SlideShare a Scribd company logo
Date posted: 17 February 2017
INTRODUCTION
1. In the last few years there have been a number of cases regarding the interpretation of
payment provisions in the Local Government, Economic Development and Construction Act
2009 (the “Construction Act”) which are now incorporated into most standard forms of
construction contract.
PAYMENT NOTICES
2. The new regime is similar to the previous one (from May 1998 to 2009), in that a
party due to make payment (the “Payer”) still has to issue a payment notice not later than
five days after the due date.
1. However, whereas previously there was no real detriment or sanction to the Payer if it
failed to issue this notice, now if the deadline for issuing the Notice passes and a Payment
Notice is not issued, the party due to receive payment (the “Payee”) may give the Payer a
Payment Notice – known as a “Payee's Notice in Default”. This notice can be issued at any
time, by the Payee, after the date that the Payment Notice was to be issued.
2. This Payee Notice in Default should state the amount considered due and the basis of
this calculation and this becomes the sum due.
PAY LESS NOTICES
1. The 2009 Act places an obligation on the Payer to pay the “notified sum”. If
deductions are to be made against the notified sum, the Payer is required to issue a “Pay
Less Notice” before the final date for payment. This Pay Less Notice must specify the sum
that the Payer considers to be due on the date the notice is served to the Payee and the
basis on which that this sum has been calculated.
2. This notice must be given not later than the prescribed period before the final date for
payment, specified in the Contract or the Scheme.
CASES
1. Unsurprisingly, the crucial importance of payment in the construction industry,
coupled with
what some see as draconian consequences for failing to issue the correct notice, has
generated a number of significant cases which have explained and/or clarified the
interpretation of the Act and the Scheme and/or the standard forms of contract.
1
Art 41 February 2017
8. These cases include: ISG Construction Ltd. v Seevic College, Leeds City Council v Waco UK
Ltd., Galliford Try Building Ltd. v Estura Ltd., Henia Investments Inc. v Beck Interiors Ltd.,
Caledonian Modular Ltd. v Mar City Developments Ltd., Harding v Paice, Jawaby Property
Investment Ltd. v The Interiors Group Ltd., Kilker Projects v Rob Purton, Surrey and Sussex
Healthcare NHS Trust v Logan Construction (South East) Ltd. and Kersfield Developments
(Bridge Road) Ltd. v Bray and Slaughter Ltd.
FORM, SUBSTANCE AND INTENT
9. Drawing together the substance of these cases brings to light a number of broad
principles, which anyone involved in applying or making payment under a construction
contract should be aware of.
1. Many of these cases are centred around the question of what happens when no
Payment and Pay Less Notice is issued.
2. The ISG and Galliford Try cases clarified that, in the absence of such notices, the
Payee may issue an Interim Payment Notice or, alternatively, rely on the sum claimed in
properly issued valid Applications for Payment. The Payee will be entitled to the sum
detailed in its Application/Notice.
3. It does, however, seem there was a realisation that this element of the Act/Contract
was potentially open to abuse by a “crafty” Payee, especially when dealing with an
inexperienced or naïve Payer. This resulted in many what are often referred to as “smash
and grab” adjudications.
4. In the six to seven months leading up to 2016, there were several cases regarding
this issue and the courts seem to have attempted to re-balance this position. Caledonia,
Henia and Severfield all elaborated on what would constitute a valid Application/Notice and
detailed the effect of such a document not being prepared and issued strictly in accordance
with the Contract.
5. In Henia, it was decided that an Application for Payment that was six days late was
not a valid Application under the Contract and, as such, the absence of a Payment Notice
and/or a Pay Less Notice was immaterial.
6. It should also be noted that the Judge also said that, if the Application for Payment
had been issued on time, a Payment Certificate issued by the Payer (which was in effect
three minutes late) would also have been viewed as invalid and the Payee would have been
entitled to the sums claimed.
7. Coulson J., in his Judgement on Caledonia, stated with regard to the principle that, in
the absence of a valid Payment Notice and/or Pay Less Notice, the Payee is entitled to the
sum detailed in a valid Application for Payment/Interim Payment Notice, that “...if
contractors” (Payee’s) “...want the benefit of these provisions, they are obliged, in
return, to set out their interim payment claims with proper clarity. If the employer
is to be put at risk that a failure to serve a payless notice at the appropriate time
during the payment period will render him liable in full for the amount claimed, he
must be given reasonable notice that the payment period has been triggered in the
first place”.
2
Art 41 February 2017
17. This was further confirmed in Coulson J.’s later Judgement in the Severfield case.
1. After this veritable flurry of cases, a further case was decided early in 2016. This case
- Jawaby Property Investment Ltd. v The Interiors Group Ltd. - confirmed and elaborated on
the Court’s view on what was required of an Application for Payment/Interim Payment
Notice to make it valid and therefore enforceable.
2. The Hon. Mrs Justice Carr stated that, to decide whether an Application for Payment/
Interim Payment Notice was indeed valid and enforceable, an assessment must be made as
to whether the Notice is clear in “Form”, “Substance” and “Intent”. This principle has been
applied to more recent cases, including Surrey and Sussex Healthcare NHS Trust v Logan
Construction (South East) Ltd. and Kersfield Developments (Bridge Road) Ltd. v Bray and
Slaughter Ltd.
3. Broadly, for an Application/Notice to be deemed valid, it must be on time (i.e. it must
be issued at the time required and not a minute later), it must be clear that the Application/
Notice is a Notice requiring action by the Payer, it must be prepared in sufficient detail to
allow the Payer to understand the claim (in accordance with the Contract or if no contract
exists to a reasonable standard), all stated dates must be correct and it must be in
accordance with the Contract.
SUMMARY
1. Quite simply, all the i’s should be dotted and all the t’s crossed. The Court’s view is
that the
obligation on the Payer to pay sums applied for by the Payee in the absence of a contrary
Payment and Pay Less Notice is so draconian that the Application/Notice must be strictly in
accordance with the Contract and that any flaw should prevent the Application/Notice from
being enforceable.
2. In our view, to assume that a failure by the Payer to issue a Payment/Pay
Less Notice automatically entitles the Payee to sums detailed in an
Application/Notice would be wrong. You must ensure that the Application/Notice is
prepared and issued strictly in accordance with the Contract.
AND FINALLY,
1. Some other noteworthy points addressed in the string of cases are:
. Final Accounts and Termination Accounts will be viewed and treated
differently.
. Erroneous claims included in an Application/Notice will not invalidate the
Application/Notice if it is, to all other intents and purposes, in accordance
with the Contract.
. In most cases concerning interim payments, a Payer will not be able to
commence a second Adjudication on the “true” value of the application.
3
Art 41 February 2017
A Pay Less Notice can incorporate an entire revaluation of the Contract; it is
not simply a document detailing deductions from a previous Payment
Certificate/Notice. This does raise the question as whether a Payment
Notice is truly required and we shall review and consider this in a
future article.
ARTICLE BY: NICK CHEETHAM (BSc (Hons), MRICS)
(nick.cheetham@ramskillmartin.co.uk or 07753 837149)
CONTACT RAMSKILL MARTIN AT:
BELPER Business Centre
(gary.martin@ramskillmartin.co.uk
MANCHESTER (nick.cheetham@ramskillmartin.co.uk SHEFFIELD Road
(frances.sawicki@ramskillmartin.co.uk
WATFORD Road
(clive.ramskill@ramskillmartin.co.uk
or07803628177)
1Heritage
Derby Road
Belper
Derbyshire
DE56 1SW
or 07753 837149)
3HardmanStreet
ManchesterM3
3HF
or07824690101)
Hilltop House
302Ringinglow
BentsGreen
SheffieldSouth
Yorkshire
or07753837148)
54Clarendon
Watford
Hertfordshire
WD171DU
S11 7PX
T: 01773599299 T: 0161 932 1535 T: 0114 230 1329 T: 01923 431600
F: 01773 880089 F: 0161 932 1401 F: 0114 229 5804 F: 01923 431700
W: www.ramskillmartin.co.uk
4
Art 41 February 2017

