SlideShare a Scribd company logo
IN THE UNITED STATES DISTRICT COURT 
FOR THE NORTHERN DISTRICT OF ILLINOIS 
EASTERN DIVISION 
IXMATION, INC., ) 
) 
Plaintiff, ) 
v. ) Case No. 14-cv-6993 
) 
SWITCH BULB COMPANY, INC., a/k/a ) 
SWITCH LIGHTING CO. and WELLS ) 
FARGO BANK, N.A., ) Judge John Z. Lee 
) 
) 
Defendants. ) 
MEMORANDUM OPINION AND ORDER 
Plaintiff Ixmation, Inc., (“Ixmation”) and Defendant Switch Bulb Company, Inc. (“Switch”) entered into an agreement whereby Ixmation agreed to manufacture a custom automated system for Switch. To secure payment, Switch obtained a Letter of Credit, which had an expiration date of October 1, 2014, from Wells Fargo Bank, N.A., issued for Ixmation’s benefit. However, before Ixmation could complete its work and collect fully on the Letter of Credit, Switch told Ixmation to halt work on the project and later executed an assignment for the benefit of creditors under California law. In response, Ixmation commenced an arbitration proceeding against Switch in April of this year and, worried that the Letter of Credit would expire, filed this suit and a motion for temporary restraining order in September, requesting that the Court maintain the status quo until the arbitration is concluded. 
Granting Ixmation’s motion, the Court previously issued a temporary restraining order placing an equitable lien on the Letter of Credit to maintain the status quo pending the arbitration. The Letter of Credit has since expired by its terms, but the equitable lien was extended over the funds that Switch previously had deposited with Wells Fargo to secure the 1 
Case: 1:14-cv-06993 Document #: 60 Filed: 10/23/14 Page 1 of 17 PageID #:813
Letter of Credit. Ixmation now moves for issuance of a preliminary injunction to maintain the equitable lien over the funds. Switch opposes Ixmation’s motion, arguing that this Court lacks authority to enter the injunctive relief Ixmation requests, that Ixmation has not met the requirements for an equitable lien, and that Ixmation has not met its burden to obtain preliminary injunctive relief. 
1 For the reasons discussed below, the Court concludes that Ixmation has failed to meet its burden to obtain a preliminary injunction, and its motion is denied. 
I. Factual and Procedural Background 
A. The Proposal, Production, and Breach 
Ixmation builds and sells production machinery and automated systems. Switch designs, manufactures, and sells various LED lighting solutions. Switch and Ixmation entered into a contract (the “Proposal”) on July 12, 2013, for the manufacture of a custom automation system. See Am. Compl. ¶ 4; id. Ex. A. By the terms of the Proposal, Ixmation agreed to design and build the custom automation system for Switch in return for $3,908,000.00, and Switch issued a purchase order for the automation system. See id. ¶ 6; id. Ex. B. The Proposal required Switch to pay Ixmation in increments contingent on Ixmation’s successful completion of certain milestones. See id. ¶ 8; id. Ex. A. The Proposal’s Appendix, documenting Ixmation’s terms and conditions of sale, contained an arbitration provision requiring the parties to arbitrate, inter alia, breach of contract claims. Id. Ex. A, Appendix I, ¶ 19. The arbitration provision also required that any disputes regarding the Proposal would be governed by Illinois law. Id. 
1 Switch concurrently moves to dismiss this lawsuit or in the alternative moves to stay the case and compel arbitration. See generally Def.’s Mot. Dismiss, or in Alt. Compel Arb. The Court has set a status hearing for November 3, 2014, at which time it will take up Switch’s motion. Additionally, two clean technology venture capital investment firms which are part of Switch’s assignment for benefit of creditors in California have moved to intervene in the proceedings here. See generally Intervenors’ Mot. Interv. Similarly, the Court will continue this motion and defer its consideration until the November 3, 2014 hearing. 
2 
Case: 1:14-cv-06993 Document #: 60 Filed: 10/23/14 Page 2 of 17 PageID #:814
Throughout the months following the Proposal and purchase order, the parties agreed to several change orders. Of particular relevance is a November 2013 change order that resulted in a credit of $573,670.00 to Switch and delayed the project delivery schedule by seven to nine weeks. See Pl’s Mot. Prel. Inj., Curtis Aff. ¶ 7. This delay was, at least partly, due to Switch unilaterally putting the project on hold for several weeks. Id. Switch later acknowledged in a February 28, 2014, email that the November 2013 change order’s revised delivery schedule meant Factory Assurance Testing (“FAT”), a production milestone stage, would not occur until the week of March 31, 2014. Id. ¶ 8; see also id. Ex. 2. In this email, Switch documented a detailed schedule for finishing production of the machine from the FAT stage of production through shipping and delivery in late April. See id. Ex. 2. 
In August 2013, Ixmation requested a Letter of Credit from Switch to secure payment for the custom automation system. On August 5, 2013, Wells Fargo issued the Letter of Credit in the amount of $3,079,200.00. See Am. Compl. Ex. D. The Letter of Credit had an expiration date of September 1, 2014. See id. On November 25, 2013, at the request of Ixmation, the amount in the Letter of Credit was reduced to $2,858,194.50, and the expiration date was extended to October 1, 2014. See id. Ex. E. As Ixmation made progress on the manufacture of the custom automation system, it drew on the Letter of Credit. The first draw occurred in October 2013 and the second in January 2014, with the draws totaling $1,836,097.80. See id. ¶ 11. The first draw was authorized after Ixmation completed its mechanical design review stage of production. See Pl.’s Mot. Prelim. Inj., Ludwig Aff. ¶ 7. The second draw was authorized after Ixmation completed a sub-system debug of the custom automation system. See id. ¶ 8. Consequently, $1,022,096.70 remained in the Letter of Credit. See Am. Compl. ¶ 11. 
3 
Case: 1:14-cv-06993 Document #: 60 Filed: 10/23/14 Page 3 of 17 PageID #:815
Ixmation would make no further draws. By early spring, a dispute between the parties arose. In March 2014, Ixmation was working on the FAT stage of production. During this time, Ixmation became concerned with Switch’s actions and communications. On March 18, 2014, Ixmation’s Senior Account Manager Randy Curtis met with Switch’s Project Manager Myron Moreno in San Jose, California, to continue discussions of FAT. See Pl.’s Mot. Prel. Inj., Randy Curtis Aff. ¶ 9. During this meeting, Moreno told Curtis that VantagePoint Capital, a venture capital firm that funded Switch, had laid off more than half of Switch’s employees, including employees who were working on the custom automation system and necessary to complete the FAT stage of production. See id. Despite this, Moreno indicated he would be coming to Ixmation’s place of business in Roselle, Illinois, at the end of March for FAT. See id. The following day, however, on March 19, 2014, Moreno told Curtis that Switch was “trending towards liquidation” and would not be able to provide parts and personnel necessary for Ixmation to complete FAT. See id. ¶ 10. These representations were confirmed on March 20, 2014, in an email from Moreno to Curtis. See id. ¶ 11; see also Am. Compl. Ex. G. 
The parties continued communications through the end of March 2014. See Pl.’s Mot. Prel. Inj., Curtis Aff. ¶¶ 12–13. For its part, Switch asserts that it was Ixmation that unilaterally ceased work on the custom automation system before reaching additional production milestones that were necessary to draw additional funds from the Letter of Credit. See Def.’s Mem. Opp. 2. An exchange of letters in late March captured the state of the parties’ business relationship. By letter on March 27, 2014, Switch’s Executive Vice President Ronald Rudolph notified Ixmation that on March 24, 2014, Switch had requested that Ixmation stop work on the custom automation system and that further financial assurances from Switch were not forthcoming because “[I]xmation insisted from the beginning that the full cost of the [custom automation system] be 4 
Case: 1:14-cv-06993 Document #: 60 Filed: 10/23/14 Page 4 of 17 PageID #:816
deposited into a bank under letter of credit with funds to be released upon [I]xmation’s appropriate performance.” See Pl.’s Mot. Prelim. Inj., Ludwig Aff. ¶ 11; id. Ex. 1. Ixmation’s President Mick Macsek promptly responded to Switch on March 28, 2014, writing that it appeared the parties were in a contractual dispute and quoting a provision of the Proposal requiring the parties to put forth best efforts to resolve disputes. See id.; id. Ex. 2. Macsek’s letter served as Ixmation’s formal request for a meeting of the companies’ senior executives. See id. Ex. 2. 
Ixmation, now cognizant of an impending breakdown in the parties’ relationship and Switch’s apparently precarious financial state, sent four senior executives to attend the meeting on April 3, 2014, in San Jose, California. Pl.’s Mot. Prelim. Inj., Ludwig Aff. ¶ 12. According to Ixmation, this meeting proved fruitless; Switch provided no answers to questions concerning the reason for Switch’s suspension of operations and apparent skeleton crew, and no satisfactory plan on how Switch intended to supply the parts and personnel necessary for Ixmation to perform FAT. See Pl.’s Mot. Prel. Inj., Curtis Aff. ¶¶ 12, 14. 
B. Arbitration and Assignment for the Benefit of Creditors 
Faced with its rapidly deteriorating business relationship with Switch, Ixmation filed for American Arbitration Association (“AAA”) arbitration on April 16, 2014. See Amend. Compl. ¶ 19. The timeline of arbitration thereafter becomes hazy. Each party insists that, after the April 16, 2014, filing by Ixmation, it was the other party that delayed further progress in the arbitration. Ixmation represented to the Court at the October 20, 2014 hearing that, after it had filed for AAA arbitration, it did not move to expedite the process or take any other actions to advance the arbitration in the hope that Switch would eventually agree to resolve their dispute. 
5 
Case: 1:14-cv-06993 Document #: 60 Filed: 10/23/14 Page 5 of 17 PageID #:817
Switch insists that is was Ixmation who delayed the arbitration. See generally Def.’s Second Supp. Mem. Opp’n. Pl.’s Mot. TRO 10–11. 
Regardless, the next significant action in the arbitration proceedings was an email sent to Ixmation by Kelly Turner of the AAA on May 6, 2014. In the email, Turner informed Ixmation that it had to pay an administration fee by July 17, 2014, before the AAA would appoint an arbitrator so that the arbitration could proceed. See Pl.’s Supp. Memo. Ex. 2. The AAA required this “proceed fee” because Ixmation had chosen to file its request for arbitration under a flexible fee schedule. See id. The email notice also imposed a deadline of May 20, 2014, for Switch to file an answer, counterclaim, or objection to Ixmation’s request to hold the arbitration in Chicago. See id. 
A little less than one month after this email was sent, on May 30, 2014, Switch instituted an assignment for the benefit of creditors under California law.2 See id. Ex. 4. While Switch apparently informed the AAA of this assignment by email on June 30, 2014, see id., Ixmation did not receive notice of Switch’s assignment until the AAA sent an email to Ixmation on July 9, 2014. See id. Ex. 5. By this point, Ixmation still had not paid the required proceed fee to begin arbitration. The next week, on July 15, 2014, Ixmation finally paid the fee, requested that the arbitration proceed without Switch, and for the first time requested expedited briefing. See id. Ex. 6. 
Thereafter a series of email communications occurred between Switch, Kelly Turner, and Ixmation. See generally id. Ex. 7. Turner contacted the parties, attempting to schedule an administrative conference call for the final weeks of July. See id. 7/16/14 Email from Kelly 
2 An assignment for the benefit of creditors is a state-level equivalent to a bankruptcy proceeding. See Pl.’s Supp. Mem. Ex. 4 (6/30/14 email from Switch to the AAA) (“An [assignment for the benefit of creditors] is a state level insolvency proceeding undertaken under state law, in this case California[.]”). 
6 
Case: 1:14-cv-06993 Document #: 60 Filed: 10/23/14 Page 6 of 17 PageID #:818
Turner to Switch and Ixmation. Ixmation replied on July 16, 2014, asking to schedule the administrative conference call for July 21 or July 22. See id. 7/16/14 Email from Ixmation to Kelly Turner. Turner then suggested a date of July 22, 2014. See id. 7/16/14 Email from Kelly Turner to Switch and Ixmation. Switch responded, indicating that week would not work for it. See id. 7/16/14 Email from Switch to Kelly Turner and Ixmation. The next day, Switch proposed a July 28 or July 29 date. See id. 7/17/14 Email from Switch to Kelly Turner and Ixmation. Thereafter Switch noted that it still was retaining counsel, that it needed to find counsel that could appear in Illinois, and that this process would take two to three weeks. See id. 7/29/14 Email from Switch to Kelly Turner and Ixmation. In an attempt to balance Switch’s need to find appropriate counsel with the need to avoid undue delay, Turner scheduled the conference call for August 15, 2014. See id. 7/29/14 email from Kelly Turner to Switch and Ixmation. 
After Switch retained counsel, it determined it would contest the Chicago locale requested by Ixmation. See id. Ex. 9. The AAA set a deadline of August 29, 2014, for both sides to submit briefing supporting its requested choice of locale. See id. Ex. 9. August 29 also served as the deadline by which Switch was required to indicate whether it woiuld agree to a single arbitrator instead of the three-arbitrator panel. See id. On September 3, 2104, the AAA decided in favor of Ixmation and determined that the arbitration would take place in Chicago. See id. Ex. 11. The AAA set a deadline of September 17, 2014, for the parties to submit a list of potential arbitrators. See id. On October 3, 2014, the AAA appointed Randall Rapp as an arbitrator. See Def.’s Mot. Dismiss or Alt. Compel., Ex. A. On October 6, 2014, Switch indicated that it would prefer a panel of three arbitrators. See id. Ex. B. Switch’s request is the 7 
Case: 1:14-cv-06993 Document #: 60 Filed: 10/23/14 Page 7 of 17 PageID #:819
last activity reflected in the record. From the record, it appears that Ixmation never raised any concern about the expiration of the Letter of Credit with the AAA. 
C. Procedural History of This Action 
Ixmation filed a complaint and moved for a temporary restraining order (“TRO”) in the Circuit Court for Cook County, Illinois, on September 5, 2014. See Def.’s Notice Remov. ¶ 1; id. Ex. A. Switch removed the case to this Court based on diversity jurisdiction on September 9, 2014. See Def.’s Notice Remov. ¶ 2. Ixmation refiled its request for a TRO on September 10, 2014. See Pl.’s Mot. TRO. This Court held a hearing on Ixmation’s motion for a TRO on September 17, 2014. The Court set a briefing schedule, allowing Wells Fargo to file a response to Ixmation’s motion for a TRO and allowing Switch to file supplemental briefing opposing Ixmation’s motion on state law grounds.3 See 9/17/14 Min. Entry. The Court also encouraged the parties to explore settlement. See id. 
The Court held another hearing on September 23, 2014. The Court noted that Switch’s supplemental briefing did not address the state law issues the Court requested, but rather reargued points Switch had already raised in its original response brief. See 9/23/14 Min. Entry. Rather than strike Switch’s brief, the Court granted Ixmation a one-day extension to file a brief replying to both Switch and Wells Fargo’s briefing. See id. The Court reset the hearing on Ixmation’s motion for TRO, originally set for September 24, 2014, to September 26, 2014. See id. 
3 The Court also denied an earlier motion to dismiss filed by Switch arguing principally that the arbitration provision in the parties’ contracted precluded this Court from intervening in the parties’ dispute. The Court found Switch’s argument unpersuasive in light of Seventh Circuit precedent holding that a court can enter injunctive relief preserving the status quo and the meaningfulness of arbitration. Merrill Lynch, Pierce, Fenner & Smith, Inc. v. Salvano, 999 F.2d 211, 215 (7th Cir. 1993). 
8 
Case: 1:14-cv-06993 Document #: 60 Filed: 10/23/14 Page 8 of 17 PageID #:820
On September 26, 2014, the Court held a hearing on Ixmation’s motion for TRO. The Court first granted Ixmation’s request to submit an amended complaint. See 9/26/14 Min. Entry. The Court then directed the parties to file supplemental briefing addressing the procedural history before the AAA. See id. The Court continued the hearing on Ixmation’s motion for TRO to September 30, 2014, at 12:30 pm. See id. 
On September 30, 2014, the Court reconvened for a hearing on Ixmation’s motion for TRO. First, the Court addressed whether Wells Fargo should remain in the case. Ixmation asserted no claims against Wells Fargo and represented on the record at the September 26, 2014, hearing that it had no claims against Wells Fargo. See generally 9/30/14 Hr’g Tr. at 3, lns. 10– 13. Without a claim pending against Wells Fargo, the Court dismissed Wells Fargo from the lawsuit and denied Ixmation’s request to compel Wells Fargo to extend the Letter of Credit.4 See 9/30/14 Hr’g Tr. at 3–4, lns. 10–25, 1–18. 
After dismissing Wells Fargo, the Court turned to Ixmation’s request for a TRO in the form an equitable lien.5 On the record before it, the Court found that Ixmation met the 
