SlideShare a Scribd company logo
TABLE OF CONTENTS
SECTIONS
1.0 HYDROLOGY
1.1 TOTAL AREA
1.2 OUTSIDE TRIBUTARY AREA
1.3 SOIL TYPE
1.4 TIME OF CONCENTRATION
1.5 RAINFALL INTENSITY
1.6 RUN OFF COEFFICIENT
1.7 CALCULATION OF PEAK DISCHARGE
2.0 HYDRAULIC CALCULATIONS
2.1 50 YEAR STORM EVENT
2.2 100 YEAR STORM EVENT
ATTACHMENTS
VICINITY MAP
ORANGE COUNTY – HYDROLOGY MANUAL SOILS MAP
ORANGE COUNTY – HYDROLOGY MANUAL – FIGURE D-1
ORANGE COUNTY – HYDROLOGY MANUAL – FIGURE B-3
HYDROLOGY SITE PLAN
HYDROCAD SOFTWARE OUTPUT DATA
1. HYDROLOGY
AREAS
1.1 TOTAL AREA:
Lot Area = 32,354 SF
Total Drainage Areas = 17,532 SF
Total Acres = 0.402 AC
AREA 1 = 3,913 SF
Acres = 0.089 AC
AREA 2 = 13,619 SF
Acres = 0.312 AC
1.2 OUTSIDE TRIBUTARY AREA:
AREA 3 = 14,822 SF
Acres = 0.340 AC
1.3 SOIL TYPE
Soil Type C
-Taken from Orange County Hydrologic Classification of Soils Map (Plate A)
see Appendix
1.4 TIME OF CONCENTRATION
Drainage Areas: A1 & A2
Length (L) of initial area = 179.52 FT
Difference in Elevation for Initial Area (ft) = 10.82 FT
Use Single Family – 1 Acre Lot
Time of Concentration (Tc) (min.) = 5 min. 30 s
Tc was calculated from the Orange county Hydrology Manual Figure D-1 (included)
1.5 RAINFALL INTENSITY
Return Period 50 Years
𝐼(𝑡) = 𝑎𝑡 𝑏
𝐼(𝑡) = (13.521)(5.5)−0.566
𝐼(𝑡) = 5.15 Intensity (in/hr)
Return Period 100 Years
𝐼(𝑡) = 𝑎𝑡 𝑏
𝐼(𝑡) = (15.560)(5.5)−0.573
𝐼(𝑡) = 5.86 Intensity (in/hr)
Values and equations taken from the Orange County Hydrology Manual
(Figure B-3) see attached.
1.6 RUN OFF COEFFICIENT
C = [ai + (
(I−Fp)ap
I
)] Orange County Hydrology Manual
Equation D-3
Where,
C = Runoff Coefficient
I = Rainfall Intensity (inches/Hour)
Fp = Infiltration Rate for Previous Areas (Inches/Hour)
ai = Ratio of Impervious Area to Total Area
Ap = Ratio of Pervious Area to Total Area (ap = 1-ai)
Impervious Area = 12,612 SF
Total Area = 17,532 SF
ai = 0.72
ap = 0.28
Fp = 0.25 in/hr
I (50) = 5.15 in/hr
I (100) = 5.86 in/hr
C(50) = [0.72 + (
(5.15−0.25)0.28
5.15
)]
C(50) = 0.986
C(100) = [0.72 + (
(5.86−0.25)0.28
5.86
)]
C(100) = 0.988
1.7 CALCULATE PEAK DISCHARGE (Q)
Q=C(I)(A)
C (Run Off Coefficient) 0.986
I (Rainfall Intensity in/hr A1) 5.15 CFS 0.46 CFS 1.600831
I (Rainfall Intensity in/hr A2) 5.15 GPM 206.4 GPM 718.5
A1 (Area of Section ft^2) 3913 Q(tot)= 2.06 CFS