More Related Content

What's hot

Non Fund Based Credit Facilities (BG & LC)
Non Fund Based Credit Facilities (BG & LC)Non Fund Based Credit Facilities (BG & LC)
Non Fund Based Credit Facilities (BG & LC)
Abinash Mandilwar
 
NJA
NJANJA
UK Adjudicators Newsletter June 2021
UK Adjudicators  Newsletter June 2021UK Adjudicators  Newsletter June 2021
UK Adjudicators Newsletter June 2021
Sean Gibbs DipArb, FCIARB, FCIOB, FRICS, MICE
 
An afternoon discussion on direct payments
An afternoon discussion on direct paymentsAn afternoon discussion on direct payments
An afternoon discussion on direct payments
Kheng Hoe Advocates
 
Foreign Collaborations - Contracts; JVs; M&As
Foreign Collaborations - Contracts; JVs; M&AsForeign Collaborations - Contracts; JVs; M&As
Foreign Collaborations - Contracts; JVs; M&As
utkarshjani
 
Business Money talks to City barrister Professor Mark Watson-Gandy about sett...
Business Money talks to City barrister Professor Mark Watson-Gandy about sett...Business Money talks to City barrister Professor Mark Watson-Gandy about sett...
Business Money talks to City barrister Professor Mark Watson-Gandy about sett...
Sofiane Bounoua
 
Cocpg
CocpgCocpg
Quantum Meruit memo
Quantum Meruit memoQuantum Meruit memo
Quantum Meruit memo
Michael Currie
 
M Wealth Corridor Sdn Bhd (formerly known as Fantastic Megaway Sdn Bhd) v Cha...
M Wealth Corridor Sdn Bhd (formerly known as Fantastic Megaway Sdn Bhd) v Cha...M Wealth Corridor Sdn Bhd (formerly known as Fantastic Megaway Sdn Bhd) v Cha...
M Wealth Corridor Sdn Bhd (formerly known as Fantastic Megaway Sdn Bhd) v Cha...
surrenderyourthrone
 
Transferable Letters of Credit
Transferable Letters of CreditTransferable Letters of Credit
Transferable Letters of Credit
Buddy Baker
 
December Newsletter
December NewsletterDecember Newsletter
December Newsletter
Cerasela Angelescu
 
Ppt for webinar ICSI- landmark judgements
Ppt for webinar  ICSI- landmark judgementsPpt for webinar  ICSI- landmark judgements
Ppt for webinar ICSI- landmark judgements
Ashok Kumar Juneja
 
UK Adjudicators October 2019 newsletter
UK Adjudicators October 2019 newsletterUK Adjudicators October 2019 newsletter
UK Adjudicators October 2019 newsletter
Sean Gibbs DipArb, FCIARB, FCIOB, FRICS, MICE
 
CLI ARTICLE ON SUBCONTRACTING
CLI ARTICLE ON SUBCONTRACTINGCLI ARTICLE ON SUBCONTRACTING
CLI ARTICLE ON SUBCONTRACTING
ANTONIOS DIMITRACOPOULOS
 
City Water International Inc. v. 816580 Ontario Inc.
City Water International Inc. v. 816580 Ontario Inc.City Water International Inc. v. 816580 Ontario Inc.
City Water International Inc. v. 816580 Ontario Inc.
Matthew Riddell
 
Cycle diagrams
Cycle diagramsCycle diagrams
Cycle diagrams
Buddy Baker
 
Term of contract, Exemption clauses
Term of contract, Exemption clausesTerm of contract, Exemption clauses
Term of contract, Exemption clauses
Shivani Sharma
 
Letter of Credit
Letter of CreditLetter of Credit
Letter of Credit
Venkata Vihari K
 
William Kosar What Every Budget Officer Should Know_Rwanda
William Kosar What Every Budget Officer Should Know_RwandaWilliam Kosar What Every Budget Officer Should Know_Rwanda
William Kosar What Every Budget Officer Should Know_Rwanda
William Kosar
 