4 Specifically, the Court found that Ixmation had not pleaded claims against Wells Fargo and admitted that it had no claims against Wells Fargo. The Court noted that under Federal Rule of Civil Procedure 65(d)(2), an injunctive order can only bind the parties, the parties’ officers, agents, servants, employees, and attorneys, and other persons in active concert or participation. See Fed. R. Civ. P. 65(d)(2). A person is in “active concert or participation” if they “aid and abet” the enjoined party or if they are in “privity” with the joined party. Blockowicz v. Williams, 630 F.3d 563, 567 (7th Cir. 2010). Ixmation bore the burden of proving that any third party it sought injunctive relief as to was within the scope of the injunction it sought to enter. Id. Ixmation had not met that burden because it failed to advance evidence that Wells Fargo acted in concert with Switch, was an agent of Switch, or was in privity with Switch. Furthermore, while the Court noted it could issue an injunction against a nonparty in order to preserve its ability to render judgment, see Herrlein v. Kanakis, 526 F.2d 252, 255 (7th Cir. 1975), the Court, mindful of its independent duty to ensure injunctions are appropriate in scope, see Chicago Board of Education v. Substance, Inc., 354 F.3d 624, 631–32 (7th Cir. 2003), declined to enter an injunction against Wells Fargo as a nonparty in this case. 
5 Switch mischaracterizes the equitable lien imposed by the Court as a sua sponte form of relief not requested by Ixmation. Ixmation, however, proposed the equitable lien in its moving papers. See Pl.’s Supp. Mem. 9 (noting that preserving the status quo would be by equitable lien if a draw were ordered on the Letter of Credit and the proceeds held in escrow or trust). 
9 
Case: 1:14-cv-06993 Document #: 60 Filed: 10/23/14 Page 9 of 17 PageID #:821
requirements for an emergency TRO and imposed an equitable lien on the Letter of Credit. The Court additionally held that, once the Letter of Credit expired by its own terms, the equitable lien would extend to that portion of the funds that Switch previously had deposited with Wells Fargo as collateral for the Letter of Credit sufficient to cover the balance that remained under the Letter of Credit. See 9/30/14 Hr’g Tr. at 9. Any additional amounts would be released to Switch. See id. The Court then scheduled a briefing schedule for Ixmation’s motion for preliminary injunction and set a hearing on the motion for October 14, 2014 at 4:30 p.m. See 9/30/14 Min. Entry. The Court also required Ixmation to post a bond in the amount of $10,000.00. See id. 
Subsequently, on October 7, 2014, Switch requested an emergency extension of time to file its response to Ixmation’s motion for preliminary injunction. See Def.’s Mot. Ext. Time. The Court held a hearing on October 8, 2014, and granted the motion based upon Switch’s agreement to be bound by the TRO until October 20, 2014. See 10/8/14 Min. Entry.6 
Switch subsequently filed a motion to dismiss or in the alternative compel arbitration and also requested leave to file an over-length response brief under Local Rule 7.1 to Ixmation’s motion for preliminary injunction. The Court granted Switch’s request and gave Ixmation two additional days to submit its reply brief. See 10/14/14 Min. Entry. The Court continued Switch’s motion and set it for hearing concurrent with Ixmation’s motion for preliminary injunction. See id. 
On October 20, 2014, the Court heard argument on Ixmation’s request for preliminary relief. The Court also heard brief argument from two venture capital firms, VantagePoint 
6 At the parties’ request, the Court also held a telephone conference on October 9, 2014. During the telephone conference, the parties represented that Wells Fargo did not wish to maintain the funds constituting the collateral for the Letter of Credit. See 10/9/14 Min. Entry. Switch proposed that the funds be placed in a separate account in another financial institution and agreed that the transfer would not alter the effect of the equitable lien over those funds. See id. The Court approved this request. See id. 
10 
Case: 1:14-cv-06993 Document #: 60 Filed: 10/23/14 Page 10 of 17 PageID #:822
Cleantech Partners II, L.P., VantagePoint Venture Partners 2006 (Q), L.P. on their motion to intervene filed on October 18, 2014. After argument, the Court took the matter under advisement. That same day, the Court denied Ixmation’s motion. See 10/20/14 Min. Entry. This Memorandum Opinion and Order sets forth the reasoning for the Court’s denial. 
II. The Court’s Authority to Issue Injunctive Relief 
As an initial matter, Switch contests the Court’s authority to grant the equitable relief previously granted to Ixmation. Specifically, Switch cites to Grupo Mexicano de Desarrollo S.A. v. Alliance Bond Fund, Inc., 527 U.S. 308 (1999) for the proposition that this Court cannot impose an injunction hindering Switch’s ability to transfer or otherwise use its assets as it sees fits. In Switch’s view, such an injunction would be nothing more than a prohibited prejudgment attachment. But Grupo Mexicano is distinguishable in two material respects. First, Grupo Mexicano involved a breach of contract action seeking only money damages. See Grupo Mexicano, 527 U.S. at 310 (focusing the question presented in the context of “an action for money damages”); see also Oak Leaf Outdoors, Inc. v. Double Dragon Int’l, Inc., 812 F. Supp. 2d 944, 946 (C.D. Ill. 2011) (noting that Grupo Mexicano determined that in a suit for money damages on a contractual breach theory such injunctive relief freezing assets pre-judgment was “historically unavailable from a court of equity”). Here, although Ixmation is seeking money damages in arbitration, it is seeking only equitable relief from this Court to preserve the status quo so that any judgment it may receive from the arbitration panel would be meaningful. See Salvano, 999 F.2d at 215 (district court has authority “to maintain the status quo without prejudice to the merits of any of the parties’ claims or defenses until an arbitration panel [can] consider the issues presented”). 
11 
Case: 1:14-cv-06993 Document #: 60 Filed: 10/23/14 Page 11 of 17 PageID #:823
Furthermore, even after Grupo Mexicano, courts have recognized a district court’s authority to enter equitable relief preserving assets where there is a “nexus between the assets sought to be frozen through an interim order and the ultimate relief requested in the lawsuit.” U.S. ex rel. Rahman v. Oncology Associates, 198 F.3d 489, 496–97 (4th Cir. 1999). Here, a nexus plainly exists between the Letter of Credit, which Switch had arranged with Wells Fargo for Ixmation’s benefit to secure payment under the agreement and Ixmation’s claim. Indeed, Switch itself admitted in its email communications that the Letter of Credit served to cover exactly the production of the custom automation system by Ixmation that is the subject of Ixmation’s claim. Accordingly, the reasoning in Grupo Mexicano did not apply in this case while the Letter of Credit was in effect, and the Court had the authority to preserve the status quo by imposing an equitable lien over it and the funds that could be drawn from it.7 
That said, whether the equitable lien would extend to the funds that Switch had deposited with Wells Fargo as collateral for the Letter of Credit upon the expiration of the Letter of Credit itself presents an interesting, and previously undecided, question of law.8 But the 
7 Contrary to Switch’s contention, Grupo Mexicano also does not “overrule” American Hospital Supply Corp. v. Hospital Products Ltd., 780 F.2d 589 (7th Cir. 1986). As Oak Leaf observes, the Seventh Circuit’s holding in American Hospital Supply Corp. did not consider the key issue in Grupo Mexicano, that is, “whether a district court has the authority to enter a preliminary injunction when the requesting party seeks only money damages for breach of contract.” Oak Leaf Outdoors, 812 F. Supp. 2d at 948 (emphasis added). Moreover, this Court relied on American Hospital Supply Corp. for the proposition that a plaintiff faced with an imminently insolvent defendant suffers irreparable harm. The Court did not invoke American Hospital Supply Corp., as Switch appears to suggest, for the general proposition that an equitable lien is available to Ixmation. Furthermore, it is well-established that a letter of credit and its associated funds does not become part of the bankruptcy estate of the debtor. See In re Duplitronics, Inc., 183 B.R. 1010, 1015 (Bankr. N.D. Ill. 1995). 
8 Under Illinois law an equitable lien requires “(1) a debt, duty or obligation owing by one person to another, and (2) a res to which that obligation fastens.” Jacobsen v. Conlon, 302 N.E.2d 471, 473 (Ill. App. Ct. 1973). In the proper circumstances, “[i]f the res to which the lien attaches is converted into money, the Court in a proper case will treat the money as substituted for the property.” In re Brass Kettle Rest., Inc., 790 F.2d 574, 575 (7th Cir. 1986) (quoting Marshall Savings & Loan Ass. v. Chi. Nat. Bank, 206 N.E.2d 117, 120 (Ill. App. Ct. 1965)). 
12 
Case: 1:14-cv-06993 Document #: 60 Filed: 10/23/14 Page 12 of 17 PageID #:824
Court need not address this question here, because it finds, after consideration of the parties’ papers, that Ixmation has failed to demonstration that a preliminary injunction is appropriate. 
III. Ixmation’s Request for Preliminary Injunction 
A. Legal Standard 
Ixmation moves for a preliminary injunction maintaining the TRO. “[A] preliminary injunction is an exercise of a very far-reaching power, never to be indulged in except in a case clearly demanding it.” Girl Scouts of Manitou Council, Inc. v. Girl Scouts of the USA, Inc., 549 F.3d 1079, 1085 (7th Cir. 2008) (internal citations and quotations omitted). The moving party must make a clear showing that it is entitled to the relief it seeks. Goodman v. Ill. Dep’t of Fin. & Prof’l Regulation, 430 F.3d 432, 437 (7th Cir. 2005). A party seeking a preliminary injunction must show that (1) it is reasonably likely to succeed on the merits; (2) no adequate remedy at law exists; (3) it will suffer irreparable harm which, absent injunctive relief, outweighs the irreparable harm the respondent will suffer if the injunction is granted; and (4) the injunction will not harm the public interest. Joelner v. Vill. of Wash. Park, Ill., 378 F.3d 613, 619 (7th Cir. 2004). Analysis of these elements occurs in two phases: a threshold phase and a balancing phase. See Girl Scouts of Manitou Council, 549 F.3d at 1085–86. 
“To survive the threshold phase, a party seeking a preliminary injunction must satisfy three requirements.” Id. at 1086. First, the party must show that it will suffer irreparable harm without the injunction. Second, the party must demonstrate that traditional legal remedies would be inadequate. Third, the party must establish that its claim has some likelihood of succeeding on the merits. If the party cannot make a showing as to each of these threshold requirements, the preliminary injunction must be denied. Id. If, however, the party meets this initial threshold, the Court will proceed to the balancing phase of the analysis. Id. 
13 
Case: 1:14-cv-06993 Document #: 60 Filed: 10/23/14 Page 13 of 17 PageID #:825
In the balancing phase, the party seeking the injunction must demonstrate that its harm in the absence of such relief outweighs any harm that may be suffered by the non-moving party if the injunction is granted. Id. In making this determination, the Court employs a sliding scale approach: “[t]he more likely the plaintiff is to win, the less heavily need the balance of harms weigh in his favor, the less likely he is to win, the more need it weigh in his favor.” Id. (quoting Roland Mach. Co. v. Dresser Indus., Inc., 749 F.2d 380, 389 (7th Cir. 1984)). Additionally, where appropriate, this balancing process “should . . . encompass any effects that granting or denying the preliminary injunction would have on nonparties (something courts have termed the “public interest”).” Id. (quoting Ty, Inc. v. Jones Grp., Inc., 237 F.3d 891, 895 (7th Cir. 2001)). Taking into account all of these considerations, the Court must exercise its discretion “to arrive at a decision based on a subjective evaluation of the import of the various factors and a personal, intuitive sense about the nature of the case.” Id. (internal citations and quotations omitted). 
B. Ixmation Has Failed to Show Irreparable Harm 
On a fuller record and with more developed argument, the Court finds that Ixmation’s unwarranted delay in seeking this injunction belies its contention of irreparable harm and defeats its motion for preliminary injunction. Delay is a factor in assessing the existence of irreparable harm, Ideal Industries, Inc. v. Gardner Bender, Inc., 612 F.2d 1018, 1025 (7th Cir. 1979), and unexcused delay on the part of parties seeking extraordinary injunctive relief is grounds for denial of a motion “because such delay implies a lack of urgency and irreparable harm.” Newdow v. Bush, 355 F. Supp. 2d 265, 292 (D.D.C. 2005). “[T]he likelihood of irreparable harm takes into account how urgent the need for equitable relief really is.” Michigan v. U.S. Army Corps of Engineers, 667 F.3d 765, 788 (7th Cir. 2011). This is particularly true where the party seeking injunctive relief has “knowledge of the pending nature of the alleged irreparable harm.” 
14 
Case: 1:14-cv-06993 Document #: 60 Filed: 10/23/14 Page 14 of 17 PageID #:826
Open Top Sightseeing USA v. Mr. Sightseeing, LLC, Case No. CV 14-820 (BAH), --- F. Supp. 2d ----, 2014 WL 2758603, at *3 (D.D.C. June 18, 2014) (citing Fund for Animals v. Frizzell, 530 F.2d 982, 987 (D.C. Cir. 1975)). Numerous courts in this district have refused to issue preliminary injunctions on this ground. See, e.g., Johnson Publ’g, Co., Inc. v. Willitts Designs Int’l, Inc., No. 98 C 2653, 1998 WL 341618, at *8 (N.D.Ill. June 22, 1998) (presumption of irreparable harm weak where the plaintiff waited four months to request injunctive relief); Stokley–Van Camp, Inc. v. Coca–Cola Co., No. 86 C 6159, 1987 WL 6300, at *3 (N.D.Ill. Jan. 30, 1987) (denying “extraordinary remedy” of preliminary injunction despite presumption of irreparable harm because plaintiff waited three months before filing action and the defendant was spending substantial amounts to market its product). 
Here, although Ixmation initiated the arbitration on April 16, 2014, it did not pay the proceed fee required by AAA until almost three months later, on July 15, 2014. At a minimum, Ixmation received notice of the required proceed fee on May 6, 2014. And although Ixmation did not know that Switch had executed an assignment for the benefit of creditors until early July, Ixmation became aware of Switch’s precarious financial state in March 2014. Perhaps more importantly, Ixmation knew in no uncertain terms that the Letter of Credit would expire on October 1, 2014. Yet, Ixmation did not seek to expedite the AAA proceedings until July 16, 2014. And, when it did, it only did so in a one-line request that the AAA “select an arbiter and hearing date on an expedited schedule.” See Pl.’s Supp. Mem., Ex. 6. After this request, Ixmation never made another request to expedite the appointment of the arbitrators or otherwise hasten the proceeding, and it never raised any concern about the expiration of the Letter of Credit with the AAA. 
15 
Case: 1:14-cv-06993 Document #: 60 Filed: 10/23/14 Page 15 of 17 PageID #:827
Instead, Ixmation waited until September 5, 2014, to file a request in state court seeking a TRO to preserve that expiration of the Letter of Credit. This was less than one month before the expiration date and nearly four and a half months after Ixmation first filed for arbitration. When asked to explain the delay, Ixmation’s counsel stated during the preliminary injunction hearing that Ixmation had waited until September in the hope that the parties would be able to come to an amicable resolution rather than proceeding with litigation. But, this strategy was at its own risk and its peril. “Although delay may not preclude the grant of ultimate relief, it may preclude preliminary relief because it undermines the sense of urgency that typically accompanies a motion for preliminary injunction.” Silber v. Barbara’s Bakery, Inc., 950 F. Supp. 2d 432, 441 (E.D.N.Y. 2013) (finding five-month delay in moving for preliminary injunction defeated a finding of irreparable harm). 
To be clear, the Court’s conclusion that Ixmation’s delay precludes preliminary relief does not absolve Switch of blame. On the record before the Court, it appears Switch may have been less than forthright with Ixmation regarding its financial condition in March 2014, failed to communicate its assignment for the benefit of creditors to Ixmation in a timely fashion, and used the procedural devices available to it to prolong the arbitration proceedings, such as challenging the location of the arbitration and insisting upon the appointment of three arbitrators. But, Ixmation should have done its part to expedite the arbitration in light of the Letter of Credit’s October 1 expiration date. It did not do so. “It is horn-book law . . . that a person who seeks the protection of equity must do equity.” In re Thomas, 204 F.2d 788, 794 (7th Cir. 1953). The Court finds that Ixmation’s failure to seek an expeditious resolution of the arbitration proceeding and delay in seeking relief from the Court, despites its full knowledge of the pending October 1 16 
Case: 1:14-cv-06993 Document #: 60 Filed: 10/23/14 Page 16 of 17 PageID #:828
deadline and reason to doubt Switch’s continuing financial health, fatally undermines its ability to demonstrate the existence of irreparable harm. For this reason, Ixmation’s motion is denied. 
IV. Conclusion 
For the reasons stated herein, Ixmation’s Motion for Preliminary Injunction [36] is denied. 
ENTERED: 10/23/14 ________________________ 
Hon. John Z. Lee 
United States District Judge 
17 
Case: 1:14-cv-06993 Document #: 60 Filed: 10/23/14 Page 17 of 17 PageID #:829