A2 (Area of Section ft^2) 13619
C (Run Off Coefficient) 0.988
I (Rainfall Intensity in/hr A1) 5.86 CFS 0.52 CFS 1.825223
I (Rainfall Intensity in/hr A2) 5.86 GPM 235.4 GPM 819.2
A1 (Area of Section ft^2) 3913 Q(tot)= 2.35 CFS
A2 (Area of Section ft^2) 13619
50 Years
Area 2
100 Years
Inputs Outputs (Flow Q)
Area 1 Area 2
Inputs
Area 1
Outputs (Flow Q)
2.0 HYDRAULIC CALCULATIONS
Using the Manning’s Equation: 𝑉 =
𝑙
𝑛
∗ 𝑅
2
3 ∗ 𝑆
1
2
Where:
n = Coefficient of Roughness
v = Water velocity down the channel (ft/sec) = flow/Cross Sectional Area
R = Hydraulic radius (ft) = cross sectional area (ft^2)/wetted perimeter (ft)
S = Gradient of channel (ft/ft)
2.1 50 YEAR STORM EVENT
1’ X 1’ Rectangular Channel
INPUT DATA OUTPUT DATA
Flow rate 2.06 CFS Depth of Flow 0.66 ft or 7.92 in
Slope (s) 0.01 FT/FT Max Velocity 3.79 FPS
Manning’s n 0.017 (unfinished PCC) Max Output Flow 2.39 CFS
Shape Channel 1’ Wide Capacity 4.2 CFS
Depth 1 FT Percent full 66%
See Attached HydroCAD Output Data
Depth of Channel > Depth of Flow
12 in > 7.92 in  OK
Design is for two 4” PVC lines
Calculations are for two 4” PVC line therefore flow is input as half from maximum flow from channel
INPUT DATA OUTPUT DATA
Flow rate 1.03 CFS Depth of Flow 0.17 FT or 2.04 IN
Slope (s) 0.67 FT/FT Max Velocity 23.32 FPS
Manning’s n 0.010 Max Output Flow 1.03 CFS
Shape 4” Dia PVC Capacity 2.03 CFS
Depth 4 IN Percent full 51%
See Attached HydroCAD Output Data
Depth of Pipe > Depth of Flow
4 in > 2.04 in  OK
2.2 100 YEAR STORM EVENT
1’ X 1’ Rectangular Channel
INPUT DATA OUTPUT DATA
Flow rate 2.35CFS Depth of Flow 0.74 FT or 8.88 IN
Slope (s) 0.01 ft/ft Max Velocity 3.90 FPS
Manning’s n 0.017 Max Output Flow 2.18 CFS
Shape Channel 1’ Wide Capacity 4.2 CFS
Depth 1 FT Percent full 74%
See Attached HydroCAD Output Data
Depth of Channel > Depth of Flow
12 in > 8.88 in  OK
Design is for two 4” PVC lines
Calculations are for two 4” PVC line therefore flow is input as half from maximum flow from channel
INPUT DATA OUTPUT DATA
Flow rate 1.18 CFS Depth of Flow 0.18 FT or 2.16 IN
Slope (s) 0.67 FT/FT Max Velocity 24.1 FPS
Manning’s n 0.010 Max Output Flow 1.18 CFS
Shape 4” Dia PVC Capacity 2.03 CFS
Depth 4 IN Percent full 54%
See Attached HydroCAD Output Data
Depth of Pipe > Depth of Flow
12 in > 2.06 in  OK