Case study: Essar Steel - Insolvency Resolution Plan
Case study: Essar Steel - Insolvency Resolution PlanCase study: Essar Steel - Insolvency Resolution Plan
Case study: Essar Steel - Insolvency Resolution Plan
DVSResearchFoundatio
 

What's hot (20)

Non Fund Based Credit Facilities (BG & LC)
Non Fund Based Credit Facilities (BG & LC)Non Fund Based Credit Facilities (BG & LC)
Non Fund Based Credit Facilities (BG & LC)
 
NJA
NJANJA
NJA
 
UK Adjudicators Newsletter June 2021
UK Adjudicators  Newsletter June 2021UK Adjudicators  Newsletter June 2021
UK Adjudicators Newsletter June 2021
 
An afternoon discussion on direct payments
An afternoon discussion on direct paymentsAn afternoon discussion on direct payments
An afternoon discussion on direct payments
 
Foreign Collaborations - Contracts; JVs; M&As
Foreign Collaborations - Contracts; JVs; M&AsForeign Collaborations - Contracts; JVs; M&As
Foreign Collaborations - Contracts; JVs; M&As
 
Business Money talks to City barrister Professor Mark Watson-Gandy about sett...
Business Money talks to City barrister Professor Mark Watson-Gandy about sett...Business Money talks to City barrister Professor Mark Watson-Gandy about sett...
Business Money talks to City barrister Professor Mark Watson-Gandy about sett...
 
Cocpg
CocpgCocpg
Cocpg
 
Quantum Meruit memo
Quantum Meruit memoQuantum Meruit memo
Quantum Meruit memo
 
M Wealth Corridor Sdn Bhd (formerly known as Fantastic Megaway Sdn Bhd) v Cha...
M Wealth Corridor Sdn Bhd (formerly known as Fantastic Megaway Sdn Bhd) v Cha...M Wealth Corridor Sdn Bhd (formerly known as Fantastic Megaway Sdn Bhd) v Cha...
M Wealth Corridor Sdn Bhd (formerly known as Fantastic Megaway Sdn Bhd) v Cha...
 
Transferable Letters of Credit
Transferable Letters of CreditTransferable Letters of Credit
Transferable Letters of Credit
 
December Newsletter
December NewsletterDecember Newsletter
December Newsletter
 
Ppt for webinar ICSI- landmark judgements
Ppt for webinar  ICSI- landmark judgementsPpt for webinar  ICSI- landmark judgements
Ppt for webinar ICSI- landmark judgements
 
UK Adjudicators October 2019 newsletter
UK Adjudicators October 2019 newsletterUK Adjudicators October 2019 newsletter
UK Adjudicators October 2019 newsletter
 
CLI ARTICLE ON SUBCONTRACTING
CLI ARTICLE ON SUBCONTRACTINGCLI ARTICLE ON SUBCONTRACTING
CLI ARTICLE ON SUBCONTRACTING
 
City Water International Inc. v. 816580 Ontario Inc.
City Water International Inc. v. 816580 Ontario Inc.City Water International Inc. v. 816580 Ontario Inc.
City Water International Inc. v. 816580 Ontario Inc.
 
Cycle diagrams
Cycle diagramsCycle diagrams
Cycle diagrams
 
Term of contract, Exemption clauses
Term of contract, Exemption clausesTerm of contract, Exemption clauses
Term of contract, Exemption clauses
 
Letter of Credit
Letter of CreditLetter of Credit
Letter of Credit
 
William Kosar What Every Budget Officer Should Know_Rwanda
William Kosar What Every Budget Officer Should Know_RwandaWilliam Kosar What Every Budget Officer Should Know_Rwanda
William Kosar What Every Budget Officer Should Know_Rwanda
 
Case study: Essar Steel - Insolvency Resolution Plan
Case study: Essar Steel - Insolvency Resolution PlanCase study: Essar Steel - Insolvency Resolution Plan
Case study: Essar Steel - Insolvency Resolution Plan
 

Viewers also liked

Cyberbullyng[1]
Cyberbullyng[1]Cyberbullyng[1]
Cyberbullyng[1]
luisitocarrillo
 
Cyberbullyng[1]
Cyberbullyng[1]Cyberbullyng[1]
Cyberbullyng[1]
luisitocarrillo
 
Planificacion
PlanificacionPlanificacion
Planificacion
Renzo Vasquez Leon
 
підготовка спеціалістів з автоматизації в НУХТ
підготовка спеціалістів з автоматизації в НУХТпідготовка спеціалістів з автоматизації в НУХТ
підготовка спеціалістів з автоматизації в НУХТ
Пупена Александр
 
Wikipedia
WikipediaWikipedia
Wikipedia
valeriamont
 
Malalties minoritàries
Malalties minoritàriesMalalties minoritàries
Malalties minoritàriesBeaLaus
 
Malalties minoritàries
Malalties minoritàriesMalalties minoritàries
Malalties minoritàriesBeaLaus
 
Presentacióncaso arturo
Presentacióncaso arturoPresentacióncaso arturo
Presentacióncaso arturo
sandrababativa1
 
Rancangan aktualisasi nilai nilai dasar profesi pns
Rancangan aktualisasi nilai nilai dasar profesi pnsRancangan aktualisasi nilai nilai dasar profesi pns
Rancangan aktualisasi nilai nilai dasar profesi pns
" Sigit School" Kutowinangun,Kebumen Jawa Tengah
 
Conferència "Qui manarà al món al 2050?"
Conferència "Qui manarà al món al 2050?"Conferència "Qui manarà al món al 2050?"
Conferència "Qui manarà al món al 2050?"
Finestra d'Oportunitat
 
Mi primera presentacion
Mi primera presentacionMi primera presentacion
Mi primera presentacion
perofusionman
 
Power point vmg
Power point vmgPower point vmg
Power point vmg
valeriamont
 
Plan de estudio
Plan de estudioPlan de estudio
Plan de estudio
Fercho_Lucero
 
Presentación caso arturo
Presentación caso arturoPresentación caso arturo
Presentación caso arturo
sandrababativa1
 