More Related Content

What's hot

media report analysis (final)
media report analysis (final)media report analysis (final)
media report analysis (final)John McMahon
 
The Law of Penalties - ANZ v Andrews and beyond
The Law of Penalties - ANZ v Andrews and beyond The Law of Penalties - ANZ v Andrews and beyond
The Law of Penalties - ANZ v Andrews and beyond
Laina Chan
 
UNL1622 – CONTRACT LAW II (REMOTENESS)
UNL1622 – CONTRACT LAW II (REMOTENESS)UNL1622 – CONTRACT LAW II (REMOTENESS)
UNL1622 – CONTRACT LAW II (REMOTENESS)
Wei Lie Lim
 
Compare the judgements of Bhatia and Balco and Secondly what in your opinion ...
Compare the judgements of Bhatia and Balco and Secondly what in your opinion ...Compare the judgements of Bhatia and Balco and Secondly what in your opinion ...
Compare the judgements of Bhatia and Balco and Secondly what in your opinion ...Suneeta Mohapatra
 
ADR - 5TH MAY - Cpt. BHATIA (F) - 5th LECTURE
ADR - 5TH MAY - Cpt. BHATIA (F) - 5th LECTUREADR - 5TH MAY - Cpt. BHATIA (F) - 5th LECTURE
ADR - 5TH MAY - Cpt. BHATIA (F) - 5th LECTURE
cmmindia2017
 
Business laws
Business lawsBusiness laws
Business laws
Chandresh Madhyan
 
Time Bars and their enforceability in English law EPC contracts
Time Bars and their enforceability in English law EPC contractsTime Bars and their enforceability in English law EPC contracts
Time Bars and their enforceability in English law EPC contracts
Eversheds Sutherland
 
Dealing with 'fit for purpose' obligation
Dealing with 'fit for purpose' obligationDealing with 'fit for purpose' obligation
Dealing with 'fit for purpose' obligation
Venkataraghavan Ramadurai, LLM, FCIArb, FCMA, MRICS
 
Atty Contract 6 24 98
Atty Contract 6 24 98Atty Contract 6 24 98
Atty Contract 6 24 98legal6
 
Mardia chemicals case by shreya a322509022
Mardia chemicals case by shreya a322509022Mardia chemicals case by shreya a322509022
Mardia chemicals case by shreya a322509022Shreya Ganguly
 
Conduct of arbitral proceeding vaibhav goyal
Conduct of arbitral proceeding vaibhav goyalConduct of arbitral proceeding vaibhav goyal
Conduct of arbitral proceeding vaibhav goyal
Vaibhav Goyal
 
Powerpoint for Legalwise Annual Property Seminar March 2016
Powerpoint for Legalwise Annual Property Seminar March 2016Powerpoint for Legalwise Annual Property Seminar March 2016
Powerpoint for Legalwise Annual Property Seminar March 2016
Laina Chan
 
Dispute resolution uae_venkat
Dispute resolution uae_venkatDispute resolution uae_venkat
Construction Law - Remedies for Breach of Contract
Construction Law - Remedies for Breach of ContractConstruction Law - Remedies for Breach of Contract
Construction Law - Remedies for Breach of Contract
Pang Khai Shuen
 
Legal Solutions In A Tough Economy
Legal Solutions In A Tough EconomyLegal Solutions In A Tough Economy
Legal Solutions In A Tough Economylegaladvice
 
J.S. Daniel paper on Arbitrated cases in lebanon and decisions of arbitrators
J.S. Daniel paper on Arbitrated cases in lebanon and decisions of arbitratorsJ.S. Daniel paper on Arbitrated cases in lebanon and decisions of arbitrators
J.S. Daniel paper on Arbitrated cases in lebanon and decisions of arbitratorsJ.S. Daniel
 
Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....
Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....
Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....
Pierrette Khoury BComm/B Laws, GDLP
 
Karyn Branco CAU Article Trial Ready Defense
Karyn Branco CAU Article Trial Ready DefenseKaryn Branco CAU Article Trial Ready Defense
Karyn Branco CAU Article Trial Ready DefenseKaryn Branco
 
Arbitration Proceeding (Working Guidlines)
Arbitration Proceeding (Working Guidlines)Arbitration Proceeding (Working Guidlines)
Arbitration Proceeding (Working Guidlines)
SME Technologist
 

What's hot (20)

media report analysis (final)
media report analysis (final)media report analysis (final)
media report analysis (final)
 
The Law of Penalties - ANZ v Andrews and beyond
The Law of Penalties - ANZ v Andrews and beyond The Law of Penalties - ANZ v Andrews and beyond
The Law of Penalties - ANZ v Andrews and beyond
 
UNL1622 – CONTRACT LAW II (REMOTENESS)
UNL1622 – CONTRACT LAW II (REMOTENESS)UNL1622 – CONTRACT LAW II (REMOTENESS)
UNL1622 – CONTRACT LAW II (REMOTENESS)
 
Compare the judgements of Bhatia and Balco and Secondly what in your opinion ...
Compare the judgements of Bhatia and Balco and Secondly what in your opinion ...Compare the judgements of Bhatia and Balco and Secondly what in your opinion ...
Compare the judgements of Bhatia and Balco and Secondly what in your opinion ...
 