More Related Content

Similar to 15005_Hydrology

WATERSHED CATCHMENT.pdf
WATERSHED CATCHMENT.pdfWATERSHED CATCHMENT.pdf
WATERSHED CATCHMENT.pdf
CtKamariahMdSaat
 
SARNATH-PROFILE-CAE
SARNATH-PROFILE-CAESARNATH-PROFILE-CAE
SARNATH-PROFILE-CAE
Sarnath R
 
Presentation 7 a ce 904 Hydrology by Rabindra Ranjan Saha, PEng, Associate P...
Presentation  7 a ce 904 Hydrology by Rabindra Ranjan Saha, PEng, Associate P...Presentation  7 a ce 904 Hydrology by Rabindra Ranjan Saha, PEng, Associate P...
Presentation 7 a ce 904 Hydrology by Rabindra Ranjan Saha, PEng, Associate P...
World University of Bangladesh
 
M.i tank
M.i  tankM.i  tank
M.i tank
beerappa143
 
Post development storm EmpireEng FINAL REPORT
Post development storm EmpireEng FINAL REPORTPost development storm EmpireEng FINAL REPORT
Post development storm EmpireEng FINAL REPORT
Shawn Austin Smyth
 
Terrace effects on soil erosion processes
Terrace effects on soil erosion processesTerrace effects on soil erosion processes
Terrace effects on soil erosion processes
Hui Shao
 
Final presentation
Final presentationFinal presentation
Final presentation
Asma-ul Husna
 
Process calculation condensation
Process calculation  condensationProcess calculation  condensation
Process calculation condensation
Chandran Udumbasseri
 
LinkedIn
LinkedInLinkedIn
LinkedIn
Col Andrews
 
Water Supply and Sewerage Design
Water Supply and Sewerage DesignWater Supply and Sewerage Design
Water Supply and Sewerage Design
Jeremy Molayem
 
Dewatering project pit alam 1 3
Dewatering project pit alam 1   3Dewatering project pit alam 1   3
Dewatering project pit alam 1 3
Muhammad Ichsan
 
Exfiltration Trench Design Manual
Exfiltration Trench Design ManualExfiltration Trench Design Manual
Exfiltration Trench Design Manual
Francis Mitchell
 
project ppt
project pptproject ppt
project ppt
Prithivi raj
 
Design-ppt_SAmodified.pptx
Design-ppt_SAmodified.pptxDesign-ppt_SAmodified.pptx
Design-ppt_SAmodified.pptx
ssuserca7f42
 
flow through venturimeter
flow through venturimeterflow through venturimeter
flow through venturimeter
Pulkit Shukla
 
12-runoffprocesses.pdf
12-runoffprocesses.pdf12-runoffprocesses.pdf
12-runoffprocesses.pdf
RupeshAditya
 
Hydrologic analysis and design 4th edition mc cuen solutions manual
Hydrologic analysis and design 4th edition mc cuen solutions manualHydrologic analysis and design 4th edition mc cuen solutions manual
Hydrologic analysis and design 4th edition mc cuen solutions manual
Macionis99
 
Soil mechanics
Soil mechanicsSoil mechanics
Soil mechanics
Ferit Fazliu
 
UnitHydrograph.pptx
UnitHydrograph.pptxUnitHydrograph.pptx
UnitHydrograph.pptx
ssuserdf29f0
 
Vertical Cooler 25 NB_GRAPHITE Rev_01.pdf
Vertical Cooler 25 NB_GRAPHITE Rev_01.pdfVertical Cooler 25 NB_GRAPHITE Rev_01.pdf
Vertical Cooler 25 NB_GRAPHITE Rev_01.pdf
PrashantDubal2
 

Similar to 15005_Hydrology (20)

WATERSHED CATCHMENT.pdf
WATERSHED CATCHMENT.pdfWATERSHED CATCHMENT.pdf
WATERSHED CATCHMENT.pdf
 
SARNATH-PROFILE-CAE
SARNATH-PROFILE-CAESARNATH-PROFILE-CAE
SARNATH-PROFILE-CAE
 
Presentation 7 a ce 904 Hydrology by Rabindra Ranjan Saha, PEng, Associate P...
Presentation  7 a ce 904 Hydrology by Rabindra Ranjan Saha, PEng, Associate P...Presentation  7 a ce 904 Hydrology by Rabindra Ranjan Saha, PEng, Associate P...
Presentation 7 a ce 904 Hydrology by Rabindra Ranjan Saha, PEng, Associate P...
 
M.i tank
M.i  tankM.i  tank
M.i tank
 
Post development storm EmpireEng FINAL REPORT
Post development storm EmpireEng FINAL REPORTPost development storm EmpireEng FINAL REPORT
Post development storm EmpireEng FINAL REPORT
 
Terrace effects on soil erosion processes
Terrace effects on soil erosion processesTerrace effects on soil erosion processes
Terrace effects on soil erosion processes
 
Final presentation
Final presentationFinal presentation
Final presentation
 
Process calculation condensation
Process calculation  condensationProcess calculation  condensation
Process calculation condensation
 
LinkedIn
LinkedInLinkedIn
LinkedIn
 
Water Supply and Sewerage Design
Water Supply and Sewerage DesignWater Supply and Sewerage Design
Water Supply and Sewerage Design
 
Dewatering project pit alam 1 3
Dewatering project pit alam 1   3Dewatering project pit alam 1   3
Dewatering project pit alam 1 3
 