Energias en chile 2
Energias en chile 2Energias en chile 2
Energias en chile 2
erianyjabbo
 
Romania
RomaniaRomania
Romania
deliacucicea
 
Rosas Blancas
Rosas BlancasRosas Blancas
Rosas Blancas
sonandmoon
 
Malaria
MalariaMalaria
Objetivos de la carrera
Objetivos de la carreraObjetivos de la carrera
Objetivos de la carrera
Fercho_Lucero
 

Viewers also liked (20)

Cyberbullyng[1]
Cyberbullyng[1]Cyberbullyng[1]
Cyberbullyng[1]
 
Cyberbullyng[1]
Cyberbullyng[1]Cyberbullyng[1]
Cyberbullyng[1]
 
Planificacion
PlanificacionPlanificacion
Planificacion
 
Guillem de Berguedà
Guillem de BerguedàGuillem de Berguedà
Guillem de Berguedà
 
підготовка спеціалістів з автоматизації в НУХТ
підготовка спеціалістів з автоматизації в НУХТпідготовка спеціалістів з автоматизації в НУХТ
підготовка спеціалістів з автоматизації в НУХТ
 
Wikipedia
WikipediaWikipedia
Wikipedia
 
Malalties minoritàries
Malalties minoritàriesMalalties minoritàries
Malalties minoritàries
 
Malalties minoritàries
Malalties minoritàriesMalalties minoritàries
Malalties minoritàries
 
Presentacióncaso arturo
Presentacióncaso arturoPresentacióncaso arturo
Presentacióncaso arturo
 
Rancangan aktualisasi nilai nilai dasar profesi pns
Rancangan aktualisasi nilai nilai dasar profesi pnsRancangan aktualisasi nilai nilai dasar profesi pns
Rancangan aktualisasi nilai nilai dasar profesi pns
 
Conferència "Qui manarà al món al 2050?"
Conferència "Qui manarà al món al 2050?"Conferència "Qui manarà al món al 2050?"
Conferència "Qui manarà al món al 2050?"
 
Mi primera presentacion
Mi primera presentacionMi primera presentacion
Mi primera presentacion
 
Power point vmg
Power point vmgPower point vmg
Power point vmg
 
Plan de estudio
Plan de estudioPlan de estudio
Plan de estudio
 
Presentación caso arturo
Presentación caso arturoPresentación caso arturo
Presentación caso arturo
 
Energias en chile 2
Energias en chile 2Energias en chile 2
Energias en chile 2
 
Romania
RomaniaRomania
Romania
 
Rosas Blancas
Rosas BlancasRosas Blancas
Rosas Blancas
 
Malaria
MalariaMalaria
Malaria
 
Objetivos de la carrera
Objetivos de la carreraObjetivos de la carrera
Objetivos de la carrera
 

Similar to Article 41 payment and pay less notices february 2017 rm03

Construction law update august 2015 quarter 2 a
Construction law update august 2015 quarter 2 aConstruction law update august 2015 quarter 2 a
Construction law update august 2015 quarter 2 a
Colin Tomlinson
 
Commercial and Construction Law Update Q2 2015
Commercial and Construction Law Update Q2 2015Commercial and Construction Law Update Q2 2015
Commercial and Construction Law Update Q2 2015
Colin Tomlinson
 
Commericial Management and Construction law update 2015 Q2
Commericial Management and Construction law update 2015 Q2Commericial Management and Construction law update 2015 Q2
Commericial Management and Construction law update 2015 Q2
Colin Tomlinson
 
Time Bars and their enforceability in English law EPC contracts
Time Bars and their enforceability in English law EPC contractsTime Bars and their enforceability in English law EPC contracts
Time Bars and their enforceability in English law EPC contracts
Eversheds Sutherland
 
December 2018 newsletter kp
December 2018 newsletter kpDecember 2018 newsletter kp
Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....
Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....
Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....
Pierrette Khoury BComm/B Laws, GDLP
 
Critical study of dishonour of cheques under negotiable instruments act,1881
Critical study of dishonour of cheques under negotiable instruments act,1881Critical study of dishonour of cheques under negotiable instruments act,1881
Critical study of dishonour of cheques under negotiable instruments act,1881
merenjithr
 
Recovering from Reform4
Recovering from Reform4Recovering from Reform4
Recovering from Reform4
BeckyRhodes
 
UK Adjudicators Newsletter November 2021
UK Adjudicators  Newsletter November 2021UK Adjudicators  Newsletter November 2021
UK Adjudicators Newsletter November 2021
SeanGibbs12
 
Slides from the niceties of notices and their importance for construction claims
Slides from the niceties of notices and their importance for construction claimsSlides from the niceties of notices and their importance for construction claims
Slides from the niceties of notices and their importance for construction claims
Robert MacDonald
 
2 claims under new fidic
2 claims under new fidic2 claims under new fidic
2 claims under new fidic
AhmetArslan47
 
Walden final
Walden   finalWalden   final
Walden final
JennaHajhassan
 
A Tale of Two Judges | A Comparison between John Hancock and ING
A Tale of Two Judges | A Comparison between John Hancock and INGA Tale of Two Judges | A Comparison between John Hancock and ING
A Tale of Two Judges | A Comparison between John Hancock and ING
The 401k Study Group ®
 
UK Adjudicators July 2020 newsletter
UK Adjudicators July 2020 newsletterUK Adjudicators July 2020 newsletter
UK Adjudicators July 2020 newsletter
Sean Gibbs DipArb, FCIARB, FCIOB, FRICS, MICE
 
Clause 16 suspension
Clause 16 suspensionClause 16 suspension
Clause 16 suspension
breyerhanna
 
Legal Memorandum BMI & Minicom 2
Legal Memorandum BMI & Minicom 2Legal Memorandum BMI & Minicom 2
Legal Memorandum BMI & Minicom 2
Valerie LeBoeuf
 
Dishonour of cheque priyanka agarwal bvdu_pune
Dishonour of cheque priyanka agarwal bvdu_puneDishonour of cheque priyanka agarwal bvdu_pune
Dishonour of cheque priyanka agarwal bvdu_pune
Priyanka Agarwal
 