ADR - 5TH MAY - Cpt. BHATIA (F) - 5th LECTURE
ADR - 5TH MAY - Cpt. BHATIA (F) - 5th LECTUREADR - 5TH MAY - Cpt. BHATIA (F) - 5th LECTURE
ADR - 5TH MAY - Cpt. BHATIA (F) - 5th LECTURE
 
Business laws
Business lawsBusiness laws
Business laws
 
Time Bars and their enforceability in English law EPC contracts
Time Bars and their enforceability in English law EPC contractsTime Bars and their enforceability in English law EPC contracts
Time Bars and their enforceability in English law EPC contracts
 
Dealing with 'fit for purpose' obligation
Dealing with 'fit for purpose' obligationDealing with 'fit for purpose' obligation
Dealing with 'fit for purpose' obligation
 
Atty Contract 6 24 98
Atty Contract 6 24 98Atty Contract 6 24 98
Atty Contract 6 24 98
 
Mardia chemicals case by shreya a322509022
Mardia chemicals case by shreya a322509022Mardia chemicals case by shreya a322509022
Mardia chemicals case by shreya a322509022
 
Conduct of arbitral proceeding vaibhav goyal
Conduct of arbitral proceeding vaibhav goyalConduct of arbitral proceeding vaibhav goyal
Conduct of arbitral proceeding vaibhav goyal
 
Powerpoint for Legalwise Annual Property Seminar March 2016
Powerpoint for Legalwise Annual Property Seminar March 2016Powerpoint for Legalwise Annual Property Seminar March 2016
Powerpoint for Legalwise Annual Property Seminar March 2016
 
Dispute resolution uae_venkat
Dispute resolution uae_venkatDispute resolution uae_venkat
Dispute resolution uae_venkat
 
Construction Law - Remedies for Breach of Contract
Construction Law - Remedies for Breach of ContractConstruction Law - Remedies for Breach of Contract
Construction Law - Remedies for Breach of Contract
 
Legal Solutions In A Tough Economy
Legal Solutions In A Tough EconomyLegal Solutions In A Tough Economy
Legal Solutions In A Tough Economy
 
J.S. Daniel paper on Arbitrated cases in lebanon and decisions of arbitrators
J.S. Daniel paper on Arbitrated cases in lebanon and decisions of arbitratorsJ.S. Daniel paper on Arbitrated cases in lebanon and decisions of arbitrators
J.S. Daniel paper on Arbitrated cases in lebanon and decisions of arbitrators
 
Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....
Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....
Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....
 
Karyn Branco CAU Article Trial Ready Defense
Karyn Branco CAU Article Trial Ready DefenseKaryn Branco CAU Article Trial Ready Defense
Karyn Branco CAU Article Trial Ready Defense
 
Arbitration Proceeding (Working Guidlines)
Arbitration Proceeding (Working Guidlines)Arbitration Proceeding (Working Guidlines)
Arbitration Proceeding (Working Guidlines)
 
Reicon14 session 3 final ppt
Reicon14 session 3 final pptReicon14 session 3 final ppt
Reicon14 session 3 final ppt
 

Viewers also liked

Suit from ixmation against Switch Lighting
Suit from ixmation against Switch LightingSuit from ixmation against Switch Lighting
Suit from ixmation against Switch Lighting
katiefehren
 
New Kmart Data Breach lawsuit spotlights PCI DSS
 New Kmart Data Breach lawsuit spotlights PCI DSS New Kmart Data Breach lawsuit spotlights PCI DSS
New Kmart Data Breach lawsuit spotlights PCI DSS
David Sweigert
 
Heartland Credit Card Security Breach Lawsuit
Heartland Credit Card Security Breach LawsuitHeartland Credit Card Security Breach Lawsuit
Heartland Credit Card Security Breach Lawsuit
LegalDocs
 
Reported Decisions
Reported DecisionsReported Decisions
Reported Decisionsrpwozniak
 
Writing Sample(SD News Memo)
Writing Sample(SD News Memo)Writing Sample(SD News Memo)
Writing Sample(SD News Memo)Granville Kaufman
 
Employment & Labor Law for the Year 2013
Employment & Labor Law for the Year 2013Employment & Labor Law for the Year 2013
Employment & Labor Law for the Year 2013
Armstrong Teasdale
 
Facebook Case_Decision and Order_LaPorte
Facebook Case_Decision and Order_LaPorteFacebook Case_Decision and Order_LaPorte
Facebook Case_Decision and Order_LaPorteTodd Welch
 
Trial Order Ash Grove v. Travelers et al
Trial Order Ash Grove v. Travelers et alTrial Order Ash Grove v. Travelers et al
Trial Order Ash Grove v. Travelers et al
Seth Row
 
Estate & Forestry Consulting Management v Koperasi Permodalan Melayu Negeri J...
Estate & Forestry Consulting Management v Koperasi Permodalan Melayu Negeri J...Estate & Forestry Consulting Management v Koperasi Permodalan Melayu Negeri J...
Estate & Forestry Consulting Management v Koperasi Permodalan Melayu Negeri J...
Yasmin Adilah
 
Red Clause Letters of Credit
Red Clause Letters of CreditRed Clause Letters of Credit
Red Clause Letters of Credit
Robert Hernandez
 
Attachment Trustee Process & Execution
Attachment Trustee Process & ExecutionAttachment Trustee Process & Execution
Attachment Trustee Process & Execution
MikeProsser
 
Chapter 5 fincredi
Chapter 5 fincrediChapter 5 fincredi
Chapter 5 fincredi
AliciaAdapon
 
validity of allotment letter
validity of allotment lettervalidity of allotment letter
validity of allotment letterSanju Ahooja
 
Stephen A. Odeyemi Vs Nigeria Telecommunications Plc
Stephen A. Odeyemi Vs Nigeria Telecommunications PlcStephen A. Odeyemi Vs Nigeria Telecommunications Plc
Stephen A. Odeyemi Vs Nigeria Telecommunications Plc
proverbs6_31
 
Public international law trendtex case_ State Immunity
Public international law trendtex case_ State ImmunityPublic international law trendtex case_ State Immunity
Public international law trendtex case_ State Immunity
Manish Kumar
 
Letter of credit
Letter of creditLetter of credit
Letter of credit
mohammed imtiaj chowdhury
 
The indian contract act 1872
The indian contract act 1872The indian contract act 1872
The indian contract act 1872rahulmathur
 
Documentary credit
Documentary creditDocumentary credit
Documentary credit
AsHra ReHmat
 

Viewers also liked (20)

Suit from ixmation against Switch Lighting
Suit from ixmation against Switch LightingSuit from ixmation against Switch Lighting
Suit from ixmation against Switch Lighting
 
New Kmart Data Breach lawsuit spotlights PCI DSS
 New Kmart Data Breach lawsuit spotlights PCI DSS New Kmart Data Breach lawsuit spotlights PCI DSS
New Kmart Data Breach lawsuit spotlights PCI DSS
 
Heartland Credit Card Security Breach Lawsuit
Heartland Credit Card Security Breach LawsuitHeartland Credit Card Security Breach Lawsuit
Heartland Credit Card Security Breach Lawsuit
 
Reported Decisions
Reported DecisionsReported Decisions
Reported Decisions
 
Writing Sample Dec 2015
Writing Sample Dec 2015Writing Sample Dec 2015
Writing Sample Dec 2015
 
Writing Sample(SD News Memo)
Writing Sample(SD News Memo)Writing Sample(SD News Memo)
Writing Sample(SD News Memo)
 
Employment & Labor Law for the Year 2013
Employment & Labor Law for the Year 2013Employment & Labor Law for the Year 2013
Employment & Labor Law for the Year 2013
 
Facebook Case_Decision and Order_LaPorte
Facebook Case_Decision and Order_LaPorteFacebook Case_Decision and Order_LaPorte
Facebook Case_Decision and Order_LaPorte
 
Trial Order Ash Grove v. Travelers et al
Trial Order Ash Grove v. Travelers et alTrial Order Ash Grove v. Travelers et al
Trial Order Ash Grove v. Travelers et al
 
Estate & Forestry Consulting Management v Koperasi Permodalan Melayu Negeri J...
Estate & Forestry Consulting Management v Koperasi Permodalan Melayu Negeri J...Estate & Forestry Consulting Management v Koperasi Permodalan Melayu Negeri J...
Estate & Forestry Consulting Management v Koperasi Permodalan Melayu Negeri J...
 
Red Clause Letters of Credit
Red Clause Letters of CreditRed Clause Letters of Credit
Red Clause Letters of Credit
 
Attachment Trustee Process & Execution
Attachment Trustee Process & ExecutionAttachment Trustee Process & Execution
Attachment Trustee Process & Execution
 
Chapter 5 fincredi
Chapter 5 fincrediChapter 5 fincredi
Chapter 5 fincredi
 
validity of allotment letter
validity of allotment lettervalidity of allotment letter
validity of allotment letter
 
Stephen A. Odeyemi Vs Nigeria Telecommunications Plc
Stephen A. Odeyemi Vs Nigeria Telecommunications PlcStephen A. Odeyemi Vs Nigeria Telecommunications Plc
Stephen A. Odeyemi Vs Nigeria Telecommunications Plc
 
Public international law trendtex case_ State Immunity
Public international law trendtex case_ State ImmunityPublic international law trendtex case_ State Immunity
Public international law trendtex case_ State Immunity
 
Letter of credit
Letter of creditLetter of credit
Letter of credit
 
The indian contract act 1872
The indian contract act 1872The indian contract act 1872
The indian contract act 1872
 
Documentary credit
Documentary creditDocumentary credit
Documentary credit
 
Lecture 10 mistake - cases
Lecture 10   mistake - casesLecture 10   mistake - cases
Lecture 10 mistake - cases
 

Similar to Suit from ixmation against Switch Lighting, October 23, 2014

Real time Attorney advice memo priviledged and confidential
Real time  Attorney advice memo priviledged and confidentialReal time  Attorney advice memo priviledged and confidential
Real time Attorney advice memo priviledged and confidential
nicemanin
 
Express working capital llc v Starving Students Inc
Express working capital llc v Starving Students IncExpress working capital llc v Starving Students Inc
Express working capital llc v Starving Students Inc
M P
 
Miles v. deutsche bank national trust company | find law
Miles v. deutsche bank national trust company | find lawMiles v. deutsche bank national trust company | find law
Miles v. deutsche bank national trust company | find law
Justin Gluesing
 
1. For the short essay questions write your answers in the space pro.docx
1. For the short essay questions write your answers in the space pro.docx1. For the short essay questions write your answers in the space pro.docx
1. For the short essay questions write your answers in the space pro.docx
SONU61709
 
Defendants Closing Argument Brief
Defendants Closing Argument BriefDefendants Closing Argument Brief
Defendants Closing Argument Brief
Faith at Poetic.Injustice
 
Fleet v. Bank of America case from California Court of Appeal
Fleet v. Bank of America case from California Court of AppealFleet v. Bank of America case from California Court of Appeal
Fleet v. Bank of America case from California Court of Appeal
LegalDocsPro
 
Tutorial4 presentation ver.3
Tutorial4 presentation ver.3Tutorial4 presentation ver.3
Tutorial4 presentation ver.3Thia Chiong Wei
 
City Water International Inc. v. 816580 Ontario Inc.
City Water International Inc. v. 816580 Ontario Inc.City Water International Inc. v. 816580 Ontario Inc.
City Water International Inc. v. 816580 Ontario Inc.Matthew Riddell
 
Messy.mechanics.lien
Messy.mechanics.lienMessy.mechanics.lien
Messy.mechanics.lien
Kevin Connolly
 
Messy.mechanics.lien
Messy.mechanics.lienMessy.mechanics.lien
Messy.mechanics.lien
Kevin Connolly
 
Hurricane Recovery Compilation for Community Association
Hurricane Recovery Compilation for Community AssociationHurricane Recovery Compilation for Community Association
Hurricane Recovery Compilation for Community Association
Associated Property Management (APM)
 
Emergency Mitigation Measures and Repairs, Allegedly Faulty, Doom Coverage
Emergency Mitigation Measures and Repairs, Allegedly Faulty, Doom CoverageEmergency Mitigation Measures and Repairs, Allegedly Faulty, Doom Coverage
Emergency Mitigation Measures and Repairs, Allegedly Faulty, Doom Coverage
NationalUnderwriter
 
Article 41 payment and pay less notices february 2017 rm03
Article 41 payment and pay less notices february 2017 rm03Article 41 payment and pay less notices february 2017 rm03
Article 41 payment and pay less notices february 2017 rm03
Nick Cheetham
 
