM All Rights Protected 2010
  • 70.
    CLIENT REFERENCES Aimee L.Strang, PMP (client) “I highly recommend Elaine's PMP certification study group course for anyone planning to take the PMP in order to advance their careers. The course is particularly helpful for those who need to retake the exam or whose jobs require that they be certified. The study group meets virtually via web meeting which is a hugely beneficial for working professionals! In addition, Elaine is extremely flexible and accommodating with participants. In addition, Elaine knows her stuff! The PMP isn't just about learning the material but also knowing HOW to take approach and tackle the test. The course is excellent for those who need a refreshers course in test taking skills. Elaine knows what study materials to recommend and will tailor sessions to fit YOUR needs. She's not going to sugar coat it. Elaine tells it like it is—which is both hard to find and welcomed. Elaine does everything in her ethical power to thoroughly prepare participants for the exam.” January 30, 2010 2010 National BDPA Technology Conference 70 PMPICON.COM All Rights Protected 2010
  • 71.
    CLIENT REFERENCES Carla Rambo- (client) “As I read all of Elaine's recommendations, it is clear that the value that Elaine brought to me was exactly what she provided others. She committed to my professional growth as much as she would commit to a large corporate enterprise. She was creative, worked diligently to remove any of my roadblocks and was a huge support. I thoroughly enjoyed all of my interactions with her and one day, I hope to meet her personally, to thank her. Everyone needs to have Elaine on their team! Make sure she's in your court, too... you'll be so very glad you did. Thank you Elaine. --Carla” March 25, 2010 2010 National BDPA Technology Conference 71 PMPICON.COM All Rights Protected 2010
  • 72.
    ??? 2010 National BDPATechnology Conference 72 PMPICON.COM All Rights Protected 2010
  • 73.
    CONTACT Elaine Jackson, PMP President, CEO PMP Interactive Consulting www.pmpicon.com elainetjackson@gmail.com # 978-290-8834 connections accepted on: LinkedIN & Twitter & Facebook 2010 National BDPA Technology Conference 73 PMPICON.COM All Rights Protected 2010