UK Adjudicators November 2020 Newsletter
UK Adjudicators November 2020 NewsletterUK Adjudicators November 2020 Newsletter
UK Adjudicators November 2020 Newsletter
Sean Gibbs DipArb, FCIARB, FCIOB, FRICS, MICE
 
Payment in construction contracts: how to get paid
Payment in construction contracts: how to get paidPayment in construction contracts: how to get paid
Payment in construction contracts: how to get paid
Barry Hembling
 
Public Matters November 2015
Public Matters November 2015Public Matters November 2015
Public Matters November 2015
Browne Jacobson LLP
 

Similar to Article 41 payment and pay less notices february 2017 rm03 (20)

Construction law update august 2015 quarter 2 a
Construction law update august 2015 quarter 2 aConstruction law update august 2015 quarter 2 a
Construction law update august 2015 quarter 2 a
 
Commercial and Construction Law Update Q2 2015
Commercial and Construction Law Update Q2 2015Commercial and Construction Law Update Q2 2015
Commercial and Construction Law Update Q2 2015
 
Commericial Management and Construction law update 2015 Q2
Commericial Management and Construction law update 2015 Q2Commericial Management and Construction law update 2015 Q2
Commericial Management and Construction law update 2015 Q2
 
Time Bars and their enforceability in English law EPC contracts
Time Bars and their enforceability in English law EPC contractsTime Bars and their enforceability in English law EPC contracts
Time Bars and their enforceability in English law EPC contracts
 
December 2018 newsletter kp
December 2018 newsletter kpDecember 2018 newsletter kp
December 2018 newsletter kp
 
Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....
Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....
Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....
 
Critical study of dishonour of cheques under negotiable instruments act,1881
Critical study of dishonour of cheques under negotiable instruments act,1881Critical study of dishonour of cheques under negotiable instruments act,1881
Critical study of dishonour of cheques under negotiable instruments act,1881
 
Recovering from Reform4
Recovering from Reform4Recovering from Reform4
Recovering from Reform4
 
UK Adjudicators Newsletter November 2021
UK Adjudicators  Newsletter November 2021UK Adjudicators  Newsletter November 2021
UK Adjudicators Newsletter November 2021
 
Slides from the niceties of notices and their importance for construction claims
Slides from the niceties of notices and their importance for construction claimsSlides from the niceties of notices and their importance for construction claims
Slides from the niceties of notices and their importance for construction claims
 
2 claims under new fidic
2 claims under new fidic2 claims under new fidic
2 claims under new fidic
 
Walden final
Walden   finalWalden   final
Walden final
 
A Tale of Two Judges | A Comparison between John Hancock and ING
A Tale of Two Judges | A Comparison between John Hancock and INGA Tale of Two Judges | A Comparison between John Hancock and ING
A Tale of Two Judges | A Comparison between John Hancock and ING
 
UK Adjudicators July 2020 newsletter
UK Adjudicators July 2020 newsletterUK Adjudicators July 2020 newsletter
UK Adjudicators July 2020 newsletter
 
Clause 16 suspension
Clause 16 suspensionClause 16 suspension
Clause 16 suspension
 
Legal Memorandum BMI & Minicom 2
Legal Memorandum BMI & Minicom 2Legal Memorandum BMI & Minicom 2
Legal Memorandum BMI & Minicom 2
 
Dishonour of cheque priyanka agarwal bvdu_pune
Dishonour of cheque priyanka agarwal bvdu_puneDishonour of cheque priyanka agarwal bvdu_pune
Dishonour of cheque priyanka agarwal bvdu_pune
 
UK Adjudicators November 2020 Newsletter
UK Adjudicators November 2020 NewsletterUK Adjudicators November 2020 Newsletter
UK Adjudicators November 2020 Newsletter
 
Payment in construction contracts: how to get paid
Payment in construction contracts: how to get paidPayment in construction contracts: how to get paid
Payment in construction contracts: how to get paid
 
Public Matters November 2015
Public Matters November 2015Public Matters November 2015
Public Matters November 2015
 

Recently uploaded

一比一原版(monash毕业证书)莫纳什大学毕业证如何办理
一比一原版(monash毕业证书)莫纳什大学毕业证如何办理一比一原版(monash毕业证书)莫纳什大学毕业证如何办理
一比一原版(monash毕业证书)莫纳什大学毕业证如何办理
bzofm
 
production-orders-under-article-18-of-the-budapest-convention-on-cybercrime-a...
production-orders-under-article-18-of-the-budapest-convention-on-cybercrime-a...production-orders-under-article-18-of-the-budapest-convention-on-cybercrime-a...
production-orders-under-article-18-of-the-budapest-convention-on-cybercrime-a...
ElenaLazr2
 
Corporate Governance : Scope and Legal Framework
Corporate Governance : Scope and Legal FrameworkCorporate Governance : Scope and Legal Framework
Corporate Governance : Scope and Legal Framework
devaki57
 
一比一原版(liverpool毕业证书)利物浦大学毕业证如何办理
一比一原版(liverpool毕业证书)利物浦大学毕业证如何办理一比一原版(liverpool毕业证书)利物浦大学毕业证如何办理
一比一原版(liverpool毕业证书)利物浦大学毕业证如何办理
aypxuyw
 
一比一原版(uottawa毕业证书)加拿大渥太华大学毕业证如何办理
一比一原版(uottawa毕业证书)加拿大渥太华大学毕业证如何办理一比一原版(uottawa毕业证书)加拿大渥太华大学毕业证如何办理
一比一原版(uottawa毕业证书)加拿大渥太华大学毕业证如何办理
uhsox
 
Should AI hold Intellectual Property Rights?
Should AI hold Intellectual Property Rights?Should AI hold Intellectual Property Rights?
Should AI hold Intellectual Property Rights?
RoseZubler1
 