Doc1031 pay day for lynn tillotson pinker & cox $189,945.99
Doc1031 pay day for lynn tillotson pinker & cox $189,945.99Doc1031 pay day for lynn tillotson pinker & cox $189,945.99
Doc1031 pay day for lynn tillotson pinker & cox $189,945.99
malp2009
 
FORMAT FOR CASE BRIEF Virtually all of the cases in thi.docx
FORMAT FOR CASE BRIEF  Virtually all of the cases in thi.docxFORMAT FOR CASE BRIEF  Virtually all of the cases in thi.docx
FORMAT FOR CASE BRIEF Virtually all of the cases in thi.docx
budbarber38650
 
NIL-Cases-July-3.docx
NIL-Cases-July-3.docxNIL-Cases-July-3.docx
NIL-Cases-July-3.docx
EnriqueLegaspiIV
 
Legal News Presentation Contract&Tort(Feb08)
Legal News Presentation Contract&Tort(Feb08)Legal News Presentation Contract&Tort(Feb08)
Legal News Presentation Contract&Tort(Feb08)legalnewsblog
 
Divorce: Cancel that line of credit
Divorce: Cancel that line of credit Divorce: Cancel that line of credit
Divorce: Cancel that line of credit
Thomas Mastromatto NMLS #145824
 
Chicago Daily Law Bulletin - 7.29.15 Fraudulent Transfer Act - Pleading Requi...
Chicago Daily Law Bulletin - 7.29.15 Fraudulent Transfer Act - Pleading Requi...Chicago Daily Law Bulletin - 7.29.15 Fraudulent Transfer Act - Pleading Requi...
Chicago Daily Law Bulletin - 7.29.15 Fraudulent Transfer Act - Pleading Requi...Paul Porvaznik
 

Similar to Suit from ixmation against Switch Lighting, October 23, 2014 (20)

Real time Attorney advice memo priviledged and confidential
Real time  Attorney advice memo priviledged and confidentialReal time  Attorney advice memo priviledged and confidential
Real time Attorney advice memo priviledged and confidential
 
Express working capital llc v Starving Students Inc
Express working capital llc v Starving Students IncExpress working capital llc v Starving Students Inc
Express working capital llc v Starving Students Inc
 
Miles v. deutsche bank national trust company | find law
Miles v. deutsche bank national trust company | find lawMiles v. deutsche bank national trust company | find law
Miles v. deutsche bank national trust company | find law
 
1. For the short essay questions write your answers in the space pro.docx
1. For the short essay questions write your answers in the space pro.docx1. For the short essay questions write your answers in the space pro.docx
1. For the short essay questions write your answers in the space pro.docx
 
Defendants Closing Argument Brief
Defendants Closing Argument BriefDefendants Closing Argument Brief
Defendants Closing Argument Brief
 
Fleet v. Bank of America case from California Court of Appeal
Fleet v. Bank of America case from California Court of AppealFleet v. Bank of America case from California Court of Appeal
Fleet v. Bank of America case from California Court of Appeal
 
Tutorial4 presentation ver.3
Tutorial4 presentation ver.3Tutorial4 presentation ver.3
Tutorial4 presentation ver.3
 
City Water International Inc. v. 816580 Ontario Inc.
City Water International Inc. v. 816580 Ontario Inc.City Water International Inc. v. 816580 Ontario Inc.
City Water International Inc. v. 816580 Ontario Inc.
 
Messy.mechanics.lien
Messy.mechanics.lienMessy.mechanics.lien
Messy.mechanics.lien
 
Messy.mechanics.lien
Messy.mechanics.lienMessy.mechanics.lien
Messy.mechanics.lien
 
Admiral.worth
Admiral.worthAdmiral.worth
Admiral.worth
 
Hurricane Recovery Compilation for Community Association
Hurricane Recovery Compilation for Community AssociationHurricane Recovery Compilation for Community Association
Hurricane Recovery Compilation for Community Association
 
Emergency Mitigation Measures and Repairs, Allegedly Faulty, Doom Coverage
Emergency Mitigation Measures and Repairs, Allegedly Faulty, Doom CoverageEmergency Mitigation Measures and Repairs, Allegedly Faulty, Doom Coverage
Emergency Mitigation Measures and Repairs, Allegedly Faulty, Doom Coverage
 
Article 41 payment and pay less notices february 2017 rm03
Article 41 payment and pay less notices february 2017 rm03Article 41 payment and pay less notices february 2017 rm03
Article 41 payment and pay less notices february 2017 rm03
 
Doc1031 pay day for lynn tillotson pinker & cox $189,945.99
Doc1031 pay day for lynn tillotson pinker & cox $189,945.99Doc1031 pay day for lynn tillotson pinker & cox $189,945.99
Doc1031 pay day for lynn tillotson pinker & cox $189,945.99
 
FORMAT FOR CASE BRIEF Virtually all of the cases in thi.docx
FORMAT FOR CASE BRIEF  Virtually all of the cases in thi.docxFORMAT FOR CASE BRIEF  Virtually all of the cases in thi.docx
FORMAT FOR CASE BRIEF Virtually all of the cases in thi.docx
 
NIL-Cases-July-3.docx
NIL-Cases-July-3.docxNIL-Cases-July-3.docx
NIL-Cases-July-3.docx
 
Legal News Presentation Contract&Tort(Feb08)
Legal News Presentation Contract&Tort(Feb08)Legal News Presentation Contract&Tort(Feb08)
Legal News Presentation Contract&Tort(Feb08)
 
Divorce: Cancel that line of credit
Divorce: Cancel that line of credit Divorce: Cancel that line of credit
Divorce: Cancel that line of credit
 
Chicago Daily Law Bulletin - 7.29.15 Fraudulent Transfer Act - Pleading Requi...
Chicago Daily Law Bulletin - 7.29.15 Fraudulent Transfer Act - Pleading Requi...Chicago Daily Law Bulletin - 7.29.15 Fraudulent Transfer Act - Pleading Requi...
Chicago Daily Law Bulletin - 7.29.15 Fraudulent Transfer Act - Pleading Requi...
 

More from katiefehren

SolarCity vs Salt River Project
SolarCity vs Salt River ProjectSolarCity vs Salt River Project
SolarCity vs Salt River Project
katiefehren
 
File0.0514269816662534
File0.0514269816662534File0.0514269816662534
File0.0514269816662534katiefehren
 
A report on usability testing of smart heating products
A report on usability testing of smart heating productsA report on usability testing of smart heating products
A report on usability testing of smart heating products
katiefehren
 
Lawsuit filed against battery startup Envia by former Envia employees
Lawsuit filed against battery startup Envia by former Envia employeesLawsuit filed against battery startup Envia by former Envia employees
Lawsuit filed against battery startup Envia by former Envia employees
katiefehren
 
Fisker's bankruptcy filing that lays out income
Fisker's bankruptcy filing that lays out incomeFisker's bankruptcy filing that lays out income
Fisker's bankruptcy filing that lays out income
katiefehren
 
List of Fisker creditors
List of Fisker creditorsList of Fisker creditors
List of Fisker creditors
katiefehren
 
Lawsuit filed by BRK against Nest and its smoke detector
Lawsuit filed by BRK against Nest and its smoke detectorLawsuit filed by BRK against Nest and its smoke detector
Lawsuit filed by BRK against Nest and its smoke detector
katiefehren
 
Kior Investor Lawsuit
Kior Investor LawsuitKior Investor Lawsuit
Kior Investor Lawsuit
katiefehren
 
Class Action WARN lawsuit against Coda
Class Action WARN lawsuit against CodaClass Action WARN lawsuit against Coda
Class Action WARN lawsuit against Coda
katiefehren
 
Corporate Billing vs Coda
Corporate Billing vs CodaCorporate Billing vs Coda
Corporate Billing vs Coda
katiefehren
 
BET Services vs Coda Automotive
BET Services vs Coda AutomotiveBET Services vs Coda Automotive
BET Services vs Coda Automotive
katiefehren
 
Exhibit Works vs Coda
Exhibit Works vs CodaExhibit Works vs Coda
Exhibit Works vs Coda
katiefehren
 
RLE/RTECH vs Coda
RLE/RTECH vs CodaRLE/RTECH vs Coda
RLE/RTECH vs Coda
katiefehren
 
CDH vs Coda Automotive
CDH vs Coda AutomotiveCDH vs Coda Automotive
CDH vs Coda Automotive
katiefehren
 
Exhibit B, letter from dealer to Fisker
Exhibit B, letter from dealer to Fisker Exhibit B, letter from dealer to Fisker
Exhibit B, letter from dealer to Fisker
katiefehren
 
Complaint against Fisker, Capital Cadillac Company
Complaint against Fisker, Capital Cadillac CompanyComplaint against Fisker, Capital Cadillac Company
Complaint against Fisker, Capital Cadillac Company
katiefehren
 
Fisker lawsuit over unpaid bills for web design
Fisker lawsuit over unpaid bills for web designFisker lawsuit over unpaid bills for web design
Fisker lawsuit over unpaid bills for web design
katiefehren
 
Fisker landlord suit
Fisker landlord suitFisker landlord suit
Fisker landlord suit
katiefehren
 
Fisker's lawsuit against insurance company
Fisker's lawsuit against insurance companyFisker's lawsuit against insurance company
Fisker's lawsuit against insurance company
katiefehren
 
NREL Forum Talk
NREL Forum TalkNREL Forum Talk
NREL Forum Talk
katiefehren
 

More from katiefehren (20)

SolarCity vs Salt River Project
SolarCity vs Salt River ProjectSolarCity vs Salt River Project
SolarCity vs Salt River Project
 
File0.0514269816662534
File0.0514269816662534File0.0514269816662534
File0.0514269816662534
 
A report on usability testing of smart heating products
A report on usability testing of smart heating productsA report on usability testing of smart heating products
A report on usability testing of smart heating products
 
Lawsuit filed against battery startup Envia by former Envia employees
Lawsuit filed against battery startup Envia by former Envia employeesLawsuit filed against battery startup Envia by former Envia employees
Lawsuit filed against battery startup Envia by former Envia employees
 
Fisker's bankruptcy filing that lays out income
Fisker's bankruptcy filing that lays out incomeFisker's bankruptcy filing that lays out income
Fisker's bankruptcy filing that lays out income
 
List of Fisker creditors
List of Fisker creditorsList of Fisker creditors
List of Fisker creditors
 
Lawsuit filed by BRK against Nest and its smoke detector
Lawsuit filed by BRK against Nest and its smoke detectorLawsuit filed by BRK against Nest and its smoke detector
Lawsuit filed by BRK against Nest and its smoke detector
 
Kior Investor Lawsuit
Kior Investor LawsuitKior Investor Lawsuit
Kior Investor Lawsuit
 
Class Action WARN lawsuit against Coda
Class Action WARN lawsuit against CodaClass Action WARN lawsuit against Coda
Class Action WARN lawsuit against Coda
 
Corporate Billing vs Coda
Corporate Billing vs CodaCorporate Billing vs Coda
Corporate Billing vs Coda
 
BET Services vs Coda Automotive
BET Services vs Coda AutomotiveBET Services vs Coda Automotive
BET Services vs Coda Automotive
 
Exhibit Works vs Coda
Exhibit Works vs CodaExhibit Works vs Coda
Exhibit Works vs Coda
 
RLE/RTECH vs Coda
RLE/RTECH vs CodaRLE/RTECH vs Coda
RLE/RTECH vs Coda
 
CDH vs Coda Automotive
CDH vs Coda AutomotiveCDH vs Coda Automotive
CDH vs Coda Automotive
 
Exhibit B, letter from dealer to Fisker
Exhibit B, letter from dealer to Fisker Exhibit B, letter from dealer to Fisker
Exhibit B, letter from dealer to Fisker
 
Complaint against Fisker, Capital Cadillac Company
Complaint against Fisker, Capital Cadillac CompanyComplaint against Fisker, Capital Cadillac Company
Complaint against Fisker, Capital Cadillac Company
 
Fisker lawsuit over unpaid bills for web design
Fisker lawsuit over unpaid bills for web designFisker lawsuit over unpaid bills for web design
Fisker lawsuit over unpaid bills for web design
 
Fisker landlord suit
Fisker landlord suitFisker landlord suit
Fisker landlord suit
 
Fisker's lawsuit against insurance company
Fisker's lawsuit against insurance companyFisker's lawsuit against insurance company
Fisker's lawsuit against insurance company
 
NREL Forum Talk
NREL Forum TalkNREL Forum Talk
NREL Forum Talk
 

Recently uploaded

The Art of the Pitch: WordPress Relationships and Sales
The Art of the Pitch: WordPress Relationships and SalesThe Art of the Pitch: WordPress Relationships and Sales
The Art of the Pitch: WordPress Relationships and Sales
Laura Byrne
 
Mission to Decommission: Importance of Decommissioning Products to Increase E...
Mission to Decommission: Importance of Decommissioning Products to Increase E...Mission to Decommission: Importance of Decommissioning Products to Increase E...
Mission to Decommission: Importance of Decommissioning Products to Increase E...
Product School
 