Exfiltration Trench Design Manual
Exfiltration Trench Design ManualExfiltration Trench Design Manual
Exfiltration Trench Design Manual
 
project ppt
project pptproject ppt
project ppt
 
Design-ppt_SAmodified.pptx
Design-ppt_SAmodified.pptxDesign-ppt_SAmodified.pptx
Design-ppt_SAmodified.pptx
 
flow through venturimeter
flow through venturimeterflow through venturimeter
flow through venturimeter
 
12-runoffprocesses.pdf
12-runoffprocesses.pdf12-runoffprocesses.pdf
12-runoffprocesses.pdf
 
Hydrologic analysis and design 4th edition mc cuen solutions manual
Hydrologic analysis and design 4th edition mc cuen solutions manualHydrologic analysis and design 4th edition mc cuen solutions manual
Hydrologic analysis and design 4th edition mc cuen solutions manual
 
Soil mechanics
Soil mechanicsSoil mechanics
Soil mechanics
 
UnitHydrograph.pptx
UnitHydrograph.pptxUnitHydrograph.pptx
UnitHydrograph.pptx
 
Vertical Cooler 25 NB_GRAPHITE Rev_01.pdf
Vertical Cooler 25 NB_GRAPHITE Rev_01.pdfVertical Cooler 25 NB_GRAPHITE Rev_01.pdf
Vertical Cooler 25 NB_GRAPHITE Rev_01.pdf
 