在线办理(UNE毕业证书)新英格兰大学毕业证成绩单一模一样
在线办理(UNE毕业证书)新英格兰大学毕业证成绩单一模一样在线办理(UNE毕业证书)新英格兰大学毕业证成绩单一模一样
在线办理(UNE毕业证书)新英格兰大学毕业证成绩单一模一样
15e6o6u
 
It's the Law: Recent Court and Administrative Decisions of Interest
It's the Law: Recent Court and Administrative Decisions of InterestIt's the Law: Recent Court and Administrative Decisions of Interest
It's the Law: Recent Court and Administrative Decisions of Interest
Parsons Behle & Latimer
 
17-03 2022 -full agreement full version .pdf
17-03 2022 -full agreement full version .pdf17-03 2022 -full agreement full version .pdf
17-03 2022 -full agreement full version .pdf
ssuser0dfed9
 
一比一原版牛津布鲁克斯大学毕业证(牛布毕业证)如何办理
一比一原版牛津布鲁克斯大学毕业证(牛布毕业证)如何办理一比一原版牛津布鲁克斯大学毕业证(牛布毕业证)如何办理
一比一原版牛津布鲁克斯大学毕业证(牛布毕业证)如何办理
meboh
 
一比一原版新加坡国立大学毕业证(本硕)nus学位证书如何办理
一比一原版新加坡国立大学毕业证(本硕)nus学位证书如何办理一比一原版新加坡国立大学毕业证(本硕)nus学位证书如何办理
一比一原版新加坡国立大学毕业证(本硕)nus学位证书如何办理
ucoux1
 
United States vs. Donald Trump Speaking Indictment
United States vs. Donald Trump Speaking IndictmentUnited States vs. Donald Trump Speaking Indictment
United States vs. Donald Trump Speaking Indictment
Todd Spodek
 
Asian legal busiess india you are invited
Asian legal busiess india you are invitedAsian legal busiess india you are invited
Asian legal busiess india you are invited
digitalrashi12
 
Capital Punishment by Saif Javed (LLM)ppt.pptx
Capital Punishment by Saif Javed (LLM)ppt.pptxCapital Punishment by Saif Javed (LLM)ppt.pptx
Capital Punishment by Saif Javed (LLM)ppt.pptx
OmGod1
 
一比一原版(ua毕业证书)加拿大阿尔伯塔大学毕业证如何办理
一比一原版(ua毕业证书)加拿大阿尔伯塔大学毕业证如何办理一比一原版(ua毕业证书)加拿大阿尔伯塔大学毕业证如何办理
一比一原版(ua毕业证书)加拿大阿尔伯塔大学毕业证如何办理
ubype
 
一比一原版(ual毕业证书)伦敦艺术大学毕业证如何办理
一比一原版(ual毕业证书)伦敦艺术大学毕业证如何办理一比一原版(ual毕业证书)伦敦艺术大学毕业证如何办理
一比一原版(ual毕业证书)伦敦艺术大学毕业证如何办理
ayvace
 
一比一原版伯恩茅斯大学毕业证(bu毕业证)如何办理
一比一原版伯恩茅斯大学毕业证(bu毕业证)如何办理一比一原版伯恩茅斯大学毕业证(bu毕业证)如何办理
一比一原版伯恩茅斯大学毕业证(bu毕业证)如何办理
ymefneb
 
一比一原版加拿大达尔豪斯大学毕业证(dalhousie毕业证书)如何办理
一比一原版加拿大达尔豪斯大学毕业证(dalhousie毕业证书)如何办理一比一原版加拿大达尔豪斯大学毕业证(dalhousie毕业证书)如何办理
一比一原版加拿大达尔豪斯大学毕业证(dalhousie毕业证书)如何办理
cadyzeo
 
一比一原版新加坡南洋理工大学毕业证(本硕)ntu学位证书如何办理
一比一原版新加坡南洋理工大学毕业证(本硕)ntu学位证书如何办理一比一原版新加坡南洋理工大学毕业证(本硕)ntu学位证书如何办理
一比一原版新加坡南洋理工大学毕业证(本硕)ntu学位证书如何办理
hedonxu
 
Indonesian Manpower Regulation on Severance Pay for Retiring Private Sector E...
Indonesian Manpower Regulation on Severance Pay for Retiring Private Sector E...Indonesian Manpower Regulation on Severance Pay for Retiring Private Sector E...
Indonesian Manpower Regulation on Severance Pay for Retiring Private Sector E...
AHRP Law Firm
 

Recently uploaded (20)

一比一原版(monash毕业证书)莫纳什大学毕业证如何办理
一比一原版(monash毕业证书)莫纳什大学毕业证如何办理一比一原版(monash毕业证书)莫纳什大学毕业证如何办理
一比一原版(monash毕业证书)莫纳什大学毕业证如何办理
 
production-orders-under-article-18-of-the-budapest-convention-on-cybercrime-a...
production-orders-under-article-18-of-the-budapest-convention-on-cybercrime-a...production-orders-under-article-18-of-the-budapest-convention-on-cybercrime-a...
production-orders-under-article-18-of-the-budapest-convention-on-cybercrime-a...
 
Corporate Governance : Scope and Legal Framework
Corporate Governance : Scope and Legal FrameworkCorporate Governance : Scope and Legal Framework
Corporate Governance : Scope and Legal Framework
 
一比一原版(liverpool毕业证书)利物浦大学毕业证如何办理
一比一原版(liverpool毕业证书)利物浦大学毕业证如何办理一比一原版(liverpool毕业证书)利物浦大学毕业证如何办理
一比一原版(liverpool毕业证书)利物浦大学毕业证如何办理
 
一比一原版(uottawa毕业证书)加拿大渥太华大学毕业证如何办理
一比一原版(uottawa毕业证书)加拿大渥太华大学毕业证如何办理一比一原版(uottawa毕业证书)加拿大渥太华大学毕业证如何办理
一比一原版(uottawa毕业证书)加拿大渥太华大学毕业证如何办理
 
Should AI hold Intellectual Property Rights?
Should AI hold Intellectual Property Rights?Should AI hold Intellectual Property Rights?
Should AI hold Intellectual Property Rights?
 