State of ICS and IoT Cyber Threat Landscape Report 2024 preview
State of ICS and IoT Cyber Threat Landscape Report 2024 previewState of ICS and IoT Cyber Threat Landscape Report 2024 preview
State of ICS and IoT Cyber Threat Landscape Report 2024 preview
Prayukth K V
 
PCI PIN Basics Webinar from the Controlcase Team
PCI PIN Basics Webinar from the Controlcase TeamPCI PIN Basics Webinar from the Controlcase Team
PCI PIN Basics Webinar from the Controlcase Team
ControlCase
 
UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3
DianaGray10
 
Generating a custom Ruby SDK for your web service or Rails API using Smithy
Generating a custom Ruby SDK for your web service or Rails API using SmithyGenerating a custom Ruby SDK for your web service or Rails API using Smithy
Generating a custom Ruby SDK for your web service or Rails API using Smithy
g2nightmarescribd
 
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
Product School
 
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
Sri Ambati
 
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered QualitySoftware Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Inflectra
 
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdfFIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
FIDO Alliance
 
DevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA ConnectDevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA Connect
Kari Kakkonen
 
Essentials of Automations: Optimizing FME Workflows with Parameters
Essentials of Automations: Optimizing FME Workflows with ParametersEssentials of Automations: Optimizing FME Workflows with Parameters
Essentials of Automations: Optimizing FME Workflows with Parameters
Safe Software
 
Bits & Pixels using AI for Good.........
Bits & Pixels using AI for Good.........Bits & Pixels using AI for Good.........
Bits & Pixels using AI for Good.........
Alison B. Lowndes
 
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
Product School
 
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdfFIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance
 
Leading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdfLeading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdf
OnBoard
 
When stars align: studies in data quality, knowledge graphs, and machine lear...
When stars align: studies in data quality, knowledge graphs, and machine lear...When stars align: studies in data quality, knowledge graphs, and machine lear...
When stars align: studies in data quality, knowledge graphs, and machine lear...
Elena Simperl
 
GraphRAG is All You need? LLM & Knowledge Graph
GraphRAG is All You need? LLM & Knowledge GraphGraphRAG is All You need? LLM & Knowledge Graph
GraphRAG is All You need? LLM & Knowledge Graph
Guy Korland
 
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Albert Hoitingh
 
JMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and GrafanaJMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and Grafana
RTTS
 

Recently uploaded (20)

The Art of the Pitch: WordPress Relationships and Sales
The Art of the Pitch: WordPress Relationships and SalesThe Art of the Pitch: WordPress Relationships and Sales
The Art of the Pitch: WordPress Relationships and Sales
 
Mission to Decommission: Importance of Decommissioning Products to Increase E...
Mission to Decommission: Importance of Decommissioning Products to Increase E...Mission to Decommission: Importance of Decommissioning Products to Increase E...
Mission to Decommission: Importance of Decommissioning Products to Increase E...
 
State of ICS and IoT Cyber Threat Landscape Report 2024 preview
State of ICS and IoT Cyber Threat Landscape Report 2024 previewState of ICS and IoT Cyber Threat Landscape Report 2024 preview
State of ICS and IoT Cyber Threat Landscape Report 2024 preview
 
PCI PIN Basics Webinar from the Controlcase Team
PCI PIN Basics Webinar from the Controlcase TeamPCI PIN Basics Webinar from the Controlcase Team
PCI PIN Basics Webinar from the Controlcase Team
 
UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3
 
Generating a custom Ruby SDK for your web service or Rails API using Smithy
Generating a custom Ruby SDK for your web service or Rails API using SmithyGenerating a custom Ruby SDK for your web service or Rails API using Smithy
Generating a custom Ruby SDK for your web service or Rails API using Smithy
 
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
 
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
 
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered QualitySoftware Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
 
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdfFIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
 
DevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA ConnectDevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA Connect
 
Essentials of Automations: Optimizing FME Workflows with Parameters
Essentials of Automations: Optimizing FME Workflows with ParametersEssentials of Automations: Optimizing FME Workflows with Parameters
Essentials of Automations: Optimizing FME Workflows with Parameters
 
Bits & Pixels using AI for Good.........
Bits & Pixels using AI for Good.........Bits & Pixels using AI for Good.........
Bits & Pixels using AI for Good.........
 
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
 
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdfFIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
 
Leading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdfLeading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdf
 
When stars align: studies in data quality, knowledge graphs, and machine lear...
When stars align: studies in data quality, knowledge graphs, and machine lear...When stars align: studies in data quality, knowledge graphs, and machine lear...
When stars align: studies in data quality, knowledge graphs, and machine lear...
 
GraphRAG is All You need? LLM & Knowledge Graph
GraphRAG is All You need? LLM & Knowledge GraphGraphRAG is All You need? LLM & Knowledge Graph
GraphRAG is All You need? LLM & Knowledge Graph
 
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
 
JMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and GrafanaJMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and Grafana
 