15005_Hydrology

  • 1. TABLE OF CONTENTS SECTIONS 1.0 HYDROLOGY 1.1 TOTAL AREA 1.2 OUTSIDE TRIBUTARY AREA 1.3 SOIL TYPE 1.4 TIME OF CONCENTRATION 1.5 RAINFALL INTENSITY 1.6 RUN OFF COEFFICIENT 1.7 CALCULATION OF PEAK DISCHARGE 2.0 HYDRAULIC CALCULATIONS 2.1 50 YEAR STORM EVENT 2.2 100 YEAR STORM EVENT ATTACHMENTS VICINITY MAP ORANGE COUNTY – HYDROLOGY MANUAL SOILS MAP ORANGE COUNTY – HYDROLOGY MANUAL – FIGURE D-1 ORANGE COUNTY – HYDROLOGY MANUAL – FIGURE B-3 HYDROLOGY SITE PLAN HYDROCAD SOFTWARE OUTPUT DATA
  • 2. 1. HYDROLOGY AREAS 1.1 TOTAL AREA: Lot Area = 32,354 SF Total Drainage Areas = 17,532 SF Total Acres = 0.402 AC AREA 1 = 3,913 SF Acres = 0.089 AC AREA 2 = 13,619 SF Acres = 0.312 AC 1.2 OUTSIDE TRIBUTARY AREA: AREA 3 = 14,822 SF Acres = 0.340 AC 1.3 SOIL TYPE Soil Type C -Taken from Orange County Hydrologic Classification of Soils Map (Plate A) see Appendix 1.4 TIME OF CONCENTRATION Drainage Areas: A1 & A2 Length (L) of initial area = 179.52 FT Difference in Elevation for Initial Area (ft) = 10.82 FT Use Single Family – 1 Acre Lot Time of Concentration (Tc) (min.) = 5 min. 30 s Tc was calculated from the Orange county Hydrology Manual Figure D-1 (included)
  • 3. 1.5 RAINFALL INTENSITY Return Period 50 Years 𝐼(𝑡) = 𝑎𝑡 𝑏 𝐼(𝑡) = (13.521)(5.5)−0.566 𝐼(𝑡) = 5.15 Intensity (in/hr) Return Period 100 Years 𝐼(𝑡) = 𝑎𝑡 𝑏 𝐼(𝑡) = (15.560)(5.5)−0.573 𝐼(𝑡) = 5.86 Intensity (in/hr) Values and equations taken from the Orange County Hydrology Manual (Figure B-3) see attached. 1.6 RUN OFF COEFFICIENT C = [ai + ( (I−Fp)ap I )] Orange County Hydrology Manual Equation D-3 Where, C = Runoff Coefficient I = Rainfall Intensity (inches/Hour) Fp = Infiltration Rate for Previous Areas (Inches/Hour) ai = Ratio of Impervious Area to Total Area Ap = Ratio of Pervious Area to Total Area (ap = 1-ai) Impervious Area = 12,612 SF Total Area = 17,532 SF ai = 0.72 ap = 0.28 Fp = 0.25 in/hr I (50) = 5.15 in/hr I (100) = 5.86 in/hr
  • 4. C(50) = [0.72 + ( (5.15−0.25)0.28 5.15 )] C(50) = 0.986 C(100) = [0.72 + ( (5.86−0.25)0.28 5.86 )] C(100) = 0.988 1.7 CALCULATE PEAK DISCHARGE (Q) Q=C(I)(A) C (Run Off Coefficient) 0.986 I (Rainfall Intensity in/hr A1) 5.15 CFS 0.46 CFS 1.600831 I (Rainfall Intensity in/hr A2) 5.15 GPM 206.4 GPM 718.5 A1 (Area of Section ft^2) 3913 Q(tot)= 2.06 CFS A2 (Area of Section ft^2) 13619 C (Run Off Coefficient) 0.988 I (Rainfall Intensity in/hr A1) 5.86 CFS 0.52 CFS 1.825223 I (Rainfall Intensity in/hr A2) 5.86 GPM 235.4 GPM 819.2 A1 (Area of Section ft^2) 3913 Q(tot)= 2.35 CFS A2 (Area of Section ft^2) 13619 50 Years Area 2 100 Years Inputs Outputs (Flow Q) Area 1 Area 2 Inputs Area 1 Outputs (Flow Q)
  • 5. 2.0 HYDRAULIC CALCULATIONS Using the Manning’s Equation: 𝑉 = 𝑙 𝑛 ∗ 𝑅 2 3 ∗ 𝑆 1 2 Where: n = Coefficient of Roughness v = Water velocity down the channel (ft/sec) = flow/Cross Sectional Area R = Hydraulic radius (ft) = cross sectional area (ft^2)/wetted perimeter (ft) S = Gradient of channel (ft/ft) 2.1 50 YEAR STORM EVENT 1’ X 1’ Rectangular Channel INPUT DATA OUTPUT DATA Flow rate 2.06 CFS Depth of Flow 0.66 ft or 7.92 in Slope (s) 0.01 FT/FT Max Velocity 3.79 FPS Manning’s n 0.017 (unfinished PCC) Max Output Flow 2.39 CFS Shape Channel 1’ Wide Capacity 4.2 CFS Depth 1 FT Percent full 66% See Attached HydroCAD Output Data Depth of Channel > Depth of Flow 12 in > 7.92 in  OK Design is for two 4” PVC lines Calculations are for two 4” PVC line therefore flow is input as half from maximum flow from channel INPUT DATA OUTPUT DATA Flow rate 1.03 CFS Depth of Flow 0.17 FT or 2.04 IN Slope (s) 0.67 FT/FT Max Velocity 23.32 FPS Manning’s n 0.010 Max Output Flow 1.03 CFS Shape 4” Dia PVC Capacity 2.03 CFS Depth 4 IN Percent full 51% See Attached HydroCAD Output Data Depth of Pipe > Depth of Flow 4 in > 2.04 in  OK
  • 6. 2.2 100 YEAR STORM EVENT 1’ X 1’ Rectangular Channel INPUT DATA OUTPUT DATA Flow rate 2.35CFS Depth of Flow 0.74 FT or 8.88 IN Slope (s) 0.01 ft/ft Max Velocity 3.90 FPS Manning’s n 0.017 Max Output Flow 2.18 CFS Shape Channel 1’ Wide Capacity 4.2 CFS Depth 1 FT Percent full 74% See Attached HydroCAD Output Data Depth of Channel > Depth of Flow 12 in > 8.88 in  OK Design is for two 4” PVC lines Calculations are for two 4” PVC line therefore flow is input as half from maximum flow from channel INPUT DATA OUTPUT DATA Flow rate 1.18 CFS Depth of Flow 0.18 FT or 2.16 IN Slope (s) 0.67 FT/FT Max Velocity 24.1 FPS Manning’s n 0.010 Max Output Flow 1.18 CFS Shape 4” Dia PVC Capacity 2.03 CFS Depth 4 IN Percent full 54% See Attached HydroCAD Output Data Depth of Pipe > Depth of Flow 12 in > 2.06 in  OK