在线办理(UNE毕业证书)新英格兰大学毕业证成绩单一模一样
在线办理(UNE毕业证书)新英格兰大学毕业证成绩单一模一样在线办理(UNE毕业证书)新英格兰大学毕业证成绩单一模一样
在线办理(UNE毕业证书)新英格兰大学毕业证成绩单一模一样
 
It's the Law: Recent Court and Administrative Decisions of Interest
It's the Law: Recent Court and Administrative Decisions of InterestIt's the Law: Recent Court and Administrative Decisions of Interest
It's the Law: Recent Court and Administrative Decisions of Interest
 
17-03 2022 -full agreement full version .pdf
17-03 2022 -full agreement full version .pdf17-03 2022 -full agreement full version .pdf
17-03 2022 -full agreement full version .pdf
 
一比一原版牛津布鲁克斯大学毕业证(牛布毕业证)如何办理
一比一原版牛津布鲁克斯大学毕业证(牛布毕业证)如何办理一比一原版牛津布鲁克斯大学毕业证(牛布毕业证)如何办理
一比一原版牛津布鲁克斯大学毕业证(牛布毕业证)如何办理
 
一比一原版新加坡国立大学毕业证(本硕)nus学位证书如何办理
一比一原版新加坡国立大学毕业证(本硕)nus学位证书如何办理一比一原版新加坡国立大学毕业证(本硕)nus学位证书如何办理
一比一原版新加坡国立大学毕业证(本硕)nus学位证书如何办理
 
United States vs. Donald Trump Speaking Indictment
United States vs. Donald Trump Speaking IndictmentUnited States vs. Donald Trump Speaking Indictment
United States vs. Donald Trump Speaking Indictment
 
Asian legal busiess india you are invited
Asian legal busiess india you are invitedAsian legal busiess india you are invited
Asian legal busiess india you are invited
 
Capital Punishment by Saif Javed (LLM)ppt.pptx
Capital Punishment by Saif Javed (LLM)ppt.pptxCapital Punishment by Saif Javed (LLM)ppt.pptx
Capital Punishment by Saif Javed (LLM)ppt.pptx
 
一比一原版(ua毕业证书)加拿大阿尔伯塔大学毕业证如何办理
一比一原版(ua毕业证书)加拿大阿尔伯塔大学毕业证如何办理一比一原版(ua毕业证书)加拿大阿尔伯塔大学毕业证如何办理
一比一原版(ua毕业证书)加拿大阿尔伯塔大学毕业证如何办理
 
一比一原版(ual毕业证书)伦敦艺术大学毕业证如何办理
一比一原版(ual毕业证书)伦敦艺术大学毕业证如何办理一比一原版(ual毕业证书)伦敦艺术大学毕业证如何办理
一比一原版(ual毕业证书)伦敦艺术大学毕业证如何办理
 
一比一原版伯恩茅斯大学毕业证(bu毕业证)如何办理
一比一原版伯恩茅斯大学毕业证(bu毕业证)如何办理一比一原版伯恩茅斯大学毕业证(bu毕业证)如何办理
一比一原版伯恩茅斯大学毕业证(bu毕业证)如何办理
 
一比一原版加拿大达尔豪斯大学毕业证(dalhousie毕业证书)如何办理
一比一原版加拿大达尔豪斯大学毕业证(dalhousie毕业证书)如何办理一比一原版加拿大达尔豪斯大学毕业证(dalhousie毕业证书)如何办理
一比一原版加拿大达尔豪斯大学毕业证(dalhousie毕业证书)如何办理
 
一比一原版新加坡南洋理工大学毕业证(本硕)ntu学位证书如何办理
一比一原版新加坡南洋理工大学毕业证(本硕)ntu学位证书如何办理一比一原版新加坡南洋理工大学毕业证(本硕)ntu学位证书如何办理
一比一原版新加坡南洋理工大学毕业证(本硕)ntu学位证书如何办理
 
Indonesian Manpower Regulation on Severance Pay for Retiring Private Sector E...
Indonesian Manpower Regulation on Severance Pay for Retiring Private Sector E...Indonesian Manpower Regulation on Severance Pay for Retiring Private Sector E...
Indonesian Manpower Regulation on Severance Pay for Retiring Private Sector E...
 