Suit from ixmation against Switch Lighting, October 23, 2014

  • 1. IN THE UNITED STATES DISTRICT COURT FOR THE NORTHERN DISTRICT OF ILLINOIS EASTERN DIVISION IXMATION, INC., ) ) Plaintiff, ) v. ) Case No. 14-cv-6993 ) SWITCH BULB COMPANY, INC., a/k/a ) SWITCH LIGHTING CO. and WELLS ) FARGO BANK, N.A., ) Judge John Z. Lee ) ) Defendants. ) MEMORANDUM OPINION AND ORDER Plaintiff Ixmation, Inc., (“Ixmation”) and Defendant Switch Bulb Company, Inc. (“Switch”) entered into an agreement whereby Ixmation agreed to manufacture a custom automated system for Switch. To secure payment, Switch obtained a Letter of Credit, which had an expiration date of October 1, 2014, from Wells Fargo Bank, N.A., issued for Ixmation’s benefit. However, before Ixmation could complete its work and collect fully on the Letter of Credit, Switch told Ixmation to halt work on the project and later executed an assignment for the benefit of creditors under California law. In response, Ixmation commenced an arbitration proceeding against Switch in April of this year and, worried that the Letter of Credit would expire, filed this suit and a motion for temporary restraining order in September, requesting that the Court maintain the status quo until the arbitration is concluded. Granting Ixmation’s motion, the Court previously issued a temporary restraining order placing an equitable lien on the Letter of Credit to maintain the status quo pending the arbitration. The Letter of Credit has since expired by its terms, but the equitable lien was extended over the funds that Switch previously had deposited with Wells Fargo to secure the 1 Case: 1:14-cv-06993 Document #: 60 Filed: 10/23/14 Page 1 of 17 PageID #:813
  • 2. Letter of Credit. Ixmation now moves for issuance of a preliminary injunction to maintain the equitable lien over the funds. Switch opposes Ixmation’s motion, arguing that this Court lacks authority to enter the injunctive relief Ixmation requests, that Ixmation has not met the requirements for an equitable lien, and that Ixmation has not met its burden to obtain preliminary injunctive relief. 1 For the reasons discussed below, the Court concludes that Ixmation has failed to meet its burden to obtain a preliminary injunction, and its motion is denied. I. Factual and Procedural Background A. The Proposal, Production, and Breach Ixmation builds and sells production machinery and automated systems. Switch designs, manufactures, and sells various LED lighting solutions. Switch and Ixmation entered into a contract (the “Proposal”) on July 12, 2013, for the manufacture of a custom automation system. See Am. Compl. ¶ 4; id. Ex. A. By the terms of the Proposal, Ixmation agreed to design and build the custom automation system for Switch in return for $3,908,000.00, and Switch issued a purchase order for the automation system. See id. ¶ 6; id. Ex. B. The Proposal required Switch to pay Ixmation in increments contingent on Ixmation’s successful completion of certain milestones. See id. ¶ 8; id. Ex. A. The Proposal’s Appendix, documenting Ixmation’s terms and conditions of sale, contained an arbitration provision requiring the parties to arbitrate, inter alia, breach of contract claims. Id. Ex. A, Appendix I, ¶ 19. The arbitration provision also required that any disputes regarding the Proposal would be governed by Illinois law. Id. 1 Switch concurrently moves to dismiss this lawsuit or in the alternative moves to stay the case and compel arbitration. See generally Def.’s Mot. Dismiss, or in Alt. Compel Arb. The Court has set a status hearing for November 3, 2014, at which time it will take up Switch’s motion. Additionally, two clean technology venture capital investment firms which are part of Switch’s assignment for benefit of creditors in California have moved to intervene in the proceedings here. See generally Intervenors’ Mot. Interv. Similarly, the Court will continue this motion and defer its consideration until the November 3, 2014 hearing. 2 Case: 1:14-cv-06993 Document #: 60 Filed: 10/23/14 Page 2 of 17 PageID #:814
  • 3. Throughout the months following the Proposal and purchase order, the parties agreed to several change orders. Of particular relevance is a November 2013 change order that resulted in a credit of $573,670.00 to Switch and delayed the project delivery schedule by seven to nine weeks. See Pl’s Mot. Prel. Inj., Curtis Aff. ¶ 7. This delay was, at least partly, due to Switch unilaterally putting the project on hold for several weeks. Id. Switch later acknowledged in a February 28, 2014, email that the November 2013 change order’s revised delivery schedule meant Factory Assurance Testing (“FAT”), a production milestone stage, would not occur until the week of March 31, 2014. Id. ¶ 8; see also id. Ex. 2. In this email, Switch documented a detailed schedule for finishing production of the machine from the FAT stage of production through shipping and delivery in late April. See id. Ex. 2. In August 2013, Ixmation requested a Letter of Credit from Switch to secure payment for the custom automation system. On August 5, 2013, Wells Fargo issued the Letter of Credit in the amount of $3,079,200.00. See Am. Compl. Ex. D. The Letter of Credit had an expiration date of September 1, 2014. See id. On November 25, 2013, at the request of Ixmation, the amount in the Letter of Credit was reduced to $2,858,194.50, and the expiration date was extended to October 1, 2014. See id. Ex. E. As Ixmation made progress on the manufacture of the custom automation system, it drew on the Letter of Credit. The first draw occurred in October 2013 and the second in January 2014, with the draws totaling $1,836,097.80. See id. ¶ 11. The first draw was authorized after Ixmation completed its mechanical design review stage of production. See Pl.’s Mot. Prelim. Inj., Ludwig Aff. ¶ 7. The second draw was authorized after Ixmation completed a sub-system debug of the custom automation system. See id. ¶ 8. Consequently, $1,022,096.70 remained in the Letter of Credit. See Am. Compl. ¶ 11. 3 Case: 1:14-cv-06993 Document #: 60 Filed: 10/23/14 Page 3 of 17 PageID #:815
  • 4. Ixmation would make no further draws. By early spring, a dispute between the parties arose. In March 2014, Ixmation was working on the FAT stage of production. During this time, Ixmation became concerned with Switch’s actions and communications. On March 18, 2014, Ixmation’s Senior Account Manager Randy Curtis met with Switch’s Project Manager Myron Moreno in San Jose, California, to continue discussions of FAT. See Pl.’s Mot. Prel. Inj., Randy Curtis Aff. ¶ 9. During this meeting, Moreno told Curtis that VantagePoint Capital, a venture capital firm that funded Switch, had laid off more than half of Switch’s employees, including employees who were working on the custom automation system and necessary to complete the FAT stage of production. See id. Despite this, Moreno indicated he would be coming to Ixmation’s place of business in Roselle, Illinois, at the end of March for FAT. See id. The following day, however, on March 19, 2014, Moreno told Curtis that Switch was “trending towards liquidation” and would not be able to provide parts and personnel necessary for Ixmation to complete FAT. See id. ¶ 10. These representations were confirmed on March 20, 2014, in an email from Moreno to Curtis. See id. ¶ 11; see also Am. Compl. Ex. G. The parties continued communications through the end of March 2014. See Pl.’s Mot. Prel. Inj., Curtis Aff. ¶¶ 12–13. For its part, Switch asserts that it was Ixmation that unilaterally ceased work on the custom automation system before reaching additional production milestones that were necessary to draw additional funds from the Letter of Credit. See Def.’s Mem. Opp. 2. An exchange of letters in late March captured the state of the parties’ business relationship. By letter on March 27, 2014, Switch’s Executive Vice President Ronald Rudolph notified Ixmation that on March 24, 2014, Switch had requested that Ixmation stop work on the custom automation system and that further financial assurances from Switch were not forthcoming because “[I]xmation insisted from the beginning that the full cost of the [custom automation system] be 4 Case: 1:14-cv-06993 Document #: 60 Filed: 10/23/14 Page 4 of 17 PageID #:816
  • 5. deposited into a bank under letter of credit with funds to be released upon [I]xmation’s appropriate performance.” See Pl.’s Mot. Prelim. Inj., Ludwig Aff. ¶ 11; id. Ex. 1. Ixmation’s President Mick Macsek promptly responded to Switch on March 28, 2014, writing that it appeared the parties were in a contractual dispute and quoting a provision of the Proposal requiring the parties to put forth best efforts to resolve disputes. See id.; id. Ex. 2. Macsek’s letter served as Ixmation’s formal request for a meeting of the companies’ senior executives. See id. Ex. 2. Ixmation, now cognizant of an impending breakdown in the parties’ relationship and Switch’s apparently precarious financial state, sent four senior executives to attend the meeting on April 3, 2014, in San Jose, California. Pl.’s Mot. Prelim. Inj., Ludwig Aff. ¶ 12. According to Ixmation, this meeting proved fruitless; Switch provided no answers to questions concerning the reason for Switch’s suspension of operations and apparent skeleton crew, and no satisfactory plan on how Switch intended to supply the parts and personnel necessary for Ixmation to perform FAT. See Pl.’s Mot. Prel. Inj., Curtis Aff. ¶¶ 12, 14. B. Arbitration and Assignment for the Benefit of Creditors Faced with its rapidly deteriorating business relationship with Switch, Ixmation filed for American Arbitration Association (“AAA”) arbitration on April 16, 2014. See Amend. Compl. ¶ 19. The timeline of arbitration thereafter becomes hazy. Each party insists that, after the April 16, 2014, filing by Ixmation, it was the other party that delayed further progress in the arbitration. Ixmation represented to the Court at the October 20, 2014 hearing that, after it had filed for AAA arbitration, it did not move to expedite the process or take any other actions to advance the arbitration in the hope that Switch would eventually agree to resolve their dispute. 5 Case: 1:14-cv-06993 Document #: 60 Filed: 10/23/14 Page 5 of 17 PageID #:817
  • 6. Switch insists that is was Ixmation who delayed the arbitration. See generally Def.’s Second Supp. Mem. Opp’n. Pl.’s Mot. TRO 10–11. Regardless, the next significant action in the arbitration proceedings was an email sent to Ixmation by Kelly Turner of the AAA on May 6, 2014. In the email, Turner informed Ixmation that it had to pay an administration fee by July 17, 2014, before the AAA would appoint an arbitrator so that the arbitration could proceed. See Pl.’s Supp. Memo. Ex. 2. The AAA required this “proceed fee” because Ixmation had chosen to file its request for arbitration under a flexible fee schedule. See id. The email notice also imposed a deadline of May 20, 2014, for Switch to file an answer, counterclaim, or objection to Ixmation’s request to hold the arbitration in Chicago. See id. A little less than one month after this email was sent, on May 30, 2014, Switch instituted an assignment for the benefit of creditors under California law.2 See id. Ex. 4. While Switch apparently informed the AAA of this assignment by email on June 30, 2014, see id., Ixmation did not receive notice of Switch’s assignment until the AAA sent an email to Ixmation on July 9, 2014. See id. Ex. 5. By this point, Ixmation still had not paid the required proceed fee to begin arbitration. The next week, on July 15, 2014, Ixmation finally paid the fee, requested that the arbitration proceed without Switch, and for the first time requested expedited briefing. See id. Ex. 6. Thereafter a series of email communications occurred between Switch, Kelly Turner, and Ixmation. See generally id. Ex. 7. Turner contacted the parties, attempting to schedule an administrative conference call for the final weeks of July. See id. 7/16/14 Email from Kelly 2 An assignment for the benefit of creditors is a state-level equivalent to a bankruptcy proceeding. See Pl.’s Supp. Mem. Ex. 4 (6/30/14 email from Switch to the AAA) (“An [assignment for the benefit of creditors] is a state level insolvency proceeding undertaken under state law, in this case California[.]”). 6 Case: 1:14-cv-06993 Document #: 60 Filed: 10/23/14 Page 6 of 17 PageID #:818
  • 7. Turner to Switch and Ixmation. Ixmation replied on July 16, 2014, asking to schedule the administrative conference call for July 21 or July 22. See id. 7/16/14 Email from Ixmation to Kelly Turner. Turner then suggested a date of July 22, 2014. See id. 7/16/14 Email from Kelly Turner to Switch and Ixmation. Switch responded, indicating that week would not work for it. See id. 7/16/14 Email from Switch to Kelly Turner and Ixmation. The next day, Switch proposed a July 28 or July 29 date. See id. 7/17/14 Email from Switch to Kelly Turner and Ixmation. Thereafter Switch noted that it still was retaining counsel, that it needed to find counsel that could appear in Illinois, and that this process would take two to three weeks. See id. 7/29/14 Email from Switch to Kelly Turner and Ixmation. In an attempt to balance Switch’s need to find appropriate counsel with the need to avoid undue delay, Turner scheduled the conference call for August 15, 2014. See id. 7/29/14 email from Kelly Turner to Switch and Ixmation. After Switch retained counsel, it determined it would contest the Chicago locale requested by Ixmation. See id. Ex. 9. The AAA set a deadline of August 29, 2014, for both sides to submit briefing supporting its requested choice of locale. See id. Ex. 9. August 29 also served as the deadline by which Switch was required to indicate whether it woiuld agree to a single arbitrator instead of the three-arbitrator panel. See id. On September 3, 2104, the AAA decided in favor of Ixmation and determined that the arbitration would take place in Chicago. See id. Ex. 11. The AAA set a deadline of September 17, 2014, for the parties to submit a list of potential arbitrators. See id. On October 3, 2014, the AAA appointed Randall Rapp as an arbitrator. See Def.’s Mot. Dismiss or Alt. Compel., Ex. A. On October 6, 2014, Switch indicated that it would prefer a panel of three arbitrators. See id. Ex. B. Switch’s request is the 7 Case: 1:14-cv-06993 Document #: 60 Filed: 10/23/14 Page 7 of 17 PageID #:819
  • 8. last activity reflected in the record. From the record, it appears that Ixmation never raised any concern about the expiration of the Letter of Credit with the AAA. C. Procedural History of This Action Ixmation filed a complaint and moved for a temporary restraining order (“TRO”) in the Circuit Court for Cook County, Illinois, on September 5, 2014. See Def.’s Notice Remov. ¶ 1; id. Ex. A. Switch removed the case to this Court based on diversity jurisdiction on September 9, 2014. See Def.’s Notice Remov. ¶ 2. Ixmation refiled its request for a TRO on September 10, 2014. See Pl.’s Mot. TRO. This Court held a hearing on Ixmation’s motion for a TRO on September 17, 2014. The Court set a briefing schedule, allowing Wells Fargo to file a response to Ixmation’s motion for a TRO and allowing Switch to file supplemental briefing opposing Ixmation’s motion on state law grounds.3 See 9/17/14 Min. Entry. The Court also encouraged the parties to explore settlement. See id. The Court held another hearing on September 23, 2014. The Court noted that Switch’s supplemental briefing did not address the state law issues the Court requested, but rather reargued points Switch had already raised in its original response brief. See 9/23/14 Min. Entry. Rather than strike Switch’s brief, the Court granted Ixmation a one-day extension to file a brief replying to both Switch and Wells Fargo’s briefing. See id. The Court reset the hearing on Ixmation’s motion for TRO, originally set for September 24, 2014, to September 26, 2014. See id. 3 The Court also denied an earlier motion to dismiss filed by Switch arguing principally that the arbitration provision in the parties’ contracted precluded this Court from intervening in the parties’ dispute. The Court found Switch’s argument unpersuasive in light of Seventh Circuit precedent holding that a court can enter injunctive relief preserving the status quo and the meaningfulness of arbitration. Merrill Lynch, Pierce, Fenner & Smith, Inc. v. Salvano, 999 F.2d 211, 215 (7th Cir. 1993). 8 Case: 1:14-cv-06993 Document #: 60 Filed: 10/23/14 Page 8 of 17 PageID #:820
  • 9. On September 26, 2014, the Court held a hearing on Ixmation’s motion for TRO. The Court first granted Ixmation’s request to submit an amended complaint. See 9/26/14 Min. Entry. The Court then directed the parties to file supplemental briefing addressing the procedural history before the AAA. See id. The Court continued the hearing on Ixmation’s motion for TRO to September 30, 2014, at 12:30 pm. See id. On September 30, 2014, the Court reconvened for a hearing on Ixmation’s motion for TRO. First, the Court addressed whether Wells Fargo should remain in the case. Ixmation asserted no claims against Wells Fargo and represented on the record at the September 26, 2014, hearing that it had no claims against Wells Fargo. See generally 9/30/14 Hr’g Tr. at 3, lns. 10– 13. Without a claim pending against Wells Fargo, the Court dismissed Wells Fargo from the lawsuit and denied Ixmation’s request to compel Wells Fargo to extend the Letter of Credit.4 See 9/30/14 Hr’g Tr. at 3–4, lns. 10–25, 1–18. After dismissing Wells Fargo, the Court turned to Ixmation’s request for a TRO in the form an equitable lien.5 On the record before it, the Court found that Ixmation met the 4 Specifically, the Court found that Ixmation had not pleaded claims against Wells Fargo and admitted that it had no claims against Wells Fargo. The Court noted that under Federal Rule of Civil Procedure 65(d)(2), an injunctive order can only bind the parties, the parties’ officers, agents, servants, employees, and attorneys, and other persons in active concert or participation. See Fed. R. Civ. P. 65(d)(2). A person is in “active concert or participation” if they “aid and abet” the enjoined party or if they are in “privity” with the joined party. Blockowicz v. Williams, 630 F.3d 563, 567 (7th Cir. 2010). Ixmation bore the burden of proving that any third party it sought injunctive relief as to was within the scope of the injunction it sought to enter. Id. Ixmation had not met that burden because it failed to advance evidence that Wells Fargo acted in concert with Switch, was an agent of Switch, or was in privity with Switch. Furthermore, while the Court noted it could issue an injunction against a nonparty in order to preserve its ability to render judgment, see Herrlein v. Kanakis, 526 F.2d 252, 255 (7th Cir. 1975), the Court, mindful of its independent duty to ensure injunctions are appropriate in scope, see Chicago Board of Education v. Substance, Inc., 354 F.3d 624, 631–32 (7th Cir. 2003), declined to enter an injunction against Wells Fargo as a nonparty in this case. 5 Switch mischaracterizes the equitable lien imposed by the Court as a sua sponte form of relief not requested by Ixmation. Ixmation, however, proposed the equitable lien in its moving papers. See Pl.’s Supp. Mem. 9 (noting that preserving the status quo would be by equitable lien if a draw were ordered on the Letter of Credit and the proceeds held in escrow or trust). 9 Case: 1:14-cv-06993 Document #: 60 Filed: 10/23/14 Page 9 of 17 PageID #:821
  • 10. requirements for an emergency TRO and imposed an equitable lien on the Letter of Credit. The Court additionally held that, once the Letter of Credit expired by its own terms, the equitable lien would extend to that portion of the funds that Switch previously had deposited with Wells Fargo as collateral for the Letter of Credit sufficient to cover the balance that remained under the Letter of Credit. See 9/30/14 Hr’g Tr. at 9. Any additional amounts would be released to Switch. See id. The Court then scheduled a briefing schedule for Ixmation’s motion for preliminary injunction and set a hearing on the motion for October 14, 2014 at 4:30 p.m. See 9/30/14 Min. Entry. The Court also required Ixmation to post a bond in the amount of $10,000.00. See id. Subsequently, on October 7, 2014, Switch requested an emergency extension of time to file its response to Ixmation’s motion for preliminary injunction. See Def.’s Mot. Ext. Time. The Court held a hearing on October 8, 2014, and granted the motion based upon Switch’s agreement to be bound by the TRO until October 20, 2014. See 10/8/14 Min. Entry.6 Switch subsequently filed a motion to dismiss or in the alternative compel arbitration and also requested leave to file an over-length response brief under Local Rule 7.1 to Ixmation’s motion for preliminary injunction. The Court granted Switch’s request and gave Ixmation two additional days to submit its reply brief. See 10/14/14 Min. Entry. The Court continued Switch’s motion and set it for hearing concurrent with Ixmation’s motion for preliminary injunction. See id. On October 20, 2014, the Court heard argument on Ixmation’s request for preliminary relief. The Court also heard brief argument from two venture capital firms, VantagePoint 6 At the parties’ request, the Court also held a telephone conference on October 9, 2014. During the telephone conference, the parties represented that Wells Fargo did not wish to maintain the funds constituting the collateral for the Letter of Credit. See 10/9/14 Min. Entry. Switch proposed that the funds be placed in a separate account in another financial institution and agreed that the transfer would not alter the effect of the equitable lien over those funds. See id. The Court approved this request. See id. 10 Case: 1:14-cv-06993 Document #: 60 Filed: 10/23/14 Page 10 of 17 PageID #:822
  • 11. Cleantech Partners II, L.P., VantagePoint Venture Partners 2006 (Q), L.P. on their motion to intervene filed on October 18, 2014. After argument, the Court took the matter under advisement. That same day, the Court denied Ixmation’s motion. See 10/20/14 Min. Entry. This Memorandum Opinion and Order sets forth the reasoning for the Court’s denial. II. The Court’s Authority to Issue Injunctive Relief As an initial matter, Switch contests the Court’s authority to grant the equitable relief previously granted to Ixmation. Specifically, Switch cites to Grupo Mexicano de Desarrollo S.A. v. Alliance Bond Fund, Inc., 527 U.S. 308 (1999) for the proposition that this Court cannot impose an injunction hindering Switch’s ability to transfer or otherwise use its assets as it sees fits. In Switch’s view, such an injunction would be nothing more than a prohibited prejudgment attachment. But Grupo Mexicano is distinguishable in two material respects. First, Grupo Mexicano involved a breach of contract action seeking only money damages. See Grupo Mexicano, 527 U.S. at 310 (focusing the question presented in the context of “an action for money damages”); see also Oak Leaf Outdoors, Inc. v. Double Dragon Int’l, Inc., 812 F. Supp. 2d 944, 946 (C.D. Ill. 2011) (noting that Grupo Mexicano determined that in a suit for money damages on a contractual breach theory such injunctive relief freezing assets pre-judgment was “historically unavailable from a court of equity”). Here, although Ixmation is seeking money damages in arbitration, it is seeking only equitable relief from this Court to preserve the status quo so that any judgment it may receive from the arbitration panel would be meaningful. See Salvano, 999 F.2d at 215 (district court has authority “to maintain the status quo without prejudice to the merits of any of the parties’ claims or defenses until an arbitration panel [can] consider the issues presented”). 11 Case: 1:14-cv-06993 Document #: 60 Filed: 10/23/14 Page 11 of 17 PageID #:823
  • 12. Furthermore, even after Grupo Mexicano, courts have recognized a district court’s authority to enter equitable relief preserving assets where there is a “nexus between the assets sought to be frozen through an interim order and the ultimate relief requested in the lawsuit.” U.S. ex rel. Rahman v. Oncology Associates, 198 F.3d 489, 496–97 (4th Cir. 1999). Here, a nexus plainly exists between the Letter of Credit, which Switch had arranged with Wells Fargo for Ixmation’s benefit to secure payment under the agreement and Ixmation’s claim. Indeed, Switch itself admitted in its email communications that the Letter of Credit served to cover exactly the production of the custom automation system by Ixmation that is the subject of Ixmation’s claim. Accordingly, the reasoning in Grupo Mexicano did not apply in this case while the Letter of Credit was in effect, and the Court had the authority to preserve the status quo by imposing an equitable lien over it and the funds that could be drawn from it.7 That said, whether the equitable lien would extend to the funds that Switch had deposited with Wells Fargo as collateral for the Letter of Credit upon the expiration of the Letter of Credit itself presents an interesting, and previously undecided, question of law.8 But the 7 Contrary to Switch’s contention, Grupo Mexicano also does not “overrule” American Hospital Supply Corp. v. Hospital Products Ltd., 780 F.2d 589 (7th Cir. 1986). As Oak Leaf observes, the Seventh Circuit’s holding in American Hospital Supply Corp. did not consider the key issue in Grupo Mexicano, that is, “whether a district court has the authority to enter a preliminary injunction when the requesting party seeks only money damages for breach of contract.” Oak Leaf Outdoors, 812 F. Supp. 2d at 948 (emphasis added). Moreover, this Court relied on American Hospital Supply Corp. for the proposition that a plaintiff faced with an imminently insolvent defendant suffers irreparable harm. The Court did not invoke American Hospital Supply Corp., as Switch appears to suggest, for the general proposition that an equitable lien is available to Ixmation. Furthermore, it is well-established that a letter of credit and its associated funds does not become part of the bankruptcy estate of the debtor. See In re Duplitronics, Inc., 183 B.R. 1010, 1015 (Bankr. N.D. Ill. 1995). 8 Under Illinois law an equitable lien requires “(1) a debt, duty or obligation owing by one person to another, and (2) a res to which that obligation fastens.” Jacobsen v. Conlon, 302 N.E.2d 471, 473 (Ill. App. Ct. 1973). In the proper circumstances, “[i]f the res to which the lien attaches is converted into money, the Court in a proper case will treat the money as substituted for the property.” In re Brass Kettle Rest., Inc., 790 F.2d 574, 575 (7th Cir. 1986) (quoting Marshall Savings & Loan Ass. v. Chi. Nat. Bank, 206 N.E.2d 117, 120 (Ill. App. Ct. 1965)). 12 Case: 1:14-cv-06993 Document #: 60 Filed: 10/23/14 Page 12 of 17 PageID #:824
  • 13. Court need not address this question here, because it finds, after consideration of the parties’ papers, that Ixmation has failed to demonstration that a preliminary injunction is appropriate. III. Ixmation’s Request for Preliminary Injunction A. Legal Standard Ixmation moves for a preliminary injunction maintaining the TRO. “[A] preliminary injunction is an exercise of a very far-reaching power, never to be indulged in except in a case clearly demanding it.” Girl Scouts of Manitou Council, Inc. v. Girl Scouts of the USA, Inc., 549 F.3d 1079, 1085 (7th Cir. 2008) (internal citations and quotations omitted). The moving party must make a clear showing that it is entitled to the relief it seeks. Goodman v. Ill. Dep’t of Fin. & Prof’l Regulation, 430 F.3d 432, 437 (7th Cir. 2005). A party seeking a preliminary injunction must show that (1) it is reasonably likely to succeed on the merits; (2) no adequate remedy at law exists; (3) it will suffer irreparable harm which, absent injunctive relief, outweighs the irreparable harm the respondent will suffer if the injunction is granted; and (4) the injunction will not harm the public interest. Joelner v. Vill. of Wash. Park, Ill., 378 F.3d 613, 619 (7th Cir. 2004). Analysis of these elements occurs in two phases: a threshold phase and a balancing phase. See Girl Scouts of Manitou Council, 549 F.3d at 1085–86. “To survive the threshold phase, a party seeking a preliminary injunction must satisfy three requirements.” Id. at 1086. First, the party must show that it will suffer irreparable harm without the injunction. Second, the party must demonstrate that traditional legal remedies would be inadequate. Third, the party must establish that its claim has some likelihood of succeeding on the merits. If the party cannot make a showing as to each of these threshold requirements, the preliminary injunction must be denied. Id. If, however, the party meets this initial threshold, the Court will proceed to the balancing phase of the analysis. Id. 13 Case: 1:14-cv-06993 Document #: 60 Filed: 10/23/14 Page 13 of 17 PageID #:825
  • 14. In the balancing phase, the party seeking the injunction must demonstrate that its harm in the absence of such relief outweighs any harm that may be suffered by the non-moving party if the injunction is granted. Id. In making this determination, the Court employs a sliding scale approach: “[t]he more likely the plaintiff is to win, the less heavily need the balance of harms weigh in his favor, the less likely he is to win, the more need it weigh in his favor.” Id. (quoting Roland Mach. Co. v. Dresser Indus., Inc., 749 F.2d 380, 389 (7th Cir. 1984)). Additionally, where appropriate, this balancing process “should . . . encompass any effects that granting or denying the preliminary injunction would have on nonparties (something courts have termed the “public interest”).” Id. (quoting Ty, Inc. v. Jones Grp., Inc., 237 F.3d 891, 895 (7th Cir. 2001)). Taking into account all of these considerations, the Court must exercise its discretion “to arrive at a decision based on a subjective evaluation of the import of the various factors and a personal, intuitive sense about the nature of the case.” Id. (internal citations and quotations omitted). B. Ixmation Has Failed to Show Irreparable Harm On a fuller record and with more developed argument, the Court finds that Ixmation’s unwarranted delay in seeking this injunction belies its contention of irreparable harm and defeats its motion for preliminary injunction. Delay is a factor in assessing the existence of irreparable harm, Ideal Industries, Inc. v. Gardner Bender, Inc., 612 F.2d 1018, 1025 (7th Cir. 1979), and unexcused delay on the part of parties seeking extraordinary injunctive relief is grounds for denial of a motion “because such delay implies a lack of urgency and irreparable harm.” Newdow v. Bush, 355 F. Supp. 2d 265, 292 (D.D.C. 2005). “[T]he likelihood of irreparable harm takes into account how urgent the need for equitable relief really is.” Michigan v. U.S. Army Corps of Engineers, 667 F.3d 765, 788 (7th Cir. 2011). This is particularly true where the party seeking injunctive relief has “knowledge of the pending nature of the alleged irreparable harm.” 14 Case: 1:14-cv-06993 Document #: 60 Filed: 10/23/14 Page 14 of 17 PageID #:826
  • 15. Open Top Sightseeing USA v. Mr. Sightseeing, LLC, Case No. CV 14-820 (BAH), --- F. Supp. 2d ----, 2014 WL 2758603, at *3 (D.D.C. June 18, 2014) (citing Fund for Animals v. Frizzell, 530 F.2d 982, 987 (D.C. Cir. 1975)). Numerous courts in this district have refused to issue preliminary injunctions on this ground. See, e.g., Johnson Publ’g, Co., Inc. v. Willitts Designs Int’l, Inc., No. 98 C 2653, 1998 WL 341618, at *8 (N.D.Ill. June 22, 1998) (presumption of irreparable harm weak where the plaintiff waited four months to request injunctive relief); Stokley–Van Camp, Inc. v. Coca–Cola Co., No. 86 C 6159, 1987 WL 6300, at *3 (N.D.Ill. Jan. 30, 1987) (denying “extraordinary remedy” of preliminary injunction despite presumption of irreparable harm because plaintiff waited three months before filing action and the defendant was spending substantial amounts to market its product). Here, although Ixmation initiated the arbitration on April 16, 2014, it did not pay the proceed fee required by AAA until almost three months later, on July 15, 2014. At a minimum, Ixmation received notice of the required proceed fee on May 6, 2014. And although Ixmation did not know that Switch had executed an assignment for the benefit of creditors until early July, Ixmation became aware of Switch’s precarious financial state in March 2014. Perhaps more importantly, Ixmation knew in no uncertain terms that the Letter of Credit would expire on October 1, 2014. Yet, Ixmation did not seek to expedite the AAA proceedings until July 16, 2014. And, when it did, it only did so in a one-line request that the AAA “select an arbiter and hearing date on an expedited schedule.” See Pl.’s Supp. Mem., Ex. 6. After this request, Ixmation never made another request to expedite the appointment of the arbitrators or otherwise hasten the proceeding, and it never raised any concern about the expiration of the Letter of Credit with the AAA. 15 Case: 1:14-cv-06993 Document #: 60 Filed: 10/23/14 Page 15 of 17 PageID #:827
  • 16. Instead, Ixmation waited until September 5, 2014, to file a request in state court seeking a TRO to preserve that expiration of the Letter of Credit. This was less than one month before the expiration date and nearly four and a half months after Ixmation first filed for arbitration. When asked to explain the delay, Ixmation’s counsel stated during the preliminary injunction hearing that Ixmation had waited until September in the hope that the parties would be able to come to an amicable resolution rather than proceeding with litigation. But, this strategy was at its own risk and its peril. “Although delay may not preclude the grant of ultimate relief, it may preclude preliminary relief because it undermines the sense of urgency that typically accompanies a motion for preliminary injunction.” Silber v. Barbara’s Bakery, Inc., 950 F. Supp. 2d 432, 441 (E.D.N.Y. 2013) (finding five-month delay in moving for preliminary injunction defeated a finding of irreparable harm). To be clear, the Court’s conclusion that Ixmation’s delay precludes preliminary relief does not absolve Switch of blame. On the record before the Court, it appears Switch may have been less than forthright with Ixmation regarding its financial condition in March 2014, failed to communicate its assignment for the benefit of creditors to Ixmation in a timely fashion, and used the procedural devices available to it to prolong the arbitration proceedings, such as challenging the location of the arbitration and insisting upon the appointment of three arbitrators. But, Ixmation should have done its part to expedite the arbitration in light of the Letter of Credit’s October 1 expiration date. It did not do so. “It is horn-book law . . . that a person who seeks the protection of equity must do equity.” In re Thomas, 204 F.2d 788, 794 (7th Cir. 1953). The Court finds that Ixmation’s failure to seek an expeditious resolution of the arbitration proceeding and delay in seeking relief from the Court, despites its full knowledge of the pending October 1 16 Case: 1:14-cv-06993 Document #: 60 Filed: 10/23/14 Page 16 of 17 PageID #:828
  • 17. deadline and reason to doubt Switch’s continuing financial health, fatally undermines its ability to demonstrate the existence of irreparable harm. For this reason, Ixmation’s motion is denied. IV. Conclusion For the reasons stated herein, Ixmation’s Motion for Preliminary Injunction [36] is denied. ENTERED: 10/23/14 ________________________ Hon. John Z. Lee United States District Judge 17 Case: 1:14-cv-06993 Document #: 60 Filed: 10/23/14 Page 17 of 17 PageID #:829