Article 41 payment and pay less notices february 2017 rm03

  • 1. Date posted: 17 February 2017 INTRODUCTION 1. In the last few years there have been a number of cases regarding the interpretation of payment provisions in the Local Government, Economic Development and Construction Act 2009 (the “Construction Act”) which are now incorporated into most standard forms of construction contract. PAYMENT NOTICES 2. The new regime is similar to the previous one (from May 1998 to 2009), in that a party due to make payment (the “Payer”) still has to issue a payment notice not later than five days after the due date. 1. However, whereas previously there was no real detriment or sanction to the Payer if it failed to issue this notice, now if the deadline for issuing the Notice passes and a Payment Notice is not issued, the party due to receive payment (the “Payee”) may give the Payer a Payment Notice – known as a “Payee's Notice in Default”. This notice can be issued at any time, by the Payee, after the date that the Payment Notice was to be issued. 2. This Payee Notice in Default should state the amount considered due and the basis of this calculation and this becomes the sum due. PAY LESS NOTICES 1. The 2009 Act places an obligation on the Payer to pay the “notified sum”. If deductions are to be made against the notified sum, the Payer is required to issue a “Pay Less Notice” before the final date for payment. This Pay Less Notice must specify the sum that the Payer considers to be due on the date the notice is served to the Payee and the basis on which that this sum has been calculated. 2. This notice must be given not later than the prescribed period before the final date for payment, specified in the Contract or the Scheme. CASES 1. Unsurprisingly, the crucial importance of payment in the construction industry, coupled with what some see as draconian consequences for failing to issue the correct notice, has generated a number of significant cases which have explained and/or clarified the interpretation of the Act and the Scheme and/or the standard forms of contract. 1 Art 41 February 2017
  • 2. 8. These cases include: ISG Construction Ltd. v Seevic College, Leeds City Council v Waco UK Ltd., Galliford Try Building Ltd. v Estura Ltd., Henia Investments Inc. v Beck Interiors Ltd., Caledonian Modular Ltd. v Mar City Developments Ltd., Harding v Paice, Jawaby Property Investment Ltd. v The Interiors Group Ltd., Kilker Projects v Rob Purton, Surrey and Sussex Healthcare NHS Trust v Logan Construction (South East) Ltd. and Kersfield Developments (Bridge Road) Ltd. v Bray and Slaughter Ltd. FORM, SUBSTANCE AND INTENT 9. Drawing together the substance of these cases brings to light a number of broad principles, which anyone involved in applying or making payment under a construction contract should be aware of. 1. Many of these cases are centred around the question of what happens when no Payment and Pay Less Notice is issued. 2. The ISG and Galliford Try cases clarified that, in the absence of such notices, the Payee may issue an Interim Payment Notice or, alternatively, rely on the sum claimed in properly issued valid Applications for Payment. The Payee will be entitled to the sum detailed in its Application/Notice. 3. It does, however, seem there was a realisation that this element of the Act/Contract was potentially open to abuse by a “crafty” Payee, especially when dealing with an inexperienced or naïve Payer. This resulted in many what are often referred to as “smash and grab” adjudications. 4. In the six to seven months leading up to 2016, there were several cases regarding this issue and the courts seem to have attempted to re-balance this position. Caledonia, Henia and Severfield all elaborated on what would constitute a valid Application/Notice and detailed the effect of such a document not being prepared and issued strictly in accordance with the Contract. 5. In Henia, it was decided that an Application for Payment that was six days late was not a valid Application under the Contract and, as such, the absence of a Payment Notice and/or a Pay Less Notice was immaterial. 6. It should also be noted that the Judge also said that, if the Application for Payment had been issued on time, a Payment Certificate issued by the Payer (which was in effect three minutes late) would also have been viewed as invalid and the Payee would have been entitled to the sums claimed. 7. Coulson J., in his Judgement on Caledonia, stated with regard to the principle that, in the absence of a valid Payment Notice and/or Pay Less Notice, the Payee is entitled to the sum detailed in a valid Application for Payment/Interim Payment Notice, that “...if contractors” (Payee’s) “...want the benefit of these provisions, they are obliged, in return, to set out their interim payment claims with proper clarity. If the employer is to be put at risk that a failure to serve a payless notice at the appropriate time during the payment period will render him liable in full for the amount claimed, he must be given reasonable notice that the payment period has been triggered in the first place”. 2 Art 41 February 2017
  • 3. 17. This was further confirmed in Coulson J.’s later Judgement in the Severfield case. 1. After this veritable flurry of cases, a further case was decided early in 2016. This case - Jawaby Property Investment Ltd. v The Interiors Group Ltd. - confirmed and elaborated on the Court’s view on what was required of an Application for Payment/Interim Payment Notice to make it valid and therefore enforceable. 2. The Hon. Mrs Justice Carr stated that, to decide whether an Application for Payment/ Interim Payment Notice was indeed valid and enforceable, an assessment must be made as to whether the Notice is clear in “Form”, “Substance” and “Intent”. This principle has been applied to more recent cases, including Surrey and Sussex Healthcare NHS Trust v Logan Construction (South East) Ltd. and Kersfield Developments (Bridge Road) Ltd. v Bray and Slaughter Ltd. 3. Broadly, for an Application/Notice to be deemed valid, it must be on time (i.e. it must be issued at the time required and not a minute later), it must be clear that the Application/ Notice is a Notice requiring action by the Payer, it must be prepared in sufficient detail to allow the Payer to understand the claim (in accordance with the Contract or if no contract exists to a reasonable standard), all stated dates must be correct and it must be in accordance with the Contract. SUMMARY 1. Quite simply, all the i’s should be dotted and all the t’s crossed. The Court’s view is that the obligation on the Payer to pay sums applied for by the Payee in the absence of a contrary Payment and Pay Less Notice is so draconian that the Application/Notice must be strictly in accordance with the Contract and that any flaw should prevent the Application/Notice from being enforceable. 2. In our view, to assume that a failure by the Payer to issue a Payment/Pay Less Notice automatically entitles the Payee to sums detailed in an Application/Notice would be wrong. You must ensure that the Application/Notice is prepared and issued strictly in accordance with the Contract. AND FINALLY, 1. Some other noteworthy points addressed in the string of cases are: . Final Accounts and Termination Accounts will be viewed and treated differently. . Erroneous claims included in an Application/Notice will not invalidate the Application/Notice if it is, to all other intents and purposes, in accordance with the Contract. . In most cases concerning interim payments, a Payer will not be able to commence a second Adjudication on the “true” value of the application. 3 Art 41 February 2017
  • 4. A Pay Less Notice can incorporate an entire revaluation of the Contract; it is not simply a document detailing deductions from a previous Payment Certificate/Notice. This does raise the question as whether a Payment Notice is truly required and we shall review and consider this in a future article. ARTICLE BY: NICK CHEETHAM (BSc (Hons), MRICS) (nick.cheetham@ramskillmartin.co.uk or 07753 837149) CONTACT RAMSKILL MARTIN AT: BELPER Business Centre (gary.martin@ramskillmartin.co.uk MANCHESTER (nick.cheetham@ramskillmartin.co.uk SHEFFIELD Road (frances.sawicki@ramskillmartin.co.uk WATFORD Road (clive.ramskill@ramskillmartin.co.uk or07803628177) 1Heritage Derby Road Belper Derbyshire DE56 1SW or 07753 837149) 3HardmanStreet ManchesterM3 3HF or07824690101) Hilltop House 302Ringinglow BentsGreen SheffieldSouth Yorkshire or07753837148) 54Clarendon Watford Hertfordshire WD171DU S11 7PX T: 01773599299 T: 0161 932 1535 T: 0114 230 1329 T: 01923 431600 F: 01773 880089 F: 0161 932 1401 F: 0114 229 5804 F: 01923 431700 W: www.ramskillmartin.co.uk 4 Art 41 February 2017